regulatory review aspects of post-fukushima safety ... › sites › gsan › act... · atomic...
TRANSCRIPT
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Regulatory Review Aspects of Post-Fukushima Safety
Enhancements in Indian NPPs
RAHUL PORWAL
Atomic Energy Regulatory Board
Mumbai, INDIA
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Outline
• Introduction
• AERB Safety Review Methodology
• Safety Observations Post-Fukushima Event
• Post-Fukushima Review Recommendations
• Implementation of Recommendations
– Kudankulam NPP: Salient Features
– Kudankulam NPP: Implementation Status
2
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Introduction (1/2)
• Fukushima Accident: Outcome of tsunami generated due to high magnitude earthquake
• NPPs suffered extended station blackout, which could not be mitigated
• Systems for ECC did not function after power restoration due to flooding
• Four hydrogen explosions damaged reactor buildings of the NPPs
• Units 5&6 survived due to air cooled DG
3
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Introduction (2/2)
• Large radioactivity release – implementation of off-site emergency measures
• Accident rated at level-7 of INES
• Accident revealed shortfalls in certain safety aspects of the NPPs
• Actions were initiated by all concerned
• AERB constituted an Expert Committee to review the safety of Indian NPPs against External Events of Natural Origin
4
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
AERB Safety Review Methodology (1/2)
• AERB: constituted in 1983
• Has developed robust procedure for safety review, regulatory inspections & issue of consents
• AERB Regulatory documents have been developed in the form of Safety Standards: Safety Codes & Safety guides
• These documents cover various safety aspects to be considered during Siting, construction, commissioning, operation, radiation safety, QA & desommissioning stage of NPPs
5
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
AERB Safety Review Methodology (2/2)
• Development and revision of these documents is a continuing process at AERB
• AERB has a unique three-tier review process for stage-wise clearances of NPPs
• First-tier safety review is carried out by Site Evaluation Committee (SEC) / Project Design Safety Committee (PDSC)
• Second-tier review is done by Advisory Committee for Project Safety Review (ACPSR)
• Third-tier safety review is carried out by AERB Board
6
Atomic Energy Regulatory Board, INDIA IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna
SAFETY OBSERVATIONS POST-FUKUSHIMA EVENT
7
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Safety Review Observations (1/3)
• Post Fukushima review basis: basic nuclear safety viz. reactivity control, core cooling & radioactivity confinement during ESBO (BDBE)
• Tsunami capable submarine faults at more than 800km from Indian coast – coincidence of earthquake & tsunami almost non-existent
• Sufficiently conservative design requirements for postulated initiating events
• Implementing Safety up-gradation over a period of time based on outcome of various safety reviews
8
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Safety Review Observations (2/3)
• Periodic safety review for all operating NPPs are conducted
• Implementation of operating experience feedback and lessons learnt from operational incidents in India and abroad are considered as appropriate
• Most of the NPPs in India are PHWRs. Core cooling by natural convection flow through SGs is possible in these NPPs
• Water inventory make-up to SGs through diesel driven fire water pumps is envisaged in PHWR design
9
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Safety Review Observations (3/3)
• For spent fuel of PHWRs, water inventory in fuel pools is much larger w.r.t. the heat load of the spent fuel
• Submergence of the spent fuel is assured for at least one week taking into account the following:-
– conservative assumptions
– maximum decay heat of the spent fuel
– No operator action
10
Atomic Energy Regulatory Board, INDIA IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna
POST FUKUSHIMA REVIEW RECOMMENDATIONS
11
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Review Recommendations (1/3)
• NPPs to be re-evaluated for addition of provisions such that basic safety functions are not hampered under BDBEs.
• Emphasis on functionality of most of the safety related SSCs even under extreme events without demand for operator action
• Voiding during natural circulation flow during heat removal be avoided. Back-up provisions for inventory make-up to important systems be available
12
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Review Recommendations (2/3)
• Preparation of Emergency operating procedures for postulated accidents initiated by BDBE
• Establishment of a seismically qualified emergency facility with adequate radiation shielding which will remain functional under BDBE
• Safety analysis for SBO to be done for beyond 24 hrs upto 7 days demonstrating that all the safety parameters are within acceptance limits
13
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
Review Recommendations (3/3)
• Provisions for accident management to be made as part of Severe accident management guidelines (SAMG)
• Analysis for hydrogen generation for all NPPs and implementation of mitigatory measures to be taken up
• For SFPs, site specific safety assessment for structural integrity, leak-tightness, stability of fuel racks & handling equipment was suggested
14
Atomic Energy Regulatory Board, INDIA IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna
IMPLEMENTATION OF RECOMMENDATIONS
15
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
KK NPP: Salient Features (1/5)
• Kudankulam NPP: 2x1000 MWe VVERs
• Unit #1 attained first criticality on July 13, 2013
• Engineered safety features provided for catering to DBEs as well as BDBEs
• Each active safety system is backed up by passive safety system and each is capable to perform the intended safety function
• While each active safety system has redundancy of 4×100%, for passive systems it is 4x33%
16
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
KK NPP: Salient Features (2/5)
• Safety system trains are completely segregated in terms of location and layout
• Operator actions to disable actuated safety system are blocked in the first 30 min to exclude human error
• All safety systems are supplied with power from dedicated independent diesel generators and battery banks
17
Atomic Energy Regulatory Board, INDIA IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna
• Systems provided for BDBA scenario
– Quick boron injection system
– Passive heat removal system
– Annulus passive filtration system
– Additional system for core passive flooding
– System for retaining and cooling of molten core
Quick Boron Injection System
KK NPP: Salient Features (3/5)
18
RPV
QBIS
Tank
SG
PRZ
RCP
MOIV
MOIVAir
Air
Atomic Energy Regulatory Board, INDIA IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna
• Core decay heat can be removed by natural circulation of primary coolant through SGs in case of SBO
• Water inventory in the SGs can be conserved with PHRS
• PHRS facilitates heat removal from SGs to atmospheric air as UHS
KK NPP: Salient Features (4/5)
19
Atomic Energy Regulatory Board, INDIA IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna
KK NPP: Salient Features (5/5)
20
Additional System for Core Passive Flooding
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
KK NPP: Implementation Status (1/4)
• Post-Fukushima safety enhancements for Kudankulam NPP as submitted by the utility was reviewed in detail
• Implementation of Recommendations was identified as ‘short-term’ (within 6 months) and ‘long-term’ (within 2 yrs) plans from start of initial fuel loading
• With systems already in place for BDBA, as a matter of abundant precaution, back-up provisions for addition of water into the RCS, SFP & SGs were made
21
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
KK NPP: Implementation Status (2/4)
• The details are as follows :- – a separate tank with borated water inventory with a
plunger pump for injecting water into RCS
– seismically qualified emergency water storage tank located at a higher elevation for make-up to SGs & SFP
– transfer of water from this tank by on-site fire tenders to the hook-up points
– inventory make-up to the steam generators and spent fuel pool through external hook-up points
– adequacy of the availability of the fire-tenders at site in this regard was also reviewed
22
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
KK NPP: Implementation Status (3/4)
• A separate mobile air cooled DG is provided. Loads catered by this DG include:-
– newly introduced systems
– pre-identified existing systems
– instruments for monitoring of important parameters
– emergency lighting
– communication systems
23
IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna Atomic Energy Regulatory Board, INDIA
KK NPP: Implementation Status (4/4)
• Battery operated portable hand-held instruments for local monitoring of important parameters are made available
• Appropriate LCO and surveillance requirements for new systems are being finalized
• Analysis of existing SSCs with regard to their available margins vis-à-vis BDBE in under progress and is being followed up as part of long-term plan
24
Atomic Energy Regulatory Board, INDIA IAEA Technical Meeting, J4-TM-46463 – Aug 26-29, 2013, Vienna
THANK YOU
25