reconstruction of huguelet drive steam piping, vaults and

11
Reconstruction of Huguelet Drive Steam Vaults and Tunnel (Design Only) University of Kentucky Project Number 2568.0 Consultant Submittal Guidelines & Executive Summary Page 1 of 6 Consultant Submittal Guidelines for the Reconstruction of Huguelet Drive Steam Piping, Vaults and Tunnel (Design Only) for the UNIVERSITY OF KENTUCKY Main Campus PROJECT NO. 2568.0 The University of Kentucky is requesting the services of a consultant to provide design for the Reconstruction Huguelet Drive Steam, Piping, Vaults and Tunnel (Design Only) located on the University of Kentucky campus at the intersection of Huguelet Drive and Rose Street. The design team's SF330 submittal should include ONLY the names of individuals that will comprise the project team, clearly indicating the specific role each will play in the overall project from schematic design (Phase 1) through contract administration (Phase 5) should the project proceed to construction. This is necessary for the primary design firm as well as for each technical consultant that the prime firm plans to use on the project. The following list is the criteria, including the multiplication factors; by which each design team's submittal will be evaluated. Bearing this in mind, each team's submittal should clearly and thoroughly address all criteria to allow objective evaluation of the team's previous experience and capability to successfully complete this project. All submittals should be in .PDF format and GIVE SPECIFIC PROJECT EXAMPLES, including photographs, drawings, resumes, schedules, budget analyses, etc. to properly substantiate the firm as well as individual experience in all categories. The submittal should include a BRIEF EXECUTIVE SUMMARY (maximum of 2 pages) as a cover to the submittal, summarizing all evaluation criteria: BE SURE TO SPECIFY WHO THE PROJECT MANAGER WILL BE IN THE EXECUTIVE SUMMARY. The consultant should focus their presentation toward the issues and needs that are unique to this project. Firms expressing interest in this project should demonstrate what special experience or attributes the firm/team has that makes it the most qualified for this project.

Upload: others

Post on 17-Oct-2021

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Reconstruction of Huguelet Drive Steam Vaults and Tunnel (Design Only)

University of Kentucky Project Number 2568.0

Consultant Submittal Guidelines & Executive Summary Page 1 of 6

Consultant Submittal Guidelines for the

Reconstruction of Huguelet Drive Steam Piping, Vaults and Tunnel (Design Only) for the UNIVERSITY OF KENTUCKY Main Campus PROJECT NO. 2568.0 The University of Kentucky is requesting the services of a consultant to provide design for the Reconstruction Huguelet Drive Steam, Piping, Vaults and Tunnel (Design Only) located on the University of Kentucky campus at the intersection of Huguelet Drive and Rose Street. The design team's SF330 submittal should include ONLY the names of individuals that will comprise the project team, clearly indicating the specific role each will play in the overall project from schematic design (Phase 1) through contract administration (Phase 5) should the project proceed to construction. This is necessary for the primary design firm as well as for each technical consultant that the prime firm plans to use on the project. The following list is the criteria, including the multiplication factors; by which each design team's submittal will be evaluated. Bearing this in mind, each team's submittal should clearly and thoroughly address all criteria to allow objective evaluation of the team's previous experience and capability to successfully complete this project. All submittals should be in .PDF format and GIVE SPECIFIC PROJECT EXAMPLES, including photographs, drawings, resumes, schedules, budget analyses, etc. to properly substantiate the firm as well as individual experience in all categories. The submittal should include a BRIEF EXECUTIVE SUMMARY (maximum of 2 pages) as a cover to the submittal, summarizing all evaluation criteria: BE SURE TO SPECIFY WHO THE PROJECT MANAGER WILL BE IN THE EXECUTIVE SUMMARY. The consultant should focus their presentation toward the issues and needs that are unique to this project. Firms expressing interest in this project should demonstrate what special experience or attributes the firm/team has that makes it the most qualified for this project.

Page 2: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Reconstruction of Huguelet Drive Steam Vaults and Tunnel (Design Only)

University of Kentucky Project Number 2568.0

Consultant Submittal Guidelines & Executive Summary Page 2 of 6

The University of Kentucky is dedicated to promoting minority participation in University work. Consultants are encouraged to consider using the services of minority sub-consulting firms where the demands of the project will permit. EVALUATION CRITERIA (Scoring for each category will be as indicated herein). The following criteria will be used in the evaluation of the submittals using an overall 100 point scale:

I. PROJECT MANAGER’S QUALIFICATIONS (35) The submittal should indicate the Project Manager’s experience with planning, managing and coordinating all aspects of a project of this scale and complexity, including the design, construction and remediation of steam vaults and tunnels containing mechanical infrastructure. The Project Manager should demonstrate expertise in addressing and successfully addressing aging steam systems in an efficient and creative manner. (Please include a maximum of three projects to demonstrate experience.) Project Manager should show commitment necessary to adequately manage and coordinate the project, including any sub-consultants, through all phases of research, design, contract documents and construction administration, maximizing project funds, while maintaining an aggressive project schedule. The submittal shall also provide the size and number of projects that the Project Manager is currently assigned to.

II. PRIMARY FIRM’S QUALIFICATIONS (35) The prime firm should have experience with large steam systems to include piping, valving

and supporting infrastructure. The firm shall demonstrate an ability to coordinate design team members and detail methods that will be used to ensure that the design schedule is met, including milestone and productivity monitoring. The submittal shall outline proven procedures for monitoring construction and resolving issues in the field as well as the organizational structure of the firm and the background of any individuals that will be assigned to this project. Special consideration will be given to experience in remediation of existing stream systems.

III. TEAM’S RELEVANT EXPERIENCE (30)

The team should include members with expertise history of design, construction and

remediation of concrete structures of various kinds. Members in of the consulting team should have a previously established working relationship. The team should demonstrate experience working together on similar projects. Include a list of projects highlighting this experience.

Page 3: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Reconstruction of Huguelet Drive Steam Vaults and Tunnel (Design Only)

University of Kentucky Project Number 2568.0

Consultant Submittal Guidelines & Executive Summary Page 3 of 6

The consultant should be careful to address each criterion, as neglect of any section will result in a lower total score for the firm. DO NOT ASSUME THOSE REVIEWING THE SUBMITTALS ARE ALREADY FAMILIAR WITH YOUR FIRM. Your presentation should be concise and to the point. Emphasis should be given to a few examples, which clearly show the team’s qualifications, rather than numerous examples, which are unrelated to the project. The proposers should take great care in compiling their written proposal, as the University reserves the right to make the award based on the written submittals. For further information concerning the scope of this project, contact Brian Hoerr, Project Manager, at (859) 218-3112

Please use the “Submit Proposal” button next to the project listed on CPMD’s website to submit your documents electronically in pdf format.

SUBMITTALS MUST BE RECEIVED NOT LATER THAN 3:00 PM EST, ON August 17, 2021.

Submittals received after this time will not be reviewed.

Page 4: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Reconstruction of Huguelet Drive Steam Vaults and Tunnel (Design Only)

University of Kentucky Project Number 2568.0

Consultant Submittal Guidelines & Executive Summary Page 4 of 6

Executive Summary for the

Reconstruction of Huguelet Drive Steam Piping, Vaults and Tunnel (Design Only) for the UNIVERSITY OF KENTUCKY Main Campus PROJECT NO. 2568.0 PROJECT SCOPE: $90,000 A. INTRODUCTION

This program presents in summary, the requirements for the preparation of design, construction documents and estimates for reconstruction/modification of the steam piping, vaults and tunnel at the intersection of Huguelet Drive and Rose Street in Lexington Kentucky on the campus of the University of Kentucky. The program is prepared as a basis for understanding and agreement within the University and as a definitive statement to the Consultant engaged in the design of the Reconstruction of Huguelet Drive Steam Piping, Vaults and Tunnel (Design Only) project. The University reserves the right to negotiate an extension of the contact to include construction administration after the design is complete and the project scope is established.

Page 5: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Reconstruction of Huguelet Drive Steam Vaults and Tunnel (Design Only)

University of Kentucky Project Number 2568.0

Consultant Submittal Guidelines & Executive Summary Page 5 of 6

B. PROJECT DESCRIPTION

In late June of 2021 structural engineers of Brown and Kubican completed an inspection of the steam vaults and tunnel at the request of University of Kentucky Physical Plant Division. A copy of the report resulting from this inspection is provided with this advertisement. The report describes water damage to both the concrete and steel members of the existing tunnel connecting two vaults which are deteriorated beyond the point of repair.

The purpose of this project is a complete evaluation of various possibilities for and the completion

of the reconstruction and/or replacement of the steam piping and vaults to include the protection or replacement of the existing steam piping and valving within. When a recommendation for the best and final solution for the reconstruction/replacement of the piping, vaults and tunnel has been detailed, the project will move forward immediately to design. The condition of the existing vaults and tunnel must be addressed at the earliest possible date.

The design will consist of preparation of Phase 1, 2 (if required), and 3 documents in accordance

with University standards and procedures.

C. PRELIMINARY PROJECT BUDGET

TOTAL CONSTRUCTION BUDGET* TBD

TOTAL PROJECT SCOPE $90,000

* The Consultant's Phase 1, 2 & 3 cost estimate submittals for the project are not to exceed this specified amount. Budget compatibility is the responsibility of the Consultant and design of the project beyond the available construction dollars listed above is unacceptable.

Page 6: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Reconstruction of Huguelet Drive Steam Vaults and Tunnel (Design Only)

University of Kentucky Project Number 2568.0

Consultant Submittal Guidelines & Executive Summary Page 6 of 6

D. PRELIMINARY PROJECT SCHEDULE The following is the tentative schedule presently proposed for this project:

8/3/21 Project Advertised for Consultant

8/17/21 Consultants' Submittals Due

8/19/21 Selection Committee Short List Meeting

9/9/21 Consultant Interviews

9/10/21 Consultant selected and notified

9/17/21 Contract negotiated

9/20/21 Begin Programming

10/11/21 Begin Phase 1 Design

TBD Program Review Meeting

TBD Phase 1 Documents submitted to CPMD

TBD Phase 1 Review Meeting

TBD Phase 2 documents submitted to CPMD

TBD Phase 2 Review Meeting

TBD Phase 3 documents submitted to CPMD

TBD Phase 3 Review Meeting

TBD Final Documents presented to CPMD

TBD Advertise

TBD Pre-Bid Conference

TBD Bid Date

TBD Contract Awarded

TBD Construction Begins

TBD Substantial Completion

TBD Final Completion

Page 7: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Structural Assessment of Existing Utility Tunnel Page 1 of 5

June 30, 2021 Mr. Graham Gray Utilites System Manager University of Kentucky Capital Project Management Division 211 Peterson Service Building Lexington, KY 40506 RE: Structural Assessment of Utility Tunnel at Rose/Huguelet (HPS 46 & 47)

University of Kentucky Lexington, Kentucky B+K Project No. 21195 Mr. Gray: As requested, we visited the site of the referenced structure on June 25, 2021. The purpose of our visit was to observe the reported deterioration of the existing utility tunnel at the intersection of Rose St and Huguelet Dr, determine the cause of the deterioration, assess the extent of the deterioration, and make recommendations. Our investigation was visual in nature and was limited to manholes HPS 46 & 47 and the tunnel between them. No other utility tunnel structure was investigated. Construction materials were not sampled or tested, and no calculations were performed. Photographs were taken to document existing conditions, some of which are included herein. Structural Description The tunnel was constructed circa 1998-99. The original construction drawings you provided for reference were dated November 9, 1998. The drawings indicated that the existing tunnel was constructed with 6 ft wide x 6 ft tall prefabricated concrete culvert segments that were delegated designed by the precast concrete supplier. Water-tight sealant and grout were required to seal the joints between the segments per the construction documents. Manholes HPS 46 & 47 at both ends of the tunnel were also made of prefabricated concrete units. According to the on-site conversation with your staff, no waterproofing was applied to the exterior surfaces of the tunnel or manholes during the construction. The tunnel was repaired and shored around 2017. The shoring/repair drawings you provided were prepared by BFMJ Consulting Structural Engineers. One set was the markups on the original drawings dated November 1, 2016, and the other set was the shoring drawings and photos dated April 2017. Based on the existing drawings, a galvanized steel frame should be installed at each joint between the existing concrete segments to support the tunnel ceiling slab. Each shoring frame consisted of (3) C12x31 channels, and they were connected to the ceiling slab and tunnel walls. The thickness of the ceiling slab and walls was likely to be 6 inches.

2224 Young Drive Lexington, KY 40505 www.brownkubican.net

Lexington ● Louisville

Page 8: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Structural Assessment of Existing Utility Tunnel Page 2 of 5

Observations During our visit, we made the following observations:

1. Existing Manhole HPS 46: We observed spalling concrete on the surface of both lower and upper sections of the vault. Reinforcing steel has corroded due to water (see photo 001). Continuous horizontal cracks were observed in the mid-lower part of the wall. We believe that it was caused by tension failure of the concrete from the applied lateral earth load (see photo 002).

Photo 001 – Manhole HP46

Spalling Concrete

Photo 002 – Manhole HP46

Continuous Horizontal Cracks

2. Tunnel Walls:

Existing concrete tunnel walls appear to be in good condition. See photo 003.

Photo 003 – Tunnel Wall

Page 9: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Structural Assessment of Existing Utility Tunnel Page 3 of 5

3. Existing Tunnel Ceiling Slabs: We observed a double-layer ½"± thick steel form deck below the concrete ceiling slab. It was not shown on either the original drawings or the repair drawings. The direction of the steel deck is parallel to the mechanical pipes and perpendicular to the shoring frames. We believe that the existing steel deck was added to support the deteriorated concrete ceiling slab during the repair in 2017. We observed that the deck is supported on the horizontal steel channel, and all the gaps at deck flutes were grouted solid (see photo 005). The existing deck is severely corroded due to water along the whole tunnel (see photo 004) except for a small portion in the middle of the tunnel (see photo 006). Most parts of the existing concrete ceiling slab were concealed by the corroded steel deck, but the exposed part and the end view of the slab both showed severe water damage, such as spalling concrete and corroded reinforcing steel (see photos 007 & 004).

Photo 004 – Tunnel Ceiling Slab

Corroded deck fell and exposed deteriorated concrete slab above.

Photo 005 – Tunnel Ceiling Slab

Corroded deck is supported on steel channel with gaps at deck flutes being grouted.

Photo 006 – Tunnel Ceiling Slab

Only a small portion of the existing deck appears to be less damaged by water.

Photo 007 – End View of Tunnel Ceiling Slab

The reinforcing steel of the ceiling slab has severely corroded.

Page 10: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Structural Assessment of Existing Utility Tunnel Page 4 of 5

4. Existing Manhole HPS 47: We observed spalling concrete on the bottom surface of the soffit slab. Most of the existing concrete below the slab rebar has fallen, and the slab rebar is exposed and severely corroded. A wide crack was observed right above the soffit slab, and we believe it was due to concrete failure from the lateral earth load (see photo 008). Corroded reinforcing steel was observed at the wall surface (see photo 009).

Photo 008 – Manhole HP47

Photo 009 – Manhole HP47

5. Existing Steel Shoring Structure:

Based on the existing drawings, all the steel shoring frame members and connectors should be hot-dipped galvanized. We found the vertical channels connected to the existing walls appear to be in better condition than the horizontal channels connected to the ceiling slabs or walls.

The channels supporting the steel form deck have corroded on their top and side surfaces (see photo 010). Many adhesive anchors mounted to the existing ceiling slab have corroded and fallen (see photo 011).

Photo 010 – Existing Shoring Beams

Corroded Shoring Beams

Photo 011 – Existing Shoring Beams

Failed Existing Anchors

Page 11: Reconstruction of Huguelet Drive Steam Piping, Vaults and

Structural Assessment of Existing Utility Tunnel Page 5 of 5

The adhesive adhesive anchors connecting the channel to the manhole wall have corroded (see photo 012). A reinforcing steel plate (supposed to be a tube beam per the repair drawings) with its anchors at the end of the tunnel has severely corroded (see photo 013).

Photo 012 – Existing Shoring Beam

Corroded Existing Anchors

Photo 013 – Existing Shoring Beam

Corroded Reinforcing Plate and Anchors

Recommendations It appears that the water damage in both concrete components and steel shoring members of the existing tunnel has developed since the repair in 2017, and the situation will only become worse. It is our opinion that the existing concrete tunnel has deteriorated beyond the point of repair, and it should be demolished, backfilled, or reconstructed as soon as possible. We strongly suggest staying away from the existing tunnel for safety concerns. The existing manholes HPS 46 & 47 were made of precast concrete units. We observed spalling concrete, exposed reinforcing steel, and wide cracks in both vaults, which indicated local structural failures. We recommend that both of them be demolished and reconstructed. We would be glad to be involved in any future project related to this assessment if possible. We can prepare construction documents and provide construction administration services for the potential project upon request. If you have any questions or if we can be of any further assistance, please call. Best regards,

Jay Zheng Wang, PE Principal Copy: Project file