Rail Baltica progress in Lithuania in 2018 Plans for 2019 Arenijus Jackus Director of Rail Baltica Coordination Department Railway Infrastructure Directorate at JSC Lithuanian railways January 23, 2018

Upload: others

Post on 03-Feb-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • Rail Baltica progress in Lithuania in2018Plans for 2019Arenijus JackusDirector of Rail Baltica CoordinationDepartment Railway InfrastructureDirectorate at JSC Lithuanian railways

    January 23, 2018

  • 20252018 2020 2021 2023

    Land expropriated for

    public needsKaunas-LT/LV

    Completed spatialplanning

    PL/LT - Kaunas

    A technical design prepared

    Kaunas-LT/LV

    Completed spatialplanning

    Vilnius-Kaunas

    Land expropriated for

    public needsPL/LT -Kaunas

    A technicaldesign prepared

    PL/LT -Kaunas

    Land expropriated for

    public needsVilnius-Kaunas

    A technicaldesign prepared

    Vilnius-Kaunas

    Project implemented

    Completed construction

    worksAll sections

    IMPLEMENTATION OF THE „RAIL BALTICA“ PROJECT. LITHANIA

    Completed construction ofsection Jiesia –

    Rokai

    Completed construction of section Kaunas –

    Palemonas

    Completed construction ofsection Rokai -

    Palemonas

  • 2016-2021Construction Rokai -Palemonas

    By the end of 2025Construction of 1435 mm "Rail Baltica" lineKaunas - LT / LV state border, Kaunas - Vilnius

    By the end of 2025• Spatiall planning. 2018

    December - LTGovernment resolutionadopted for:

    PL/LT – Kaunas”,Kaunas Node, “Vilnius –Kaunas”

    infrastructure facilities• Design and upgrading/

    construction Kaunas –PL / LT

    Poland

    Latvia

    RU

    BY2016-2018

    Constructed Jiesia – Rokai

    2016-2020Construction Kaunas -Palemonas

    Kaunas-LT/LV (167 km)• Completed Special plan and EIA;• Ongoing Land acquisition for: Main line. Plan to be completed in Q1 2019 Local Access roads. Preparatory stage• Ongoing preparation of the Technical design

    Kaunas - LT / LV

    Archaeological study, procurement

    Kaunas – Vilnius (100 km)Feasibility study is already prepared

    2013-2015 Constructed PL/LT – Kaunas(central station). Built 120 km of 1435 mm RB line, 1 stage.

  • KAUNAS NODE. THE WAY FORWARD

    Jiesia

    Rokai

    Kaunas

    Palemonas

    HES

    OP: Kaunas node can be seen as the main

    hub of Rail Baltica, ...gateway to the

    Lithuanian railway network both on 1435

    mm gauge and on 1520 mm gauge

    Decisions on Kaunas Node were made -

    agreed with project partners and the

    European Commission

    Construction workscontinues.

    Plan to be finished in2021

  • IMPLEMENTATION OF „RAIL BALTICA“ PROJECT IN 2018. PLANS FOR 2019

    2019Kaunas–

    PalemonasConstruction

    ongoing

    Land acquisition

    Kaunas - LT / LV completed

    Rokai –Palemonas

    Constructionstarted

    Land acquisition

    Project Kaunas - LVcompleted, acquisition

    ongoing

    Jiesia-RokaiConstruction completed

    Construction onsection Kaunas–

    Palemonas started

    2018

    The project coordinator RB Rail implements:Studies, including

    - Technical Studies;- Commercialization

    Studies

    Technical designSection Kaunas - LT / LV

    Vilnius connection

    study completed

    Initiated Spatialplanning procedure.

    Resolution of the Government

    adopted

    Archeological study Kaunas –LT/LV started

    Preparation of specialplans and EIA Sections

    “PL/LT – Kaunas”, Kaunas Node, “Vilnius –

    Kaunas” and railway infrastructure facilities

    started

  • Thank you for your attention

    Rail Baltica progress in 2018 �Plans for 2019The Project Progress in 2018 �Political Commitments Slide Number 3Design Guidelines Approved�7 Detailed Technical Design Tenders Launched�List of participants �Detailed Technical Design in Estonia  Detailed Technical Design in Latvia Detailed Technical Design in Lithuania Key studies in 2018 Finished and procured ongoing technical studiesStudies completed or to be completed soonSlide Number 18Key procurements in 2019Thank you for your attention!Slide Number 21Slide Number 22Rail Baltica route alignment in Estonia approved Technical design and construction in 2019Ülemiste passenger terminalPärnu passenger terminalMuuga multimodal freight terminalEnvironment and horizontal studiesThank you!Slide Number 30Slide Number 31Slide Number 32Slide Number 33Slide Number 34Slide Number 35Slide Number 36Slide Number 37Rail Baltica progress in Lithuania in 2018 �Plans for 2019Slide Number 39Slide Number 40KAUNAS NODE. �THE WAY FORWARD IMPLEMENTATION OF „RAIL BALTICA“ PROJECT IN 2018. PLANS FOR 2019Thank you for your attention