rate analysis

13
BRICK WORK Half brick wall volume of brick = 0.215 X 0.1025 X 0.065 = 0.00143 effective volume of a brick = 0.225 X 0.1025 X 0.075 = 0.00173 = 1.000 X 1.000 X 0.1025 = 0.10250 = 0.103 = 59.26 0.002 = 59.00 = 0.103 - 59 X 0.001432438 = 0.01799 Nr of bricks in a square = 59 = 546.30 0.108 = 547 One brick wall header coarse = 1 X 0.5 X 0.215 = 0.1075 effective volume of a brick = 0.215 X 0.1125 X 0.075 = 0.0018 = 0.108 = 59.26 0.002 strecher coarse = 1 X 0.5 X 0.215 = 0.1075 effective volume of a brick = 0.215 X 0.225 X 0.075 = 0.00363 = 0.108 X 2 = 59.26 0.004 Total Nr of bricks = 59.26 + 59.2592593 = 118.52 Nr of bricks in a square = 118.5 = 1097.39 0.108 = 1097 Sand & Cement Quantities of 1:5 Mortar bulk volume of mortar = 1 + 0.33 = 1.33 bulk volume of cement = 1.33 X 1 = 0.22166667 6 bulk volume of sand = 1.33 X 5 = 1.10833333 6 = 0.222 X 1441 X 0.01798619 = 0.086 Cube 50 1.33 = = 0.43196827 Cube Nr of bricks per 1m 2 volume of a brick in 1m 2 Nr of bricks in 1m 2 volume of mortar in 1m 2 volume of a brick in 1m 2 Nr of bricks in 1m 2 Nr of bricks in 1m 2 m 3 m 3 m 3 volume of cement in 1m 2 volume of sand in 1m 2

Upload: samanmala-senarath

Post on 26-Oct-2015

71 views

Category:

Documents


1 download

DESCRIPTION

construction field

TRANSCRIPT

BRICK WORK

Half brick wall

volume of brick = 0.215 X 0.1025 X 0.065 = 0.00143

effective volume of a brick = 0.225 X 0.1025 X 0.075 = 0.00173

= 1.000 X 1.000 X 0.1025 = 0.10250

=0.103

= 59.260.002

= 59.00

= 0.103 - 59 X 0.00143244 = 0.01799

Nr of bricks in a square =59

= 546.300.108= 547

One brick wall

header coarse = 1 X 0.5 X 0.215 = 0.1075

effective volume of a brick = 0.215 X 0.1125 X 0.075 = 0.0018

=0.108

= 59.260.002

strecher coarse = 1 X 0.5 X 0.215 = 0.1075

effective volume of a brick = 0.215 X 0.225 X 0.075 = 0.00363

=0.108

X 2 = 59.260.004

Total Nr of bricks = 59.26 + 59.259259 = 118.52

Nr of bricks in a square =118.5

= 1097.390.108

= 1097

Sand & Cement Quantities of 1:5 Mortar

bulk volume of mortar = 1 + 0.33 = 1.33

bulk volume of cement =1.33 X

1= 0.2216667

6

bulk volume of sand =1.33 X

5= 1.1083333

6

=0.222 X 1441 X 0.0179862

= 0.086 Cube501.33

= = 0.4319683 Cube

Nr of bricks per 1m 2

volume of a brick in 1m2

Nr of bricks in 1m2

volume of mortar in 1m2

volume of a brick in 1m2

Nr of bricks in 1m2

Nr of bricks in 1m2

m3

m3

m3

volume of cement in 1m2

volume of sand in 1m2

= 0.086 X 5 = 0.4319683 Cube

Rate analysis for half brick wall

(per square)

materials

550 Bricks @ 7.50 = 4,125.00 add5% wastage = 206.25

1.30 cwt cement @ 790.00 = 1,027.00

0.10 cube sand @ 6800.00 = 680.00

50 gal water @ 1.50 = 75.00 = 6,113.25

labour

1.5 day skilled labour @ 1000.00 = 1,500.00

2 day u/skilled labour @ 600.00 = 1,200.00

add5% scaffolding = 60.00 8,873.25

basic rate per square = 8,873.25

add35% profit & overhead = 3,105.64

11,978.89

FORMWORK

Column Formwork (9 " X 9 " X 5 ')

4 X9

X 5 = 15.00

= 1.39 12 10.76

(i) Material

18.15 sq.ft 25mm thk. Class II timber planks @ 45.00 = 816.75

17.10 L.ft 50X50 mm ClassII timber yorks @ 20.00 = 342.00

16.12 L.ft 50X25mm thk. Class II timber battens @ 12.00 = 193.44

1.50 pounds wire nails @ 95.00 = 142.50 = 1,494.69

(ii) Labour for fabricating

0.5 day carpenter @ 1,000.00 = 500.00

volume of sand in 1m2

A.Making Mould

0.5 day u/skilled labour @ 600.00 = 300.00

total cost for making mould = 2,294.69 = 2,294.69

assume 4 uses & cost per use 2,294.69 = 573.67 = 573.67 4

(i) Material

12 Nos 16mm Dia. 18" long bolts @ 300.00 = 3,600.00

Assume 20 uses & cost per use 3,600.00 = 180.00 = 180.00 20

0.5 ltr mould oil @ 250.00 = 125.00 = 125.00

35 L.ft 100X50mm props @ 40.00 = 1,400.00 Assume 10 uses & cost per use 1,400.00

= 140.00 = 140.00 10 1,018.67

(ii) Labour

0.25 day carpenter @ 1,000.00 = 250.00

0.25 day u/skilled labour @ 600.00 = 150.00

total cost for making mould = 400.00 = 400.00

cost per assembling per use = 1,418.67

Labour

0.25 day carpenter @ 1,000.00 = 250.00

0.25 day u/skilled labour @ 600.00 = 150.00 = 400.00

total cost for 9"X9" column 5'-0" high per use = 1,818.67

= 1,818.67

= 1304.59 1.39

25% profit & overhead = 1,630.74

Beam Formwork ( 9 " X 12 " X 20" )

contact area =9

20 + 212

20 = 5512 12

=55

= 5.11 m2 10.76

B.Assembling(Per use)

C.Dismentling,cleaning & repairing (Per use)

per 1m2

(i) Material

60.00 sq.ft 25mm thk. Class II timber planks @ 45.00 = 2,700.00

24.00 L.ft 50X25 mm ClassII timber batttens @ 12.00 = 288.00

45.00 L.ft 50X50mm thk. Class II timber ledgers @ 20.00 = 900.00

30.00 L.ft 100X50mm thk. Class II timber bearers @ 40.00 = 1,200.00 at bottom of mould

2.00 pounds wire nails @ 95.00 = 190.00 = 5,278.00

(ii) Labour for fabricating

1.5 day carpenter @ 1,000.00 = 1,500.00

2 day u/skilled labour @ 600.00 = 1,200.00 = 7,978.00

total cost for making mould = 7,978.00

assume 4 uses & cost per use 7,978.00 = 1,994.50 = 1,994.50 4

10% add for repairs = 199.45 = 199.45

cost per use = 2,193.95

(i) Material

110.00 L.ft 100X50mm thk. Class II timber props @ 40.00 = 4,400.00

80.00 L.ft 50X50mm thk. Class II bracings to @ 20.00 = 1,600.00 moulds & props

50.00 L.ft 50X50mm thk. Class II bracings to @ 20.00 = 1,000.00 moulds & props

6.00 sq.ft 25mm thk. Class II timber base @ 45.00 = 270.00 plate to props

22.00 nos. wedges @ 15.00 = 330.00 = 7,600.00

Assume 6 uses & cost per use 7,600.00 = 1,266.67 = 1,266.67 6

10% add for repairs = 126.67 = 126.67

cost for assembling = 1,393.33

1.00 day carpenter @ 1,000.00 = 1,000.00

2.00 day u/skilled labour @ 600.00 = 1,200.00

A.Making Mould

B.Assembling(Per use)

C.Labour & sundries

0.50 gal mould oil @ 1125.00 = 562.50

0.50 pounds wire nails @ 95.00 = 47.50

cost per use for assembling = 2,810.00 = 2,810.00

Labour

0.50 day carpenter @ 1,000.00 = 500.00

2 day u/skilled labour @ 600.00 = 1,200.00

cost per use for assembling = 1,700.00 = 1,700.00

total cost for making mould,assemling,repairing,dismentling & cleaning per use = 8,097.28

8,097.28 = 1,584.12

5.11

25% profit & overhead = 1,980.15

Slab Formwork ( 20 " X 10 " )

contact area 20 X 10 = 200

200 = 18.5910.76

(i) Material

220 sq.ft 25mm thk. Class II timber planks @ 45.00 = 9,900.00 with tung & groove jooints

121.00 L.ft 100X50 mm ClassII timber runners @ 40.00 = 4,840.00 at 2'-0" intervals

4.00 pounds wire nails @ 95.00 = 380.00 = 15,120.00

(ii) Labour for fabricating

3.00 day carpenter @ 1,000.00 = 3,000.00

3.00 day u/skilled labour @ 600.00 = 1,800.00 = 19,920.00

total cost for making mould = 19,920.00

assume 4 uses & cost per use 19,920.00 = 4,980.00 4

20% add for repairs = 996.00

D.Dismentling,cleaning & repairing (Per use)

per 1m2

A.Making Panel

cost for assembling = 5,976.00 = 5,976.00

(i) Material

690.00 L.ft 100X50mm thk. Class II timber props @ 40.00 = 27,600.00

66.00 L.ft 50X50mm thk. Class II bracings to @ 20.00 = 1,320.00 props

122.00 nos. wedges @ 15.00 = 1,830.00

333.00 sq.ft 25mm thk. Class II timber base @ 45.00 = 14,985.00 = 45,735.00 plate to props

Assume 6 uses & cost per use 45,735.00 = 7,622.50 = 7,622.50 6

1.00 day carpenter @ 1,000.00 = 1,000.00

4.00 day u/skilled labour @ 600.00 = 2,400.00

1.00 gal mould oil @ 1125.00 = 1,125.00

2.00 pounds wire nails @ 95.00 = 190.00

cost per use for assembling = 4,715.00 = 4,715.00

Labour

0.50 day carpenter @ 1,000.00 = 500.00

2 day u/skilled labour @ 600.00 = 1,200.00

cost per use for assembling = 1,700.00 = 1,700.00

total cost for making mould,assemling,repairing,dismentling & cleaning per use = 20,013.50

20,013.50 = 1,076.73

18.59

25% profit & overhead = 1,345.91

1. 10mm dia. T/S for issolated column footings not exceeding 1.5 m depth from G.L2. 20mm dia. T/S in columns up to DPC level3. 6mm dia. M/S for strruips in columns up to DPC level

B.Assembling(Per use)

C.Labour & sundries

D.Dismentling,cleaning & repairing (Per use)

per 1m2

Ex: Tender hs been called for construction of two storey office building Colombo.analysis the following rate per tender purpose.

Material

Labour

ADVANCED MATHEMATICAL TECHNIQUES FOR ENGINEERING APPLICATIONS

HYDRAULICS & HYDROLOGY

THE ANALYSIS OF ENGINEERING STRUCTURES

THE DESIGN OF ENGINEERING STRUCTURES

GEOTECHNICAL ENGINEERING

PROPERTIES OF MATERIALS FOR ENGINEERING APPLICATIONS

ADVANCED MATHEMATICAL TECHNIQUES FOR ENGINEERING APPLICATIONS

HYDRAULICS & HYDROLOGY

THE ANALYSIS OF ENGINEERING STRUCTURES

THE DESIGN OF ENGINEERING STRUCTURES

GEOTECHNICAL ENGINEERING

PROPERTIES OF MATERIALS FOR ENGINEERING APPLICATIONS

ADVANCED MATHEMATICAL TECHNIQUES FOR ENGINEERING APPLICATIONS

PROPERTIES OF MATERIALS FOR ENGINEERING APPLICATIONS

ADVANCED MATHEMATICAL TECHNIQUES FOR ENGINEERING APPLICATIONS

PROPERTIES OF MATERIALS FOR ENGINEERING APPLICATIONS