questworks ltd - edenville two · pdf [email protected] block c, 1st floor, suite 10,...

6
Proposed Housing Development at Edenville Estate, Kiambu County Progress Report by Questworks Limited January 20, 2018

Upload: trinhnguyet

Post on 11-Feb-2018

219 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Questworks Ltd - Edenville Two · PDF fileinfo@questworks.co.ke Block C, 1st Floor, Suite 10, Nairobi, Kenya Court F All ground floor structures are complete 1st floor shutter is in

Proposed Housing Development at Edenville Estate,

Kiambu County

Progress Report by Questworks Limited

January 20, 2018

Page 2: Questworks Ltd - Edenville Two · PDF fileinfo@questworks.co.ke Block C, 1st Floor, Suite 10, Nairobi, Kenya Court F All ground floor structures are complete 1st floor shutter is in

2

Project Summary

Date: January 20, 2018 Project: Proposed Housing Development at Edenville Estate, Kiambu County Client: M/s Paramount Chief Estate Ltd (Phase II)

COURT 3 BEDROOM 4 BEDROOM PROGRESS IN % A 36

97

B 37

92

C 29

70

D

44 85

E 34

50

F

39 45

G

44 35

H

29 40

TOTAL 136 156

Court A

Shower cubicles done in most of the houses.

Granite counter tops complete in all the houses.

Electrical wiring and fitting almost done in most of the houses.

Court B

Cladding complete in all the houses.

Glazing is almost in most of the houses.

2nd coat of paint applied in all the houses.

Court C

Chain link fencing is still in progress.

Paving slabs and road Kerbs still in progress.

Ruff & tuff is ongoing.

Court D

Gutters installation in progress.

Wardrobe and kitchen cabinets still in progress.

Staircase fitted with mahogany in progress.

Page 3: Questworks Ltd - Edenville Two · PDF fileinfo@questworks.co.ke Block C, 1st Floor, Suite 10, Nairobi, Kenya Court F All ground floor structures are complete 1st floor shutter is in

3

Court E

External drainage in progress.

T&G is ongoing.

Gypsum ceiling almost finished.

Court F

Floor tiles is done in a few houses.

Staircase balustrading is in progress.

Window fitting is complete in all the houses.

Court G

Ring beam almost complete in most of the houses.

Wet works is still in progress.

Court H

Roofing is in progress in some of the houses.

Steel doors installation in progress.

Amarjit Singh Virdi

QUESTWORKS LTD - PROJECT MANAGERS

Page 4: Questworks Ltd - Edenville Two · PDF fileinfo@questworks.co.ke Block C, 1st Floor, Suite 10, Nairobi, Kenya Court F All ground floor structures are complete 1st floor shutter is in

4

Site Pictures

COURT A

COURT B

COURT C

COURT D

Page 5: Questworks Ltd - Edenville Two · PDF fileinfo@questworks.co.ke Block C, 1st Floor, Suite 10, Nairobi, Kenya Court F All ground floor structures are complete 1st floor shutter is in

5

COURT E

COURT F

COURT G

COURT H

Page 6: Questworks Ltd - Edenville Two · PDF fileinfo@questworks.co.ke Block C, 1st Floor, Suite 10, Nairobi, Kenya Court F All ground floor structures are complete 1st floor shutter is in

EXTERNAL WORKS

Retailing Wall

Culvet