SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED KAREN HEDLUND, P.E. POWER ENGINEER TACOMA POWER – GENERATION APRIL 6, 2017

Upload: others

Post on 05-Apr-2020

22 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

SWITCHGEAR REPLACEMENT:OVERVIEW & LESSONS LEARNED

KAREN HEDLUND, P.E.

POWER ENGINEER

TACOMA POWER – GENERATION

APRIL 6, 2017

Page 2: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

• Project scope

• Overview of project activities

• Highlights and lessons learned

PRESENTATION OVERVIEW

Page 3: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

• Replace station service switchgear

• Replace station service control switchboards

• Protective relay switchboard

PROJECT SCOPE

Page 4: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

SWITCHGEAR REPLACEMENT: OVERVIEW

Page 5: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

START DESIGN (JAN 2012)

• Key Design Areas

• Cable inspection

• Location and core drill

• Breaker control scheme

• Protective relay scheme

• Anchoring

SWITCHGEAR REPLACEMENT: OVERVIEW

Start

Design

(Jan

2012)

Page 6: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

BID & AWARD

• Two attempts to secure vendor

• Awarded to a manufacturer using GE breakers

SWITCHGEAR REPLACEMENT: OVERVIEW

Bid &

Award

Start

Design

(Jan

2012)

Page 7: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

SWITCHGEAR INSPECTION

• Site inspection revealed insulator cracks, bus connection hardware issues, and workmanship issues

• Manufacturer replaced insulators on-site

• Re-inspection revealed new cracked insulators

SWITCHGEAR REPLACEMENT: OVERVIEW

Switchgear

InspectionBid &

Award

Start

Design

(Jan

2012)

Page 8: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

CONTRACT TERMINATION

• Initiated insulator testing on-site

• Documented and sent report to manufacturer

• Negotiated with manufacturer to terminate contract

• End result was a full refund

SWITCHGEAR REPLACEMENT: OVERVIEW

Switchgear

Inspection

Contract

Termination

Bid &

Award

Start

Design

(Jan

2012)

Page 9: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

RE-DO BID & AWARD

• Rewrote specification

• Vetted design with potential manufacturer

SWITCHGEAR REPLACEMENT: OVERVIEW

Switchgear

Inspection

Contract

Termination

Re-Do

Bid &

Award

Bid &

Award

Start

Design

(Jan

2012)

Page 10: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

COLLABORATION

• Manufacturer visits Tacoma Power

• Tacoma Power visits factory

SWITCHGEAR REPLACEMENT: OVERVIEW

Switchgear

Inspection

Collaboration

Contract

Termination

Re-Do

Bid &

Award

Bid &

Award

Start

Design

(Jan

2012)

Page 11: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

CUTOVER PLAN & RISK ASSESSMENT

• Multiple meetings with stakeholders

• Developed detailed cutover strategy

• Evaluated and addressed risks

• Created cable/ splice location plan

• Communication

SWITCHGEAR REPLACEMENT: OVERVIEW

Switchgear

Inspection

Collaboration

Cutover

Plan & Risk

Assessment

Contract

Termination

Re-Do

Bid &

Award

Bid &

Award

Start

Design

(Jan

2012)

Page 12: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

SWITCHGEAR INSTALLATION & INTEGRATION

• Cowlitz River Project (TP) labor performed all construction activities

• Manufacturer’s technician performed Site Acceptance Testing

• Tacoma Power led commissioning of breaker control logic

• Resolved issues

• Protective relay schemes commissioned

SWITCHGEAR REPLACEMENT: OVERVIEW

Switchgear

Inspection

Collaboration

Cutover

Plan & Risk

Assessment

Contract

Termination

Re-Do

Bid &

Award

Bid &

Award

Switchgear

Installation

& IntegrationStart

Design

(Jan

2012)

Page 13: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

SWITCHGEAR IN-SERVICE (OCT 2016)

SWITCHGEAR REPLACEMENT: OVERVIEWSwitchgear In-

Service

(Oct 2016)Switchgear

Inspection

Collaboration

Cutover

Plan & Risk

Assessment

Contract

Termination

Re-Do

Bid &

Award

Bid &

Award

Switchgear

Installation

& IntegrationStart

Design

(Jan

2012)

Page 14: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

DESIGN

• Walkdown equipment and as-built drawings

• Review original equipment documents

• Review equipment anchoring requirements

• Engage experts

HIGHLIGHTS AND LESSONS LEARNED

Page 15: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

BID & AWARD

• Understand the implications of procurement options

• Communicate what’s important to you

• Include hold points for detailed drawing review

• Include measurable performance requirements

• Evaluate need for performance bond

• Realistic schedule

HIGHLIGHTS AND LESSONS LEARNED

Page 16: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

SWITCHGEAR INSPECTION AND TESTING

• Plan a thorough Factory Acceptance Test (FAT)

• Recommend sending design engineer and plant electrician to FAT

• Perform thorough site inspection

• Identify who provides commissioning test equipment

• Request field service technicians resumes

HIGHLIGHTS AND LESSONS LEARNED

Page 17: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

CONTRACT TERMINATION

• Document and escalate issues promptly

• Initiate and perform tests, then document in report

• Keep stakeholders informed

• Use the T&Cs, contract, PO

HIGHLIGHTS AND LESSONS LEARNED

Page 18: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

COLLABORATION

• Meet with the vendor to review design

• Visit the manufacturing facility to resolve issues

• Include craft persons in discussions

HIGHLIGHTS AND LESSONS LEARNED

Page 19: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

CUTOVER PLAN AND RISK ASSESSMENT

• Start early to develop cutover plan

• Think through the details

• Review loads and the impact to facility during cutover

• Leverage existing contracts

• Get buy-in from stakeholders

HIGHLIGHTS AND LESSONS LEARNED

Page 20: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

SWITCHGEAR INSTALLATION

• Tools and materials

HIGHLIGHTS AND LESSONS LEARNED

Page 21: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

SWITCHGEAR INTEGRATION

• Identify roles & responsibilities within the team

• Purchase spare parts with the switchgear

• Review test results before factory field personnel leaves site

• Collaborate with plant staff

• Perform thorough testing

• Isolate protective relay outputs to avoid false trips

HIGHLIGHTS AND LESSONS LEARNED

Page 22: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

QUESTIONS?

KAREN HEDLUND, P.E.

POWER ENGINEER

TACOMA POWER – GENERATION

(253) 502-8318

[email protected]

JOHN LAMBERT

HYDRO PROJECT ELECTRICIAN

TACOMA POWER – GENERATION

(253) 779-7468

[email protected]

Page 23: SWITCHGEAR REPLACEMENT: OVERVIEW & LESSONS LEARNED · switchgear replacement: overview & lessons learned karen hedlund, p.e. power engineer tacoma power –generation april 6, 2017

THANK YOU!MOSSYROCK DAM