rced-94-265 air traffic control: status of faa's plans to ... · towers in the future, thereby...

30
GAO United States General Accounting Office Report to the Chairman, Subcommittee on Transportation and Related Agencies, Committee on Appropriations, House of Representatives September 1994 AIR TRAFFIC CONTROL Status of FMs Plans to Close and Contract Out Low-Activity Towers

Upload: others

Post on 17-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

GAO United States General Accounting Office

Report to the Chairman, Subcommittee on Transportation and Related Agencies, Committee on Appropriations, House of Representatives

September 1994 AIR TRAFFIC CONTROL

Status of FMs Plans to Close and Contract Out Low-Activity Towers

Page 2: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

:., : .“’ .:

Page 3: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

---

GAO United States General Accounting Oflice Washington, D.C. 20548

- _- Resources, Community, and Economic Development Division

B-257854

September 12, 1994

The Honorable Bob Carr Chairman, Subcommittee on

Transportation and Related Agencies

Committee on Appropriations House of Representatives

Dear Mr. Chairman:

The House and Senate Appropriations Committees’ reports for the Department of Transportation and Related Agencies Appropriations Act for 1994 (P.L. 103-122) specify funding for the Federal Aviation Administration (FAA) to (1) close level 1 (low-activity) air traffic control towers that do not meet FAA’S benefit-cost criteria and (2) contract out for the operations of level 1 towers.’ The reports also specified funding to relocate, to other facilities, controllers affected by the contracting out and closures.

From fiscal year 1994 through fiscal year 1997, FAA plans to close low-activity towers that do not meet its benefit-cost criteria, contract out the operations of all remaining towers, and relocate controllers from towers that are closed or contracted out to other FAA facilities.2 FAA does not believe that safety will be jeopardized by closing or contracting out level 1 towers. FAA’S benefit-cost criteria include an assessment of safe@, and FAA has not experienced safety problems with towers that are already operated by contractors. According to the Aircraft Owners and Pilots Association, which represents the major users of airports with level 1 towers, its members have not experienced safety problems with contracted out towers.

Because of congressional interest in ensuring aviation safety in a cost-effective manner, you asked us to (1) determine the reasonableness

~. -~ ‘FAA delineates air trsffic control towers into five levels depending on the traff~c’s density and the complexity of responsibilities. Level 1 towers are those with the lowest activity and are generally located in smaller cities that are served by commuter airliies rather than major carriers.

2FAA refers to low-activity towers that it operates as level 1 towers and those operated by a contractor as contract towers. For consistency, we refer to both FAA- and contractor-operated towers as level 1 towers in this report.

Page 1 GAWBCED-94-265 Low-Activity Tower Program

Page 4: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

I- B-267854

Results in Brief

of FAA’S plans to close level 1 towers3 and contract out the operations of others, (2) assess the reasonableness of the potential savings that could result from such actions, (3) identify the factors that could impede FAA’s

plans to close and contract out towers, and (4) identify steps that FAA can

take to enhance its strategy for reassigning controllers from closed or contracted out level 1 towers.

FAA’S plans to close or contract out all of its level 1 towers appear reasonable. Of the 151 level 1 towers, 36 do not meet FAA's benefit-cost criteria for continued operations. FAA is planning to permanently close 23 of these towers within the next 3 years-l 1 that have been temporarily closed since the air traffic controllers’ strike in 1981 and 12 that are operated by FAA. FAA does not plan to close one temporarily closed tower because the agency estimates that the tower will soon meet the benefit-cost criteria. FAA estimates that it can save as much as $5 million annually by closing the 23 towers. FAA plans to close the remaining 12 towers in the future, thereby realizing additional savings of $3 million annually.

Of the remaining 127 towers, 32 are currently contracted out. FAA

estimates that it could save as much as $120 million (in constant 1994 dollars) if it contracts out the operation of the remaining level 1 towers by fiscal year 1997.4 FAA will not realize immediate savings primarily because of the short-term costs to relocate controllers to other facilities.

Several factors may affect FAA’S efforts to close or contract out level 1 towers quickly. First, according to FAA program management officials, the agency is receiving mixed signals from the Congress regarding level 1 towers. On the one hand, various congressional committees have directed FAA to use benefit-cost criteria to establish and discontinue tower operations. On the other hand, FAA program management officials told us that individual Members of Congress have asked FAA to continue operating some towers that, in FAA’S dete rmination, do not meet the agency’s benefit-cost criteria. Second, FAA cannot contract out towers until the Department of Labor completes its wage determinations for each tower

31f FAA closed a tower, federal funding would cease. A tower could remain open if a local airport authority or other entity funded the operation, as is the case with about 40 towers in the United States. Since FAA does not fund their operations, we did not consider these towers.

%avings represent the present discounted value in 1994 dollars. FAA discounts costs over a E-year period at the Of&e of Management and Budget’s specified rate of 7 percent. FAA based its February 1994 estimate on contracting out 95 towers.

Page 2 GAWCED-94-266 Low-Activity Tower Program

Page 5: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

B-257854

---- . location! FAA needs the wage determinations so that contractors can provide accurate bid estimates.

Currently, 142 air traffic control facilities other than level 1 towers are overstaffed, and 171 are understaffed. For the 25 towers to be contracted out in f=cal year 1994, FAA’S agreement with the controllers union allows for the reassignment of controllers to overstaffed facilities. However, FAA

does not have a strategy for reassigning controllers from towers to be closed or contracted out to higher-level facilities after f=cal year 1994. Also, a number of controllers at level 1 towers could not, in the past, perform required duties at other facilities. Therefore, FAA could incur significant costs in relocating controllers a second time if they do not succeed at higher-level facilities.

Background .--~

FAA provides air traffic control services to the nation through a system of about 460 towers categorized at levels 1 through 5. Level 1 towers have the lowest activity and are the least complex. For example, the Charlottesville, Virginia, airport has a level 1 tower that controls about 63,000 operations a year. On the other hand, Chicago O’Hare International Airport has a level 5 tower that controls about 840,000 operations a year. As of June 1994, FAA

had responsibility for 151 level 1 towers. Figure 1 shows the operational status of these towers.

.~. 6The Service Contract Act of 1965 requires the Department of Labor to perform wage determinations for service contracts to ensure that contractors’ employees receive the prevailing wage for similar types of employees in the area, in this case, FAA controllers.

Page 3 GACURCED-94-265 Low-Activity Tower Program

Page 6: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

-. -_.-- B-257864

- Figure 1: Operational Status of Level 1 Towers

FAA Operated (107)

Note: includes one temporarily closed tower that FAA does not plan to permanently close.

Source: FAA.

The House and Senate Appropriations Committees directed that FAA use

$15.8 million to (1) close towers that do not meet its benefit-cost criteria and contract out the operations of 25 level 1 towers by the end of fiscal year 1994 ($7.3 million) and (2) relocate controllers to other facilities ($8.5 million). The Vice President’s National Performance Review also recommended that FAA contract out level 1 tower operations because the Review believed that contractors can provide the same level of service at less cost to the government. If funding is available, FAA plans to contract out the operations of all level 1 towers at a rate of about 25 per year for fiscal years 1994 through 1997. FAA estimates that this could save about $120 million (in constant 1994 dollars) during fiscal years 1994-97. Figure 2 shows FAA's pkms to contract out all level I towers through fiscal year 1997, including 32 that are now operated by contractors.

Page 4 GAO/RCED-94-265 Low-Activity Tower Program

Page 7: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

B-267864

FAA-Operated and Contracted-Out Level 1 Towers, Fiscal Years 1993-97

Number of Level 1 Towers

130

120

110

100

60

80

70

60

50

40

30

20

10

0

1993

Fiscal Year

1994 1995 1996 1997

1 1 FAA-Operated

Contracted Out

Source: FAA.

FAA’s Plans for Closing and Contracting Out Level 1 Towers

FAA's regulations establish benefit-cost criteria to determine when towers should be established or closed. To be established or to continue in operation as an FAA- or contractor-operated tower, the tower must have a benefit-cost ratio greater than l-the point at which benefits equal costs. According to FAA's criteria, towers with a benefit-cost ratio below 1 should be closed. However, FAA's guidance allows for keeping towers open if unique requirements exist. Such factors include unique weather, topography, and operational conditions; potential use of the site to relieve capacity from and help in the training for a hub airport; potential significant changes in traffic activity; positive economic impacts for local commerce; and national security. FAA has determined that these impacts are subjective, controversial, not easily quantifiable, and negligible in comparison to safety and efficiency benefits and excludes them from its benefit-cost criteria. (App. I summarizes the criteria.)

Page 6 GAOIRCED-94-266 Low-Activity Tower Program

Page 8: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

B-267864

-.- - FAA has determined that 36 level 1 towers do not meet its benefit-cost criteria and cannot be justified on the basis of other unique requirements. In a June 1993 study provided to the Subcommittee on Transportation and Related Agencies, House Committee on Appropriations, FAA recommended closing 23 of the 36 towers-l 1 that have been temporarily closed since the air traffic controllers’ strike in 1981 and 12 that are operated by FAA. As

noted earlier, FAA expects one temporarily closed tower to soon meet the benefit-cost criteria. FAA estimates that it can save as much as $5 million annually by closing the 23 towers. FAA expects to dismantle (decommission) the 11 temporarily closed towers by September 30,1994. According to FAA program management officials, the 12 FM-operated towers have never met FAA’S benefit-cost criteria and are planned to be closed. (App. II lists the level 1 towers that do not meet FAA’S criteria,)

In addition to the 23 level 1 towers that FAA recommended closing, 12 other towers do not meet FAA's benefit-cost criteria and could be closed. According to FAA officials, the agency plans to close these towers in the future, but because of the lack of funding and because of congressional interest in their continued operations, FAA did not recommend closing them immediately. FAA’S closing of the 12 towers would save an additional $3 million annually.

FAA implemented a policy on July 18,1994, that would allow towers that do not meet the benefit-cost criteria to operate for 2 full fiscal years with the expectation that if a tower again did not meet the criteria, FAA’S funding

would cease. According to FAA officials, the agency has not sent letters to airport officials informing them of its new policy but plans to do so in the near future.

FAA Has Not Entered Into New Contracts

~ FAA has yet to enter into contracts for the 25 level 1 towers that were directed by the House and Senate Appropriations Committees to be contracted out by the end of fiscal year 1994. However, FAA expects to award these contracts by the end of the fiscal year. (App. III lists the 25 towers selected.)‘j As a result, FAA will use only $2.1 million of the $7.3 million appropriated for contract start-up costs in fiscal year 1994. According to FAA officials, the agency has reprogrammed the balance ($5.2 million) for such other purposes as locality pay.

%I the basis of a survey sent to all level 1 tower employees, FAA, in cooperation with the National Air I I

Traffic Controllers Association (an employee union), selected the first 25 towers to be contracted out.

Page 6 GAO/RCED-94265 Low-Activity Tower Program / i I

Page 9: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

~. B-267864

FAA announced its contract plans on March 8,1994. In accordance with federal procurement requirements, FAA had to allow 30 days for interested parties to respond to the announcement. According to FAA officials, about 90 companies or individuals expressed an interest in FAA’s plans to contract out level 1 towers. FAA provided them with its “request for technical proposal” on April l&1994. FAA formed a committee to review the responses and select those that will be given an invitation to bid on the contracts. FAA expects to award the contracts by September 1994,

FAA Will Not Realize FAA estimates that it could save as much as $120 million in operating

Immediate Savings efficiencies (in constant 1994 dollars) without affecting safety if it contracts out the operation of all level 1 towers by fiscal year 1997.

From Changing Tower Greater savings could occur if additional towers were closed rather than

Operations contracted out. But FAA will not realize immediate savings because it has to pay the costs of relocating controllers to other FAA facilities.

FAA stated that the average annual operating cost for a contractor-operated level 1 tower is about $250,000, while the operating cost for an FAA-operated tower is $450,000. The differences in operating costs occur because contractors are not bound by Civil Service requirements and FAA and union work rules that result in higher staffing levels at FAA-operated towers. Savings result from the following:

. Contractors can perform level 1 tower functions with fewer staff than FAA. For example, the contractor for the level 1 tower in Bellingham, Washington, uses seven controllers and a manager, who typically controls trafEc. If operated by FAA, the tower would be staffed by 13 controllers and 1 manager, who would not normally control traffic. (App. IV shows the staffing at contractor-operated level 1 towers compared with FAA’s

estimated staffing, which is based on FAA’s standards.) l Contractors have more flexibility: They can use split shifts and part-time

and seasonal staffing, thereby reducing the number of staff needed.

According to an FAA official, Civil Service requirements and various agreements with the National Air Traftic Controllers Association prohibit FAA from requiring employees to work split shifts, although employees could volunteer for such a work assignment. In addition, in determining its staffing standards, FAA must consider anmral and sick leave and have sufficient staff to cover such contingencies. Contractors, however, usually do not offer benefits that are comparable to those provided to federal employees. Furthermore, contractors realize further savings because they

Page 7 GAO/ECED-94-265 Low-Activity Tower Program

Page 10: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

--._ -_ - B-267864

generally hire experienced controllers and do not incur initial training or permanent change-of-station costs7

However, FAA will not realize any savings from contracting out towers for 2 to 3 years primarily because the agency will incur costs to relocate level 1 controllers to other facilities. For example, FAA will incur about $8.5 million in the first year to move about 250 controllers, an average cost of about $34,000 per employee. Over the $-year period that FAA plans to contract out level I towers, FAA estimates that the cost to relocate about 1,000 level 1 controllers will be about $34 million. After that, FAA will not have to relocate as many employees and will not have to hire and tram controllers to replace the approximately 250 attrited controllers each year.

FAA Faces Challenges Several factors may affect FAA’S efforts to close or contract out level 1

in Changing Tower towers. First, according to FAA program officials, the agency is receiving mixed signals from the Congress. On the one hand, various congressional

Operations committees have directed FAA to use benefit-cost criteria to establish and discontinue tower operations. On the other hand, individual Members of Congress have asked FAA to establish or continue operating towers that do not meet the criteria for continued operations. To be effective, FAA will

have to follow through with its policy to discontinue funding towers that do not meet its criteria at the end of the Z-year grace period.

Second, FAA cannot award contracts for the operation of level 1 towers until the Department of Labor completes its wage determinations for each potential contractor-operated tower location. In March 1994, FAA requested that the Department of Labor provide wage determinations for all level 1 tower locations. On July 29,1994, the Department provided wage determinations for the first 25 towers to be contracted out.

FAA Could Improve Its Level 1 Tower Program

FAA and the National Air Traffic Controllers Association entered into an agreement on how to assign controllers from the 25 towers to be contracted out in fiscal year 1994. However, this agreement does not provide a strategy for reassigning controllers from towers to be closed or contracted out after fiscal year 1994. Without such a strategy, overstaffing at some facilities could be exacerbated without resolving understafGng at others. Also, since a number of controllers at level 1 towers have not been able to perform required duties at other facilities, FAA could incur

,_- --.-._.._. .I- -.-_ .-.-. _ ._~ ~_~ ~~~~ I ..-.-._ - ~~ ~~ _, 7According to FAA officials, experienced controllers that contractors employ include former military and retired FAA controllers. In addition, contractors can employ controllers that were fired as a result of the 1981 strike, about 4,800 of which are interested in performing air tmfTiic control duties again.

Page 8 GAOIRCED-94-266 Low-Activity Tower Program

Page 11: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

..-- B-267654

significant costs-averaging $34,000 for each employee-to relocate controllers a second time if they do not succeed at higher-level facilities.

FAA’s and Labor Union’s Agreement Provides Only Limited Guidance for Relocating Level 1

As of May 1994, the workforce of about 17,590 controllers was over the level prescribed by FAA’S stafGng standards by about 250 staKs According to FAA’s staffing standards, 142 facilities (above level 1) were overstaffed

Controllers

by about 1,295 controllers, and 171 facilities (above level 1) were understaffed by about 810 controllers9

According to the agreement between FAA and the labor union for the 25 towers to be contracted out in fiscal year 1994, if a facility is fully staffed or overstaffed, FAA will allow controllers to transfer there as long as they receive meaningful work and training opportunities. The agreement also states that if a facility cannot accept all applicants, FAA will give first priority to those with hardships. The agreement also states that consideration will be given to controllers whose move will result in no cost to the government. However, the agreement does not specify how much overstaffing will be allowed.

FAA’S initial decision on relocating staff at level 1 towers was based on an employee placement application sent in May 1994 to about 170 controllers at the 25 towers selected to be contracted out in 1994. The application asked controllers to select four facilities, at least one of which must be within the region where they are assigned. According to FAA officials, the agency and union made reassignment decisions on the basis of the employees’ responses. FAA expects to relocate the 170 controllers to about 95 higher-level facilities.

According to our analysis of the employees’ application results, FAA will

need to establish more definitive criteria to deal with existing and potential overstaffing at certain facilities. Of the 95 facilities where FAA

plans to relocate controllers, 63 are overstaffed or will be overstaffed when the controllers report there. For example, the level 3 tower in Sarasota, Florida, has one controller more than the number suggested by FAA’S staffing standard. Since FAA assigned three controllers to the Sarasota tower, that tower will have four controllers more than the number suggested by FAA’S staffing standard. Furthermore, a survey sent by FAA in

%We previously testified that FAA had identified some problems with its staffii standards. (TAA Work Forces: Important Decisions Affecting Staff Use and Management, GAOfl-RCED-93-59, June 30,1993).

‘FAA develops staffing standards for trainees in the aggregate rather than by facility. As a result, these numbers do not include trainees.

Page 9 GAOlltCED-94266 Low-Activity Tower Program

Page 12: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

B-267864

November 1993 to all level 1 controllers showed that an additional seven controllers from the remainin g towers to be contracted out also selected Sarasota as their first choice for relocation. If FAA also allows these controllers to transfer to Sarasota, the tower would be seriously overstaffed, and such action would not help to resolve understaffrng at other facilities.

To ensure that relocated controllers are most effectively utilized, the House Committee on Appropriations recommended, for fiscal year 1995, that FAA transfer level 1 controllers only to facilities that are understaffed.10 FAA’s doing so, however, will depend on the reliability of its staffing

standards. Although FAA officials believe that the standards accurately reflect current needs, the agency is reevaluating the assumptions and methodologies used to develop the standards. Also, according to FAA

program management officials, the agency will be negotiating new agreements with the union for the towers to be contracted out after fiscal year 1994.

FAA Has Several Options for “Training Failures”

Another factor that FAA needs to consider is that many level 1 controllers have previously worked at higher-level facilities but were unable to perform the requisite duties. Although FAA could not provide us with data showing the number of level 1 controllers that fall into this category, union officials estimated that about 60 percent of the almost 1,000 level 1 controllers did not effectively perform at higher-level facilities and are considered by FAA to be “training failures.” Labor union officials are concerned that reassigned controllers will not be able to perform the duties required at the new facilities. FAA officials said that they, in agreement with the union, plan to allow controllers a chance to perform at higher-level facilities. If they cannot, FAA, in accordance with its agreement with the union, will relocate them again if funding is available or allow them to relocate at their own expense,

FAA officials maintain that the training failure issue is mitigated because FAA’s approach to training is much different than it was a few years ago and that the new “train to succeed” philosophy will enhance controllers’ ability to perform at higher-level facilities. Under this philosophy, FAA focuses on identifying and developing specific skills that need to be enhanced. If the efforts to enhance specific skills do not succeed, FAA will determine if further training is needed or whether the employee should be

I%. Rep. No. 103.543,p.45.

-..

Page 10 GACMWED-94-266 Low-Activity Tower Pmgrnm

Page 13: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

B-267854

-- assigned to some other job function that does not involve separating aircraft.

Of the 13 controllers at two level 1 towers that we visited, 10 had transferred there because they could not perform the required duties at higher-level towers. The controllers expressed mixed views about relocating. Some feared failing again; others viewed this as an opportunity for advancement. Union officials were concerned that FAA will not have funds to relocate controllers a second time, which will cause the controllers to pay for their own moves.

Conclusions I -~

--- We recognize that safety is paramount in deciding whether to close or contract out towers. According to FAA officials, safety will not be jeopardized by closing or contracting out tower operations. Although FAA can justify opening or closing towers on the basis of unique requirements that are not included in the benefit-cost criteria, the agency has been slow in closing towers when they do not meet unique circumstances or the benefit-cost criteria. As a result, FAA spends millions of dollars to operate towers whose continued operations have not been justified. Nevertheless, FAA's new policy to provide a X-year grace period for towers to meet the benefit-cost criteria and to discontinue funding those towers that do not meet the criteria seems to be a reasonable approach.

Contracting out low-activity towers provides budgetary savings and provides FAA with a means to infuse controllers into other geographical areas where the need for them exists. But the infusion could cause overstaEmg at some towers if it is not part of an integrated strategy that is compatible with FAA’S priorities for its workforce. Furthermore, labor union officials are concerned that reassigned controllers will not be able to perform the duties required at the new facilities. Although FAA believes that controllers’ success rate will be better under its new “tram to succeed” philosophy, we believe that controllers’ prior performance capability at higher-level facilities is a legitimate concern that could have a negative impact on FAA’s strategy for reassigning controllers.

Recommendations We recommend that the Secretary of Transportation direct the Administrator, FAA, to

Page 11 GAO/WED-94-266 Low-Activity Tower Program

Page 14: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

B-257864

l establish procedures to ensure that FAA’S new policy to close towers that do not meet benefit-cost criteria for a Z-year period is effectively implemented and

l develop a strategy for reassigning controllers horn contractor-operated towers to understaffed facilities and for minimizing overstaffing at other towers to be contracted out after fiscal year 1994.

Agency Comments and Our Evaluation

We discussed the report’s findings and recommendations with the Manager and Acting Assistant Division Manager, System Plans and Programs Division, Air Traffic Plans and Requirements Service; Acting Manager, Resource Management Program, Office of Air Traffic Program Management; and other FAA officials. FAA officials generally agreed with the tidings and recommendations contained in the report.

The officials said that FAA had identified towers that did not meet benefit-cost criteria in a staff study provided last year to the Subcommittee on Transportation and Related Agencies, House Committee on Appropriations. However, FAA did not recommend closing all of these towers because language in various committee reports directed that they be established or remain open. FAA implemented a policy on July 18,1994, to provide a 2-year grace period before closing any towers. The officia.ls said that all towers not meeting benefit-cost criteria will be included under FAA’s new policy.

FAA officials also said that they were reevaluating the qutications of those interested in submitting bids for performing tower operations under contract. However, FAA has not received wage determinations from the Department of Labor for all contract locations. As a result, contractors cannot develop precise bid estimates, and FAA cannot award contracts, The officials said that the Department of Labor provided wage determinations on July 29,1994, for the 25 locations to be contracted out in fiscal year 1994 but as of August 1,1994, had not yet provided estimates for the remainder. FAA officials said that getting estimates for the remaining locations will help them ensure that contracts are awarded by the end of fiscal year 1994.

FAA officials also said that the method used to reassign FAA controllers from the 25 level 1 towers to be contracted out in fiscal year 1994 to higher-level facilities was based on an agreement with the National Air Traffic Controllers Association. Regarding the issue of training failures, FAA officials said that the agreement stipulates that if funding is available,

Page12 GAOIRCED-94-265Imw-ActivityTowerProgram

Page 15: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

- B-267864

FAA will relocate the controllers. However, if funding is not available, the controllers will be allowed to relocate at their own expense. The officials said that FAA does not plan to terminate controllers who cannot perform duties at higher-level facilities and that FAA will be negotiating a new agreement with the union for towers to be contracted out after fiscal year 1994. As requested, we did not obtain written agency comments on a draft of this report.

We conducted our work between August 1993 and July 1994 in accordance with generally accepted government auditing standards, Our objectives, scope, and methodology are discussed in appendix V.

Unless you publicly announce its contents earlier, we plan no further distribution of this report until 30 days after the date of this letter. At that time, we will send copies to the Secretary of Transportation; the Administrator, FAA; and the Director, Office of Management and Budget. We will make copies available to others upon request.

Please contact me at (202) 512-2834 if you or your staff have any questions. Major contributors to this report are listed in appendix VI.

Sincerely yours,

Kenneth M. Mead Director, Transportation Issues

Page13 GAOLRCED-94-266Low-ActivityTowerProgram

Page 16: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Contents

Letter

Appendix I FAA’s Process for Assessment of Benefits

Assessment of Costs

16 16 17

Determining When How FAA Applies the Benefit-Cost Criteria 17

Towers Should Be Established or Closed

Appendix II Level 1 Towers That Do Not Meet FAA’s Benefit-Cost Criteria

Appendix III First 25 Level 1 Towers to Be Contracted Out

Appendix IV Actual Staffing Compared With FAA-Estimated Staffing for AI1 Contractor-Operated Towers

22

Appendix V Objectives, Scope,

23

and Methodology

Page 14 GAOIRCED-94-266 Low-Activity Tower Program

Page 17: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Contents

Appendix VI Major Contributors to This Report

Tables Table II. 1: Temporarily Closed Towers That Do Not Meet FAA’s 19 Criteria and Were Recommended for Closure by FAA

Table II.2: Operating Towers That Do Not Meet FAA’s Criteria 20 -_

Figures Figure 1: Operational Status of Level 1 Towers 4 Figure 2: Planned Distribution of FAA-Operated and 5

Contracted-out Level 1 Towers, Fiscal Years 1993-97

Abbreviations

FAA Federal Aviation Administration GAO General Accounting Offke

Page 16 GAOIRCED-94-265 Low-Activity Tower Program

I

Page 18: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Appendix I I-

FAA’s Process for Determining When Towers Should Be Established or Closed

The Federal Aviation Administration’s (FAA) process for determining when to establish or close air traffic control towers is based on an economic analysis of the benefits and costs of operating a tower. A brief description of the benefit and cost factors #at FAA uses in the analysis follows.

Assessment of Benefits

FAA assesses both the safety and efficiency benefits of towers. However, the primary emphasis is on safety; that is, preventing or reducing (1) collisions between aircraft (such as midair or air-to-ground collisions) and (2) other such accidents as wheels-up landings or collisions with field obstructions. Under this scenario, lives are saved and fewer aircraft become damaged, To determine the effectiveness of towers in reducing the risk of collisions between aircraft, FAA analyzes the National Transportation Safety Board’s data and estimates the expected number and type of aircraft that would be involved in an accident. FAA then determines the number and type of aircraft that would use the tower; estimates benefits by dete rmining the avoided fatalities, serious and minor injuries, and aircraft damage; and assigns explicit values to these avoided losses.

For example, the value for a fatality and a serious injury is $2.6 million and $673,000, respectively.‘l The values assigned to aircraft damage vary by severity depending on the aircraft’s type and whether the aircraft was destroyed or sustained substantial or minor damage. FAA uses a similar analysis in determining the benefits derived from preventing other types of accidents. However, because of the differences between the physical and operational environments of airports, FAA limits the analysis to those types of accidents that a tower can prevent. This includes wheels-up landings, aircraft collisions with objects other than another aircraft, landing on the wrong runways, and overshooting or undershooting a runway during takeoff or landing.

Efficiency benefits derive primarily from reduced flying time. By reducing flying time, airlines save on the costs of operating aircraft and passengers save time when flight paths are shortened. Other nonquantifiable benefits may be associated with tower services. For example, tower controllers may save lost pilots or report bad weather conditions that will cause a pilot to cancel a flight that could have resulted in an accident.

“Placing a monetary value on ir@y and loss of life represents a standard practice in analyzing potential safety benefits. In adopting these values, a tradeoff must be made between the cost of enhancing safety and the benefit that will be derived from that enhancement.

Page 16 GAO/ICED-94-266 Low-Activity Tower Program

Page 19: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

- Appendix I FAA’s Process for Determining When Towers Should Be Established OP Cloeed

Assessment of Costs ~^ ~.-~

An airport’stower costs fall into two categories-investment and annti costs. Investment costs are one-time expenditures for facilities, equipment, and operational start-up. Annual costs are those associated with staff, maintaining facilities and equipment, and procuring supplies and leased services.

On average, the primary investment cost in establishing a tower are the facilities and equipment costs and the one-time expense of relocating experienced controllers from various other facilities and training their replacements. The costs for one replacement controller include the cost of providing the basic course for controUers at the FAA Academy, associated travel costs, and the controller’s salary during the training period.

In estimating annual costs for a level 1 tower, FAA uses the average number and salary grade level of staff required to operate the tower for 12 hours, FAA determined that the average level 1 tower consists of one Air Traffic Manager (GS-11, step 5) and five controllers (GS-10, step 5).12 FAA

calculates the costs of staff using annual salary data plus 29.65 percent to account for retirement, health, and other benefits as well as relocation costs. FAA’s experience suggests that one controller relocates from a level 1 tower about once every 2 years. Therefore, relocation costs comprise one-half of the annual average. FAA uses annual fixed costs for any leased communications equipment. FAA determines the costs for supplies, rent, utilities, contracted services, and related administration by using an approximate percentage-for example, 3.7 percent-of controllers’ salaries.

In deciding whether to close and dismantle (decommission) a tower, FAA

considers the same annual operating costs as those for establishing a tower and the one-time cost of shutting it down. Shutdown costs include expenditures for relocating controllers and dismantling and moving equipment.

How FAA Applies the The benefit-cost criteria compare the present value of a tower’s benefits

Benefit-Cost Criteria with costs over a &year period. In making the comparison, FAA uses a 7-percent discount rate as directed by the Office of Management and Budget. If the tower is a candidate for being contracted out, FAA will

substitute the contractor’s proposed costs in lieu of FAA’S costs in the benefit-cost analysis computations. Regardless of whether the tower is to be operated by FAA or a contractor, FAA seeks to establish towers that have

~.-. ~~- -~~.~ “GS = general schedule pay rate for the federal government.

Page 17 GAOLRCED-94-266 Law-Activity Tower Program

Page 20: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Appendix I FM’s Process for Determining When Towers Should Be Eetibliahed or Closed

a benefit-cost ratio greater than or equal to 1 and close towers when the benefit-cost ratio is less than 1.

However, such unique factors as weather, topography, and operational conditions; potential use of the site to provide capacity and training relief for a hub airport; potential significant changes in traffic activity; and national security may override the results of FAA’s benefit-cost analysis. For example, FAA’S tower in American Samoa-with a .99 benefit-cost ratio-does not meet FAA’s criteria, but the tower provides service to both international and national carriers (unique operational requirement). FAA acknowledges that other positive and negative economic impacts accrue to a community through the presence of a tower, such as benefits to local commerce and the potential increase in noise and aircraft engine emissions. However, FAA does not consider these factors in its benefit-cost analysis because it has determined that these impacts are subjective, controversial, not easily quantifiable, and negligible in comparison to safety and efficiency benefits.

Page 18 GAO/WED-94-266 Low-Activity Tower Program

Page 21: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Appendix 11

Level 1 Towers That Do Not Meet FAA’s Benefit-Cost Criteria

~.______ .- Table 11.1: Temporarily Closed Towers That Do Not Meet FAA’s Criteria and City and state Were Recommended for Closure by Ponce, P.R. FAA

Plainview, Tex. .-

Benefit-cost ratio

.08

.19

Pine Bluff, Ark. .21

Merced, Calif. .23 -______ -..~__ Mayaguez, P.R. .30

Akron, Ohio .31

Spartanburg, SC. .34 -I. ~ -, -I Hickory, NC. .34

Benton Harbor, Mich. .36

New Bern, NC .41 .-- Hot Springs, Ark. .48

Note: Benefit-cost ratios are as of June 1993. In addition, the temporarily closed tower in Knoxville, Tennessee, did not meet FAA’s benefit-cost criteria, but FAA did not recommend that it be permanently closed because the agency estimates that the tower will soon meet the criteria.

Page 19 GAO/FtCED-94-265 Low-Activity Tower Program

Page 22: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Appendix II Level 1 Towers That Do Not Meet FAA's Benefit-Cost Criteria

Table 11.2: Operating Towers That Do Not Meet FAA’s Criteria City and state Benefit-cost ratio

Bloomington, Ind.

Jackson, Tenn8 “-

.34 -..--

.36

Cape Girardeau, Mo.~ .39

Marion, Ill.a

Lewisburg, W.Va.a ~-

.39 .--~

.46

Hobbs, N.M.” .47

Wheeling, W.Va. ._ ,~- Williamsport, Pa. --

.52

52

Pendleton, Oreoa .53

Valdosta, Ga.a

Muncie, tnd.a‘

.57 _. -.-

.62

Greenville, Miss. .70

Walla Walla, Wash.

Lake Tahoe, Calif.”

.70

.7i

Columbia, MO. .73

Grand Island, Nebr. .74 . . . ~~ Joplin, MO. .78

Olvmpla, Wash. .86

Shreveport, La. .86

Ardmore, Okla.a .87

Gary, Ind.a

Fayetteville, Ark.

St. Joseph, MO.

Twin Falls City, Idahoa

Note: As of June 23, 1994.

--

63

39

.92

.9a

aN~t recommended for Immediate closure by FAA

Page 20 GAOIRCED-94-265 Low-Activity Tower Program

Page 23: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Appendix XII

First 25 Level out

1 Towers to Be Contracted

City and state Charlottesville, Va. -.. -I-.. ~~~. Detroit City, Mich.

Westiield, Mass.

Hartford, Conn. -~-~ --. --. Lewiston, Idaho

San Juan (Isla Grande), P.R.

San Antonio (Stinson), Tex. _~~ ~-~ .~~.~ ._- ~~~ Alexandria, La.

Kaunakakai, Hawaii

Salina, Kans. -- -~~.~~-- -I__-~- Palmdale, Calif.

Salinas, Calif.

Meridian, Miss. -~ ~~ -~~~~~ ~~-~..~~- Texarkana, Ark.

Cincinnati (Lunken), Ohio

Alton, III. ~..-.~ ~.-- ._~ -~____ New Haven, Corm,

Tuscalusa, Ala.

Groton, Conn. _.-_._~ .~~- ~~ ~-__-~~ Salem, Oreg.

Greenville, S.C.

Panama City, Fla.

Brownsville, Tex.

Pocatello, Idaho

Hagerstown, Md.

Note: Towers are listed in the order in which FAA selected them to be contracted out in fiscal year 1994.

Page 2 1 GAO/WED-94-265 Low-Activity Tower Program

Page 24: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Appendix IV

Actual Staffing Compared With FAA-Estimated Staffing for All Contractor-Operated Towers

Location of facility Number of contractor Number of

Staff FAA staff”

Ardmore, Okla. 3

Athens, Ga. 4

6 b

Bellingham, Wash. 8 14

Cape Girardau, MO. 4 5

Cleveland (Cuyahoga County), Ohio 6 8 Eagle, Col. -

-- 4 b

Enid (Woodring), Okla. 4 7

Farminaton. N.M. 4 9

Flagstaff, Ariz.

Gary, lnd.

4

5

6 b

Hailev. Idaho 4 7

Hobbs (Lea County), N.M. 3 7

Lakeland, Fla. 7 9

Laredo. Tex. 5 7

Lewisburg/Greenbrier, W.Va. 3 6

Manon (Williamson County), Ill. 5 6

Martha’s Vinevard, Mass. 5 b

Mobile, Ala. 7

Mosinee, Wise. 6

b

6

Nashua, N.H. 5 8

New Iberia, La 4 8

Newburgh, N.Y. 7 b

Norman, Okia. 4 b

North Myrtle Beach, SC. 7 8

Owensboro (Davies County), Ky. 5 7

PacoimalWhiteman. Catif. 5 8

Paducah (Barkley), KY. 5 8 .~ -. _ -__I Pendleton, Oreg. 4 7

Smyrna, Tenn. 4 8

Topeka (Phillip Ballard), Kan. 3 7

Valdosta, Ga. ~I-

6 6

Waukeaan. IIt, 6 9

aFAA staff are those that would be assigned to the contractor locations on the basis of FAA’s staffing standards.

bFAA could not provide staffing information for these towers either because activity data were not available to estimate staffing needs or the tower was established subsequent to our request for data.

Page 22 GAO/WED-94-266 Low-Activity Tower Program

Page 25: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Appendix V

Obj&tives, Scope, and Methodology

The Chairman, Subcommittee on Transportation and Related Agencies, House Committee on Appropriations, asked us to (1) determine the reasonableness of FAA's plans to close level 1 towers and contract out the operations of others, (2) assess the reasonableness of the potential savings that could result from such actions, (3) identify the factors that could impede FAA’S plans to decommission and contract out towers, and (4) identify steps that FAA can take to enhance its strategy for reassigning controllers from contracted out level 1 towers.

We reviewed FAA'S criteria for establishing, closing, and contracting out level 1 air traffic control towers and discussed them with FAA officials. However, we did not evaluate or verify the data that FAA uses in applying the benefit-cost criteria. We collected data from FAA showing the number of level 1 towers that do not meet these criteria and discussed reasons why FAA established or has not closed them. We also discussed with FAA

officials their plans to relocate staff from towers that will be contracted out from fiscal year 1994 through fiscal year 1997 and discussed with FAA

and National Air Traffic Controller’s Association officials the process they used to select the 25 towers to be contracted out in fiscal year 1994. We obtained their views on the contracting out program and potential impact on the controller workforce.

We collected, reviewed, and analyzed FAA'S survey instrument that included information on where controllers wanted to transfer when their tower was converted to contractor operations. We aggregated data from the survey showing the air traffic facilities where employees wanted to relocate and compared these data with locations that are close to becoming or are already overstaffed in accordance with FAA'S staffing standards. We also reviewed, analyzed, and discussed with officials FAA'S

guidance on relocating controllers from their facility. We visited FAA-staffed level 1 towers in Charlottesville, Virginia, and Hagerstown, Maryland-two towers selected to be contracted out in fiscal year 1994. We discussed the impact of contracting out these facilities with the tower manager and available controllers. We also discussed relocation preferences and prior work experiences at other FAA facilities and why they previously left those facilities.

We also discussed with FAA program management and contracting officials the status of the contract for the level 1 towers and determined how the contract was developed. We discussed FAA'S procedures for announcing the contract and developing the request for a technical proposal and determined reasons for any delay. We visited one tower in Smyrna,

Page 23 GAOiRCED-94-265 Low-ActivityTowerProgram

Page 26: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Appendix V Objectives, Scope, and Methodology

- ._ Tennessee, that is currently operated by a contractor and discussed operational procedures and staffing with the tower manager and controllers. We also visited two contractors--Barton ATC, Inc., in Murfreesboro, Tennessee, and NYMA in Greenbelt, Maryland-and spoke with Aircraft Owners and Pilots Association officials to discuss their experience with level 1 tower operations. We also discussed with FAA officials their progress in obtaining wage determinations from the Department of Labor and how the Department’s delay may affect awarding the contract before the end of fiscal year 1994 and discussed with a Department of Labor official the process used in making such determinations.

Page 24 GAO/EKED-94-265 Low-Activity Tower Program

Page 27: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Appendix VI

Major Contributors to This Report i

Resources, Allen Li, Associate Director E

Community, and Mary Ann Kruslicky, Assistant Director Roy K. Judy, Assignment Manager I

Economic Steven J. Schamberger, Evaluator-in-Charge

Development Division, Washington, I) D.C.

i

(341394) Page 25 GAO/RCED-94-265 Low-Activity Tower Program

Page 28: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32
Page 29: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

Ordering Information

The first copy of each GAO report and testimony is free. Additional copies are $2 each. Orders should be sent to the following address, accompanied by a check or money order made out to the Superintendent of Documents, when necessary. Orders for 100 or more copies to be mailed to a single address are discounted 25 percent.

Orders by mail:

-I U.S. General Accounting Office P.O. Box 6015 Gaithersburg, MD 20884-6015

or visit:

Room 1100 700 4th St. NW (corner of 4th and G Sts. NW) U.S. General Accounting OiYice Washington, DC

Orders may also be placed by calling (202) 512-6000 or by using fax number (301) 258-4066.

Each day, GAO issues a list of newly available reports and testimony. To receive facsimile copies of the daily list or any list from the past 30 days, please call (301) 258-4097 using a touchtone phone. A recorded menu will provide information on how to obtain these lists.

n_

PRINTED ON /$A RECYCLED PAPER

Page 30: RCED-94-265 Air Traffic Control: Status of FAA's Plans to ... · towers in the future, thereby realizing additional savings of $3 million annually. Of the remaining 127 towers, 32

United States Generai Accounting 0ffice Washington, D.C. 20548-0001

Official Businees Penalty for Private Use $300

Address Correction Requesfed

Bulk Mail PostagetAz Paid

Permit No. GlOO