rebuilding the world trade center

24
IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009 Rebuilding of the District Cooling Plant at the World Trade Center Hemant Mehta, P.E. and Christopher Tso, P.E. WM Group Engineers, P.C. CRC Engineering, P.C.

Upload: ctso

Post on 08-Sep-2014

2.186 views

Category:

Documents


1 download

DESCRIPTION

Presented at the June 2009 IDEA Conference - Rebuilding the World Trade Center Central Chiller Plant

TRANSCRIPT

Page 1: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Rebuilding ofthe District Cooling

Plantat the

World Trade Center

Hemant Mehta, P.E. and Christopher Tso, P.E.

WM Group Engineers, P.C. CRC Engineering, P.C.

Page 2: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Executive Summary

Project highlights and challenges:• 12,500 ton central chiller plant, river water systems and

site chilled water distribution system design• Provides ten (10) stakeholders with CHW for cooling• Uses river water from the Hudson River for condensing• Rehabilitation of the existing river water pump station• Compliance with environmental permit (SPDES) for

river water use• Salt water (river water) systems design• Chiller plant energy modeling and configuration study• Site chilled water distribution system design passing

through other stakeholder areas• Extensive coordination with other projects onsite at

varying stages of design / construction

Page 3: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Project Highlights

• 12,500 ton chiller plant and distribution system– Five 2500 ton electric centrifugal chillers– Five 300 hp chilled water pumps with VFDs– Two 1000 ton free/pre-cooling plate & frame heat

exchangers (chilled water / river water)

• River water pump station rehabilitation– Environmental permit requirements– Four 500 hp vertical turbine river water pumps with

VFDs– Replacement/rehabilitation of traveling screens and

sluice gates

Page 4: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Stakeholders Served

• National September 11 Memorial & Museum• Freedom Tower retail• Transportation Hub• Performing Arts Center• East Bathtub retail• Vehicle Security Center• Master Manager• MTA Cortland Street

‘1-train’ Subway Station• North Access• South Projection

Page 5: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Project Challenges

• Rigging of equipment• Coordination with many other projects onsite

at varying stages of design/construction– Central chiller plant is located below grade inside

the National September 11 Memorial & Museum– Site chilled water distribution passes through other

stakeholder spaces– Phased stakeholder loads– Construction staging/logistics– Site wide systems integration

Page 6: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

World Trade Center Site

Page 7: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

World Trade Center Site

Chiller Plant Below Memorial Plaza

Page 8: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Chiller Plant Configuration Study

• Detailed energy and operating cost modeling– Hourly weather data– Hourly river water temperature data– Equipment part-load performance– VFDs vs constant speed drives for the chillers– Free cooling operation– Utility rate schedule

• Procurement considerations– Multiple bidders required

Page 9: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Cooling Load Profile

Page 10: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

River Water Temperature

Page 11: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Free Cooling Operation

Page 12: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

River Water Systems Design

• Condition survey– River water pump station equipment– River water pump station diver inspection– River water pump station ductbank condition

survey– Interior piping inspection of 60 and 66 inch

underground river water mains• Environmental permit requirements (SPDES)– VFDs for river water pumps– Metering/logging of flows and temperatures

Page 13: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

River Water Pump Station

Page 14: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Existing River Water Piping Inspection

Page 15: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

River Water Systems Design

• Salt water system design– Materials and coatings– Cathodic protection

• Dual headered piping system for seasonal interior river water piping inspection

• Replacement/refurbishment of traveling screens and sluice gates

Page 16: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Interior River Water Piping Inspection

Page 17: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Stakeholder Chilled Water Interface

• Interface at each stakeholder mechanical room– Flow meter, temperature & pressure transmitters– Monitoring of interface at chiller plant

Page 18: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Phased Stakeholder Loads

• Phased loads– Memorial: September 2011 (partial opening)– Freedom Tower: October 2011– Transportation Hub: November 2012– East Bathtub Retail: November 2012

• Two chillers with hot gas bypass to serve the Memorial partial opening

Page 19: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Construction Logistics

• Chiller plant is below grade inside the Memorial– The Memorial plaza at grade must be completed for

partial opening (September 2011)– Plant access through equipment rigging hatch and

shared freight elevator– Site access from Route 9A

• River water pump station– Located below grade, under a pedestrian plaza– Equipment access via hatches in plaza– Pedestrian plaza owned by Battery Park City

Page 20: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Construction Logistics

• Coordination with other projects onsite– National September 11 Memorial & Museum– Freedom Tower– Vehicle Security Center– West Vent Structure– South Projection– Route 9A Relocation

Page 21: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Construction Logistics

Page 22: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Construction Logistics

Page 23: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Site Wide Systems Integration

• Fire Alarm• Radio systems• Telecommunications• BMS

Page 24: Rebuilding the World Trade Center

IDEA Centennial Conference: “Local Energy, Global Solution” June 28–July 1, 2009

Contact Information

Hemant Mehta, P.E.PresidentWM Group Engineers, P.C.370 Seventh Avenue, Suite 701New York, NY 10001(646) [email protected]://www.wmgroupeng.com

Christopher Tso, P.E.PresidentCRC Engineering, P.C.1261 Broadway, Suite 608New York, NY 10001(212) [email protected]://www.crc-eng.com