renew school sustainable school building renovation … · 2015. 10. 1. · iee renew school 3 the...
TRANSCRIPT
IEE Renew School
1
RENEW SCHOOL
Sustainable school building renovation promoting timber prefabrication, indoor environment quality and active use of renewables
D3.1
Cooperation models and financing methods for advanced school renovations with prefabrication technology in selected front runner school buildings
Prepared by: Passiefhuis-Platform vzw and external expert Dipl.- Ing. Sonja Geier, HSLU T&A, Switzerland, in consultation with RenewSchool partners.
date: 29/9/2015
The sole responsibility for the content of this publication lies with the authors. It does not necessarily reflect the opinion of the European Union. Neither the EASME nor the European Commission are responsible for any use that may be made of the information contained therein.
IEE Renew School
2
INTRODUCTION
Previous research projects showed that time and cost optimized as well as high-quality application of prefabricated elements in building retrofit depends less on technological availability than on frictionless project progress with unimpeded action chains and optimized work-flows. Communication channels, information flow, interface management and a clear definition of rights, responsibilities and obligations are crucial aspects to achieve this [1][2][3]. Prefabrication offers a lot of opportunities compared to current applied standards, but the retrofit reality is lagging behind it technological options. Therefore the Renew School project aims to learn from practice and to gain a new understanding by a so-called «bottom-up approach»1 in order to support practice. This practice is being investigated by means of different cases study analysis (school building projects) from the Renew School partner countries: Austria, Belgium, Denmark, Italy, Norway, Poland and Slovenia. The applied cooperation models and financial methods in these case studies were analyzed in order to gain deeper understanding on how they work. Additionally, the reasons for choosing prefabrication technology, key decision makers for it and the experienced barriers and advantages were also analyzed.
[1] Geier Sonja, et al. (2013). Evaluation of Collaboration Models». Public Report. FP7 project E2ReBuild. 2011-2014. Grant agreement n°260058; www.e2rebuild.com/en/links/deliverables/Sidor/default.aspx.
[2] Geier Sonja, et al. (2013). Collaboration Models for Industrialised Renovation Methods and Prefabrication – Opportunities, Barriers, Risk. In: Proceedings Passivhus Norden Conference 2013. Göteborg, Sweden, 15.-17.Oct. 2013
[3] Geier Sonja, et al. (2013). Collaboration Models for Industrialised Renovation – Experiences and Outlook on Organizational and Legal Frame Conditions. In: Proceedings Sustainable Building Conference 2013. Graz, Austria, 25.-28. Sept. 2013.
SCOPE AND CONSTRAINTS Advanced school building renovations in which prefabricated technology is used is a
complex process. The scope within the investigation presented in this report focused
on distilling an understanding of cooperation models used, on financing methods
and aspects affected by use of industrial method with timber prefabrication.
Therefore, it was deliberately chosen as ‘out of scope’ to investigate all possible
social, environmental, economic and construction related aspects of the building
process in the case studies, as well as not to investigate aspects affected by chosen
renovation measures, the user and architectural aspects.
1 Geier S., et.al. (2013). p 8-9
IEE Renew School
3
The diagram below illustrates this narrowed scope.
Figure 1: Scope of the Renew School Survey ; Source [1]
MAIN OBJECTIVES
The main objectives are to: Identify key aspects of cooperation within the project teams in each school building case study that influence frictionless work flow and optimization of technical solutions.
Therefore each case study was analyzed in terms of: - different actors involved their roles and interconnections - experiences with all phases of the renovation process and maintenance - links between the owner, the architect, the main contractor and the other different parties involved, and - suggestions on improving/optimizing the cooperation in future projects.
Investigate the way these front runner examples were financed, in terms of: - what financing tools/mechanisms they used - which sources of capital were used, and - what were the positive and negative experiences with the used financing model.
Find out experiences with the use of prefabricated timber technology in the school renovation processes in terms of:
- reasons to choose this technology - who and what had a decisive role in decision making - what level of “off-site” prefabrication was used, and - what was experienced as benefits and barriers .
KEY QUESTIONS The key questions that were in focus to be answered with the help of the case studies are:
Cooperation models Q1: What are the strengths and weaknesses in the cooperation models in the front-runner school renovations?
IEE Renew School
4
Financing
- Q2: What are the methods of financing in the front-runner school renovations?
Followed by a sub-question: o Which financial sources/constructions are typical? o What are the positive and negative experiences?
Prefabrication technology
- Q3: What advantages and barriers (process, financing) arise with the prefabrication technology using timber elements?
METHODOLOGY AND MEANS USED For this work data from the Renew School identified front runner case studies school building projects was collected to get an in-depth understanding of the complexity of cooperation models, composition of funding sources and experiences with prefabricated timber technology. To this end, tools used were survey questionnaire and individual interviews. The survey questionnaire was suitable in order to generate data on the front runner cases by asking different key actors involved (project manager or owner and investor, architect – planner and the main contractor). Additionally, the interviews were appropriate to get an understanding of the unique approach/experience of each project. An extensive survey with number of questions was developed by the Passiefhuis Platform (PHP) (example shown in Appendix) and sent to the Renew School partners, who used this tool to contact key actors of each case study and conduct the interviews. The survey was accessible on-line via ‘Survey Monkey’. Completing the survey and the interviews were anonymous, strictly confidential and in accordance with the privacy law. It was pointed out to the interviewees that it is important to mention positive as well as negative experiences about the applied solutions in their answers. The survey questions were not only focusing on collecting relevant information on the total of 14 selected front runner projects from the Renew School partner countries, but also on the conventional practice in their consequent city/region, since it was acknowledged important to gain an understanding of the wider context where the case studies are located. The selection of the case buildings was done as part of WP2, Task 2.1 “Collecting Frontrunners” of the Renew School work plan, where it came apparent that due to lack of completed advanced school building renovations using prefabricated timber technology in some Renew School participating countries, the scope had to be
IEE Renew School
5
widened to include educational buildings in the wider sense (e.g. kinder gardens). Additionally, in Belgium, the only application of timber prefabricated technology was so far applied to new built schools, therefore two such cases were selected. In total, twenty four respondents answered the survey and interview questions and were consequently analyzed. The data was analyzed by the WP3 leader PHP together with the external expert Sonja Geier of Lucerne University of Applied Sciences and Arts–Engineering & Architecture, Competence Centre Typology & Planning in Architecture (CCTP) in Switzerland. The analysis findings were consulted with the Renew School Partners. The majority of the twenty four respondents of the survey and interviews were school owners and main contractors (38% and 33% respectively), followed by the architects 24% and facility managers and project coordinators 5% each. To this list of respondents, 23% were representatives of the community/municipality where a front runner building was placed and investors (advisors, financier). This variety and number of reached respondents proved to be beneficial for collecting their experiences and points of view which is further elaborated in this report. GENERAL FINDINGS
The survey and interview questions were carefully developed to investigate the following aspects:
- General questions concerning the project in focus - Questions concerning specifics of the cooperation model - Questions relating to the financing method - Several questions on timber prefabrication technology - Final questions about the cooperation and financing of school renovations
within common practice in cities/regions where the front runners are located.
In total, the survey had thirty seven questions. Answers were collected for:
- one secondary school in Norway - two schools in Belgium (note that these are new built due to lack of
representative renovation project) - four schools in Austria - four in Slovenia (kinder gardens) - one school from Denmark - one school in Poland, and - one kindergarden in Italy.
IEE Renew School
6
Interestingly, the main reasons to renovate coming from the survey answers were to: (note that it was possible to give multiple answers to this question)
- Improve thermal comfort in winter (found in 71% of the answers), followed by improve indoor air quality and degradation of components and installations (58% in both cases).
- The next group with high number of answers is with reasons to renovate based on reduce energy costs, environmental awareness and improve thermal comfort in summer.
- The group with lowest percentages of answers was to: improve the image of the school, improve visual comfort (daylight/shading) and improve acoustical performance.
In 70% of the front runner cases the energy conditions were demanded as integral part of the renovation. Interestingly this was expressed in different ways: required reaching the passive house standard, or through more general sustainability requirements without specifying an energy standard , or energy requirement to be better than the applicable building code or even meeting the energy-efficiency requirements of an (eco) fund provider. This demonstrates different pathways that the front runner cases had for advanced renovation using prefabrication technology. Moreover, in 58% of the cases there were specific requirements on conditions (indoor air, thermal, visual comfort). Regarding use of public tenders, the diagram below shows the importance of criteria
in evaluation. The results demonstrate that main criteria was the priorities of
investment costs (88%), followed by quality (53%) and experience of the tender
applicant (47%). Operating cost and technical merit were 35% and 29% respectively.
Least important were the methodology, CO2 emissions and life cycle cost.
The lowest price and conditions within were pointed out in the answers as main
evaluation criteria. It is somewhat surprising that for these front runner buildings,
the importance of CO2 emissions and calculations based on life cycle are not more
prominent.
IEE Renew School
7
Figure 2: Renew School front runners survey: overview of responses Q18.
IEE Renew School
8
Key Question Q1 Cooperation models Q1: What are the strengths and weaknesses in the cooperation models in the front-runner school renovations? Respondents were asked to give a chronological overview/description of the building
process actions (from preparation, through planning and tendering, to production
planning prefabrication, on-site and off-site work, construction, completion and
maintenance).
Table 1: Strengths and weaknesses identified in the cooperation of the 14 Renew School case studies;
Cooperation Models Strengths Cooperation Models Weaknesses
S1 Internal driving forces pushed the
project and innovative ideas (such as
prefabrication) for a long time in order
to realize renovation.
S2 A central source of data proved to be
beneficial for the project processing.
S3 Personal meetings and dialogues in
the beginning foster mutual cooperation
in the team that is necessary for
thorough information handling and
frictionless procedures.
S4 Extended design phases provide
optimization options.
W1 Communication and information
management between partners was
lacking behind expectations.
W2 Experts (passive house/ timber
manufacturing/HVAC) were not
integrated from the beginning.
W3 No standardized documentation for
the building itself and possible «learning
curves»
W4 The introduction of the users after
renovation was dominated by technical
experts less experienced to explain the
functions in an understandable way.
W5 Lowest price principle as main driver
for the designation of cooperation
partners (especially of the contractors).
W6 Less importance of architectural
design.
IEE Renew School
9
Ad S1
Nearly in all demo projects that applied successfully prefabricated elements had a
strong driving force behind the project, pushing it forward but without having the
security that it can be financed and carried out finally. Most often it was the mayor
of the municipality (or an representative of a public administration) with a high
personal engagement. It was this internal «motor» who opened the path and pushed
the vision to an innovative renovation project [Q8, #2, 4, 8, 9, 11, 12, 13, 15, 16, 17,
18]
Ad S2
Two respondents [Q21,# 1 and Q22, # 4] pointed out that the information
management either due to the usage of «central information sharing system» or
«cloud programme» for the project management proved to be beneficial for project
progress and cooperation.
Ad S3
Personal meetings and dialogues enabled a better mutual understanding and
induced consequently a better atmosphere of trust and confidence. A problems and
challenges normally came up – the problem-solving was facilitated [Q22, # 1, 3, 6, 7,
8].
«The suggestion is to meet in person in the beginning». [Q22, #7 and #8]
Ad S4
Figure 3: Action chain of the renovation in Søreide (primary school in Norway)
The renovation of the Søreide primary school from Denmark, was an interesting in
terms of cooperation to optimization. The project was based on a PPP model, the
competition criteria were the costs, the application of wood, reaching the passive
house standard and the design. The prefabrication idea was established in the
competition were 6 teams took part. The winning proposal was based on a
cooperation of the contractor and the architect. In an extended design phase
IEE Renew School
10
«Planning and detailed planning» after the contracts were established (see «P» and
«C» in Figure 4) the architect, engineers and contractors optimized the prefabricated
elements and the solution set.
Ad W1
Some respondents claimed that information and communication was lagging and
that the communication between the cooperation partners would have needed
improvement and another understanding of cooperation:
«Exchange of info between main and prefab-elements contractor […] could be
better.» [Q22, #1]
«The communication between the architect, the main contractor and the engineering
company was suboptimal» [Q28, # 3,#18]
«I suggest more mutual listening and finding the best possible solution irresistible of
the profit of each contractor. [Q22, #4]
«Less mutual listening» [Q22, #7]
Ad W2
The information flow between design and execution or the early integration of
experts in early planning phases was addressed directly in many answers [Q22, #1,
#3, Q28, # 1, # 2 #10], however it can be read between the lines in a a lot of answers
throughout the survey. In fact, the survey showed the challenge of getting all actors
necessary for planning and implementation together hindered by the barrier of how
the financing models could be established.
Basically, any financing model was an aggregation of different sources. Each source
was bound to requirements, for instance: application of innovative or sustainable
technologies or materials, achieving comfort criteria, etc. Nearly in all projects the
time needed to find develop the financial model was about 4-5 years. At this time
the renovation project was not fixed and the planning effort had to be kept as low as
possible. Thus, a team that would have been necessary to streamline all activities in
financing and target-setting for the renovation did not exist in the early design
phases.
«Better architect + contractor collaboration earlier is strictly necessary» [Q22, #3]
IEE Renew School
11
Figure 4: Cooperation model of the school renovation project in Neumarkt.
This is visible in the team set-up of the «Neumarkt» school renovation (see Figure 3).
The design and planning team (green ellipses and background) was working along
the entire planning phases without knowing who will be the executing contractor.
In Neumarkt the architect was very experienced in prefabrication from previous
projects. Nevertheless, the public procurement regulation hindered them to
optimize the elements in terms of production capabilities given by the manufacturer.
Hence many of the implemented cooperation models had to neglect possible (and
radical) optimization options.
Ad W3
Two respondents proposed that renovation projects in future [Q22, #12, #13] should
take care of a better and more precise documentation. Especially public buildings are
very sensitive regarding their further operation and maintenance regarding a proper
documentation.
However, who is responsible? In case of the architect being the coordinator, it is him
to bring all documentations together. On the other side, it is also the duty of the
owner`s representative taking care of wrapping up everything in the end.
Ad W4
IEE Renew School
12
This chapter aims to highlight the cooperation between all actors in the design,
planning and execution phase. Nevertheless, it is only possible to take advantage of
a high quality renovation if the users in the end are enabled to use the building in
the right way. Most often technicians are responsible to introduce the technologies
to the users. However, two respondents claimed that this introduction should be
done by people who are able to speak the ‘language of the users’. [Q22, #9, #14]
Ad W5
All demo projects were driven by the «lowest price» principle. This was due the
obligation of the public procurement. The tender should identify the bidder being
able to realize the solution proposed by the design team to the lowest possible price.
Hence, there was less room to think about an alternative solution that might be even
easier to realize.
Ad W6
What was also interesting in the answers is that the architectural design had less
importance. Either it was due to those providing the answers (owners and investors
are more interested in economic aspects as they are responsible to bring up the
money), or it is a most likely neglected aspect as the financing model is dominating.
Only one quote [Q21 #1] pointed out that there was an architectural competition in
the beginning.
The following part of the cooperation model analysis is focusing on the links (defined
as contract, communication, information and legal requirements) that the school
building OWNER, ARCHITECT, MAIN CONTRACTOR had with the different involved
parties.
Cooperation Model: Links OWNER to the different parties involved:
2 of the 18 respondents were professional investors [#3 and 5 in Q3]; in [#2] there
was a representative of the municipality (MOL) the investor.
Actually it has to be questioned whether there is a tendency to establish
professional investors or owner representatives?
Basically the intrinsic motivation of mayors (even if less professional) to realize
innovative and high quality solution would be higher as they identify themselves
with the project. Professional representatives and investors would steer and control
the entire process more efficient, however due to their profession they would stick
more to their «business as usual» standards and would act less ambitious concerning
probably «unreachable» objectives.
Cooperation Model: Links ARCHITECT to the different parties involved:
IEE Renew School
13
In most of the renovations the owner designated the architect – either based on the
fact of confidence and trust in the person or by an architectural competition.
Despite the denomination based on trust or the architectural competition in nearly
all renovations the architect and the planning team was separated from the
implementing contractors. There was no contractual relationship. Only in [#8 and 9
in Q21] the architect was hired by the contractor.
The respondents were further asked, after having their experience with the front
runner building, on how they think the cooperation between involved parties could
have been improved?
The majority of answers revolved around communication. Communication during
commissioning phase was experienced as difficult, with recommendation to
separate the delivery in an architectural and an installation technical part by
commissioning.
Communication through regular meetings with the architect/site manager once per
week and monthly meetings of the project group with the school teachers proved
beneficial to the whole process.
In summary, better integrated planning and better sharing between the architect
and the main contractors is sought after. Also, the need for thorough planning was
strongly emphasized as important to keep the benefits of the prefabrication
technology. The complexity of the planning and construction processes were
unnecessarily made difficult due to design process that was done without taking into
consideration the limitations of the prefabrication technology.
The respondents were also asked on suggestions to improve sharing of information
and resources in future projects. Suggestion came to improve exchange of
information between the main and the prefab elements constructor regarding air
tightness, as this caused lower quality in reaching the required air tightness level.
Partners were also asked on suggestion on which optimization of the cooperation
are still possible to have a better ‘unburdening’? One of the respondents has
specified the following: “One optimization for this project could have been that the
builder/investors would be more involved in the chosen solution. When the builder is
not involved from the start and later becomes involved and disagrees with the
solution, it creates delays, more work and higher cost for the entire project”.
IEE Renew School
14
Key Question Q2 Financing
- Q2: What are the methods of financing in the front-runner school renovations?
Followed by a sub-question: o Which financial sources/constructions are typical? o What are the positive and negative experiences?
Typically, it was found that the municipality / school owner pays the energy bill of
the school/kinder garden out of the yearly operating budget, and this is the case
before and after the renovation.
Interestingly, in one case, the renewable energy system installed on the building
produce energy in excess of the school needs. This energy is sold to the electrical
network and it repays the whole energy bills of the schools.
The graph below shows the answers received regarding financial methods applied.
Figure 5: Renew School front runners survey: overview of responses Q10.
IEE Renew School
15
The answers show majority of financing coming from funds and grants, followed by
preferential loan programmes and VAT reductions. Importantly, novel forms of
financing have been used, although in small number of cases, of third party financing
(7%), ESCO Energy Service Company (7%), and energy guarantees (7%).
This shows that typically, the funding has come as combination of sources: majority
of which are public capital, and increasingly with private capital (preferential loans),
to which further mechanisms of private capital such as third party financing with its
form of ESCO formula and guarantees has been complementary enabler for
achieving the necessary renovation budget. The sole use of third party financing (as
PPP Public Private Partnership) with ESCO and guarantees demonstrates that such
mechanisms have economic sense in buildings realizing high energy savings and
quality of construction.
In more detail, an EFRO funding, regional development funding, eco funding were all
accessed to supplement the budget of a province/municipality where the school is
located. Also, national funding and research funding as grants were also used. The
case buildings often represented the ‘first off’ in, for example applying an energy
standard such as the passive house or implementation of innovative technologies
(e.g. lighting, LED systems, control systems) for which research grants were applied.
Private financing was also used in form of private bank funding (typically with
preferential loans at 2% interest rate), private company investing in the PV system
installed on a school building, or combination of private and public financing (PPP).
Finally, VAT reduction where possible was also used.
The factors influencing choice of financing method ranged from: as “only available”
and the “only feasible” with details that the used grants were incentives to go
further than most common renovations and that the only choice was to combine
several sources of financing, since the municipality did not have sufficient financial
resources.
Looking into the experiences of what were the positive and negative aspects with
the used financing method and possible ways for improvement revealed:
- Disadvantage with the traditional banks that could give a loan with the
guarantee of the government gave unfavourable conditions. One ethical bank
gave better conditions.
- Advantage with the municipality as being only “one owner”, for calculation of
construction and maintenance costs.
- Those using EU grants experienced positive aspects as the systematic
approach with good organization, yet negative was the complex procedures
that can result in non-use of already appropriate funds.
IEE Renew School
16
- A lot of effort needed to convince the regional government of the
comprehensive way of renovation resulted with additional hours of work.
It became apparent that majority of the front runner projects had to combine
several financing sources, each of which had their own requirements, with an overall
picture of fragmentation due to these various “side objectives”.
In reflection to the financing of front runner buildings with the wider conditions in
the city/region where they are located, the respondents were also asked to explain
how school renovation projects are typically financed.
The answers provided showed that usually the funding comes from the municipal
budget or the city budget where the school is located. To this funds operated by
central government is in cases linked.
New direction reported by one responded is preparations on PPP-Energy
Performance Contracting for up to 30 schools that need retrofit, in which certain
level of energy savings should be guaranteed by the private partner the Energy
Performance Contractor.
As to what are the main advantages of the commonly used financing models in their
cities/regions, the respondents placed “one owner” (typically municipality)
benefiting from the energy savings directly in the budget.
Negative aspects were that should the intended project goes beyond the valid
building codes, the municipality must on its own obtain additional funds that would
come from different sources, including EU funds.
When own funds of the city, for example were used, this resulted to faster and
simpler investment process. The disadvantage here is that the related lack of
requirements as to the environmental effects of the investment leads to maintaining
common bad practice if school managers do not consider decreasing energy costs to
be a critical issue.
A barrier is also reported when there is no separate available funding for thermal
retrofits, so application of these measures to school retrofit must compete with
other maintenance actions such as removal of asbestos and works on water
installations, for example.
Key Question Q3
Prefabrication technology
IEE Renew School
17
- Q3: What advantages and barriers (process, financing) arise with the prefabrication technology using timber elements?
The survey respondents gave the following as typical answers as to “what were the
reasons to choose for prefabricated technology?”
- Short time of construction on site and higher quality of construction, as well
as the advantage of having precise cost for planning for this structure.
- Several answers were provided on the advantage on using local craftsman
quality.
- It was also repeated on the time problem with schools (i.e. short renovation
time available during summer), as reason to opt for prefabricated
technology.
Below is table with the received answers.
IEE Renew School
18
Figure 6: Renew School front runners survey: overview of responses Q7.
The following question intended to evaluate their experience as to “why have you
chosen prefab = “we heard it’s faster” approach:
Figure 7: Renew School front runners survey: overview of responses Q20.
There is a common agreement by the number of answers received to the above
question that the used prefabrication method has led to limiting execution time,
whereby speed on site is seen as biggest advantage, followed by improving quality,
lower burden on site. Less evident is that the project management is easier and
lower cost is achieved.
Below is an overview of the answers to this question aggregated from point of view
of respondents: school owners, architects and main contractors.
IEE Renew School
19
IEE Renew School
20
Figure 8: Renew School front runners survey: overview of responses Q20.
Furthermore, the respondents were asked on who and what had a decisive role in
the decision process? (with the prefabricated technology). Highlighted was the role
of the mayor and local politicians, then the municipality with the public tender/call
and the investor and /or building owner. In cases (such as with the kinder garden
example), when the municipality had little experience with advanced energetic
renovation, advise was sought from a consultant in low energy buildings, upon which
the municipality took decisions.
In more detail:
IEE Renew School
21
- The main decisions regarding technical issues with the prefabricated modules
were taken by the main contractor and the architect.
- Noticeable is chain of decision making as ‘top down’, namely, the political will
(mayor and local politicians role) and investors is found as an accelerator for
opting for advanced renovations using prefabricated technology, that is then
put in place by the municipality open call/tender to which architects and
contractors provide further decisions making regarding technical aspects of
the prefabrication technology.
The main initiative for the use of prefabrication technology came from various
actors. Namely, in some cases it was by the architect and the contractor, or through
the tender offer that was selected which had prefab solution although that was not
specifically asked in the tender.
In other cases it was the owner who demanded it from the beginning or the investor.
This shows that initiators for use of prefabrication in school renovation projects can
be by different actors and in most cases from the very start of the project and from
the preliminary design.
Those who have experienced working with prefabricated technology have provided
the following insights into what were the legal constraints. Transportation
restrictions on module dimensions was mentioned, fire safety regulations and
requirements due to use of timber whereby additional documentation was needed
to prove that wood works in terms of fire protection, also the financial limits. It was
also reflected on the possible problems with the static to fix timber prefab elements
into existing brick/concrete walls.
On the “off-site” integrated elements in the prefabricated timber modules (diagram
below), predominantly the insulation, air-tightness, window frames and glazing was
integrated. Electricity was also in over 20% of cases while installations (ventilation
ducts, heating, sanitary hot waste and rain pipes, in minority of cases (less than
10%). Noticeably, in several cases the prefabricated elements came with fixation
points ready, partly shading system installed or the first internal finish layer
prepared.
IEE Renew School
22
Figure 9: Renew School front runners survey: overview of responses Q19.
DISCUSSION
The current cooperation models lack sufficient (and professional?) information and
communication management. On the one side, the project responsible (from the
owners’ side) is most likely a mayor (in case of small municipalities). On the other
side, in cities or in case schools that are administered on an aggregated level, there
are most often professional setting up a financial model and the cooperation model
right from the beginning.
Nevertheless, the design and planning procedures afterwards are vastly
characterized by ambiguities concerning clear and target-oriented planning
IEE Renew School
23
procedures. As prefabrication depends on a finalized planning before production
may start, any uncertainty in the design and planning before influences the result in
terms of time and quality (and money too).
OUTLOOK
The next step with the investigation of the cooperation models is the international
workshop on 19th November 2015 in Stuttgart, Germany. This workshop is intended
to gather experts and practitioners to create a dialog between research and practice
on how to initiate a “game change” for successful cooperation models in sustainable
school buildings renovation.
This event is organized in the context of the Renew School project. Presentations
and interactive part followed by questions, answers session and networking moment
will focus on finding ways forward to the key question: “What are the enablers for
change in the current practice of school building renovation”?
Attention in the workshop will be given to further explore the effect on the
cooperation models when General Contractor or the Main Contractor is involved.
Also, on the role of communication in terms of importance of physical meetings vs
“virtual” meetings, given the current available IT tools.
APPENDIX
Surveys questions
Page 1
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3
In WP3 we are interested in the financial and cooperation models which are used in school renovation projects. We will assess • the financial aspects • the contractual relations • the work order • communication aspects The collected data is strictly confidential and anonymous, in accordance with the law on privacy. This questionnaire will take about 40 minutes of your time. How to fill in this questionnaire? • To gather the right answers it's recommended to have a personal interview with the architect (or planner), projectmanager (or owner and investor) and the main contractor. The interviews can be done with all parties together or seperate. Questions 5 until 18 are typical questions for school owners only. • It is important to mention positive and negative experiences about the applied solutions. • Click on 'next' to go forward, and 'previous' to go backwards. • The answers will be registrated immediatly. You can leave the webbrowser always without progressing. • A progress bar will allow you to know how far you are in the survey. If you have questions, you can always send a message to [email protected] or give a call at +32 473 68 98 22 We thank you for your participation!
1. Contact information of interviewee
2. I fill in this questionnaire for...
*Name:
Company:
Emailadress:
Phone:
*
one of the selected frontrunner projects
nmlkj
the conventional practice in my region/country
nmlkj
Page 2
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3
3. Function of the interviewee.
4. For which project do you fill in this questionnaire?
*
*
School owner
gfedc
Facility manager of the school
gfedc
Project coordinator
gfedc
Architect
gfedc
Main contractor
gfedc
Other
gfedc
Other (describe)
Romsdal Secondary School, Norway
nmlkj
Søreide Primary School, Norway
nmlkj
Risør Technical College, Norway
nmlkj
Backsippans Preschool, Sweden
nmlkj
School Zonnekind, Kalmthout, Belgium
nmlkj
School CVO HeusdenZolder, Belgium
nmlkj
Detmold Vocational College, Germany
nmlkj
Schwanenstadt, Austria
nmlkj
Rainbach, Austria
nmlkj
St.Leonhard, Austria
nmlkj
Neumarkt, Austria
nmlkj
Tišina kindergarten, Slovenia
nmlkj
Lavrica kindergarten, Slovenia
nmlkj
Kekec kindergarten, Slovenia
nmlkj
Storžek kindergarten, Slovenia
nmlkj
Siemianowice, Poland
nmlkj
Kirkebjerg, Denmark
nmlkj
Vibengen, Denmark
nmlkj
Capriva del Friuli kindergarten, Italy
nmlkj
Page 3
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP35. What was/were the main reason(s) to renovate?
6. Was a “rebuild”(instead of renovation) ever been considered?
7. What were the reasons to choose for using prefabricated modules?
55
66
Degradation of components or installations
gfedc
Improve thermal comfort in winter
gfedc
Improve thermal comfort in summer
gfedc
Improve visual comfort (daylighting/shading)
gfedc
Improve air quality
gfedc
Improve acoustical performance
gfedc
Availability of a funding opportunity or grant application limited in time
gfedc
Energy cost
gfedc
Image of the school
gfedc
Environmental awareness
gfedc
Others
gfedc
Others (explain)
55
66
yes
nmlkj
no
nmlkj
not applicable
nmlkj
Page 4
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP38. Who and what had a decisive role in the decision process?
9. How does the school pay its energy bills? (Possibly different before and after the renovation.) For example: Before renovation the school payed their energy bills out of the general operating budget. This operating budget is a fixed amount per pupil given by the government. After the renovation the energy bills are payed by a DBFMcompany. (DBFM = Design, Build, Finance and Maintenance). This company is responsable for the building during 30 years after completion.
55
66
55
66
Page 5
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP310. Which financing tools/mechanisms were finally USED to finance the construction of the school?
funds
gfedc
guarantees or surety
gfedc
(preferential) loan programs
gfedc
Grants
gfedc
Third party financing
gfedc
Trading (certificates)
gfedc
Tax Rebates
gfedc
Tax deductions
gfedc
VAT reductions
gfedc
Esco (energy service company)
gfedc
Please describe it in detail:
55
66
Page 6
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP311. Why was finally choosen for the used financing tools/mechanisms?
12. What are the positive and negative experiences with the used financing model? Do you have suggestions to improve this?
55
66
55
66
Page 7
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP313. Give for each financing tool/mechanism which was considered to finance the construction the source were you found very usefull information? (websiteadress, mail supportadress,...)
14. Were there energetic energy performance conditions linked to?
funds
guarantees or surety
(preferential) loan programs
Grants
Third party financing
Trading (certificates)
Tax Rebates
Tax deductions
VAT reductions
Esco (energy service company)
Other 1
Other 2
Other 3
Other 4
Other 5
Yes
nmlkj
No
nmlkj
No idea
nmlkj
If yes, please describe
55
66
Page 8
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP315. Were there other important conditions (Indoor air comfort, thermal comfort, visual comfort, ...) linked to it?
Yes
nmlkj
No
nmlkj
No idea
nmlkj
If yes, please describe
55
66
Page 9
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3
16. Which sources of capital were used and what was their contribution (amount)?
17. Impact of the renovation costs
National government
Regional government (region)
Region government (province)
Region government (municipality)
Building owner
Building occupier
Building contractor
Bank
Energy supplier
Energy distributor
Energy service company
Other (describe)
For how many pupils was the building designed before renovation?
What was the budget for education per pupil before renovation?
Yearly budget for maintaining this building before renovation?
Yearly energy expenses before renovation?
For how many pupils was the building designed after renovation?
What is the budget for education per pupil after renovation?
Yearly budget for maintaining this building after renovation?
Yearly energy expenses after renovation?
Page 10
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP318. How were the tenders evaluated?
investment cost
gfedc
operating cost
gfedc
life cycle cost
gfedc
experience of the tenderer
gfedc
methodology
gfedc
quality
gfedc
technical :…merit
gfedc
CO2emissions
gfedc
other
gfedc
Explain more in detail
55
66
Page 11
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP319. What was “offsite” integrated in the prefabricated walls?
Insulation
gfedc
Airtightnessmeasures
gfedc
Window frames
gfedc
Glazing
gfedc
Ventilation ducts
gfedc
Ventilation equipment
gfedc
Heating pipes
gfedc
Sanitary water pipes
gfedc
Rain water pipes
gfedc
Cooling pipes
gfedc
Electricity
gfedc
Photovoltaics
gfedc
Thermal solar collector
gfedc
Other 1
gfedc
Other 2
gfedc
Other 3
gfedc
Other 4
gfedc
Other(s) (Specify)
55
66
Page 12
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP320. Do you agree that the following issues are advantages of the used prefabrication method?
don't agree at all partially don't agree neutral partially agree totally agree
Limiting execution time nmlkj nmlkj nmlkj nmlkj nmlkj
Easier project management
nmlkj nmlkj nmlkj nmlkj nmlkj
Improving quality nmlkj nmlkj nmlkj nmlkj nmlkj
Clarifying responsibilities of partners
nmlkj nmlkj nmlkj nmlkj nmlkj
Better stability nmlkj nmlkj nmlkj nmlkj nmlkj
Spaces remain used nmlkj nmlkj nmlkj nmlkj nmlkj
Less burden on site nmlkj nmlkj nmlkj nmlkj nmlkj
Better comfort nmlkj nmlkj nmlkj nmlkj nmlkj
Less cost nmlkj nmlkj nmlkj nmlkj nmlkj
Other 1 nmlkj nmlkj nmlkj nmlkj nmlkj
Other 2 nmlkj nmlkj nmlkj nmlkj nmlkj
Other 3 nmlkj nmlkj nmlkj nmlkj nmlkj
Other 4 nmlkj nmlkj nmlkj nmlkj nmlkj
Other(s) (Specify)
55
66
Page 13
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3
The next question is about the action chain. See some examples below. Instead of answering the question in textform it is recommended to draw the action chain directly in the powerpointfile which was recently distributed to you.
Page 14
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP321. Give a chronological overview/description of the building process actions? (Preparation, preliminary design, contract planning team, design, cost calculation, planning to get building permit, detailed planning, tendering, cost statement, contract main contractor, design freeze , production planning prefab, onsite preparation for renewables and prefab elements, Offsite prefabrication in fabrication hall, standard onsite construction work, installation of prefab elements onsite, completion, maintenance)
22. Do you have any suggestions to improve the sharing of information and resources in future projects?
55
66
55
66
Page 15
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP323. Who initiated the idea of prefab construction and in which phase was that?
24. Were/Are there any legal constraints that impede high energy efficient and/or prefab construction solutions?
55
66
55
66
Page 16
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3
The next question is about the cooperation models. See some example below and the powerpointfile. Instead of answering the next 3 questions it is recommended to draw the cooperation model directly in the powerpointfile which was recently distributed to you. Questions to ask are: Which parties had a contractual relation? Which parties had communication (bidirectional) with eachother? Degree of communication? Between which parties there was an information flow? Degree of information flow? Were there influences of legal requirements between the parties?
Page 17
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP325. Cooperation model: Please indicate which links (contract, communication, information, legal requirements) there were between OWNER and the different involved parties.
contract type =
performance contract
contract type = funding
commitment
intensive communication (bidirectional)
moderate communication (bidirectional)
little communication (bidirectional)
intensive information
input
moderate information
input
low information
input
influenced by legal
requirements
Project manager gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Owner gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Investor gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Operator gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Facility manager gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Utility provider (electricity)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Utility provider (gas) gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
District heating provider
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Architect gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Architect Project coordinator
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Building Physics
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner statics gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner fireprotection
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Heating gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Ventilation gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Cooling (summercomfort)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Electricity gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner lighting gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner daylighting gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner building control systems
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Site manager gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Consultant energy gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other planner/consultant:…
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Main contractor gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor construction
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor prefabmodules
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor windows gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor shading gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Page 18
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Contractor roof gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Heating gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Ventilation
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Cooling gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Electricity gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor lighting gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor daylighting
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor building control systems
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other contractor:… gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
School management gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Parents association gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Pupils gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Teachers gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Caretaker gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
External users of the school building (club music, sport,…)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Authority (building permits)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Authority (fire protection)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Insurance company gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Funding Institution gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Funding Body gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Funding Entity gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Investor (PPP) gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other 1 gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other 2 gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Others (Please specify)
55
66
Page 19
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP326. Cooperation model: Please indicate which links (contract, communication, information, legal requirements) there were between ARCHITECT and the different involved parties.
contract type =
performance contract
contract type = funding
commitment
intensive communication (bidirectional)
moderate communication (bidirectional)
little communication (bidirectional)
intensive information
input
moderate information
input
low information
input
influenced by legal
requirements
Project manager gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Owner gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Investor gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Operator gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Facility manager gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Utility provider (electricity)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Utility provider (gas) gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
District heating provider
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Architect gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Architect Project coordinator
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Building Physics
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner statics gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner fireprotection
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Heating gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Ventilation gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Cooling (summercomfort)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Electricity gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner lighting gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner daylighting gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner building control systems
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Site manager gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Consultant energy gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other planner/consultant:…
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Main contractor gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor construction
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor prefabmodules
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor windows gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor shading gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Page 20
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Contractor roof gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Heating gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Ventilation
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Cooling gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Electricity gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor lighting gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor daylighting
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor building control systems
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other contractor:… gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
School management gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Parents association gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Pupils gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Teachers gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Caretaker gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
External users of the school building (club music, sport,…)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Authority (building permits)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Authority (fire protection)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Insurance company gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Funding Institution gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Funding Body gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Funding Entity gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Investor (PPP) gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other 1 gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other 2 gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Others (Please specify)
55
66
Page 21
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP327. Cooperation model: Please indicate which links (contract, communication, information, legal requirements) there were between MAIN CONTRACTOR and the different involved parties.
contract type =
performance contract
contract type = funding
commitment
intensive communication (bidirectional)
moderate communication (bidirectional)
little communication (bidirectional)
intensive information
input
moderate information
input
low information
input
influenced by legal
requirements
Project manager gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Owner gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Investor gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Operator gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Facility manager gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Utility provider (electricity)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Utility provider (gas) gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
District heating provider
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Architect gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Architect Project coordinator
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Building Physics
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner statics gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner fireprotection
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Heating gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Ventilation gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Cooling (summercomfort)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner Electricity gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner lighting gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner daylighting gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Planner building control systems
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Site manager gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Consultant energy gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other planner/consultant:…
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Main contractor gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor construction
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor prefabmodules
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor windows gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor shading gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Page 22
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Contractor roof gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Heating gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Ventilation
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Cooling gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor Electricity gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor lighting gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor daylighting
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Contractor building control systems
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other contractor:… gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
School management gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Parents association gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Pupils gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Teachers gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Caretaker gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
External users of the school building (club music, sport,…)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Authority (building permits)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Authority (fire protection)
gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Insurance company gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Funding Institution gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Funding Body gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Funding Entity gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Investor (PPP) gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other 1 gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Other 2 gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc gfedc
Others (Please specify)
55
66
Page 23
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP328. How do you think the cooperation between partners could have been better?’
29. Which optimizations are still possible to have a better unburdening?
30. Were certain responsibilities defined in the contractual relation? Please explain
31. I confirm my answers
55
66
55
66
55
66
I confirm
nmlkj
No
nmlkj
Page 24
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3
The following questions should be asked at people who have a good insight in school building projects in their region/country.
32. The anwers that I give are applicable for
*Austria
nmlkj
Belgium
nmlkj
Denmark
nmlkj
Germany
nmlkj
Italy
nmlkj
Norway
nmlkj
Poland
nmlkj
Slovenia
nmlkj
Sweden
nmlkj
If only applicable for a certain region (please describe)
55
66
Page 25
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP333. Give for each financing tool/mechanism, which is usefull to finance schoolrenovationprojects, the source were schools can find interesting information? (websiteadress, mail supportadress,...)
34. Explain how school renovation projects are financed most of the time.
funds
guarantees or surety
(preferential) loan programs
Grants
Third party financing
Trading (certificates)
Tax Rebates
Tax deductions
VAT reductions
Esco (energy service company)
Other 1
Other 2
Other 3
Other 4
Other 5
55
66
Page 26
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP335. What are the positive and negative experiences of the most common used financing models? Do you have suggestions to improve this?
36. How do schools pay their energy bills? (Possibly different before and after the renovation.) For example: Before renovation the school payed their energy bills out of the general operating budget. This operating budget is a fixed amount per pupil given by the government. After the renovation the energy bills are payed by a DBFMcompany. (DBFM = Design, Build, Finance and Maintenance). This company is responsable for the building during 30 years after completion.
55
66
55
66
Page 27
Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP3Renew School Questionnaire WP337. Which legal responsibilities has every party in the standard renovation process? (f.e. What happens in case hidden defects are detected after some years?)
55
66