rehabilitation of a pipeline in a new european country

Upload: argentinoar01

Post on 14-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    1/11

    5 PiPelines international digest | deCeMBer 2011

    teChniCal

    T

    he management wanted to know the actual integrity status

    of the pipelines and information regarding other details of

    the lines (such as their exact route). Among other factors, the

    study involved: Topography survey

    Terrestrial survey

    Pipeline detection

    Geographical investigation for soil-resistivity assessment

    Collecting and review of existing information

    Collecting right-of-way information at the local city hall and

    cadastral data for reimbursement contracts to be made by the

    client

    Pipeline inspection and integrity non-destructive testing

    measurements

    Production and delivery of alignment sheets.

    The goal of the project was to gather integrity data on these

    pipelines and to evaluate these data to determine the integrity

    condition of the pipelines and facilities. The pipelines, constructed to

    API 5L X52 with bitumen wrapping, were designed in the early 1970s.The pipelines were initially installed with

    20 inch diameter pipe, but since 1986 some sections have been

    replaced with 16 inch diameter pipe, due to leakage or other

    circumstances.

    Alternative scope of workAfter a few meetings and an ILF presentation of an alternative

    project and survey plan, the client decided to reduce the scope of

    work to some basic investigations in order to obtain a rst integrity

    status of the pipelines. The survey work would therefore include a

    topographic survey, a pipeline-detection survey, a terrestrial survey, a

    long-range ultrasonic/guided-wave ultrasonic (LRUT/GWUT) survey,excavations, radiographic inspection (x-ray), and visual inspection.

    Topographic surveyThis measured all topographical items, including landmarks,

    buildings, streams, rivers, rail tracks, roads, visible crossings of

    third-party infrastructure, etc., in a 50 m corridor on both sides of the

    pipeline. The data collected were entered onto alignment sheets and

    delivered as a database, conforming to the geographical information

    system (GIS) database structure prescribed by the client, for direct

    implementation into the GIS.

    Pipeline detection survey

    This was needed to gather the necessary data to develop detailedalignment sheets and to prepare reliable as-build documentation.

    This survey recorded the exact pipeline position (x, y, z), bend

    identication, and possible diameter changes.

    Terrestrial surveyAll structures and landmarks, in corridor of 100 m on both sides

    of the pipeline, were surveyed to gather reliable data on terrestrial

    conditions and to mark the pipeline route with a grid of survey

    reference markers for possible rehabilitation project execution on the

    pipelines.

    LRUT/GWUTThe most suitable positions for LRUT/GWUT were determined,

    together with the client; these were at locations were the pipeline

    route changes from above-ground to below-ground. With these

    Rehabilitation of a pipeline

    in a new European countryby Abraham Louwerse, ILF Consulting Engineers, Munich, GermanyILF was invited to assess the integrity status of two pipelines in a new European country. In the last few years there were someleakages and nobody really knew the exact position of these pipelines and equipment. The pipelines were installed 30 yearsago, and there was little documentation available; the pipelines are non-piggable and are without any cathodic protection.The client decided to carry out an integrity-assessment study for these two major pipelines before deciding on rehabilitationprocedures.

    Figure 1: The LRUT/GWUT system in use.

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    2/11

    6 PiPelines international digest | deCeMBer 2011

    teChniCal

    spot checks, at the most corrosion-sensitive area of the pipelines, it

    was possible to evaluate the general integrity of the pipeline.

    The advanced LRUT/GWUT system (Figure 1) is designed for rapid

    screening of long lengths of pipe to detect corrosion and other

    forms of axial and circumferential metal degradation. It can be

    used on a wide variety of pipes including those that are insulated.

    The tests can be done with the pipeline operational (inservice), sodisruption and any expensive down-time are minimised. Hundreds

    of metres of pipe can be inspected in a single shift and 100 per cent

    thickness of the pipe wall is inspected during a test.

    The LRUT/GWUT system uses low-frequency ultrasonic guided-

    waves that travel along the full wall thickness of the pipe as a

    circular type wave front around the pipe circumference. The

    pulse-echo application means that changes in wall thickness

    (such as corrosion) along the pipe length will generate signals that

    return to the transducers. These returning echoes are presented

    on a simple amplitude versus distance A-scan signal, which theoperator can use to discriminate between genuine pipe features

    (such as welds) and problem areas (such as corrosion wall loss)

    via the operational software.

    Figure 2: EMAT schematic.

    Chainage No.Diameter

    (inches)

    Wall

    thickness

    (mm)

    Defects

    144 IP3A 20 8.34 Coating degradation and damage

    5054 IP22 24 11.9 OK

    11628 IP34 16 9.36Coating degradation, dent in pipeline, welding anomalies

    Bad support with corrosion indication

    18081 IP36C 16 9.2Coating degradation and damage, welding anomalies

    Bad support with corrosion indication

    24417 IP37 16 8.39 Coating degradation and damage

    31418 IP58 16 7.75 Crossing is sagging, welding anomalies

    31681 IP60 14 12.2 Coating degradation and damage, four anomalies detected

    32315 IP61A 16 7.75 Coating degradation and damage, two welding anomalies

    32794 IP61B 16 7.95Coating degradation and damage, welding anomalies

    Bad support with corrosion indication

    36144 IP73 16 7.92 Coating degradation and damage

    47534 IP77A 16 7.92 Coating degradation and damage

    53144 IP85 20 14.38Coating degradation and damage, two remnant welding

    anomalies, Bow crossing of ditch

    54231 IP88 20 9.24 Coating degradation and damage

    55726 IP92 20 9.8 Coating degradation and damage

    62100 IP95C 20 7.92 Coating degradation and damage

    85213 IP120 20 7.83 Coating degradation and damage, four anomalies detected(Class 2, 3), four welding anomalies

    100026 IP139 16 9.35Coating degradation and damage, four anomalies detected

    (Class 2, 3), nine welding anomalies

    Table 1: LRUT and GWUT investigations or the Route 1 pipeline.

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    3/11

    7 PiPelines international digest | deCeMBer 2011

    teChniCal

    Chainage No.Diameter

    (inches)

    Wall

    thickness

    (mm)

    Defects

    13 MS2 8 7.89 Coating degradation and damage

    94 MS4 14 8.63 OK

    466 MS6 16 7.25 Coating degradation and damage

    643 MS7A 16 7.16Three leak repairs and coating with severe degradation

    672 MS7B 16 6.9

    3420 MS14 16 10.5 OK

    6318 MS23 16 10.8 Coating degradation and damage

    6318 MS24 16 12.33 Defects in welding

    22271 MS47 16 7.6 OK

    26757 MS54 16 8.63 Welding defects

    Table 2: LRUT and GWUT investigations or the Route 2 pipeline.

    Chainage Depth (m)Diameter

    (inches)Pipe type Condition Radius (m) Angle ()

    3,160 m 120 cm 16 Spiral 2.6 124

    3,407 m 150 cm 16 3.0 127

    3,439 m 130 cm 16 Seamless 1.5 148

    8,976 m 130 cm 16 3.0 127

    9,319 m 100 cm 16 7.0 114

    18,655 m 120 cm 16 Spiral Corrosion 6.4 140

    22,207 m 120 cm 16 Spiral Corrosion 5.0 134

    Table 4: Pipe bends (elbows) and diameter or the Route 2 pipeline.

    Chainage Depth (m) Diameter(inches)

    Pipe type Condition Radius (m) Angle ()

    6,375 m 150 20 Seamless 1.5 159

    7,648 m 130 20 Seamless 1.5 147

    32,489 m 150 20 Seamless Poor 0.6 90

    32,792 m 190 20 Seamless Bad 0.7 110

    33,664 m 60 20 Segments 116

    55,569 m 95 20 Spiral Bad 4.6 138

    62,725 m 130 20 Seamless Poor 0.8 112

    63,425 m 150 16 Seamless Good 0.9 120

    75,231 m 200 20 6 9091,747 m 160 20 6.5 140

    Table 3: Pipe bends (elbows) and diameter or the Route 1 pipeline.

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    4/11

    8 PiPelines international digest | deCeMBer 2011

    teChniCal

    Two types of guided wave longitudinal and torsional are

    used to broaden the range of possible frequencies and to adjust

    for dierent situations, for example the presence of liquids.

    Symmetrical and exural waves allow defect detection and

    interpretation of the results.

    An important point to note is that LRUT/GWUT techniques do

    not provide a direct measurement of pipe wall thickness, but

    are sensitive to a combination of the depth and circumferential

    extent of any metal loss. LRUT/GWUT is not able to distinguish

    the dierence between internal or external material loss.

    As a redundancy for the LRUT/GWUT we executed nineEMAT measurements on positions where the spiral-welded

    pipe was giving bad readings via the LRUT/GWUT technology.

    In this case, the electromagnetic acoustic transducer (EMAT)

    technology was a hand-held tool which could be moved around

    the pipe (it was not a collar, like guided wave). The EMAT must

    be placed on the pipe and it shoots forwards by approximately

    1.5 m (Figure 2). The transducer can be moved circumferentially

    around the pipe and with this movement a 360 coverage with a

    measuring length of

    1.5 m can be achieved.

    ExcavationsFifty locations were selected to excavate the pipeline for the

    bend identication and wall thickness measurements. Thediameter changes should have been excavated as well, but

    because of the method used for pipeline replacement in the

    past, these were not detectable.

    Table 5: Wall thickness measurement or the Route 1 pipeline.

    ChainagePipeline

    depth (cm)Pipe type Grade

    Pipe

    condition

    Pipe

    diameter

    (inches)

    Wall

    thickness

    min (mm)

    Wall

    thickness

    max (mm)

    144 m API 5L X52 20 7.8 8.1

    5,054 m Spiral API 5L X52 Bad 20 9.5 12.5

    5,141 m AG API 5L X52 20 9.2 9.2

    6,375 m 150 Seamless API 5L X52 20 12.9 13.6

    7,648 m 130 Seamless API 5L X52 20 8.18 13.8

    11,628 m AG Spiral API 5L X52 Bad 16 8.5 9.6

    Spiral API 5L X52 Poor 8.7 8.7

    Spiral API 5L X52 Poor 8.7 8.7

    24,417 m AG Spiral API 5L X52 20 8.0 8.9

    2628 km 130 Spiral API 5L X52 Bad 20 3.6 7.9

    29,621 m AG Seamless API 5L X52 Poor 22 9.4 9.8

    30,127 m AG Seamless Poor 20 7.7 7.8

    31,418 m AG Spiral API 5L X52 Poor 20 7.5 7.931,604 m AG Seamless Poor 14 12.2 12.9

    32,315 m AG Spiral Poor 14 7.2 8.8

    32,465 m AG Spiral Poor 14 7.2 8.8

    32,489 m 150 Seamless API 5L X52 Poor 20 7.5 9.8

    32,792 m 190 Seamless API 5L X52 Bad 20 9.6 10.9

    33,664 m 60 20 7.9 8.2

    36,144 m AG Spiral API 5L X52 20 7.0 7.2

    Spiral API 5L X52 Poor 20 6.9 7.5

    53,144 m AG Seamless Poor 20 13.0 15.1

    54,231 m AG Spiral API 5L X52 Poor 20 8.6 9.255,569 m 95 Spiral API 5L X52 Bad 20 7.9 11.9

    55,726 m API 5L X52 Bad 20 7.8 9.1

    Spiral API 5L X52 Poor 20 7.0 7.9

    62,725 m 130 Seamless Poor 20 9.3 9.3

    63,425 m 150 Seamless Good 20 9.4 10.8

    75,231 m 200 20 8.3 9.3

    85,213 m AG Spiral API 5L X52 Bad 20 6.5 8.2

    91,747 m 160 API 5L X52 20 9 9.4

    100,026 m AG Spiral API 5L X52 Bad 20 9.5 9.5

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    5/11

    9 PiPelines international digest | deCeMBer 2011

    teChniCal

    According to the information received from the client, the

    bypasses should have been constructed in parallel positions to the

    old pipeline, and connected with elbows to the original line. It was

    later discovered that this was not the way these bypasses had been

    constructed.

    After a second detection survey, in which these connections were

    still undetectable, the client mobilised its eld inspectors and the

    construction company who carried out the bypass construction

    to indicate the positions in the eld. During this identicationsurvey we were informed about the changed construction method

    for the bypass connections: over a length of 50100 m the new

    pipeline was positioned in the original route of the old pipeline and

    connected without the elbows as indicated during the project scope.

    Due to some landowner issues and high water conditions, there

    were some locations which could not be accessed, and at which

    excavations were therefore cancelled by the clients project

    management and ILF. At the other excavations, the pipeline

    diameter and wall thickness were measured and a general

    inspection of the coating was performed.

    Bends (elbows)In agreement with the client, the locations of short-radius bends

    and elbows which were excavated during the pipeline-detection

    survey to investigate the bend type, radius, change of direction

    angle, wall thickness, position, depth, and coating condition

    were selected. Table 3 shows the data from these investigations.

    According to EN 1594, eld bends for pipelines greater than 16

    inches in diameter shall have at least 40 times the diameter: this is

    a radius of 16 m for 16 inches, and 20.3 m for 20 inch pipes. Factory

    bends can have smaller radii. In general bends, made of segments

    (mitred, or cut elbows) are not permitted according to EN 14161.

    While only performing visual inspection on the investigated

    bends, it was not possible to identify if the bends were mitred orfactory bends.

    Wall thicknessAccording to EN 1594 the minimum required wall thickness is

    calculated with following equation:

    where:

    DP = design pressure (bar)

    DOD = outside diameter (mm)

    fo = utilisation factor according to EN 1594Rt0.5 = yield strength according to API 5L (N/mm)

    This equation does not consider any supplemental wall

    thickness, such as might be used for corrosion. Also, the equation

    Table 6: Wall thickness measurement or the Route 2 pipeline.

    Table 7: Clients technical specifcation or wall thickness.

    ChainagePipeline

    depth (cm)Pipe type Grade

    Pipe

    condition

    Pipe

    diameter

    (inches)

    Wall

    thickness

    min (mm)

    Wall

    thickness

    max (mm)

    013 m AG Seamless API 5L X52 Fair 814 7.7 8.0

    94 m 90 Seamless API 5L X52 Bad 16 8.2 8.9

    466 m AG Spiral API 5L X52 Corrosion 16 6.9 7.3

    657 m 80 Spiral API 5L X52 Corrosion 16 7.0 7.3

    3,160 m 120 Spiral API 5L X52 16 10.0 10.8

    3,407 m 150 API 5L X52 16 6.3 6.8

    3,411 m AG Spiral API 5L X52 Corrosion 16 7.2 10.8

    3,439 m 130 Seamless API 5L X52 16 10.9 11.8

    6,318 m AG Spiral API 5L X52 Corrosion 16 11.3 12.8

    Spiral API 5L X52 Corrosion 16 11.5 13.5

    8,976 m 130 API 5L X52 16 6.3 6.8

    9,319 m 100 API 5L X52 16 9.9 10.6

    18,655 m 120 Spiral API 5L X52 Corrosion 16 10.0 10.022,207 m 120 Spiral API 5L X52 Corrosion 16 9.3 10.1

    22,227 m 120 Spiral API 5L X52 Corrosion 16 7.5 7.6

    26,757 m AG Spiral API 5L X52 Corrosion 16 7.6 8.8

    Pipe diameter

    (inches)

    Design pressure classes

    Wall thickness

    (mm)

    Alternative

    wall thickness

    (mm)

    (client approval

    needed)

    GradeANSI ISO (bar)

    16 400 64 12.5 8.8 L360 NB

    20 400 64 14.2 10 L360 NB

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    6/11

    10 PiPelines international digest | deCeMBer 2011

    teChniCal

    is only a rule of thumb and is valid for straight pipe (not for

    bends).

    For the Route 1 pipeline with its original operating pressure of

    36 bar, an fo of 0.72 (which is the reciprocal safety factor), and Rt0.5

    of 360 N/mm, this leads to a minimum wall thickness of 3 mm for

    the 16 inch pipeline, and one of 3.9 mm for the 20 inch pipeline.

    For the Route 2 pipeline with an original operating pressure of

    42 bar, a wall thickness of 3.6 mm is the absolute minimum

    required.

    To these values a safety design factor of 2 mm and a corrosion

    allowance of 3 mm is to be added, giving the following results:

    Route 1: wall thickness >8 mm for the 16 inch and 8.9 mm

    for the 20 inch pipelines

    Route 2: wall thickness >8.6 mm for the 16 inch pipeline.

    According to the clients technical specication, based on the

    local standard for wall thickness calculations, the specications

    in Table 7 are given, included the prescribed 2 mm safety design

    factor and the 3 mm corrosion allowance. All wall thicknesses

    below the minimum prescribed values are marked in red in

    Tables 5 and 6.

    Material

    The information received from the client stated that there is onlyAPI 5L X52 and L360 linepipe material used for these pipelines.

    According to API 5L, the API 5L X52 and the L360 linepipe

    materials are equal. The minimum yield strength (Rt0.5) is 360N/

    mm and the chemical composition for X52 gives maximum

    contents (mass fraction) of 0.26 per cent carbon, 1.4 per cent of

    manganese, and 0.03 per cent of phosphorous and sulphur for

    welded pipes (in non-sour service).

    Radiographic inspection (x-ray)During the ultrasonic testing (UT) of the pipelines, some

    very badly welded seams were visually observed, and it was

    recommended to the client that they be checked or examined

    by radiographic means. Twelve welded joints were therefore

    investigated by means of x-ray inspection to gather information

    about the general quality of some suspicious welding joints. The

    radiographic test where executed on three joints on the 20 inch

    line, two joints on the 24 inch line, six joints on the 16 inch line,

    and one joint on the 14 inch line.

    The nding after evaluation of the discontinuities on the

    radiographic lms were that there had been incomplete

    Figure 3: Examples o poor welding.

    Table 8: Inspected welded joints.

    Chainage value No. Measured Positive result Negative result

    3411 MS14 1 (joint) on 14 inch Rejected

    6318 MS23 1 (joint) on 16 inch Rejected

    5054 IP22 1 (joint) on 24 inch Approved

    5054 IP22 1 (ws) on 20 inch Approved

    11628 IP34 w1 1 (joint) on 16 inch Rejected

    11628 IP34 w2 1 (joint) on 16 inch Approved

    11628 IP34 w3 1 (joint) on 16 inch Rejected

    31604 IP60 1 (joint) on 14 inch Rejected

    32315 IP61 1 (joint) on 16 inch Rejected

    53144 IP85 1 (joint) on 20 inch Rejected

    85213 IP120 w1 1 (joint) on 20 inch Rejected

    85213 IP120 w2 1 (joint) on 20 inch Rejected

    Results of the 12 investigation points 3 Approved 9 Rejected

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    7/11

    11 PiPelines international digest | deCeMBer 2011

    teChniCal

    penetration and/or incomplete fusion, and nine of the 12

    investigated joints were therefore rejected. Figure 3 ab and

    Table 8 give further details.

    Visual inspectionFor all above-ground installations, excavations, and

    UT investigation sites, a visual inspection was carried out

    which included identification of the pipe type (spiral or

    longitudinally welded), the identification of bends, and the

    measurement of diameter and wall thickness. Also the general

    state of the coating was evaluated and recorded.

    For above-ground installations such as flanges and

    valves, the general state, presence of all bolts and nuts, and

    the corrosion condition, were recorded. The presence of

    handwheels for the valves were also checked.

    Along the pipeline route there are many roads crossings,

    some of which have ventilation pipes which indicate an

    installed casing. On the locations where there were no

    ventilation pipes observed, especially on the national roadsand highways, it was assumed that, according to the old

    standard that was in place during the construction of the

    original pipeline, the ventilation pipes were corroded, had

    disappeared or been stolen for scrap metal collection.

    Data on all road crossings was obtained, regardless of road

    type minor, secondary, national, or highway. Some casings

    made of old oil barrels under a minor road were detected,

    as well as some concrete pipes as a kind of casing under a

    secondary road. It was assumed that many of these crossings

    had not been constructed in conformity with the old standard,

    and certainly they were not in accordance with new standards

    and practices.

    At some water crossings the pipe could be seen lying directly

    in the watercourse. According to European norms, the rule for

    thumb for water crossings is to cross at least 0.8 m below the

    deepest point of the water course.

    Instrumentation and pipeline valvesIn general, the inspected instrumentation and valves were in

    a very poor condition, and it was not certain whether the valve

    diameter matched the pipeline diameter for many valves. None

    of the valves could be remotely controlled and, in many cases,

    the handwheels to operate the valves were missing. Even if

    there was a handwheel, it was very hard or even impossible

    to operate due to corrosion. In some cases flange bolts weremissing. Mostly the external conditions were between bad

    and poor, and paint had been used for corrosion protection (if

    existent at all). At facilities, where identifiable, the pressure

    class was PN64.

    LeakagesDuring the pipeline detection survey leakages were detected

    which were immediately reported to the client. The client had

    recorded all leakages on the pipelines in the previous two

    years: the total number of reported/recorded leakages in 2008

    was 28.

    The repair methods were neither in accordance to the qualitycontrol and safety standards of the client nor to internationally

    accepted standards (Fig.4 a-c). Most repairs were observed as

    being executed by simple steel screwed-on clamps, withoutFigure 4: Examples o poor reinstatement.

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    8/11

    12 PiPelines international digest | deCeMBer 2011

    teChniCal

    even removing and reinstalling the coating. Some severe

    damage caused by excavation works for leakage repair was

    also observed on the pipeline.

    Buoyancy protectionIn areas where the soil contains a lot of water (moor or

    marsh), and also for larger river crossings, buoyancy protection

    for the pipeline is required and is mandatory. According to the

    European standard EN 1594, the pipe should be ballasted or

    anchored, if necessary, in areas where the pipe tends to float or

    because of the high groundwater table.

    It was seen that some kind of buoyancy protection for the

    pipelines had been used in a few locations, although this was

    neither according to European standards nor sufficient. At

    a few locations the bare pipe was seen lying directly in the

    water, covered by some concrete blocks (Figure 5).

    Pipeline integrity assessment

    Pipelines to be rehabilitated

    The pipeline system is a combination of pipelinesconstructed in the 1970s and some new sections that have

    been constructed in recent years due to leakages. The newly

    constructed pipeline are 16 inch diameter L360 NB with a

    three-layer polyethylene (PE) coating; the old, original, 20 inch

    diameter pipeline was constructed from API 5L X52 steel with a

    bitumen coating.

    Because of the bad coating condition of the old pipelines,

    frequent leakages, river and road crossings situations, reduced

    wall thicknesses, poorly maintained pipeline furniture,

    non-classified elbows, non-existing cathodic protection

    (CP) system, non-piggability, and bad welding quality, a

    rehabilitation was considered for all the old pipelines to thespecification of the newly constructed pipelines to bring this

    pipeline system back to fit-for-purpose condition and to be in

    line with the standards and pipeline safety regulations.

    This meant that there should be rehabilitated 101 km of

    new 16 inch pipeline would be installed. The rehabilitation

    sequence/steps and detailed explanation are discussed later.

    Integrity status conclusions

    Integrity managementA pipeline integrity management plan had not been

    implemented, and there was no knowledge of the pipelines

    integrity. Maintenance had only been carried out in a poor

    manner following failure, leakage, or breakdown. The followings

    aspects were observed:

    Generally, there was no CP system installed; the one that

    was partly installed on Route 1 was not maintained.

    Wall thickness measurement indicated that, in thelocations that were investigated, +/- 90 per cent, was not

    sucient according either the clients standard or the EN

    standard.

    There was no coating investigation routine, such as direct

    current voltage gradient (DCVG).

    The lines are not piggable because of:

    Elbow and bend radiuses and welds

    Gate valves are not full-bore

    Diameter reductions

    Dierent pipeline diameters

    No pig launcher or receiver stations.

    Health, safety and environmentThere had been frequent leakages along the pipeline because of

    internal and external corrosion, pipe stresses, and geographical

    Figure 5: Concrete blocks used at a river crossing.

    Figure 6: Concrete block laying on the pipe.

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    9/11

    13 PiPelines international digest | deCeMBer 2011

    teChniCal

    inuences (such as landslides). This was environmentally

    unjustiable and public safety, as well as the safety of the clients

    personnel, was in jeopardy. Corporate reputation was also at

    stake; when a serious incident occurs, it is realistic to assume

    that the pipelines present integrity status will be examined and

    published by the public media. As mentioned already, there had

    been 28 leakages detected and reported in the last two years.

    Pipeline operationWhen looking at the status of the installations and situations

    along the pipelines, very strong doubts arose concerning the

    qualication and pipeline integrity knowledge of the pipeline

    operators. It was strongly suggested that the pipeline operators

    and inspectors should be urgently trained in pipeline integrity,

    safe operating work procedures, and safety awareness.

    For example, an inspectors alarm bells should normally

    go o if he observes a heavy concrete block of a few 100 kg

    laying on top of the pipeline (Figure 6), or when a pipeline is

    completely kinked because of the support of the river crossing

    has collapsed (Figure 7).

    Steps for rehabilitationThe integrity status of the pipeline had a very low quality, and

    the situation was very dangerous for both public safety and the

    pipelines direct environment. The asset utilisation and asset

    capability were both greatly reduced because of this poor integrity

    status, and it was just a matter of time before the pipeline would

    have been out of service for a lengthy period because of an

    incident.

    The following steps for rehabilitation were therefore considered:

    Coating integrityChecking the coating of the previous, already constructed

    L360 NB pipelines by DCVG and measure the soil resistivity of

    the complete pipeline routes.

    Design for cathodic protection and isolation couplingsThe CP system must be designed, taking the previous soil

    resistivity survey results as base, for an adequate external

    corrosion protection. During this design the optimum

    and preferable positions for isolation couplings are to be

    calculated.

    Pipeline exchangeExchange the old API 5L X52 pipeline material with the L360

    NB and three-layer PE coating (according to DIN EN ISO 21809).

    This means the complete exchange of the 26.766 km Route 2

    line and the remaining 74.899 km of 16 inch diameter old Route

    1 pipeline. The design of the new pipeline should be piggable

    with launcher and receiver stations, and with piggable bends

    and valves.

    CrossingsAll pipeline crossings should be made by directional drilling,

    horizontal directional drilling, or prefabricated siphons; if this

    is not possible, existing crossings should be rehabilitated to beof a safe and reliable construction (Figure 8).

    Line valves and valve stationsNew 16 inch full-bore line valves should be located in above-

    ground stations, and preferably equipped with remote process

    control (safety response), and pressure and temperature

    transmitters. This means that electrical power supply and

    communication, by public network, satellite, or by dedicated

    fibre optic cables along the line, will be necessary.

    Location of isolation couplings

    The requirements for isolation couplings depend on the CPsystem that is to be installed. The exact locations for isolation

    couplings cannot be specified until that time.

    Figure 8: Pipe bent due to

    ground movement.

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    10/11

    14 PiPelines international digest | deCeMBer 2011

    teChniCal

    Fencing and markersAll above-ground installations should be fenced-in to out keep

    unauthorised people and to hinder unauthorised operations.

    On the fences, the product identication codes and telephone

    numbers should be visible.

    All changes in direction and crossings should be identied

    with state-of-the-art markers. These markers should have

    the clients identication/tag plates on which the emergency

    telephone numbers and the position identications are clearly

    visible. According to the new standards, the next upstream and

    downstream positioned markers should always be able to be

    seen, to enable the identication of the pipeline route.

    PIMS (pipeline integrity management system)

    Pipeline operationsA training programme for pipeline operators and pipeline

    inspectors should be set up to make them a part of the PIMS. This

    will stimulate a professional dedication to their job and a sense of

    responsibility.

    It is also important that the operators report their work and

    observations to a focal point at their department (the integrity

    engineer) in order to gather together all relevant information for

    implementation in the new GIS system, and to make it possiblefor the integrity engineers to evaluate the right statistics in order

    to initiate maintenance and other relevant actions for integrity

    management. The PIMS should include an inspection programme

    and a maintenance programme.

    Route inspection programmeFor an inspection programme, the following aspects are to be

    included:

    A time schedule for car, walking, and/or helicopter

    inspections.

    The pipeline must be clearly indicated by markers.

    Templates for inspection reports are to be made. All itemsand installations must be listed, dening how and what is

    to be checked and inspected; this includes geographical and

    topographical changes.

    Figure 9: Unauthorised

    excavation o unused section

    o line.

    Figure 10: The process o managing integrity.

    http://-/?-
  • 7/27/2019 Rehabilitation of a pipeline in a new European country

    11/11

    15 PiPelines international digest | deCeMBer 2011

    teChniCal

    Procedures are to be set up concerning what is to be

    inspected, what is be to reported, how the reports are to be

    made, and to whom the reports are to be given.

    A schedule for ILI to observe the feature degradation and to

    plan maintenance.

    Maintenance programmeIn the course of time, several maintenance strategies were

    developed with their own advantages and disadvantages. The three

    major existing categories of maintenance are:

    Corrective maintenance (CM)

    Preventive maintenance (PM)

    Risk-based maintenance (RBM).

    Corrective maintenanceThe CM strategy is independent of time or condition of

    the system, and the work consists only of repairing defective

    equipment. Thus, the unscheduled and unpredictable work leads

    to relatively low costs. High expenditures could arise, however,when the whole system has to be shut down because of the repairs.

    Preventive maintenancePM contains all the work/interventions performed periodically

    on critical units according to specied instructions, or vendor

    maintenance manuals, recommendations, and procedures.

    Examples of PM are:

    Greasing the valves

    Function testing line valves

    Emission testing valve seals and compressor/pump seals

    Intelligent pig runs

    DCVG coating investigation

    Close interval potential survey measurements

    Cleaning/drying liquids in the pipeline (semi-routine) by

    pigging or drain systems.

    An extension of preventive maintenance is condition-based

    maintenance, which has to be developed for each individual

    pipeline system on the basis of the experience during the rst

    years of operation, followed by continuous improvement based

    on actual experience (the Deming circle).

    Risk-based maintenanceIn risk-based maintenance, the system and its components are

    evaluated in terms of their probability of failure and the risks

    involved (Figure 10). The results are visualised in a risk matrix.

    With the focus on the relevant system components for the

    operation, the integrity of the whole system is improved. Highly

    qualied sta are required to undertake this analysis.

    In central Europe, it is recommended that condition-based

    maintenance is regularly undertaken to achieve a high reliability

    of the individual components and thus for the whole system.

    Quantitative risk assessmentBefore commissioning a pipeline a quantitative risk

    assessment (Bowtie) should be set up and implemented for

    all installations and equipment as well as for the pipeline route

    itself. By evaluating the possible internal and external risks it is

    possible to direct and customise the operational and integrity-

    management system in the high-risk areas along the pipeline,

    which include high density population areas, industrial areas,

    environmentally sensitive areas, landslide areas, mining areas,

    rivers and water crossings, direct current rail tracks, highways,

    and parallel crossings with high-voltage power lines.

    http://-/?-