Page 1: REBO general - 2015-10-15

1

on the REBO terminal in ENERGY PORT OOSTENDE MARITIME ACCESS & LOGISTIC OPERATIONS

Emmanuël Timmermans

business development manager

Page 2: REBO general - 2015-10-15

2

RENEWABLE ENERGY BASE OOSTENDE

– priority for offshore installation vessels –

- easy access by: airplane; road; railway; helicopter - no locks - loading & unloading - storage area - O&M facilities

Page 3: REBO general - 2015-10-15

3

1 / LOCATION 2 / MARITIME ACCESS 3 / REBO 4/ INFRASTRUCTURE & LOGISTICS 5/ REALISATIONS 6/ O&M

Page 4: REBO general - 2015-10-15

4

Page 5: REBO general - 2015-10-15

5

1/ LOCATION Europe – Belgium – Oostende

BERLIN

MILAN

PARIS

LONDON

270 km

300 km

1000 km

850 km

BRUSSELS

OOSTENDE

900 km ESJBERG

Page 6: REBO general - 2015-10-15

6

1/ LOCATION Belgian sea ports

OOSTENDE

BRUSSELS

ANTWERP

GHENT

HASSELT BRUGES

KORTRIJK

WALLONIE

FLANDERS

ZEEBRUGGE

Page 7: REBO general - 2015-10-15

7

1/ LOCATION windfarms in the North Sea

OOSTENDE

250 km

Page 8: REBO general - 2015-10-15

8

1/ LOCATION

map of the port

- open sea - inner water - railway - highway - airway

COMPLETE INDUSTRIAL AREA IS MULTIMODAL UNLOCKED:

outer port inner port

Page 9: REBO general - 2015-10-15

9

Page 10: REBO general - 2015-10-15

10

2/ MARITIME ACCESS

approach from open sea to port

300 m

270 m

150m (-8,5m TAW)

Page 11: REBO general - 2015-10-15

11

2/ MARITIME ACCESS

approach from open sea to port – harbour wall heads

Page 12: REBO general - 2015-10-15

12

2/ MARITIME ACCESS

approach from open sea to port – widening eastern shore 2015

Page 13: REBO general - 2015-10-15

13

2/ MARITIME ACCESS

approach from open sea to port

Neptune

Length over all (LOA) 60 m

Width 38 m

Maximum draft 3,9 m

accomodation 60 p

Page 14: REBO general - 2015-10-15

14

2/ MARITIME ACCESS

approach from open sea to port Pacific Osprey

Length over all (LOA) 160,9 m

Width 49 m

Minimum draft 5,5 m

Maximum draft 6 m

accomodation 111 p

Page 15: REBO general - 2015-10-15

15

2/ MARITIME ACCESS

Port Control & MRCC: Maritime Rescue & Coordination Centre

Page 16: REBO general - 2015-10-15

16

Page 17: REBO general - 2015-10-15

17

3/ REBO

history

Page 18: REBO general - 2015-10-15

18

3/ REBO

shareholders & goal SHAREHOLDERS Public Private Founded 2012 GOAL 1. Invest in existing and new port infrastructures to attract offshore wind activities. 2. Exploitation of a 15 ha offshore terminal.

Commercial exploitation Port of Oostende

A flagship organisation in the field of civil engineering, construction, hydraulic engineering and restoration

Invest in entrepreneurs, real estate, & infrastructure.

Offshore & Wind Assistance offers a wide range of services including maintenance of offshore installations for wind energy and oil and gas applications, marine logistic services

DEME Blue Energy (DBE) was created to develop wave and tidal energy projects worldwide.

Page 19: REBO general - 2015-10-15

19

3/ REBO

Renewable Energy Base port of Oostende

assembly & storage area with direct access to open sea

assembly & storage area behind the locks

offices & storage

Page 20: REBO general - 2015-10-15

20

3/ REBO

investments REBO invested more than € 15.000.000 (2013 -2014): -> reinforcement of the sea bed along the quays (new jackup vessels)

Page 21: REBO general - 2015-10-15

21

3/ REBO

investments REBO invested more than € 15.000.000 (2013 -2014): -> reinforcement of the sea bed along the quays (new jackup vessels) -> reinforcement > 10 Ha of terminal surfaces (heavy lift capacity: 10 - 20 T/m²)

Page 22: REBO general - 2015-10-15

22

3/ REBO

investments REBO invested more than € 15.000.000 (2013 -2014): -> reinforcement of the sea bed along the quays (new jackup vessels) -> reinforcement > 10 Ha of terminal surfaces (heavy lift capacity: 10 - 20 T/m²) -> invest in real estate (project management and O&M infrastructure)

Page 23: REBO general - 2015-10-15

23

3/ REBO

Wind farms in the North Sea windfarms in the Belgian part of the North Sea

REBO terminal

Page 24: REBO general - 2015-10-15

24

3/ REBO

share holders Belgian wind farms / share holders REBO

Page 25: REBO general - 2015-10-15

25

3/ REBO

• outstanding geographical location

• excellent & immediate access to open sea

• no locks

• 127 ha available in the port of Oostende for renewable energy activities

• quays with a capacity able to handle from 4 T/m² to 20T/m²

• 15 Ha of terminal surfaces (with heavy lift capacity) and with capacity for extension

• priority to offshore wind vessels

summary

Page 26: REBO general - 2015-10-15

26

Page 27: REBO general - 2015-10-15

27

4.1/ INFRASTRUCTURE

gravel reinforced sea bed

Page 28: REBO general - 2015-10-15

28

4.1/ INFRASTRUCTURE

Neptune for C-Power

Page 29: REBO general - 2015-10-15

29

4.1/ INFRASTRUCTURE

RORO pontoons

Page 30: REBO general - 2015-10-15

30

4.1/ INFRASTRUCTURE

Bold Tern – Fred Olsen / HEAVY LIFT QUAY

Page 31: REBO general - 2015-10-15

31

4.1/ INFRASTRUCTURE

Innovation – GeoSea

Page 32: REBO general - 2015-10-15

32

4.1/ INFRASTRUCTURE

Innovation – GeoSea

Port of Aalborg (DK) Project: Westermost Rough Offshore Windfarm (UK)

Page 33: REBO general - 2015-10-15

33

4.1/ INFRASTRUCTURE

> 127 ha dedicated areas for wind farm logistics > 15 Ha of terminal surfaces with heavy lift capacity up to 20 T/m2 > heavy load bearing quays > dedicated pontoons, mooring facilities for workboats, tugboats, crew vessels

summary

Page 34: REBO general - 2015-10-15

34

4.2 / LOGISTICS

Construction & loading of 6 Gravity Base Foundations (GBF)

site Halve Maan – unit weight: 2700 tons

Page 35: REBO general - 2015-10-15

35

4.2 / LOGISTICS

GBF – preparation for loading with Rambiz floating crane

Page 36: REBO general - 2015-10-15

36

4.2 / LOGISTICS

GBF – move on SPMT

Page 37: REBO general - 2015-10-15

37

4.2 / LOGISTICS

GBF – half submerged (weight reduction)

Page 38: REBO general - 2015-10-15

38

4.2 / LOGISTICS

storage for jacket on pontoons

Page 39: REBO general - 2015-10-15

39

prepiles – Flinder Rose unloading

4.2 / LOGISTICS

Page 40: REBO general - 2015-10-15

40

prepiles – storage on quay side

4.2 / LOGISTICS

Page 41: REBO general - 2015-10-15

41

nacelles, 4 hubs, 8 tower sections – pontoon manoeuvering

4.2 / LOGISTICS

Page 42: REBO general - 2015-10-15

42

blades arrival by road (night transport only) (63,5 m long) truck turning into harbour area

4.2 / LOGISTICS

Page 43: REBO general - 2015-10-15

43

blades arrive by ship – unloading blades

4.2 / LOGISTICS

Page 44: REBO general - 2015-10-15

44

arrival & unloading of Alstom Haliade (420 T) – arrival on pontoon square onto the quay

4.2 / LOGISTICS

Page 45: REBO general - 2015-10-15

45

arrival & unloading of Alstom Haliade (420 T) – off it comes

4.2 / LOGISTICS

Page 46: REBO general - 2015-10-15

46

arrival & unloading of Alstom Haliade (420 T) – ready positioned

4.2 / LOGISTICS

Page 47: REBO general - 2015-10-15

47

4.2 / LOGISTICS

spare infield cable Northwind – Jan De Nul – 40 ton

Page 48: REBO general - 2015-10-15

48

4.2 / LOGISTICS

spare infield cable Northwind –Jan De Nul – 40 ton

Page 49: REBO general - 2015-10-15

49

4.2 / LOGISTICS

ready for assembly

Page 50: REBO general - 2015-10-15

50

4.2 / LOGISTICS

Neptune & Goliath in the port

Page 51: REBO general - 2015-10-15

51

4.2 / LOGISTICS

Thor for C-Power

Page 52: REBO general - 2015-10-15

52

4.2 / LOGISTICS

Thor for C-Power

Page 53: REBO general - 2015-10-15

53

4.2 / LOGISTICS

WIND for Belwind

Page 54: REBO general - 2015-10-15

54

4.2 / LOGISTICS

Thor & Wind

Page 55: REBO general - 2015-10-15

55

4.2 / LOGISTICS

quay

Page 56: REBO general - 2015-10-15

56

4.2 / LOGISTICS

Bold Tern

Page 57: REBO general - 2015-10-15

57

4.2 / LOGISTICS

hub with blades on Neptune

Page 58: REBO general - 2015-10-15

58

4.2 / LOGISTICS

positioning in between spuds & towers

Page 59: REBO general - 2015-10-15

59

4.2 / LOGISTICS

Haliade 150 6MW loaded on Bold Tern in floating position

Page 60: REBO general - 2015-10-15

60

4.2 / LOGISTICS

ready to go to sea

Page 61: REBO general - 2015-10-15

61

4.2 / LOGISTICS

passing harbour walls heads

Page 62: REBO general - 2015-10-15

62

4.2 / LOGISTICS

Bold Tern sailing out with haliade 150 6MW

Page 63: REBO general - 2015-10-15

63

4.2 / LOGISTICS

Deme platforms at work

Page 64: REBO general - 2015-10-15

64

4.2 / LOGISTICS

Bold Tern at work

Page 65: REBO general - 2015-10-15

65

Page 66: REBO general - 2015-10-15

66

5/ REALISATIONS

INSTALLATION ZONE

O&M ZONE

Page 67: REBO general - 2015-10-15

67

5/ REALISATIONS

C-Power - Northwind – Belwind I – Alstom

C-Power I, II, III 52 x 6,15 MW Senvion turbine total 325,2 MW

Belwind I 55 x 3 MW Vestas turbine total 165 MW

Northwind 72 x 3 MW Vestas turbine total 216 MW

Belwind I (Alstom test) 1 x 6 MW Haliade 150 turbine total 6 MW

Page 68: REBO general - 2015-10-15

68

Page 69: REBO general - 2015-10-15

69

6/ O&M

new & renovated buildings along the quay

MHI Vestas – Alstom – Parkwind - Geosea

Page 70: REBO general - 2015-10-15

70

new & renovated buildings with direct access to the quay

Falck Safety Services – Cofely – Senvion – OWA – Technum – Flidar – eCoast (sanitary facilities for up to 100 people)

6/ O&M

Page 71: REBO general - 2015-10-15

71

new & renovated buildings with direct access to the quay

Falck Safety Services: training basin & boat landing

6/ O&M

Page 72: REBO general - 2015-10-15

72

new & renovated buildings with direct access to the quay

Falck Safety Services: tower

6/ O&M

Page 73: REBO general - 2015-10-15

73

6/ O&M

heli port

Page 74: REBO general - 2015-10-15

74

6/ O&M

3 pontoons and 1 fixed crane for service vessels

Page 75: REBO general - 2015-10-15

75

6/ O&M

bunkering for service vessels

Page 76: REBO general - 2015-10-15

76

6/ O&M

bunkering for service vessels

Page 77: REBO general - 2015-10-15

77

6/ O&M

3 pontoons and 1 fixed crane for service vessels

Page 78: REBO general - 2015-10-15

78

6/ O&M

6000 movements (2013 - 2014)

Page 79: REBO general - 2015-10-15

79

6/ O&M

Oostende, homebase for …

Page 80: REBO general - 2015-10-15

80

7/ PORT COLLABORATIONS

an international collaboration of sea ports with a focus on offshore wind

– Port of Oostende –

– Port of Ramsgate – Port of Newhaven – Pool Port – – Brunsbuettel Ports – Rendsburg Port –

www.seanergyports.eu

Page 81: REBO general - 2015-10-15

81

SEE YOU SOON www.reboostende.be

Page 82: REBO general - 2015-10-15

82

CONTACT

Rebo