red line nordic rail 2011eng

Upload: dkalatzis

Post on 06-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    1/30

    Ansaldo STS Sweden

    03/05/2012

    Resignalling of Stockholm

    Underground Red Line. From relay technology toCBTC without traffic closures

    Lucas Orve, CBTC conference 2011-11-08

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    2/30

    03/05/2012

    Ansaldo STS Sweden

    AGENDA

    Introduction

    Technical principles, System Architecture CBTC Interlocking Traffic Control Centre Onboard systems

    Migration strategy Summary Questions

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    3/30

    Ansaldo STS Sweden

    Introduction, Technical principles, Systemarchitecture

    03/05/2012

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    4/30

    03/05/2012

    Ansaldo STS Sweden

    RED LINE GENERAL (1)

    General:

    First commissioning: 1964 Stations: 35 Total track length: 39,7 km Train positioning: ~640 track circuits Signalling system: Relay technology

    Cab signsalling: 75 Hz coded track circuit(15, 50, 80 km/h) Traffic Control: Control panel with fixed

    buttons, located at Liljeholmen

    Multiwire communication with peripheralequipment housings/rooms along line

    Procurement process: RFQ new system 2009 Notice of award November 2010 Formal T0 May 2011

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    5/30

    03/05/2012

    Ansaldo STS Sweden

    RED LINE GENERAL (2)

    New system:

    Communication Based Train Control(CBTC)

    Computerised Traffic Control Centre withworkstations Datorbaserad

    Transponders for train positioning

    Axle counters for train detection Optical signals, mainly for protection ofpoints and non-equipped trains

    New signal aspect

    Redundant communication system WIFI communication with access points Existing track circuits retained up to

    (including) MIxed Mode Existing cab codes retained up to (including)

    MIxed Mode High level of flexibility in the project planning

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    6/30

    03/05/2012

    Ansaldo STS Sweden

    RED LINE GENERAL (3)

    System overview

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    7/30

    Ansaldo STS Sweden

    CBTC

    03/05/2012

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    8/30

    03/05/2012

    Ansaldo STS Sweden

    CBTC

    Train positioning based on transponders and radio communication

    Radio block for metros and similar applications requiring a highlevel of capacity

    Radio Block Centres (RBC:s); Zone Controller (ZC)

    Coarse subdivision into fixed blocks, based on axle counters: Protection for non-equipped trains

    Simplifies startup and operation under irregular conditions Allows interfacing with existing cabsignalling system

    Flexible block separation:

    Overlay on existing blocks Increased block resolution to

    Moving Block Adaptation to individual conditions

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    9/30

    03/05/2012

    Ansaldo STS Sweden

    The functions moving block

    Fixed blockprinciple

    Moving blockprinciple

    CBTC

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    10/30

    Ansaldo STS Sweden

    Interlocking

    03/05/2012

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    11/30

    03/05/2012

    Ansaldo STS Sweden

    INTERLOCKING

    Microlok II from Ansaldo STS US Inc

    (Union Switch & Signal Inc, Pittsburg, USA) Distributed architecture Interfaces with Zone Controller (ZC) Interfaces with the existing interlocking at the

    system border

    Interfaces with code generators for cabsignalling (up until, including, Mixed Mode) Advanced tools for configuration and

    maintenance

    Same supplier as existing system Microlok II well adapted to this type of

    applications

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    12/30

    Ansaldo STS Sweden

    TRAFFIC CONTROL CENTRE (TCC)

    03/05/2012

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    13/30

    03/05/2012

    Ansaldo STS Sweden

    TRAFFIC CONTROL CENTRE (TCC)

    Computer based architecture with workstations and overview screen

    Previous generation in use in e. g. Copenhagen Metro Functions (examples)

    Train positioning Automatic operation, based on time

    table, algorithms and conflict resolution Local macros

    Manual control Playback Event handling and recording Alarm handling and recording Simulation for test and training Support functions

    Interface with external systems for control of third rail, tunnel lightning,fans, passenger information systems, etc.

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    14/30

    Ansaldo STS Sweden

    ATP ONBOARD FOR CBTC

    03/05/2012

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    15/30

    03/05/2012

    Ansaldo STS Sweden

    ATP ONBOARD FOR CBTC

    Proven platform from Ansaldo STS

    Wide spectrum of onboard applications and installations Simple cutover Installation in parallel with existing cab signalling (up unitil,

    including, Mixed Mode) Full supervision of warning curves and braking curves

    ATO Upgradeable to UTO (Unmanned Train Operation)

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    16/30

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    03/05/2012

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    17/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    GENERAL

    New communication paths to peripheral locations to be establishedas soon as possible

    Traffic Control to be transferred as early as possible The new signalling system, based on CBTC, to be installed and

    tranferred station-by-station

    Track circuits and cab code generators are retained at this stage New ATP system for CBTC will gradually be installed on board trains,in parallel with existing cab signalling

    Mixed mode means that the whole line has been moved to CBTC,

    but allows (by means of the cab signalling codes) operation alsousing existing cab sinalling onboard system.

    When all trains have been fitted with the new ATP for CBTC, then thecode generators and track circuits can be decommissioned

    The final step will be to introduce new block separation, includingMoving Bliock, by means of configuration.

    A ld STS S d

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    18/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    COMMUNICATION: Communication with peripheral rooms

    and equipment houses is established asearly in the project as possible, by meansof a Data Communication System (DCS)

    This system is controlled from a centrallylocated DCS server

    Coordinated with establishing the DCS,other fierld works are undertaken, inparticular cable laying.

    New local interlocking systems are thendeployed in the existing peripheral

    rooms, including interfaces for controlsand indications

    This is followed by preparations for connecting existing track circuitsand code generators

    Installation of radio base stations for Zone Controllers

    A ld STS S d

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    19/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    COMMUNICATION OBJECTIVES:

    Cabling and other field works completed as early as possible Making sure that communication paths are already available, in

    preparation of subsequent phases Establishing interfaces with existing signalling systems, allowing

    maximum flexibility in the planning

    Wayside Backbone NetworkFully redundant

    Train network B

    MRU BMRU A

    RBS-Backhaul A

    RBS A RBS A

    MST A

    Train network A

    DRCU A DRCU B

    application

    MRCU BMST B

    RBS A

    application

    MRCU A

    RBS-Backhaul B

    RBS B RBS BRBS B

    CRCU

    Central SignalingEquipment

    Wayside SignalingEquipment

    Carborne Controller

    StationaryRadio Network

    application

    Ansaldo STS S eden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    20/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    TRAFFIC CONTROL CENTRE

    The first step is to install and commission the new Traffic ControlCentre, using new computer control technologies

    This new TCC is then connected to the existing signalling system atthe pace permitted by the field works for the DCS (phase 1).

    The goal is to transfer control and staff to the new system as soon as

    possible This means that the existing TCC can be decommissioned early inthe project, irrespective of the old interlocking systems still being inuse

    New line sections are then progressively cut over to the newinterlocking system under CBTC. This is of course coordinated with

    the corresponding transfer of control. This arrangement means that the border between new/old

    interlocking can gradullay be moved without any major effect on thecontrol. principles

    Ansaldo STS Sweden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    21/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    TRAFFIC CONTROL SYSTEM OBJECTIVES

    Staff is trained and allowed to acquire expereince wit controlprinciples early in the project

    Any potential shortcoming in the TCC are detected early A very large degree of independence is established relative to other

    parts of the systemStort mtt av oberoende, relativt vriga delar

    Ability to test and verify the new control system prior to cutover Abilityto perform cutover in steps Back-door in case of

    unexpected problems Low project risk

    Ansaldo STS Sweden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    22/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    INTERLOCKING SYSTEM Zone Controllers (ZC) are installed in a limited number of locations

    along the track. In the existing peripheral locations along the line, the following

    systems are progressively installed: Microlok II for control of signals, points axle counters, etc Interface circuits for indications from existing track circuits (to enable a

    smooth transition) In addition to this, the existing circuits for cab code generation will be

    retained

    When a line section is ready, then this will be commissioned. This is(of course) coordinated with the correspondig transfer of control

    Transponders (balises) are then deployed along the line

    Initially, the new CBTC system will use the same block separation asemployed by the existing track circuits

    Because cab signalling codes are still transmitted, it is still possible tooperate a train with the existing onboard system

    Because the new system receives information from the existing trtack

    circuits, these can be treated as blocks under CBTC

    Ansaldo STS Sweden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    23/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    INTERLOCKING SYSTEM OBJECTIVES

    Interlocking is installed and commissioned in stages, resulting in lowproject risk

    Initially, the new signalling system will receive track occupancyinformation also rom the existing track circuits, enabling positioning ofall trains, even if not fitted with the new ATP under CBTC

    In a similar manner, trains with existing cab singalling will receive cabcodes, and will thus be capable of operating on the same line section

    This allows trains of both categories (old cab signalling or new CBTC)to operate on a converted section.

    However, for logistic reasons, this facility will not be used until theentire line has been converted. This stage is referredto as Mixed

    Mode, underwhich trainswith old and newonboard systems willbe able to operate independantly

    Mixed Mode provides an exceptional high degree of flexibility in thetransition

    Ansaldo STS Sweden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    24/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    ONBOARD SYSTEM

    New onboard system will be installed in parallel with existing cabsignalling

    System selection will be a manual procedure on startup During the first part of the project up until and including MIxed Mode

    the existing cab signalling can be used During the projects latter part, starting from Mixed Mode, the new

    ATP under CBTC can be used During Mixed Mode, either of the systems can be activated

    New signalling aspect to indicate route set, but subsequent blocks(up to next signal) occupied. This is to allow an increased level of

    flexibility, when operating trains without active ATP or immediatelyafter restart of the system.

    Ansaldo STS Sweden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    25/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    ONBOARD SYSTEM OBJECTIVES:

    Onboard systems can be installed under a very high degree ofindependence, relative to other project activities

    Up until the time when the old cab signalling is dismantled, trains canoperate also on theBlueandGreenlines

    DuringMixed Modeeither of the systems can be There is requirement for all trains to be fitted with the new system,

    until endof Mixed Mode New signalling aspect will increase safety and improve capacity, in

    particular when operating a non-equipped

    Ansaldo STS Sweden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    26/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    MIXED MODE:

    Mixed mode means that the whole line is converted into CBTC Track circuits and cab codes will nevertheless be retained, in order to

    allow operation of trains with old cab signalling Only the old cab signalling will be used up until start of Mixed Mode

    (except test trains) During Mixed Mode, the driver will select which system to activate as

    part of the startup procedure (governed by SLs strategy, driver

    training, etc It is of course possible to operate a train which has not yet been fitted

    with the new ATP under CBTC (and also the opposite) Mixed Mode is terminated by decommissioning track circuits and cab

    code generators This means that all trains must be fitted with the ATP, in order to exit

    Mixed Mode

    Ansaldo STS Sweden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    27/30

    03/05/2012

    Ansaldo STS Sweden

    MIGRATION STRATEGY

    MIXED MODE OBJECTIVES:

    Mixed Moderepresents a state of complete flexibility This provides room for tailoring the onboard installation schedule,

    training program, etc MIxed Mode can be extended in time, should this be required due to

    unforeseen events

    Ansaldo STS Sweden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    28/30

    03/05/2012

    sa do S S S ede

    MIGRATION STRATEGY

    SUMMARY

    The focus of the Migration Strategy is to provide maximum flexibilityand independence between the different project activities

    Should unexpeted events necessitate this, there is always a back

    door, by which the project can back up to a previous state During Mixed Mode, all types of trains can operate on the line, thus

    providing optimal flexibility

    A new signal aspect will increase safety and flexibility, especiallywhen operatin non-equipped trains

    Up until the time when the old cab signalling is dismantled, trains canoperate also on the Blue and Green lines

    In the final stages, blocks will be shortened, in order to establishmoving block

    Ansaldo STS Sweden

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    29/30

    Questions?

    03/05/2012

    ?

    ?

    ?

    ?

    ?

    ??

    ?

    ? ?

  • 8/3/2019 Red Line Nordic Rail 2011Eng

    30/30