RANJANGAON PROJECT PROGRESS - JUNE 2017

Upload: others

Post on 11-Mar-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

RANJANGAON PROJECT PROGRESS - JUNE 2017

Page 2: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

JASPER

Page 3: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

Jasper Progress Status

Possession activities are in progress.

Page 4: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

JET

Page 5: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

Jet Progress Status

• Internal Painting work done at all floors.

• Sanitary ware fixing work in progress.

• Lift Installation done, Testing in progress.

• All Common area tiling done, Lift cladding in progress.

• Common area & External painting done.

• Internal finishes and Possession activities in progress.

Page 6: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

MOONSTONE

Page 7: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

Moonstone Progress Status

All flat internal tiling work completed, Common staircase tiling done. Common passage tiling in progress.

Aluminum window fixing work in progress.

Lift material received at site.

External paint completed.

Flat internal electrical wiring completed from 1st to 4th floor.

External plumbing work 85% complete.

Page 8: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

LARIMAR

Page 9: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

Larimar Progress Status

• All Floor flat internal tiling work completed.

• External painting work completed on long side, Short side work in progress.

• Flat Internal painting work in progress, Primer putty done at all floors.

• 80% Aluminum window work done at all floors.

• External plumbing line work done.

• Lift lobby & staircase tiling work done.

• Lift Shaft chipping & Laser survey done.

Page 10: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

ONYX

Page 11: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

ONYX Progress Status

Internal & External plaster done at all Floors.

External primer coat done.

Internal concealed plumbing work complete.

Toilet Dado Work in Progress, 30% Done at all floors.

Page 12: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

QUARTZ

Page 13: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

QUARTZ Progress Status

• 2nd slab completed, 3rd slab 70% work done

Page 14: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

RUBY

Page 15: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

RUBY Progress Status

Footing and stub wall work in progress.

Page 16: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

Jade Plinth Preparation Pearl Plinth Preparation

Emerald ExcavatedDiamond Excavated

Page 17: Ranjangaon Project Progress- May 2017 · 2017. 7. 14. · Ranjangaon Project Progress- May 2017 Author: TBS Created Date: 7/14/2017 12:41:26 PM

Development Activities

Approach road Plum wall RCC work in progress.

Main road curb stone fixing work in progress.

Entrance plaza line out work in progress.

DC area civil work done.

Hardscape work in progress near Jasper & Jet. Senior citizen area hardscape done.

Retaining wall finishing work in progress