ERL Status & Schedule. R&D ERL ERL Status & Schedule. Gary McIntyre. February 17-18, 2010. ERL Status & Schedule. Although important to C-AD, ERL must compete for resources with machine operations – Sharing resources limits the work that can be performed… During shutdown periods - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

R&D ERLERL Status & Schedule

Gary McIntyre

February 17-18, 2010

ERL Status & Schedule

Page 2: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Status & Schedule

• Although important to C-AD, ERL must compete for resources with machine operations –

– Sharing resources limits the work that can be performed… During shutdown periods Operations maintenance days Anytime ERL work is in conflict with operations efforts

– Best efforts are being made by all ERL-involved groups but schedule slip can and does occur.

2

Page 3: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Status & Schedule

3

Energy Recovery Linac Milestone Schedule

5-Cell Crymodule to Building 912 10/17/08Start of Cold Emissions Testing 03/24/09Gun Cavity begins processing 01/25/10HTSS testing complete 03/09/10Gun cavity string delivered to BNL09/01/10Gun Cryomodule moved to BLG 912 12/17/10Sub systems connections to e-Gun Cryomodule complete 02/22/11Testing start of Gun to 5-cell Cavity Cold with metal cathode 03/15/11VTF Refrigerator operational 03/23/11Removal of G-5 components and installation of Injection components 06/01/11G-5 with Injection (Zig-Zag) Testing Starts 07/18/11ERL component installation complete & checkout complete 10/24/11ERL -All Systems- Testing 10/24/11

Page 4: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Status & Schedule

• The critical path remains the electron gun cavity cryomodule– Steps to complete the cryomodule include:

Cavity processing Hermetic Cavity String assembly String installation into e-Gun cryomodule

– G-5 (e-Gun to 5 cell Cavity) next major milestone– Followed by the full ERL complete

4

e-Gun cavity with large grain R&D cavity

Page 5: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Status & Schedule

• Cavity Processing – on going at JLab– Buffered chemical polishing - on-going– Vacuum firing to 600C - complete– High pressure rinsing - on-going– Vertical cold testing at 2K - expected start 02/23/10

5

e-Gun cavity in vacuum furnace (Jefferson Laboratory)

Model of e-Gun cavity in Helium Vessel

Page 6: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Status & Schedule

6

e-Gun Cavity Hermetic String Assembly

e-Gun cavity in Helium Vessel

Cathode side thermal transition

Fundamental Power Coupler side thermal transition

Assembly/transport cart

Tooling design complete – parts of tooling package in fabrication, others in approval loop.All string components in-house or ordered , no negative schedule impact.

Page 7: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Status & Schedule

• String installation into e-Gun cryomodule– Cathode transporter in house – Installation tooling design start

scheduled for 04/2010 – All cryomodule components ordered

with no negative schedule impact

7

Ballast tank

Cathode transporter

Cryomodule vacuum vessel

Cathode insertion point & choke joint

High temperature SC Solenoid

Page 8: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Schedule

8

• Major Milestones G-5 Testing

• Requires e-Gun installed in Cryomodule All major cryomodule components ordered e-Gun cryogenics lines routing design in process

• Requires G-5 magnets, instrumentation and vacuum chambers

• All magnets and stands in-house• Installation as time permits

• Remainder of G-5 vacuum chambers due 04/28/10• Beam instrumentation for G-5 & ERL due 08/26/10

• Removal of G-5 “straight” line & install “zig-zag” line• Additional testing with this configuration

Page 9: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Status & Schedule

9

G-5 Layout

E-Gun & cathode transporter

5-cell cavity with ballast tank

Page 10: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Status & Schedule

• Complete ERL Installation– Requires removal of G-5 Test components– All Loop magnets, stands, and power supplies in-house– All Loop vacuum chambers in-house– Moveable arc stand in-house.– Magnet stand pre-survey underway.– ERL Dump due 03/26/10– Loop Beam Instrumentation due 08/26/10– Staging manpower remains biggest challenge

10

Page 11: R&D ERL ERL Status & Schedule

February 17-18, 2010

R&D ERL

Gary McIntyre

ERL Status & Schedule

11

ERL Layout in Building 912

e-Gun Cryomodule

5-cell Cryomodule

ERL Loop

ERL Dump

1MW Klystron

1MW IGBT Power Supply

Laser Room