regional transmission organization overview

22
Regional Transmission Organization Overview Presented to The Energy Regulatory Office of Kosovo and The Illinois Commerce Commission June 8, 2009

Upload: others

Post on 11-Dec-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Regional Transmission Organization Overview

Regional Transmission Organization OverviewPresented to The Energy Regulatory Office of Kosovo and The

Illinois Commerce CommissionJune 8, 2009

Page 2: Regional Transmission Organization Overview

Agenda

• Regional Transmission Organization (RTO) Background– Federal Energy Regulatory Commission

(FERC) RTO Characteristics and Functions • Current RTOs• Midwest ISO (MISO) Specifics• Major Challenges

Page 3: Regional Transmission Organization Overview

FERC Order 2000

• Characteristics identified in the order:– Independence from market participants– Appropriate scope and regional configuration– Possession of operational authority for all

transmission facilities under the RTO’s control– Exclusive authority to maintain short-term

reliability

Page 4: Regional Transmission Organization Overview

FERC Order 2000 cont’d

• Minimum functions identified in the order:– Administer its own tariff and employ a

transmission pricing system that will promote efficient use and expansion of transmission and generation facilities

– Create market mechanisms to manage transmission congestion

– Develop and implement procedures to address parallel flow issues

Page 5: Regional Transmission Organization Overview

Order 200 Functions cont’d

• Serve as a supplier of last resort for all ancillary services required in Order No. 888 and subsequent orders

• Operate a single Open-Access Same-Time Information System (OASIS) site for all transmission facilities under its control with responsibility for independently calculating Total Transmission Capacity (TTC) and Available Transmission Capacity (ATC)

Page 6: Regional Transmission Organization Overview

Order 200 Functions cont’d

• Monitor markets to identify design flaws and market power

• Plan and coordinate necessary transmission additions and upgrades

• Interregional coordination

Page 7: Regional Transmission Organization Overview

ISOs and RTOs

Page 8: Regional Transmission Organization Overview

Comparison of RTO/ISO Services

Sources: ISO/RTO Council: “The Value of Independent Regional Grid Operators”; FERC; Booz Allen research

Services Provided MISO ISO-NE

NYISO PJM SPP ERC

OTCAIS

OGrid Operations 2002 1997 1998 1997 1997 1996 1998Transmission Scheduling 4 4 4 4 4 4 4

Regional Economic Dispatch 4 4 4 4 4 4 4

Transmission Planning 2002 1997 1999 1997 1998 1997 2002Regional Transmission Planning

4 4 4 4 4 4 4

Regional Interconnection 4 4 4 4 4 4 4

Transmission Cost Allocation Method

2 4 4 4 4 4 4

Wholesale Market Operations 2005 1999 1999 1998 2006 2001 1998

Real-time Energy Market 4 4 4 4 4 4 4

Locational Energy Price 4 4 4 4 4 2009 4

Hourly Energy Price 4 4 4 4 4 4 4

Congestion Price 4 4 4 4 4 4 4

Losses Price 4 4 4 2 4 4 4

Day-ahead Energy Market 4 4 4 4 0 2009 2008Virtual Bidding 4 4 4 4 0 0 2009Ancillary Services Market 2009 4 4 4 2 4 4

Regulation 2009 4 4 4 2 4 4

Operating Reserves 2009 4 4 4 2 4 4

Financial Transmission Rights

4 4 4 4 4 0 4

Capacity Market 0 4 4 4 0 0 0

Settlements and Billing 4 4 4 4 4 4 4

Market Oversight 2005 1997 1999 1998 2006 2004 1998

Full Market CapabilityNo Market Capability Dates represent estimated start

Page 9: Regional Transmission Organization Overview

The Midwest ISO’s RoleWhat We Do

• Provide Independent Transmission System Access

• Deliver Improved Reliability Coordination

• Perform Efficient Market Operations

• Coordinate Regional Planning

• Foster Platform for Wholesale Market Development

Implications• All parties have equal and

non-discriminatory access

• Substantial regional reliability improvements

• Lower cost unit commitment, dispatch and congestion management

• Integrated system planning

• Encourage infrastructure investment and facilitate regulatory initiatives

Page 10: Regional Transmission Organization Overview

Midwest ISO facts• Independent, voluntary, regulated by the FERC • Network model: 5,464 generating units• $41 Billion energy market • 1,896 pricing nodes• Governed by independent eight member board• 31 transmission owning members• $2.4 B in new transmission projects thru 2015

Page 11: Regional Transmission Organization Overview

11

MISO Market Area

Page 12: Regional Transmission Organization Overview

1996 1999

Discussions begin to form Midwest ISO

First Board of Directors elected

2002FERC approvalas an RTO

Tariff Administrationunder Midwest ISO OATT

2005

Midwest Energy Markets Begin

2001

2006Began Ancillary Services Market Initiative

2007

JOA with PJM

Start-Up Reliability Coordination &Tariff Administration

Joint and Common Market Initiative

ASM Initiative

Midwest Energy Markets

BA AlignmentASM Testing

2008

Midwest ISO Evolution

Reliability Coordination

2004

2009

ASM Launch

Page 13: Regional Transmission Organization Overview

Pet Coke199; 0.2%

Waste189; 0.1%

Hydro3,589; 2.7%

Other68; 0.1%

Oil/Gas8,777; 6.7%

Oil3,435; 2.6%

Nuclear10,361; 7.9%

Gas31,371; 23.9%

Coal/Gas242; 0.2%

Coal68,010; 51.8%

Wind5,065; 3.9%

Coal, 220 MWCoal\Gas, 15 MW

Gas637 MW

Oil\Gas688 MW

Other, 23 MWWaste, 5.5 MWWater, 9.5 MW

Wind1941 MW

Total New Capacity = 3,539 MW

13

Nameplate Capacity by Fuel

Total Nameplate Capacity: 131,308 MW

Page 14: Regional Transmission Organization Overview

The Energy Balance

Losses InterchangePowerGenerated

Load

58 6259 6160

DEMAND GENERATIONHertz

Page 15: Regional Transmission Organization Overview

What is a Balancing Authority?• An electric power system or combination of

electric power systems bounded by interconnection metering and telemetering

• Balancing Authority duties– Balance Supply and Demand within their area– Maintain interchange of power with other Balancing

Authorities– Maintain frequency of the electric power system

within reasonable limits

Page 16: Regional Transmission Organization Overview
Page 17: Regional Transmission Organization Overview

Balancing Authority AlignmentEnergy and Operating Reserves Market Operations

ALTE

ATC

Midwest ISO BalancingAuthority Area (MBAA)

MECS

DECO MECS

IPL

MP

MDU NIPS

ALTWATC

NSP NWEC

NSP

Local Balancing Authority (LBA)

Transmission Operator (TOP)

Midwest ISO BA (MBA)

MRO

SERC

RFC

Regional ReliabilityOrganization

AMIL AMMO CIN

HE

FE

CWLP

SMPMPC

OTP

OTP

GRE

SIPC

CWLD

UPPCWEC

MGEWPS

SIGE

CONS

DECOITC

CONSMETC

Page 18: Regional Transmission Organization Overview

Midwest ISO Market Overview• The Midwest ISO market

consists of four components:

Day Ahead Energy Market

Real Time Energy Market

Financial Transmission Rights Market (FTR)

Ancillary Services Market

FTRFTR

DayAhead

DayAhead

RealTime

ASM

Page 19: Regional Transmission Organization Overview
Page 20: Regional Transmission Organization Overview

Ancillary Services• Integrated into market operations Jan. 6, 2009

• Flexible capacity needed to maintain secure operation of power system

– Loss or increase of Load– Loss or increase of Resources

• Regulation Reserves

• Contingency Reserves(sometimes called Operating Reserves)

– Spinning– Supplemental (non-spinning)

Page 21: Regional Transmission Organization Overview

21

Planning Activities

Key Issues

CongestionRenewable

PolicyOperational Impacts

New Generation and

Demand Response

ChangingRegulatory

Requirements

FairCost

Allocation

Load Growthand DSM

AgingInfrastructure

Key Issues Currently Impacting Transmission Planning

Page 22: Regional Transmission Organization Overview

Wind IntegrationOperational Impacts in the Midwest ISO

Yearly Hourly Avg Load Vs WindSeptember 2007 - August 2008

52,000

55,000

58,000

61,000

64,000

67,000

70,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hour

Load

(MW

)

600

630

660

690

720

750

Wind G

eneration (MW

)

LoadWind

• In addition to infrastructure costs, operational issues are expected to drive additional Contingency Reserve and market wide charge costs when large quantities of an intermittent resources are online.

– Ramp Requirements: wind has a negative correlation to daily ramps resulting in need for additional reserves to support ramp

– Load Following: wind changes in same time horizon as load, resulting in need for additional capacity to meet load

– Wind Forecasting: accuracy decreases with extended time horizon, introducing inefficiency into the commitment process