renewable energy in the visayas cebu green economic series: renewable energy summit march 7, 2011...
TRANSCRIPT
Renewable Energy in the Visayas
Cebu Green Economic Series: Renewable Energy Summit
March 7, 2011
ATTY. JOSEFINA PATRICIA M. ASIRITChief of Staff/Undersecretary
Outline
• Power situation in the Visayas
• Renewable Energy in Visayas
• National Renewable Energy Plan
Actual Power Sector Situation: Visayas
January February March April May June July August September October November December
2010 Highest Peak = 1,431 MW
2010 Lowest Peak = 944 MW
Note: Leyte-Luzon HVDC power flow not considered Source of Data: DOR of NGCP
CEDC Testing & Commissioning of
Unit 1 (72 MW)
CEDC Testing & Commissioning of
Unit 2 (72 MW)
2010 Demand Curtailed at Peak (MW)
Jan 6 (22 MW)
Feb 25 (35 MW)Apr 28 (88 MW)
May 25(66 MW)
Jun 4 (71 MW)
Jul 5 (39 MW)
Aug 31 (34 MW)
Sep 20 (46 MW)
Oct 4(48 MW)
Nov 24(29 MW)
Dec 16(106 MW)
PEDC Testing & Commissioning of
Unit 1 (72 MW)Max Capacity =
1,417 MW Min Capacity = 862 MW
2009 Highest Peak = 1,241 MW
2009 Lowest Peak = 852 MW
2008 Lowest Peak = 587 MWTyphoon Frank
2008 Highest Peak = 1,176 MW
2010 vs 2009 = 15.3% Demand Increased
GOMP System Capacity Actual Capacity and Demand
Geothermal Hydro
Coal Oil-based
Legend:
Max Maintenance =353 MW
Max Capacity = 1,960 MW
2011 Min Peak = 983 MW
Implemented MLD due to low system
generation
Max Capacity = 1,528 MW
2011 Max Peak = 1,322 MW
Note: Leyte-Luzon HVDC power flow not considered
Source: DOR of NGCPSource: GOMP of NGCP
Testing & CommissioningKSPC 140 MWPEDC 70 MW
CEDC 224 MWCTPP 1, 50 MW (27-31
Jan)FO
LGPP U1, 37 MW(1- 16 Jan)FOLGPP U2, 37 MW(17- 31
Jan)MONNGP 12 MW (1-31 Jan)MO
UMPP U2 ,30 MW (21-31 Jan)MO
UMPP U3 ,30 MW (1-14 Jan)MO
PB101,32 MW (1-31 Jan)ESPDPP 3, 12.5 MW (7-31
Jan)FOTPC,45 MW (1-31 Jan)
PDPP 1,36 MW (1-31 Jan)
CDPP U3,6 MW (1-20 Jan)CPPC U6, 7 MW (7-19 Jan)PB 103 U1,6 MW (1-31 Jan)PDPP 3,10 MW (10-14 Jan)PPC U10,5 MW (14-17 Jan)
LGPP U2, 37 MW(5- 18 Jan)UMPP U1 ,30 MW (8-17 Jan)
CTPP 1, 50 MW (18-28 Jan)TPC B6,33 MW (5-8 Jan)
TPC B7,33 MW (15-30 Jan)
GOMP Rated Capacity = 2,095 MW
Min Maintenance =135 MW
Min Capacity = 1,743 MW
MO = Maintenance OutageFO = Forced OutageRS = Reserve Shutdown
Min Capacity = 985 MW
Actual Power Sector Situation: January 2011
Visayas
2011 Visayas GOMP2011 Visayas GOMPPower Sector Situation:
Expectations in 2011
1. Excludes Embedded Generators ( 33 MW Installed Capacity)
2. Cebu Land base Gas Turbine (54 MW) not available for dispatch
3. Cebu Energy Development Corporation 3 x 82 MW (130 MW) all units available starting January 2011
4. KEPHILCO (200 MW) and Panay Energy Development Corp. 2 x 82 MW (PEDC 164 MW) not yet considered in NGCP GOMP
5. Unplanned/Forced Outage not yet considered6. Normal Hydro Condition7. Leyte-Luzon HVDC Power flow not considered
ASSUMPTIONS:
2010 Gross Power Generation, GWh
Total Generation = 65,795 GWh
Awarded RE contractsin
Visayas
Wind Projects
Potential Capacity
Province Capacity (MW)
Aklan 50
Iloilo 33
Guimaras 80
Negros Occidental 15
Bohol 10
Total: 188 MW
Hydropower Projects
ProvincePotential Capacity
(MW)
Aklan 40.8
Antique 39.9
Iloilo 32
Negros Occidental 31
Bohol 9.2
Cebu 0.5
Negros Oriental 73.7
Total: 227.1
*Installed capacity: 10 MW in Antique
Ocean Energy
• Deep Ocean Power Philippines, Inc. owns the only RE contract for
ocean energy in Visayas. • Investment = P1.5 million
• Potential site: Anini-y, Antique
Ocean Energy
Biomass Projects
Province
Capacity for
Export (MW)
Capacity for own use
(MW)
Aklan 12 0
Capiz 0 5.8
Iloilo 65 0
Negros Occiden
tal 8.5 74.7
Leyte 0 11
Total: 85.5 91.5
Total Investment (awarded contracts): P17.4 billion
Geothermal Projects
Province
Potential Capacity
(MW)
Installed Capacity
(MW)
Negros Occidental 241.88
Biliran 20 0
Leyte 722.68
Total: 964.56
National Renewable Energy Plan
• Target Completion: 1st Quarter, 2011 • Collaboration among Renewable Energy Management Bureau
(REMB) and all DOE Bureaus• Outlines Target Dates for RE Policy Mechanisms in 2011
a. Renewable Portfolio Standards (DOE Draft) – 2nd Quarter
b. Feed-In Tariff Rates (NREB submission) – 2nd Quarter
c. Green Energy Option Program – 2nd Quarter
d. Net-Metering – 3rd Quarter
e. Transmission System Development – 3rd Quarter
f. Distribution System Development – 3rd Quarter
National Renewable Energy Plan
• Creation of Renewable Energy Market and RE Registrar – 1st Quarter, 2012
• Off-Grid Development – 4th Quarter, 2011
• Promulgation of Rules and Regulationsa. RETF Administration – 2nd Quarter
b. Mechanism for RE Host Community/LGU Incentives
c. BIR-DOF Revenue Regulations for Fiscal Incentives
Ensure Energy Security
Achieve Optimal Energy Pricing
Develop a Sustainable
Energy System
Good Governance thru stakeholder participation, transparency, multi-sectoral partnership and use of ICT
“Energy Access for More” A key priority of government to mainstream
access of the greater majority to reliable energy services and fuel, most importantly, local productivity and countryside development
Energy Reform Agenda
Thank you