Core Competencies Profile SummaryExtensive experience in Concept & Feasibility Studies, Front-end Engineering Design (FEED), Pre-Commissioning & Commissioning, and Detail Design (EPC) phases of Onshore projectsProficient in utilizing innovative processing technology for delivering competitive advantage through new processes or products, quality/shelf life improvements, yield improvements, and/or other cost reductions Skilled in performing P&ID Development, Line Sizing Calculations, Pump Design Calculations, Flare Blow Down Analysis, Relief Load Calculations, Hazop Study & so on using various software tools like HYSYS, & UNISIMExcels in engineering surveys, troubleshooting & start-up assistance, pre-commissioning / commissioning assistance, operating manual review for Process and Utility unitsInsight full exposure to all global licensors like UOP, KTI B.V., AXENS, Shell, & so onSkills in supervising performance bottlenecks and taking corrective measures to avoid the same, liable for investigating the unusual / unacceptable resultsResourceful in administering the optimization and development of facility design basis/ duty specification, FEED development & Design follow-upsHolding Professional Membership of IChemE, UK, AIChE – USA, National Level and Chicago SectionTeam player with strong planning, interpersonal, analytical & negotiation skills; self-directed and able to work independently & as part of a team
Soft Skills
Work ExperienceOct’16-Till date
Oct’14-Sept’16
Apr’11-Jun’14
Jun’09-Mar’11
Samsung Engineering Co. Ltd., Korea as Senior Engineer – Process
Samsung Engineering IndiaPvt. Ltd., Noida as Principal Engineer – I
P-MECH Consultant Pvt. Ltd., Vashi as General Manager – Process
UHDE India Pvt. Ltd., Pune as Manager – Process
Process Conceptual Design
Detail Engineering
Front-end Engineering
Pre-commissioning& Commissioning
Technical Services
Project Planning & Execution
Resource Planning & Scheduling
Reporting & Documentation
Process Health & Safety
RAHUL DESHPANDE
Qualified Process Engineer with over total 22 years of experience in proposal engineering, FEED, Detailed Engineering, vendor evaluation and pre-commissioning & commissioning assistance from Refinery (Hydrocracker, Hydrogen, SRU), Fertilizer (Ammonia), Petrochemical (Maleic Anhydride, Butadiene Extraction unit BdEU and Benzene Extraction Unit BzEU), Polymer (Polybutadine Rubber PBR), LNG, Power Plant(BOP) and Off-site & Utilities Projects
+919004392206 [email protected]
Change Agent
Collaborator Communicator
Motivator Planner
Previous ExperienceMar’08-May’09
Jan’06-Mar’08
Mar’04-Nov’05
Aug’02-Mar’04
Sep’00-May’02
Aug’94-Sept’00
Key Result Areas:Performing process conceptual study, process calculation &process optimization activity and preparing study reportPreparing all Process Engineering Documentation such as Process & Utility Flow Diagrams (PFDs & UFDs), MSD, PSFS, and Process Safeguarding memorandum (PSM), with associated Heat & Mass Balances, P&IDs, Equipment List, Line List, Process Calculations, Equipment & Instrument Process Datasheets, and Process Package specificationsContributing in Design Review, HAZOP, 3D Model Review & Value Engineering and closing out all action items; evaluating discrepancies in design and resolving issuesChecking simulations on HYSYS including preparation of PFDs & mass balance, detailing of P&IDs, checking of equipment sizing, line sizing, preparation of equipment data sheets, process data for instrumentation, process data for instrumentation, cause & effect Diagrams, line schedule, operating manuals and so onHolding technical responsibility for interfacing with other project disciplines, contractors and vendorsEnsuring that all technical and engineering requirements are met including the correct and timely performance of discipline engineering tasks within the project groupMonitoring project HS&E aspects, including adherence to statutory obligations and internal procedures; ensuring adherence with safety requirements by participating actively in HAZOP meetings conducted by Safety EngineerParticipating in Design Review & 3D Model Review and HAZOP Meetings with responsibility of closing out all the action itemsMentoring and coaching staff in a way, that they become self-starting, motivated and completion driven, all according the requirements of their function descriptionPeriodically conducting quality inspections on completed jobs and internal audits to assess the status Identifying areas of improvement and recommending process modifications to enhance operational efficiencies Coordinating for implementing suggestions / recommendations in the plant
Highlights:Independently conducted flare network design activity including safety valve capacities for Chambal Fertilizer and Chemicals Limited (CFCL) Ammonia Plant projectReceived an appreciation letter from the client - Oman LNG, Sultanate of Oman and a bonus for the good job on Nigeria LNG projectEnsured successful completion of the prestigious ESSAR Oil Refinery Sulfur Recovery Unit Project within approved budget by continuous monitoring of budget movement and optimized utilizationPrepared instrument specifications for SABIC’s generic process design package (GPDP) of LLDP plant along with the code of practicePivotal in streamlining processes through measures such as project management
Technip India Limited, Chennai as Principal Engineer
Foster Wheeler India Pvt. Ltd., Chennai as Sr. Process Engineer
Mott MacDonaold & Co. LLC, Oman as Process Engineer
Toyo Engineering India Limited, Mumbai as Sr. Process Engineer
Petro Infrastructure Engineering Consultancy, KSA as Process Engineer
Apr’ 93 - Feb’ 94
Education
Technical Skills
Professional Affiliations
Personal Details
Toyo Engineering India Limited, Mumbai as Sr. Process Engineer
Mysore Petrochemicals Limited, Taloja as Management Trainee
B.E. in Petroleum & Petrochemical from Pune university, India in 1992Diploma in Chemical Engineering of B.T.E. Maharashtra State in 1989
Application Software: Aspentech HYSYS , UNISIM, & MS OfficeIn-house Software Features: Line Sizing (Single & Two Phases), Pump Design Calculations, Relief Valve Sizing, Relief Valve Line Sizing, Flare Network Design, IA Receiver Sizing, Air Compressor, Horizontal Flare Knock-out Drum, Control Valve Sizing, Vessel sizing and Man-hours Estimation
Senior associate member of IChemE - UK Member of AIChE – USA national level and Chicago section
Date of Birth: 24th November 1969Address: 401, Atlantic Heights, Opp. Spandan Hospital, V.B.Phadke Marg, Mulund-East, Mumbai – 400 081, Maharashtra State, IndiaLanguages Known: Marathi, English, & HindiMarital status : MarriedPassport No. : L2522478Date of issue : 03/07/2013Expiry date : 02/07/2023
*Refer to Annexure for project details
ANNEXURE
Project DetailsAt Samsung Engineering Co. Ltd., Korea (Contract)
Title: ONGC Petro Additions Ltd.(OPaL) – DFCU and Associated unitsRole: Senior Engineer - Process
Coordinated with technical service providers (OPaL-SECL-SEI-Vendor), focal point forn issues between OPaL operation and SECL engineering, often in consultation with domain personsPerformed Heat Run Test of Butadiene Extraction Unit Recycle Gas Compressor – DCS Board
At Samsung Engineering India Pvt. Ltd., India
Title: KLPE Phase-II (Steam Cracker Unit)Role: Lead Engineer
Checked specifications between ITB documents, licensor document and FEED contractor documentsPerformed FEED verification work; verified process data for consistency between mechanical data sheet, process data sheet, P&IDs and material selection diagramReviewed & commented on sized equipment list of SCU Calculated & summarised Pump (NPSH)Reviewed & clarified Cause &Effect Diagram – Utility SideChecked overdesign margin between design basis and process data sheetsRevised flare header line size based on flare load summary using FLARENET softwareConducted pump hydraulic calculations for large capacity pumps and cooling water header size check;software used – HYTOSE
Title: ONGC Petro Additions Ltd.(OPaL) –DFCU and Associated unitsRole: Principal Engineer – Process, Grade-I
Performed function loop check activity for BdEU & BzEU with reference to test loop, P&IDs, cause & effect diagrams, control narrative, alarm & trip set point list and DCS consoleResolved DFCU and AU area punch list for FORMAT-IVInterfaced with technical service providers (OPaL-SECL-SEI-Vendor), focal point for issues between OPaL operation and SECL engineering, often in consultation with domain personsRendered services as an Area Coordinator for DFCU and AUProvided resolution to client comments on operating manual (OM) and as-built drawingsEnsured pre-commissioning activities are executed according to plan, project scope & specificationsManaged NMP loading operations including Hazard Identification & Risk Assessment (HIRA), and Pre-start-up Safety Review (PSSR) Inspection ChecklistEnsured chemical cleaning and final passivation as per chemical cleaning vendor procedure Administered acceptance of facilities based on test run (pump MRT, compressor MRT), protocols – DCS board-man role
At P-mech Consultant Pvt. Ltd., India
Title: 3 x 2 MW PS-3 Power Plant Role: Lead Engineer
Updated P&ID based on client’s commentsCalculated line sizing for HT & LT cooling water system, lube oil system, charge air & exhaust air system and compressed air systemPrepared equipment data sheetsPerformed pump design calculations
Title: 200MW Ashuganj Power PlantRole: Lead Engineer
Updated P&ID based on 3D model Performed line sizing calculations for HT & LT cooling water system, lube oil system, fuel gas system, main pipe module, charge air & exhaust air system and starting & control air systemCalculated pump design for HT & LT cooling water system
Title: BPCL Uran LPG Bottling PlantRole: Lead Engineer
Prepared Conceptual &Feasibility Study Report of new LPG lines from mounted sphere vessel (MSV) to pump house No. 1 & 2Did TBA of LPG transfer pump
Title: OOCEP (Enerflex P&P Job#K3030)Role: Lead Engineer
Updated P&IDs Prepared vessel data sheets & valve list
Title: TLP Compressor AreaRole: Lead Engineer
Performed hydraulic calculations for compressed air lines, cooling water lines and make-up water linesPrepared valve list & instrument data sheets
Title: Domgas ProjectRole: Lead Engineer
Updated Tr.1 and Tr.2 P&ID based on client’s mark-upPrepared equipment list &valve list
Title: HPCL Gantry Augmentation (Sewree – II)Role: Lead Engineer
Developed P&ID for a 8bay gantryPerformed pump design calculationsFormulated line list & valve list Prepared design basis
Title: Chittagong Power PlantRole: Process Engineer
Performed duct pressure drop and line sizing calculations
At Uhde India Pvt. Ltd., India
Title: IOCL VGO UnitRole: Process Engineer
Prepared flushing plansProvided pre-commissioning and commissioning assistanceCoordinated with Licensor & IOCL Core Engineering Group
Title: Al-Jubail Fertilizer CompanyRole: Process Engineer
Conducted Vibration Study of control valve FV-67 from CO2 removal section
Title: Synthetic Iron Oxide Pigment PlantRole: Lead Engineer
Developed P&IDsPrepared enquiry specifications, vendor documents review, Technical Bid Analysis(TBA) and Technical Recommendations (TR)Reviewed equipment data sheetsDeveloped instrument data sheets
At Technip India Limited, India
Title: Essar Oil Refinery Expansion Project – New Sulphur Recovery Unit Phase – I and New LT Scot Unit of Base SRU PlantRole: Lead Engineer
Managed process engineering activities from IFR stage to IFC-1 stageDeveloped PFDs, &P&IDsPrepared equipment listReviewed and updated equipment data sheets, &instrument data sheetsPerformed pump design, safety valve sizing, and flare KOD design calculationsParticipated in HAZOP study sessions and prepared HAZOP close-out report
Performed vendor evaluation for pumps, blowers and furnaces
At Foster Wheeler India Pvt. Ltd., India
Title: SABIC – Preparation of Generic Process Design Package(GPDP) for Linear Low Density Polyethylene (LLDP) PlantRole: Lead Engineer
Developed P&IDsPrepared instrument data sheets
Title: Nigeria LNG Seven Plus Project Role: Sr. Process Engineer
Prepared process specifications for EPC contractReviewed and updatedPFS, PEFS, MEFS, mass balancePerformed process engineering calculations for pumps, compressors, vessels sizing, line sizing, safety valve sizing, &instrument air requirement
Title: Pluto LNG ProjectRole: Lead Engineer
Worked on the following units –Dehydration Unit, Acid Gas Recovery Unit, Regenerative Thermal Oxidizer Unit, Liquefaction Unit, Mercury Removal Unit, Refrigeration Storage Unit, &Fractionation UnitConducted following process engineering activities in the above units – PFS & PEFS review, mass balance review, preparation of equipment data sheets, process safeguarding memorandum, cause & effect diagram, relief valve sizing calculations, and compressor hydraulics calculations
Title: Pluto LNG ProjectRole: Lead Engineer
Worked for the following offsite & utility units –Refrigerant Storage, Condensate Storage, Demineralized Water Unit, Potable Water Unit, Cooling Water Unit, Instrument, and Tool Air UnitAdministered process activities like PFS & PEFS review, process design basis, hydraulic calculations, equipment and instrument datasheets
Title: IOCL Refinery ProjectRole: Sr. Process Engineer
Developed interconnecting P&IDs and utility distribution diagramsPerformed hydraulic calculations for offsite & utility pumps
At Mott MacDonald and Co. LLC, Sultanate of Oman (Contract)
Title: Oman LNG (Tr.1 and Tr.2)Role: Process Engineer
Worked with OLNG Shell Technologists for plant modifications and expansion project in the development of process design basis, pump hydraulics calculations, power recovery turbine calculations, fuel gas balance calculations, site verifications and HAZOP study sessions
At Toyo Engineering India Limited, India
Title: Kujang Fertilizer ProjectRole: Sr. Process Engineer
Reviewed PFD, P&ID, & Material Balance Prepared equipment and instrument datasheets
Title: KR2 Revamp ProjectRole: Sr. Process Engineer
Worked for Condensate Fractionation Unit, Naphtha Hydrotreating Unit, Mercury Removal UnitPerformed process engineering activities pump hydraulic calculations, equipment and instrument data sheets preparation, vessel sizing calculations and safety valve sizing calculations
Title: Motor Spirit Unit (Isomerization Unit)Role: Sr. Process Engineer
Reviewed & updated P&IDs, and Equipment &Instrument Datasheets
At Petro Infrastructure Engineering Consultancy, Saudi Arabia (Contract)
Title: Saudi Aramco ProjectsRole: Process Engineer
Performed detailed engineering activities
Title: Ar-Razi Saudi Methanol Company ProjectRole: Process Engineer
Prepared PFD, P&ID, &Instrument Datasheets
Title: Ar-Razi Saudi Methanol Company ProjectRole: Process Engineer
Performed detailed engineering work for refinery upgradation based on operation feedback
At Toyo Engineering India Limited, India
Title: Mangalore Refinery and Petrochemicals Ltd. (MRPL), Phase I and Phase IIRole: Sr. Process Engineer
Worked for hydrocracker and hydrogen unitsPerformed detailed engineering activities pump hydraulic calculations, P&ID review, equipment and instrument datasheet reviewProvided pre-commissioning and commissioning assistance on site to ClientPrepared pressure balance report of the plantCoordinated between licensor, site construction team, operation team and PMC team
Title: Chambal Fertilizer and Chemicals Limited (CFCL) Ammonia PlantRole: Sr. Process Engineer
Worked from beginning of the project IFR stage to IFC-1 stagePerformed detailed engineering activities, flare network design, DCS – Factory Acceptance Test (FAT) at vendor’s office and prepared pre-commissioning documents
Title: Polybutadine Rubber PlantRole: Sr. Process Engineer
Provided pre-commissioning and commissioning assistance in the form of preparation of punch list, flushing schemes for utilities, leak test, preparation of water run trial test, preparation and establishment of solvent circulation loop
At Mysore Petrochemicals Limited, India
Title: Maleic Anhydride PlantRole: Shift Engineer
Managed day-to-day production shift activities, manpower handling, preparation of production shift reports, filling of the daily process log sheets and troubleshooting of the plant