  • ravenna

  • Production capacity

    Generation section 1 -

    -

    Composed of:

    • one 122.8 MWe gas turbine plant (TG501) with a recovery steam boiler (BA501) - 190 t/h high pressure steam and 44 t/h low pressure steam

    • two condensation and partial back-pressure turbines: 37.5 MWe (20TD2) and 65 MWe 20TD300

    Generation section 2 Composed of two combined cycles each made up of:

    • one 266 MWe gas turbine plant

    • one recovery steam boiler - 280 t/h high pressure steam, 44 t/h medium pressure steam, 32 t/h low pressure steam

    • one 127 MWe steam turbine

    Year the combined cycles became operational

    2004

    Products

    Electricity

    Technological steam

    Eni companies served at the site

    Versalis and Syndial

    Address

    via Baiona, 107 – 48100 Ravenna

    certification

    Re g.n.IT-001459

    GESTIONE AMBIENTALEVERIFICATA