repair of fire damage structure
TRANSCRIPT
SD0107 Repair of Fire Damage Concrete Structure 1
Repair of Fire Damage Structure
SD0107 Repair of Fire Damage Concrete Structure 2
Contents
Introduction Effects of fire on material Repair to fire damage structure involves
evaluation or the assessment of the fire damage structure
Selection of repair material Method of placing the repair material
Case Study
SD0107 Repair of Fire Damage Concrete Structure 3
Introduction
The assessment of fire history and the residual strength of a structure, is complex and requires skill and experience to achieve. The normal purpose of a repair is to restore in the required structure the performance it had before the fire, both in respect of strength and of fire resistance in a future fire.
SD0107 Repair of Fire Damage Concrete Structure 4
Introduction cont….
The decision whether the fire damaged structure could be repaired and reused depends on : The temperature and duration of fire Properties of concrete and steel used Residual strength of concrete element
affected by fire
SD0107 Repair of Fire Damage Concrete Structure 5
Recommendations for efficient planning of repair
1. To assess the damage 2. Determine the feasibility of repair 3. Decide the best method to be used
for repair
4. Prepare a scheme for reconstruction 5. Consult with the local authority 6. Schedule the sequence of operations 7. Prepare a scheme for propping and
bracing including a schedule of prop loads 8. Specify the extent of repair work in detail.
SD0107 Repair of Fire Damage Concrete Structure 6
Assessment of Damage
For proper assessment of the structure we need to consider the effect of fire on material as well as structural member.
Change in Compressive strength of concrete: In most of the cases strength loss is pronounced
when subjected to above 300 ‘C temperature. Colour changes in concrete:
Concrete on heating undergoes colour changes. Observation made on concrete after heat, can give
information about heat penetration into concrete mass. Which can be seen from the table given below.
SD0107 Repair of Fire Damage Concrete Structure 7
Colour changes in concrete with temperature
TEMPERATURE IN CONCRETE
COLOUR
0 TO 300 NORMAL
300 TO 600PINK, RED OR
REDDISH BROWN
600 TO 900 WHITISH GREY
900 TO 1000 BUFF
SD0107 Repair of Fire Damage Concrete Structure 8
Depth of Heat penetration into Concrete during Exposure to Fire Test
Test Period (hour)
Surface Temperature at end of Test ('C)
Distance from surface of colour change Position corresponding to temperature
300 'C 650 'C 1000 'C
mm mm mm
1 950 57 18 -
2 1050 79 25 6
3 1150 120 44 3
Depth of Heat penetration into Concrete
SD0107 Repair of Fire Damage Concrete Structure 9
Cycle of effects of fire on reinforced concrete structure
Stage on heating1. Rise in surface
temperature
2. Heat transfer to interior surface
3. Heat transfer to reinforcement (accelerated if spalling occurs)
Probable effectsSurface cracking
Loss of concrete strength,
cracking and spalling
Reduction of yield strength,
possible buckling and/or
increase in deflection
SD0107 Repair of Fire Damage Concrete Structure 10
Cycle of effects cont…… On cooling4. Reinforcement
cools
5. Concrete cools
6. After concrete cools
Recovery of yield strength to
practically original value, any
buckled bars remained buckled
Cracks close up; further
reduction in strength; Deflection
recovery incomplete for severe
fire
Very dry concrete absorbs
moisture from atmosphere
results in further deformations
and cracking
SD0107 Repair of Fire Damage Concrete Structure 11
Collection of data (Diagnosis)
1. Debris
Examine relevant debris to determine the duration of fire or temperature reached.
2. Concrete colour
Estimate the equivalent exposure from the depth of pink coloration.
3. Visual classification
There should be detailed examination and classification of damage for each structural member. We should use clearly stated description for each classification
SD0107 Repair of Fire Damage Concrete Structure 12
Class of damage Description of damage (Column)
Class 1 Undamaged except for some peeling of plaster finish, smoke deposit
Class 2 Substantial loss of plaster finish - Concrete surface having extensive micro cracking and pink buff colour - minor spalling only
Class 3Plaster finish almost entirely removed. Concrete surface buff coloured and elsewhere locally spalled to reveal reinforcement -Separation of concrete cover- concrete may give hollow sound.
Class 4Sever damage including extensive spalling revealing considerable areas of steel reinforcement. One or more bars buckled and column may show sign of distortion.
Damage classification for a typical reinforced concrete framed structure
SD0107 Repair of Fire Damage Concrete Structure 13
Damage classification for a typical reinforced concrete framed structure
Class of damage Description of damage (Floor Panels)
Class 1Suspended ceiling extensively damaged but some panels may still be in place; few hollow tiles damaged but reinforced concrete ribs intact except for smoke soot.
Class 2 Substantial damage to hollow tiles - concrete ribs spalled with reinforcement revealed over small areas
Class 3 Reinforced Concrete ribs - extensively spalled of, but reinforcement generally still adhering to concrete; concrete seems smoke covered or pink; No severe Deflection.
Class 4 Sever damage including extensive spalling revealing considerable areas of steel reinforcement. Deflection may be severe.
SD0107 Repair of Fire Damage Concrete Structure 14
Damage classification for a typical reinforced concrete framed structure
Class of damage Description of damage (Beams)
Class 1 Smoke deposit; minor spalling only and no exposed reinforcement
Class 2
Substantial spalling along adjacent planes revealing main reinforcement of outer surface of corner bars, micro cracking of surface, cover concrete to soffit may have "hollow" ring. Concrete colour - Black/Pink
Class 3 Substantial spalling revealing reinforcement; concrete colour buff, cracks several millimeters in width. No severe Deflection.
Sever damage including extensive spalling revealing considerable areas of steel reinforcement. Deflection may be severe and/or Fractures; Main reinforcement buckled. Concrete buff/grey coloured.
SD0107 Repair of Fire Damage Concrete Structure 15
Prognosis (Feasibility of repair )Classification of repair
Class of repair Description
Class 1 Superficial gunite repair of slight damage not required fabric reinforcement.
Class 2 Non structural repair over a large area, e.g. restoring cover to reinforcement where this has been partly lost. The gunite will be reinforced with a nominal light fabric.
Class 3Principal strengthening repair reinforced in accordance with the load carrying requirement of the member. Concrete and reinforcement strength may be significantly reduced.
Class 4
Strengthening repair with original concrete and reinforcement written down to zero strength or complete demolition according to the following factors.
(a) If member is badly distorted and or there is loss of tension in prestressing tendons or concrete is weakened throughout - demolish and replace.
(b) If member is unsound structurally but removal would cause inconvenient disruption of adjoining member – add new materials to support original design load.
SD0107 Repair of Fire Damage Concrete Structure 16
Schedule for damage classification
Typical Section of schedule for damage classification
Ground floor columns and first floor beams and slabs
Columns Beams Slabs
Class of damage 1 2 3 4 1 2 3 4 1 2 3 4
Member reference
no.
2 5 3 14 111 21 131 31 101 102 104
11 12 4 211 121 231 41 201 202 204
21 23 13 311 331 141 301 203
31 33 23 112 152 221 401 302
41 35 24 212 452 241 303
42 43 33 312 321 304
44 412 132 403
45 404
SD0107 Repair of Fire Damage Concrete Structure 17
Plot of Fire Damage v/s Temperature
Fire Damage factor v/s Temp
0
0.2
0.4
0.6
0.8
1
1.2
0 100 200 300 400 500 600 700
Temperature 'c
Fire
Dam
age
Fact
or w/c ratio 0.40
w/c ratio 0.65
SD0107 Repair of Fire Damage Concrete Structure 18
Damage classification: Typical assessments and decision
Damage Classification: Typical summary of assessments and decisions
Member no.
Class of
Damage
Fire damage factors
Quality of original
construction
Feasibility of repair
Effect of
adjoining
members
Time for
repair: Cost of repair
Decision Remarks
Concrete Steel
203 2 1 1 1 1 0 NADemolish and Reconstruct
Adjoining beams and staircase too badly
damaged for repaired
141 3
Compression -
0.93 Shear -
0.92
Main bars - 0.77
Links - 1
1 1 1 1Repair as redesign
13 3 0.85
Main bars - 0.60
Links - 1
1 1 1 1Repair as redesign
Note that redesign would be same if column had been
classed 4B
SD0107 Repair of Fire Damage Concrete Structure 19
Repair Material
The basic principle of repair is that the repair medium should be as close as possible in all physical characteristics (Elastic modulus, Coefficient of expansion, Strength) to the base material or/and the properties of the new and old work are similar to facilitate maintaining a good bond by limiting the boundary stresses.
SD0107 Repair of Fire Damage Concrete Structure 20
Repair material contd….
A good repair material should have the best combination of following properties. (It should be compatible with the old material)
1. Mechanical properties as close to the base material.
2. Good adhesion in dry, damp or wet condition.
3. Low shrinkage (during curing and long term)
SD0107 Repair of Fire Damage Concrete Structure 21
Method of placing the repair material
This can be done by:
1. Recasting in formwork
2. Spraying (Guniting)
3. Hand applied mortars.Each method will give satisfactory results, providing the specification, material and techniques are appropriate and the work competently done by experienced operatives.
SD0107 Repair of Fire Damage Concrete Structure 22
1. Repair by recasting in formwork
This method is particularly used when • Larger volume of material is to be placed.• Repetition of use of formwork• The whole length of beam and column required
repair
2. Repairs by spraying (Guniting)• A mixture of cement, aggregate and water is
projected into a place with high velocity.
Method of placing contd….
SD0107 Repair of Fire Damage Concrete Structure 23
• Typically the materials used are coarse sand and Portland cement, the aggregate less than 10 mm size maximum
• Compaction to produce a dense homogeneous mass is achieved by its own velocity, with as little subsequent working as possible being done.
• The material can be placed on vertical as well overhead surfaces with limiting thickness.
• Typical characteristics are good density, low permeability, high strength and good bond.
Method of placing contd….
SD0107 Repair of Fire Damage Concrete Structure 24
3. Repaired by hand applied mortars• Technique used will be similar to good
rendering practice, but using a slurry bond coat. A polymer latex admixture is frequently added, to both bond coat and repair mortar.
• This act as water reducing agent allowing a lower water cement ratio to be used.
Method of placing contd….
SD0107 Repair of Fire Damage Concrete Structure 25
CASE STUDYA shopping cum school complex in the western part of Bangalore city was considerably damaged due to fire by some miscreants.The building comprises of Basement Floor
Used as boys hostel Ground Floor
‘Co-optex’ a handloom fabric show room First Floor
Used as Library and Classrooms
The fire spread very fast and last for more than Eight
hours.
The entire fabric in the showroom caught fire.
SD0107 Repair of Fire Damage Concrete Structure 26
Building at the time of Investigation
SD0107 Repair of Fire Damage Concrete Structure 27
Columns & Beams Layout
SD0107 Repair of Fire Damage Concrete Structure 28
Effects of Fire on Structure
The fire had reached every part of the building namely walls, columns, beams and roof ceiling.
Walls had cracked everywhere Plaster of walls, ceiling of roof, beams and columns had spalled off. Reinforcement in most parts of slab and few beams was exposed considerably. Cracks had developed in slabs and beams. width of the cracks being more than acceptable
limits. Some beams and slabs had even deflected.
SD0107 Repair of Fire Damage Concrete Structure 29
Schematic representation of damages on Ground Floor
SD0107 Repair of Fire Damage Concrete Structure 30
Schematic representation of damages on First Floor
SD0107 Repair of Fire Damage Concrete Structure 31
Reinforcement were exposed in Ground Floor slab
SD0107 Repair of Fire Damage Concrete Structure 32
Reinforcement were exposed in Ground Floor slab
SD0107 Repair of Fire Damage Concrete Structure 33
Reinforcement were exposed due to spalling of concrete cover (beam FB2)
SD0107 Repair of Fire Damage Concrete Structure 34
Typical Distress in Column
SD0107 Repair of Fire Damage Concrete Structure 35
Distress walls (115mm thick) of cupboard on First Floor
SD0107 Repair of Fire Damage Concrete Structure 36
Investigation In order to assess the existing strength of
hardened concrete of different structural
members and to detect any cracks the
investigation was done.
Investigation was carried out in three steps:
1. Physical Examination
2. Non-Destructive Testing of Structural element
(a) Rebound Hammer Test
(b) Ultrasonic Pulse Velocity Test
3. Load Test on First Floor slabs and Beams
SD0107 Repair of Fire Damage Concrete Structure 37
Loading of slab using sand
SD0107 Repair of Fire Damage Concrete Structure 38
Checking of deflection of slab
Dial gauges are mounted at midspan to measure the deflection
Reading were taken immediate after the loading
After 24 hour of loading
After 24 hour from removal of load to measure the recovery
SD0107 Repair of Fire Damage Concrete Structure 39
Rectification schemeInvestigation revealed that the structure was not structurally sound and all structural damages required to be repaired.
Following repaired were done;
1. Encasement of Column by concreting
2. Guniting of First Floor Beam and Slab
3. Post Grouting of Columns and beams
4. Treatment to brick masonry walls
5. Restoring rotating canopy
6. Other non structural repair
SD0107 Repair of Fire Damage Concrete Structure 40
Encasement of column by Concreting
Encasement of entire column was done in view of structural stability, though they were disintegrated on the ground floor only.
1. Unloading of Columns
2. Surface Preparation
All loose materials were removed by chipping and cleaned by Sand Blasting
SD0107 Repair of Fire Damage Concrete Structure 41
Encasement of column cont…
3. Use of Bonding agent
A coating of NITO-BOND or its equivalent was applied on the clean surface as per manufacturer’s specifications.
4. Shear connectors of 12 mm dia at 1000 mm c/c were inserted in drilled holes of 16 mm dia.
5.The gap around shear connectors were sealed by appropriate non-swing sealing compound.
SD0107 Repair of Fire Damage Concrete Structure 42
Encasement of column cont…
6. The new reinforcement cage was positioned around the column as per requirement.
7. The twin U-ties were inserted around the new reinforcement and welded to form a rectangular type.
8. After the formwork has been completed M25 grade concrete with good workability possessing high slump is poured and well compacted.
SD0107 Repair of Fire Damage Concrete Structure 43
Encasement of column cont…9. At beam column junction slab was punctured for
150 mm square and concrete was poured from top of the slab into the formwork to ensure good concreting at joints.
10.Encasement concrete is cured for a minimum period of 14 days.
11.The column formwork is stripped only 24 hrs after concreting.
SD0107 Repair of Fire Damage Concrete Structure 44
Grouting of columns
SD0107 Repair of Fire Damage Concrete Structure 45
A A
1000
Existing Footing
Existing Column100 mm thk concrete with M20, 12.5 mm down size aggregates
Existing beam
8 Dia ties at 200 c/c
12 Dia Bars
12 Dia connectors at 1000 c/c with 16 Dia holes (Staggered)
Single layer epoxy coat over roughened and cleaned surface of column.
Grouting of columns
12 Dia 8 nosEpoxy silica putty 1:6 or Rendroc
8 Dia ties at 200 c/c
Sectional plan AA
Epoxy silica putty 1:6 or Rendroc
12 Dia connectors at 1000 c/c staggered
100
All dimensions are in mm
SD0107 Repair of Fire Damage Concrete Structure 46
Grouting of columns
SD0107 Repair of Fire Damage Concrete Structure 47
Guniting of Slabs and Beams
Large scale distress was observed in slabs and beams with spalling of concrete cover exposing the reinforcement. Cracks were also of common sight everywhere.
Repair methodology adopted is as follows:
SD0107 Repair of Fire Damage Concrete Structure 48
Guniting of Slabs and Beams cont…
1. Slab/beam was supported wherever necessary.
2. Concrete cover was chipped off and all loose materials were removed by sand blasting.
3. A thin layer of NITO-BOND was applied on the cleaned surface.
4. Shear connector of 12 mm dia at 1000 mm c/c were inserted in drilled hole of 16 mm dia in a zigzag manner.
SD0107 Repair of Fire Damage Concrete Structure 49
Guniting of Slabs and Beams cont…
5. The gap around shear connectors was sealed by an appropriate non shrink sealing component.
6. Weld-mesh of 75x75x3 mm was wrapped on to the exposed surface of rib of beam and to slab bottom and tack welded to the exposed reinforcement at close intervals and to shear connectors.
SD0107 Repair of Fire Damage Concrete Structure 50
Guniting of Slabs and Beams cont…
7. Gunite mortar mixed with gunite aiding admixture of 40 mm thick around rib of beam and of 25 mm thick for roof slabs was applied under an operating pressure of around 0.6 N/sq.mm
8. The gunited surface was cured for a minimum period of seven days
SD0107 Repair of Fire Damage Concrete Structure 51
Typical c/s of beam and slab
SD0107 Repair of Fire Damage Concrete Structure 52
Post grouting of columns and beams
It is always possible that some cracks, cavities and voids are unfilled. Post grouting fulfill this task. In addition it ensures homogeneity of encasement concrete/gunite with old concrete.
The different steps followed are as follows:
SD0107 Repair of Fire Damage Concrete Structure 53
Post grouting of columns contd…
1. 16 mm dia holes were drilled to a depth of 100 to 200 mm at 1000 mm c/c in a zigzag manner on all the vertical surface of column and beams.
2. 12 mm dia PVC nozzle was inserted into each hole and the gap around the nozzle was sealed using sealing agent.
3. Pressure grout was applied through every nozzle with a free flowing neat cement grout mixed with the expansive agents (CONBEX-100)
SD0107 Repair of Fire Damage Concrete Structure 54
Post grouting of columns contd…
4. The operating pressure for post grouting was around 1 N/sq.mm
5. Grouting of every hole was continued until refusal.
SD0107 Repair of Fire Damage Concrete Structure 55
Grouting of beams
SD0107 Repair of Fire Damage Concrete Structure 56
Conclusion
The distressed building was thoroughly investigated through physical examination along with NDT and Load Test.
The deficiencies and distress were identified and documented to best of one’s ability. A feasible restoration scheme was proposed and executed carefully and efficiently.
Thereafter a building was put into normal service as it was certified as structurally sound.
SD0107 Repair of Fire Damage Concrete Structure 57
References
A book of ‘Structural Failure’ by R. Jagdish. ‘FIRE SAFETY IN BUILDING’ by
Mr. V.K. Jain. Concrete Society Technical Report no. 15,
May 1978 CONCRETE, volume 18 number, 5 May
1984
Thank you