Red and Bonita Mine Site – Photos 2015 Mucking Operation Water Treatment Ongoing operations to manage the 500 gpm flow while the underground is mucked out to the bulkhead area at approximately 300 feet. The mine crew had mucked about 80 feet as of July 23, so we’re about on schedule and hope to increase the rate of production now that we have the treatment system tuned. Retention/settling pond below waste dump – receiving mine water during underground operations July 21, 2015

Upload: others

Post on 12-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Red and Bonita Mine Site – Photos 2015 · 7/24/2015  · Red and Bonita Mine removal action photo log, July 24, 2015 Author: US EPA, Region 8, EPR-Emergency Response Subject: Upper

Red and Bonita Mine Site – Photos 2015

Mucking Operation Water Treatment

Ongoing operations to manage the 500 gpm flow while the underground is mucked out to the bulkhead area at approximately 300 feet. The mine crew had mucked about 80 feet as of July 23, so we’re about on schedule and hope to increase the rate of production now that we have the treatment system tuned.

Retention/settling pond below waste dump – receiving mine water during underground operations July 21, 2015

Page 2: Red and Bonita Mine Site – Photos 2015 · 7/24/2015  · Red and Bonita Mine removal action photo log, July 24, 2015 Author: US EPA, Region 8, EPR-Emergency Response Subject: Upper

Pond preparation – expanded first cell and raising berms for increased storage

Page 3: Red and Bonita Mine Site – Photos 2015 · 7/24/2015  · Red and Bonita Mine removal action photo log, July 24, 2015 Author: US EPA, Region 8, EPR-Emergency Response Subject: Upper

Headgates and pipe to pond

Page 4: Red and Bonita Mine Site – Photos 2015 · 7/24/2015  · Red and Bonita Mine removal action photo log, July 24, 2015 Author: US EPA, Region 8, EPR-Emergency Response Subject: Upper

Pond lined with geo-textile fabric and filter bag system set up to west

Page 5: Red and Bonita Mine Site – Photos 2015 · 7/24/2015  · Red and Bonita Mine removal action photo log, July 24, 2015 Author: US EPA, Region 8, EPR-Emergency Response Subject: Upper

Sodium hydroxide addition upstream and flocculent addition below – pH raised from @ 3 su to 7 su

Page 6: Red and Bonita Mine Site – Photos 2015 · 7/24/2015  · Red and Bonita Mine removal action photo log, July 24, 2015 Author: US EPA, Region 8, EPR-Emergency Response Subject: Upper

Mine water redirected to the settling pond during operations underground and treatment

Page 7: Red and Bonita Mine Site – Photos 2015 · 7/24/2015  · Red and Bonita Mine removal action photo log, July 24, 2015 Author: US EPA, Region 8, EPR-Emergency Response Subject: Upper

Discharge from pond after settling without filtering – lower turbidity than pre-work

Page 8: Red and Bonita Mine Site – Photos 2015 · 7/24/2015  · Red and Bonita Mine removal action photo log, July 24, 2015 Author: US EPA, Region 8, EPR-Emergency Response Subject: Upper

Mine water treatment and water clarification through the cells of the pond – July 23, 2015