Proposed Housing Development at Edenville Estate,
Kiambu County
Progress Report by Questworks Limited
January 20, 2018
2
Project Summary
Date: January 20, 2018 Project: Proposed Housing Development at Edenville Estate, Kiambu County Client: M/s Paramount Chief Estate Ltd (Phase II)
COURT 3 BEDROOM 4 BEDROOM PROGRESS IN % A 36
97
B 37
92
C 29
70
D
44 85
E 34
50
F
39 45
G
44 35
H
29 40
TOTAL 136 156
Court A
Shower cubicles done in most of the houses.
Granite counter tops complete in all the houses.
Electrical wiring and fitting almost done in most of the houses.
Court B
Cladding complete in all the houses.
Glazing is almost in most of the houses.
2nd coat of paint applied in all the houses.
Court C
Chain link fencing is still in progress.
Paving slabs and road Kerbs still in progress.
Ruff & tuff is ongoing.
Court D
Gutters installation in progress.
Wardrobe and kitchen cabinets still in progress.
Staircase fitted with mahogany in progress.
3
Court E
External drainage in progress.
T&G is ongoing.
Gypsum ceiling almost finished.
Court F
Floor tiles is done in a few houses.
Staircase balustrading is in progress.
Window fitting is complete in all the houses.
Court G
Ring beam almost complete in most of the houses.
Wet works is still in progress.
Court H
Roofing is in progress in some of the houses.
Steel doors installation in progress.
Amarjit Singh Virdi
QUESTWORKS LTD - PROJECT MANAGERS
4
Site Pictures
COURT A
COURT B
COURT C
COURT D
5
COURT E
COURT F
COURT G
COURT H
EXTERNAL WORKS
Retailing Wall
Culvet