Protection & Automation Strategies for Distribution Automation in a Smart Grid12th International Workshop On Electric Power Control Centers Bedford Springs, Pennsylvania, USAJune 2-5, 2013

Ratan Das, Senior Principal Engineer, Distribution Automation, June 5, 2013

30 May 2013 | Slide 1

© ABB

Grid

Distribution System

Centralized Substation Protection and Automation

Balancing Authority to DMS

Introduction

30 May 2013 | Slide 2

© ABB

Understanding the Grid

30 May 2013 | Slide 3

Source: NERC Document - Understanding the Grid DEC12

© ABB

A Proposed Natural Gas

Combined Cycle Power Plant in

New YorkSource: New York Power Authority

How the Grid is Changing

30 May 2013 | Slide 4

http://www.naturalgas.org/overview/uses_eletrical.asp

http://www.seia.org/research-resources/solar-industry-data

http://www.saferwholesale.com/WG7-5KW-Wind-Turbine-Wind-Generator-7500W-48V-p/gud-wg75kw.htm

© ABB30 May 2013 | Slide 5 http://www.nerc.com/news/Headlines%20DL/NERC_Regions_Color_072512.jpg

FRCC: Florida ReliabilityCoordinating CouncilMRO: Midwest ReliabilityOrganization NPCC: Northeast PowerCoordinating CouncilRFC: ReliabilityFirstCorporationSERC: SERC ReliabilityCorporationSPP: Southwest PowerPoolTRE: Texas Reliability Entity WECC: Western ElectricityCoordinating Council

© ABB30 May 2013 | Slide 6

http://www.opuc.texas.gov/images/NERC_Interconnections_Map.jpg

Electricity to 334 million people Electricity demand of 830 GW 211,000 miles/340,000 Km. of high-voltage transmission line (230kV or higher)

© ABB30 May 2013 | Slide 7 http://www.ferc.gov/market-oversight/mkt-electric/nerc-balancing-authorities.pdf

Over 100 Balancing Authorities. Overseeing the Balancing Authorities are operators called Reliability Coordinators.

Relationship between Reliability Coordinators and Balancing Authorities is similar to that between air traffic controllers and pilots.

© ABB30 May 2013 | Slide 8 https://www.rfirst.org/Pages/AboutUs.aspx

RELIABILITY FIRST CORPORATION (RFC) NJDEPAMDWVOHINMI ILKYTNVAWIDC

Load Serving Entities (LSE): 53Bay City, Cannelton Utilities, City of Chelsea, City of Croswell, City of Eaton Rapids, City of Hart, City of Lansing City of Marquette Board of Light & Power, City of Portland, City of St. Louis, City of Wyandotte, Cloverland Electric Cooperative, CMS ERM Michigan LLC, Constellation New Energy (MECS‐CONS), Constellation New Energy, Consumers Energy Company 3.7%,Detroit Edison Company 5%,Duke Energy Indiana 3.3%,Ferdinand Municipal Light & Water,FirstEnergy Solutions (MECS‐DET), FirstEnergy Solutions (MECS‐DET),Glacial Energy (MECS‐DET), Holland Board of Public Works, Hoosier Energy Indiana Municipal Power Agency (DUKE CIN), Indiana Municipal Power Agency (NIPSCO), Indiana Municipal Power Agency, Indianapolis Power & Light, Integrys Energy Services (MECS‐CONS), Integrys Energy Services (MECS‐DET), Just Energy (MECS‐DET), Michigan Public Power Agency, Michigan South Central Power Agency, MidAmerican Energy Company Retail, Northern Indiana Ontonagon County Rural Electrification Assoc. PJM Interconnnection, LLC 77%Sempra Energy Solutions (MECS‐CONS)Sempra Energy Solutions (MECS‐DET) Direct Energy (fka:Strategic Energy,LLC) (MECS), Direct Energy (fka:Strategic Energy,LLC) (MECS), Spartan Renewable Energy, Thumb Electric Cooperative US Department of Energy, Vectren Energy Delivery of IN, Village of Sebewaing Wabash Valley Power Association Inc. Wabash Valley Power Association Inc. (MECS C), Wabash Valley Power Association Inc.(NIPSCO) Wisconsin Electric Power Co. 3%Wolverine Power Marketing Cooperative Wolverine Power Supply Cooperative Wolverine Power Marketing Cooperative

© ABB30 May 2013 | Slide 9

PJM INTERCONNECTION, LLC NJDEPAMDWVOHINMI ILKYTNVANCDC

Membership: 800+Generating capacity:~186 GWPeak demand:~164 GWGenerating Sources: ~1350Solar: Over 1 GWTransmission lines (mi): ~60kGWh of annual energy:~832Annual billings: ~$29BStates served: 13+DCSquare miles: ~214,000Population: ~60 M

EMS:Analogs: ~50,000 (2Sec-10Sec)Buses: ~14,000 (69-765 kV)(~7000 neighboring buses)PMU: 129/81 Substations

http://www.pjm.com/

© ABB

IED Interfaces

30 May 2013 | Slide 10

Sensor

IED

Switchgear

Circuit Breaker Station Computer/ Concentrator/Station Automation System

PC/TabletInstrument Transformer

© ABB

Present Distribution System

30 May 2013 | Slide 11

DMS

IED 1 IED 2 IED n

RTU

Non Microprocessor

Relay PU n…MU 2…MU 1…

Comm. Network

Comm. Network

IEC 61850-9-2

GOOSE

Instrument Transformer/Sensor/Breaker

LAN/WAN/Serial

LAN/WAN

Control Center

Substation

Bay

Process Units

IED 3

PU 1…

Hardwired

PU x…

IEC61970/61968, IEC61580, IEC101, IEC104, DNP, Modbus, etc.

Station Automation System

GPS Limited FLISRVVO/CVRLimited IT-OT Convergence

Limited FLISRLimited VVO/CVRLimited IT-OT Convergence

© ABB

Future Distribution System

30 May 2013 | Slide 12

DMS

Station Protection & Automation System

IMU 1…IED n

RTU

Non Microprocessor

Relay PU n…

Comm. Network

Comm. Network

GOOSE

LAN/WAN/Serial

LAN/WANControl Center

Substation

Bay

Process Units

IED 1

PU 1…

Hardwired

PU x…

IMU n…

Instrument Transformer/Sensor/Breaker

IEC61970/61968, IEC61580, IEC101, IEC104, DNP, Modbus, etc.IEEE 1588, IRIG B

IEC 61850-9-2

FLISRVVO/CVRSE Asset Mgmt (IT-OT)

GPS

FLISRVVO/CVRSE Asset Mgmt (IT-OT)

GPS

© ABB

Balancing Authority (BA) to DMS

30 May 2013 | Slide 13

BA EMS

Utility 1 EMS

Comm. Network

Comm. Network LAN/WAN

MAN/WAN

BA Control Center

Utility EMS

Utility 1 DMS

IEC61970/ IEC61968, IEC61580

SEContingency Analysis AGCVVO Asset Mgmt (IT-OT)

GPS

GPS SE Contingency Analysis AGCVVO

DMS 1

GPS

DMS 2

GPS

DMS n

GPS

FLISRVVO/CVRSE Asset Mgmt (IT-OT)

Utility n EMS

GPS

© ABB

Summary

30 May 2013 | Slide 14

Grid

Distribution System

Centralized Substation Protection and Automation

Balancing Authority to DMS

© ABB

For Additional Information or Discussion

30 May 2013 | Slide 15

Contact: Ratan DasSenior Principal EngineerABB Inc., Distribution [email protected]