RELEASES FOR TYPHOON YOLANDA - FYs 2013, 2014, 2015 & 2016
as of March 31, 2016
(In pesos)
No. Date FY 2013 FY 2014 FY 2015 FY 2016
NATIONAL GOVERNMENT AGENCIES 15,371,041,891 25,724,423,763 19,353,527,017 55,386,342 60,504,379,013
Department of Agriculture 1,728,720,000 1,045,569,785 58,620,000 2,832,909,785
Office of the
Secretary SA, RA 10634
SARO-BMB-E-
14-0002003 4-Mar-14
Funding requirements for
Reconstruction Assistance for Yolanda-
affected farmers 1,045,569,785 1,045,569,785
BFAR 1,728,720,000 0 1,728,720,000
RS, RA 10352
SARO-BMB-E-
13-0021033 2-Dec-13
Procurement of 4,890 units of 5.5hp
Marine Gasoline Engine as a relief
assistance to the four regions affected
by Typhoon Yolanda (Regions 4B, 6, 7
and 8) 23,000,000 23,000,000
UF, RA 10352
SARO-BMB-E-
13-0025942 27-Dec-13 Government Facility (BFAR Offices) 500,000,000 500,000,000
UF, RA 10352
SARO-BMB-E-
13-0025942 27-Dec-13
Provision of banca and fishing
paraphernalia 800,010,000 800,010,000
UF, RA 10352
SARO-BMB-E-
13-0025942 27-Dec-13 Assistance to Aquaculture 405,710,000 405,710,000
Office of the
Secretary
RRP, RA 10633,
C.A.
SARO-BMB-E-
15-0006361 23-May-15
Repair/rehabilitation of various
irrigation systems of the National
Irrigation Administration (NIA) 58,620,000 58,620,000
Department of Agrarian Reform 100,000 100,000
Office of the
Secretary RS, RA 10352
ABM-BMB-E-13-
0007049 29-Jan-13
Clearing operations in support to areas
in Region VIII affected by typhoon
Yolanda (Office building) 100,000 100,000
Department of Budget and Management 1,200,000 1,551,493 6,115,500 8,939,000 17,805,993
Office of the
Secretary RS, RA 10352
SARO-BMB-C-
13-0025079 19-Dec-13 Reconstruction of office building roof 1,200,000 1,200,000
RS, RA 10633
SARO-BMB-C-
14-0005816
20-May-14 Repair of office building destroyed by
Super Typhoon Yolanda 1,551,493 1,551,493
Office of the
Secretary NF, RA 10651
SARO-ROVIII-15-
0018633
9-Nov-14 Payment for the 4,530 bags of rice procured
from the NFA which were distributed to various
municipalities/cities during relief operations
after onslaught of Typhoon "Yolanda"6,115,500 6,115,500
By Year/Implementing Agency/Fund Source/SARO/Purpose
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Page 1 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
DBM Reg VINF, RA 10651,
C.A.
SARO-BMB-D-
16-000702421-Mar-16
support the construction/spot concreting with
box culvert of Brgy. Cairohan-Bulabog Farm-to-
Market Road, damaged by Typhoon "Quinta"
(2012)
8,939,000 8,939,000
Department of Education 1,110,290,000 3,859,346,000 751,932,518 5,721,568,518
Office of the
Secretary RS, RA 10352
SARO-BMB-B-
13-0024624 16-Dec-13
Provision of school seats in newly
constructed classrooms (119,070
armchairs and 2,646 teacher's table and
chair) 94,905,000 94,905,000
RS, RA 10352
SARO-BMB-B-
13-0024780 16-Dec-13 Repair and rehabilitation of classrooms 974,076,000 974,076,000
RRP, RA 10633
SARO-BMB-B-
14-0006064
27-May-14
Repair and rehabilitation of classrooms 1,000,000,000 1,000,000,000
RS, RA 10352
SARO-BMB-B-
13-0005589 30-May-13 Classroom Repairs (2013 BEFF) 40,169,0004/
40,169,000
RS, RA 10352
ABM-BMB-B-13-
0001192 4-Jan-13 Temporary learning spaces - 1,140,000 4/ 1,140,000
RS, RA 10352,
C.A
issued thru a
letter authority 11-Nov-14
Construction and/or renovation Library
Hubs (Leyte Province) 2,000,000 2,000,000
RS, RA 10352,
C.A
issued thru a
letter authority 11-Nov-14
Construction and/or renovation Library
Hubs (Ormoc City) 2,000,000 2,000,000
RS, RA 10352,
C.A
issued thru a
letter authority 11-Nov-14
Construction and/or renovation Library
Hubs (Tacloban City) 2,000,000 2,000,000
RS, RA 10352,
C.A
SARO-BMB-B-
14-0009823 22-Jul-14
Construction, repair, rehabilitation,
including provision of furniture of
schools 2,300,000,0002/
2,300,000,000
RS, RA 10633
SARO-BMB-A-
14-0005514 13-May-14 Construction of new classrooms 553,346,000 553,346,000
RF, RA 10633 C.A.
SARO-BMB-B-
15-0006265 21-May-15
Repair/ rehabilitation of school
buildings 751,932,518 751,932,518
Department of Energy 0 951,079 951,079
Office of the
Secretary AA
SARO-BMB-A-
14-0004504
15-Apr-14 Payment of customs duties and internal
revenue taxes for the importation of 3
units STC: JCB Backhoe Loaders
(donation) intended for the
reconstruction assistance on Typhoon
Yolanda-affected areas
951,079 951,079
Page 2 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
State Universities and Colleges 0 826,527,595 1,099,250,055 1,925,777,650
Repair and Reconstruction of Academic
Buildings in the ff.:
Cebu Normal
University RRP, RA 10633
SARO-ROVII-14-
0006198 29-May-14 Cebu Normal University 1,238,1781/
1,238,178
Cebu
Technological
University RRP, RA 10633
SARO-ROVII-14-
0006197 29-May-14 Cebu Technological University 14,399,5791/
14,399,579
Romblon State
University RRP, RA 10633
SARO-ROIVB-14-
0006255 2-Jun-14 Romblon State University 23,697,758 23,697,758
Palawan State
University RRP, RA 10633
SARO-ROIVB-14-
0006251 2-Jun-14 Palawan State University 241,110 241,110
Western
Philippines
University RRP, RA 10633
SARO-ROIVB-14-
0006252 2-Jun-14 Western Philippines University 2,108,310 2,108,310
Oriental Mindoro
State University RRP, RA 10633
SARO-ROIVB-14-
0006253 2-Jun-14 Oriental Mindoro State University 6,626,700 6,626,700
Occidental
Mindoro State
University RRP, RA 10633
SARO-ROIVB-14-
0006254 2-Jun-14 Occidental Mindoro State University 1,561,600 1,561,600
Iloilo State College
of Fisheries RRP, RA 10633
SARO-ROVI-14-
0006216 30-May-14 Iloilo State College of Fisheries 16,727,339 16,727,339
Northern Iloilo
Polytechnic State
College RRP, RA 10633
SARO-ROVI-14-
0006217 30-May-14
Northern Iloilo Polytechnic State
College 94,061,887 94,061,887
Western Visayas
College for
Science
and Technology RRP, RA 10633
SARO-ROVI-14-
0006218 30-May-14
Western Visayas College for Science
and Technology 5,174,366 5,174,366
Guimaras State
College RRP, RA 10633
SARO-ROVI-14-
0006220 30-May-14 Guimaras State College 1,522,500 1,522,500
Aklan State
University RRP, RA 10633
SARO-ROVI-14-
0006221 30-May-14 Aklan State University 18,443,684 18,443,684
Univ. of Antique RRP, RA 10633
SARO-ROVI-14-
0006222 30-May-14 Univ. of Antique 20,036,180 20,036,180
Capiz State
University RRP, RA 10633
SARO-ROVI-14-
0006223 30-May-14 Capiz State University 76,902,356 76,902,356
Southern Leyte
State University RRP, RA 10633
SARO-ROVIII-14-
0006299 2-Jun-14 Southern Leyte State University 6,651,813 6,651,813
Eastern Visayas
State University RRP, RA 10633
SARO-ROVIII-14-
0006300 2-Jun-14 Eastern Visayas State University 125,041,807 125,041,807
Visayas State
Universiyt RRP, RA 10633
SARO-ROVIII-14-
0006301 2-Jun-14 Visayas State Universiyt 113,801,918 113,801,918
University of
Eastern
Philippines RRP, RA 10633
SARO-ROVIII-14-
0006302 2-Jun-14 University of Eastern Philippines 4,713,365 4,713,365
Page 3 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Northwest Samar
State University RRP, RA 10633
SARO-ROVIII-14-
0006303 2-Jun-14 Northwest Samar State University 233,808 233,808
Samar State
University RRP, RA 10633
SARO-ROVIII-14-
0006304 2-Jun-14 Samar State University 1,235,363 1,235,363
Eastern Samar
State University RRP, RA 10633
SARO-ROVIII-14-
0006305 2-Jun-14 Eastern Samar State University 217,708,830 217,708,830
Palompon
Institute of
Technology RRP, RA 10633
SARO-ROVIII-14-
0006306 2-Jun-14 Palompon Institute of Technology 21,831,564 21,831,564
Naval State
University RRP, RA 10633
SARO-ROVIII-14-
0006307 2-Jun-14 Naval State University 12,121,939 12,121,939
UPS (Tacloban
and Palo Campus) RRP, RA 10633
SARO-NCR-14-
0007231 9-Jun-14 UPS (Tacloban and Palo Campus) 39,671,955 39,671,955
TUP (Negros
Occidental
Campus) RRP, RA 10633
SARO-NCR-14-
0007233 9-Jun-14 TUP (Negros Occidental Campus) 773,686 773,686
Rehabilitation and/or repair of
damaged buildings and infrastructure of
the following SUCS:
Marinduque State
College
RRP, RA 10633,
C.A.
SARO-ROIVB-15-
0007054 3-Jun-15 Marinduque State College 486,340 486,340
Catanduanes State
University
RRP, RA 10633,
C.A.
SARO-ROV-15-
0007382 8-Jun-15 Catanduanes State University 4,374,450 4,374,450
Dr. Emilio B.
Espinosa Sr.
Memorial State
College of
Agriculture and
Technology
RRP, RA 10633,
C.A.
SARO-ROV-15-
0007891 11-Jun-15
Reconstruction/repair of buildings and
other structures damaged by Typhoon
Yolanda 14,253,400 14,253,400
Central Bicol State
University of
Agriculture
RRP, RA 10633,
C.A.
SARO-ROV-15-
0007379 8-Jun-15
Central Bicol State University of
Agriculture 6,545,053 6,545,053
Partido State
University
RRP, RA 10633,
C.A.
SARO-ROV-15-
0007377 8-Jun-15 Partido State University 3,209,010 3,209,010
Sorsogon State
University
RRP, RA 10633,
C.A.
SARO-ROV-15-
0007376 8-Jun-15 Sorsogon State University 5,973,160 5,973,160
Leyte Normal
University
RRP, RA 10633,
C.A.
SARo-ROVIII-15-
0007840 11-Jun-15 Leyte Normal University 13,294,958 13,294,958
Rehab/repair of damaged buildings and
infrastructure of Western Visayas State
University for the following campuses
Calinog Campus 21,499,435 21,499,435
Pototan Campus 8,061,005 8,061,005Western Visayas
State University
SARO-ROVI-15-
000892630-Jun-15
RRP, RA 10633,
C.A.
Page 4 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Janiuay Campus 2,656,565 2,656,565
Lambunao Campus 23,887,435 23,887,435
CAPSU, ISCOF,
NIPSC, WVSU, ASU
and UA
RRP, RA 10633,
C.A.
ROVI-15-
0020023-28 17-Nov-15
Replacement/acquisition of laboratory
equipment and facilities damaged by
typhoon "Yolanda" in FY 2013 140,699,525 140,699,525
University of the
Philippines System
RRP, RA 10633,
C.A.
SARO-NCR-15-
0021827 3-Dec-15
Replacement/acquisition of laboratory
equipment and facilities of the University
which were damaged by Typhoon "Yolanda" 49,897,700 49,897,700
Eastern Samar State Univ
RRP, RA 10633,
C.A.ROVIII-15-0020060 20-Nov-15
312,614,000 312,614,000
Eastern Visayas State Univ
RRP, RA 10633,
C.A.ROVIII-15-0020061 20-Nov-15
274,586,659 274,586,659
Leyte Normal Univ.
RRP, RA 10633,
C.A.ROVIII-15-0020063 20-Nov-15
30,485,919 30,485,919
Naval State Univ
RRP, RA 10633,
C.A.ROVIII-15-0020065 20-Nov-15
13,544,230 13,544,230
Palompon Institute of Tech
RRP, RA 10633,
C.A.ROVIII-15-0020066 20-Nov-15
19,454,000 19,454,000
Samar State Univ
RRP, RA 10633,
C.A.ROVIII-15-0020067 20-Nov-15
1,171,600 1,171,600
So. Leyte State Univ
RRP, RA 10633,
C.A.ROVIII-15-0020069 20-Nov-15
12,000,000 12,000,000
Visayas State Univ
RRP, RA 10633,
C.A.ROVIII-15-0020071 20-Nov-15
129,181,860 129,181,860
Cebu Technological
University
RRP, RA 10633,
C.A.
ROIVB-15-0021070 25-Nov-15
Replacement/acquisition of laboratory
equipment and facilities which were
damaged by Typhoon Yolanda as approved
by OP dated April 22, 2015 and Nov 9, 2015
for the purpose3,131,551 3,131,551
Western Philippines
University
RRP, RA 10633,
C.A.
ROIVB-15-0021185 26-Nov-15
Replacement/acquisition of laboratory
equipment and facilities which were
damaged by Typhoon Yolanda1,242,200 1,242,200
Palawan State
University
RRP, RA 10633,
C.A.
ROIVB-15-0022171 7-Dec-15
Replacement/acquisition of laboratory
equipment and facilities of PSU
damaged by Typhoon Yolanda4,500,000 4,500,000
Cebu Normal
University
RRP, RA 10633,
C.A.
ROIVB-15-0021068 25-Dec-15
Replacement/acquisition of laboratory
equipment and facilities which were
damaged by Typhoon Yolanda as approved
by OP dated April 22, 2015 and Nov 9, 2015
for the purpose 2,500,000 2,500,000
Western Visayas
State University
SARO-ROVI-15-
000892630-Jun-15
RRP, RA 10633,
C.A.
Replacement/acquisition of laboratory
equipment and facilities damaged by
Typhoon "Yolanda"
Page 5 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
CHED 0 4,844,525 4,844,525
AA
SARO-BMB-B-
14-0010458 31-Jul-14
Rehabilitation of CHED Regional Office
Building 4,844,525 4,844,525
Department of Environment and Natural Resources 176,558,358 0 1,000,000,000 1,176,558,358
Office of the
Secretary RS, RA 10352
Various ABMs
transferred
thru Sub
Allotments
Advice (SAA)
Rehabilitation including cash for work,
financial assistance, repair and
improvement of office building 176,258,358 176,258,358
RRP, RA 10633,
C.A.
SARO-BMB-E-
15-0000796 15-Feb-15
National Greening Program - Mangrove
and Beach Forest Development
Program 400,000,0005/
400,000,000
RRP, RA 10633,
C.A.
SARO-BMB-E-
15-0012031 28-Aug-15
National Greening Program - Mangrove
and Beach Forest Development
Program 600,000,000 600,000,000
EMB RS, RA 10352
Various ABMs
transferred
thru SAA
Calamity Assistance to EMB Personnel
(Food, medicine and clothing) 300,000 300,000
Department of Finance 2,000,000,000 2,000,000,000
Office of the
Secretary AA
SARO-BMB-C-
14-0004875
25-Apr-14 To cover the requirements of Credit
Support Fund to provide assistance to
victims in areas affected by Typhoon
Yolanda funded by the Federal Republic
of Germany - Kredintanstalt Fur
Weideraufbau - Interest Differential
Fund (KFW-IDF) Grant2,000,000,000 2,000,000,000
Department of Health 1,453,350,000 500,000,000 1,953,350,000
Office of the
Secretary RS, RA 10352
Recovery and Rehabilitation Program
for Typhoon Yolanda 453,350,000 453,350,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13
Hospitals, RHUs and BHUs Health
Services 717,410,000 717,410,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13 Hiring of health personnel 4,000,000 4,000,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13
Maternal and Child Health and
Nutrition 27,390,000 27,390,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13 Prevention of communicable diseases 1,900,000 1,900,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13 Provision of essential medicines 6,500,000 6,500,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13 Medical/Surgical Assistance 20,000,000 20,000,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13
Provision of WASH (water, sanitation,
and health facilities) 115,200,000 115,200,000
Page 6 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13 Provision of service vehicles 10,500,000 10,500,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13
Provision of Pneumococcal and
influenza vaccines for Senior Citizens 29,000,000 29,000,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13
Prevention of non-communicable
diseases 17,600,000 17,600,000
OS, RA 10352
SARO-BMB-B-
13-01354 27-Dec-13 Generation sets for hospitals 50,500,000 50,500,000
CF, RA 10352, C.A.
SARO-BMB-14-
0005520 13-May-14
Release of funds to cover the
construction of Phase 1 of Eastern
Visayas Regional Medical Center 500,000,000 500,000,000
Department of the Interior and Local Government 2,012,180,000 2,467,732,486 737,938,480 5,217,850,966
Office of the
Secretary OS, RA 10352
SARO-BMB-D-
13-01357 27-Dec-13 Municipal Halls 982,180,000 982,180,000
OS, RA 10352
SARO-BMB-D-
13-01357 27-Dec-13 Public Markets 582,350,000 582,350,000
OS, RA 10352
SARO-BMB-D-
13-01357 27-Dec-13 Civic Centers/Evacuation Centers 175,700,000 175,700,000
OS, RA 10352
SARO-BMB-D-
13-01357 27-Dec-13
DILG RO 8 and Project Administrative
Cost 51,170,000 51,170,000
Region VII CF, RA 10352, C.A.
SARO-BMB-D-
14-0006333 2-Jun-14
Rescue/Recovery/Relief and
Rehabilitation 290,702 290,702
RRP, RA 10633
SARO-BMB-D-
14-0006256 2-Jun-14
Recovery and rehabilitation assistance
for Typhon Yolanda 2,000,000,000 2,000,000,000
PNP OS, RA 10352
SARO-BMB-D-
13-01358 27-Dec-13 Police Stations 124,140,000 124,140,000
CF, RA 10352, C.A.
SARO-BMB-D-
14-0005552 4-Mar-14
Rescue/Recovery 262,897,450 262,897,450
BFP OS, RA 10352
SARO-BMB-D-
13-01359 27-Dec-13
Fire Prevention and Suppression
Activities 72,360,000 72,360,000
CF, RA 10352, C.A.
SARO-BMB-D-
14-0005517 4-Mar-14
Rescue/Recovery 189,092,900 189,092,900
BJMP OS, RA 10352
SARO-BMB-D-
13-01360 27-Dec-13
Supervision, Security and Control Over
District, City and Municipal 24,280,000 24,280,000
CF, RA 10352, C.A.
SARO-BMB-D-
14-00055194-Mar-14
Rescue/Recovery 15,451,434 15,451,434
DILG
OS, FY2014
DPWH
SARO-BMB-D-
14-002879729-Dec-15 Repair and rehabilitation of typhoon
Yolanda damaged facilities 737,938,480 737,938,480
Department of Justice 2,000,000 50,000,000 52,000,000
BUCOR RS, RA 10352
SARO-BMB-D-
13-0024597 16-Dec-13
Construction of two-storey prison
dormitory
(Leyte Regional Prison) 2,000,000 2,000,000
NBI SA, RA 10634
SARO-BMB-D-
14-0003944 7-Apr-14
Implementation of Disaster Victims
Identification (DVI) in areas affected by
Typhoon Yolanda 50,000,000 50,000,000
Page 7 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Department of Labor and Employment 113,500,933 892,726,765 1,006,227,698
Office of the
Secretary RS, RA 10352
savings and
realignment
within DOLE
authority
Skills Training and Emergency
Employment in Region VII (Northern
Cebu)8,518,750 8,518,750
Emergency Employment program (EEP)
in the following Yolanda affected
municipalities:RS, RA 10352 Region VI 7,072,913 7,072,913
RS, RA 10352 Region IV-B 9,295,293 9,295,293
RS, RA 10352
savings and
realignment
within DOLE
authority Region VIII 611,835 611,835
RS, RA 10352
two letter
authorities
18 & 26
Nov-13 Region VIII 83,502,142 83,502,142
RS, RA 10352
SARO-BMB-B-
13-0022289 9-Dec-13 Region VIII 4,500,000 4,500,000
Emergency Employment Program and
Livelihood Assistance
SA, RA 10634
SARO-BMB-D-
14-0004057 8-Apr-14 Region IVB 57,493,000 57,493,000
SA, RA 10634
SARO-BMB-D-
14-0004059 8-Apr-14 Region VI 265,947,000 265,947,000
SA, RA 10634
SARO-BMB-D-
14-0004060 8-Apr-14 Region VII 88,822,000 88,822,000
SA, RA 10634
SARO-BMB-D-
14-0004061 8-Apr-14 Region VIII 203,968,000 203,968,000
SA, RA 10634
SARO-BMB-A-
14-0006796 4-Jun-14
Recovery and rehabilitation of DOLE
Region 8 and North and West Leyte
Field Offices 6,921,000 6,921,000
PRC
RS, RA 10352,
C.A
SARO-BMB-B-
14-0009176 4-Jul-14
Rehabilitation of PRC Tacloban: Rental
Cost and Purchase of Equipment 924,765 924,765
PRC
RS, RA 10352,
C.A letter authority
Rehabilitation of PRC Tacloban: Rental
Cost and Purchase of Equipment 901,000 901,000
TESDA SA, RA 10634
SARO-BMB-D-
14-0004062 8-Apr-14
Training Programs for the Yolanda
affected regions; TESDA RO VI (P81.2M),
RO VII (P40.5M), RO VIII (P146M)267,750,000 267,750,000
Page 8 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Department of Public Works and Highways 737,000,000 2,370,492,863 1,591,646,938 46,447,342 4,745,587,143
Office of the
Secretary OS, RA 10352
SARO-BMB-A-
13-01250 13-Nov-13
Various infrastructure projects (no
details) 600,000,000 600,000,000
RS, RA 10352
realignment
within DPWH
authority
Various infrastructure projects (no
details) 137,000,000 137,000,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004984 30-Apr-14
Rehabilitation / improvement of Iloilo –
Capiz Road (old route) 4,489,0001/
4,489,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004984 30-Apr-14
Repair of Suage Bridge along Iloilo –
Capiz Road (old route), Janiuay, Iloilo 3,681,000 1/ 3,681,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004984 30-Apr-14
Repair/rehabilitation of Lambunao –
INCA Road 3,786,000 1/ 3,786,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004984 30-Apr-14
Repair / rehabilitation / improvement
of Barotac Nuevo – Polot-an, Bga. Bante
Road 13,480,0001/
13,480,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004984 30-Apr-14
Repair / rehabilitation / improvement
of Passi – Calinog Road 2,472,0001/
2,472,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004984 30-Apr-14
Repair/rehabilitation of Maasin –
Cabatuan Road 9,392,000 1/ 9,392,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004984 30-Apr-14
Rehabilitation / improvement of Baje –
San Julian – Ngingi-an – Bingawan Road 5,413,0001/
5,413,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004984 30-Apr-14
Repair / rehabilitation / improvement
of Polot-an – Pototan – Poblacion Road 3,805,0001/
3,805,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004984 30-Apr-14
Repair/rehabilitation of Pototan – Tina
– Lambunao Road 15,555,0001/
15,555,000
Rehabilitation / construction of various
flood control structures:
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
a. Canturing Flood Control along
Boundary Southern Leyte – Maasin –
Macrohon Road, Maasin City, Southern
Leyte 47,310,000 47,310,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
b. Subang Daku Flood Control along
Boundary Southern Leyte – Maasin –
Macrohon Road, Maasin City, Southern
Leyte 47,300,000 47,300,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
c. Das-ay Flood Control (Phase II)
along Junction Himay-angan – Silago –
Abuyog Road, Hinunangan, Southern
Leyte 45,990,000 45,990,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Repair of Mabuhay River Control,
K1136+127 – K1136+159, Brgy.
Mabuhay, Sison, Surigao del Norte 2,000,000 2,000,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Repair of road slip along Surigao –
Agusan Road, K1139+900 –
K1139+929.20, Sison, Surigao del Norte 200,000 200,000
Page 9 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Restoration of DPWH Dinagat covered
court, Brgy. Don Ruben, San Jose,
Dinagat Islands 350,000 350,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Restoration of DPWH stockroom
(bodega), San Jose, Dinagat Islands 205,000 205,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Construction of flood control / drainage
facilities along Cebu North Hagnaya
Wharf Road 31,500,000 31,500,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Construction of flood control / drainage
facilities along Bogo – Curva – Medellin
– Daanbantayan Road 31,500,000 31,500,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Construction of Ipil San Fernando River
Control, Ipil, San Fernando, Romblon 45,950,000 45,950,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Construction of Poblacion Magdiwang
River Control, Poblacion, Magdiwang,
Romblon 35,292,000 35,292,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Construction of Ipil Magdiwang River
Control, Magdiwang, Romblon 29,246,000 29,246,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Construction of Parpagoha River
Control, San Andres, Romblon 44,471,000 44,471,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Construction of Progreso Este River
Control, Odiongan, Romblon 37,063,000 37,063,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Construction of Cambijang River
Control, Cajidiocan, Romblon 34,197,000 34,197,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Rehabilitation of flood control
structure, Brgy. Cagmanipis, Calbayog
City, Samar 14,730,000 14,730,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Rehabilitation of flood control
structure, Brgy. Payahan, Calbayog City,
Samar 16,720,000 16,720,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
Rehabilitation of flood control
structure, Brgy. Carayman, Calbayog
City, Samar 19,200,000 19,200,000
Repair/rehabilitation of Cluster I –
Regional Office Compound
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
a. RD’s Office, Legal, ICT, ARD’s Office,
Administrative, Monitoring, Cashier,
Accounting and RDMC Office 23,933,620 23,933,620
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
b. Maintenance, Construction and
COA’s Office 22,795,640 22,795,640
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 c. BAC Office 4,094,280 4,094,280
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 d. Training/PMS and Quarters 8,568,000 8,568,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 e. Multi-purpose and Kitchen 13,816,750 13,816,750
Page 10 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 f. PJHL Office 3,012,570 3,012,570
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 g. Supply Office 2,237,200 2,237,200
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 h. Planning and Design Division 5,389,850 5,389,850
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 i. Motorpool and Canteen 8,679,690 8,679,690
Repair/rehabilitation of Cluster II –
Regional Equipment Compound
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 a. ARD’s Staff House 3,993,000 3,993,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 b. RES Staff House 3,283,000 3,283,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 c. RD’s Office Staff House 8,568,000 8,568,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
d. Multi-Purpose Building Regional
Equipment Services Compound 2,941,000 2,941,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 e. Generator Powerhouse 1,385,000 1,385,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 f. Fuel Station, RES Compound 408,000 408,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 g. Annex “A” Building, RES Compound 15,000,000 15,000,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
h. Area Base Shop Building, RES
Compound 62,000,000 62,000,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14 i. Main Building, RES Compound 14,814,000 14,814,000
CF, RA 10352, C.A.
SARO-BMB-A-
14-0004985 30-Apr-14
j. San Juanico Field Office, Staff House
and Quarters 10,000,000 10,000,000
SA, RA 10634
SARO-BMB-A-
14-0003255 24-Mar-14
Repair/maintenance of the roadside
structures and government buildings in
Cebu 140,116,700 140,116,700
SA, RA 10634
SARO-BMB-A-
14-0005400 9-May-14
Repair / rehabilitation of Candauay-
Ocoy River Control, Dumaguete City,
Negros Oriental 12,404,000 12,404,000
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
a. National Road
1. Side slope protection along
Mambusao – Imbug Road, Km 96+000 –
Km 97+700, intermittent section (1.5M)
2. Rehabilitation of national road along
junction national road Mianay – Duyoc
– Panitan Road, Km 0094+950 – Km
0095+000, with except
5,500,000 5,500,000
National Road
Page 11 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
1. Repair / resurfacing of unpaved road
shoulder along Bacolod South Road,
K0096+590 – K0099+500, with
exception, Ilog, Negros Occidental 398,000 398,000
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
2. Repair/resurfacing of unpaved road
shoulder along Bacolod South Road,
K0102+000 – K0110+000, with
exception, Cauayan, Negros Occidental
576,000 576,000
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
3. Repair / rehabilitation of slope
protection at Abutment along Bacolod
South Road, K0206+601 – K0260+616,
Brgy. Culipapa, Hinoba-an, Negros
Occidental 587,000 587,000
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
4. Repair / resurfacing of unpaved road
surface along Kabangkalan Junction
Salong Tapi Dacongcogon Banatayan
Road, K0130+000 – K0134+807, with
exception, Kabangkalan City
946,000 946,000
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
5. Repair / resurfacing of unpaved road
surface along Dancalan – Candoni
Damutan Valley Road, K0132+000 –
K0147+807, with exception, Candoni
1,579,000 1,579,000
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
6. Repair / resurfacing of unpaved road
surface along Candoni Sipalay Road,
K0144+000 – K0154+000, with
exception, Sipalay, Negros Occidental 691,000 691,000
Flood Control
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
1. Ilog Hilabangan Flood Control, Sitio
Paril, Barangay VI, Kabangkalan City
2,606,000 2,606,000
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
2. Construction of grouted rip-rap along
Bacolod South Road, K0164+000 –
K0164+900, with exception, Brgy. Gil
Montilla, Sipalay, Negros Occidental
3,000,000 3,000,000
SA, RA 10634
SARO-BMB-A-
14-0005401 9-May-14
a. National Road
1. Construction of slope protection /
coconet along Bago Mambucal Road,
Negros Occidental 1,000,000 1,000,000
1. Repair / rehabilitation /
reconstruction of Daguitan Bridge and
Approach along Maharlika Highway,
Dulag, Leyte, K0941+759
Page 12 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
SA, RA 10634
SARO-BMB-A-
14-0005443 12-May-14
a. for pier 2 and 3
45,100,000 45,100,000
SA, RA 10634
SARO-BMB-A-
14-0005443 12-May-14
b. abutment only
5,500,000 5,500,000
2. Repair / rehabilitation / construction
of Hilataban Bridge along Burauen-
Albuera Road, Burauen, Leyte
SA, RA 10634
SARO-BMB-A-
14-0005443 12-May-14
a. Bridge to Regional Office
31,900,000 31,900,000
SA, RA 10634
SARO-BMB-A-
14-0005443 12-May-14
b. Box Culvert - Central Office
4,000,000 4,000,000
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
1. Repair/rehabilitation of roadside
structure along Toledo - Naga - Uling
Road, K0037+020 1,573,660 3/ 1,573,660
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
2. Repair/rehabilitation of roadside
structure along Cebu - Toledo - Wharf
Road, K0031+800 437,0153/
437,015
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
3. Repair/rehabilitation of roadside
structure along Cebu - Toledo - Wharf
Road, K0045+250 938,7443/
938,744
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
4. Repair/maintenance of roadside
structure/road shoulder along Toledo -
Tabuelan - San Remegio Road,
K0050+485 139,892 139,892
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
5. Repair/maintenance of road shoulder
along Toledo - Tabuelan - San Remegio
Road, K0067+400 - K0068+860
94,900 94,900
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
6. Repair/maintenance of roadside
structure/road shoulder along Cebu -
Balamban Trancentral Road, K0036+000
- K0042+600 379,312 379,312
Bridges
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
1. Repair/rehabilitation of scoured
bridge footing and Piers 3 and 4 at Sangi
Bridge, Toledo City, Cebu 724,972 724,972
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
2. Repair/rehabilitation of scoured
bridge footing at Buanoy Bridge, Pier 4,
Buanoy, Balamban, Cebu 459,660 459,660
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
3. Repair/rehabilitation of scoured
bridge footing at Pondol Bridge, Pier 1,
Pondol, Balamban, Cebu 309,245 309,245
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
4. Repair/rehabilitation of Caridad
Bridge - Abutment "B", Brgy. Caridad,
Tuburan, Cebu 474,825 474,825
Page 13 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
5. Repair/rehabilitation of Campanga
Bridge - Abutment "B" Brgy. Campanga,
Barili, Cebu 759,000 759,000
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
6. Repair/rehabilitation of Ylaya Bridge
II - Abutment "B", Brgy. Ylaya, Barili,
Cebu 539,367 539,367
Flood Control
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
1. Repair/maintenance of Sta. Ana
revetment, Brgy. Sta. Ana, Barili, Cebu
1,300,000 1,300,000
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
1. Rehabilitation/reconstruction of
slope protection structure along
Santander - Barili - Toledo Road,
K0149+980 and K0163+200, Samboan
and Malabuyoc Sections 8,400,000 8,400,000
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
2.
Rehabilitation/reconstruction/reclamati
on of shore protection structures of
Poblacion, Boljoon, Cebu 43,930,000 43,930,000
SA, RA 10634
SARO-BMB-A-
14-0005860 21-May-14
3. Widening of critical/landslide section
along Natalio Bacalso Avenue,
K0101+780 - K0101+960, Boljoon, Cebu
45,260,000 45,260,000
SA, RA 10634
SARO-BMB-A-
14-0005856 21-May-14
1. Repair/rehabilitation of damaged
lined canal along Tacloban - Baybay -
South Road 2,490,000 2,490,000
SA, RA 10634
SARO-BMB-A-
14-0005856 21-May-14
2. Repair/rehabilitation of damaged
guardrails and other signages of
national road along Tacloban - Baybay -
South Road 2,080,000 2,080,000
SA, RA 10634
SARO-BMB-A-
14-0005856 21-May-14
3. Repair/restoration of damaged/drop
off pavement of national road along
Bato - Bontoc Road, K1111+900,
K1112+300, K1112+500, K1113+200,
K1113+900, K1114+900
4,670,000 4,670,000
SA, RA 10634
SARO-BMB-A-
14-0005856 21-May-14
4. Repair/restoration of eroded
shoulder/washed shouldering materials
of national road along Tacloban -
Ormoc - Baybay - Southern Leyte
Boundary Road, K1052+100,
K1063+100, K1075+300, K1097+300,
K1054+300, K1074+200, K1088+100,
K1098+400, K1112+200, K1115
7,630,000 7,630,000
Page 14 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
SA, RA 10634
SARO-BMB-A-
14-0005856 21-May-14
5. Repair/restoration of damaged slope
protection of national road and bridges
along Lapaz - Javier - Bito Road,
K0962+000 - K0971+524 at Pinocawan
Bridge, Rizal Bridge 2,800,000 2,800,000
SA, RA 10634
SARO-BMB-A-
14-0005856 21-May-14
6. Rehabilitation of Bangkerohan Flood
Control Structure along Ormoc - Baybay
- Southern Leyte Boundary Road,
Hilongos Leyte 7,430,000 7,430,000
SA, RA 10634
SARO-BMB-A-
14-0005856 21-May-14
7. Rehabilitation/repair/improvement
of Mahaplag River Flood Control,
Kinawit, Poblacion, Mahaplag, Leyte
17,120,000 17,120,000
SA, RA 10634
SARO-BMB-A-
14-0005856 21-May-14
8. Rehabilitation of Baybay seawall,
Baybay, Leyte 6,460,000 6,460,000
SA, RA 10634
SARO-BMB-A-
14-0005863 21-May-14
Repair/Rehabilitation of spillway
conecting Barangays Banban,
Arebasore, and Barras 7,910,000 7,910,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
1. Repair/rehabilitation/construction of
Bulwang Revetment Wall, Numancia,
Aklan 19,599,000 19,599,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
2. Repair/rehabilitation/construction of
Kalibo Revetment Wall, Kalibo, Aklan
19,599,000 19,599,000
Construction/repair/rehabilitation of:
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
1. Iloilo Capiz Road (new route), Km
105+100 - Km 122+568, Capiz 14,146,000 14,146,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
2. IloiloEast Coast Capiz Road, Km 106+(-
279) - Km 171+773, Capiz 21,903,000 21,903,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
3. Roxas City Boundary Panitan Bailan
Road, Km 112+(-267) - Km 122+739,
Capiz 11,303,000 11,303,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
4. Maayon Junction Bailan Road, Km
121+(-465) - Km 131+068, Capiz 7,957,000 7,957,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
5. Junction National Road Cuartero -
Mianay-Duyoc-Calaan- Panitan Road,
Km 103+(-128) - Km110+757 10,358,000 10,358,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
6. Junction National Road Cuartero -
Maindang - Tapulang Road, Km 115+(-
394) - Km 120+357, Capiz 6,883,000 6,883,000
Implementation of various
infrastructure projects :
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
1. Construction of side slope protection
along Iloilo - Capiz Road (new route),
Km 68+800 - Km 100+100 (intermittent
section) 6,770,000 6,770,000
Page 15 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
2. Construction of side slope protection
along Iloilo - Capiz Road (old route), Km
92+000 - Km 95+200 with exception
6,453,000 6,453,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
3. Road upgrading/rehabilitation along
Junction National Road Ayuyan -
Tinaytayan Road, Km 92+000 - Km
95+180 with exception 7,942,000 7,942,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
4. Side slope protection along Capiz -
Aklan Road, Km 326+000 - Km 346+000
(intermittent section) 6,777,000 6,777,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
5. Side slope protection along Sigma -
Mambusao - Jamindan Road, Km
86+000 - Km 101+800 (intermittent
section) 7,101,000 7,101,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
6. Side slope protection along Junction
Cuartero - Maindang - Tapulang -
Maayon Road, Km 89+000 - Km
101+800 (intermittent section)
6,983,000 6,983,000
Implementation of various
infrastructure projects
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
1. Concreting with slope protection
works along Bacolod South Road,
K0207+900 - K0208+356, Barangay
Culipapa, Hinob - an, Negros Occidental
8,195,000 8,195,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14
2. Construction of slope protection
works along Bacolod South Road,
Barangay Maricalum, Sipalay City
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14 a. K0170+400 - K0170+420 3,781,000 3,781,000
SA, RA 10634
SARO-BMB-A-
14-0006022 26-May-14 b. K0171+300 - K0171+326 2,079,000 2,079,000
SA, RA 10634
SARO-BMB-A-
14-0006246 2-Jun-14
1. Construction of Slope Protection
along DM-Junction-Legaspi-Sto.
Domingo-Tabaco-Tiwi-Camarines Sur
Boundary Road, Tiwi, Albay KO574+945-
575+219 & KO575+300-575+480 16,050,000 1/16,050,000
SA, RA 10634
SARO-BMB-A-
14-0006246 2-Jun-14
2. Construction of Slope Protection
along DM Junction-Legaspi- Sto
Domingo-Tabaco-Tiwi-Camarines Sur
Boundary Road, Tiwi, Albay KO577+400-
577+582 & KO578+600-579+140 16,000,000 1/ 16,000,000
Page 16 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
SA, RA 10634
SARO-BMB-A-
14-0006246 2-Jun-14
3. Construction of Slope Protection
along DM Junction-Legaspi- Sto
Domingo-Tabaco-Tiwi-Camarines Sur
Boundary Road, Tiwi, Albay KO580+200-
580+301 & KO581+700-581+791 15,280,000 1/15,280,000
SA, RA 10634
SARO-BMB-A-
14-0006246 2-Jun-14
4. Basud River Control, Basud, Sto
Domingo, Albay (Sta. 0+000 - Sta.
0+250) 12,760,000 1/12,760,000
SA, RA 10634
SARO-BMB-A-
14-0006246 2-Jun-14
5. Tuliw River Control, Tuliw,
Malinao, Albay (Sta. 0+000 - Sta. 0+113) 12,435,000 1/12,435,000
SA, RA 10634
SARO-BMB-A-
14-0006246 2-Jun-14
6. Basud River Control, Labanon,
Bacacay, Albay (Sta. 0+000 - Sta. 0+113) 13,500,000 1/13,500,000
SA, RA 10634
SARO-BMB-A-
14-0006246 2-Jun-14
7. Repair/Improvement of Line Canal
along DMT-Junction-Legaspi-Sto
Domingo-Tabaco-Tiwi-Camarines Sur
Boundary (Cararayan Section), Tiwi,
Albay 4,125,000 1/4,125,000
SA, RA 10634
SARO-BMB-A-
14-0006794 4-Jun-14
Repair/rehabilitation of Llorente River
Flood Control (Phase II), Llorente
Eastern Samar 28,880,000 28,880,000
SA, RA 10634
SARO-BMB-A-
14-0007241 10-Jun-14
1. Construction of Arpili Revetment,
Balamban, Cebu, K0055+301 19,030,000 19,030,000
SA, RA 10634
SARO-BMB-A-
14-0007241 10-Jun-14
2. Construction of Buanoy Revetment,
Balamban, Cebu, K0059+115 37,750,000 37,750,000
SA, RA 10634
SARO-BMB-A-
14-0007241 10-Jun-14
3. Construction of Barili Revetment,
Barili, Cebu, K0060+800 19,030,000 19,030,000
SA, RA 10634
SARO-BMB-A-
14-0007241 10-Jun-14
4. Construction of Suba Revetment,
Tuburan, Cebu,K0096+309 37,750,000 37,750,000
SA, RA 10634
SARO-BMB-A-
14-0009054 2-Jul-14
1. Loading of hauling GI sheets, various
affected municipalities in Leyte and
Samar 2,656,426 2,656,426
SA, RA 10634
SARO-BMB-A-
14-0009054 2-Jul-14
2. Digging/excavation of grave sites,
Tacloban City, Tanauan and Palo City 32,967 32,967
SA, RA 10634
SARO-BMB-A-
14-0009054 2-Jul-14
3. Debris collection and clean-up
operation, Tacloban City and Palo, Leyte 12,234,390 12,234,390
SA, RA 10634
SARO-BMB-A-
14-0009054 2-Jul-14
4. Immediate repair/rehabilitation of
damaged Tacloban DZR Airport,
Tacloban City 886,908 886,908
SA, RA 10634
SARO-BMB-A-
14-0009054 2-Jul-14
5. Clearing of the following waterways
including disposal of debris: 5,080,000 5,080,000
Page 17 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
a. Clearing of waterways along
Burayan Creek
b. Clearing designated site of
temporary shelters at Brgy. Abucay
government Center, Palo, leyte and
Brgy. Caiban along Maharlika Highway
c. Clearing/disposal of debris within
area equipment services compund
d. Clearing of Astrodome
e. Clearing/cleaning activities at
Daniel Z. Romualdez (DZR) Airport
Terminal Building
f. Clearing debris at Deped office
compund
g. Clearing/ leveling of disposed
debris at designated dump sites
h. Clearing of debris/ logs at Daguitan
Bridge
SA, RA 10634
SARO-BMB-A-
14-0009055 2-Jul-14
1. Rehabilitation/reconstruction of
drainage along Picas-San Jose-daniel Z.
Rodriguez (DZR) Airport, Tacloban City 1,363,000 1,363,000
SA, RA 10634
SARO-BMB-A-
14-0009055 2-Jul-14
2. Emergency
repair/rehabilitation/construction of
flood control structure along Tanghas -
Lirang Creek and drainage structures,
Tacloban City 14,420,000 14,420,000
SA, RA 10634
SARO-BMB-A-
14-0009167 4-Jul-14
1. Rehabilitation/Construction of Road
Slip along Burauen-Mahagnao Road,
Burauen, Leyte, K0988+200 and
K0989+800 18,292,370 18,292,370
SA, RA 10634
SARO-BMB-A-
14-0009167 4-Jul-14
2. Repair/rehabilitation of Dulag
Seawall, Brgy. San Jose / Luan, Dulag,
Leyte, K0936+685 – K0936+935 19,220,877 19,220,877
SA, RA 10634
SARO-BMB-A-
14-0009167 4-Jul-14
3. Repair/rehabilitation/reconstruction
of Bil-at Seawall along Maharlika
Highway, Dulag, Leyte, K0934+816 –
K0935+000 19,286,923 19,286,923
SA, RA 10634
SARO-BMB-A-
14-0009167 4-Jul-14
4. Repair/rehabilitation/reconstruction
of damaged slope
protection/revetment wall along Jaro-
Dagami-Burauen-La Paz Road, Burauen,
Leyte, K0976+580 – K0976+603 6,041,686 6,041,686
Page 18 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
SA, RA 10634
SARO-BMB-A-
14-0009167 4-Jul-14
5. Rehabilitation/construction of box
culvert (Malitbog River) along Burauen-
Albuera Road, Burauen, Leyte,
K0976+027.90 8,613,664 8,613,664
SA, RA 10634
SARO-BMB-A-
14-0009167 4-Jul-14
6. Construction of Double Barrel Box
Culvert along Burauen-Mahagnao Road,
Burauen, Leyte, K0985+800 7,001,060 7,001,060
SA, RA 10634
Implementation of various
infrastructure projects
SA, RA 10634
SARO-BMB-A-
14-0009537 15-Jul-14
1. Fabrication/ installation of Tetrapods
along Bato Flood Control, K0939+500 -
K0940+365 along Borongan-Guiuan
Road 44,540,000 44,540,000
SA, RA 10634
SARO-BMB-A-
14-0009537 15-Jul-14
2. Fabrication/ installation of Tetrapods
along Bato Flood Control, K0993+000 -
K0993+800 along Borongan-Guiuan
Road 44,975,000 44,975,000
SA, RA 10634
SARO-BMB-A-
14-0009537 15-Jul-14
3. Fabrication/ installation of Tetrapods
along Cabay - Balangkayan Flood
Control, K0967+200 -K0968+000 along
Borongan-Guiuan Road 44,935,000 44,935,000
SA, RA 10634
SARO-BMB-A-
14-0009922 23-Jul-14
Repair/rehabilitation of Somoje Flood
Control, Somoje, San Juan, Southern
Leyte 5,672,000 5,672,000
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Basic housing assistance in Regions VI
and VIII 58,800,000 58,800,000
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Additional Basic Housing assistance in
Regions VI and VIII 88,200,000 88,200,000
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Roofing of various school buildings in
Region VIII 28,519,470 28,519,470
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Major repair of the 2-storey DBM
Regional Office Building in Region VIII 3,138,079 3,138,079
Construction/restoration of
infrastructure projects:
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Construction of single box culveret,
Baras, Palo, Leyte 1,487,302 1,487,302
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Restoration of Daniel Z. Romualdez
Airport - San Jose Baras Road,
Candahug Section, Palo Leyte 45,521,166 45,521,166
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Construction of Payapay Bridge
Approach along San Jose Manlurip
Road, Candahug, Palo, Leyte 3,894,683 3,894,683
Repair/rehabilitation projects in Eastern
Samar
Page 19 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Repair/rehabilitation/improvement of
Bato Flood Control along Borongan-
Guian Road, K0939+500-K0940+365,
Borongan City 46,117,000 46,117,000
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Repair/rehabilitation/improvement of
Suribao Flood Control along Borongan-
Guian Road, K0951+000-K0951+716,
Borongan City 13,826,000 13,826,000
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Repair/rehabilitation/improvement of
Cabay, Balangkayan Flood Control along
Borongan-Guian Road, K0967+200-
K0968+000, Balangkayan 9,050,000 9,050,000
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Repair/rehabilitation/improvement of
Hernani Flood Control along Borongan-
Guian Road, K0993+000-K0993+800,
Hernani 46,632,000 46,632,000
SA, RA 10634
SARO-BMB-A-
14-001173 11-Aug-14
Repair/rehabilitation/improvement of
eroded shoulder along Junction
Buenavista-Lawaan Road, K0995+680;
K0953+990-K0954+600; K0955+300-
K0955+620 18,905,000 18,905,000
NF, RA 10633
SARO-BMB-A-
14-0015815 14-Oct-14
Repair/rehabilitation of Borongan
Seawall along Wright/Taft-Borongan
Road, K0920+350-K0920+800,
Borongan, Eastern Samar 41,400,000 41,400,000
NF, RA 10633
SARO-BMB-A-
14-0015815 14-Oct-14
Repair/rehabilitation of Brgy. Sto. Nino
Seawall along Wright/Taft-Borongan
Road, K0889+100-K0889+700, Sulat,
Eastern Samar 41,600,000 41,600,000
NF, RA 10633
SARO-BMB-A-
14-0015815 14-Oct-14
Repair/rehabilitation of Nabuangan
Seawall along Wright/Taft-Borongan
Road, K0901+500-K0902+100, Sulat,
Eastern Samar 39,900,000 39,900,000
NF, RA 10633
SARO-BMB-A-
14-0015815 14-Oct-14
Repair/rehabilitation of Revetment,
Barangay 6 Poblacion, San Julian along
Wright/Taft-Borongan Road, K0918+800-
K0919+100, San Julian, Eastern Samar 9,800,000 9,800,000
NF, RA 10633
SARO-BMB-A-
14-0015815 14-Oct-14
Repair/rehabilitation of Barangay
Pagbabangan Seawall, K0920+350-
K0920+800, San Julian, Eastern Samar 35,600,000 35,600,000
NF, RA 10633
SARO-BMB-A-
14-00127756 29-Dec-14
Construction of access road, Pago
Resettlement Site, Pago, Tanauan, Leyte 2,000,000 2,000,000
Page 20 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Mindoro
Occidental DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/restoration of Mindoro West
Coastal Road, Barokan-Sahing Section,
K0306+770 – KO307+010, Barangay Sta.
Lucia, Sablayan 24,200,000 24,200,000
Mindoro Oriental
DEO
Repair/restoration of Calapan North
Road
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
a. Km 40+020-Km 40+039.80, Puerto
Galera 1,447,000 1,447,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
b. Km 41+800 – Km 41+812.80 Puerto
Galera 955,000 955,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
c. Km 45+100, Puerto Galera
5,000,000 5,000,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
d. Km 22+900, San Teodoro
1,500,000 1,500,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
e. Km 40+500, Puerto Galera
2,000,000 2,000,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
f. Km 58+150, Puerto Galera
1,500,000 1,500,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
g. Km 59+850, Puerto Galera
600,000 600,000
Southern Mindoro
DEO
Repair/restoration of Calapan South
Road
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
a. K0115+275.60 – K0115+295.10
248,000 248,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
b. K0115+343.70 – K0115+387.90
558,500 558,500
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
c. K0116+414.40 – K0116+428.40
377,500 377,500
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
d. K0119+143.50 – K0119+225.40
866,000 866,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
e. K0160+540.20 – K0160+519.20
536,000 536,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
f. K0169+642 – K0169+682
476,500 476,500
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
g. K0170+788.70 – K0170+820
381,000 381,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
h. K0171+807.60 – K0171+847.60
472,000 472,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
i. K0116+167.40 – K0116+179.90
346,000 346,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/maintenance of Orcunoma River
Control (Upstream), Bongabong2,300,000 2,300,000
Repair/restoration of Mindoro
Oriental/Occidental East Coast Road
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
a. K0194+740.20 – K0194+768
298,100 298,100
Page 21 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
b. K0195+073.30 – K0195+132.18
564,000 564,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
c. K0198+242.30 – K0198+257.30
178,200 178,200
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/restoration of Bansud Seawall,
Sta. 0+260 – Sta. 0+305 1,700,000 1,700,000
Palawan 3rd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of Roadside Structure,
K0044+500 – K0044+516, Junction
Puerto Princesa South Road (PPSR) –
Napsan -Apurawan Road, Barangay
Napsan, Puerto Princesa City 1,636,500 1,636,500
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of drainage Structures,
K0213+300, K-0212+500 & K0207+320,
Aramaywan-Berong-Puerto Princesa
Road, Aborlan, Palawan
993,500 993,500
Romblon DEO
Repair/rehabilitation of Damaged
Slope/Shore Protection along Tablas
Circumferential Road (Naabang
Section)RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
a. K0080+480-K0081+032.50
19,000,000 19,000,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
b. K0081+100 – K0081+397.50
17,000,000 17,000,000
Repair/maintenance of Damaged Road
Sections along Tablas Circumferential
RoadRRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
a. K0040+800 – K0040+900
8,704,000 8,704,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
b. K0041+200 – K0041+250
9,081,000 9,081,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
c. K0042+050 – K0042+085
2,608,000 2,608,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
d. K0044+950 – K0044+975
1,243,000 1,243,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
e. K0110+060 – K0110+080
797,000 797,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
f. K0007+150 – K0007+200
2,817,000 2,817,000
Albay 2nd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Legaspi City-
Punta de Jesus Road, K0552+000 –
K0574+000, Manito, Albay 2,680,000 2,680,000
Catanduanes DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/maintenance of Line Canal along
Caramoran-San Andres Road Section,
Tubli, Caramoran, Catanduanes
(K0126+800) 2,000,000 2,000,000
Page 22 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Emergency Repair/maintenance of
Slope Protection along Viga-Bagamanoc
Road Section, Del Pilar, Viga,
Catanduanes (K0047+300) 500,000 500,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
WC-II Resurfacing Unpaved Road
Surface along Baras-Gigmoto-Viga Road
Section with Exception, San Vicente-
Sioron-Sicmil, Catanduanes 182,000 182,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
WC-II Resurfacing Unpaved Road
Surface along Baras-Gigmoto-Viga Road
Section with Exception, Tinago-Soboc-
Buenavista, Catanduanes 280,000 280,000
Antique DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Iloilo-Antique Road,
Paliwan Bridge approach (South
Approach), Barangay Cubay North,
Bugasong, Antique 12,071,000 12,071,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Bugasong-Valderama
Road, Barangay Ilaures, Bugasong,
Antique 19,140,000 19,140,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Odion-Sibalom-San
Remegio-Leon Road, Barangay
Aningalan, San Remigio, Antique 6,521,000 6,521,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/maintenance of DPWH
Office/Warehouse Building, Antique
DEO, San Jose, Antique 172,000 172,000
Iloilo 2nd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Construction of slope protection and
concreting of shoulder along Passi-
Calinog road, K0050+482 – K0051+232
with exception, Iloilo 10,070,000 10,070,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Upgrading/concreting of Balabag-
Maquina-Cayos-Patlad Road including
slope protection, K0284+865 –
K0289+886 with exception, Iloilo80,120,000 80,120,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Construction of Slope Protection and
Concreting of Shoulder along Polot-an-
Pototan-Poblacion Road, K0279+(-777)
– K0279+250 with exceptions, Iloilo2,710,000 2,710,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Construction of Slope Protection and
Concreting of Shoulder along Iloilo-
Capiz road (New Route), K0042+000 –
K0057+300 with exceptions, Iloilo 13,390,000 13,390,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Construction of Slope Protection and
Concreting of Shoulder along Iloilo East
Coast-Capiz Road, K0280+400 –
K02822+500 with exceptions, Iloilo 8,230,000 8,230,000
Page 23 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Construction of Slope Protection of
Abutments A & B of Punong Grande
Bridge along Dueñas-Diversion Road,
K0045+631, Iloilo; L =22.00 lm 1,311,000 1,311,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/maintenance of Maquina Bridge
Approach along Balabag-Maquina-
Cayos-Patlad Road, K0287+163, Iloilo; L
= 29.80 lm 2,840,000 2,840,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Balabag River Control,
Sta. 1+120 – Sta. 0+336, Iloilo; L = 0.216
km 26,180,000 26,180,000
Aklan DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation/construction of
Tambak Seawall, New Washington,
Aklan 51,626,000 51,626,000
Iloilo 4th DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Slope Protection and
Drainage along Cabatuan-New Lucena-
Banga-Bante Road, New Lucena, Iloilo1,404,000 1,404,000
Iloilo 2nd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation / reconstruction /
replacement / retrofitting of Baje
Bridge, Barangay Calinog, Calinog, Iloilo18,296,000 18,296,000
Iloilo 3rd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Passi-Sara
Road, K0069+(-345)-K0097+750
(Intermittent Section), Iloilo 4,988,000 4,988,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Ajuy-
Conception Road, K0215+(-097)-
K0220+925, Iloilo 4,916,000 4,916,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Concepcion-
San Dionisio Road,K0219+381-
K0220+161,Iloilo 7,650,000 7,650,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Iloilo East Coast-
Capiz Road, K0171+(-251) -K0150+669
(Intermittent Section), Iloilo7,747,000 7,747,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of San Dionisio-
Capinang Road, K0198+(-880) -
K0203+039 (Intermittent Section), Iloilo997,000 997,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Sara-San
Dionisio Road, K0203+(-350)-K0207+598
(Intermittent Section), Sara and San
Dionisio, Iloilo 998,000 998,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Iloilo East Coast
Estancia Wharf, K0182+965-K0183+408,
Iloilo 9,721,000 9,721,000
Page 24 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Sara-
Concepcion Road, K0217+720-
K0218+105, Concepcion Iloilo 1,995,000 1,995,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Balasan-Carles
Road, K0174+(-099)-K0186+455,
(Intermittent Section), Balasan and
Carles, Iloilo 1,995,000 1,995,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Barotac Viejo-
San Rafael Road, K0075+(-801)-
K0091+1000, (Intermittent Section),
Barotac Viejo and San Rafael, Iloilo 1,995,000 1,995,000
Capiz 1st DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Planning,
Accounting, Construction Section and
Motor Pool at the DPWH Compound,
Km I, Roxas City 4,852,851 4,852,851
Capiz 2nd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Reconstruction/rehabilitation of DPWH
Main Building Office, Barangay
Consolacion, Dumalag, Capiz2,500,000 2,500,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Construction of Slope Protection along
Junction North Road Dumarao-San
Rafael Road, Km 82+500 –Km 83+0001,500,000 1,500,000
Cebu 3rd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Arpili revetment along
Toledo-Tabuelan-San Remegio Road,
K0055+300 – K0055+389.19 1,200,000 1,200,000
Tacloban City DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair / rehabilitation / reconstruction
of drainage system along Magsaysay
Boulevard, Tacloban City K0909+295 –
K0910+244, with exception19,620,000 19,620,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation / reconstruction of Shore
Protection along Magsaysay Boulevard,
Tacloban Cty, K0909+390 - K0909+430,
K0909+867 - K0909+878, K0910+075 -
K0910+240
40,000,000 40,000,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Flood Control
Structure along Burayan River, Tacloban
City 3,682,000 3,682,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Flood Control
Structure along Esperas Avenue
(Magallanes Old Road), Tacloban City 28,560,000 28,560,000
Leyte 1st DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Construction / rehabilitation of Flood
Control along Daang Maharlika Highway
K0922+527 – K0922+927, Barangay Sto.
Niño, Tanauan, Leyte 4,530,000 4,530,000
Page 25 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Leyte 1st DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Tigbao-Pulak-Sta. Fe
Road (Road ID S00039LT) Road Slip and
Slope Protection, San Isidro, Sta. Fe,
Leyte K0910+369- K0910+900 18,100,000 18,100,000
Leyte 1st DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Critical Section (Road
Slip) along Palo-Carigara-Ormoc Road,
(S00034LT) K0935+182 – K0935+332,
Barangay Binongtoan, Alangalang, Leyte30,000,000 30,000,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Dapdap Flood Control
along Palo-Carigara-Ormoc Road,
(S00034LT), K0928+673 Bridge ID
(B00047LT), Barangay Dapdap,
Alangalang, Leyte 1,960,000 1,960,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Lingayon Flood
Control along Palo-Carigara-Ormoc
Road, (S00034LT), K0927+227, Bridge ID
(B00046LT), Lingayon, Alangalang, Leyte2,000,000 2,000,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Restoration of Palo-East by Pass Road,
Salvacion-Baras, Palo, Leyte, Newly
Constructed Road, (K0917+763.3 –
K0917+863.3), Barangay Baras, Palo,
Leyte 4,251,900 4,251,900
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Restoration of Revetment Works, San
Joaquin Flood Control, K0916+911
(Abutment A, Cogon Section), Barangay
Cogon, Palo, Leyte1,739,200 1,739,200
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Candahug
Shoreline Protection along Baras-
Candahug-DZR Airport Road,
(K0916+031 – K0916+431), Candahug,
Palo, Leyte 23,916,000 23,916,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation/reconstruction of
Kaurangan Flood Control (K0917+000 –
K0919+000), Palo, Leyte
39,323,600 39,323,600
Leyte 2nd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair / rehabilitation / reconstruction
of Damaged PCCP and Slope
Protection/Revetment Wall along Jaro-
Dagami-Burauen-La Paz Road, Burauen,
Leyte, K0975+966 – K0976+1067,300,000 7,300,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation / reconstruction of
Spillway (Matagara River) along
Burauen-Albuera Road, Burauen, Leyte,
K0991+585 3,000,000 3,000,000
Page 26 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Leyte 3rd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of Roadslip along Calubian-San
Isidro-Tabango-Villaba-Palompon Road,
K1014+249 – K1014+530, San Isidro
7,505,000 7,505,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of Roadslip along Calubian-San
Isidro-Tabango-Villaba-Palompon Road,
K1015+800 – K1015+900, San Isidro
2,045,000 2,045,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of Roadslip along Calubian-San
Isidro-Tabango-Villaba-Palompon Road,
K1026+200 – K1026+300, Tabango
3,574,000 3,574,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of Roadslip along Calubian
Junction-San Isidro-Tabango-Villaba-
Palompon Road (installation of RCBC),
K1039+500, Villaba 1,394,000 1,394,000
Leyte 4th DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation/reconstruction of Critical
Section along National Roads, Road Slip
along Palo-Carigara-Ormoc Road,
K1001+870 – K1001+900 1,360,000 1,360,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Tugbong Flood Control
along Libunao-Matag-ob-Palompon
Road, K0992+67 5,000,000 5,000,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Bao Flood Control
along Palo-Carigara-Ormoc Road,
K0908+616 6,600,000 6,600,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Palanas Flood Control
along Ormoc-Baybay-Southern Leyte
Boundary Road, K01031+710
9,360,000 9,360,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Calingatnan Flood
Control along Ormoc-Baybay-Southern
Leyte Boundary Road, K01028+0884,690,000 4,690,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Bacan Flood Control
along Ormoc-Baybay-Southern Leyte
Road, K01034+265 4,230,000 4,230,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Sibugay Flood Control
along Ormoc-Baybay-Southern Leyte
Boundary Road, K01027+113
1,460,000 1,460,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of Bagongbong Flood
Control along Ormoc-Baybay-Southern
Leyte Boundary Road, K01018+334
2,310,000 2,310,000
Page 27 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation of DPWH Office Building,
Leyte 4th District Engineering Office,
Barangay Punta, Ormoc City4,596,000 4,596,000
Northern Samar
2nd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/improvement of Bantayan River
Control along Catarman (Boundary) -
Rawis Road, Bantayan-San Roque
section, K0768+100 – K0768+200, San
Roque, Northern Samar
17,809,000 17,809,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/improvement of Dale River
Control along Catarman (Boundary) -
Rawis Road, Dale-Pambujan Section,
KO773+800 – KO773+900, San Roque,
Northern Samar 17,794,000 17,794,000
Biliran DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of DPWH Biliran
District Engineering Office, Barangay
Calumpang, Naval, Biliran 3,340,959 3,340,959
Biliran DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of Washed-out Shoulders,
Clogged-up Waterways and Road Slip
along Biliran Circumferential Road
(Culaba-Caibiran Section) K1083+000 –
K1093+000 12,513,000 12,513,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of Damaged Slope Protection
along Biliran circumferential Road
(Culaba-Caibiran Section) 4,676,000 4,676,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of Damaged Slope Protection
along Naval-Caibiran Cross Country
Road 1,869,000 1,869,000
Eastern Samar
DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Balangkayan
Seawall along Borongan-Guiuan Road,
K0936+300 – K0936+940, Balangkayan41,300,000 41,300,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Barangay Del
Remedio Seawall along Wright-Taft-
Borongan Road, Sulat K0906+500 –
K0907+150, Sulat 41,600,000 41,600,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Barangay Nato
Seawall along Junction Taft-Oras-
Arteche Road,
K0893+300 – K0893+700, Taft 20,100,000 20,100,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Guinob-an
Seawall along Junction Buenavista-
Lawaan Road, Lawaan, K0955+200 –
K0955+400, Lawaan 7,700,000 7,700,000
Eastern Samar
DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/rehabilitation of Maintenance
Repair Shop, Area III Equipment
Services, Borongan City 1,401,648 1,401,648
Page 28 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Rehabilitation / replacement of Roofing
and Framing Part of Workshop Building
1 & 2 at Area III, Equipment Services,
Borongan City 2,267,523 2,267,523
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair/improvement of DPWH Building,
Guiuan, Eastern Samar 926,256 926,256
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0000728 4-Feb-15
Repair of Damaged DPWH building,
Barangay Cabong, Borongan City,
Eastern Samar 6,860,197 6,860,197
NF, RA 10633, C.A.
SARO-BMB-A-
15-0001769 23-Feb-15
Procurement of construction materials
for the victims of Typhoon Yolanda in
regions IV-B, VI and VIII, see details
below:
Accessories for Housing Roof Materials
for use of Families affected by typhoon
Yolanda at Regions VI and VIII
NF, RA 10633, C.A.
SARO-BMB-A-
15-0001769 23-Feb-15
Umbrella nails (20,600 kgs.)
1,236,000 1,236,000
NF, RA 10633, C.A.
SARO-BMB-A-
15-0001769 23-Feb-15 Common Wire Nails (20,600kgs.) 824,000 824,000
Housing and School Building Roof
Assistance to various affected by
typhoon Yolanda
NF, RA 10633, C.A.
SARO-BMB-A-
15-0001769 23-Feb-15
44,190 pcs. Of G.I. sheets
21,653,100 21,653,100
NF, RA 10633, C.A.
SARO-BMB-A-
15-0001769 23-Feb-15
umbrella nails (7,600 kgs.)
456,000 456,000
Housing Roof Assistance for Region IV-B
NF, RA 10633, C.A.
SARO-BMB-A-
15-0001769 23-Feb-15
Common Wire Nails (7,600 kgs.)
304,000 304,000
Balance of umbrella nails for school
building repair at Region VIII
NF, RA 10633, C.A.
SARO-BMB-A-
15-0001769 23-Feb-15
umbrella nails (5,113 kgs.)
306,780 306,780
Mindoro Oriental
DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Rehabilitation.reconstruction of Gabion
at Gutad, Calapan City, Oriental
Mindoro (Sta.0+000 - Sta. 0+247)
13,130,000 13,130,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Rehabilitation.reconstruction of Gabion
at Alag River, Baco, Oriental Mindoro
(Sta.0+000 - Sta. 0+304)
18,440,000 18,440,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Rehabilitation.reconstruction of San
Rafael Gabion,San Teodoro, Oriental
Mindoro (Sta.0+000 - Sta. 0+304) 18,070,000 18,070,000
Page 29 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Rehabilitation/ reconstruction of
Dulangan Rier Control, Puerto Galera,
Oriental Mindoro 14,070,000 14,070,000
Leyte 2nd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Repair/rehabilitation/imrovement of
Flood Control, Barugo-Carigara Road
K0492+396, Barangay Can-isak, Barugo,
Leyte 15,407,000 15,407,000
Samar 1st DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Rehabilitation/improvement of
concrete revetment flood contol
structure in the Municipality of San
Jorge, Samar 131,884,000 131,884,000
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Rehabilitation/improvement of flood
control structure, Barangay San
Joaquin, Tinambacan District, Calbayog
City, Samar 15,707,153 15,707,153
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Rehabilitation/improvement of flood
control structure, Barangay Peña (Phase
II), Tinambacan District, Calbayog City,
Samar 16,851,203 16,851,203
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Rehabilitation/improvement of flood
control structure, Barangay Malaga
(Phase II), Tinambacan District,
Calbayog City, Samar 13,865,944 13,865,944
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0001770 23-Feb-15
Repair/ improvement of Drainage
System along Daang maharlika,
(S00062SM), Barangay Ba-ay,
K0709+800 - K0711+100, Calbayog City,
Samar 5,760,393 5,760,393
Central Office NF, RA 10633, C.A.
SARO-BMB-A-
15-0001791 23-Feb-15
Construction of 20 units of Bunkhouses
in Concepcion and Estancia, Iloilo5,983,956 5,983,956
Central Office NF, RA 10633, C.A.
SARO-BMB-A-
15-0003571 24-Mar-15
Procurement of roofing accessories and
other construction kit as "Basic
Assistance Program" for the families
affected by Typhoon Yolanda in Regions
VI and VIII 10,262,500 10,262,500
Romblon DEO
Repair and rehabilitation of ports in
Romblon:
1. Port of San Agustin, Poblacion, San
Agustin 29,963,000 29,963,000
2. Port of Carmen, Carmen, San Agustin,
Tablas 19,246,000 19,246,000
3. Port of Cajidiocan, Poblacion,
Cajidiocan, Sibuyan Island 19,843,000 19,843,000
4. Port of Alcantara, Poblacion,
Alcantara, Tablas Island 30,628,000 30,628,000
5. Port of Malbog, Malbog, Looc, Tablas
Island 37,144,000 37,144,000
24-Mar-15NF, RA 10651SARO-BMB-A-
15-0003573
Page 30 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Regional Office
VIII and Eastern
Samar DEO NF, RA 10651
SARO-BMB-A-
15-0003574 24-Mar-15
Site clearing/ development
activities/programs for the victims of
Typhoon Yolanda 23,511,755 23,511,755
Samar 2nd DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/improvement of flood control
structures along Lawaan River, Bgrys.
Palaypalay and Buscada, Basey, Samar
64,690,995 64,690,995
Leyte 1st DEO RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Rehabilitation of DPWH Leyte 1st DEO
(Quarter House) Sto. Niño, Tanauan,
Leyte 19,613,595 19,613,595
Leyte 5th DEO RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Construction/rehabilitation of flood
control structure (Phase III), Baybay
City, Southern Leyte 22,076,000 22,076,000
Northern Samar
2nd DEO RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation of Pangpang-
Palapag Mapanas-Gamay-Lapinig Road
(S00037SM), Mapanas Anito Section
K0831+000-K0832-000 4,570,000 4,570,000
Northern Samar
2nd DEORRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/reinstallation of damaged
guardrails along Catarman-Rawis Road,
Rawis-Catubig Road, Catubig-Las Navas 7,397,000 7,397,000
Samar 1st DEO RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation/improvement of
motorpool building, DPWH Calbayog
City, Samar 3,197,000 3,197,000
Tacloban City DEO RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Road rehabilitation along San Jose -
Candahug Road K0913+(-956)-
K0914+000, Tacloban City 37,169,000 37,169,000
Leyte 5th DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation of slope
protection at abutment of Bartolini
Bridge along Tacloban-Baybay-Maasin
Road K1038+249, Baybay City, Leyte1,114,000 1,114,000
Leyte 5th DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation of slope
protection at abutment of Lunsoc
Bridge along Tacloban-Baybay-Maasin
Road K1047+145, Baybay City, Leyte1,193,000 1,193,000
Leyte 5th DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation of slope
protection at abutment of Cambanoy
Bridge along Tacloban-Baybay-Maasin
Road K1048+090, Baybay City, Leyte1,193,000 1,193,000
Leyte 5th DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation of slope
protection at abutment of Calbig-a
Bridge along Tacloban-Baybay-Maasin
Road, K1049+916, Baybay City, Leyte785,000 785,000
Page 31 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Leyte 5th DEORRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation of slope
protection at abutment of Bagalongon
Bridge along Maharlika Highway,
K0976+057, Abuyog, Leyte 305,000 305,000
Leyte 5th DEORRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation of slope
protection at abutment of Sewing
Bridge along Lapaz-Javier-Bito Road,
K0969+643, Javier, Leyte 203,000 203,000
Leyte 5th DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation of slope
protection at abutment of Kangapo
Bridge along Tacloban-Baybay-Maasin,
K1043+324, Baybay City, Leyte504,000 504,000
Leyte 5th DEO
RRP, RA 10633,
C.A.
SARO-BMB-A-
15-0007363 8-Jun-15
Repair/rehabilitation of damaged flood
control structure, Taganas Flood
Control along Tacloban-Ormoc-Baybay-
Southern Leyte Bdry. Road,
K1100+263.2-K1100+350, Hilongos,
Leyte 6,362,000 6,362,000
DPWH-CO
NF, RA 10651
SARO-BMB-A-
15-0020299 2-Nov-15
Implementattion of various projects in
Catanduanes which were damaged by
Typhoon "Yolanda".55,296,000 55,296,000
NF, RA 10651
SARO-BMB-A-
15-0028338 28-Dec-15
Implementation of various calamity-
related projects (P399,633,284 SARO
Amount)16,004,630 16,004,630
Aklan - DEO
NF, RA 10651, C.A.
SARO-BMB-A-
16-0000266 22-Jan-16
Release of funds to cover the
reconstruction of seawall, Brgy. Fatima,
New Washington Aklan, which was
damaged by Typhoon "Yolanda"46,447,342 46,447,342
Department of Social Welfare and Development 5,906,604,000 11,441,571,882 13,449,523,526 30,797,699,408
Office of the Secretary
For implementation of various
programs and projects (Yolanda
Recovery & Rehabilitation Plan)
OS, RA 10352
SARO-BMB-B-
13-01355 27-Dec-13
Central Office - National Project
Monitoring Office 953,490,000 953,490,000
OS, RA 10352
SARO-BMB-B-
13-01355 27-Dec-13 Supplemental Feeding Program 113,010,000 113,010,000
AA
SARO-BMB-B-
14-0003767 3-Apr-14
Asian Development Bank Grant for
Typhoon Haiyan (Yolanda) Project (ADB
Grant No. 0369) under the Asia Pacific
Disaster Response Fund 131,208,0006/
131,208,000
Page 32 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
AA
SARO-BMB-B-
14-0014889 2-Oct-14
Grant proceeds from ADB-JFPR for
Emergency Assistance and Early
Recovery for Poor Municipalities
Affected by Typhoon Yolanda, Grant
No. 9175-PHI, withdrawal Application
No. 004 18,591,8827/
18,591,882
OS, RA 10352
SARO-BMB-B-
13-01252 14-Nov-13 For disaster relief and assistance 2,005,234,000 2,005,234,000
CF, RA 10352
SARO-BMB-B-
13-0025902 27-Dec-13
Augmentation of DSWD QRF for
Typhoon Yolanda 991,538,261 991,538,261
CF, RA 10155, C.A.
SARO-BMB-B-
13-01323
27-Dec-13 Augmentation of DSWD QRF for
Typhoon Yolanda 76,971,739 76,971,739
OS, RA 10352
SARO-BMB-B-
13-01324 27-Dec-13
Augmentation of the QRF for the
Yolanda Recovery and Rehabilitation
Plan (Social Assistance-General Food
Distribution) 1,766,360,000 1,766,360,000
SA, RA 10634
SARO-BMB-B-
14-0018681 20-Nov-14
Recovery and Rehabilitation Programs
and Activities for Typhoon Yolanda
affected families and communities in
Regions IV-B, VI, VII, VIII and CARAGA 2,737,500,000 2,737,500,000
RRP, RA 10633
SARO-BMB-B-
14-0020109 5-Dec-14 Sustainable Livelihood Project 1,500,000,000 1,500,000,000
RRP, RA 10633
SARO-BMB-B-
14-0020109 5-Dec-14 Cash for Work Livelihood Program 1,000,000,000 2/ 1,000,000,000
OS, RA 10633
SARO-BMB-B-
14-0026598 29-Dec-14
Emergency shelter assistance to LGUs in
Yolanda affected areas 4,265,880,000 4,265,880,000
UF, RA 10654
(Support to
FAPs)
SARO-BMB-B-
14-00010113 25-Jul-14
Initial implementation in FY 2014 of the
KALAHI-CIDDS NCDDP, in support of
adopting community-driven
development (CDD) as a national
strategy for fast recovery of areas badly
hit by Typhoon Yolanda 1,788,392,000 1,788,392,000
SA, RA 10652
SARO-BMB-B-
15-0000249 22-Jan-15
Emergency shelter assistance for
Typhoon Yolanda victims 2,084,480,000 2,084,480,000
AA
SARO-BMB-B-
15-0003038 16-Mar-15
Revalidation of allotment to cover the
grant proceeds from ADB-JFPR for
emergency Assistance and Early
Recovery for Poor Municipalities
affected bt Typhoon Yolanda 3,701,753 3,701,753
AA
SARO-BMB-B-
15-0003891 30-Mar-15
Revalidation of allotment to cover Asian
Development Bank Grant for Typhoon
Haiyan (Yolanda) Project under the Asia
pacific Disaster Response Fund 80,668,000 80,668,000
Page 33 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
UF (RRP), RA
10651
SARO-BMB-B-
15-0005420 7-May-15
Emergency shelter assistance under the
Comprehensive Rehabilitation and
Recovery Plan for Typhoon Yolanda 5,000,000,000 5,000,000,000
UF (SIPSIP), RA
10651
SARO-BMB-B-
15-0006300 21-May-15
Emergency shelter assistance under the
Comprehensive Rehabilitation and
Recovery Plan for Typhoon Yolanda 6,180,520,000 6,180,520,000
AA
SARO-BMB-B-
15-0006127 19-May-15
Grant proceeds from ADB-JFPR for
Emergency Assistance and Early
Recovery for Poor Municipalities
Affected by Typhoon Yolanda, Grant
No. 9175-PHI 100,153,773 100,153,773
Department of Science and Technology 0 31,000,000 31,000,000
Office of the
Secretary SA, RA 10634
SARO-BMB-E-
14-0005964 23-May-14
Reconstruction/Rehabilitation of Office
Buildings 31,000,000 31,000,000
Department of Trade and Industry 0 17,881,500 17,881,500
Office of the
Secretary RS, RA 10352, C.A
SARO-BMB-A-
14-0018920 21-Nov-14
Realignment of funds from MOOE to
cover the requirements for the Typhoon
Yolanda Rehabilitation projects in DTI-
Regional Office No. VIII and Leyte
Provincial Office:
RS, RA 10352, C.A
SARO-BMB-A-
14-0018920 21-Nov-14
Replacement/Augmentation of
Motor Vehicles 4,000,000 4,000,000
RS, RA 10352, C.A
SARO-BMB-A-
14-0018920 21-Nov-14 DTI Diskwento Product Depot 9,000,000 9,000,000
RS, RA 10352, C.A
SARO-BMB-A-
14-0018920 21-Nov-14 Office Furniture and Fixtures 2,382,000 2,382,000
RS, RA 10352, C.A
SARO-BMB-A-
14-0018920 21-Nov-14
IT equipment for Region 8 and Leyte
Provincial Office 2,499,500 2,499,500
Department of Transportation and Communications 2,100,000,000 214,227,790 658,500,000 2,972,727,790
Office of the
Secretary RS, RA 10352 A-13-01296 26-Dec-13
Redevelopment/reconstruction of
Tacloban Airport 2,100,000,000 2,100,000,000
SA, RA 10634
SARO-BMB-A-
14-0004809 24-Apr-14 Sea lift operations 30,102,222 30,102,222
QRF, RA 10633 letter authority 23-Oct-14
Provision of delivery trucks to DSWD
from Dec. 2013 - June 2014 8,604,000 8,604,000
Ports:
QRF, RA 10633 letter authority 12-Nov-14
1. Rehabilitation of Catbalogan
Municipal Port 15,000,000 15,000,000
QRF, RA 10633 letter authority 12-Nov-14 2.Talalora Port Development Project 15,000,000 15,000,000
Page 34 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
QRF, RA 10633 letter authority 12-Nov-14 3. Talisay, Llorente Port Project 11,000,000 11,000,000
QRF, RA 10633 letter authority 12-Nov-14
4. Amandayhan (Basey) Port
Rehabilitation Project 12,500,000 12,500,000
QRF, RA 10633 letter authority 12-Nov-14
5. Poblacion (Basey) Port Rehabilitation
Project 6,500,000 6,500,000
QRF, RA 10633 letter authority 12-Nov-14
6. San Antonio (Basey) Port
Rehabilitation Project 1,000,000 1,000,000
QRF, RA 10633 letter authority 12-Nov-14
7. Rehabilitation of Balangkayan
Municipal Fishing Port 35,000,000 35,000,000
QRF, RA 10633 letter authority 12-Nov-14 8. Rehabilitation of Dolores Port 12,000,000 12,000,000
QRF, RA 10633 letter authority 12-Nov-14
9. Rehabilitation of Lawaan (Poblacion)
Port 11,000,000 11,000,000
QRF, RA 10633 letter authority 12-Nov-14 10. Rehabilitation of Maslog Port 8,000,000 8,000,000
QRF, RA 10633 letter authority 12-Nov-14
11. Repair/reconstruction of damaged
seawall of Hernani Port 6,000,000 6,000,000
QRF, RA 10633 letter authority 12-Nov-14
12. Lawaan (Bitaog) Port Development
Project 4,500,000 4,500,000
Government Buildings:
QRF, RA 10633 letter authority 12-Nov-14 1. LTFRB Tacloban Regional Office 10,000,000 10,000,000
QRF, RA 10633 letter authority 12-Nov-14
2. Rehabilitation of LTO Palompon
District Office Building 5,500,000 5,500,000
Maritime
Industry
Authority SA, RA 10634
SARO-BMB-A-
14-0004823 24-Apr-14 Sea lift operations/relief operations 22,251,568 22,251,568
SA, RA 10634
SARO-BMB-A-
14-0005932 23-May-14 Sea lift operations/relief operations 270,000 270,000
OSEC
RRP, RA 10633,
C.A.
SARO-BMB-A-
14-0024342 23-Dec-15
Implementation of various
rehabilitation projects for Airports and
Ports Projects 658,500,000 658,500,000
National Economic Development Authority 29,538,600 0 29,538,600
Office of the
Secretary RS, RA 10352
SARO-BMB-C-
13-0025830
Rehabilitation of RO VIII facilities
destroyed by super Typhoon Yolanda 29,538,600 29,538,600
GOVERNMENT OWNED AND CONTROLLED CORPORATIONS 11,328,471,784 11,000,000,000 22,551,638,264 44,880,110,048
National Housing Authority 2,438,638,000 11,000,000,000 20,969,018,000 34,407,656,000
RS, RA 10352
SARO-F-13-
0022037 4-Dec-13
Implementation of the FY 2013
Emergency Housing Assistance for
Calamity Victims Programs 238,638,000 238,638,000
OS, RA 10352
SARO-BMB-F-
13-01329 27-Dec-13
Asssistance to households in "no-build"
zones 2,200,000,000 2,200,000,000
Page 35 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
NF, RA 10633
SARO-BMB-F-
14-0016181 20-Oct-14
Construction of additional permanent
housing of Yolanda victims in Regions IV-
B, V, VI, VII and VIII 11,000,000,000 11,000,000,000
SA, RA 10652
SARO-BMB-F-
15-001055 12-Feb-15
Construction of permanent housing for
victims of Typhoon Yolanda 7,999,978,000 7,999,978,000
RRP, RA 10633,
C.A.
SARO-BMB-F-
15-0008237 18-Jun-15
Construction of permanent housing for
victims of Typhoon Yolanda 1,300,000,000 1,300,000,000
UF, (RRP), RA
10651
SARO-BMB-F-
15-0013924 24-Sep-15
Comprehensive Rehabilitation and
Reconstruction Program (CRRP) 4,314,000,000 4,314,000,000
UF, (RRP), RA
10651
SARO-BMB-C-
15-0024366 23-Dec-15
Funding requirements of the National
Housing Authoruty for the construction
of permanent housing units and
community 5,227,000,000 5,227,000,000
OS, FY2014
DPWH
SARO-BMB-C-
15-002881729-Dec-15
Yolanda Resettlement (unfunded
balance of the P6,386,040,000 for
permanent housing units) 1,159,040,000 1,159,040,000
OS, FY2014
DPWHSARO-BMB-C-
15-0028818 29-Dec-15
Yolanda resettlement (construction of
3,424 additional housing units) 969,000,000 969,000,000
Phil. Coconut Authority 2,868,690,000 2,868,690,000
OS, RA 10352
SARO-BMB-F-
13-01327 27-Dec-13 Coconut Tree Disposal and Utilization 186,520,000 186,520,000
OS, RA 10352
SARO-BMB-F-
13-01327 27-Dec-13 Coconut Fertilization 2,682,170,000 2,682,170,000
National Food Authority 111,205,000 111,205,000
OS, RA 10352
SARO-BMB-F-
13-01331 27-Dec-13
Repair/rehabilitation/reconstruction of
Infrastructure facilities & Post harvest
facilities 111,205,000 111,205,000
National Electrification Administration 3,929,360,000 922,620,264 4,851,980,264
UF (RRP), RA
10651 (FY 2015)SARO-BMB-C-
15-0024367 23-Dec-13
Requirements of the NEA for the power
supply provision in the Ntional Housing
Authority (NHA) "Yolanda" permanent
resettlement sites 394,400,000 394,400,000
OS, RA 10352
SARO-BMB-F-
13-01330 27-Dec-13
Rehabilitation of damaged distribution
facilities of Electric Cooperatives affcted
by Typhoon Yolanda 3,929,360,000 3,929,360,000
OS, FY2014
DPWH SARO-BMB-C-
15-0028820 29-Dec-15
Sitio Electrification Program (for
Yolanda-affected communities) 528,220,264 528,220,264
Page 36 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
National Power Corporation 101,480,000 101,480,000
OS, RA 10352
SARO-BMB-F-
13-01332 27-Dec-13
Restoration of power generation
facilities in missionary affected areas by
Typhoon Yolanda 101,480,000 101,480,000
Transco 1,500,000,000 1,500,000,000
OS, RA 10352
SARO-BMB-F-
13-01333 27-Dec-13
Restoration of transmission and sub-
transmission lines in areas affected by
Typhoon Yolanda 1,500,000,000 1,500,000,000
Local Water Utilities Adm. 334,098,784 660,000,000 994,098,784
OS, RA 10352
SARO-BMB-F-
13-01317 27-Dec-13
Calamity related
rehabilitation/restoration projects 257,088,784 257,088,784
OS, RA 10352
SARO-BMB-F-
13-01328 27-Dec-13
Generator sets and treatment facilities
and pumping equipment in areas
affected by Typhoon Yolanda 77,010,000 77,010,000
OS, FY2014
DPWH SARO-BMB-C-
15-0022219 29-Dec-15
Water Supply provision in NHA-
resettlement areas 660,000,000 660,000,000
National Irrigation Administration 45,000,000 0 45,000,000
OS, RA 10352
SARO-BMB-F-
13-01319 27-Dec-13
Repair/Rehabilitation of Andanan RIS
(Bayugan City, Agusan del Sur) 45,000,000 45,000,000
LOCAL GOVERNMENT UNITS 36,831,947 0 36,831,947
Palo, Leyte OS, RA 10352
SARO-BMB-G-
13-01300 27-Dec-13
Repair of the second floor of Palo
Municipal Building, which has been
destroyed by the recent Super Typhoon
Yolanda 6,713,392 6,713,392
Javier, Leyte OS, RA 10352
SARO-BMB-G-
13-01352 27-Dec-13
Rehabilitation/repair of Municipal
Building 3,639,035 3,639,035
Municipalities in
Iloilo: OS, RA 10352
SARO-BMB-G-
13-01301 27-Dec-13
Repair/rehabilitation/construction of
the Municipal hall/Building destroyed
by Super Typhoon Yolanda in the
following municipalities in Iloilo:
Carles OS, RA 10352
SARO-BMB-G-
13-01301 27-Dec-13 Carles 5,000,000 5,000,000
Estancia OS, RA 10352
SARO-BMB-G-
13-01301 27-Dec-13 Estancia 3,000,000 3,000,000
Concepcion OS, RA 10352
SARO-BMB-G-
13-01301 27-Dec-13 Concepcion 1,500,000 1,500,000
San Rafael OS, RA 10352
SARO-BMB-G-
13-01301 27-Dec-13 San Rafael 2,000,000 2,000,000
Balasan OS, RA 10352
SARO-BMB-G-
13-01301 27-Dec-13 Balasan 1,500,000 1,500,000
Page 37 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
San Dionisio OS, RA 10352
SARO-BMB-G-
13-01301 27-Dec-13 San Dionisio 2,000,000 2,000,000
Sara OS, RA 10352
SARO-BMB-G-
13-01301 27-Dec-13 Sara 3,000,000 3,000,000
Lemery, Iloilo OS, RA 10352
SARO-BMB-G-
13-01350 27-Dec-13
Repair/rehabilitation of Municipal
Building which was damaged by
Typhoon Yolanda 1,000,000 1,000,000
Mayorga, Leyte OS, RA 10352
SARO-BMB-G-
13-01351 27-Dec-13
Rehabilitation/repair of the Municipal
building which was damaged by
Typhoon Yolanda 3,000,000 3,000,000
Santa Fe, Cebu OS, RA 10352
SARO-BMB-G-
13-01349 27-Dec-13
Rehabilitation/repair of Santa Fe
Municipal Building which was damaged
by Typhoon Yolanda 4,479,520 4,479,520
Grand Total 26,736,345,622 36,724,423,763 41,905,165,281 55,386,342 105,421,321,008
Page 38 of 39
No. Date FY 2013 FY 2014 FY 2015 FY 2016
Implementing
Agency/LGU
FUND SOURCE
1/
SARO/ABM
Purpose Y E A R
TOTAL RELEASES
Page 39 of 39