Page 1: RAB Vapor Intrusion Mitigation

ACTIVITY NAME

Vapor Intrusion MitigationFormer Naval Air Station Moffett Field

Restoration Advisory Board Meeting May 11, 2017

Wilson DoctorNavy Project Manager

Page 2: RAB Vapor Intrusion Mitigation

5 BRAC Program Management Office.

Vapor Intrusion MitigationSchematic of Vapor Intrusion Pathway

Page 3: RAB Vapor Intrusion Mitigation

6 BRAC Program Management Office.

Vapor Intrusion Mitigation Methods

Vapor Intrusion Mitigation Methods

– Eliminate preferential pathways

– Increase ventilation inside the building

– Active sub-slab ventilation (depressurization)

Page 4: RAB Vapor Intrusion Mitigation

7 BRAC Program Management Office.

Vapor Intrusion Mitigation Methods

Eliminate Preferential Pathways– Fill subsurface vaults – Seal cracks/expansion joints in floor slabs– Seal pipe penetrations/floor drains

Sealing floor cracks Sealing floor drains

Page 5: RAB Vapor Intrusion Mitigation

8 BRAC Program Management Office.

Vapor Intrusion Mitigation Methods

Increase Ventilation Inside the Building– Fresh air intake – Increased air exchange rate

Page 6: RAB Vapor Intrusion Mitigation

9 BRAC Program Management Office.

Vapor Intrusion Mitigation Methods

Active Sub-slab Ventilation– Sub-slab depressurization system creates a negative pressure field below the building preventing soil gas from entering the building

Schematic Sub-Slab Depressurization System Sub-Slab Depressurization Blower and Vent

Page 7: RAB Vapor Intrusion Mitigation

10 BRAC Program Management Office.

Confirmation Sampling

ROD Amendment for the Vapor Intrusion Pathway (EPA, 2010) for long-term exposure

Chemical of ConcernIndoor Air Cleanup

Level (µg/m3)

Commercial

Trichloroethene (TCE) 5

Perchloroethylene (PCE) 2

cis-1,2-Dichloroethene 210

trans-1,2-Dichloroethene 210

Vinyl Chloride 2

1,1-Dichloroethane 6

1,1-Dichloroethene 700

Following implementation of mitigation measures, conduct air sampling to verify effectiveness.

Page 8: RAB Vapor Intrusion Mitigation

11 BRAC Program Management Office.

Current Status and Schedule

• Vapor Intrusion Mitigation Work Plan– Draft submitted March 17, 2017– Final scheduled for Summer 2017

• Vapor Intrusion Mitigation Field Work– Scheduled for Fall 2017 through Spring 2018

• Completion Report– Draft scheduled for Summer 2018– Final Scheduled for Winter 2018

Page 9: RAB Vapor Intrusion Mitigation

12 BRAC Program Management Office.

Vapor Intrusion Mitigation

QUESTIONS ?