renewable energy implementation, challenges and … · renewable energy implementation, challenges...
TRANSCRIPT
Renewable Energy Implementation, Challenges and Solutions Kenneth A. Donohoo, P.E. Director, System Planning Distribution and Transmission Oncor Electric Delivery Company LLC [email protected] Center for the Commercialization of Electric Technologies Deployment of Large-Scale Renewable Resources in ERCOT Friday, December 10, 2010 Austin, Texas
CCET Presentation Ken Donohoo 12/10/2010 2
ONCOR SYSTEM “Wires Only” Company formerly known as TXU
Electric Delivery (DPL, TESCO & TPL) Largest transmission and distribution system
operator in Texas More than 6,200 Transmission Circuit Breakers More than 970 Stations More than 1,550 Power Transformers More than 170 Autotransformers More than 15,127 miles of Transmission: 5,173 circuit miles of 345 kV 7,010 circuit miles of 138 kV 2,946 circuit miles of 69 kV
More than 102,000 miles of distribution lines Delivers power to approximately 3 million homes
and businesses Employs 3,400 people Keeps the lights on for more than 7 million Texans
CCET Presentation Ken Donohoo 12/10/2010 3
ERCOT SYSTEM SUMMARY Electric Reliability Council of Texas
(ERCOT) manages the flow of electric power to 22 million Texas customers
85 percent of the state's electric load and 75 percent of the Texas land area
2010 Peak Demand 65,776 MW 2009 Energy 308,277,759 MWh Schedules power on an electric grid
that connects 40,000 miles of transmission lines and more than 550 generation units
Manages financial settlement for the competitive wholesale bulk-power market and administers customer switching for 6.5 million Texans in competitive choice areas
CCET Presentation Ken Donohoo 12/10/2010 4
Our Market
Competitive ERCOT market since 2002
Nodal Market Go-Live December 1, 2010
New Peak demand in 2010, 2.7% increase
Regulated
Transmission and Distribution
CCET Presentation Ken Donohoo 12/10/2010 5
CREZ TIMELINES
Interim Order CREZ Designations
(Aug 2007)
Transmission Optimization Study Complete - ERCOT
(April 2, 2008)
2009 2008 2007
Designate/Qualify TSPs – PUC
(2nd – 4th Qtr 2008)
Line Routing & CCN Preparation
PUC Approves CCNs
CREZ Transmission Plan Approved – PUC
(July, 2008)
“Where are the good wind zones in Texas…”
“Which TSPs will build”
2011 - 2013 2010
“What needs to be built to meet PUC scenarios”
Priority CCNs Filed
All Other CCNs Filed
“How much transmission will be built”
CONCEPTUAL PLANNING IMPLEMENTING REALITY
CREZ Reactive Study
ROW Acquisition, Procurement, & Project Construction
“Getting projects completed”
CCET Presentation Ken Donohoo 12/10/2010 7
Texas Leading Nation In Renewable Energy
• Over 9,000 MW of renewable generation in operation • Greater than 20% penetration levels achieved at lower load levels • Significant swings in actual operations
• Renewable Portfolio Standard in effect (1997 & 2005 sessions) • 2015 standard already surpassed (5,880 MW) • Will exceed 2025 objective (10,000 MW) within the next few years
• Building transmission to support another 9,000 MW (CREZ) • $5 billion transmission expansion • Completion expected 2013 • Oncor leading the way on regulatory approval and construction
• New Transmission Service Providers • Cross Texas, ETT, Lone Star, WETT • ERCOT, new and existing TSP’s working very well together
CREZ CCN Applications to Date
TSP Project (Docket No. if filed)
CCN Filing Date
CCN Deadline
CCN Status
Cross Texas Gray to Tesla (37956) 5/3/10 10/29/10 Approved
Silverton to Tesla (38435) 7/28/10 1/24/11 Pending
Gray to White Deer (38650) 9/29/10 3/28/11
ETT Clear Crossing to Dermott (37951)
5/3/10 10/30/10 Approved
Tesla to Riley (38494) 8/18/10 2/15/11 Pending
Riley-Edith Clarke-Cottonwood (38562)
9/8/10 3/8/11 Pending
Tesla-Edith Clarke-Clear Crossing-West Shackelford (38743)
10/20/10 4/19/11
12/10/2010 8 CCET Presentation Ken Donohoo
CREZ CCN Applications to Date
TSP Project (Docket No. if filed)
CCN Filing Date
CCN Deadline
CCN Status
LCRA TSC Tippet to North McCamey (36686)
2/27/09 8/27/09 Approved
Twin Buttes to McCamey D (Big Hill) (37778)
1/15/10 7/15/10 Approved
Gillespie to Newton (37448) 10/28/09 4/28/10 Project Replaced
McCamey D (Big Hill) to Kendall to Gillespie (38354)
7/28/10 1/28/11 Pending
Lone Star Central A to West Shackelford to Sam Switch /Navarro (38230)
5/24/10 11/19/10 Approved
12/10/2010 9 CCET Presentation Ken Donohoo
TSP Project (Docket No. if filed)
CCN Filing Date
CCN Deadline
CCN Status
Oncor Bowman – Jacksboro (37015)
5/29/09
11/29/09 Approved
Jacksboro-Willow Creek – Parker (37119)
6/30/09 12/30/09 Approved
Dermott – Scurry County – Tonkawas (37409)
9/16/09 3/16/10 Approved
Tonkawas – Sweetwater – Central (37407)
9/16/09 3/16/10 Approved
Bowman – Riley (37408) 9/16/09 3/16/10 Approved
Brown – Newton (37464) 10/7/09 4/7/10 Approved
Newton-Killeen (37463) 10/7/09 4/7/10 Approved
Central Bluff – Bluff Creek (37529)
10/28/09 4/28/10 Approved
Bluff Creek – Brown (37530)
10/28/09 4/28/10 Approved
12/10/2010 10 CCET Presentation Ken Donohoo
CREZ CCN Applications to Date
TSP Project (Docket No. if filed)
CCN Filing Date
CCN Deadline
CCN Status
Oncor Riley to West Krum (38140) 5/3/10 11/3/10 Approved
Willow Creek to Hicks (38324) 6/16/10 12/16/10 Pending
Clear Crossing to Willow Creek (38517)
8/18/10 2/18/11 Pending
West Krum to Anna (38596) 9/8/10 3/8/11 Pending
West B to Moss (38677) 9/29/10 3/29/11
Sharyland Hereford to White Deer (38290)
6/16/10 12/16/10 Pending
Silverton to Cottonwood (38560)
9/8/10 3/8/11 Pending
Hereford – Nazareth-Silverton (38750)
10/20/10 4/20/11
White Deer to Silverton 11/10/10 5/10/11
12/10/2010 11 CCET Presentation Ken Donohoo
CREZ CCN Applications to Date
TSP Project (Docket No. if filed)
CCN Filing Date
CCN Deadline
CCN Status
STEC Bakersfield to Big Hill (38648)
9/29/10 3/29/11
STEC (for Garland)
Odessa – North McCamey – Bakersfield
3/18/11 9/18/11
WETT Cottonwood to Dermott (38295)
6/16/10 12/16/10 Approved
Scurry County South – Long Draw – Grelton – Odessa (38484)
8/18/10 2/18/11 Pending
Long Draw – Sand Bluff – Divide; Bearkat – Sand Bluff
11/10/10 5/10/11
12/10/2010 12 CCET Presentation Ken Donohoo
CREZ CCN Applications to Date
Ongoing Grid Integration Activities
System Planning Issues
Completed or In Progress
– Voltage Ride-Through Requirement
– CREZ Reactive Study
– Sub Synchronous Resonance
Future Issues
– Ancillary Services necessary for CREZ-level wind capacity
– WGRs with multiple POIs
12/10/2010 13 CCET Presentation Ken Donohoo
Ongoing Grid Integration Activities
System Operations Issues
Completed or In Progress
– Ramp Rate limits
– Reactive Power capability
– Voltage Ride-Through, voltage management practices
– WGR scheduling practices, Resource Plan updates
Future Issues
– Forecasting, forecasting, forecasting
– Emerging Technologies participation in Ancillary Services
12/10/2010 14 CCET Presentation Ken Donohoo
ERCOT Peak Summer Week Generation by Fuel Type (actual) July 12-18, 2009
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
Nuclear Coal CombCycle GasSteam PrivateGas GasTurbine Wind Other
Sunday 07/12/09
Monday 07/13/09
Tuesday 07/14/09
Wednesday 07/15/09
Thursday 07/16/09
Friday 07/17/09
Saturday 07/18/09
12/10/2010 15 CCET Presentation Ken Donohoo
ERCOT 2013 High Wind Week Generation by Fuel Type (projected)
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
Nuke Coal Combined Cycle Gas Steam Private Gas Turbine Wind Other
Monday 03/11/13
Tuesday 03/12/13
Wednesday 03/13/13
Thursday 03/14/13
Friday 03/15/13
Saturday 03/16/13
Sunday 03/17/13
12/10/2010 16 CCET Presentation Ken Donohoo
ERCOT CREZ Reactive Study Summary
Reactive static and dynamic devices are needed to transmit energy from West Texas to maintain appropriate voltage control under normal and contingency conditions
Three major work areas Shunt capacitors & reactors location, size and response capability Specifications of series capacitor line compensation Evaluate sub-synchronous interactions
Study conducted by ABB, Inc. along with CREZ TSPs and ERCOT
Study is the first of its kind and includes qualifications about the planning assumptions and translation to actual operations
Actual “real world” operations will be dissimilar from the study
These represent minimum required reactive equipment
Reactive equipment needed as new lines come into service
17 12/10/2010 CCET Presentation Ken Donohoo
ERCOT CREZ Reactive Study Summary IDENTIFIED ISSUES
Shunt device switching is greater than current operations Increase in O&M and possible forced outages of facilities
Problematic wind farm dynamic stability analysis models Analysis software limitations and outdated Low System Strength (Short Circuit Ratio – SCR) Fundamental-frequency source impedance Low fault duty/short circuit capability Wind turbine operational issues Physical ambiguity May result in voltage and power oscillations Solution is more facilities
– Additional transmission lines – Synchronous condenser – Additional series capacitor compensation – Traditional or wind synchronous generation
18 12/10/2010 CCET Presentation Ken Donohoo
ERCOT CREZ Reactive Study Summary IDENTIFIED ISSUES
Sub-synchronous interactions Sub-Synchronous Resonance (SSR)
– Oscillatory responses at frequencies below 60 Hz
Sub-Synchronous Control Interactions (SSCI) – Wind turbines – Control instability due to interactions with series capacitor compensated lines – HVDC interaction possible
Sub-Synchronous Torsional Interactions (SSTI) – Thermal generators – Significant damage to generator shaft – Potential destabilization by control operation of active devices (SVC,
STATCOM, DC etc…)
Solutions – Problem occurs most when generator is radial with series compensation – System Protection – Operational Clearance Procedures – Modify Interconnection Procedures and Allowed Turbine Types
19 12/10/2010 CCET Presentation Ken Donohoo
Static Var Compensators (SVC) (Voltage Reservoir)
CCET Presentation Ken Donohoo 12/10/2010 20
• Oncor Current Installations • Home to the largest and fastest in the world • Dynamic Reactive Device with 20 ms response time • 2009 Parkdale Two +300 to -265 Mvar units (+600, -530 Mvar Total)
• Application won Texas Environmental Excellence Award (TCEQ) • 2010 Renner Two +300 to -265 Mvar units (+600, -530 Mvar Total)
• SVC is a robust, advanced technology used to provide high speed grid voltage control
• Enables renewable energy transfers to load centers • Prevents widespread load outages (blackout) • Voltage support must be supplied quickly and locally • Replaces capability previously supplied by local generation
• Reduces need for local generation • Need increases as more local generation reduces operation, mothball or
retirement and generation is added outside of load centers • Need compounded by continuing load growth within load centers
• Future Installations • CREZ Related Brown and Parker in 2013 • Study for more in DFW
CCET Presentation Ken Donohoo 12/10/2010 21
Questions? ERCOT Reactive Study Link: http://www.ercot.com/content/news/presentations/2010/CREZ%20Reactive%20Power%20Compensation%20Study.pdf PUCT CREZ Transmission Program Information Center http://www.texascrezprojects.com/default.aspx CREZ Monitor Quarterly Reports (details on construction, cost and in-service dates) http://www.texascrezprojects.com/quarterly_reports.aspx