realising benefits from government ict investment – a fool's errand?

24
Realising Benefits from Government ICT investment – a fool’s errand? Virtual Government Seminar, Tokyo 12 th March 2010 Stephen Jenner [[email protected]]

Upload: lenhi

Post on 11-Feb-2017

230 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Realising Benefits from Government ICT investment – a fool's errand?

Realising Benefits from Government ICT investment –a fool’s errand?

Virtual Government Seminar, Tokyo 12th March 2010

Stephen Jenner [[email protected]]

Page 2: Realising Benefits from Government ICT investment – a fool's errand?

Change programmes - the rationale

“The fundamental reason for beginning a programme is to realise benefits through change. The change may be to do things differently, to do different things, or to do things that will influence others to change.”

Office of Government Commerce (OGC)

“It is only possible to be sure that change has worked if we can measure the delivery of benefits it is supposed to bring.”

Cabinet Office

Page 3: Realising Benefits from Government ICT investment – a fool's errand?

But the track record is not good in the UK

“Implementation of IT systems has resulted in delay, confusion and inconvenience to the citizen and, in many cases poor value for money to the taxpayer.”

Public Accounts Committee

“Deficiencies in benefits capture bedevils nearly 50% of government projects” and, “30-40% of systems to support business change deliver no benefits whatsoever.”

Office of Government Commerce

Page 4: Realising Benefits from Government ICT investment – a fool's errand?

Or in Europe…

“After at least a decade of large investments (running into billions of Euro) at digitalizing the public sector, governments in Europe are still mostly unable to objectively quantify and show the benefits and returns of such investments.”

e GEP, 2006

“The Implementation of eGovernment solutions is expected to bring a number of advantages including efficiency, increased user satisfaction, and reduction of administrative burden. However, this cannot be taken for granted any longer.”

eGovMoNet, 2008

Page 5: Realising Benefits from Government ICT investment – a fool's errand?

Or in Australia…

“Data from Australia on achieved benefit/cost ratios [in] central government indicates that rates of return on ICT investments often are low or negative.”

OECD

“benefits realisation and the measurement of benefits arising from investments in ICT are areas where there is substantial scope for improvement”

Sir Peter Gershon

Page 6: Realising Benefits from Government ICT investment – a fool's errand?

Or indeed in the US…

“The United States federal government will spend over USD 60 billion on ICT technology and systems in 2006. This huge expenditure has led many to ask if ICT investment is providing more than USD 60 billion in value to government agencies and, ultimately, tax payers. The answer is increasingly that nobody knows.”

OECD, 2006

“the committee has no confidence that the amounts being assessed have any relationship to the benefits anticipated.”

US Senate Appropriations Committee, 2006

Page 7: Realising Benefits from Government ICT investment – a fool's errand?

7

And it doesn’t appear that things are getting better

“Not all computing projects fail – only most of them. Now and again serendipity sees a company or government department buying and implementing a system that does as much as half of what was originally intended.”

Collins and Bicknell, 1998

“even when technically successful, ICT projects do not often deliver the financial and other benefits they promise. It is the remarkable ubiquity of the failure of ICT projects – particularly large ICT projects – and the large sums of money that can disappear as a result that should be of most concern”

Gauld and Goldfinch, 2006

Page 8: Realising Benefits from Government ICT investment – a fool's errand?

And empirical research concludes…

“There is a demonstrated, systemic tendency for project appraisers to be overly optimistic. This is a worldwide phenomenon that affects both the private and public sectors…appraisers tend to overstate benefits, and underestimate timings and costs.” HM Treasury

Forecasts are “highly, systematically and significantly misleading (inflated). The result is large benefit shortfalls”.

Flyvbjerg

“Delusional optimism: we overemphasise projects’ potential benefits and underestimate likely costs, spinning success scenarios while ignoring the possibility of mistakes.” Lovallo and Kahneman

Page 9: Realising Benefits from Government ICT investment – a fool's errand?

So we face 3 Benefit Challenges

1. Ensuring benefits claimed are robust and realisable.

2. Planning for all potential forms of value created.

3. Realising benefits and creating value – exploiting the capability created.

Page 10: Realising Benefits from Government ICT investment – a fool's errand?

Capturing all forms of value

Moving beyond hurdle rates of return to ask – have all potential forms of value been identified?

Page 11: Realising Benefits from Government ICT investment – a fool's errand?

Going beyond forecast to creating value

• Managing benefits from a portfolio perspective.

• Continuous Participative Engagement.

• Learning from experience.

From optimism in planning and pessimism in implementation to realism in planning and enthusiasm in

implementation

Page 12: Realising Benefits from Government ICT investment – a fool's errand?

But – the problem starts with the business case so start with the end in mind

“It has often been observed when analysing IS/IT project failures that all the ingredients for failure existed on Day One of the project, or even before it started!”

Ward and Taylor

Page 13: Realising Benefits from Government ICT investment – a fool's errand?

1. Understand the benefits you are buying

Beware ‘Strategic alignment’ as an investment justification,

“Our CEO defines ‘strategic projects’ as expensive projects without a Business case.”

Corporate Executive Board paper

Page 14: Realising Benefits from Government ICT investment – a fool's errand?

Understand the benefits you are buying- Strategic Contribution Analysis

Page 15: Realising Benefits from Government ICT investment – a fool's errand?

Understand the benefits you are buying- Strategic Contribution Analysis

Using a consistent benefits categorisation framework

User value Monetary Time-based non-monetary Value-based non-monetary

(such as less frustration from reduced unnecessary contact)

Departmental efficiency Contributions to departmental efficiency plans/targets (from website rationalisation, channel shift, shared infrastructure, removal of duplicate processes)

Departmental effectiveness Improved policy impact Increased regulatory

compliance, etc

Wider Public Value Trust Reputation Inclusion, etc

Page 16: Realising Benefits from Government ICT investment – a fool's errand?

Understand the benefits you are buying- Efficiency benefits

Beware staff time savings – they are

vouchers

Page 17: Realising Benefits from Government ICT investment – a fool's errand?

17

Understand the benefits you are buying- Efficiency benefits

“We were survivors, dwellers forever in the cracks of the vast organisational chart. Disperse us, downsize us, squash us, transfer us, and we will reassemble someday, somewhere, to once again build new layers of redundancy, waste, and glaring irrelevance.”

Lerner

Page 18: Realising Benefits from Government ICT investment – a fool's errand?

2. Triangulate and Validate forecasts

• Use Reference class forecasting.

• Validate the benefits with the recipients – before investment.

• Establish effective accountability for benefits realisation.

Page 19: Realising Benefits from Government ICT investment – a fool's errand?

3. Appraise Attractiveness/Return in the context of Achievability/Risk

Page 20: Realising Benefits from Government ICT investment – a fool's errand?

4. ‘Gates with teeth’

• Challenge and Support.

• Based on joint planning for success.

•Staged release of funding

• Concludes with a formal re-commitment to benefits realisation.

Page 21: Realising Benefits from Government ICT investment – a fool's errand?

5. A ‘Clear line of sight’ from strategic intentto benefits realisation

• Investment Appraisal report

• Benefits Scorecard

• Portfolio Analysis • Proving Model report

SR2004 CSR07 10 Year TotalQuality of

Benefit Forecast

Scale of Benefits Forecast

Quality ofRealisation

PlanningLikelihood ofRealisation

Confidence Victims and Witnesses OBTJ Enforcement Re-offending Q1 03/04 - Q4

05/06 2006/07 2007/08NSPIS Custody & Case Prep 79.08 199.82 348.06 AMBER AMBER AMBER AMBER Realised Plan ActualPentiP - 5.08 14.06 GREEN GREEN AMBER AMBER Efficiency Cashable - - 0.39 0.71 COMPASS CMS (50%) 10.95 20.79 52.74 GREEN AMBER GREEN AMBER HD=1 Efficiency Opportunity 4.95 2.69 26.136 50.59 NWNJ IT tool (WMS) 5.70 9.66 25.02 GREEN GREEN GREEN AMBER D=2 HD=1 NK=1 HD=1 Effectiveness 0.26 0.24 0.94 1.12 SOCA 0.61 1.21 3.43 GREEN GREEN GREEN GREEN M=1 Total 5.21 2.93 - 27.473 52.42 Libra application (includes benefits jointly delivered with 3a) 18.15 81.70 154.31 GREEN RED AMBER AMBER M=1 NK=1

OASys 79.52 93.18 239.12 GREEN GREEN GREEN GREEN MC=2Q1 03/04 - Q4

05/06 2006/07 2007/08NOMIS (70%) 5.06 50.00 162.33 GREEN GREEN GREEN GREEN MC=1 HD=1 Realised Plan ActualViSOR 0.93 2.21 6.08 GREEN GREEN GREEN GREEN Efficiency Cashable - - - - CJSE Release 1a (NSPIS-CMS) 1.63 9.76 17.88 GREEN GREEN GREEN AMBER Efficiency Opportunity 31.40 8.88 35.50 39.04 CJSE Release 1b (NSPIS - Libra) 0.87 19.08 37.29 AMBER GREEN AMBER AMBER Effectiveness 0.13 0.39 1.56 2.83

XHIBIT/CJSE Release 2a&b (XHIBIT Portal) 9.29 7.11 21.15 AMBER RED GREEN AMBER M=1 D=1 M=1 Total 31.53 9.27 - 37.06 41.87 PROGRESS 1.88 12.02 26.04 GREEN GREEN GREEN GREEN M=4 HD=1 D=2

Secure Email/Emailing Securely 1.49 1.90 4.78 AMBER RED AMBER AMBER D=2Q1 03/04 - Q4

05/06 2006/07 2007/08CJSE Release 3a 0.00 0.01 0.02 AMBER AMBER AMBER Realised Plan ActualCJSE Release 3b 1.10 2.13 6.07 GREEN AMBER AMBER Efficiency Cashable - 0.70 17.45 COMPASS infrastructure (50%) 85.95 95.79 252.74 see COMPASS CMS Efficiency Opportunity 2.59 0.53 2.67 1.70 Libra enabled 30.17 34.26 95.54 see LIBRA application Effectiveness - 0.34 2.54 4.42 NOMIS infrastructure (30%) 2.17 21.43 69.57 see NOMIS application Total 2.59 0.87 - 5.91 23.57 OMNI infrastructure 1.03 3.11 6.48 OMNI cost effectiveness - 9.36 36.37

LINK enabled 8.68 11.79 28.49 Q1 03/04 - Q4

05/06 2006/07 2007/08

Shared Access 5.85 7.80 24.05 D=2 Realised Plan ActualEquip direct 16.50 16.50 55.00 Efficiency Cashable - - - - Equip enabled 41.41 149.10 311.00 Efficiency Opportunity 26.77 5.68 22.70 24.36

CEI 9.78 21.43 45.54 D=9 M=1 HD=3 D=5 M=1 HD=11 D=3 M=1 D=5 M=1 NK=1 D=1 M=1 Effectiveness 12.40 5.26 21.06 21.21 Economic/Social Value Benefits 15.61 113.53 291.21 Total 39.17 10.94 - 43.76 45.57

433.41 999.74 2,334.36

1274.65 KEY

250.18 Q1 03/04 - Q4

05/06 2006/07 2007/08

12.90% 2003/04 2003-05 2003-06 2003-07 2003-08Benefits as %

of Cost Realised Plan Actual57.09 90.37 142.59 183.78 202.01 Efficiency Cashable - 0.53 1.63 5.21 32.69 85.10 Efficiency Opportunity 0.11 0.05 0.21 0.37

- - - - Effectiveness - 0.53 1.63 5.21 32.69 85.10 42% Total 0.11 0.05 - 0.21 0.37

111.21 194.71 269.22 408.09 519.61 5.50 15.38 39.29 83.26 129.20 - 8.55 10.12 19.22 49.96 Q3 05/06 Q4 05/06

5.50 23.93 49.40 102.47 179.16 34% No. % No. %25.05 58.82 97.87 132.70 170.63 6 6% 2 2%

- 2.05 31.53 68.59 110.46 26 27% 35 36%- 2.05 31.53 68.59 110.46 65% 13 13% 19 20%

154.55 283.61 426.40 512.40 585.28 52 54% 41 42%- 0.30 2.59 8.50 32.07

3.23 8.43 18.80 32.10 47.28 3.23 8.73 21.39 40.60 79.35 14%

3Ring Fence costs from 2003-06 and Delivery Plan RF budget from 2006-08. Full benefits by recipient used. Corrections includes YJB.

RAG

1

2

3

Summary of Key Mitigating Actions

1. Settlement Letter Conditions/Hurdle rates 2. Root Cause Model 3. Social Value Research 4. Analysis of benefits enabled by CJS IT funded infrastructure

1. Quarterly Benefits Integrity Check 2. Benefits Eligibility Framework

Risk Description

2006/07 Q1

Difficulty with tracking/measure.

Benefits Rating

Pro

g

RAG of Benefits in SR2004 Benefits Realisation Plans

2006/07 Q1

YJB Benefits Realisation Plan

Direct Benefits

2006/07 Q1

HMCS Benefits Realisation Plan

2006/07 Q1

Infr

astr

uctu

re

Scale of CJS IT benefits forecast

1. Process Modelling 2. CJO Benefit Realisation Plans approved by OB and BWG 3. Project Benefit Realisation Plans approved by BWG CJSIT benefits realisation

Total 10 year CJS IT Application benefits Ring Fence only

CJS IT Application NPV Ring Fence only

CJS IT Application IRR Ring Fence only Cost Benefit Analysis3

Quality of CJS IT benefits forecast

Risk Register - CJS IT Benefits Management

CJS IT BENEFITS SCORECARD June 2006This table shows the full CJS IT Programme benefits picture, including ring fence benefits and benefits enabled by the ring fence infrastructure (£m)

Ap

pli

cati

on

s

CJS IT Benefits Realisation Plans

CJS IT Projects

Forecast Benefit Values Self assessment of RAG status Police Benefits Realisation Plan

TOTAL BENEFITS

Total CPS RF Cost/BudgetDirect & Enabled BenefitsTotal CPS Benefits

Total Corrections RF Cost/BudgetDirect BenefitsEnabled BenefitsTotal Corrections Benefits

Total Police RF Cost/Budget

Enabled BenefitsTotal Police Benefits

Total HMCS Benefits

Total HMCS RF Cost/BudgetDirect BenefitsEnabled Benefits

Forecast

2. Independent Scores assessed by Proving Services

Benefit on track/ahead of scheduleBenefit not yet due for realisation

Benefit behind schedule

NOTE: Benefits shown only include quantified, validated benefits but other enabled benefits have been identified

and will be included as further work is undertaken

Forecast

Forecast

Forecast

Forecast

CPS Benefits Realisation Plan

2006/07 Q1

NOMS Benefits Realisation Plan

1. Based on BRP submissions & agreed with Strand Board leads, this shows the number of benefits to the Strands in terms of value (ie. mission critical, highly desirable etc)

MC = Mission Critical, HD = Highly Desirable, D = Desirable, M = Minimal, NK = Not Known

Strand Board Alignment1

Relative Contribution to

Strategic Drivers2

Benefits to the CJS and Society

Home CJO, 76%

x-CJS, 9% Social Value, 16%

Home CJO x-CJS Social Value

Benefits By Type

Efficiency Opportunity

61%

Efficiency Cashable

9%

Effectiveness30%

Efficiency Cashable Efficiency Opportunity Effectiveness

ATTRACTIVENESS ANALYSIS ECONOMIC ANALYSIS* NPV (£M) IRR (%) PAY BACK PERIOD

(YEARS) EXCLUDING OPTIMISM BIAS

INCLUDING OPTIMISM BIAS

CONFIRMATION THAT THE ABOVE FIGURES ARE COMPLIANT WITH BENEFITS ELIGIBILITY FRAMEWORK (BEF) Yes No

CONFIRMED BY: COMMENTS:

BENEFITS ANALYSIS OVER 10 YEAR PROJECT LIFE CYCLE (£M) STATE 10 YEAR PERIOD COVERED OR PROJECT LIFE SPAN IF LESS THEN 10 YEARS: RECIPIENT EFFICIENCY –

CASHABLE EFFICIENCY – OPPORTUNITY VALUE

EFFECTIVENESS - CASHABLE

EFFECTIVENESS – OPPORTUNITY VALUE

CJO: Police CJO: CPS CJO: DCA CJO: NOMS CJO: YJB CROSS CJS: BEYOND THE CJS(SPECIFY):

TOTALS:

INC

LU

DE

D IN

B

RP

A

GR

EE

D IN

P

RIN

CIP

LE

NO

T Y

ET

A

GR

EE

D

SOURCE OF CONFIRMATION OR PROPOSED ACTIONS & TIMESCALES TO ENSURE BENEFITS ARE INCLUDED IN BENEFITS REALISATION PLAN

BENEFITS INCLUDED IN THE POLICE BENEFITS REALISATION PLAN (BRP) OR AGREED IN PRINCIPLE BY THE POLICE BENEFITS REALISATION LEAD(BRL)

BENEFITS INCLUDED IN THE CPS BRP OR AGREED IN PRINCIPLE BY THE CPS BRL

BENEFITS INCLUDED IN THE DCA BRP OR AGREED IN PRINCIPLE BY THE DCA BRL

BENEFITS INCLUDED IN THE NOMS BRP OR AGREED IN PRINCIPLE BY THE NOMS BRL

BENEFITS INCLUDED IN THE YJB BRP OR AGREED IN PRINCIPLE BY THE YJB BRL

ACHIEVABILITY ANALYSIS

PROVING SERVICES ACHIEVABILITY SCORE BREAKDOWN CONCEPT CASE (COMPLETE AS APPROPRIATE)

BUSINESS CASE (COMPLETE AS APPROPRIATE)

ASSESSMENT OF DEGREE OF BUSINESS CHANGE REQUIRED TO REALISE BENEFITS RECIPIENT BRL ASSESSMENT COMMENTS

HIG

H

ME

DIU

M

LOW

N

/A

Police CPS DCA NOMS YJB Others [specify]

PROVING MODEL ASSESSMENT DATE OF CURRENT ASSESSMENT: ACHIEVABILITY SCORE: PROGRESS SINCE LAST ACHIEVABILITY ASSESSMENT:

(1) TOTAL PROJECT COSTS YEAR RESOURCE

(£M) CAPITAL

(£M) TOTAL (£M)

TOTAL

(2) RESOURCE/CAPITAL CURRENTLY ALLOCATED FROM THE RING FENCE

(3) OTHER FUNDING SOURCES

YEAR RESOURCE (£M)

CAPITAL (£M)

TOTAL (£M)

RESOURCE (£M)

CAPITAL (£M)

TOTAL (£M)

TOTAL

RESOURCE/CAPITAL GAP (1-(2+3)) RESOURCE/CAPITAL REQUIRED FROM THE RING FENCE

YEAR RESOURCE (£M)

CAPITAL (£M)

TOTAL (£M)

RESOURCE (£M)

CAPITAL (£M)

TOTAL (£M)

TOTAL

FUNDING – OTHER ISSUES AVAILABILITY CONFIRMED? FUNDING AVAILABLE TO REALISE BUSINESS CHANGE? Yes

No BY: DATE

CONFIRMATION THAT OVERSPENDS WILL BE MET BY DEPARTMENTAL BASELINES

Yes No

BY: DATE

RECYCLING OF COST SAVINGS YEAR LEGACY SYSTEM

SAVINGS SAVINGS

RECYCLED? AMOUNT BY WHICH THE RING FENCE

REQUEST CAN BE REDUCED TOTAL

• Recipient Organisation Benefits Realisation Report

• Contributor project benefits report

RecipientCost Avoidance

Self Assessment Cashable Opportunity Cashable Opportunity £ %Crown Courts 12.700 35.620 0.000 25.920 0.000 74.240 6.7%

Quality of Benefits Forecast Other CJOs 0.000 117.820 0.000 52.760 0.000 170.580 15.3%Scale of Benefits Forecast Cross CJS 0.000 0.000 0.000 173.710 0.000 173.710 15.6%Quality of Realisation Planning Outside CJS 0.000 0.000 0.000 694.860 0.000 694.860 62.4%Likelihood of Realisation Total £ 12.700 153.440 0.000 947.250 0.000 1113.390 100.0%

Benefits Realised this financial year £m Last report NowMonetary Value of Benefits Realised YTD 0.01 NPV £m* 154.301 -

4.10.0%

Variance -4.09

Performance £ M

From 1 month after Go-live at each court centre

Reduced waiting time claim valuesBenefit not yet due for realisation10 Reduction in solicitor waiting - 12.7 Efficiency cashable

PSA Targets 2, 3 and 5

Crown Court

Following rollout to all prisons in a CJA

Benefit not yet due for realisation9 NOMS Benefits - 36.9 Effectiveness opportunity

PSA Target 5

NOMS

Benefit ahead of or in line with plan10

Benefit ahead of or in line with plan

No of bail forms sent and time taken

9

3 months after go live in a CJ Area

No of enquiries made to CCBenefit ahead of or in line with plan

No of daily/warned lists sent and time taken

8 Police Benefits - 115.52 Efficiency opportunity

PSA Target 5

Police

3 months after go live in a CJ Area

Number of enquiries made to CCBenefit ahead of or in line with plan

No of daily lists faxed/time taken.

7 CPS Benefits - 2.3 Efficiency opportunity

PSA Target 5

CPS

From 1 month after Go-live at each court centre

Backlog countBenefit ahead of or in line with plan

Number of disposals

6 Crown Court Efficiency benefits - 35.61 Efficiency opportunity

PSA Targets 2, 3 and 5

Crown Court

From 3 months after Go-live at each court centre

Number of disposalsBenefit ahead of or in line with plan5 Court time saving (Same day delays) - 5.98 Effectiveness opportunity

PSA Targets 2, 3 and 5

Crown Court

From 6 months after Go-live at each court centre

Percentage of ineffective hearingsBenefit not yet due for realisation4 Court time saving ( Ineffective Hearings)

Assumption of improvement of 1-10% 31.78 Effectiveness opportunity

PSA Targets 1, 2, 3 and 5 Crown Court, Police, CPS, Probation

From Go-live at each court centre

No. of adjournments as a result of no PSRBenefit ahead of or in line with plan3 Court time saving (PSR adjournments)

Improvement from 15% to 3.4% 4.06 Effectiveness opportunity

PSA Targets 2, 3 and 5

Crown Court

To start 6 months after completion in a CJ Area

Time from CC result to PNC update

2 Reduction in the cost of crime

PNC update down to 3 days 694.86 Effectiveness opportunity

PSA Targets 1 and 3

UK economy

To start 6 months after completion in a CJ Area

Time from CC result to PNC updateBenefit realisation behind Plan

Realisation Ramp Up Key Measures/Indicators of Benefit

Benefits Realisation

Status

1 Reduction in the cost of crime

PNC update down to 3 days 173.71 Effectiveness opportunity

PSA Target 5

CJS

94.2*NPV discounted at 3.5%

Project Life Cycle Benefits Profile (Top 5-10 benefits over 10 years)

Benefit Description

Impact

Benefit Category Strategic AlignmentMain Recipient

Name(s) of recipient agreed with

Q4 Assessment

Q4 forecast for Q1

Forecast in latest published Delivery Plan YTD IRR %

Approved by SRO:

Benefit not yet due for realisation

CJS IT BENEFITS PROGRESS REPORT - QUARTER 4 2004-05 FOR CJS EXCHANGE XHIBIT PORTAL

10 Year Analysis

Efficiency £ M Effectiveness Total

Q3 Assessment

Q3 Forecast for Q4

Cumulative Cost and Benefit Forecast 2003-2013

-

200

400

600

800

1,000

1,200

2003-04

2004-05

2005-06

2006-07

2007-08

2008-09

2009-10

2010-11

2011-12

2012-13

Year

£'m

Cumulative Benefits Cumulative Costs

Page 22: Realising Benefits from Government ICT investment – a fool's errand?

6. Independent review

“humans not only are prone to make biased predictions, we’re also damnably overconfident about our predictions and slow to change them in the face of new evidence. In fact, these problems of bias and overconfidence become more severe the more complicated the prediction.”

Ayers

Page 23: Realising Benefits from Government ICT investment – a fool's errand?

6. Independent review

Ayers suggests an, “‘Advocatus Diaboli’… whose job it is to poke holes in pet projects. These professional “No” men could be an antidote to overconfidence bias.”

Davidson Frame proposes the use of “murder boards” to pull a proposal apart to, “make sure that arguments in support of project ideas do not have built into them the seeds of their own destruction.”

Steve Jenner - I suggest a ‘fool’ to ask the questions others don’t dare to ask and identify those, ‘assumptions that masquerade as facts’.