reference group meeting hamburg, germany 29 … · 2020. 10. 2. · • entso-e guideline for cost...
TRANSCRIPT
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
REFERENCE GROUP MEETINGHAMBURG, GERMANY29 SEPTEMBER 2016
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Drafting a roadmap for the evacuation of offshore renewable generation inthe context of the PROMOTioN projectSeptember 29, 2016
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
CONTENT
• WP1, WP12 & Task 1.4• Purpose of the draft roadmap• Methodology• Discussion
14.04.2020 2
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
WP1, WP12 & Task 1.4
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
WP1, WP12 & Task 1.4
Work Package Structure
03.05.16 4
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
WP1, WP12 & Task 1.4
WP 1 - Requirements for meshed offshore grids
03.05.16 5
Partners: TenneT (WP Leader), DNV GL, EIRGRID, SGI, DWG, GE, RTE, TU Delft, Statoil, SOW, DTU, RWTH Aachen, FGH, Dong Energy, Carbon Trust, Tractebel, Iberdrola, T&D Europe, USTRAT, Energinet, SHE Trans
Objectives:• Definition of a common set of equal requirements for all the WPs to ensure the compatibility of
results• Definition of fundamental topologies to align the language used within the PROMOTioN project
(e.g. radial multi-terminal, meshed, etc.)• Analyze past studies in the area of offshore grids to form a starting point for the PROMOTioN
project• Assess and evaluate the operational, financial and technical aspects of existing offshore
connections and grids• Define reference scenarios for the development of offshore wind in the North Seas and the
evolution of the load/generation in the surrounding countries• Derivation of an initial roadmap for the evacuation of offshore renewable generation• Identify under which circumstances a certain fundamental topology will claim its existence
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
WP1, WP12 & Task 1.4
WP 12 – Deployment plan for future European offshore grid development
03.05.16 6
Partners: TenneT (WP Leader), DNV GL, ABB, RTE, Statoil, SOW, FGH, Carbon Trust, Tractebel, Iberdrola, T&D Europe, Energinet, SHE Trans
Objectives:• The key objective is to produce a Deployment Plan for European future offshore grid
development. This plan will clearly define all required technical, regulatory, economic, financial, legal, governmental and market actions.
Further objectives:• To evaluate results of all work packages and to identify key required technical, regulatory,
economic, financial, legal, governmental and market barriers;• To collect relevant data and underlying grid development scenario’s to identify a ‘optimal
scenario’ for the development of a future European offshore grid and its integration with the on-shore grid;
• To analyse the economic and financial viability of results and recommendations of the different work packages and to develop a business case;
• To integrate the current PROMOTION project and past project results in a final deployment plan for future European offshore grid development.
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• Objectives• Derivation of a draft roadmap, taking into account technical and
economical factors, and the development pace of total installed offshore wind energy capacity, including its location
• Detailed study considering the economic viability of offshore grids• Presentation of the draft roadmap and some typical flows on a
geographic map through an interactive presentation tool• Deliverable 1.6 due end of March 2017) – Report and computer
demonstration with a draft roadmap and reference off-shore grid expansion plan
• This initial roadmap will be enriched by WP12
WP1, WP12 & Task 1.4
Task 1.4 – Initial roadmap for the evacuation of offshore renewable generation
03.05.16 7
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Purpose of the draft roadmap
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• What PROMOTioN will do• Alleviate the remaining technical, financial & regulatory barriers for the
development of an offshore meshed grid in the North Seas• (Re-)Demonstrate the economic viability of such a grid
• What PROMOTioN will not do• Define precisely the infrastructure that must be built in the North Seas in
the upcoming decades – nevertheless everything must be ready at the end of the project to allow TSOs to do so
Purpose of the draft roadmap
Scope of PROMOTioN
03.05.16 9
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• We must be sure that all relevant questions are on the table at the beginning of the project, such that WPs will bring all needed answers
• E.g. in which cases a DRU can be used• We must understand when critical technologies will be needed
• E.g. DC CBs• We must understand the successive steps towards the
development of an offshore grid, because the grid must be technically viable during each step
• We must understand the critical factors influencing the offshore grid topology
• E.g. development pace of offshore wind energy, costs of components, but also the planning time horizon
Purpose of the draft roadmap
Why a roadmap in that context?
03.05.16 10
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• Purpose: to show how an offshore meshed grid could be developed (one of the likely ways) in the upcoming decade 2020-2030 (“reference offshore grid expansion plan” – temporal evolution) such that
• We raise all unclear points about the technical way to develop such a grid (components to use)
• We can show the impact of several factors on the likely development• But the purpose is not to say what should be actually
implemented in the North Seas
Purpose of the draft roadmap
Proposed purpose for the roadmap
03.05.16 11
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Methodology
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• The offshore grid expansion plan must make sense from an economic point of view
• Idea of economic optimum• But impossible to develop an optimization problem considering all
details• Need of a pragmatic approach to reach a “near-optimum”, based on
several steps• The output of Task 1.4 is a draft, that will be reworked in WP12
• Feedback on assumptions, methodology from the stakeholders can imply changes
• Limited time horizon in Task 1.4: 2030 (probably 2050 in WP12)• Output: draft grid expansion plan, but not development of wind
generation (we do not have anymore a vertically integrated power sector in Europe) → we will only study how, where and when to put cables, converters, etc.
Methodology
Global philosophy
03.05.16 13
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• Main steps to draft a roadmap• Optimization of the global topology
• “Macro-level”: how much transfer capacity we need between hubs/countries and when (too complex to include too much details in the optimization problem)
• Possibility to create new substations (hubs) in the North Seas (or to use existing platforms)
• Analysis of the possible technological solutions to realize the global topology
• Consideration of requirements (e.g. maximum loss of power infeed)• Possible iteration with the previous step (e.g. costs)
• Assessment of the economic viability of the different possible technological solutions
• Derivation of the final roadmap
Methodology
Decomposition in steps
03.05.16 14
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• How do we connect optimally (least cost) the wind farms with the shores (and together) such that we can evacuate all the offshore wind energy?
• Possibility to create substations• Similar to e-Highway2050, but
with a limited scope (North Sea)• Example of WindSpeed project →• It gives rough indications of what
makes sense from an economic point of view, but that’s it
Methodology
Optimisation of the global topology: explanation
03.05.16 15
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• Preliminary problem• Objective function
• Minimization of the offshore grid cost (CAPEX), but the grid must be able to transmit onshore all the generated offshore energy (if no transmission outage)
• Nodes• Some are predefined (OWF, onshore connection points), but candidates based on
a sampling• Connection of nodes
• Discrete capacities (e.g. four types of cables are used – 500 MW, 700 MW, 1000 MW, 1200 MW)
• Linearized version of the power flow equations
Methodology
Optimisation of the global topology: example
7-Sep-2016 16
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Methodology
Optimisation of the global topology: example
03.05.16 17
Map for 6 consecutive years (distances in km)Red dots: OWFs; Blue dots: onshore connection points; Hollow dots: possible substations
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• Once we have the transfer capacities, how do we do that concretely to reach a solution that satisfies requirements
• For each step (evolving grid)• Example of ISLES project
• We have to know what kind of converters/CB/… we put where, how and when
• Several solutions can be possible (see next step)
Methodology
Analysis of technological solutions: explanation
03.05.16 18
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• The previous step will give transfer capacities (capacities of cables) between nodes and will indicate the need for new substation
• What technologies must be used in which way to satisfy the requirements imposed on offshore HVDC grids?
• Use of DRU/VSC, DCCBs• Analysis of technological solutions: detailed design
Methodology
Analysis of technological solutions: explanation
7-Sep-2016 19
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• Techno-economic simulation of the behaviour of the power systems (generation/failures/flows/prices/…) for the different possible configurations to conclude on the draft roadmap and its economic viability
• Similar to what was done in e-Highway2050
Methodology
Assessment of the economic viability: explanation
03.05.16 20
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Discussion
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• What is the primary purpose of an offshore grid?• What could be a typical planning time horizon for such a grid?
• Planning time horizon: we know more or less what will happen• 5 years?
• Do we need a N-1 security rule in an offshore grid?• Interpretation of the N-1 security in that context?
Discussion
Main discussion points
03.05.16 22
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Functional Requirements from AC and DC grids to DC grid protection Dirk Van HertemKU Leuven and EnergyVille29-09-2016
© T
enne
TTS
O G
mbH
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
CONTENT
• DC grid protection and WP4 of promotion
• System and Components Constraints
• Expected performance
• Request for feedback
03.05.16 2
© T
enne
TTS
O G
mbH
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗HVDC is receiving massive attention from industrie, especiallyfor offshore connections and interconnectors
↗DC grids are seen as a logical evolution↗Offering redundancy↗Possible cost savings
↗DC grids require protection↗Current HVDC protection: at the AC side
↗ not a good solution for the future pan-European grid
DC grids and DC grid protection
03.05.16 3
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗to develop a set of functional requirements for various DC grids: from small scale to large overlay grids and for a variety of system configurations and converter topologies
↗to analyse a wide range of DC grid protection philosophies on a common set of metrics
↗to identify the best performing methods for the systems under study
↗to develop detailed protection methodologies for the selected methods
↗to develop configurable multi-purpose HVDC protection IEDs to enable testing of the methodologies
↗to investigate the key influencing parameters of protection systems on the cost-benefit evaluation
WP4: develop multi-vendor protection systems
03.05.16 4
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Protection system: What to protect?↗Humans↗System ↗Components
↗For the AC system:↗After single fault, selective protection system clears fault↗Backup protection if that fails↗Protection operates in 60 – 200 ms↗Operated N-1: no single credible fault/contingency causes large
sustained outage↗Expected behavior at a single line fault↗Expected behavior at busbar fault↗Expected behavior at fault at lower levels (e.g. distribution)↗Fault ride through behavior of wind farm
↗3 GW / 1.8 GW / … maximum loss of infeed
What are our expectations of DC gridprotection?
03.05.16 5
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗What about the DC grid?↗Same as AC?↗Which reliability?↗Are the limits (delays, power loss,…) the same?↗What are relevant faults at the DC side
↗Pole to pole?↗Pole to ground?↗Busbar?
↗What is the accepted behavior at the DC side↗AND the connecting AC systems
↗Continental Europe, Ireland, offshore wind, offshore load↗Do we expect the same for all systems?
↗Small --> medium --> large
What are our expectations of DC gridprotection?
03.05.16 6
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Type (a) line protection : impact only on the faulty line↗Type (b) line+ protection : impact on the faulty line and on the closest
MMC converter ↗Type (c) open grid protection : impact of all the breakers at a bus ↗Type (d) grid splitting protection : impact only on the faulty zone↗Type (e) low-speed HVDC grid protection : impact on the entire grid
Overview: Fault clearing strategies (zones-impact)
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Functional requirements?
03.05.16 8
System and components constraints
Expected performance for DC grids (small, medium and large)• Various DC faults
Functional requirements for DC grids
• Current technology• Foreseeable limit
(2030→2050)
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Components of DC grid protection: influencing eachother
03.05.16 9
Protection equipment
Control equipment
Power system componentsConvertersSwitchgearFault current limiters
System controlsCommunications
Relays/AlgorithmsMeasurements
Communications
Restoration
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Selectivity & speed↗E.g., maximum portion of the
grid which can be disconnected↗Maximum time for which grid
can be disconnected↗Backup protection
↗Lower probability, but higher impact
↗Robustness towards system changes
System functional requirements lead to requirements for protection
↗Suitable protection philosophies↗Selective↗Partly selective↗Non-selective
↗Suitable fault clearing strategies
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Protection algorithms↗Speed↗Selectivity↗Sensitivity↗Reliability
↗Breakers↗Speed↗Interruption capability↗Energy absorption capability
↗Fault current limiters↗Di/dt …
Protection requirements lead to requirements for protection components
↗Suitable candidates↗Protection algorithms
↗Non-unit↗Unit/Pilot
↗Breakers: Mechanical, Hybrid
↗Inductors/SFCL/…
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• Potential Faults/events:• AC faults (single-phase-to-ground, three-phase-to-ground)• Outage of a converter• DC line faults (pole-to-ground, pole-to-pole)• DC busbar faults
• Potential effects on the AC & DC systems:• DC system: overvoltage, under voltage, overcurrent, DC grid
instability, DC overload• AC system: overvoltage, under voltage, overcurrent, AC grid
instability (transient stability, small signal stability, frequency stability), AC overload
• what is acceptable?
Why relevant? Fault occur and they influence the total system
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
DC Line (pole-to-ground) fault: example 1
13
Test system: 3-terminal bipolar with metallic return DC Power during and after pole-to-ground fault
Utilizing fast selective DC protection (fault clearing ~5ms): DC system:
• Possible overload post fault clearing AC system:
• Very short transients
Time [ms]
0 50 100 150
Pow
er [M
W]
-1000
-500
0
500
1000
1500Pdcp3 Pdcp2 Pdcp1
Conv1
Conv3
Conv2
100km
150km
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
DC Line (pole-to-ground) fault: example 2
03.05.16 14
Utilizing AC circuit breaker for fault clearing (fault clearing 2~3 cycles): DC system:
• Outage of the whole DC system• Possible large fault currents depending on grounding configuration
AC system:• See multiple short-circuit faults once converters are blocked• Possible instability
AC2AC1
Conv1
Conv2
Conv3
Conv4
Conv5
Fault
Conv blkAC sees SC faults
Fault cleared
DC restart
t
P PAC1
some ms
40~60 ms
hundreds ms
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
DC Line (pole-to-ground) fault: example 3
03.05.16 15
Utilizing converters with fault blocking capability: DC system:
• Outage of the whole DC system AC system:
• Short interruption• Possible instability
o Asynchronous AC systemso Synchronous AC systems
Synchronized AC systems
ωω
AC2AC1
Conv1
Conv2
Conv3
Conv4
Conv5
FaultConv Blk
DC restart
t
P PAC1
some ms
tens ms?
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
HVDC converter outage: influence on ac frequency and generator rotor angles
03.05.16 16
Simplified representation of ac system:• Equivalent synchronous generator (SGeq) with inertia constant H• Droop control action is neglected within the considered time frame (0-0.2s)• HVDC converter outage = Load step on synchronous generator
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714. 03.05.16 17
13
579
47,548
48,549
49,550
H [s
]
Freq
uenc
y [H
z]
ΔP [pu]
For ΔT = 0.1 s
47,5-48 48-48,5 48,5-49 49-49,5 49,5-50
12345678910
00,
10,
20,
30,
40,
50,
60,
70,
80,
9 1
H [s
]
Freq
uenc
y [H
z ]
ΔP [pu]
00.25
0.50.75
1
4949,249,449,649,8
50
ΔP [p
u]
Freq
uenc
y [H
z]
ΔT [s]
For H = 5s
49-49,2 49,2-49,4 49,4-49,6 49,6-49,8 49,8-50
00.10.20.30.40.50.60.70.80.91
00,
020,
040,
060,
08 0,1
0,12
0,14
0,16
0,18 0,2
ΔP [p
u]
Freq
uenc
y [H
z]
ΔT [s]
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Maximum loss of power infeed and duration:
Constraints from synchronous AC Systems
03.05.16 18
∆P
t
Pmax
fewms
> hundreds ms
Maximum allowed
permanent loss
Tens -100 ms
P1
P2
Pzone2 < Pmax
Pzone1 < P2
Zone 1FB
Zone 2ACCB
DC Disconnector
DC circuit breaker
Full bridge MMC
AC
AC
AC circuit breaker
Half bridge MMC
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Maximum temporary power loss and duration↗at a node↗to a synchronous zone↗to a control area
↗Voltage support requirement
Constraints from asynchronous AC Systems
03.05.16 19
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Point-to-point HVDC offshore links↗AC fault ride-through: hundreds ms (e.g. 384 ms for 30% Vremaining GB [1])↗DC faults are protected using AC circuit breakers: 2~3 cycles
↗Constraints to DC grids:↗Fault interruption: within 2 ~3 cycles↗Converter DC LVRT capability?
Constraints from wind farms
03.05.16 20
F1
DC chopper
F2ACCBACCB
F2
[1] A. J. Beddard and U. Oj, “Factors Affecting the Reliability of VSC-HVDC for the Connection of Offshore Windfarms,” PhD thesis, 2014.
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Converter (for all types of converters): ↗Udc at the converter terminal
↗Normal operation: 90% - 110%↗Minimum voltage and duration for a converter has to stay unblocked: 0.8pu
hundreds ms?↗Iarm of the converter
↗IGBT (maximum instantaneous current limit):↗2 [pu] on maximum dc value allowed by IGBT↗Future technology: SiC, GaN?
↗Diode/thyristors ↗Surge withstand capability [kA2t]
Constraints from DC grid components
03.05.16 21
DC fault ride through capability
Udc/Udcn
t
tUV,blkUmin,blk
100%110%
90%
When a converter is allowed to be blocked and tripped
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗DC Circuit Breakers: constraints to relay speed
Constraints from DC grid components
03.05.16 22
Energy absorption branch
Auxiliary branch
Main branchRCBCurrent limiter
Imax
tbr,otbr,t tint tc
∆tbr,t ∆tbr,int ∆tbr,rcb
Parameter Unit Typical valueForeseeablevalues(2030-2050)
Breaker tripping delay [ms]Hybrid: 2-3 ms, Mechanical: 5-10 ms
Fault current interruption capability [kA]
Hybrid: 5-10 kA, Mechanical: 10-16 kA
Energy absorption capability [MJ] ~ 10 MJ
Bypass delay [ms] ?Residual current interruption capability [kA] 0.1 kA
Maximum current rate of rise [kA/s] 3-5 kA/s
Maximum breaker surge arrestor voltage [pu] 1.5
Rated voltage [kV] 320 500?
Structure of a DC circuit breaker
Fault interruption process
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Cable constraints [3]:
WP4.1 Investigation and evaluation of fault detection and selectivity methods, towards functional requirements
Constraints from DC grid components
03.05.16 23
Parameter Unit Typical value
Foreseeablevalues(2030-2050)
Remarks
Lightning impulse withstand level [pu] 2,1 (same
polarity) Lightning impulse withstand level
Switching impulse withstand level [pu] 1,2 (opposite
polarity) Switching impulse withstand level
Maximum continuous dc voltage (applied during type and routine test)
[pu] 1,85Maximum continuous dc voltage (applied during type and routine test for 15minutes)
Thermal overload limit [pu] ?
[3] Cigre WG B1.32 - Recommendations for testing DC extruded cable systems for power transmission at a rated voltage up to 500 kV
t
U0
2.1 [pu]
t
U0
-1.2 [pu]
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
• Stress on AC and DC system
• AC side system fault ridethrough capability
• DC side voltage capability• Chicken and egg problem:
DC grid design depends on what we expect from itsoperations and operationalexpectations depend on the system in place
• What do we want as behavior? What is acceptable?
Towards Functional Requirements of DC Grids
24
∆P
t
Pmax
5ms Few hundreds ms
Allowed power outage – time requirementPmax: allowed maximum permanent loss
Allowed voltage deviations(source: cigre B4-56)
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
↗Feedback on the approach↗DC requirements are fundamentally different than AC
requirements, and we need to/can choose before designingprotection systems
↗Availability of DC grids: expectation or requirements?↗What is a “small” grid↗What is a “medium” grid↗What is a “large” grid
↗What is an acceptable outage?↗Is 3000 MW for continental Europe a fixed value? Likely to change?↗Will we need to define LVRT grid codes for the DC grid to enable a
multi-vendor grid↗Can a dc grid be “shut-down” for a short amount of time: tens ms?
WP4.1 Investigation and evaluation of fault detection and selectivity methods, towards functional requirements
Constraints/Expected performance from DC grids: Input requested
03.05.16 25
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Questions?
26
COPYRIGHTPROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks MAIL [email protected] WEB www.promotion-offshore.net
The opinions in this presentation are those of the author and do not commit in any way the European Commission
PROJECT COORDINATORDNV GL, Kema Nederland BVUtrechtseweg 310, 6812 AR Arnhem, The NetherlandsTel +31 26 3 56 9111Web www.dnvgl.com/energy
CONTACT
PARTNERSKema Nederland BV, ABB AB, KU Leuven, KTH Royal Institute of Technology, EirGrid plc, SuperGrid Institute, Deutsche WindGuard GmbH, Mitsubishi Electric Europe B.V., Affärsverket Svenska kraftnät, Alstom Grid UK Ltd (Trading as GE Grid Solutions), University of Aberdeen, Réseau de Transport d‘Électricité, Technische UniversiteitDelft, Statoil ASA, TenneT TSO B.V., German OFFSHORE WIND ENERGY Foundation, Siemens AG, DanmarksTekniske Universitet, Rheinisch-Westfälische TechnischeHochschule Aachen, Universitat Politècnica de València, Forschungsgemeinschaft für. Elektrische Anlagen und Stromwirtschaft e.V., Dong Energy Wind Power A/S, The Carbon Trust, Tractebel Engineering S.A., European University Institute, Iberdrola Renovables Energía, S.A., European Association of the Electricity Transmission & Distribution Equipment and Services Industry, University of Strathclyde, ADWEN Offshore, S.L., Prysmian, Rijksuniversiteit Groningen, MHI Vestas Offshore Wind AS, Energinet.dk, Scottish Hydro Electric Transmission plc
APPENDIX
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
DISCLAIMER & PARTNERS
03.05.16 27
© PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 691714.
Work package 7Regulation & FinancingCBA in the offshore contextPresentation Reference Group Meeting, 29 September 2016, Hamburg
Building blocks
Offshore grid planning
Offshore grid investment/ construction
Offshore grid operation
Legal framework
Spatial planning Jurisdictional
constraints (e.g support scheme)
Joint planning instruments
Licensing regimesConnection
responsibility
Access rulesBalancing responsibilityGrid code compliancy
Economic framework
CBA MethodOffshore-onshore
coordinationParticipation of grid
users
(Joint) support schemeRevenue models/ tariff
designInvestment and
efficiency incentivesCBCA methods
Connection / access charging
Rules on ancillaryservices
Capacity allocation
Financial framework
Risk analysis in offshore grid planning
Ownership & governance
Investor participation and fundingmechanisms
Analysis risk perceptioncapital providers (ROIC)
Compensation and liability
REGULATION FINANCING
WP7 Setup 1st intermediate deliverable
2
CBA in the EU– why relevant for a meshed offshore grid
3
2nd PCI list (2015) – NSOG and BEMIP corridor *Yellow connections are potentially competing projects
Selection of energy infrastructure projects evolved from:
Political decision economic assessment (CBA)
There a several ways to perform a good CBA:
Agreement on a common method is crucial
ENTSO-E’s CBA 1.0, 2.0 methodologies are pushing for a common method
Evolution of a meshed grid?
VS
FSR analytical framework for a robust CBA
Input1/ Accounting for project interaction2/ Common high quality dataset3/ Disaggregated cost reporting
Calculation4/ Concentrate on a reduced list of effects5/ Distributional concerns should be disregarded6/ Model should be explicitly stated7/ A common discount factor should be used8/ Uncertainty should be addressed
Output9/ (Geographically) disaggregated benefit reporting10/ Ranking should be based on monetisation
4
Assessment of the CBA methodology
5
Status of implementationENTSO-E 1.0
(approved by the ECin 2015)
ENTSO-E 2.0 (version for ACER opinion)
ENTSO-E Market design - balancing
Significantly more important in the
offshore context?
INPUT(1) Project interaction must be taken into account in the project and baseline definition
One baseline (TOOT). Arbitrary clustering rules
One baseline (TOOT), ambiguous update of the clustering rule
Harder applicable but dealt with. Almost greenfield
development
INPUT(2) Data consistency and quality should be ensured TYNDP TYNDP TYDNP
INPUT(3) Costs should be reported in disaggregated form Not clear Not clear Not clear
Immature technology
CALCULATION(4) CBA should concentrate on a reduced list of effects
Reduced list Reduced list Reduced list
CALCULATION(5) Distributional concers should not be addressed in the calculation of net benefits
OK OK OK
CALCULATION(6) The model used to monetise the production cost savings and gross consumer surplus needs to be explicitly stated
Explicit model available Explicit model available Explicit model available
CALCULATION(7) A common discount factor should be used for all projects
4 % for all 4 % for all Uniform; aligned with TYNDP & PCI
CALCULATION(8) A stochastic approach/scenario analysis should be used to address uncertainty
OK The need is mentioned, but not specified how to apply the tools
OK
OUTPUT(9) Benefits should be reported in disaggregated form
Not clear Not clear Regional and country effects should be reported Various
winners/losers
OUTPUT(10) Ranking should be based on monetisation Multi-criteria analysis Multi-criteria analysis, additional monetization of losses
Monetized ranking is suggested Various significant
externalities
TRAN
SPAR
ANCY
COORDINATION
COMPARABILITY
Selection of case studies: projects/ national regulatory frame or plan
Dynamic picture,idea on the longterm is that projectsget interconnectedto form a meshednetwork
6
Assessment of case studiesEWIC
(IRL-UK)COBRA CABLE
(NL-DK)ISLES
(SCO-IRL- N-IRL)Concern in the
ENTSO-E 1.0 and2.0 methodology
Phase Commissioned in September 2012 Final investment decision taken, expected to be in operation by 2019
In the study phase
EU funding “Project of European Interest”, included in (TEN-E) Priority Interconnection Plan. Received significant EEPR funding (110 m€)
On the 2013 and 2015 PCI list. EEPR funding received/allocated for studies and construction (86.5 m€)
On the 2013 and 2015 PCI list. The EU INTERREG IVa Program funded 1.6 m£ for ISLES I one and 0.9 m£ for ISLES II
INPUT(1) Project interaction must be taken into account in the project and baseline definition
No project interaction taken intoaccount
TOOT approach is applied and change incongestion rent of other interconnectorsis calculated
No interaction with other PCI projects istaken into account. Interaction betweenISLES clusters is analyzed partially.
Critical
INPUT(2) Data consistency and quality should be ensured
Ok Ok No TYNDP by local data is utilizedalthough from respected sources. /
INPUT(3) Costs should be reported in disaggregated form
Ok Ok Ok Harmonisationneeded
CALCULATION(4) CBA should concentrate on a reduced list of effects
Ok Ok Ok for the 2015 analysis. However, notthe ENTSO-E CBA 1.0. list is applied. /
CALCULATION(5) Distributional concerns should not be addressed in the calculation of net benefits
Ok Ok Ok/
CALCULATION(6) The model used to monetize the production cost savings and gross consumer surplus needs to be explicitly stated
Explicitly stated but not detailedmarket and network model used
Ok, explicitly stated and detailed marketand network model is used(details are not public)
Ok, explicitly stated and detailed marketand network model is used
/
CALCULATION(7) A common discount factor should be used for all projects
Ok, there was no common discountfactor determined thus the allowedWACC of EirGrid was used
Ok A very low discount factor is applied inthe 2012 analysis (2%) and no value isprovided in the 2015 analysis
/
CALCULATION(8) A stochastic approach/scenario analysis should be used to address uncertainty
Uncertainty is disregarded, noscenario or sensitivity analysis applied
Ok, 2 scenarios are applied plussensitivity analysis by varying total costand discount factor
Scenario and sensitivity analysis isapplied, although not using the TYNDPscenarios.
/
OUTPUT(9) Benefits should be reported in disaggregated form
Only the benefits for Ireland areconsidered
Ok, benefits are reported disaggregated Ok, benefits are reported disaggregated OkOUTPUT(10) Ranking should be based on monetization
Ok, full monetisation is applied Partial monetisation is applied, but a finalNPV value of the project is underlined.Additional indicators in non-monetarymetrics are mentioned more forinformational purposes
Both quantitative as qualitative cost andbenefit indicators are reported. No fullmonetization is conducted.
Harmonisationneeded
7
Conclusions
• Coordination: how to deal with project interaction?We (EU) do not want the best (individual) projects but the best project portfolio to be developed
How to deal with coordination/project interaction? - In the current institutional setting: application of 2 baselines
- Changing the institutional setting: a more regional approach is required⇒ Project promoters do not have the resources/information/incentives(?) to deal with this issue⇒ Regional group selecting the PCI projects should get more responsibility/resources
• Transparency (costs and benefits): raising trust and public acceptanceCases perform good but harmonisation in the reporting needed
• Comparability (monetization): where do the experts stop and politics start?A common method (≠ value) for the determination of indicators (e.g. SoS) is needed
8
Thank you for your attention, questions?
Contact:[email protected]
Statements/questions for the audience
- Some PCI projects receive generous public support (up to 75% funding inexceptional cases), shouldn’t these CBA documents be easier accessible andmore transparent?
- How high is the cost for a “pure” interconnector project to make anticipatoryinvestment in order to facilitate it’s inclusion in a meshed network later? Is thisstrongly technology dependent?
- How do you (project promoters) deal with interactions among PCI projects?Especially relevant in the case of merchant interconnectors.
- Would it be a good idea to ask for a ‘light’ CBA to access funding for studies anda ‘full’ CBA for funding for construction works?
- What about the idea to create a “North Seas ISO” in charge of the operation andlong term planning of the offshore (meshed) grid and then organize tenders forthe construction and ownership of individual lines making part of the plan of thisISO? This idea is based on experiences in the US and would be a way to tacklethe coordination problem, but radically changes the governance. 10
References
11
• The Union list of PCIs published in the official Journal of the European Union (27/01/2016) -COMMISSION DELEGATED REGULATION (EU) 2016/89
• THINK report 10- Cost Benefit Analysis in the Context of the Energy Infrastructure Package (01/2013) led by N.-H. von der Fehr
• THINK report 5 - Offshore Grids: Towards a Least Regret EU Policy (01/2012) led by F. Lévêque• NSCOGI – Final report – Working group 1: Grid configuration (11/2012)• ENTSO-E Guideline for Cost Benefit Analysis of Grid Development Projects – CBA 1.0 (02/2015,
approved by EC)• ENTSO-E Guideline for Cost Benefit Analysis of Grid Development Projects – CBA 2.0
(04/2016,draft for public consultation)• STORY - CBA for projects at distribution level, lessons learned from the transmission level
(05/2016, draft) by N. Keyaerts• Examples of collaboration and best practice in offshore grid connectivity to enable offshore
renewables (June 2015), sub report for ISLES II• Innovating grid regulation to regulate grid innovation: from Orkney Isles to Kriegers Flak via Italy
(2011) published in Renewable energy by L. Meeuws and M. Saguan• An offshore wind union? Diversity and convergence in European offshore wind governance (2015)
published in Climate Policy by O.Fitch-Roy• A Review of the North Seas Offshore Grid Modelling: Current and Future Research (2016)
published in Renewable & Sustainable Energy Reviews by J. Gorenstein Dedecca and R. Hakvoort
Annexes
12
Reduced list of effects
13
Assessement of the 4 methodologies
14
Coordination
Value of a projects is a function of the realisation of other projects
Captured by the baseline definition of a CBA analysis:ENTSO-E: one baseline (only TOOT, on voluntarity basis >1)ENTSOG: two baselines (TOOT and PINT)
Arguments against multiple baselines:Computational powerUncertainty about realisation other projects (information)
Pathways for improvement:Short-term: two baselines as minimum requirement by ENTSO-ELong-term: European institution could perform this (complex) analysis
Clustering vs complementary projects: improvement in ENTSO-E CBA 1.0 -> 2.0
ENTSO-E 1.0-2.0
ENTSOG ENTSO-E formarket design
# of baselines 1 2 Not applicable
15
Transparency
No explicity requirement to report: Disaggregated cost componentsGeographically disaggregated benefits
Why important:Checking the efficiency of the investment (disaggregated cost components)Comparing uncertain cost estimates easier when disaggregated, plus build-up of cost
databaseAid for CBCA decisions (cost components and geographically disaggregated benefits)
Arguments against disaggregation:Sensitive cost information? Potential disadvantage for project promotor in future auctions?
=> We do not argue to publish this information publiclyPolitically sensitive to disclose expected geographically disagreggated benefits?
Degree of disaggregation? Starting point: cost components already enumerated in themethodologies
ENTSO-E 1.0-2.0 ENTSOG ENTSO-E formarket design
Cost components X X X
Benefits per jurisdiction X X V
16
Comparability
Goal is to assess the net benefit and to rank projects -> One dimensional output needed (monetary)
We argue to go from non-transparent implicit weighting of indicators to full explicit monetisation
How?Union-wide methods should be agreed upon to estimate the monetary value of hard to quantify indicators (most prominently the VOLL1) ≠ one EU wide value for VOLL throughout the year. Who takes this responsability?
Additionally reporting the indicators (eg CO2 reduction of RES integration) possibly using othermetrics is still advised, but cautiousness should be excercised to avoid double counting
1Example: Guidelines of Good Practice on Estimation of Costs due to Electricity Interruptions and Voltage Disturbances, CEER, December 2010.
ENTSO-E 1.0-2.0
ENTSOG ENTSO-E formarket design
Type of CBA MCA MCA Pure CBA
17
owerontrol
Research Group&
Technical Perspective on Benefits of
Meshed DC Grids
Tim Green
owerontrol
Research Group&
2
Opening Thoughts
• Is it possible to consider technical perspective separate from
economic perspective?
• Grids need an investment case for their assets. Do DC Grids
have sufficient economic benefit from their technical features?
• Which way around do we want to view the problem?
• Are we looking for benefits of technical solution?
• Or do we have a problem and we are looking for the best solution?
owerontrol
Research Group&
3
Differences Between Transmission
Networks and Distribution Networks
BSP Primary
Transmission
• Role is bulk transfer of energy• Routes are all double circuits• Network is meshed to provide multiple
routes to loads and generators• EHV low loss network• Large degree of redundancy –
extremely low interruption rate
Distribution
• Role is to serve loads• Some generators, and increasing quickly• Structure is radial not meshed• Alternative routes available through switching • Double circuits used at higher levels, single circuits
at lower levels• Lower voltages than transmission and higher
losses.• Smaller degree of redundancy – low interruption
rate
Slide from
under-
graduate
module
owerontrol
Research Group&
4
Why build an offshore DC grid?
• No demand customers to supply within the grid• So what is resilience of a grid used for?• What is the value to a wind farm of a resilient connection?• What is the value to the host AC network? (Services as well as Energy)• What redundancy / asset-utilisation is implied by resilience provision?
• What is the “option value” of a grid?
owerontrol
Research Group&
5
Issues for Integration with Host AC Grid
• At times of high renewable energy
production, conventional generators
are stood down and the real physical
inertia of the AC system is reduced.
• Rates of change of frequency become
higher and frequency deviations larger
owerontrol
Research Group&
6
AC Grid Strength
• South East England is where several HVDC interconnectors land and is a region that has little synchronous plant and even that is being displaced by offshore wind farms.
• The short circuit ratio is low and reactive current during a fault is sought.
• Control interactions possible in weak grid
• Cascading failure through failure to ride-through network faults is a risk.
Source: System Operability Framework 2014, National Grid
owerontrol
Research Group&
7
Loss of In-feed Mitigation
Here, one of two 2.5GW DC-links
suffers an outage
Overload capability (set at 30%) of
the other link is used to reduce the
loss of in-feed and reduce the
frequency error
This action gives time for further
action to be planned
120.104.88.072.056.040.0 [s]
6000.
4700.
3400.
2100.
800.0
-500.0
3.18 GW With Overload
2.5 GW No Overload
DC Power Flows in HVDC LinksLink A Outage (-2.5 GW)
[MW]
DIg
SIL
EN
T
120.104.88.072.056.040.0 [s]
51.0
50.6
50.2
49.8
49.4
49.0
49.36 Hz
49.53 Hz
Grid FrequencyLink A Outage (-2.5 GW)
[Hz]
DIg
SIL
EN
T
owerontrol
Research Group&
8
• Device junction temperatures may become
an issue during overload.
• Dynamic Rating should be used to provide
large amount of extra power during start of
system events then reduce to a steady-
state overload rating
Thermal Implications of
Converter Overload
owerontrol
Research Group&
9
MMC Converter Ratings
Siemens MMC Technology
at 864 MW at ±320 kV
Alstom Sub-Module
at circa 1,000 A and 1,700 V
Voltage ripple on sub-
module capacitor
Commutation current
limit of IGBTs
Temperature of
IGBTs
Modulation
limit Available arm
voltage
owerontrol
Research Group&
10
Fault Management
• Need effective management of faults to
• provide continuity of export of wind farm
• avoid loss-of-infeed problems
• Lots of work done on various ideas but
are we reaching consensus?
• Possibly some interesting trade-offs
between speed and cost
Breaker from GEIRI (Beijing), has:nominal current of 1.5 kA;breaking current of 15 kA; nominal voltage of 200 kV
owerontrol
Research Group&
11
Control of Fault and Re-charge Conditions
Concerns are:
• Limit current to protect converters themselves
• Limit current for breaker / isolator to operate
• Recharge network and re-establish power flow
• Avoid loss penalty in normal use
• Keep equipment size small
• Ensure stability of host AC network
owerontrol
Research Group&
12
How quickly can fault
clearance occur?
What are the best
strategies for current
control?
Example six terminal
network
(i) fault detected,
(ii) disconnect ordered,
(iii) disconnect
complete
(iv) recharge start,
(v) recharge end.
owerontrol
Research Group&
13
Simulated network recovery timings for a fault at the NOR terminal of the
NOR-KIL cable on the six terminal network, varying the number of bipolar
AACs available to recharge the network
owerontrol
Research Group&
14
Impact of DC Fault Clearance on AC Grid
Frequency and voltage at points across the GB transmission system
following a 200 ms momentary outage of the HVDC study systems
owerontrol
Research Group&
15
Closing Remarks
• Clarity is needed over how technical features of DC grids create
economic benefits to balance cost
• Always need to look at counter-factual – how else could the same
benefits be provided?
• How are additional technical benefits of DC Grids (beyond energy
transfer and resilience) recognised in economic terms?
• Cost-effective provision of fault management within DC grid is
important step
• Benefits of services to host AC system are important for small AC
systems but will they become important for lager systems?
29/09/2016
sustainable energy for everyoneBenefits of a meshed offshore grid in the
North Seas Region
Edwin Haesen
© ECOFYS | |
Ecofys domains of expertise across the energy value chain
29/09/20162
Energy
Policies
Energy
Systems
and Markets
Urban
Energy
Climate
Strategies
and Policies
Sustainable
Industries
and Services
Policy & StrategyProduction, Trading,
Transport & DistributionProsumers, Industries
and Financiers
© L
ichtm
eist
er/F
oto
lia;
Vik
tor/
Foto
lia;
Did
iLav
chie
va/T
hin
ksto
ckphoto
s; E
yetr
onic
/Foto
lia;
Andre
y Arm
yagov/
Foto
lia
PWC/Tractebel/Ecofys study on North Seas meshed offshore grid
© ECOFYS | |
Our expertise areas across the entire energy value chain
29/09/20163
Business Areas
• Energy Policies• Climate Strategies and
Policies
• Energy Systems and Markets• WTTS
• Urban Energy• Sustainable Industries and
Services
Clients • Governments and non-profits
• Development banks• Increasingly corporates
aiming to adapt climate policies
• Energy supply companies, TSOs and DSOs and bio-energy suppliers
• Governments and authorities• Financial institutions
• Energy-intensive manufacturing, equipment, agro-food industries
• Corporations and financial institutions
• Branch organisations, governments and authorities
Services • Policy development, deployment and evaluation
• Strategy and regulation studies
• Energy and climate strategy design
• Conceptual energy solutions• Scenario and feasibility
studies• Emission trading system
and carbon pricing mechanism design
• Market design studies• Demand & production
forecasting• Energy and carbon asset
assessment• Risk assessment and
mitigation• Policy & strategy impact
assessment• Revenue model development• Operational consultancy
activities
• Design of implementation strategies
• CO2 emission reduction assistance
• Certification and labelling• Purchasing advice• Funding and subsidy advice• Energy knowledge transfer,
training and capacity building• Risk assessment and
mitigation
100% renewable energy, upscaling of climate initiatives
Policy & StrategyProduction, Trading,
Transport & Distribution
Prosumers, Industries and Financiers
PWC/Tractebel/Ecofys study on North Seas meshed offshore grid
© ECOFYS | |
EC studies on North Seas energy system
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid4
Benefits of a Meshed Offshore Grid in the Northern Seas Region• Compares the costs and benefits of a “meshed” offshore grid
with separate radial connections to shore for each wind farm
2014 • PWC • Tractebel• Ecofys
Regulatory matters concerning the development of the North Sea offshore energy potential • Identifies the existing regulatory barriers • Delivered a set of regulatory models, which would enable a
coordinated development of an offshore grid
2015/2016 • PWC • Tractebel• Ecofys
Baseline Environmental Assessment for the Grid in the Irish and North Seas• Give guidance on how to assess the adequacy of
environmental considerations of the aggregated energy plan at regional level
• Provide recommendations on how negative effects can be minimized and how positive effects can be optimized
2016 (ongoing)
• Ecofys• RPS
© ECOFYS | |
Analysis of 3 load/generation scenarios in a business-as-usual and a coordinated offshore grid development
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid5
© ECOFYS | |
A comparison
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid6
RADIAL MESHED
VS.
© ECOFYS | |
Scenario Definition
> Scenario 1: ENTSO-E Vision 4 Scenario 2030*
> Scenario 2: PRIMES reference scenario 2030
> Scenario 3: NSCOGI scenario
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid
Country Scenario 1 (based on
ENTSO-E Vision 4)
Scenario 2 (based on
PRIMES reference)
Scenario 3 (based
on NSCOGI)
Belgium 4.00 2.65 3.10
Germany 23.60 20.10 16.70
Denmark 5.54 3.00 1.20
France 9.94 11.77 4.49
Great Britain 40.19 22.86 17.00
Ireland 1.85 0.15 1.63
Netherlands 6.80 4.85 6.00
Norway 6.40 1.00 0.70
Sweden 1.40 0.34 0.33
TOTAL 100 67 51
* In 2016 BEAGINS project updated with EWEA High scenario and EC High RES scenario (80.8 GW)
7
© ECOFYS | |
Spatial Allocation of Offshore Wind
> Offshore wind capacity assigned to specific areas within each country zone based on following priorities:
1. Sites in operation & under construction in 2014 (same capacity)
2. Permitted sites, starting with lowest Levelised Cost of Energy (calculated with Ecofys Offshore Wind Cost Model)
3. Other planned sites, such as designated areas by national governments, starting with lowest LCoE (calculated with Ecofys Offshore Wind Cost Model)
4. Additional areas as needed – aiming for least constrained areas.
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid
CAPEX Wind Turbine Supply
CAPEX Installation
CAPEX Electrical Supply
CAPEX FoundationSupply
Levelis
ed
Co
st o
f En
erg
y[€
/ M
Wh
]
Valu
e m
ap
pin
g
OPEX
Energy Yield
8
© ECOFYS | |
Offshore Wind Farm Sites and Relative LCOEs
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid9
© ECOFYS | |
Identification of Grid Connection Points and Capacity
> Connection capacity is calculated using the tool SCANNER (Tractebel)
– Incorporation of ENTSO-E’s 2030 reference grid (TYNDP2012)
– The hosting capacity is the maximum injection capacity of a node, taking into account the N-1 criterion.
– Hourly differences, yearly average used.
> Optimal hosting capacity for scenario 1 is not sufficient in Belgium and Germany and in specific import areas.
> The obtained values not strictly binding for the installed capacity of offshore wind farms. Impact of interconnectors not taken into account.
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid
Region Optimal hosting capacity
Belgium 2.2 GW
France 28.23 GW
Germany 21.53 GW
Great-Britain 49.27 GW
Ireland 4.06 GW
Netherlands 19.01 GW
10
© ECOFYS | |
Definition of Connection Routes Based on Radial and Meshed Configurations
> Radial: No coordination, each project is developed independently. Point-to-point connection of offshore wind farms from offshore substation to a suitable onshore substation and shore-to-shore interconnectors.
> Meshed: A coordinated onshore, offshore and interconnection development is considered using anticipated technology
> Meshed variants: The proposed meshed design for the whole of the Northern Seas region includes all of the solution variants.
> An iterative process was included to optimise the meshed grid capacities
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid11
© ECOFYS | |
High RES scenario (radial - meshed) (BEAGINS, 2016)
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid12
© ECOFYS | |
PRIMES scenario (radial - meshed) (BEAGINS, 2016)
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid13
© ECOFYS | |
NSCOGI scenario (radial - meshed) (BEAGINS, 2016)
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid14
© ECOFYS | |
Results Electrical Design: Capex/Opex optimisation
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid
Scatter plot of the technology choice based on the rated power and
transmission length of each link considered for the radial scenario 1
15
© ECOFYS | |
Energy Densities and hourly wind profiles
> Representative PPC is used and scaled to size of each wind farm
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid
Average wind speeds at 10 m for the
Northern Seas region (MERRA dataset)
0
5
10
15
20
25
30
1 1001 2001 3001 4001 5001 6001 7001 8001
Win
d S
peed
(m
/s)
Hour of Year
0
20
40
60
80
100
120
140
160
1 1001 2001 3001 4001 5001 6001 7001 8001
Po
wer O
utp
ut
(M
W)
Hour of Year
16
© ECOFYS | |
Infrastructure CAPEX
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid17
Cost difference meshed wrt. radial
Scenario 1 +7.8 b€
Scenario 2 +4.9 b€
Scenario 3 +10.3 b€
© ECOFYS | |
Generation operational cost savings
> Figures including the cost of losses, reduction of CO2 costs (avoided wind curtailment) and the generation savings
> Key drivers for the reduction of the total annual cost of electricity supply :
– Level of offshore wind capacity
– Opportunities for energy exchanges
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid18
Generation cost reduction
Scenario 1 -5.1 b€
Scenario 2 -1.5 b€
Scenario 3 -3.4 b€
© ECOFYS | |
Generation investment cost savings
> Increased transfer capacities between power systems allow reducing the total installed capacity while keeping the same reliability level
> Avoided investments in new peaking units for all three scenarios
> Higher gains possible in scenarios with less intermittent production units
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid19
Investment cost reduction
Scenario 1 -3.4 b€
Scenario 2 -4.8 b€
Scenario 3 -7.8 b€
© ECOFYS | |
Summary of the study
> Costs 4.9 to 10.3 B€ higher for meshed grids
> Important annual operational savings from 1.5b€ to 5.1 b€ thanks to optimized energy exchanges and offshore wind integration through a meshed grid
> Possibility of generation investment cost savings requiring coordination between Member States
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid20
CAPEXAnnual
operational costreduction
Investment cost reduction
Scenario 1 +7.8 B€ -5.1 b€ -3.4 b€
Scenario 2 +4.9 B€ -1.5 b€ -4.8 b€
Scenario 3 +10.3 B€ -3.4 b€ -7.8 b€
© ECOFYS | |
Regulatory matters concerning the development of the North Sea offshore energy potential
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid21
© ECOFYS | |
Regulatory matters concerning the development of the North Sea offshore energy potential
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid22
Overall project plan and
definition of responsibilities
Pilot projects
Cooperation agreement for allocation of
costs
Financing, realizing and
putting the grid into operation
Development of the RES plants and connecting them to the grid
© ECOFYS | |
Baseline Environmental Assessment for the Grid in the Irish and North Seas
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid23
© ECOFYS | |
Next?
Energy
•Overall RES ambition RES
•Security of (onshore) Supply
Economy
•Investment opportunities
•R&D•Business model transition (ports, logistics)
•Jobs and global export
Environment
•Integrated maritime planning
•Marine bio-diversity areas
•Sustainable fisheries
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid24
Do we understand all benefit categories of a North Seas energy system?
Do we agree on the need for action?
© ECOFYS | |
Find us
Virtually:
29/09/201625
Personally:
Ecofys GroupKanaalweg 15-G3526 KL Utrecht – The Netherlands
Ecofys Germany (Cologne)Am Wassermann 3650829 Cologne – Germany
Ecofys Germany (Berlin)Albrechtstraße 10 c10117 Berlin – Germany
Ecofys UK1 Alie StreetLondon E1 8DE – United Kingdom
Ecofys BelgiumPericles Building23, Rue de la ScienceWetenschapsstraat 231040 Brussels – Belgium
PWC/Tractebel/Ecofys study on North Seas meshed offshore grid
© ECOFYS | |
> Edwin Haesen (PhD)
> Senior Consultant
> Energy Systems & Markets
> +32 (0) 2 880 41 05
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid26
© ECOFYS | | 29/09/201627
sustainable energy
for everyone
PWC/Tractebel/Ecofys study on North Seas meshed offshore grid
© ECOFYS | |
Belgium
> Belgium
Note: Scenario 3 > Scenario 2
> Operational + Permitted + Planned = 2.8 GW
> New area is proposed for additional 1.2 GW (6.5 MW/km²) outside of shipping routes and other constraints
29/09/20
GW Scen 1 Scen 2 Scen 3
Operational 0.7 0.7 0.7
Permitted 1.1 1.1 1.1
Planned 1.0 1.0 1.0
New 1.1 0.3
Total 4.0 2.8 3.2
PWC/Tractebel/Ecofys study on North Seas meshed offshore grid28
© ECOFYS | |
Germany
> Germany
> 2.9 GW currently operational, 8 GW permitted & 25 GW in early planning phase, so sufficient capacity for all scenarios
GW Scen 1 Scen 2 Scen 3
Operational 2.9 2.9 2.9
Permitted 8.0 8.0 8.0
Planned 13.0 9.4 5.8
New
Total 23.9 20.3 16.7
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid29
© ECOFYS | |
Denmark
> Denmark
> 1.2 GW currently operational & 5.5 GW in early planning phase, so sufficient capacity for all scenarios
GW Scen 1 Scen 2 Scen 3
Operational 1.2 1.2 1.2
Permitted
Planned 4.5 2.0
New
Total 5.7 3.2 1.2
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid30
© ECOFYS | |
France
> France
Note: Scenario 2 > Scenario 1
> Only considering English Channel
> 2 GW in early planning stage
> Additional areas proposed by France Energie Éolienne (up to 15 GW fixed platforms), divided into parcels (5 MW/km²)
GW Scen 1 Scen 2 Scen 3
Operational
Permitted
Planned 2.0 2.0 2.0
New 6.2 7.9 1.6
Total 8.2 9.9 3.6
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid31
© ECOFYS | |
Ireland
> Ireland
Note: Scenario 1 = Scenario 3
> Only considering Irish Sea & St. George’s Channel
> 25 MW permitted, 1.5 GW permitted & 1+ GW in planning stages, so sufficient capacity for all scenarios
GW Scen 1 Scen 2 Scen 3
Operational 0.0 0.0 0.0
Permitted 1.5 1.0 1.5
Planned 1.0 1.0
New
Total 2.5 1.0 2.5
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid32
© ECOFYS | |
The Netherlands
> The Netherlands
Note: Scenario 3 > Scenario 2
> 0.2 GW operational, 3.2 GW permitted & large areas allocated by government, which were allocated into parcels (5 MW/km²)
GW Scen 1 Scen 2 Scen 3
Operational 0.2 0.2 0.2
Permitted 3.2 3.2 3.2
Planned
New 3.6 1.5 2.7
Total 7.1 4.9 6.1
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid33
© ECOFYS | |
Norway
> Norway
Note: Scenario 2 = Scenario 3
> Only considering southern North Sea
> No large-scale operational or permitted sites
> Proposed areas from Norwegian Water Resources and Energy Directorate, which were allocated into parcels (5 MW/km²)
GW Scen 1 Scen 2 Scen 3
Operational
Permitted
Planned
New 6.9 1.2 1.2
Total 6.9 1.2 1.2
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid34
© ECOFYS | |
Sweden
> Sweden
Note: Scenario 2 = Scenario 3
> Only considering western Baltic
> 110 MW operational & 1.8 GW permitted, so sufficient capacity for all scenarios
GW Scen 1 Scen 2 Scen 3
Operational 0.1 0.1 0.1
Permitted 1.5 0.6 0.6
Planned
New
Total 1.6 0.8 0.8
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid35
© ECOFYS | |
United Kingdom
> United Kingdom
> Excluding Atlantic Ocean (Scotland)
> 3.6 GW operational, 2.8 GW permitted, 18 GW planned & 16+ GW possible (within Round 3 commitments, and territorial waters of Isle of Man, Northern Ireland & Scotland), so sufficient capacity for all scenarios
GW Scen 1 Scen 2 Scen 3
Operational 3.6 3.6 3.6
Permitted 2.8 2.8 2.8
Planned 18.1 16.8 11.2
New 15.9
Total 40.4 23.2 17.7
29/09/2016 PWC/Tractebel/Ecofys study on North Seas meshed offshore grid36