red line nordic rail 2011eng
TRANSCRIPT
-
8/3/2019 Red Line Nordic Rail 2011Eng
1/30
Ansaldo STS Sweden
03/05/2012
Resignalling of Stockholm
Underground Red Line. From relay technology toCBTC without traffic closures
Lucas Orve, CBTC conference 2011-11-08
-
8/3/2019 Red Line Nordic Rail 2011Eng
2/30
03/05/2012
Ansaldo STS Sweden
AGENDA
Introduction
Technical principles, System Architecture CBTC Interlocking Traffic Control Centre Onboard systems
Migration strategy Summary Questions
-
8/3/2019 Red Line Nordic Rail 2011Eng
3/30
Ansaldo STS Sweden
Introduction, Technical principles, Systemarchitecture
03/05/2012
-
8/3/2019 Red Line Nordic Rail 2011Eng
4/30
03/05/2012
Ansaldo STS Sweden
RED LINE GENERAL (1)
General:
First commissioning: 1964 Stations: 35 Total track length: 39,7 km Train positioning: ~640 track circuits Signalling system: Relay technology
Cab signsalling: 75 Hz coded track circuit(15, 50, 80 km/h) Traffic Control: Control panel with fixed
buttons, located at Liljeholmen
Multiwire communication with peripheralequipment housings/rooms along line
Procurement process: RFQ new system 2009 Notice of award November 2010 Formal T0 May 2011
-
8/3/2019 Red Line Nordic Rail 2011Eng
5/30
03/05/2012
Ansaldo STS Sweden
RED LINE GENERAL (2)
New system:
Communication Based Train Control(CBTC)
Computerised Traffic Control Centre withworkstations Datorbaserad
Transponders for train positioning
Axle counters for train detection Optical signals, mainly for protection ofpoints and non-equipped trains
New signal aspect
Redundant communication system WIFI communication with access points Existing track circuits retained up to
(including) MIxed Mode Existing cab codes retained up to (including)
MIxed Mode High level of flexibility in the project planning
-
8/3/2019 Red Line Nordic Rail 2011Eng
6/30
03/05/2012
Ansaldo STS Sweden
RED LINE GENERAL (3)
System overview
-
8/3/2019 Red Line Nordic Rail 2011Eng
7/30
Ansaldo STS Sweden
CBTC
03/05/2012
-
8/3/2019 Red Line Nordic Rail 2011Eng
8/30
03/05/2012
Ansaldo STS Sweden
CBTC
Train positioning based on transponders and radio communication
Radio block for metros and similar applications requiring a highlevel of capacity
Radio Block Centres (RBC:s); Zone Controller (ZC)
Coarse subdivision into fixed blocks, based on axle counters: Protection for non-equipped trains
Simplifies startup and operation under irregular conditions Allows interfacing with existing cabsignalling system
Flexible block separation:
Overlay on existing blocks Increased block resolution to
Moving Block Adaptation to individual conditions
-
8/3/2019 Red Line Nordic Rail 2011Eng
9/30
03/05/2012
Ansaldo STS Sweden
The functions moving block
Fixed blockprinciple
Moving blockprinciple
CBTC
-
8/3/2019 Red Line Nordic Rail 2011Eng
10/30
Ansaldo STS Sweden
Interlocking
03/05/2012
-
8/3/2019 Red Line Nordic Rail 2011Eng
11/30
03/05/2012
Ansaldo STS Sweden
INTERLOCKING
Microlok II from Ansaldo STS US Inc
(Union Switch & Signal Inc, Pittsburg, USA) Distributed architecture Interfaces with Zone Controller (ZC) Interfaces with the existing interlocking at the
system border
Interfaces with code generators for cabsignalling (up until, including, Mixed Mode) Advanced tools for configuration and
maintenance
Same supplier as existing system Microlok II well adapted to this type of
applications
-
8/3/2019 Red Line Nordic Rail 2011Eng
12/30
Ansaldo STS Sweden
TRAFFIC CONTROL CENTRE (TCC)
03/05/2012
-
8/3/2019 Red Line Nordic Rail 2011Eng
13/30
03/05/2012
Ansaldo STS Sweden
TRAFFIC CONTROL CENTRE (TCC)
Computer based architecture with workstations and overview screen
Previous generation in use in e. g. Copenhagen Metro Functions (examples)
Train positioning Automatic operation, based on time
table, algorithms and conflict resolution Local macros
Manual control Playback Event handling and recording Alarm handling and recording Simulation for test and training Support functions
Interface with external systems for control of third rail, tunnel lightning,fans, passenger information systems, etc.
-
8/3/2019 Red Line Nordic Rail 2011Eng
14/30
Ansaldo STS Sweden
ATP ONBOARD FOR CBTC
03/05/2012
-
8/3/2019 Red Line Nordic Rail 2011Eng
15/30
03/05/2012
Ansaldo STS Sweden
ATP ONBOARD FOR CBTC
Proven platform from Ansaldo STS
Wide spectrum of onboard applications and installations Simple cutover Installation in parallel with existing cab signalling (up unitil,
including, Mixed Mode) Full supervision of warning curves and braking curves
ATO Upgradeable to UTO (Unmanned Train Operation)
-
8/3/2019 Red Line Nordic Rail 2011Eng
16/30
Ansaldo STS Sweden
MIGRATION STRATEGY
03/05/2012
-
8/3/2019 Red Line Nordic Rail 2011Eng
17/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
GENERAL
New communication paths to peripheral locations to be establishedas soon as possible
Traffic Control to be transferred as early as possible The new signalling system, based on CBTC, to be installed and
tranferred station-by-station
Track circuits and cab code generators are retained at this stage New ATP system for CBTC will gradually be installed on board trains,in parallel with existing cab signalling
Mixed mode means that the whole line has been moved to CBTC,
but allows (by means of the cab signalling codes) operation alsousing existing cab sinalling onboard system.
When all trains have been fitted with the new ATP for CBTC, then thecode generators and track circuits can be decommissioned
The final step will be to introduce new block separation, includingMoving Bliock, by means of configuration.
A ld STS S d
-
8/3/2019 Red Line Nordic Rail 2011Eng
18/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
COMMUNICATION: Communication with peripheral rooms
and equipment houses is established asearly in the project as possible, by meansof a Data Communication System (DCS)
This system is controlled from a centrallylocated DCS server
Coordinated with establishing the DCS,other fierld works are undertaken, inparticular cable laying.
New local interlocking systems are thendeployed in the existing peripheral
rooms, including interfaces for controlsand indications
This is followed by preparations for connecting existing track circuitsand code generators
Installation of radio base stations for Zone Controllers
A ld STS S d
-
8/3/2019 Red Line Nordic Rail 2011Eng
19/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
COMMUNICATION OBJECTIVES:
Cabling and other field works completed as early as possible Making sure that communication paths are already available, in
preparation of subsequent phases Establishing interfaces with existing signalling systems, allowing
maximum flexibility in the planning
Wayside Backbone NetworkFully redundant
Train network B
MRU BMRU A
RBS-Backhaul A
RBS A RBS A
MST A
Train network A
DRCU A DRCU B
application
MRCU BMST B
RBS A
application
MRCU A
RBS-Backhaul B
RBS B RBS BRBS B
CRCU
Central SignalingEquipment
Wayside SignalingEquipment
Carborne Controller
StationaryRadio Network
application
Ansaldo STS S eden
-
8/3/2019 Red Line Nordic Rail 2011Eng
20/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
TRAFFIC CONTROL CENTRE
The first step is to install and commission the new Traffic ControlCentre, using new computer control technologies
This new TCC is then connected to the existing signalling system atthe pace permitted by the field works for the DCS (phase 1).
The goal is to transfer control and staff to the new system as soon as
possible This means that the existing TCC can be decommissioned early inthe project, irrespective of the old interlocking systems still being inuse
New line sections are then progressively cut over to the newinterlocking system under CBTC. This is of course coordinated with
the corresponding transfer of control. This arrangement means that the border between new/old
interlocking can gradullay be moved without any major effect on thecontrol. principles
Ansaldo STS Sweden
-
8/3/2019 Red Line Nordic Rail 2011Eng
21/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
TRAFFIC CONTROL SYSTEM OBJECTIVES
Staff is trained and allowed to acquire expereince wit controlprinciples early in the project
Any potential shortcoming in the TCC are detected early A very large degree of independence is established relative to other
parts of the systemStort mtt av oberoende, relativt vriga delar
Ability to test and verify the new control system prior to cutover Abilityto perform cutover in steps Back-door in case of
unexpected problems Low project risk
Ansaldo STS Sweden
-
8/3/2019 Red Line Nordic Rail 2011Eng
22/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
INTERLOCKING SYSTEM Zone Controllers (ZC) are installed in a limited number of locations
along the track. In the existing peripheral locations along the line, the following
systems are progressively installed: Microlok II for control of signals, points axle counters, etc Interface circuits for indications from existing track circuits (to enable a
smooth transition) In addition to this, the existing circuits for cab code generation will be
retained
When a line section is ready, then this will be commissioned. This is(of course) coordinated with the correspondig transfer of control
Transponders (balises) are then deployed along the line
Initially, the new CBTC system will use the same block separation asemployed by the existing track circuits
Because cab signalling codes are still transmitted, it is still possible tooperate a train with the existing onboard system
Because the new system receives information from the existing trtack
circuits, these can be treated as blocks under CBTC
Ansaldo STS Sweden
-
8/3/2019 Red Line Nordic Rail 2011Eng
23/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
INTERLOCKING SYSTEM OBJECTIVES
Interlocking is installed and commissioned in stages, resulting in lowproject risk
Initially, the new signalling system will receive track occupancyinformation also rom the existing track circuits, enabling positioning ofall trains, even if not fitted with the new ATP under CBTC
In a similar manner, trains with existing cab singalling will receive cabcodes, and will thus be capable of operating on the same line section
This allows trains of both categories (old cab signalling or new CBTC)to operate on a converted section.
However, for logistic reasons, this facility will not be used until theentire line has been converted. This stage is referredto as Mixed
Mode, underwhich trainswith old and newonboard systems willbe able to operate independantly
Mixed Mode provides an exceptional high degree of flexibility in thetransition
Ansaldo STS Sweden
-
8/3/2019 Red Line Nordic Rail 2011Eng
24/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
ONBOARD SYSTEM
New onboard system will be installed in parallel with existing cabsignalling
System selection will be a manual procedure on startup During the first part of the project up until and including MIxed Mode
the existing cab signalling can be used During the projects latter part, starting from Mixed Mode, the new
ATP under CBTC can be used During Mixed Mode, either of the systems can be activated
New signalling aspect to indicate route set, but subsequent blocks(up to next signal) occupied. This is to allow an increased level of
flexibility, when operating trains without active ATP or immediatelyafter restart of the system.
Ansaldo STS Sweden
-
8/3/2019 Red Line Nordic Rail 2011Eng
25/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
ONBOARD SYSTEM OBJECTIVES:
Onboard systems can be installed under a very high degree ofindependence, relative to other project activities
Up until the time when the old cab signalling is dismantled, trains canoperate also on theBlueandGreenlines
DuringMixed Modeeither of the systems can be There is requirement for all trains to be fitted with the new system,
until endof Mixed Mode New signalling aspect will increase safety and improve capacity, in
particular when operating a non-equipped
Ansaldo STS Sweden
-
8/3/2019 Red Line Nordic Rail 2011Eng
26/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
MIXED MODE:
Mixed mode means that the whole line is converted into CBTC Track circuits and cab codes will nevertheless be retained, in order to
allow operation of trains with old cab signalling Only the old cab signalling will be used up until start of Mixed Mode
(except test trains) During Mixed Mode, the driver will select which system to activate as
part of the startup procedure (governed by SLs strategy, driver
training, etc It is of course possible to operate a train which has not yet been fitted
with the new ATP under CBTC (and also the opposite) Mixed Mode is terminated by decommissioning track circuits and cab
code generators This means that all trains must be fitted with the ATP, in order to exit
Mixed Mode
Ansaldo STS Sweden
-
8/3/2019 Red Line Nordic Rail 2011Eng
27/30
03/05/2012
Ansaldo STS Sweden
MIGRATION STRATEGY
MIXED MODE OBJECTIVES:
Mixed Moderepresents a state of complete flexibility This provides room for tailoring the onboard installation schedule,
training program, etc MIxed Mode can be extended in time, should this be required due to
unforeseen events
Ansaldo STS Sweden
-
8/3/2019 Red Line Nordic Rail 2011Eng
28/30
03/05/2012
sa do S S S ede
MIGRATION STRATEGY
SUMMARY
The focus of the Migration Strategy is to provide maximum flexibilityand independence between the different project activities
Should unexpeted events necessitate this, there is always a back
door, by which the project can back up to a previous state During Mixed Mode, all types of trains can operate on the line, thus
providing optimal flexibility
A new signal aspect will increase safety and flexibility, especiallywhen operatin non-equipped trains
Up until the time when the old cab signalling is dismantled, trains canoperate also on the Blue and Green lines
In the final stages, blocks will be shortened, in order to establishmoving block
Ansaldo STS Sweden
-
8/3/2019 Red Line Nordic Rail 2011Eng
29/30
Questions?
03/05/2012
?
?
?
?
?
??
?
? ?
-
8/3/2019 Red Line Nordic Rail 2011Eng
30/30