recruitment of the new ltpp sps-10: warm mix asphalt experiment
DESCRIPTION
Recruitment of the New LTPP SPS-10: Warm Mix Asphalt Experiment. Gabe Cimini LTPP NCRSC Project Manager. Presentation Outline. LTPP Approach to WMA Research Site Requirements Roles and Responsibilities SPS-10 Nomination Process. Why WMA?. 356 million tons of WMA produced in 2012 - PowerPoint PPT PresentationTRANSCRIPT
Recruitment of the New LTPP SPS-10:Warm Mix Asphalt Experiment
Gabe Cimini LTPP NCRSC Project Manager
Presentation Outline
• LTPP Approach to WMA Research• Site Requirements• Roles and Responsibilities• SPS-10 Nomination Process
Why WMA?
• 356 million tons of WMA produced in 2012– 24% of all plant mix produced in US was WMA
• 35 different WMA technologies• WMA is a priority innovation under FHWA’s Every
Day Counts (EDC) Initiative
Objectives
• Long-term performance of WMA relative to HMA• Capture data on WMA with RAP
Benefits to Agencies• Detailed construction information including a
construction report• Rigorous materials testing (over multiple
intervals) using latest testing technology• Ongoing FWD, distress, profile, and texture
monitoring to study short and long term performance
• Ability to study Agency-specific issues related to WMA
SPS-10 Requirements
• Overview– AC overlay of existing AC pavements– 2” to 4” overlay thickness– Dense graded mix– RAP content 10-25% (binder replacement)– 1 HMA control test section– 2 WMA test sections
• Foaming Process• Chemical Additive
– Tack Coats between lifts
Site Layout Requirements
• WMA:– Production of ≤ 275°F or– Production at least 30°F less than HMA
Existing Pavement Requirements
• Uniformity– Subgrade type/condition– Base thickness/type– Bound layer thickness/type– Surface condition– Traffic loading– Pre-overlay repairs based on Highway Agency’s
standard practice
Experiment Layer Requirements
• Mix design/binder grade selection based on Agency’s standard practice
• Overlay thickness selected by Agency’s standard practice
• Uniformity between HMA and WMA– Same binder source/grade– Same aggregate source/gradations– Mix design/JMF
Supplemental Sections
• Agencies can build additional test sections that will be monitored as part of the LTPP program– Varying levels of RAP– Additional WMA technologies– Layer thickness variation– Open or gap graded mixtures– Varying aggregate sources/absorption levels– Other variables of interest to Agency
Roles/Responsibilities
• Agencies– Nominate project(s)– Validate in-situ conditions– Submit inventory data– Develop plans, specifications, mix design– Provide construction and
inspection/control/management – Perform materials sampling/patching– Collect traffic data– Provide traffic control
Sampling Areas (Draft)Coring at 0, 6, 12 and 18 months after construction
Traffic Data Collection Guidelines• Quality traffic data is critical in assessing the vehicle loading on
pavements– Permanently mounted sensors whenever possible– As long as a documented calibration plan is followed, data from both
portable and permanent equipment will be accepted (required LTPP Traffic Sheet 16 – Site calibration summary)
– The agency should plan to repair faulty equipment within 1 month– At a minimum, 2 weeks of continuous classification data 4 times per year
(a total of 8 weeks of classification data)– Data to be submitted by the agency on a monthly basis, however, the data
will be accepted if submitted quarterly as well – If a WMA test site does not have weight data, then the agency must
submit an LTPP Traffic Sheet 10 (Traffic volume and load estimate). Submitting 1 Sheet 10 per year is sufficient
Roles/Responsibilities• FHWA– Develop experimental
design/research plan– Coordinate among Agencies– Oversee construction data collection– Perform materials testing– Provide materials sampling support– Collect performance monitoring data– Store, analyze, and report data
3
LTPP Data & Information
Climate Load
Materials
Structure
Response
Distress
Nomination Process• FHWA accepting nominations now • Projects to be constructed in 2014 and 2015• Nomination forms are available from FHWA and
the LTPP Regional Support Contractors (RSCs)• FHWA will evaluate nominations and notify
Agencies• Coordination through LTPP RSCs
Additional Tests on Materials
• Material Testing somewhat limited• Additional information beneficial on national level• Agencies encouraged to perform additional tests• Recommended by the FHWA Asphalt Mixture
Expert Task Group, based upon NCHRP Research Results Digest 370:
Additional Tests on Materials Flow Number (AMPT)
AASHTO TP 79
Hamburg TestAASHTO T 324 (Note: Prepare specimens at air voids content of 7±1% and conduct test at standard conditions: 50°C under water.)
APA AASHTO T 340Dynamic Modulus (AMPT) AASHTO PP 61Beam Fatigue AASHTO T 321
Overlay Test TxDOT Method: Tex-248-F, Test Procedure for Overlay Test, February 2014
Simplified Viscoelastic Continuum Damage (S VECD)‑ AASHTO TP 107Superpave Indirect Tension Test (IDT) University of FloridaSemi-Circular Bending Test at Intermediate Temperatures Louisiana Transportation Research Center (LTRC)IDT Creep Compliance and Strength AASHTO T 322Semi-Circular Bending Test AASHTO TP 105Disk Shaped Compact Tension – DC(T) Test ASTM D7313Moisture Sensitivity AASHTO T 283 (Note: 1 Freeze/Thaw cycle)Volumetric Properties AASHTO R 35Gyratory Compaction to Ndesign AASHTO T 312
Name Agency Phone Email
Jack Springer
FHWA-LTPP 202.493.3144 [email protected]
Gabe Cimini
North Central RSC
716.632.0804 EXT. 7470
Contact Information
19