ravensthorpe nickel operations - first quantum minerals

18
RAVENSTHORPE NICKEL OPERATIONS April 2013

Upload: others

Post on 19-Mar-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

RAVENSTHORPE NICKEL OPERATIONS

April 2013

2

Disclaimer

Certain statements and information contained in this presentation, including all statements that are not historical facts, contain forward-looking statements and forward-looking information within the meaning of

applicable securities laws. Such forward-looking statements or information include but are not limited to statements or information with respect to the anticipated commencement, completion and terms of the proposed

offer and the anticipated strategic and operational benefits of the offer. Often, but not always, forward-looking statements or information can be identified by the use of words such as “plans”, “expects” or “does not

expect”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “projects”, “anticipates” or “does not anticipate” or “believes” or variations of such words and phrases or statements that certain

actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved.

With respect to forward-looking statements and information contained in this presentation, First Quantum has made numerous assumptions including among other things, assumptions about the price of copper, gold,

cobalt, nickel, PGE, and sulphuric acid, anticipated costs and expenditures, and First Quantum's ability to achieve its goals. Although management of First Quantum believes that the assumptions made and the

expectations represented by such statements or information are reasonable, there can be no assurance that a forward-looking statement or information herein will prove to be accurate. Forward-looking statements and

information by their nature involve known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements, or industry results, to be materially different from any

future results, performance or achievements expressed or implied by such forward-looking statements or information. These risks, uncertainties and other factors include, but are not limited to, uncertainties surrounding

the ability to realize operational synergies following completion of the offer, reliance on Inmet’s publicly available information which may not fully identify all risks related to its performance, success in integrating the

retail distribution systems, and the integration of supply chain management processes, future production volumes and costs, costs for inputs such as oil, power and sulphur, political stability in Zambia, Peru, Mauritania,

Finland, Turkey, Spain, Panama and Australia, adverse weather conditions in any of the foregoing countries, labor disruptions, mechanical failures, water supply, procurement and delivery of parts and supplies to the

operations and the production of off-spec material.

See First Quantum’s annual information form for additional information on risks, uncertainties and other factors relating to the forward-looking statements and information. Although we have attempted to identify factors

that would cause actual actions, events or results to differ materially from those disclosed in the forward-looking statements or information, there may be other factors, many of which are beyond the control of First

Quantum, that might cause actual results, performances, achievements or events not to be anticipated, estimated or intended. Accordingly, readers should not place undue reliance on forward-looking statements or

information.

While First Quantum may elect to update the forward-looking statements at any time, First Quantum does not undertake to update them at any particular time or in response to any particular event, other than as may be

required by applicable securities laws. Investors and others should not assume that any forward-looking statement contained in this presentation represents management's estimate as of any date other than the date of

this presentation.

Neither First Quantum nor any of its directors or officers has verified the accuracy or completeness of information or statements contained herein which are made by or derived from third-party sources (including any

projections or estimates made by third-party research analysts). Such third-party sources may have failed to identify events or facts which may have occurred or which may affect the significance or accuracy of any such

information or statements. First Quantum has no means of verifying the accuracy or completeness of such information or statements made by or derived from third-party sources or whether there has been any failure by

such sources to identify events that may have occurred or may affect the significance or accuracy of any information or statements.

This presentation does not constitute an offer to buy or an invitation to sell, or the solicitation of an offer to buy or invitation to sell, any securities of First Quantum or Inmet. Such an offer may only be made pursuant to

the offer and takeover bid circular First Quantum has filed with the Canadian securities regulators and pursuant to registration or qualification under the securities laws of any other such jurisdiction.

In accordance with applicable Canadian securities regulatory requirements, all mineral reserve and mineral resource estimates disclosed herein have been prepared in accordance with Canadian National Instrument 43-

101 - Standards of Disclosure for Mineral Projects ("NI 43-101"), classified in accordance with Canadian Institute of Mining Metallurgy and Petroleum's "CIM Standards on Mineral Resources and Reserves Definitions

and Guidelines" (the "CIM Guidelines"). The terms "mineral resources", "measured mineral resources", "indicated mineral resources" and "inferred mineral resources" are recognized by Canadian securities regulatory

authorities, however, they may not be recognized by the securities regulatory authorities of other jurisdictions. Pursuant to the CIM Guidelines, mineral resources have a higher degree of uncertainty than mineral

reserves as to their existence as well as their economic and legal feasibility. Inferred mineral resources, when compared with measured or indicated mineral resources, have the least certainty as to their existence, and it

cannot be assumed that all or any part of an inferred mineral resource will be upgraded to an indicated or measured mineral resource as a result of continued exploration. Pursuant to NI 43-101, inferred mineral

resources may not form the basis of any economic analysis, including any feasibility study. Accordingly, readers are cautioned not to assume that all or any part of a mineral resource exists, will ever be converted into a

mineral reserve, or is or will ever be economically or legally mineable or recovered.

Note: all dollar amounts in US dollars unless otherwise indicated; C$ indicates Canadian dollars

3

Itinerary

Time Activity

08:10 Project History and Overview, with Assistant General Manager and Management Team.

09:30 Mine Pit Tour for visual overview of operations (with Mining Manager):

Pit Lookout (site layout; geological overview; staged mining approach; grade control areas; Hale-Bopp and

Shoemaker-Levy deposits)

Pit tour

ROM Stockpile and Crusher area (new crushers; stacker reclaimers for blending; buffer ponds; rejects

handling)

10:30 Plant Overview by foot (with Plant Manager):

New Crushers

Beneficiation Plant

Pressure Acid Leach

Acid Leach and Power Plant

MHP Load-out

12:00 Q&A over lunch with Management Team, in Boardroom.

13:00 Depart RNO for Hopetoun.

13:30 Visit Hopetoun and RNO residential housing.

15:50 Depart Ravensthorpe for Perth.

4

Ravensthorpe - First Quantum’s Record to Date

Purchased as a decommissioned operation February 2010

Design phase February – June 2010

Recruitment campaign started June 2010

Modifications July 2010 – September 2011

First production October 2011

First exports November 2011

Commercial production 28 December 2011

2012 Production 32,884 tonnes nickel

5

Ravensthorpe’s Facts & Figures

Expected mine life >30 years

Three ore bodies Halleys

Hale-Bopp

Shoemaker-Levy

Lease Area 3,788 hectares

Corporate tax rate

Mineral royalty

30% of earnings

2.5% of net sales

Workforce 640 employees (incl. 200 contractors)

Residential Focus >200 currently live in Hopetoun

6

Our Modifications to Make Ravensthorpe Work

Front end materials handling

Dewatering

Buffer storage capacity

Upgraded Tailings Storage Facility

Refurbish existing plant

7

Ravensthorpe - Making it Work - Two New Crushing Plants

8

Ravensthorpe - Making it Work - Refurbish Stacker Reclaimers

9

Ravensthorpe - Making it Work - Dewatering and Rejects Management

10

Ravensthorpe - Making it Work - Upgraded Tailings Facility

11

Ravensthorpe - Making it Work – Refurbished Plant

The reconstructed crushing plants, beneficiation,

dewatering and rejects handling circuits are performing to

expectations and are consistently achieving the design

throughputs.

12

Ravensthorpe

Recoverable Resources

• Mineral Recoverable Resources have been defined as the recoverable portion of the Mineral Resource contained within the life of mine pit profiles as developed by the previous owners BHP Billiton.

• These estimates are considered suitable for the initial mine planning works and are currently considered as Potential Recoverable Resources by First Quantum.

13

Ravensthorpe’s Laterite Profile

14

Ravensthorpe’s Product - From Mine to Customer

CHINA –

Jinchuan,

Sichuan, Huaze

BRAZIL

INDIA

MHP shipped

via Esperance

Port

15

Ravensthorpe’s Operational Achievements to Date

AREA ACHIEVEMENT

Crushing and conveyors to reclaimer

- limonite & saprolite

1400 dry tonnes vs. 1270 dry tonnes design

Beneficiation –limonite 1050 dry tonnes vs. 1142 dry tonnes design

–saprolite 460 dry tonnes vs. 426 dry tonnes design

Atmospheric Leach 200 dry tonnes vs. 135 dry tonnes design

PAL Trains 170 dry tonnes vs. 150 dry tonnes design

MHP Loadout 140 tonnes nickel vs. 142 tonnes nickel design

Acid Plant 4200 tonnes H2SO4 vs. 4,400 tonnes H2SO4 design

16

Ravensthorpe’s Production Record to Date

17

Ravensthorpe’s Safety Performance

2012 Safety Performance Change

Lost Time Injury (LTI) Frequency Rate Reduced 0.70 to 0.13

LTI Severity Rate Reduced 24.39 to 0.26

Hazard reporting frequency Increased 20.89 to 96.07

RAVENSTHORPE NICKEL OPERATIONS

April 2013