report no. 6-763 - digital.library.unt.edu

192
TECHNICAL REPORT NO. 6-763 SHOCK-ABSORBING MATERIALS Report 2 CELLULAR CONCRETE AS A BACKPACKING MATERIAL by G. C. Hoffm Civil Engineering Departmert B106 C. E . Building University of Illinois Urbana, Illinois 61801 0l 00 0 ID ,~ ~? sii#AiI r flit June 1971 Sponsored by Defense Atomic Support Agency Conducted by U. S. Army Engineer Waterways Experiment Station, Vicksburg, Mississippi metadc303920 APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED

Upload: others

Post on 25-Feb-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REPORT NO. 6-763 - digital.library.unt.edu

TECHNICAL REPORT NO. 6-763

SHOCK-ABSORBING MATERIALSReport 2

CELLULAR CONCRETE AS A BACKPACKING MATERIAL

by

G. C. Hoffm

Civil Engineering DepartmertB106 C. E . Building

University of IllinoisUrbana, Illinois 61801

0l 00 0 ID

,~ ~?sii#AiI r flit

June 1971

Sponsored by Defense Atomic Support Agency

Conducted by U. S. Army Engineer Waterways Experiment Station, Vicksburg, Mississippi

metadc303920

APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED

Page 2: REPORT NO. 6-763 - digital.library.unt.edu

Destroy this report when no longer needed. Do not returnit to the originator.

The findings in this report are not to be construed as an officialDepartment of the Army position unless so designated

by other authorized documents.

Page 3: REPORT NO. 6-763 - digital.library.unt.edu

TECHNICAL REPORT NO. 6-763

SHOCK-ABSORBING MATERIALSReport 2

CELLULAR CONCRETE AS A BACKPACKING MATERIAL

by

G. C. Hoff

June 1971

Sponsored by Defense Atomic Support Agency

Nuclear Weapons Effects Research SC 210

Conducted by U. S. Army Engineer Waterways Experiment Station, Vicksburg, Mississippi

ARMY-MRC VICKSBURG, MISS.

APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED

Page 4: REPORT NO. 6-763 - digital.library.unt.edu
Page 5: REPORT NO. 6-763 - digital.library.unt.edu

THE CONTENTS OF THIS REPORT ARE NOT TO BE

USED FOR ADVERTISING, PUBLICATION, OR

PROMOTIONAL PURPOSES. CITATION OF TRADE

NAMES DOES NOT CONSTITUTE AN OFFICIAL EN-

DORSEMENT OR APPROVAL OF THE USE OF SUCH

COMMERCIAL PRODUCTS.

3

Page 6: REPORT NO. 6-763 - digital.library.unt.edu

ABSTRACT

The use of low-density cellular concrete, having an oven-dry unit

weight of 50 pcf or less, as a backpacking material for deeply buried pro-

tective structures was studied. Cellular concrete was found to be suitable

for this type of application. A number of physical properties of cellular

concrete were determined to provide input to design codes. Constrained

compressive crushing stress levels from 20 to 1,000 psi for slow rates of

loading were observed. Rapid-loading tests and equation of state measure-

ments were also made to determine the rate sensitivity of the concrete.

Compressional wave velocities from 2,000 to 6,000 ft/sec were also measured.

Modulus of elasticity values from 20,000 to 220,000 psi were measured for

concretes in the as-cast condition with respect to moisture. Flexural

strength to compressive strength ratios from 0.16 to 0.33 were observed.

Early age stiffening characteristics of cellular concrete were also studied.

Some design procedures based on the data analysis are suggested.

Some possible areas of difficulty during prototype use of cellular

concrete as a backpacking, such as lift heights, cold joints, temperature

problems, and water-saturation problems, are also explored. Lift heights

should not exceed those that cause an increase in density over the desired

density by more than a stipulated amount in the lower portion of the lift.

The effects of joint roughness and curing on the joint performance are min-

imal. Temperatures over about 120 F tend to cause collapse of the struc-

ture of unhardened low-density cellular concrete. In a free-water environ-

ment, saturation of the cellular concrete is inevitable unless steps are

taken to prevent the water from reaching the concrete. Suggestions for

doing this are offered.

Page 7: REPORT NO. 6-763 - digital.library.unt.edu

PREFACE

This study was conducted in the Concrete Division of the U. S. Army

Engineer Waterways Experiment Station (WES) under the sponsorship of the

Defense Atomic Support Agency (DASA) as part of Nuclear Weapons Effects Re-

search (NWER) Subtask SC 210, "Response of Buried Structures to Ground

Shock." The work was accomplished under the general supervision of

Mr. T. B. Kennedy, former Chief of the Concrete Division, Mr. Bryant

Mather, present Chief of the Concrete Division, and Mr. J. M. Polatty,

Chief of the Engineering Mechanics Branch. Other staff members actively

participating in the investigation were Messrs. J. L. Hawley, Donato Bres-

cia, and G. C. Hoff. Mr. B. R. Sullivan, Chief of the Engineering Physics

Section, prepared Appendix C. Mr. Hoff was project leader and prepared

this report.

Directors of the WES during the investigation and the preparation and

publication of this report were COL Alex G. Sutton, Jr., CE, COL John R.

Oswalt, Jr., CE, COL Levi A. Brown, CE, and COL Ernest D. Peixotto, CE.

Technical Directors were Messrs. J. B. Tiffany and F. R. Brown.

5

Page 8: REPORT NO. 6-763 - digital.library.unt.edu

CONTENTS

ABSTRACT------------------------------------------------------------- 4

PREFACE-------------------------------------------------------------- 5

NOTATION------------------------------------------------------------- 11

CONVERSION FACTORS, BRITISH TO METRIC UNITS OF MEASUREMENT----------- 12

CHAPTER 1 INTRODUCTION---------------------------------------------- 13

1.1 Design and Construction Considerations------------------------ 131.2 Objective----------------------------------------------------- 161.3 Scope--------------------------------------------------------- 16

1.3.1 Physical Properties--------------------------------------- 161.3.2 Construction Problem Areas-------------------------------- 17

CHAPTER 2 MATERIALS AND FABRICATION, AND PLACING EQUIPMENT ANDPROCEDURES-------------------------------------------------18

2.1 Materials------------------------------------------------------ 182.1.1 Portland Cement--------------------------------------------182.1.2 Foaming Agent-----------------------------------------------19

2.2 Mixture Procedures and Proportions---------------------------- 192.3 Specimen Preparation and Curing------------------------------- 262.4 Placing Equipment and Procedures------------------------------ 262.5 Surface Sealers----------------------------------------------- 27

CHAPTER 3 TEST EQUIPMENT AND PROCEDURES----------------------------- 28

3.1 Constrained Compression Tests--------------------------------- 283.1.1 Slow-Loading Tests---------------------------------------- 283.1.2 Rapid-Loading Tests--------------------------------------- 283.1.3 Multiple-Shot Loading Tests------------------------------- 29

3.2 Flexural Strength Tests--------------------------------------- 303.2.1 Modulus of Rupture Determinations------------------------- 303.2.2 Horizontal Joint Tests------------------------------------ 30

3.3 Ultrasonic Pulse Velocity Tests------------------------------- 323.4 Rate-of-Hardening Tests--------------------------------------- 323.5 Modulus of Elasticity and Poisson's Ratio Tests--------------- 323.6 Temperature Studies------------------------------------------- 33

3.6.1 Adiabatic Temperature Rise-------------------------------- 333.6.2 Mixture Water Temperature Study--------------------------- 333.6.3 Lift Heat Effects----------------------------------------- 333.6.4 Ambient Air Temperature Effects--------------------------- 334

3.7 Lift Height Study--------------------------------------------- 343.8 Moisture Studies---------------------------------------------- 35

3.8.1 Saturation Study------------------------------------------ 353.8.2 Flow and Erosion Tests------------------------------------ 363.8.3 Surface Sealer Tests-------------------------------------- 37

CHAPTER 4 TEST DATA AND ANALYSIS PLAN------------------------------- 51

4.1 Constrained Strength Determinations--------------------------- 514.2 Modulus of Rupture Determinations----------------------------- 524.3 Ultrasonic Pulse Velocity Determinations---------------------- 52

6

Page 9: REPORT NO. 6-763 - digital.library.unt.edu

4.4 Modulus of Elasticity and Poisson's Ratio Determinations----- 534.5 Regression Analysis------------------------------------------ 534.6 Data Dispersion---------------------------------------------- 54

CHAPTER 5 TEST RESULTS--------------------------------------------- 55

5.1 CONSTRAINED COMPRESSION TEST RESULTS------------------------- 555.1.1 Slow-Loading Test Results-------------------------------- 555.1.2 Rapid-Loading Test Results------------------------------- 555.1.3 Multiple-Shot Loading Test Results----------------------- 55

5.2 Flexural Strength Test Results------------------------------- 555.2.1 Modulus of Rupture Test Results-------------------------- 555.2.2 Horizontal Joint Test Results---------------------------- 56

5.3 Ultrasonic Pulse Velocity Test Results----------------------- 565.4 Rate-of-Hardening Test Results------------------------------- 565.5 Modulus of Elasticity and Poisson's Ratio Test Results------- 575.6 Temperature Study Results------------------------------------ 57

5.6.1 Adiabatic Temperature-Rise Results----------------------- 575.6.2 Mixture Water-Temperature Results------------------------ 575.6.3 Lift Heat Effects Results-------------------------------- 585.6.4 Ambient Air Temperature Effects-------------------------- 58

5.7 Lift Height Results------------------------------------------ 585.8 Moisture Study Results--------------------------------------- 58

5.8.1 Saturation Results--------------------------------------- 585.8.2 Flow and Erosion Test Results---------------------------- 595.8.3 Surface Sealer Test Results------------------------------ 59

CHAPTER 6 DISCUSSION OF TEST RESULTS------------------------------- 86

6.1 Constrained Strength-Deformation Characteristics------------- 866.1.1 Slow-Loading Results------------------------------------- 866.1.2 Rapid Loading-------------------------------------------- 936.1.3 Multiple-Shot Loading Capability------------------------- 94

6.2 Flexural Strength-------------------------------------------- 956.2.1 Modulus of Rupture--------------------------------------- 956.2.2 Horizontal Joint Tests----------------------------------- 96

6.3 Ultrasonic Pulse Velocities---------------------------------- 986.4 Rate of Hardening-------------------------------------------- 996.5 Modulus of Elasticity and Poisson's Ratio-------------------- 1006.6 Temperature Problems----------------------------------------- 1016.7 Lift Height Results------------------------------------------ 1056.8 Saturation Problems------------------------------------------ 106

CHAPTER 7 CONCLUSIONS AND RECOMMENDATIONS-------------------------- 117

7.1 Conclusions-------------------------------------------------- 117

7.2 Recommendations---------------------------------------------- 120

APPENDIX A DEVELOPMENT OF A LABORATORY TEST METHOD FOR LOW-DENSITY CONCRETE BACKPACKING---------------------------- 121

A.1 Constrainment-------------------------------------------------121A.2 Specimen and Test Preparations------------------------------- 124A.3 Piston Size-------------------------------------------------- 125A.4 Deformation Rates-------------------------------------------- 126

7

Page 10: REPORT NO. 6-763 - digital.library.unt.edu

APPENDIX B TEST DATA----------------------------------------------

APPENDIX C OBSERVATIONS ON THE EQUATION OF STATE OF CELLULARCONCRETE-------------------------------------------------169

C.1 Theoretical Considerations------------------------------------169C.2 Experimental Method------------------------------------------ 170C.3 Experimental Results----------------------------------------- 171

REFERENCES----------------------------------------------------------177

TABLES

5.1 Summary of Constrained Stress Versus Freshly Mixed Density,Correlation Regression Coefficients, a = a(d)b +2 Sest,y----- 60

5.2 Summary of Modulus of Rupture Versus Freshly Mixed Density,Correlation Regression Coefficients, R = a(d)b +2 Sest,ypsi---------------------------------------------------------- 61

5.3 Summary of Horizontal Joint Test Results--------------------- 625.4 Summary of Ultrasonic Pulse Velocity Versus Freshly Mixed

Density, Correlation Regression Coefficients, V = (a + bd)+2 Sest---------------------------------------------------- 63

5.5 Summary o Modulus of Elasticity and Poisson's Ratio Data---- 645.6 Secant Modulus of Elasticity Versus Hardened Density Rela-

tion, Es = a(d)b +2 5est,y -------------------------------- 655.7 Summary of Temperature-Rise Study Batching Data-------------- 656.1 Summary of Ultrasonic Pulse Velocity (V) Versus Cement Con-

tent (C) Relations, V = aCb +2 Sest,y , ft/sec--------------- 112

FIGURES

3.1 Typical test record for a slow-loading test----------------- 393.2 Slow-loading constrained compression test configuration----- 403.3 Impact air hammer apparatus (IAHA)---------------------------- 413.4 Typical test record for a rapid-loading test---------------- 433.5 Joint scriber and scribe pattern---------------------------- 443.6 Horizontal joint study sampling schedule-------------------- 453.7 Lift height study, 30-foot column--------------------------- 463.8 Lift height study, 16-foot column--------------------------- 463.9 Pressure pycnometer----------------------------------------- 473.10 Low-head, unlimited reservoir permeability test equipment--- 483.11 Specimen container------------------------------------------ 493.12 Sealer study falling head permeameter----------------------- 505.1 Typical stress-deformation curves--------------------------- 665.2 Summary of stress versus freshly mixed density relations,

slow-loading tests, 28-day strength------------------------- 675.3 Summary of stress versus freshly mixed density relations

for rapid-loading tests, 28-day strength-------------------- 685.4 Stress-deformation relations for multiple-shot loading------ 695.5 Summary of the modulus of rupture versus freshly mixed

density relations------------------------------------------- 695.6 Summary of ultrasonic pulse velocity versus freshly mixed

density relations for water-cement ratios 0.66 and 0.76----- 70

8

133

Page 11: REPORT NO. 6-763 - digital.library.unt.edu

5.7

5.8

5.9

5.10

5.11

5.125.135.14

5.155.165.175.185.195.205.215.225.236.1

6.2

6.3

6.4

6.5

6.6

6.7

A.1A.2A.3A.4

A.5A.6A.7A.8B.1-B.27B.28-B.31B.32-B.35

Summary of ultrasonic pulse velocity versus freshlymixed density relations for water-cement ratios 0.86and 0.96---------------------------------------------Summary of ultrasonic pulse velocity versus freshlymixed density relations showing effect of water-cementratio, 28 days age-----------------------------------Penetration resistance versus time relations for 23-and 32-pcf nominal density concretes------------------Penetration resistance versus time relation for 39-and )3-pcf nominal density concretes------------------Summary of secant modulus of elasticity versus freshlymixed density relations-------------------------------Adiabatic temperature development curve---------------Effect of mixture water temperature on early-age heat--Effect of hydration heat on adjoining lifts ofconcrete----------------------------------------------Effect of 100 F air-curing temperature----------------Effect of 120 F air-curing temperature----------------Effect of lift height on concrete density-------------Saturation curve for a cellular concrete--------------Flow data for 23-pcf concrete-------------------------Flow data for 32-pcf concrete-------------------------Erosion data for 23-pcf concrete----------------------Erosion data for 32-pcf concrete----------------------Sealer effectiveness test results---------------------Yield stress versus theoretical porosity relation fora neat cellular concrete------------------------------Relation between yield stress and the design parameter,dc/(l + k)-------------------------------------------Relations between design parameter, dc/(l + k) , andfreshly mixed density for various water-cement ratios--Proposed relation between stress ratio and design pa-rameter, dc/(l + k) , for cellular concrete-----------Rapid loading versus slow loading relation for the av-erage stress to 40 percent deformation characteriza-tion, ' 0 .40- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Ultrasonic pulse velocity versus cement content rela-tions for neat cellular concrete----------------------Secant modulus of elasticity versus modulus parameterrelation----------------------------------------------Rock-backpacking-structure configuration---------------Thick-walled cylinder stresses------------------------Split-wall confining pipe-----------------------------Loading pistons--------------------------------------Typical constrained stress versus deformation relation-Effect of piston diameter on stress-------------------

Effect of piston size on bottoming point--------------Rate of deformation effects---------------------------Test data, stress versus density relations------------Test data, modulus of rupture versus density relations-Test data, modulus of elasticity versus densityrelations---------------------------------------------

9

71

72

73

74

757576

77787980808182838485

113

113

114

114

115

115

116128129130130131131132132

134-160161-164

165-168

Page 12: REPORT NO. 6-763 - digital.library.unt.edu

C.1 Schematic of experimental setup------------------------------ 173C.2 Particle velocity versus time histories---------------------- 174

C.3 Particle velocity versus time histories when impacted withaluminum driver plate---------------------------------------- 175

C.-- Pressure versus time histories------------------------------- 176

10

Page 13: REPORT NO. 6-763 - digital.library.unt.edu

NOTATION

The principal symbols used in this report are listed below. Special-

purpose subscripts and symbols are not listed but are explained in the text.

a,b = equation coefficients

B = beam width

C = cement content, or elastic wave velocity

d = density

D = beam depth

E = modulus of elasticity

f' = yield strengthck = water-cement ratio

L = length

n = porosity

p = pressure

P = load

r = radius

R = modulus of rupture

S = strength

T = time

u = particle velocity

U = energy, or shock wave velocity

V = compressional wave velocity; also, volume (with appropriatesubscripts)

W = weight

X,Y = rectilinear coordinates

E = strain or deformation

y = unit weight

p = specific gravity

a = stress

11

Page 14: REPORT NO. 6-763 - digital.library.unt.edu

CONVERSION FACTORS, BRITISH TO METRIC UNITS OF MEASUREMENT

British units of measurement used in this report can be converted to metric

units as follows.

Multiply By To Obtain

inches

feet

cubic feet

cubic yard

pounds

pounds per square inch

pounds per cubic foot

Fahrenheit degrees

foot -pounds

feet per second

2.54

0.3048

0.02832

0.764555

453.5924

0.070307

16.02

5/90.138255

0.3048

centimeters

meters

cubic meters

cubic meters

grams

kilograms per square centimeter

kilograms per cubic meter

Celsius or Kelvin degreesa

meter-kilograms

meters per second

12

a To obtain Celsius (C) temperature readings from Fahrenheit (F)readings, use the following formula: C = (5/9)(F - 32). Toobtain Kelvin (K) readings, use: K = (5/9)(F - 32) + 273.15.

Page 15: REPORT NO. 6-763 - digital.library.unt.edu

CHAPTER 1

INTRODUCTION

1.1 DESIGN AND CONSTRUCTION CONSIDERATIONS

The use of low-density1 cellular concrete as a backpacking for deeply

buried structures requires an understanding of the properties and character-

istics of these concretes when they are placed as large volume sections in

underground environments. The protective structure designer requires num-

bers that represent the physical properties of the in-place concrete; and

because of the special use of cellular concrete in this situation, these

numbers are generally not available in the literature. The construction

engineer is faced with the problem of using a material as backpacking that

normally is used for roof and floor fills (Reference 1). Some of the con-

struction problems associated with making this transition are unique.

The first area of concern is the in-place physical properties of the

cellular concrete. The effective use of a backpacking requires that its

compressive strength and deformation capabilities be known (Reference 2).

A number of external factors will influence the resistance to loading of-

fered by a cellular concrete of predetermined design. The first of these

will be the degree of constrainment of the concrete when loaded. This con-

straint is a result of the deeply buried configuration (Appendix A). The

values used to describe the strength of the backpacking should reflect

this constrainment. Unfortunately, the actual amount of constrainment and

manner of loading of the concrete are variables that may never be exactly

known and, therefore, must be approximated.

Cellular concrete is a load- and strain-rate sensitive material (Ref-

erence 3). The time rate and history of loading of the backpacking are

variables that will depend on a number of external factors over which a

designer may have no control; yet these factors can influence the

1 Low-density means the concrete has an oven-dried density of less than

50 pcf. (A table of factors for converting British units of measurement

to metric units is presented on page 12.)

13

Page 16: REPORT NO. 6-763 - digital.library.unt.edu

resistance offered by the backpacking when it is loaded. The backpacking

may also be subjected to repeated shock loadings, the frequency and inten-

sity of which may not be known.

Other physical properties such as flexural strength, compressional

wave velocity, modulus of elasticity, and Poisson's ratio are also essen-

tial for design purposes. These properties and the compressive strength

of the cellular concrete should be obtained in such a manner that the con-

dition of the concrete when evaluated approaches that of the in-place con-

crete. An important consideration in this respect is the moisture condi-

tion of the concrete when tested. The in-place concrete will remain at

essentially the same moisture content as when cast, because it will be

sealed on the outer periphery by competent rock and on the ends and inner

periphery by the liner it is protecting. The characterizing parameters for

each type of test should represent concrete in the as-cast moisture

condition.

The cellular concrete, having been designed properly, must then be

fabricated and put in place in such a manner that the finished product

actually represents the designed concrete. Some of the construction prob-

lems associated with the actual use of cellular concrete as backpacking

have been examined (Reference 4), but some others require additional study.

Assuming the concrete can be satisfactorily made and brought to the point

of placement, the depth or lift height to which the concrete can be placed

at one time must be known.

In a deep lift, the very high air content of the cellular concrete

allows the lower regions of the lift to compress or consolidate in the un-

hardened state due to the increasing superincumbent loads resulting from

the unhardened concrete in the upper region. As will be mentioned later,

the consolidation problem may be further compounded by increasing tempera-

tures of and moisture migration in the concrete. In consolidating, the

density of the concrete is increased. As the cellular concrete strength

is a function of the density (Reference 3), the strength will also increase.

When a particular backpacking design strength is to be uniform throughout

the concrete mass, this increase, and hence strength gradient, is not de-

sirable. It is also not desirable from an economy standpoint because it

l4

Page 17: REPORT NO. 6-763 - digital.library.unt.edu

will take more cement to fill a given volume than was initially planned.

Once a satisfactory lift height is determined, where a controlled amount of

density change occurs for a given cellular concrete design, construction

schedules can be established.

By having to place the cellular concrete in lifts for large sections,

the problem of joint preparation arises. Because of the planned mode of

resistance of the buried structure to loading, it is desirable that large

sections of the backpacking do not slide across joints and thus produce a

more serious loading condition than anticipated. Properly designed cold

joints should enable the cellular concrete backpacking to act as a single

mass.

Associated with both the lift height and cold joint problems is the

problem of heat both in and around the cellular concrete. Because of the

high air content of the concrete and, hence, its insulating characteristics,

and the possibility of the confining rock medium behaving as an infinite

heat sink, large amounts of the heat caused by the hydration of the cement

will remain in the concrete for long periods of time. Unhardened cellular

concrete placed in hot environments will experience a reduction of the sur-

face tension of the air bubbles in the void system and a subsequent expan-

sion of the heated air in the bubble. This causes the bubbles to burst

with resulting consolidation of the concrete. This hot environment can

exist in the upper regions of large placements where the bottom of the

placement has begun to stiffen and is developing very hot temperatures. It

can also exist at the interface between a lift of older hot concrete and a

lift of new unhardened concrete, or it can exist in the hot air environment

provided by heat loss from hydrating adjacent sections of concrete. Again,

this is not desirable from the standpoints of both design and economy. Ap-

propriate steps must be taken to reduce, eliminate, or work around these

temperature problems.

Once the cellular concrete is in place it probably will not be seri-

ously affected by any external factors other than loading (Reference 3),

with the exception of water. For the strengths and densities of cellular

concrete being considered for backpacking in this study, cellular concrete

should be considered as being susceptible to water infiltration even at

15

Page 18: REPORT NO. 6-763 - digital.library.unt.edu

very low water pressures (Reference 3). The presence of additional water

in the concrete reduces the amount of void space and greatly affects the

performance of the concrete. To adequately design against the infiltration

of water into the cellular concrete, an understanding of the saturation

characteristics of this concrete is essential.

The problems described above will vary in complexity and severity for

each set of field conditions. Obtaining solutions to these problems for

all possible situations would be a formidable task. The studies described

herein were done, for the most part, in preparation for an actual field job

involving buried structures backpacked with cellular concrete (References

4 and 5). In most cases, the studies were not designed to provide in-depth

answers to the specific problem area studied, but were meant instead to

produce qualitative results that would provide guidance to the individuals

undertaking the actual work.

1.2 OBJECTIVE

The objective of the study was to investigate low-density cellular

concrete for use as a backpacking material for deeply buried structures.

Specifically, the investigation was to determine some physical properties

of the concrete that were indicative of its desired in-place performance

and to examine some problems associated with placing large mass sections

of cellular concrete in underground environment.

1.3 SCOPE

1.3.1 Physical Properties. A constrained compression test was de-

veloped (Appendix A) and used to evaluate numerous mixture designs of cel-

lular concrete for both slow and rapid rates of loading. A limited number

of test specimens were evaluated for multiple-shot loading capabilities.

Other physical properties such as flexural strength, compressional

wave velocity, modulus of elasticity, and Poisson's ratio were also deter-

mined for a number of different mixture proportions. All physical proper-

ties were determined while the concrete was in a moisture condition approx-

imating that of the as-cast condition. Some measurements of the response

of concrete to high-pressure shock loading were also attempted (Appendix C).

16

Page 19: REPORT NO. 6-763 - digital.library.unt.edu

1.3.2 Construction Problem Areas. Selected mixtures were studied for

hydration temperature development, techniques for reducing this temperature,

and the effects of this temperature on additional placements of fresh con-

crete. The effect of lift height on density of the concrete and the prep-

aration of cold joints related to lift construction were also studied.

The effect of free water on in-place cellular concrete was studied and

an examination of some surface sealers for moisture exclusion was conducted.

17

Page 20: REPORT NO. 6-763 - digital.library.unt.edu

CHAPTER 2

MATERIALS AND FABRICATION, AND PLACING EQUIPMENT AND PROCEDURES

2.1 MATERIALS

2.1.1 Portland Cement. Type III cement was used for all the concrete

in the program with the exception of some Type I cement that was used in

portions of the temperature studies. The portland cements representing

both the Type I (RC-551) and Type III (RC-560) met the requirements for

Types I and III, respectively, and had the following chemical and physical

characteristics:

Chemical Analysis Physical Properties

Constituents Percent Type I Type IIIRC-554 RC-560

Type I Type IIIRC-554 RC-560

S i02

A1203

Fe2023CaO

MgO

SO3s3

Ignition loss

Total

Insolubleresidue

Na20

K20

Total alkaliesas Na 0

2C3A

CiS

20.7

4+.8

4.1

61.7

1.8

2.3

1.4

0.99

0.10

0.18

0.26

0.35

6

60

21.1

4.8

4.0

64.6

1.8

2.14

1.4

100.1

0.01

0.13

0.23

0.28

6

58

Normal consistency,pct

Setting time, Gill-more, hours:minutes

Initial

Final

Autoclave expan-

sion, pct

Air content ofmortar, pct

Compressive strengthof mortar, psi

1 day

3 days

7 days

28 days

(Continued)

18

25.0

3:x +5:30

0.01

8.3

2,850

3,765

5,145

27.2

3:20

6:50

0.01

7.2

2,390

3,810

5,165

Page 21: REPORT NO. 6-763 - digital.library.unt.edu

Chemical Analysis Physical Properties

Constituents Percent Type I Type IIIRC-554 RC-560

Type I Type III

RC-554 RC-560

C2S 14 17 Surface area, air

C A? - - 12 permeability fine-I4i ness (Blaine),

cm2/g 3,845 4,790

Specific gravity 3.14 3.13

Heat of hydration,cal/g

7 days 77.7 80.8

28 days 89.7 91.4

2.1.2 Foaming Agent. A foaming agent, AD-186, was used to provide

the stable air-bubble system necessary for the fabrication of cellular con-

crete. A spectroscopic analysis of the foaming agent indicated the presence

of decomposition products of proteins reacted with aliphatic fatty acids or

salts of fatty acids. The manufacturer refers to his product as a hydro-

lyzed stabilized protein foaming agent.

For use, a premixed solution of a predetermined concentration of

foaming agent and water was prepared. The solution was then placed in a

pressure container and subjected to a controlled air pressure. The air

pressure forced the solution through a discharge line into a blending noz-

zle that agitated the solution and combined it with compressed air. The

resulting product that issued from the blending nozzle was a stable, pre-

formed foam having the consistency of shaving cream obtained from aerosol

cans. This preformed foam provides the stable air-bubble system in the

cellular concrete.

2.2 MIXTURE PROCEDURES AND PROPORTIONS

All the cellular concrete was batched in a 5.5-ft3 horizontal-drum

mortar mixer. The rubber-edged blades of the mixer were modified to obtain

19

Page 22: REPORT NO. 6-763 - digital.library.unt.edu

better mixing action by adding heavy-duty 1-inch screening between the

struts of each individual blade. The batching sequence was water followed

by cement, which was mixed until a well-blended slurry was obtained. The

preformed foam was then added and blended into the slurry until a uniform

consistency of cellular concrete was obtained.

The following procedure was used to design all of the neat cellular

concretes used during the program.

The total size of a batch of neat cellular concrete can be expressed

in terms of the volumes of all the constituents in the batch:

Vb = V + V (2.1)

where

Vb = volume of batch, ft 3

b3V = volume of neat slurry, ft3

5

V = volume of preformed foam, ft 3

The volume of slurry is composed of cement, water, and entrained air:

V5 =Vc +Vsw +Vsa (2.2)

where

Vc = volume of cement, ft 3

Vs= volume of slurry water, ft 3

V = volume of entrained slurry air, ft 3

The preformed foam volume is composed of the volume of foam air and the

volume of premixed solution:

V =V +V (2-3)

20

Page 23: REPORT NO. 6-763 - digital.library.unt.edu

where

Vfa = volume of foam air, ft3

V = volume of foam water, ft 3

Substituting in Equation 2.1:

V = V + V + V + V + V (2.4)b c sw sa fa 'w (

The proportioning of the cellular concrete begins with the selection

of the desired freshly mixed density and water-cement ratio for the con-

crete. The water-cement ratio by weight of the ingredients of the concrete

can be expressed as

k W(2.5)

wc

where

k = water-cement ratio of the slurry, dimensionless

W = weight of total water in concrete, pounds

We = weight of cement in concrete, pounds

The weight of the total water is composed of the weight of the slurry water

plus the foam water:

Wtw =sw + W f(2.6)

where

W = weight of slurry water, pounds

W = weight of foam water, pounds

The amount of air needed to form the cellular structure of the concrete

is determined by the density of concrete desired once the water-cement and

properties of the cement are known. The density is expressed as:

21

Page 24: REPORT NO. 6-763 - digital.library.unt.edu

Wb

d Wb - (2.7)c Vb

where

do = freshly mixed concrete density, pcf

Wb = total weight of mixture ingredients, poundsb3

V = total batch volume, ft3b

The total batch weight is:

w = w + w(.)b c tw (2.8)

=W +W +Wc sw fw

From Equations 2.5, 2.7, and 2.8, the batch volume can be written as:

W + W-c tw

b dc

W + kwc cdc

WVb = (k + 1) (2.9)

c

or

Wc k+ 1c(2.10)

The concrete volume requirement and/or batching equipment capacity will

then determine the amount of cement in the batch. Having determined the

amount of cement, the total amount of water needed can be found from Equa-

tion 2.5. The volumes of cement and water can then be found as:

22

Page 25: REPORT NO. 6-763 - digital.library.unt.edu

W

V = pc(2.11)Cew

and

V = ---- (2.12)tw 7w

where

pc = specific gravity of the cement, dimensionless

w unit weight of water, pcf

The volume of air in the slurry Vsa is usually small with respect to the

air volume provided by the foam. For simplicity in design, the required

batch air, Va , can be written as:

Va = Vsa + V fa Vfa (2.13)

and assumed to be provided entirely by the foam. From Equation 2.1,, then

V = V - V - V (2.1)a b c tw (.4

where Vb, C , and Vtw have already been determined.

The foam-producing generator nozzle operates at a constant discharge

rate and produces a foam of constant density. Assuming all of the solids

of the foam to be water, the foam density, df , is expressed as:

W

fwd -(2.15)f Vf

From Equations 2.3 and 2.15

V ~ V = V - vfa a f fw

d V= V -f~

f 7

1 - d

Va = V w(2.16)a f 7

23

Page 26: REPORT NO. 6-763 - digital.library.unt.edu

and7

Vf= = W d V (2.17)S 7- d aw f

From Equation 2.17, the exact amount of foam to be put in the batch is

determined.

The amount of slurry water that must be initially added to the cement

can be found from Equations 2.6 and 2.15, where:

W = dV (2.18)fw f f

and

Wsw = W -W (2.19)swtw fw

The water-cement ratio in the slurry before the foam is added is then:

Wk sw

1 Wc

where k = water-cement ratio of ingredients initially added to mixer,dimensionless

As an example, assume that a 4.0-ft 3 batch of 32-pcf concrete with a final

water-cement ratio of 0.86 is needed. The specific gravity of the cement

is 3.15; the foam density is 2.3 pcf; and the unit weight of water is

62.3 pcf from Equations 2.5, 2.10, 2.11, and 2.12.

bdc (4.0)(32) = 68.8 poundsc k+1 1.8

Wtw = kWc = 0.86(68.8) = 59.2 pounds

Wc 68.83VC,= W = 688 = 0.350 ft3c pcyw (3.15)62.3

Wt 5Vt = = 59.2 0.950 ft3

tw 7Y 62.3w

The volume of air and foam required can then be found from Equations 2.14

and 2.17.

Page 27: REPORT NO. 6-763 - digital.library.unt.edu

va =Vb --c vtw = (.o - 0.350 - 0.950) ft3

V = 2.700 ft3

V = 7 wd V = 62.3 2.700 ft3f 7w - df a 62.3 -2.3

Vf = 2.925 ft 3

The foam and slurry waters can then be found from Equations 2.18 and 2.19.

W = d V = 2.3(2.925) pounds

= 6.7 pounds

W 5 = WW -W = 59.2 - 6.7

= 52.5 pounds

Hence, if 68.8 pounds of cement and 52.5 pounds of water are blended in the

mixer to form a slurry and the 2.925 ft3 of foam is added, the desired con-

crete with respect to density and water-cement ratio should be obtained.

Small adjustments may have to be made to compensate for air content changes

during mixing.

For comparison purposes throughout the studies reported herein, it was

attempted to use five specific water-cement ratios by weight, i.e. 0.66,

0.76; 0.86, 0.96, and 1.06, and four specific freshly mixed densities of

23, 32, 39, and 43 pcf at each water-cement ratio. Exceptions were not

uncommon and are noted where they occurred. The number of batches pro-

viding test specimens for the slow-loading tests were 13, 31, 31, 21, and

36 for the 0.66, 0.76, 0.86, 0.96, and 1.06 water-cement ratios, respec-

tively. The number of batches providing specimens for the rapid-loading

test were 16, 22, 16, and 30 for the 0.76, 0.86, 0.96, and 1.06 water-cement

ratios, respectively.

25

Page 28: REPORT NO. 6-763 - digital.library.unt.edu

2.3 SPECIMEN PREPARATION AND CURING

Except where stated otherwise, all specimens were cured in their

casting molds for 24 hours and upon removal from these molds were immedi-

ately placed and sealed in polyethylene plastic bags and stored at 73 F

until tested.

The test specimens for all of the constrained compression tests were

cast as 6- by 12-inch cylinders. Forty-eight hours before being tested,

each specimen was removed from its bag and the top and bottom 3 inches were

sawed off. The remaining 6- by 6-inch cylinder was then resealed in its

plastic bag until tested. At testing time, the time lapse from removal of

the specimen from the bag to the start of test was only a few minutes.

When a 6- by 12-inch cylinder was used for a specific type of test, the

unformed end of the cylinder was trimmed with a saw to eliminate surface

irregularities.

Each 6- by 12-inch cylinder used for the Poisson's ratio and modulus

of elasticity determinations was instrumented with two A-9-6 electrical

strain gages placed vertically and diametrically opposite and two similar

gages placed circumferentially and diametrically opposite. The gages were

bonded to the specimens by means of a very low modulus, flexible epoxy

binder (CRD-EP-1). The binder also was used to cover the gage for water-

proofing purposes. To avoid moisture loss from the specimens during gage

mounting, a special polyethylene tent was built and the mounting was done

within the tent at a relative humidity of 98 percent. The surface of the

specimen was not dried in any way before, during, or after the gages were

mounted. The gages were mounted after 24 days of continuous bag curing.

2.4 PLACING EQUIPMENT AND PROCEDURES

The placing of the cellular concrete in all molds and formwork with

the exception of the lift height study was done by pouring the very fluid

concrete from the mixer into a bucket and from the bucket into the desired

container. No vibration or consolidation of the concrete was attempted.

The concrete for the columns cast during the lift height study was pumped

from the mixer to the point of placing using an open-throat positive

displacement pump and continuous plastic hose.

26

Page 29: REPORT NO. 6-763 - digital.library.unt.edu

2.5 SURFACE SEALERS

The

studies.

following materials were used as surface sealers in the moisture

WES Designation Description

CRD CM-9 Styrene -butadiene product

CRD CM-lO Two-component epoxy thinnedwith a volatile solvent

CRD CM-ll Paraffin-resin mixture

CRD CM-12 Liquid latex

CRD CM-8 Vinyl-based liquid-type solvent

CRD CM-13 Asphalt

CRD CM-1+ Latex wall paint

RC-560 Neat Type III cement slurry

- - Hydraulic cement slurry

27

Page 30: REPORT NO. 6-763 - digital.library.unt.edu

CHAPTER 3

TEST EQUIPMENT AND PROCEDURES

3.1 CONSTRAINED COMPRESSION TESTS

The details of the design of the constrained compression test are con-

tained in Appendix A.

A split-wall confining pipe was used to provide lateral constraint to

the concrete tested in compression. The steel pipe (Figure A.3) had a

6-inch-inside diameter with 1/4-inch-thick walls and accommodated a 6-inch-

high specimen. The 1/4-inch wall thickness resulted in negligible lateral

strains for the largest vertical loads experienced during the program.

After placing the specimen in the pipe, both closure bolts were torqued to

a final closure of 5 ft-lb. Loads were applied through a 4-inch-diameter

loading piston centered on the 6-inch-diameter specimen. The constraining

pipe, loading piston, closure torque, and specimen size (6- by 6-inch cyl-

inder) were the same for both the slow- and rapid-loading tests.

3.1.1 Slow-Loading Tests. Load was applied to the specimens using a

30,000-pound Universal testing machine operating at a constant rate of

loading piston movement of 0.18 in/min (3 percent deformation per minute).

Deformations were measured by a linear slide-wire potentiometer affixed to

the base platform and the moving loading head of the testing machine.

Loads were converted to applied stress by dividing the magnitude of the

applied load by the area of the 4-inch-diameter loading piston. The re-

sulting stress-deformation data from each test were recorded in a graphical

form (Figure 3.1) using an X-Y recorder. Figure 3.2 shows the slow-loading

test arrangement.

3.1.2 Rapid-Loading Tests. Rapid-loading tests were conducted using

the Impact Air Hammer Apparatus (IAHA). A cross section of the IAHA is

shown in Figure 3.3. Load was applied to the specimen through the 4-inch-

diameter piston on the end of the driving shaft. The driving shaft had a

maximum travel distance of 4 inches.

Before beginning a test, a small amount of gas pressure is placed in

the trigger actuator chamber to lock the triggering mechanism in place on

the driving shaft. The specimen is then placed and centered under the

28

Page 31: REPORT NO. 6-763 - digital.library.unt.edu

loading piston. The upper surface of the specimen is brought in full con-

tact with the bottom surface of the loading piston by means of an adjustable

turnscrew on the bottom of the base bearing plate of the apparatus. The

desired amount of gas pressure is then placed in the accumulator tank, and

the specimen is ready for testing. By electrically releasing the gas pres-

sure through an orifice in the actuator chamber, the triggering mechanism

rotates and releases the driving shaft that, due to the accumulator tank

pressure, drives the loading piston into the specimen.

Compressed nitrogen gas was used as the load gas for all tests. The

amount of gas pressure required for each individual test depended on the

energy absorbing capacity of the sample being evaluated. Experience with

the IAHA and the cellular concrete allowed the IAHA operators to vary the

gas pressure from test to test, depending on the material being evaluated,

such that the total time of test for a full 14 inches of deformation of each

sample never varied from 15 3 msec. Rise times to the start of the crush-

ing plateau varied between 2 and 4 msec.

Loads were measured by a recording load cell placed between the driv-

ing shaft and the loading piston. Deformations were measured using a lin-

ear slide-wire potentiometer fastened to the IAHA frame and the driving

shaft. The output from both the load cell and the slide-wire potentiometer

was recorded on a dual-trace oscilloscope photograph record such as that

shown in Figure 3.4. The electrical impulse that released the gas in the

trigger actuator chamber also operated the shutter on the oscilloscope cam-

era, thus opening the shutter at the instant the test began. Both traces

on the photograph record are on a common time basis. The upper trace in-

dicates total deformation in inches at any point in time; the lower trace

indicates the load on the sample at any point in time. By combining the

load and deformation on a common time basis and converting the load to

stress over the area of the loading piston and deformation to percent of

total sample height, a stress-deformation record such as shown in Figure

3.1 was obtained.

3.1.3 Multiple-Shot Loading Tests. The multiple-shot loading tests

were conducted exactly like the rapid-loading tests (Section 3.1.2) with

the exception that only enough pressure was used in the accumulator tank

29

Page 32: REPORT NO. 6-763 - digital.library.unt.edu

to partially deform the specimen on the first loading. After the first

loading shot, the driving shaft and piston were reset for firing, the load-

ing surface of the specimen was brought in contact with the piston face by

means of the baseplate turnscrew, the accumulator tank was recharged, and

the air hammer was fired again. This behavior would duplicate a rock frag-

ment driven into the backpacking by an initial shock wave and then driven

in even farther by a second shock wave.

Two oscilloscope records were obtained for each test, one for each of

the two shots. The records were combined so that the point where the first

record ended was the point where the second record began. Deformation for

both shots, expressed in percent, was referenced to the initial height of

the specimen before the testing began.

3.2 FLEXURAL STRENGTH TESTS

Flexural strength tests were made to determine the modulus of rupture

of the cellular concrete at various densities and water-cement ratios and

also to evaluate the effects of cold joints in the concrete for a selected

mixture. In both cases, the equipment and testing were in accordance with

CRD-C 16-66, "Flexural Strength of Concrete (Using Simple Beam with Third-

Point Loading)."

3.2.1 Modulus of Rupture Determinations. Six-inch-square by 20-inch-

long beams were evaluated. The distance between each support and its

closest loading point and between both loading points was 6 inches. All

beams were placed in plastic bags immediately after removal from the cast-

ing forms and were bag-cured at 73 F until tested at 28 days age. Each

beam remained in the bag until testing time when it was removed, immediately

placed in the load apparatus, and tested.

3.2.2 Horizontal Joint Tests. Cellular concrete with a freshly placed

density of 32.7 pcf at a water-cement ratio of 0.86 by weight was used to

fabricate sixteen 2-foot cubes. Each cube was placed in two lifts. The

first lift was placed to a depth of 1 foot and allowed to harden. Before

placing the second lift, the top surface of the first lift was prepared

four different ways. Eight cubes had the top surface exposed to air for

3 days before the next lift was placed. Four of these eight had the

30

Page 33: REPORT NO. 6-763 - digital.library.unt.edu

surface scribed in a waffle pattern to provide some roughness for the next

lift to bond to. The remaining four air-dried cubes were left in the as-

cast condition. The last cubes were treated in the same manner as the

first eight with the exception that the exposed surface was sealed in plas-

tic to prevent drying. The seal was removed at the time the fresh concrete

was placed.

The scribing was done using a simple apparatus resembling an ordinary

leaf and grass rake. Eight 5/32-inch-diameter by 3/4-inch-long prongs ta-

pered to a point were used as shown in Figure 3.5a. The scribing was done

at right angles to the cube mold, with the first indentation occurring at a

distance of 3/4 inch from the mold. The resulting pattern is shown in Fig-

ure 3.5b. The depth of scribing was approximately 1/2 inch. All loose

material resulting from scribing was removed with a vacuum cleaner.

The second lift was placed to the top of the mold. The top surfaces

of the first eight blocks were again exposed to air drying while the sur-

faces of the second eight were sealed in plastic. After the second lift

had cured 28 days, the forms were removed and the blocks sampled. The

sampling originally was to involve drilling some 6-inch-diameter cores

from each block and also to saw some 6- by 6- by 24-inch beams from each

cube. The sampling arrangement is shown in Figure 3.6. Half of the beams

shown in the top view were to have been drilled cores. The drilling op-

eration was extremely difficult; and because of the weak, brittle nature

of the concrete, very few intact cores were obtained. None of the cores

were tested because no useful comparison data could be obtained from

the small number of cores available. Only 11 of the 16 blocks were cored.

A no-joint control beam was obtained from each lift. The other beams

from each block included the joint at their center. Immediately after saw-

ing, each beam was placed in a plastic bag and stored until the concrete in

the second lift was 60 days old, at which time each beam was tested in

third-point flexure. This method placed the cold joint in the region of

maximum moment and presented a severe loading situation for the joint. The

plane of failure was noted for each beam along with the maximum failure

load.

31

Page 34: REPORT NO. 6-763 - digital.library.unt.edu

A 4-inch cube was sawed from each half of each broken flexure beam and

oven-dried to a constant weight. The densities of the cubes were then de-

termined in order to establish if density variations between the two lifts

of concrete were influencing the failures of the beams. Compressive

strengths of each cube were also determined in accordance with ASTM C513.

3.3 ULTRASONIC PULSE VELOCITY TESTS

Ultrasonic pulse velocity equipment and tests were in accordance with

CRD-C 51-68, "Tentative Method of Test for Pulse Velocity Through Concrete."

All samples were 6-inch-diameter by 12-inch-(normal) high cylinders that

were continuously bag-cured with interruptions in curing occurring only for

the few minutes required to obtain a pulse velocity reading at a given age.

Velocities were determined for all pulse velocity samples at ages of 3, 7,

14, 28, and 60 days and also at 90 and 180 days for concrete samples made

with water-cement ratios of 0.86 and 0.96.

3.4 RATE-OF-HARDENING TESTS

Rate of hardening of the cellular concrete was determined in accord-

ance with CRD-C 68-69, "Time of Setting of Concrete Mixtures by Penetration

Resistance," with the exceptions that none of the specimens were consoli-

dated by mechanical means and that the minimum spacing between penetration

points was 2 inches. Specimens of concrete made at water-cement ratios of

0.76, 0.86, 0.96, and 1.06 with nominal densities of 23, 32, 39, and 43 pcf

at each water-cement ratio were evaluated at varying time intervals to

90 hours total elapsed time after batching.

3.5 MODULUS OF ELASTICITY AND POISSON'S RATIO TESTS

The modulus of elasticity and Poisson's ratio were determined in ac-

cordance with CRD-C 19-66, "Static Young's Modulus of Elasticity and Pois-

son's Ratio in Compression of Cylindrical Concrete Specimens."

The test specimens were 6- by 12-inch cylinders with sawed ends so

capping was not necessary. All specimens were bag-cured from the time of

removal from the mold until tested. The curing of each specimen was in-

terrupted for a few hours at 24 days of age for the instrumenting of the

32

Page 35: REPORT NO. 6-763 - digital.library.unt.edu

specimen with electrical-resistance strain gages. Care was taken during

instrumentation to prevent moisture loss from the specimens. Two 6-inch

gages were mounted diametrically opposed in a vertical direction with two

similar gages mounted circumferentially opposed at the midpoint of the

specimen. After the gage installation, each specimen was returned to its

curing bag where it remained until testing at 28 days age. With the excep-

tion of the ends of each cylinder that were in contact with the testing

machine, the curing bag remained around the specimen during test to prevent

surface drying of the cylinder. When tested, each cylinder had a moisture

content approximating that of the as-cast condition. Data were obtained in

the form of stress-strain records for both sets of gages by using an X-Y

recorder.

3.6 TEMPERATURE STUDIES

3.6.1 Adiabatic Temperature Rise. The adiabatic temperature rise of

cellular concrete made with Type III cement (RC-560) with a water-cement

ratio of 0.86 and a freshly mixed density of 43.9 pcf was determined in ac-

cordance with CRD-C 38-66, "Method of Test for Temperature Rise in Con-

crete," with the exception that the concrete was not vibrated when placed.

3.6.2 Mixture Water Temperature Study. Because of the expense in-

volved in conducting the quantitative adiabatic tests, a simpler but quan-

titatively less accurate test was used to obtain qualitative heat develop-

ment results that would reflect the general effects of varying the mixing

water temperature.

Eight thick-walled polystyrene picnic coolers were used as both the

container and insulator for the concrete. Each cooler was filled with one

batch of concrete. Each batch of concrete was a different combination of

the cement type and mixing water temperature variables. Using thermometers,

two concurrent temperature measurements were made in each cooler at points

near the center of the concrete mass. The measurements were made at vari-

ous time intervals through 15 hours total elapsed time.

3.6.3 Lift Heat Effects. This test was designed to produce qualita-

tive results relating to the effects of the heat generated in a hardened

lift of concrete on the temperatures developed in fresh cellular concrete

33

Page 36: REPORT NO. 6-763 - digital.library.unt.edu

placed on the surface of the hardened concrete.

Two 2-foot cubes of concrete were cast, each cube being composed of

two 1-foot lifts. Three thermocouples were placed in each lift. In each

cube, the first thermocouple was placed 1-1/2 inches below the top surface

of the lift and at the center of the horizontal area of the lift. The

second and third thermocouples were placed directly below the first but at

depths of 6 and 10-1/2 inches below the lift surface, respectively. The

concrete placed in each lift was not vibrated. After placing the concrete

in the first lift, the thermocouples in that lift were monitored to deter-

mine the heat development in the lift. After initial stiffening of the

first lift had occurred, the second lift was placed and its thermocouples

were monitored along with the first lift thermocouple nearest the joint be-

tween the two lifts. The heat development as indicated by these thermo-

couples was measured until it appeared to reach peak values and began to

decline.

3.6.4 Ambient Air Temperature Effects. Three 6- by 12-inch cylinders

were made from each of four different densities of cellular concrete. Im-

mediately after casting, one cylinder from each density was placed in air

temperatures of 80, 100, and 120 F and allowed to harden. After 24 hours

curing, one-half of the cylinder mold was removed and the amount of damage

to each cylinder noted.

3.7 LIFT HEIGHT STUDY

Two columns of cellular concrete were placed and sampled to determine

the variation in density of the concrete with increasing lift height. The

first column was cast in a 6-inch-inside-diameter by 30-foot-long plastic

pipe (Figure 3.7). The pipe was plugged on the lower end and placed in a

9-inch-inside-diameter cased hole in the ground. Concrete with a unit

weight of 32.4 pcf and a water-cement ratio of 0.86 was pumped into the

pipe through a 50-foot-long, 2-inch-inside-diameter plastic hose. Pumping

was done with an open-throat, positive displacement pump. The end of the

discharge hose was kept at a distance of approximately 1 foot from the

freshly placed concrete surface with the hose being continually withdrawn

from the pipe during placing.

34

Page 37: REPORT NO. 6-763 - digital.library.unt.edu

The concrete was allowed to harden and cure for 3 days at which time

the annulus between the hole casing and the pipe was gradually filled with

water. The water caused the pipe to be displaced and float out of the

casing. As the pipe moved out of the casing, sections of the pipe approxi-

mately 12 inches long were cut off and immediately measured and weighed.

Twenty-nine sections were obtained. At a later date, the concrete in each

section was removed and the weight of the plastic pipe determined. By sub-

tracting this weight from the original weight measurement that included the

pipe, the density of the concrete in each section was calculated.

The second column was cast in a 48-inch-diameter by 16-foot-long cor-

rugated culvert pipe (Figure 3.8). The cellular concrete mixture had a

unit weight of 31.8 pcf. The pumping equipment and procedures were the

same as for the 30-foot column. After hardening and curing for 3 days,

3-foot sections of the corrugated pipe were removed from top to bottom of

the pipe and 1-foot-thick slices were cut from the exposed concrete by

means of a chain saw. Each slice was immediately quartered with an 8-inch

cube being cut from the center of each quarter by a diamond saw. The weight

and measurements of each cube were determined immediately after cutting.

Cutting was done without the use of water or oil so as not to change the

density of the concrete through the addition of some fluid which might have

been absorbed. The average density of the four cubes from each slice was

reported as the as-cast density of the concrete at that point. The cubes

were then oven-dried, and the oven-dry density of the concrete was obtained

so as to get an indication of moisture variations in the column.

3.8 MOISTURE STUDIES

3.8.1 Saturation Study. Five 6- by 12-inch cylinders were used to

determine the amount of available voids in a selected design of concrete

that could be filled with free water. The 28-day bag-cured and oven-dried

densities of the concrete were 51 and 33 pcf, respectively.

Each cylinder, in the bag-cured condition, was placed in a pressure

pycnometer (Figure 3.9). The pycnometer was filled with measured amounts

of water until it contained a specified volume of material (specimen plus

water). The water completely covered the specimen. Pressure was then

35

Page 38: REPORT NO. 6-763 - digital.library.unt.edu

applied gradually to the surface of the water, thus forcing the water into

the specimen. Additional measured amounts of water were continually added

to the pycnometer to maintain a constant filled volume as the water in the

pycnometer was forced into one specimen. When a pressure of 1,200 psi was

reached, no additional water could be added to the system, thus indicating

saturation of the specimen. The amount of voids available for filling by

water was determined from the volume of water forced into the specimen plus

the volume of water initially in the specimen (bag-cured weight minus oven-

dry weight divided by 62.3). During the buildup to 1,200-psi water pres-

sure, the amounts of water forced into the specimen at pressures of 50, 150,

300, and 600 psi were also noted.

3.8.2 Flow and Erosion Tests. A low-head, unlimited reservoir perme-

ability unit (Figure 3.10) was used to determine the water flow character-

istics and erosion possibilities of the cellular concrete. The unit, as

used, tested six 6- by 6-inch test cylinders simultaneously at pressure

heads that were determined by the head losses through the system.

Each specimen was bag-cured 28 days before being placed in a specimen

container (Figure 3.11). The specimen container was constructed from a

standard 6- by 12-inch concrete cylinder mold that was held between two

8- by 8- by 1/4-inch-thick steel plates by means of four bolts. Rubber

gaskets were used as seals between the container and end plates. A 1-inch

nipple was welded in the center of the top plate for connection to the

water reservoir. A deflection flange was placed directly under the nipple

opening to prevent surface erosion of the specimen by water coming into the

container. The bottom plate had a 1-inch-diameter hole in its center to

allow water passing through the concrete to discharge from the container.

Immediately after removal from the curing bag, the peripheral area of

the cylinder was given an initial coating of vinyl-based sealer and the

specimen was replaced in the curing bag. Approximately 4 hours later, a

second coat of sealer was applied over the first; and before it could

harden, the specimen was placed in the bottom half of the split-walled

specimen container that was then tightly closed about the specimen to pre-

vent leakage. Molding clay was used to seal the top edge of the specimen.

The water reservoir consisted of an elevated barrel of a constant

36

Page 39: REPORT NO. 6-763 - digital.library.unt.edu

volume. The barrel was continually filled with water, with an overflow

outlet at the top of the barrel providing a constant water level in the

barrel. Outlets at the bottom of the barrel provided the source of water

for the test specimens.

The bottom of each specimen container was immersed in water contained

in a metal trough (Figure 3.11). An overflow was provided in the trough to

maintain the water level in the trough at a constant level. The overflow

was constructed so it would allow the collection of overflow water.

After the specimen was in place in the container and the hoses from

the reservoir to the container were connected, water was allowed to flow

through the system with any air in the system being bled off through a

bleeder tube. The head on each specimen was determined from piezometer

tubes. After 15 minutes of flow time, the initial flow determination was

made by collecting the overflow water in a known volume container and meas-

uring the time it took to collect it. The water sample was also used to

determine total solids of the water passing through the specimen. Addi-

tional measurements of the same type were made over the duration of the

test. The total elapsed flow time did not exceed 80 hours for any test.

3.8.3 Surface Sealer Tests. A falling head permeameter was used to

determine the effectiveness of various types of surface sealers. By plac-

ing a known head of water on a sealed concrete surface and then measuring

the loss of head with time as the water passes through the sealed surface,

an indication of the sealers' effectiveness can be obtained.

The permeameter was constructed by placing a 6-inch-inside-diameter by

6-foot-long Plexiglas pipe on the sealed surface of an 18-inch cellular

concrete cube (Figure 3.12). The concrete had a freshly mixed density of

31 pcf and water-cement ratio of 1.06 by weight. Ten cubes were cast and

cured 7 days in the wooden forms in which they were cast. The exposed top

surface of the concrete was covered with a polyethylene sheet during curing

to prevent drying. On the seventh day, the polyethylene sheet was removed

and surface irregularities of the concrete were scraped off. The coating

was then applied over the entire surface and allowed to dry for 3 days.

The coating thickness varied from material to material because of the

widely different consistencies of the various material sealers.

37

Page 40: REPORT NO. 6-763 - digital.library.unt.edu

Manufacturers' guidelines for coating application were followed when pro-

vided. In all cases only one coat was applied. The average thickness of

the paraffin and cement slurry coatings was approximately 1/16 inch.

After the coating had dried for 3 days, the bottom of the wooden form

was removed and the cube with the side forms still on was placed on wooden

supports in a large tank as shown in Figure 3.12. The tank was filled with

water to the level of the top surface, of the concrete, with an outlet pro-

vided in the tank to maintain that level. The vertical Plexiglas pipe was

centered on the block and sealed around the outer edge with modeling clay

to prevent water leakage. The pipe was then filled to its top with water

and the test observations were immediately begun. The filling of the pipe

took approximately 2 minutes. Care was taken not to erode or damage the

sealed surface during filling.

Water-level determinations were made visually using a tape measure

affixed to the pipe. The total elapsed time at which any given water level

was observed was measured with a stopwatch and referenced to the time at.

which the pipe was completely filled.

The same procedure was used for all nine sealers. The control block

(no sealer) was evaluated at 10 days age using the same procedures.

38

Page 41: REPORT NO. 6-763 - digital.library.unt.edu

1600

-1200

concon

U)w Ua

IdDUn , ,

800

400

0

2 OrO

[ _ _I _I _ _ I __ I _ _ J I _ _

I0 20 30 40 50 60DEFORMATION, PCT

Figure 3.1 Typical test record for a slow-loading test.

70 800

Page 42: REPORT NO. 6-763 - digital.library.unt.edu

.. ms M s +30,o60 LB UNI1VERSAL ITEST ING MACHINE

Figure 3.2 Slow-loading constrained

compression test configuration.

4o

Page 43: REPORT NO. 6-763 - digital.library.unt.edu

- 8.6" -EXHAUST

2 WAY SOLENOID

4-::

l

O" RINGS

jli

I I

i

I

I I -

w - I

II

m

I III

Q IIIU Iz iw

F-U Q

cc Ixw

U

F-

LOAD

I

II I ICI I. ,

i '

o.

w

I

a.

ICE'

w

z

J

Milli

CLAMP 'I

CELL r

ACCELEROMETER

4" I

4.5"

2 WAY SOLENOID

GAS LINE TO TRIGGER

CROSS SECTION

SCALE IN INCHES0 1 2 3

GAS SOURCE

Figure 3.3 Impact air hammer apparatus (IAHA).

0

U1

Z

0

w

0

F-

lu

Cf)

C9

O

Z

W

J

O

N

Q

3

F-V)D

Q

x

w

Page 44: REPORT NO. 6-763 - digital.library.unt.edu
Page 45: REPORT NO. 6-763 - digital.library.unt.edu

Figure 3.4 Typical test record for arapid-loading test.

43

T

Page 46: REPORT NO. 6-763 - digital.library.unt.edu

7 AT/2-/N.

FRONT VIEW

a. JOINT SCRIBER

44

SIDE VIEW

A-TOP V/EWOF FIRSTL IF T

b. JOINT SCRIBE PATTERN

Figure 3.5 Joint scriber and scribe pattern.

6.14 /Z' 0-

-

o-5ii_

Page 47: REPORT NO. 6-763 - digital.library.unt.edu

HH

TOP VIEW

U

U

2-FT CUBE

-6" X6" E 24"JO/NT BEAMS (6)

CONTROL BEAMS (2)

SIDE VIEW

HORIZONTALALJO/N T

Figure 3.6 Horizontal joint study sampling schedule.

Page 48: REPORT NO. 6-763 - digital.library.unt.edu

Figure 3.7 Lift height study, 30-foot column.

Figure 3.8 Lift height study,16-foot column.

4A?

*1

46

All,

«

K

y.

'r

L

.tip rK. A

M

C.

i

Page 49: REPORT NO. 6-763 - digital.library.unt.edu

sy

aa

rr #5

Figure 3.9 Pressure pycnometer.

N

1I

4 "t ' t

i

r

s

Page 50: REPORT NO. 6-763 - digital.library.unt.edu

' 4 ?

p

..

z 717'Wt

S

s, .

-11

ar

Figure 3.10 Low-head, unlimited reservoirpermeability test equipment.

48

I /e

x

titer. -s 3

S

. P', M

Page 51: REPORT NO. 6-763 - digital.library.unt.edu

TO WATER RESERVOIR

SHUTOFF VALVE

BLEEDER TUBE

TOPIEZOMETER

TUBES

1/4-INCH REDRUBBER GASKET ---

DEFLECTION FLANGE

TROUGH

TEST

WATER LEVEL SPECIMEN

1/4-INCH RED RUBBER GASKET

Figure 3.11 Specimen container.

49

Page 52: REPORT NO. 6-763 - digital.library.unt.edu

-/NT/AL WATER LEVEL

_T1

I -

_jul

65

CONTI NUALLY CHANGINGWATER LEVEL

CLAY SEAL

- -. CELLULAR- -: CONCRETE

- - - 4 - - -

Figure 3.12 Sealer study

OUTLET

_WOODENFORMS

falling head permeameter.

50

h

ho = 6 FT

SEALED SURFACE-

LH

vr

IZ .411 1 z .411lif I

_-

Page 53: REPORT NO. 6-763 - digital.library.unt.edu

CHAPTER 4

TEST DATA AND ANALYSIS PLAN

4.1 CONSTRAINED STRENGTH DETERMINATIONS

All measured loads were converted to stress in pounds per square inch

of area of contact of the loading piston. The stress to yield strain is

predominantly a compressional stress and from yield strain to 40 percent

deformation is a combination of compressive and shear stresses. The defor-

mation of each sample was expressed as the amount of deformation per unit

length of sample times 100 to equal percent deformation. Typical stress-

deformation curves for the cellular concrete are shown in Figure 5.1.

In order to describe the stress-deformation characteristics of each

sample tested in constrained compression, three values of stress are deter-

mined. These values in pounds per square inch are: (a) yield stress a ,

(b) average stress to 40 percent deformation 0.40 , and (c) stress at

40 percent deformation 00.4 0 . The percent of deformation at which the

average stress x0.40 occurs is midway between yield strain and 40 per-

cent deformation. Yield strain can be assumed to be approximately 2 per-

cent when not specifically given.

The values of yield strain Ey , yield stress cy , and stress at

40 percent deformation a0.40 are obtained directly from the output records

from each test. The average compressive stress between yield strain and

40 percent deformation for curves such as those shown in Figure 5.1 can be

calculated by first determining the amount of plastic energy (nonrecover-

able) U absorbed per unit volume of material. The general case for de-p

termining the absorbed plastic energy is:

UE0.40- d (4.1)Ey

where U is equal to the area under the stress-deformation curve betweenp

the yield strain Ey and 40 percent deformation E0.40 . The average

stress T0.40 to 40 percent deformation can then be expressed as:

51

Page 54: REPORT NO. 6-763 - digital.library.unt.edu

U

0.40 E0.40 - y

Various techniques can be used to determine U . The stress-p

deformation records obtained from the constrained loading tests of this

program were integrated by mechanical means.

4.2 MODULUS OF RUPTURE DETERMINATIONS

The flexural strength of concrete as determined from the third-point

loading of simple beams (Test Method CRD-C 16) is characterized by a param-

eter, R , called the modulus of rupture. When the fracture occurred within

the middle third of the span length as it did for all the flexural strength

test beams and horizontal joint beams in the study, the modulus of rupture

was calculated as

R ~ 2 (4-3)BD

where

R = modulus of rupture, psi

P = maximum applied load, pounds

L = span length, inches

B = average width of beam specimen, inches

D = average depth of beam specimen, inches

4.3 ULTRASONIC PULSE VELOCITY DETERMINATIONS

The compressional wave velocity of concrete as determined from the

ultrasonic pulse velocity test (Test Method CRD-C 51) is characterized by a

parameter, V , called the pulse velocity. It is determined simply as

V = (4.4)

52

Page 55: REPORT NO. 6-763 - digital.library.unt.edu

where

V = pulse velocity, ft/sec

L = path length, feet

T = effective time it takes the pulse to pass through the specimen,seconds

4.4 MODULUS OF ELASTICITY AND POISSON'S RATIO DETERMINATIONS

The electrical resistance strain gages provided output for both ver-

tical and circumferential strains. X-Y recorders were used to put the

output in the form of stress-strain curves. By using each test record

separately and the secant technique at 40 percent of the yield strength of

the concrete as shown on the record being used, the modulus of elasticity,

E , was determined. Poisson's ratio was determined at the same point.

4.5 REGRESSION ANALYSIS

Where a sufficient range of freshly mixed densities and characteriza-

tion parameters associated with these densities existed for a particular

cellular concrete water-cement ratio, a relation between the density and

the test parameter was developed. This was done for the characterization

values representing stress, modulus of rupture, ultrasonic pulse velocity,

and secant modulus of elasticity. Inspection and analysis of the data in-

dicated that the line-of-best-fit as determined by least-squares techniques

for the relations developed could be expressed in most cases in the form of

a curvilinear regression of the equation

Y = aXb (4.5)

where

Y = characterization value (a, R, V, or E)

X = freshly mixed density, pcf

a,b = equation coefficients

The graphical presentations of these relations include statistical

53

Page 56: REPORT NO. 6-763 - digital.library.unt.edu

tolerance limits for the data. These limits were established from the

standard error of the estimate, Sesty , where:

n 2(y. - y)2

Se = > (4.6)est,y n - 2

i=land

y. = observed dependent variable

y = predicted dependent variable

n = number of observations

An expression of +2 S established statistical tolerance limits that- est,y

enclosed the range within which approximately 95 percent of all future ob-

servations can be expected to fall.

4.6 DATA DISPERSION

When a number of observations were made of particular test measure-

ments involving specified test variables, the measure of dispersion used

for those observations was the standard deviation of a single observation.

It was calculated as

2 -EX - xxs(x) = n - 1 (-7)

where

s(x) = standard deviation of a single observation

x = observed dependent variable

54

Page 57: REPORT NO. 6-763 - digital.library.unt.edu

CHAPTER 5

TEST RESULTS

5.1 CONSTRAINED COMPRESSION TEST RESULTS

5.1.1 Slow-Loading Test Results. Each test produced a stress-

deformation record similar to those shown in Figure 5.1. The curves in

Figure 5.1 are typical of those obtained over the range of densities at

each water-cement ratio. Using the stress characterization values, a rela-

tion between density and stress for each water-cement ratio was obtained.

These relations are summarized in Table 5.1 and are shown graphically in

Figures B.1 through B.15. Summaries of the curvilinear regressions for

each characterization stress are shown in Figure 5.2.

5.1.2 Rapid-Loading Test Results. The stress-deformation curves were

obtained by combining, on a common time basis, the two traces from each

oscilloscope photograph. In each case, the resulting stress-deformation

curve had the same general shape as the curve obtained from the slow-loading

test of a companion specimen (see Figure 5.1). The characterizing stress

values were different, however, and were used to develop the stress-density

relations shown in Figures B.16 to B.27. These relations are summarized in

Table 5.1 and in Figure 5.3.

5.1.3 Multiple-Shot Loading Test Results. Four cylinders each at

densities of 21 and 45 pcf, and five cylinders each at densities of 29.5

and 40 pcf were evaluated. All the concrete had a water-cement ratio of

0.86. The stress-deformation curves were derived from oscilloscope records

and were combined for each density so as to obtain an average stress-

deformation curve for that density. The average curves for all four den-

sities are shown in Figure 5.4.

5.2 FLEXURAL STRENGTH TEST RESULTS

5.2.1 Modulus of Rupture Test Results. A total of 180 flexure beams

were tested. Concretes with water-cement ratios of 0.76, 0.86, 0.96, and

1.06 were evaluated with the number of beams for each water-cement ratio

being 51, 44, 51, and 34, respectively. The beams for each water-cement

ratio represented 11 batches of concrete with the exception of the

55

Page 58: REPORT NO. 6-763 - digital.library.unt.edu

1.06 water-cement ratio where only 8 batches were made.

The results of the modulus of rupture determinations were related to

the freshly mixed density and are shown in Figures B.28 to B.31. A summary

of the regression analyses for this data is shown in Figure 5.5 and

Table 5.2.

5.2.2 Horizontal Joint Test Results. A summary of the horizontal

joint test results is shown in Table 5.3. In the few instances where data

omissions occur, the samples from those blocks were not suitable for test-

ing. One entire block (for the moist-cured, unprepared surface variables)

did not have any satisfactory samples.

None of the joint beams experienced a failure across the joint. Only

one of the fifty beams tested did not fail in the concrete from the lower

lift.

5.3 ULTRASONIC PULSE VELOCITY TEST RESULTS

A total of 172, 6- by 12-inch cylinders were tested. Concretes with

water-cement ratios of 0.66, 0.76, 0.86, and 0.96 were evaluated with the

number of cylinders for each water-cement ratio being 36, 36, 48, and 52,

respectively. The cylinders for each water-cement ratio represented 12

batches of concrete. In most instances, the ultrasonic pulse velocity was

determined for each cylinder at ages of the concrete of 3, 7, 14, 28, and

60 days. The 0.86 and 0.96 water-cement ratio concrete cylinders were also

evaluated at 90 and 180 days age.

Ultrasonic pulse velocity versus freshly mixed density relations were

developed for each water-cement ratio and concrete age and are summarized

in Figures 5.6 and 5.7. The line-of-best-fit in each case can be repre-

sented by the relation X = aXb . A summary of the regression coefficients

and related statistical information is given in Table 5.4. The effect of

water-cement ratio on the pulse velocity for the range of densities evalu-

ated at 28 days age is shown in Figure 5.8.

5.4 RATE-OF-HARDENING TEST RESULTS

One sample each from concretes with water-cement ratios of 0.76, 0.86,

0.96, and 1.06 and nominal densities of 23, 32, 39, and 43 pcf at each

56

Page 59: REPORT NO. 6-763 - digital.library.unt.edu

water-cement ratio was evaluated. The resulting penetration resistance

versus elapsed time curves (from the time the water in the mixture first

came in contact with the cement) for each sample are shown in Figures 5.9

and 5.10. The median value of the freshly mixed density for the four

batches representing each nominal density is also indicated along with the

variation in density that occurred.

5.5 MODULUS OF ELASTICITY AND POISSON'S RATIO TEST RESULTS

Modulus of elasticity and Poisson's ratio determinations were made for

concrete with nominal densities of 23, 32, 39, and 43 pcf each at water-

cement ratios of 0.66, 0.76, 0.86, and 0.96. One batch of concrete at each

density and water-cement ratio provided the specimens for those variables.

A summary of the data is shown in Table 5.5. The modulus was determined

using the secant technique at 40 percent of the yield strength of the con-

crete cylinder being tested. Poisson's ratio was determined at the same

point.

Relations between the freshly mixed density at 28 days age and the

secant modulus at the same age are shown for each water-cement ratio in

Figures B.32 to B.35 and are summarized in Figure 5.11 and Table 5.6. The

line-of-best-fit for the limited amount of data available was in the form

Y = aXb in each case.

5.6 TEMPERATURE STUDY RESULTS

5.6.1 Adiabatic Temperature-Rise Results. Three batches of concrete

were used to fill the adiabatic container. The concrete had an average

freshly mixed density of 43.9 pcf and a cement content of 6.78 bags/cu yd.

The temperatures of the mixture ingredients and resulting concrete at time

of placement are shown in Table 5.7.

The adiabatic temperature development curve for the concrete is shown

in Figure 5.12. Testing was terminated at 213 F because of the possibility

of equipment damage due to the increasing water vapor pressure in the

concrete.

5.6.2 Mixture Water-Temperature Results. The initial temperatures of

the mixture ingredients and the temperature of the concrete when placed are

57

Page 60: REPORT NO. 6-763 - digital.library.unt.edu

shown in Table 5.7. The temperature development curves for concretes made

with mixing water temperatures of 40, 60, 80, and 100 F for both Type I

(RC-554) and Type III (RC-560) cement are shown in Figure 5.13.

5.6.3 Lift Heat Effects Results. The concrete, made with both Type I

(RC-554) and Type III (RC-560) cement, had a water-cement ratio of 0.86

with average (for both lifts) freshly mixed densities of 36.8 and 35.2 pcf,

respectively, and cement contents of 4.75 and 4.95 bags/cu yd, respectively.

The heat development curves for both lifts of both mixtures are shown in

Figure 5.14 in the form of a temperature increase from the initial placing

temperature versus elapsed time from initial placing of each lift. Peak

temperatures of 170 and 182 F occurred in the bottom of the second lifts

for the Type I and Type III mixtures, respectively.

5.6.4 Ambient Air Temperature Effects. The concrete was made at nom-

inal densities of 23, 32, 39, and 43 pcf, all with a water-cement ratio of

0.86 by weight. The measure of damage due to the increased curing tempera-

ture was by visual inspection and resulted in only qualitative comparisons.

These comparisons can be made from the photographs in Figures 5.15 and 5.16.

5.7 LIFT HEIGHT RESULTS

Figure 5.17 shows the hardened densities for both lift heights as func-

tions of the depth of concrete in the lift. In the as-cast condition, the

density appeared to vary approximately 7 pcf in a 16 -foot lift and approxi-

mately 20 pcf in a 30-foot lift. The first 16 feet of the 30-foot lift

showed a density change of approximately 12 pcf. The amount of evaporable

water in the 16-foot lift appeared to be a fairly uniform amount over the

entire lift height, varying from approximately 11 pcf near the top of the

lift to 13 pcf at the bottom.

5.8 MOISTURE STUDY RESULTS

5.8.1 Saturation Results. The saturation data for the five cylinders

evaluated were averaged and are presented in Figure 5.18 as the relation

between available void space filled and water pressure. No measurable

amounts of water, as dictated by the degree of sophistication of the

58

Page 61: REPORT NO. 6-763 - digital.library.unt.edu

pycnometer, could be forced into the specimens after a water pressure of

1,200 psi was reached.

5.8.2 Flow and Erosion Test Results. Two specimens each of concrete

with water-cement ratios of 0.76, 0.86, and 0.96 and nominal freshly mixed

densities of 23, 32, and 43 pcf, respectively, were tested. All specimens

were bag-cured 28 days before testing.

The waterhead was determined at any given time by the varying losses

in the system. The densities of 23, 32, and 43 pcf had average heads of

5.10, 6.09, and 6.61 feet, respectively, over the test time period and

range of water-cement ratios used.

The results of the flow portion of the tests are shown in Figures 5.19

and 5.20 for the 23- and 32-pcf concrete, respectively. The total flow

time was approximately 50 hours for the 23-pcf concrete and 80 hours for

the 32-pcf concrete. No flow was observed for the 43-pcf concrete.

The results of the erosion portion of the test are shown in Figures

5.21 and 5.22 for the 23- and 32-pcf concrete, respectively. The average

total solids in the tap water prior to its passing through each specimen

was 333 ppm. This determination and the other total solids measurements

were made by evaporating the water samples at 194 F and drying the residue

at 210 F.

5.8.3 Surface Sealer Test Results. The results of the sealer study

are shown in Figure 5.23 in the form of a waterhead-time relation. The

sealers showing little reduction in head with time can be considered as

being more effective than those that show a rapid head loss with time.

The reference numbers in Figure 5.23 correspond to the following sealer

types: (1) no sealer, (2) styrene-butadiene product, (3) two-component

epoxy thinned with a volatile solvent, (4) paraffin-resin mixture,

(5)' liquid latex, (6) vinyl based liquid-type solvent, (7) asphalt, (8) la-

tex wall paint, (9) neat Type III cement slurry, and (10) hydraulic cement

slurry.

59

Page 62: REPORT NO. 6-763 - digital.library.unt.edu

TABLE 5.1 SUMMARY OF CONSTRAINED STRESS VERSUS FRESIfLY MIXED DENSITY, CORRELATION REGRESSION COEFFICIENTS. o = a(d)b +2 St,y

Water- Freshly No. of Yield Stress, o Average Stress to 40% Deformation, Stress at 40% Deformation,Cement Mixed Samples y_00.400.40

Ratio Density a b S Correla-Range est,y tion a b S Correla- a b S Correla-

Coeffi- est,y ion est,y tioncient Coeffi- Coeffi-

cient cient

pcf

Slow-Loading Tests:

0.66

0.76

0.86

0.960

1.06

20 to 47

22 to 43

23 to 46

18 to 44

23 to 45

143

98

109

64

111

23.25 x 10-5

32.76 x 10-5

22.32 x 10-4

30.79 x 10-4

13.75 X 104

3.875

3.713

3.095

2.960

2.625

50.2

39.3

25.5

20.5

21.0

0.952

0.963

0.944

0.949

0.943

10.82 x 105

22.16 x 10-

14.06 x 10-4

38.12 x 10~4

64.61 x 10_

4.141

3.873

3.268

2.927

2.756

53.7

37.0

18.0

18.3

19.6

0.964

0.978

0.972

0.980

0.975

49.33 x 10-6

11.81 x l0-5

48.55 x 10~5

22.99 x 10-4

23.18 x 10-

4.407

4.086

3.605

3.110

3.080

69.6

h5.8

28.9

27.9

28.3

0.964

0.974

0.970

0.969

0.961

Rapid-Loading Tests:

0.76

0.86

0.96

1.06

23 to 43

23 to 46

18 to 43

23 to 46

47

68

46

83

17.99 x 10-4

20.56 x l0o-3

28.73 x 10- 3

31.28 x 10-3

3.391

2.643

2.550

2.467

48.0

52.4

24.3

42.3

0.975

0.963

0.988

0.935

13.41 x 10-4

15.62 x 10-3

25.81 x 10-3

24.71 x 10-3

3.478

2.715

2.558

2.528

47.6

55.1

18.8

33.0

0.981

0.964

0.994

0.965

37.97 x 10-5

53.46 x 10-4

14.73 x 10-3

16.65 x 10-3

3.851

3.039

2.726

2.657

59.4

63.8

27.9

52.9

0.980

0.973

0.987

0.951

Page 63: REPORT NO. 6-763 - digital.library.unt.edu

TABLE 5.2 SUMMARYRELATION

OF MODULUS OF RUPTURE VERSUS FRESHLY MIXED DENSITY,REGRESSION COEFFICIENTS, R = a(d)b +2 S , psi

- est,y

Water- Freshly No. of Regression Standard CorrelationCement Mixed Samples Coefficients Error of CoefficientRatio Density a b the Estimate

Range Sesty

pcf

0.76 23 to 42.8

0.86 23 to 43

0.96 22 to 43

1.06 23 to 42

51 2.740 x 10 -3 2.665

44 6.983 x 10-4 2.970

51 6.569 x 10-4 2.962

34 7.022 X 10 4 2.930

COR-

5.2

4.7

2.9

0.953

0.971

0.969

0.979

Page 64: REPORT NO. 6-763 - digital.library.unt.edu

TABLE 5.3 SUMMARY OF HORIZONTAL JOINT TEST RESULTS

Block Surface Joint Lift Cube Test Results Beam Test ResultsNo. Curing Surface Location

No. of Oven-Dry Cube Control Beams Joint Beams Failure LocationsCubes Density Strength

Modulus of No. of Modulus of s(x Bottom Across Top

Mean s(x' :Mean s(x) Rupture Beams Rupture Lift Joint Lift

pcf pcf psi psi psi psi psi

7 Air Unprepared BottomTop

8 BottomTop

9 BottomTop

14 BottomTop

2 Air Prepared BottomTop

4 BottomTop

5 BottomTop

8 BottomTop

11 Moist Unprepared BottomTop

17 BottomTop

19 BottomTop

1 Moist Prepared BottomTop

3 BottomTop

6 BottomTop

15 BottomTop

21.721.4

21.220.9

21.722.4

20.721.4

20.221.1

20.821.2

21.021.9

20.721.5

21.221.9

21.621.6

21.621.5

20.521.0

21.221.1

21.522.9

21.321.6

0.6

0.34C.260.29C. 54

0.27

0.53

0.570.22

0.540.h2

0.130.49

0.390.80

0.110.111.20

0.35

0.55

0.39

0.200.17

0.370.33

0.270.62

0.370.70

62.170.9

64.463.9

57.471.0

51.067.7

49.577.6

58.687.8

54.268.6

46.873.8

60.074.2

57.067.2

65.865.4

50.492.6

7.973.594.90h.1O

7.8710.43

5.2710.91

2.7013.22

3.9521.80

3.226.27

6.2014.53

4.5913.81

15.804.31

7.01

5.964.936.38

55.0 6.4470.4 4.87

58.679.8

51.565.3

3.5012.55

3.756.93

16.121.2

20.6

18.220.5

16.016.7

18.821.2

16.8

18.221.2

16.416.1

21.9

20.9

18.318.5

22.322.9

17.019.4

18.518.5

17.20.615.718.9

2 10.8 1.48 2 0 0

2 9.6 2.19 2 1 0

2 13.8 3.32 1. 0 1

6 13.2 1.36 6 0

3 13.6 2.37 3 0

0

3 13.3 1.62 3 0 0

2 10.0 0.92 2 0 0

6 11.5 2.20 6 0 0

1 12.0 -- 0 0

6 13.5 4.13 6 0 0

4 16.6 1.74 6 0 0

3 12.8 0.46 3 0 0

2 15.3 3.54 2 0 0

2 20.0 6.01 2 0 0

6 13.1 1.07 6 0 0

R)

Page 65: REPORT NO. 6-763 - digital.library.unt.edu

TABLE 5.4 SUMMARY OF ULTRASONIC PULSE VELOCITY VERSUS FRESHLY MIXED DENSITY, CORRELATION REGRESSION COEFFICIENTS, V = ad +2 Sest- s,y

Age w/c = 0.66 w/c = 0.76 w/c = 0.86 w/c = 0.96

No. of a b Standard Corre- No. of a b Standard Corre- No. of a b Standard Corre- No. of a b Standard Corre-Obser- Error of lation Obser- Error of lation Obser- Error of lation Obser- Error of lation

vations Estimate Coef- vations Estimate Coef- vations Estimate Coef- vations Estimate Coef-

Sest,y ficient Sest,y ficient Sest,y ficient Sest,y ficient

days ft/sec ft/sec ft/sec ft/sec

3 36 154.45 0.897 146

7 36 189.22 0.875 203

14 36 187.73 0.896 193

28 36 215.16 0.870 194

60 36 22

90 --

180 --

0.985 36 368.75 0.621 129

0.977 36 344.37 0.680 118

0.982 36 332.18 0.716 144

0.982 36 374.23 0.696 119

0.972 48 274.71 0.647 191

0.983 48 297.17 0.660 232

0.984 48 258.41 0.744 181

o.988 48 308.36 0.722 235

5.59 0.863 211 0.979 36 428.81 0.668 133 0.986 48 334.10 0.724 249

-- -- -- -- -- -- -- -- -- 48 312.58 0.747 281

-- -- -- -- -- -- -- -- -- 34 356.82 0.714 244

0.915 36 685.45 0.345 64

0.909 36 562.92 0.476 82

0.962 52 506.26 0.543 75

0.948 52 495.49 0.575 86

0.951 52 499.98 0.586 85

0.944 52 542.45 0.564 114

0.959 52 570.58 0.549 105

uJ\

0.934

0.973

0.984

0.985

0.986

0.973

0.977

Page 66: REPORT NO. 6-763 - digital.library.unt.edu

TABLE 5.5 SUMMARY OF MODULUS OF ELASTICITY AND POISSON'S RATIO DATA

Water- Freshly No. of Yield Yield Strain, E Poisson's Secant Modulus

Cement Mixed Tests Stress, cry_ Ratiob of Elasticity

Ratio Density yea

Mean s(x)a s(x) Mean s(x) Mean s(x)

pcf

o.66

0.76

4-z

0.86

0.96

22.832.238.443.2

23.631.839.043.8

23.632.0

39.443.0

23.231.639.243.0

4555

4553

5555

5545

psi psi

19

78213257

3474

166213

22

57106160

2129

5655

1.07.4

25.454.7

1.59.1

13.925.8

0.76.5

18.117.0

1.52.9

11.42.7

in/in

1,322

1,3341,8261,508

1,3551,4281,5481,46o

1,0601,0001,1821,404

1,032544650562

in/in

88207282362

11525682

227

4241

246235

334313323

psi

0.1980.2190.2050.195

0.2270.2500.2050.193

0.2520.2010.2270.226

0.2340.1920.2370.214

0.0230.0140.0250.018

0.0150.0130.0290.009

0.0390.0250.0230.017

0.0120.0410.034o.o16

psi

17,37069,770140,930188,190

33,70063,930

121,950167,680

26,85072,620

110,030145,980

22,720

59,85092,440

105,370

2, 3203,65020,4909,890

7201,000

13,9605,070

8606,7405,6402,780

8608,7709,6002,000

a s(x) = standard deviation of a single observation.

b Calculated at 0.4 o .

Page 67: REPORT NO. 6-763 - digital.library.unt.edu

TABLE 5.6 SECANT MODULUS OF ELASTICITY VERSUS HARDENED DENSITY RELATION,E = a(d)b +2 S

s - est,y

All concrete made with Foaming Agent M and evaluatedmoisture condition.

at the as-cast

Water- No. of Density a b S CorrelationCement Specimens Range esty CoefficientRatio

pcf

0.66 19 22.8 to 43.2 0.00023 3.637 14.15 0.9930.76 17 23.6 to 43.8 0.00797 2.623 9.90 0.9900.86 20 23.6 to 43.0 0.00449 2.765 6.70 0.9920.96 19 23.2 to 43.0 0.00914 2.507 6.10 0.983

TABLE 5.7 SUMMARY OF TEMPERATURE-RISE STUDY BAT CHING DATA

Cement Round Water- Freshly Initial Temperature, FNo. Cement Mixed

Ratio Density Water Cement Slurry Concrete

pcf

Type I 1 0.86 35.6 40 65 50 58(RC-566) 2 o.86 35.2 60 65 64 67

3 0.86 35.0 80 65 82 804 0.86 33.6 100 65 94 92

Type III 1 0.86 37.6 40 65 45 58(RC-567) 2 0.86 36.8 60 65 65 69

3 0.86 35.6 80 65 81 824 0.86 36.4 100 65 95 92

Adiabatic Test:

Type III Avg of 0.86 43.9 42 60 50 52(RC-567) three

batches

65

Page 68: REPORT NO. 6-763 - digital.library.unt.edu

DENSITY=23.0 PCFW/C=0.88

DENSITY=38.5 PCFW/C=0.86

20 40 60 0

DEFORMATION, PCT

DENSITY=3I.9 PCFW/C=0.86

DENSITY=43.0 PCFW/C=0.86

20 40

Figure 5.1 Typical stress-deformation curves.

66

400

200

0

U)a-

,U)

400

200

00 60

I I I I

Page 69: REPORT NO. 6-763 - digital.library.unt.edu

800

600

'GAO

400(ORP06

0"2 00

16 22 26 30 34 38 42 46

c. YIELD STRESS

800

600 ,

400 10-

0g

200

18 22 26 30 34 38 42 46

b. AVERAGE STRESS800 __________

a-

zO 600

ac

0w* 400f-)

200

U

08 22 26 30 34 38 42 46

FRESHLY MIXED DENSITY, PCF

c. 40PCT DEFORMATION

Figure 5.2 Summary of stress versus freshlymixed density relations, slow-loading tests,28-day strength.

67

/

P 0"

SIo

0 "

6.6bog6

a

_ q

i

5

Page 70: REPORT NO. 6-763 - digital.library.unt.edu

U)

CL

U)

J

U)0.

z0

4

0LL.

0

F-)

a.

0

U)0.

NWQ-

4

0

U)

a.

U)

600

400

200

OL18

033'

22 26 30 34 38 42 46FRESHLY MIXED DENSITY, PCF

c. 40 PCT DEFORMATION

Figure 5.3 Summary of stress versus freshly mixed den-sity relations for rapid-loading tests, 28-day strength.

68

800

600 ----

200 -

6l 22 26 30 34 38 42 46

ca. YIELD STRESS00 ____

600

4 00

00

2006

8 22 26 30 34 38 42 46

b. AVERAGE STRESS800r

-7

1b _

i i i

i

5

0" 6 .,

0.0

I

Page 71: REPORT NO. 6-763 - digital.library.unt.edu

750_

SHOT I SHOT 2

6000 h/

WATER-CEMENT RATIO= 0.86 (BY WEIGHT)

300 -- - ' ...

I0 20

III' II

c

\ +

30 40

DEFORMATION, PCT

50 60

Figure 5.4 Stress-deformation relations for multiple-shot loading.

22 26 30 34

FRESHLY MIXED DENSITY, PCF

38 42

o.--

0

Figure 5.5 Summary of the modulus of rupture versus

freshly mixed density relations.

69

U)0.

U)wI-,)

, ~II .

150

00 70 80

80

jtj 60CL

I-

00U.

J

00 _

28-DAY STRENGTH

+ E

06.

~- 6- -6

-K--

18 46

I -r -- -

i i i i P -+

1 21

Page 72: REPORT NO. 6-763 - digital.library.unt.edu

6000 28DAY

600060DAY

I4DAY

5000

47DAY

4000 3A

3000

200022 26 30 34 38 42

a. WATER-CEMENT RATIO 0.667000

0

0

22_0 1_ _ _ _ _ _

28 30 34 38

FRESHLY MIXED DENSITY, PCF

b. WATER-CEMENT RATIO 0.76

42

46

46

Figure 5.6 Summary of ultrasonic pulse velocity versus freshlymixed density relations for water-cement ratios 0.66 and 0.76.

70

7000

uw

U-

F-)

0LJ

w

J

u

z0U)

__ +_ i i i +--------

uw 600'

LA-

I-uo 500'w

wN,J

a 400

z0

S300'

20

2SDAY60O >

0t/4DAY

SDAY

0)

j DAY

i E + I

r

Page 73: REPORT NO. 6-763 - digital.library.unt.edu

6U00

uw

F-

F-

0Jw

J

B.

0U

J

26 30134 326 30 34 38

FRESHLY MIXED DENSITY, PCF

b. WATER-CEMENT RATIO 0.96

42 46

Figure 5.7 Summary of ultrasonic pulse velocity versus freshlymixed density relations for water-cement ratios 0.86 and 0.96.

71

90 DAY/IODAY

5000

4000

3000

2000

1000

6000

5000

4000

3000

2000

uw

Fi-

0Jw

J

z0U

I-J

60 DA Y

3 AY

22 26 30 34 38 42 46

a. WATER-CEMENT RATIO 0.86

60,90, AND 80 D AY

28 DAY

3 DA Y

-

I00022

J

Page 74: REPORT NO. 6-763 - digital.library.unt.edu

6000

sooo -0

4000

3000

18 22 28 30 34FRESHLY MIXED DENSITY, PCF

38 42

Figure 5.8 Summary of ultrasonic pulse velocity versus freshly mixeddensity relations showing effect of water-cement ratio, 28 days age.

72

UwNF-L

0Jw

w

U

z0N'

F-J

46

Page 75: REPORT NO. 6-763 - digital.library.unt.edu

60

Figure 5.9 Penetration resistance versus time relations for

23- and 32-pcf nominal density concretes.

73

80

WATER -CEMENT

RA T/0

-- /.06

10 20 30 40 50 80 70 80 90

a. FRESHLY MIXED DENSITY = 22.5 0.5 PCF

0.6

0 10 20 30 40 50 60 70 80 9ELAPSED TIME, HOURS

b. FRESHLY MIXED DENSITY = 32.4 0.4 PCF

U)

40

201

200

150

U,a~

U,U,

I-U)

00l

50

0

0

0

Page 76: REPORT NO. 6-763 - digital.library.unt.edu

2 00

150 "Ti O -

Soc

0 10 20 30 40 50 60 70 809

Q. FRESHLY MIXED DENSITY = 39.3 0.3 PCF00

300

200-

0

C

__________

0 10 20 30 40 50ELAPSED TIME, HOURS

b. FRESHLY MIXED DENSITY = 43 PCF

Figure 5.10 Penetration resistance versus time relation for39- and 43-pcf nominal density concretes.

74

60 70 80 90

0

Page 77: REPORT NO. 6-763 - digital.library.unt.edu

?U0 r

DATA USED FOR EACH WATER CONTENTRATIO REPRESENT THE SECANT MODULUSFROM THE ORIGIN TO 0.4fc 0 \ /

60.

/

022 26 38 42 46

Figure 5.11 Summary of secant modulus of elasticityversus freshly mixed density relations.

2O

f10..

170

130TYPE I CEMENT

CEMENT CONTENT = 6.65 BAGS/CU YDWATER-CEMENT RATIO= 0.86 (BY WEIGHT)

FRESHLY MIXED DENSITY = 43 PCF

90

5o0_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

10 20 30 40ELAPSED TIME, HR

50 60 70

Figure 5.12 Adiabatic temperature development curve.

75

0

x< 150

I-U

100JW

0N,

D

0

18 30 34FRESHLY MIXED DENSITY, PCF

k

TEST TERM/NA TED-,

213 F

LL.0

w

wa-

0

P -

i'

i

,in

w

Page 78: REPORT NO. 6-763 - digital.library.unt.edu

170

/00 F 80F130

60 F40 F M/X WATERTEMPERA TURE

90

50

a. TYPE I CEMENT

170

13 0 ~/0 0F..--

130

80 F

40 F MIX WATERTEMPERA TURE

90

5000 2 4 6 8 10 12 14 I

ELAPSED TIME, HOURS

b. TYPE MI CEMENT

Figure 5.13 Effect of mixture water temperature onearly-age heat.

76

w

w

w

6

Page 79: REPORT NO. 6-763 - digital.library.unt.edu

I

0 E3 12ELAPSED TIME, HR

b. TYPE IE CEMENT

Figure 5.14 Effect of hydration heat on adjoininglifts of concrete .

77

BOT TOM- L /FT / BOTTOM- L /FT 2

80 MIDDLE - MIDDLE- L /F-_ 2LIFT /

/

STOP - L/FT / TOP -L/FT 2

40

0Co 4 8 12 16 2(

a. TYPE I CEMENT

20

BOTTOM-LFr2MIDDLE-L/FT /

80 rO FMIDDLE- LIFr2BOrroM-L/FT i

OP-L/T/ TOP - L/F2

4 0-

02

w

Ix

uzW

4rFe-l0W

a2-

1 yn

I

0

to8 0V4

Page 80: REPORT NO. 6-763 - digital.library.unt.edu

a. Top view.

Figure 5.15

y:

b. Side view.

Effect of 100 F air-curing temperature.

78

6

Page 81: REPORT NO. 6-763 - digital.library.unt.edu

a. Top view.

b. Side view.

Figure 5.16 Effect of 120 F air-curing temperature

79

.A

F

1

'

> VF

yy

F

r ;

Page 82: REPORT NO. 6-763 - digital.library.unt.edu

AS-CAST,30-FT LIFT

42

"

AS-CAST, /6-Fr LIFT34

28

OVEN DRY-16-Fr LIFT

18

10noc

DEPTH FROM16

TO P24

OF LIFT, FT

Figure 5.17 Effect of lift height on concrete density.

120

Ua Ioo

-J-J

w 10 - -- - - - - a

9/000 80

w WATER-CEMENT RATIO= 0.86

-J BAG-CURED DENSITY = 51 PCF

>60I4

600 800WATER PRESSURE, PSI

Figure 5.18 Saturation curve for a cellular concrete.

80

U.

CL}

H

zw

w

LuJzw0

32

0 200 400 1000 1200 1400

n13

An' i I I I i

0, .:

Page 83: REPORT NO. 6-763 - digital.library.unt.edu

0

WATER-CEMENT RATIO=0.76

0O00- o-

20

10 -

WATER - CEMENT RATIO= 0.86

20

WATER - CEMENT RATIO =0.96

J80 ----

Z80

00

4I 0 - - -- - - ---- --- - --- - - -

O

41 11-

Figure 5.19

10 100 1000TOTAL FLOW TIME, HOURS

Flow data for 23-pcf concrete.

81

Page 84: REPORT NO. 6-763 - digital.library.unt.edu

0

WATER-CEMENT RATIO =0.76

-- [11----O 000 01~ CD

80

WATER -CEMENT RATIO= 0.86

4C - Q0__

0

20 - -- -

800

WATER -CEMENT RATIO = 0.96

4 10 100 100TOTAL FLOW TIME, HOURS

Figure 5.20 Flow data for 32-pcf concrete.

82

0J

J

Q

F-

U

0w

0

Page 85: REPORT NO. 6-763 - digital.library.unt.edu

10 20 30 40 50

TOTAL FLOW TIME, HOURS

Figure 5.21 Erosion data for 23-pcf concrete.

83

600

500

400

C')

0U)

-J

I-0

WATER-CEMENTRATIO

o 0.760 0.86A 0.96

00 -

'TAPWATER BASE =333 PPM

300-

2000 60

Page 86: REPORT NO. 6-763 - digital.library.unt.edu

1800

1600

1400

1200

WATER- CEMENTRAT/O = 0.86

a

rn O000

J

H

WA TER - CE ME NT

RAT/O =0.76

800

WATER- CEMENTRAT/0 =0.96 A

400

TAPWATER = 333 PPM

2000 20 40 60

TOTAL FLOW TIME, HOURS80

Figure 5.22 Erosion data for 32-pcf concrete.

84

Page 87: REPORT NO. 6-763 - digital.library.unt.edu

1200 1600

ELAPSED TIME, SECONDS

2000

Figure 5.23 Sealer effectiveness test results.

7

31wd

w

coD

I

2I

400 800 2400

Do .5

0 " 0

-- "

O "7

O " 0

9

2,3,4

0

O

l',.

Page 88: REPORT NO. 6-763 - digital.library.unt.edu

CHAPTER 6

DISCUSSION OF TEST RESULTS

6.1 CONSTRAINED STRENGTH-DEFORMATION CHARACTERISTICS

6.1.1 Slow-Loading Results. As shown in the typical constrained

stress versus deformation curves in Figure 5.1, the cellular concretes

studied have a curve shape approximating that considered to be better for

an efficient backpacking material (Reference 2). In most cases, the slopes

of the initial (elastic) portion and the crushing (plastic) portion of the

curves increase with increasing densities. Locking of the curves generally

did not begin to occur until after 40 percent deformation was reached; but

in a few instances involving the higher density, higher strength concretes,

the locking regime may have begun between 35 and 40 percent deformation.

The start of the locking, in these cases, was not as distinct as that ob-

served for lower densities.

Cellular concrete is limited as far as strength is concerned by the

inherent strength of its constituents and by the formulations necessary to

produce the desirable characteristics of a backpacking. Neat cellular con-

crete is basically a hardened cement paste with a large void content. For

the purposes of this study, porosity, n , will be defined as the volume of

these voids divided by the total volume of the concrete where the voids

consist of the pores in the cement paste (both gel pores and capillary

pores) plus the entrained and entrapped air voids.

Numerous investigators have related the strength of hardened cement

paste to porosity either directly or indirectly. As shown in Reference 6

it was found that:

VS = 120,000 m - 3,600 (6.1)

0

where S is strength of the hardened paste and Vm is the constant in the

BET surface area equation. Vm is proportional to the surface area of the

cement gel, which in turn is proportional to the amount of cement gel.

W0 is the original water content after bleeding. It was later suggested

in References 7 and 8 that the strength of the hardened paste could be

86

Page 89: REPORT NO. 6-763 - digital.library.unt.edu

empirically related to a volume of gel/space ratio by a power function

where:

S = S (x)b (6.2)

where X = gel/space ratio and could include the effects of entrained and

entrapped air (Reference 8) and b varied somewhat but was approximately

equal to three.

As shown in Reference 9, it was found from experimental evidence that:

s = so(1 - Vp)2 .7 (6.3)

where Vp is the porosity. Based on a simple geometric model, it was sug-

gested in Reference 10 that:

S = s 1 - 1.2V2) (6.4)

It was suggested in Reference 11 that the data for strength as given

in Reference 6 be plotted against (W - W ) = W , i.e., the original watero n e

content less the nonevaporable water content, where W is more closely

related to porosity than Vm/Wo . As shown in Reference 11, it was then

found that:

s3= (1 - We)6 (6.5)

and it was further speculated that the strength of hardened cement paste

could be approximated as:

S = s(1 - vP) 6 (6.6)

In all of the above cases, it is readily obvious that a decrease in

porosity will reflect an increase in the strength of the paste.

For backpacking design purposes, a suggested approach is to relate

the desired strength to the porosity of the cellular concrete which, in

87

Page 90: REPORT NO. 6-763 - digital.library.unt.edu

turn, is a function of the water-cement ratio, concrete density, and spe-

cific gravity of the cement. This provides some latitude in the selection

of a cellular concrete design for a particular requirement.

Using the notation of Section 2.2, the volume of water in the concrete

will be considered as being composed of both evaporable and nonevaporable

water (Reference 12), that is:

Vw =Vew +Vnw (6.7)

where

VeW = volume of evaporable water

Vnw = volume of nonevaporable water

The space left in the concrete after the evaporable water leaves is con-

sidered as void space. The theoretical porosity, n , for a neat cellular

concrete, as defined above, is then:

Vn = Vt (6.8a)

V +Va ew (.b=V +V +V (6.8b)

c w a

V

V +V +V (6.8c)c nw v

The density expression:

w W +Wd_=t _= c w 69

c t V + V + V (.

t c w a

can be rewritten in terms of water-cement ratio and specific gravities to

be:

(1 + k)W

c Vc +V +Vv(6.10a)c nw v

88

Page 91: REPORT NO. 6-763 - digital.library.unt.edu

(1 + k)V p 7

V +V +VC nw v

where

pc = specific gravity of the cement

w unit weight of water

The volume of voids is then expressed as:

Vv = ac[1 + k)VCpC7W - d(VC + Vnw)

(6. lob)

(6.11)

Using an average value of 0.20 for the ratio of hydration water to cement

by weight (Reference 12)

nw = 0.20

c

(7 )V

pcyw cor

V =0.20 pcVc

nw c c

Equation 6.11 can then be written as

V =dv -de C

VcdC

(6.12)

(6.13)

(1 + k)VcpcyW - dc(Vc + 0.20 pcVc)]

(1 + k)pcYw - dc(1 + 0.20p )] (6.14)

Substituting in Equation 6.8a,

[(1 + k)pcyw - dc(l + 0.20p)]

(wt/d)

(1 + k)pC7w - dc(1 + 0.20p)]

(1 + k)Wc

+(1+k)pcyw - dc(1 + 0.20pc

V(l + k)pc7

89

Vcn = -

c

c

c

Page 92: REPORT NO. 6-763 - digital.library.unt.edu

d (1 +0.20pc

n= 1 - dc( + O2p) (6.15)(1 +kp7

c w

Equation 6.15 is the expression for the theoretical porosity of the cellu-

lar concrete in terms of density, water-cement ratio of the freshly mixed

concrete, specific gravity of the cement, and the unit weight of water. It

has been assumed in this development that the specific gravity of water is

unity.

Using the values of specific gravity for the Type III cement of this

study and a unit weight of water of 62.3 pcf, Equation 6.15 can be ex-

pressed as

0.00834d(1-n) = 1+kc (6.16)

In relating the constrained strength of the cellular concrete, as

measured in this study, to porosity, only the yield stress should be con-

sidered as it is basically a compressive stress whereas past the yield

point the stresses are more complex, being functions of both compressive

action and punching shear. These complex stresses may not relate directly

to porosity. Backpackings are usually designed for an average crushing

stress, that is, the average stress value of the crushing plateau of the

stress-deformation curve. To relate porosity to this design value, the re-

lation between y and ~0.40 must be known. The stress-density rela-

tions of Table 5.1 suggest that for a common density, the two stress values

are related in a power function form of

a(.40 (y)B (6.17)

where B = bo.40/by . In analyzing the relation between ay and Q0.40in the form 0040 = a(ay)b for each water-cement ratio, correlation co-

efficients between 0.96 and 0.99 were obtained. Comparing the regressions

obtained in each instance, it was found that statistically they were not

significantly different, thus indicating an independence from the influ-

ence of water-cement ratio. By being independent, all the data were then

90

Page 93: REPORT NO. 6-763 - digital.library.unt.edu

combined and analyzed with the resulting relation of

-1.008 +7 sa0.4 0 = 1.109(ay) + 76 psi (6.18)

at the 95 percent statistical tolerance limits. The correlation coeffi-

cient was 0.971. For the sake of simplicity, Equation 6.18 can be approxi-

mated as

0.4 0 =1 y175a (6.19)

The data for the 525 constrained slow-loading tests are shown in Fig-

ure 6.1 in the form of a yield stress versus theoretical porosity plot. A

separate least-squares regression analysis of the data for each of the water-

cement ratios indicated that the line-of-best-fit in each instance was in

the form

a = a (1 - n)b (6.20)y

where the coefficients a and b varied somewhat between each water-

cement ratio. Statistically, however, the lines-of-best-fit were not sig-

nificantly different from each other. Correlation coefficients varied be-

tween 0.94 and 0.98. The relation for all the data together can be approx-

imated by the expression

y = 42,000(1 - n) 3 (6.21)

where the 95 percent statistical tolerance limits are at +81 psi and the

correlation coefficient is 0.94.

Combining Equations 6.15 and 6.17, the yield stress can be expressed

as a function of the two principal variables, i.e., water-cement ratio and

freshly mixed density, plus the specific gravity of the cement, where

d (1 + 0.20p c) b

a =a d +0p) (6.22)y [ (1 + k)P7Jw

91

Page 94: REPORT NO. 6-763 - digital.library.unt.edu

1+020 bdo 1 + O.20pcb

a = (6.23)y r o 1+ k pc(623

From Equations 6.16 and 6.18

a = 0.02436(l+ck) (6.24)

Equation 6.24 is shown graphically in Figure 6.2. The relations between

do/(l + k) and the freshly mixed density, d , are shown in Figure 6.3.

Using these two figures together, along with Equation 6.19, a starting

point in the design of a neat cellular concrete for particular backpacking

requirements of density and strength can be obtained.

The curve in Figure 6.1 represents the results from a particular ce-

ment. Other cements may produce slightly different results. A possible

approach to a more universal design curve for all cements is to put Equa-

tion 6.23 in the form

Q d b1 + 0.20pc

(6.25)a 1+ kp7

Reasonable limits of specific gravity for portland cements are from 3.1 to

3.2. The last term in Equation 6.25 varies then between (0.008388)b and

(0.008226)b , respectively. Assuming the value of b to be of the same

order and magnitude as indicated in Equation 6.24, the specific gravity

term can be assumed to be fairly constant for the practical range of spe-

cific gravities, and hence

a d b

-c~(1>~ (6.26)Q + k

The value of the coefficient b for a wide range of cement brands and

types should be determined by test. The data from the Type III cement of

this study indicate that the value is approximately three. As a third

power function for a range of specific gravities, Equation 6.25 is shown

92

Page 95: REPORT NO. 6-763 - digital.library.unt.edu

in Figure 6.4. This curve, together with Figure 6.3, may provide a design

technique applicable to most portland cements.

The range of densities and water-cement ratios used in this study is

not necessarily the limits of design that can be used to satisfy backpack-

ing requirements. From practical considerations, however, the lower limit

of density is approximately 18 pcf. It is also doubtful that water-cement

ratios below 0.55 could be used without creating fabrication problems. The

upper limits of density with respect to backpacking use are not so well de-

fined. Densities of 60 pcf have been used (Reference 3) with very good

success. Water-cement ratios above 1.0 (by weight) begin to create fabri-

cation problems because of the excess of free water, which tends to destroy

the stability of the preformed foam.

6.1.2 Rapid Loading. The results of a rapid-loading test often pro-

vide only qualitative results. Different loading systems, techniques, and

rates will provide different test results for the same material. The

rapid-loading test does provide twofold information, however. First, it

does show if the material is strain and/or load rate sensitive; second, it

gives some indication of the magnitude of load resistance that might be ex-

pected. This is evident from the results shown in Figure A.8, Table 5.1,

and Appendix C. The rapid-loading tests, as described in Section 3.1.2,

might produce the response of cellular concrete at some reasonable distance

from the origin of the shock wave producing the loading, while the results

of Appendix C may pertain to very close-in loadings.

By comparing the two equation forms for slow and rapid loading (Table

5.1) at a common water-cement ratio and density, a relation between the two

in the form of

( br/bsa = ar _s (6.27)

is produced where a and b are the equation coefficients of Table 5.1,

a is any of the characterization stresses, and subscripts r and s in-

dicate the rapid- and slow-loading cases, respectively. Comparing the

average stress value, Q0.40 , for the four water-cement ratios for which

both slow- and rapid-loading tests were conducted, it was found that for

93

Page 96: REPORT NO. 6-763 - digital.library.unt.edu

all practical purposes, the relation between ar and as was independent

of the water-cement ratio. By combining all of the data an expression in

the form

ar= 2.620-9 (6.28)

resulted for the average stress characterization, a0.40 . Equation 6.28

is shown in Figure 6.5 and provides results that are within 10 percent of

what might be determined for each water-cement ratio individually. It is

shown in Equation 6.28 and Figure 6.5 that cellular concrete as tested by

the IAHA is rate-sensitive and, as such, should be treated accordingly in

the analysis of the response of backpacked structures.

6.1.3 Multiple-Shot Loading Capability. If a backpacked structure

survives the effects of its first shock loading and the deformations of the

cavity walls are within the elastic strain region of the medium, the back-

packing should retain almost all of its original potential. If the defor-

mations of the cavity wall were such that partial closure of the cavity

resulted, there would be a corresponding crushing of the backpacking. As-

suming the backpacking does not lock under the initial loading and partial

closure of the cavity, some of the potential of the backpacking theoreti-

cally should be available for additional loading. This is evident in Fig-

ure 5.8. For the range of densities studied at a typical water-cement ra-

tio, the cellular concrete appears to have some multiple-shot resistance

capacity provided the initial loading does not completely crush the mate-

rial. The test configuration approximates the situation where a piece of

rock that has broken from the cavity wall is driven into the backpacking

by the initial shock loading. The majority of the backpacking crushing

takes place in a region adjacent to the area of rock-packing contact. With

additional loading (second shot), the rock is driven further into the back-

packing with additional crushing occurring. The backpacking can then ab-

sorb many thrusts of the rock as determined by its remaining crushing capa-

bility after each loading. The effects of the crushing of the backpacking

due to liner movement should also be considered but is beyond the scope of

this work.

94

Page 97: REPORT NO. 6-763 - digital.library.unt.edu

It is doubtful that the cellular concrete will be able to rebound and

regain any appreciable amount of its original volume as the forces in the

cellular concrete would not be great enough to force and compact the walls

of the cavity into some semblance of its original form.

The curves in Figure 5.8 show that the cellular concrete achieves the

same crushing stress plateau for both shots. The second shot, however, be-

gins from a zero load point. After the initial loading, assuming partial

closure of the cavity has occurred, it is unlikely that the backpacking

would achieve its original state of stress before loading because of the

dead load of rock mass it would now have to support. Given sufficient

time, the backpacking would probably attempt to creep out from under any

stress concentrations, thus resulting in a somewhat uniform stress through-

out the material. The time it would take to accomplish this, if at all,

would depend on the properties of the material in question. With an ini-

tial stress simulating dead load in the cellular concrete, it is possible

that the second shot crushing stress plateaus as shown in Figure 5.8 would

have been somewhat higher. The manner in which the IA[A operates, however,

did not permit this aspect of the multiple-shot loading to be evaluated.

6.2 FLEXURAL STRENGTH

6.2.1 Modulus of Rupture. Statistically, the modulus of rupture ver-

sus density relations shown in Figure 5.9 for the 0.86, 0.96, and 1.06

water-cement ratio concretes are not significantly different from each

other. A trend toward higher moduli with decreased water contents for a

given density is evident, however. A substantial increase in moduli is

experienced when the water-cement ratio is reduced further from 0.86 to

0.76.

Previous information (Reference 13) has concluded that a reasonable

range of ratios for flexural strength to compressive strength of cellular

concretes is 0.2 to 0.33. Comparing the regression equations of Tables

5.1 and 5.2, a ratio of

a b-bR= -- (d) r y (6.29)Q ay y

95

Page 98: REPORT NO. 6-763 - digital.library.unt.edu

is obtained where the subscripts r and y denote the modulus of rupture

and yield stress values, respectively. From Equation 6.29, the following

ratios were obtained for a freshly mixed density range of 22 to 43 pcf.

Water-Cement R Flexural StrengthRatio y Yield Strength

0.76 0.16 to 0.330.86 0.19 to 0.210.96 0.211.06 0.19 to 0.24

These values, in general, appear to fall within the range of ratios usually

associated with cellular concretes.

6.2.2 Horizontal Joint Tests. One of the more significant results

of the horizontal joint tests was the fact that none of the flexural joint

beams failed across the joint. All of the beams except one fractured in

the concrete of the lower (or first) lift. In general, the concrete den-

sities, cube strengths, and flexural control beam strengths for the bottom

lifts were less than the values obtained for similar specimens from the

top (or second) lifts. In most instances, the corresponding values from

both lifts statistically were not significantly different. Because the

strength of the cellular concrete (Sections 6.1.1 and 6.2.1) is influenced

by density, among other things, the lower values of compressive and flex-

ural strength corresponding to the lower densities of the bottom lifts are

not unusual.

In all but one instance, the flexural strength of the joint beams is

less than the flexural strength of the control beams from either lift. Be-

cause the joint beams failed in the lower lift concrete, their strengths

might be expected to be the same as the strengths of the lower lift con-

trol beams. This is not the case, however. Observation of the bleeding

characteristics of cellular concrete leads to the speculation that the

difference in flexural strength for the same concrete is due, in large

part, to the increased moisture content of the concrete near the surface

of the lower lift. The excess mixture water in neat cellular concretes

bleeds downward into the concrete. Because of the permeable nature of the

concrete (Section 6.8), the bleed water from the top lift can pass

96

Page 99: REPORT NO. 6-763 - digital.library.unt.edu

completely through the concrete, carrying with it some finer particles of

-cement. This "erosion" is not of the same magnitude as that discussed in

Section 6.8. It occurs during the setting period of the concrete. Upon

encountering the hardened joint, some of the cement particles are deposited,

thus reinforcing the joint. The bleed water passes into the more mature

concrete of the lower lift and is retained in the upper regions of that

lift. This increases the moisture content of the top regions of the lower

lift and reduces the tensile stresses that develop there as the concrete

attempts to reach a moisture equilibrium while bag-curing. This condition

lowers the flexural strength in the vicinity of the joint.

The average flexural strengths of the joint beams having an air-cured

joint were 12.1 and 12.3 psi for the unprepared and prepared conditions,

respectively. The average flexural strengths of the joint beams having

moist-cured joints were 14.5 and l4.4 psi for the unprepared and prepared

conditions, respectively. For both the moist-cured and air-cured joints,

the effects of joint roughness appear to be minimal with either roughness

condition being adequate. The moist-curing of the lower surface of the

joint seems to provide some benefits by increasing the flexural strength

of the concrete in the top of the lower lift. The increase is not sig-

nificant however. The presence of the joint, in general, reduced the flex-

ural strength of a beam by approximately 6 psi. While this is approxi-

mately 30 percent of the strength of the control beams, the magnitude is

such that the reduction in strength should not affect the overall perform-

ance of a mass of cellular-concrete backpacking that contains horizontal

cold joints.

In summary, for cellular concretes that will be used as backpacking,

the presence of horizontal cold joints does not appear to be a problem

area. The benefits of surface roughness are minimal and the as-cast sur-

face should suffice. The joint appears to be stronger than the concrete

in the immediate vicinity of the joint with most flexural failures occur-

ring in the weaker concrete. Curing of the joint surface by covering with

plastic shortly after casting as opposed to no special curing will improve

the strength of the weaker concrete but not significantly. Addition of

free moisture for curing is not desirable as it fills the voids needed

97

Page 100: REPORT NO. 6-763 - digital.library.unt.edu

for the deformation capability of the concrete. Curing compounds have not

been studied.

6.3 ULTRASONIC PULSE VELOCITIES

The curves in Figures 5.6 and 5.7 indicate that the compressional wave

velocity of cellular concrete is continuing to increase with age of the

concrete. The curing conditions of the specimens (Section 2.3) were such

that no additional moisture was added to the concrete; hence the principal

phenomenon occurring in the concrete was the formation of additional cement

gel with subsequent decreases in free moisture and porosity. Increases in

the freshly mixed density of the concrete as shown in Figures 5.6 to 5.8

(at any given age or water-cement ratio) also produce increases in the com-

pressional wave velocity. Again the changing phenomenon is an increase in

cement gel content.

As the cement gel content appears to be influencing the magnitude of

the compressional wave velocity, a definite relation between the two can

probably be established. Equation 6.15 can be rewritten to represent the

amount of cement gel present in a given cellular concrete. In the assump-

tions made to arrive at the form of Equation 6.15, however, the degree of

hydration of the cement at a given age with respect to complete hydration

is not considered. Because a number of factors such as cement composition,

fineness, and particle size will affect the amount of hydration products

at a given age, for design purposes it is simpler to relate the wave ve-

locities to something more definite such as the initial cement content of

the concrete. The relations between compressional wave velocity and

cement content for bag-cured neat cellular concrete at various ages are

shown in Figure 6.6. A summary of the equation coefficients can be found

in Table 6.1. The correlation between cement content and compressional

wave velocity appears to improve with age. No reasonable correlation

could be made for data obtained at 3 days age. This is probably due to

the smaller amounts of cement gel and the larger quantities of free mois-

ture present in the concrete at early ages. The higher water-cement ratio

concretes provided the most dispersion to the data at 3 days age.

The effect of path length for the compressional waves was not studied.

98

Page 101: REPORT NO. 6-763 - digital.library.unt.edu

The void size and distribution may result in longer path lengths as the

wave travels around the voids. This may result in other values of wave

velocity. The difference may not be significant, however. The effect of

moisture content of the concrete also was not studied. The compressional

wave velocity of pure water is approximately 4,800 ft/sec. At high mois-

ture contents (after some saturation) and low cement contents, the velocity

results may be affected.

6.4 RATE OF HARDENING

Rate-of-hardening information is necessary to determine the accessi-

bility of the top surface of the cellular concrete and also for form re-

moval purposes. It has been suggested (Reference 14) that the concrete

possesses a certain "walkability" before it sustains nominal construction

foot traffic. Acceptable walkability occurs at such time as the average

of five tests by a Proctor penetrometer on the periphery of a 30-inch-

diameter circle produces a bearing value in excess of 10 pounds with a

1/4-inch penetration of a 1/20-in2 needle. Walkability, as such, was not

measured for the concretes of this study but may have great utility in the

preparation of job specifications with regard to surface accessibility.

The rate-of-hardening curves in Figures 5.9 and 5.10 provide some in-

sight as to the early age strength development of cellular concrete. In

general, the concretes with the lowest water-cement ratio, and hence the

highest cement content for a given density, begin to stiffen earliest as

might be expected. The data indicate that there are exceptions to this

observation but these must be weighed against the fact that only small

populations are being studied. In no instance was any penetration resist-

ance encountered before 7 hours had elapsed. With one exception, the

range of elapsed time for a resistance value of 1 psi at a particular den-

sity was less than 4 hours. All of the tests were conducted at 73 F. In

a prototype situation, the early stiffening may be accelerated by higher

curing temperatures (Section 6.6), thus permitting earlier construction

traffic and form removal. At densities greater than 30 pcf, forms have

been removed as early as 5 hours after completion of placing when the

cellular concrete sections were very thick and the ambient curing

99

Page 102: REPORT NO. 6-763 - digital.library.unt.edu

temperatures between 95 and 100 F (Reference 5). The effects of these con-

ditions should be determined by test for each particular job, however.

6.5 MODULUS OF ELASTICITY AND POISSON'S RATIO

Elasticity data on moist-cured low-density cellular concretes appear

to be meager. The elastic moduli generally have design significance when

the concrete is of a semistructural or structural grade and, hence, are

usually not measured for the very low-density concretes. In understanding

the performance of and designing backpacked protective structures, however,

the elastic modulus of the backpacking is an important parameter.

The data represented by the curves in Figure 5.11 indicate that the

elastic modulus increases in a power function form for increasing values

of freshly mixed density. The results of other studies (Reference 14) in-

volving freshly mixed density ranges, which begin at approximately the den-

sities at which this study ends, tend to substantiate the curvilinear re-

lation. At densities greater than 50 pcf, the moduli density relations

have been represented by parabolic curves of approximately the fourth de-

gree (Reference 15).

It has been shown (Reference 15) that the modulus of elasticity of

concrete is a function of unit weight and compressive strength. The

formula

Ec =W1.533/ft (6.30)

presented in the ACI Code (Reference 16) defines this relation for values

of W between 90 and 155 pcf. For a given compressive strength, the mod-

ulus of elasticity of lightweight concrete is usually lower than that of

normal weight concrete (Reference 17); however, in some instances, it has

been shown to be greater (Reference 18). Using Equation 6.30 with the

data obtained from the 75 moduli tests of this study, the relation in Fig-

ure 6.7 was developed. The line-of-best-fit for the data points involved

a decision to use either a straight-line or a simple-power function. For

the range of values on the abscissa, the statistical differences between

the two curves are marginal. For a zero value of density or strength,

100

Page 103: REPORT NO. 6-763 - digital.library.unt.edu

however, the modulus would also be zero; hence, the selection of the power

function was made. Its use may not be warranted beyond the range of these

data, however.

The line-of-best-fit in Figure 6.7 is expressed as

Ec = (0.o875W1.3 6 5(f,)O.455 + 25) x 103 psi (6.31)

at the 95 percent statistical tolerance limits. The scatter in the data

is such that Equation 6.30 could possibly be considered as a lower bound

in lieu of a tolerance limit as shown in Figure 6.7. Additional tests are

needed to firmly establish this, however. Depending on the importance of

E in the structure-backpacking design, the designer should decide whether

values determined by Equations 6.30 or 6.31 are adequate or whether addi-

tional tests on specific concrete are warranted.

Values for Poisson's ratio of the moist-cured cellular concrete varied

between 0.192 and 0.252. These values are not unreasonable or unusual and

are similar to those reported by other investigators (Reference 13).

6.6 TEMPERATURE PROBLEMS

Heat buildup and temperature rise associated with the hydration of the

cement in the cellular concrete can create serious problems during construc-

tion if proper precautions are not taken. The cement contents of the con-

cretes of this study varied from 3 bags/cu yd for the very low-density,

high water-cement ratio concrete to approximately 8 bags/cu yd for the

high-density, low water-cement ratio concrete. Although at the lower limit

of cement content excessive temperatures might not be expected, the heat

buildup is aided by the insulating characteristics of the concrete (high

air content), which inhibits the dissipation of the heat with time. The

problem is further compounded by the fact that, when used as a backpacking,

the material is placed in very thick sections in a containing media such

as rock which behaves as a very effective heat sink. Cellular concrete

thicknesses of 11 to 12 feet around cylindrical tunnels of substantial

lengths have been placed (Reference 5).

The problems associated with the concrete temperatures are primarily

101

Page 104: REPORT NO. 6-763 - digital.library.unt.edu

related to fresh concrete in its unhardened state. As shown in Figure 5.12,

in an adiabatic condition, which is approximated by the conditions at the

center of a large mass of cellular concrete, temperatures can become quite

excessive and actually create steam pressure in the concrete. Steam has

been observed coming from thermal cracks in sections of concrete with

thicknesses as small as 2 feet (Reference 19). Once the concrete has

hardened, the elevated temperatures are no problem except that the curing

conditions of the interior mass will produce concrete strengths which may

be different from those obtained from the quality control cylinders repre-

senting that mass of concrete. Thermal cracking generally has little ef-

fect in the overall performance of a backpacking mass. Problems occur when

unhardened concrete is placed in close proximity to the hot, hardened con-

crete. When this occurs, the elevated temperatures cause the air in the

air-bubble system of the concrete to heat up and expand. This is accom-

panied by a reduction in the surface tension of the liquid film forming

the bubble skin. Upon reaching a critical point, the bubble bursts. Many

bubbles may join together to form large voids that then collapse. These

collapses result in either localized "potholing" or a general subsidence

of the surface of the concrete. Subsidence of 4 feet in 12-foot lifts has

been observed (Reference 5). This phenomenon can be seen in Figures 5.16

and 5.17. The unhardened concrete was placed in and allowed to cure at

elevated air temperatures of 100 and 120 F with 80 F being the control

(results not shown). These air temperatures are not uncommon behind bulk-

heads on tunnels that already have some cellular concrete placed behind the

bulkhead. Air temperatures as high as 155 F have been observed. No col-

lapse was observed at 80 F. At 120 F (Figure 5.16), the results are obvi-

ous. The only concrete not collapsed is the 43-pcf concrete, which had the

lowest air content and highest cement content. The air bubbles in the

43-pcf concrete have expanded, thus producing the cracked dome of material

on its top surface. At 140 F (results not shown), even the 43-pcf concrete

experienced complete collapse.

The potential collapse problem associated with the elevated tempera-

tures can be experienced at any stage of a cellular concrete placing opera-

tion. The problem can exist in situations where a new lift is placed on

102

Page 105: REPORT NO. 6-763 - digital.library.unt.edu

an existing hardened lift that is very hot and has not had its surface

cooled to a sufficient depth before placing of the next lift. The heat

given off by the hardened lift is contained by the fresh concrete; and if

it can build up to a harmful temperature before the fresh concrete has set,

collapse in the lower regions of the new lift may occur. This is shown in

Figure 5.15 for both Type I and Type III cements. The temperatures recorded

for the upper region of the first lift in each case are lower than the

temperatures at the interior and bottom of the lift, due to the dissipa-

tion of the heat through the top of the lift into the air. This transfer

of heat causes the air above existing lifts and behind bulkheads to become

very hot and this hot air in turn can cause the problems mentioned earlier.

After the placement of the second lift in each case, the temperatures in

the bottom of the second lift become greater by as much as 30 F than at

other locations in the lift (Figure 5.15). This is the effect of the heat

of the first lift. If the initial temperature of the fresh concrete of the

second lift is sufficiently high, the fresh concrete can become too hot

after a very short time with resulting bubble collapse. The problem can

also exist in very large volume lifts, such as those experienced when the

total time of placement of the lift exceeded the time required for some of

the concrete placed during the earlier stages of the same lift to reach its

maximum temperature buildup. The concrete between the region that has be-

gun to harden near the bottom of the lift and the concrete that was most

recently placed is then affected in the same manner as fresh concrete

placed on an existing hot lift. An overall subsidence of the surface of

the lift may then be observed, perhaps even while placing is still going

on. While placing a large section of cellular concrete (which experienced

some subsidence) made with a water-cement ratio of 0.85 and a cement con-

tent of 6 bags/cu yd at an ambient air temperature of 95 F, thermocouples

in the bottom of a large lift indicated temperatures of 160 F while placing

was still in progress (Reference 5). Internal temperatures in this section

peaked at 185 F.

To avoid these problems, the initial temperature of the fresh con-

crete should be kept as low as practical. Figures 5.13 and 5.14 show the

effect of mixture water temperature on the early age heat in cellular

103

Page 106: REPORT NO. 6-763 - digital.library.unt.edu

concrete for Type I and Type III cements, respectively. As has been shown

many times for structural and mass concrete, the cooler the water, the

cooler the concrete. The reduced initial temperatures allow the concrete

to harden before higher damaging temperatures are reached. The effect of

cement fineness is also a factor as the more surface area of cement that is

hydrating initially, the more heat that is generating. The Type III cement

is more finely ground than the Type I and thus contributes more surface

area for early hydration and, hence, more heat. The requirement for fine-

ness of the cement must be balanced with the water requirement for the

backpacking design to prevent excessive water in the concrete. The data

from the cement analysis (Section 2.1.1) show the fineness for the Type I

and Type II cements to be 3,845 and 4,790 cm2/gm, respectively. This dif-

ference is reflected in the temperature curves of Figures 5.13 and 5.14 with

the finer cement, i.e. the Type III, producing higher temperatures than the

Type I cement at comparable periods of early hydration. The total heat

produced by each cement over an extended time period will be approximately

the same, however, as the compositions are not significantly different.

The use of coarser cements, or depressed concrete temperatures, or both,

will produce cement pastes that stiffen at slow rates. The time needed for

stiffening to occur must be balanced against the time that the preformed

foam will retain its bubble structure. If the paste does not harden suffi-

ciently before the bubbles begin to break down, the cellular concrete will

collapse in the same manner as the high temperature collapse.

In summary, elevated temperatures can cause collapse of the air-

bubble system of the cellular concrete while it is in the unhardened state.

This collapse results in localized "potholing" or general subsidence of the

unhardened cellular concrete, which produces density increases and hence

changes in physical properties. These elevated temperatures can be present

in the air behind sealed bulkheads used as the formwork during placing of

the concrete. They can also exist in the lower regions of a lift of un-

hardened concrete that is either influenced by the heat of a hardened lift

of concrete adjacent to it or by the temperatures developed in the new lift

itself because of excessive placement times. The problems can be avoided

by (1) using cooled mixing water and, if possible, cement, (2) using

104

Page 107: REPORT NO. 6-763 - digital.library.unt.edu

minimum handling and placing times, (3) using low-heat, coarser ground

cements, (4) restricting total placement times to periods that do not allow

internal temperatures to become excessive, and (5) adequately cooling (by

air blowing) the surface of adjacent sections of hardened concrete and the

ambient air in which the fresh cellular concrete is to be placed.

6.7 LIFT HEIGHT RESULTS

The results of both the 16- and 30-foot lifts indicate that density

increases do occur with increasing depth of concrete. The increases may

indicate an increase in the amount of water in the concrete because the

excess water in the mixture (bleed water) has a tendency to flow down into

the concrete. The lower sections might then contain the excess water in

the air void system. The comparison between the as-cast and the oven-dried

cubes from the 16-foot lift tends to discount this as the amount of evapo-

rable water in the concrete appeared to be the same from top to bottom.

The density changes then are only a function of the amount of cement paste

in a given volume. For a density increase, either the number of air voids

per unit volume is decreased, or the existing air voids are compressed, due

to the superincumbent load, while the concrete is still in the unhardened

state. Upon hardening, the number of air cells would then still be the

same but their size would be smaller with the difference in the original

and final volumes being replaced by additional paste.

Figure 5.2 shows that changes in density result in changes in strength.

The change in density of 7 pcf in the 16-foot lift can produce a change in

the crushing level stress (Q0.40) from approximately 100 to 190 psi (Fig-

ure 5.2a) for the concrete design used in that section. Changes of this

magnitude are not desirable because if the stress transmitted through the

backpacking to a structural liner is not fairly uniform, ovaling or dis-

tortion of the liner may result and thus destroy the effectiveness of the

liner's original design.

It is desirable to restrict the lift height of the cellular concrete

to some value that is consistent with the allowable stress differences the

liner in question can stand and the quality control that can be achieved

for the cellular concrete placement. For example, if variation in density

105

Page 108: REPORT NO. 6-763 - digital.library.unt.edu

due to lift height of +3 pcf from a design density, d , is acceptable from

a strength standpoint, but the quality control during placement can be ex-

pected to be no better than +2 pcf, then the actual lift height that can be

placed should be restricted to that height which yields d +1 pcf.

6.8 SATURATION PROBLEMS

After placement of backpacking around tunnel liners or silos is com-

plete, the problem of groundwater infiltration into the backpacking arises.

All of the materials currently under investigation for use as back-

packing are very porous, with void contents to 80 percent being commonplace.

Cellular concrete is no exception. This high void content is necessary to

meet the structural behavior requirements of the material, i.e., to deform

in excess of 40 percent of the initial thickness of the material with no

appreciable increase in the stress level necessary for yielding to occur.

This deformation is essential in absorbing the movements of the surrounding

medium and in changing the input loading pulse accompanying a nuclear ex-

plosion into an input pulse less detrimental to the buried structure and

its contents. Once the desired stress-strain relation for the materials is

developed, the question then asked about the backpacking is what will hap-

pen if water, from a ground source or introduced by other means, infil-

trates the backpacking material to such a degree that all the available

permeable void space in the material becomes filled with water. Will the

material still be able to absorb the ground movements and change the dy-

namic loading pulse into a less detrimental form?

Cellular concrete possesses both interconnecting voids and noninter-

connecting voids. For the purposes of water saturation, the first of these

void conditions is the less desirable. In this condition, water can

quickly fill all the voids in a given specimen with little difficulty. The

second void condition is perhaps the more desirable condition as each void

would be a separate cell filled with a gas. A rupturing of each cell wall

would be necessary for water to migrate into the cells.

The void space in any given specimen is composed of the space filled

with gas (air and others), both entrained and entrapped, plus the space

filled with free water. This void space is composed of permeable pores

106

Page 109: REPORT NO. 6-763 - digital.library.unt.edu

available for saturation, permeable pores unavailable for saturation, and

impermeable pores. The short-term saturation tests run on all the con-

cretes fill only the permeable pores available for saturation and those are

not filled completely because of the gas in the pores being compressed and

having no place to go. When referring to a material being completely satu-

rated in this study, what in effect is meant is that no more fluid can be

forced into the available permeable pore spaces without further large in-

creases in water pressure being applied.

The degree to which saturation of the material will occur will depend

not only on the type of void structure but on the strength of the matrix,

and the method by which the water is introduced or applied to the material.

The crushing stresses of the cellular concretes vary from 20 to 900 psi, de-

pending on their particular design. In a closed cell situation, the walls

of the cell will rupture, when subjected to increasing pressures, at pres-

sure levels governed by the strength of the matrix. A low-strength matrix

will fracture and allow the closed cells to fill at much lower water pres-

sures than a high-strength matrix. When we say the cell walls rupture or

fracture, it is not in the catastrophic sense of the word but in the forma-

tion of microcracks, perhaps only one or so per cell, that would allow the

water to migrate into the cell and equalize the pressure in that cell to

that of the cells or other areas supplying the pressurized water. The sta-

bility of the material in mass is not destroyed by this type of saturation,

but the strength is somewhat reduced due to the moisture and the cracking.

Assuming that the above situation is occurring, the question now

arises as to what happens to the gas that originally filled the cells.

This problem relates itself to the manner in which the water is introduced

or applied to the material. Under almost all field conditions, the ground-

water will be transient with respect to location of the material. The gas

in the voids will become compressed as the water pressure increases and

with the migration of the water into the material, the gas will be forced

ahead under pressure with a portion of it probably being moved out with the

transient water. Some of the gas will undoubtedly remain behind in a com-

pressed state in the material. If the material were subjected to a station-

ary hydrostatic pressure, which is highly improbable but could happen, all

107

Page 110: REPORT NO. 6-763 - digital.library.unt.edu

the gas would remain in the compressed state and it would be virtually im-

possible to fill every void space.

The data shown in Figure 5.18 indicate that water pressures in excess

of 300 psi for a short-time test are necessary to saturate most of the

available permeable void spaces in a very dense (with respect to cellular

concrete backpacking densities) concrete made at an average water-cement

ratio. Under long-term conditions this same degree of saturation could

possibly result at lower water pressures. This saturation results from a

stationary constant pressure situation where the gas remains compressed in

the material. Specimens statically loaded in this condition show a negli-

gible amount of deformation if the volume of water in and around the speci-

men is not allowed to change as loading progresses. If free water is al-

lowed to escape from the system as the static loading progresses, the usual

stress-strain relation for an unsaturated material will result but at a

higher crushing strength level due to the increased water pressure neces-

sary to keep the water in the voids. However, under the dynamic loading

that would result from the shock wave accompanying an explosion, the free

water in the system would not have time to migrate; the shock wave would

then pass through the originally porous material as if it were rigid. Very

little, if any, deformation would result; and in all probability, severe

damage would result to the structure being protected.

The curve in Figure 5.18 indicates that very low water pressures are

all that is required to fill at least half of available voids in cellular

concrete. The results of the low-head permeability testing are shown in

Figures 5.19 and 5.20 and tend to indirectly substantiate this. At average

water heads of approximately 6 feet, water readily passes through the lower

density concretes and tends to fill some of the voids with water. Regard-

less of the water-cement ratio, all of the 23-pcf concretes exhibited the

same general pattern. Initially, the concrete appeared to be experiencing

a flow-rate reduction with time of test run; however, the amount of reduc-

tion reached a maximum within the first 24 hours. A flow-rate increase

then began with most of the maximum reduction in flow rate being regained

within the next 24 to 30 hours. The amount of total solids measured in the

discharge water (Figure 5.21) after the initial total solids was established

108

Page 111: REPORT NO. 6-763 - digital.library.unt.edu

leveled off at approximately 30 ppm more than the total solids of the tap

water before it passed through the concrete. This leveling off occurred

about the same time as the maximum flow reduction occurred. All the test

specimens were badly eroded and damaged after testing.

Regardless of the water-cement ratio of the 32-pcf concrete, all spec-

imens exhibited the same general behavior pattern (Figure 5.20). The flow

rate through the specimens appeared to decrease with time of the test run.

Within the 80-hour test period, the total solids of the discharge water de-

creased (Figure 5.21) to approximately 30 ppm more than that of the origi-

nal tap water before it passed through the specimens. These specimens did

not appear to be eroded at the top surface as were the 23-pcf specimens.

No appreciable flow could be determined through the 43-pcf concrete

with a water-cement ratio of 0.76; however, some small flows were noted for

the 0.86- and 0.96-water-cement ratio material. These flows were not

enough to accurately measure. The specimens did not appear to be physi-

cally altered by the flow.

The most obvious conclusion drawn from these tests is that the cellu-

lar concrete is very permeable at low densities and low hydrostatic pres-

sure. In being very permeable, the concrete allows the water to reach most

areas of the concrete mass and fill some of the available voids in those

areas. The higher density concretes seem to indicate that, with sufficient

strength development and subsequent reduction in void content, the permea-

bility at low heads is greatly reduced for short-term flow conditions.

Whether or not the concrete will maintain its reduced permeability for ex-

tended periods of time under low heads or for shorter periods of time under

greater heads is not known. Tests of specimens fabricated by two major man-

ufacturers of foaming agents for cellular concrete were conducted by an in-

dependent testing laboratory. The results of those tests showed that at

water pressures of 80 psi, maintained for 24 hours, no water could be

l Private communications; letter dated 26 Jan 1965 from Chemical Concen-

trates, Redondo Beach, Calif.; and letter dated 3 Feb 1965 from Mearl

Corporation, Roselle Park, N. J.

109

Page 112: REPORT NO. 6-763 - digital.library.unt.edu

forced through cellular concrete, provided the density of the concrete was

greater than approximately 70 pcf. At lower densities, the water flowed

through the specimens at rates that were related to the concrete density.

The total solids measurements made from the discharge water indicate

that the water is picking up some additional total solids as it passes

through the specimen, thus eroding the specimen. The very high values of

total solids that occurred early during the test indicated the severest

period of erosion. Some of the particles eroded evidently plugged the

channels through which flow was occurring and gave the appearance that the

rate of flow through the concrete was decreasing (Figures 5.19 and 5.30).

For the 23-pcf concrete, these plugs were also eroded with time, and the

flow rate picked up. The flow channels then became fairly uniform with a

somewhat constant rate of erosion occurring as is indicated in Figures 5.21

and 5.22. Evidence of the flow channel plugging was also observed for other

backpacking materials tested in a similar manner (Reference 3).

If the material is very permeable, it will probably not be very prac-

tical as a backpacking material if it is used by itself with no other sys-

tems that could divert or resist the intrusion of groundwater. Even if the

cellular concrete can be designed to be almost impermeable by itself, there

is no guarantee that under sustained associations with groundwater on the

surface of the backpacking that either complete or partial saturation of

the concrete will be eliminated. If the material does become saturated,

either partially or completely, the pore-water pressures that may develop

in the concrete may, under certain conditions, apply destructive pressures

to the walls of the pores in the concrete, thus reducing the effectiveness

of the material as backpacking.

The obvious solution to the problem is to build the structures requir-

ing protection in media where there is no water. This is, of course, an

almost impossible task but areas where the groundwater or other water would

present a problem can be treated and maintained in ways that would prevent

water from reaching the cellular concrete backpacking. Grout curtains in

rock, wellpoint systems in soil, drains around the structures, sandwich-

type structures, and many other methods could be applied to eliminate this

threat of saturation.

110

Page 113: REPORT NO. 6-763 - digital.library.unt.edu

The possibility of waterproofing the surface of the cellular concrete

also exists. However, complete waterproofing would not be the answer for

elevated pressures. An ideal backpacking can have a crushing stress level

that is very low (25-150 psi) and will deform at that crushing stress for

strains in excess of 40 percent. If the possibility of invasion by free

water from an outside source into this material is eliminated for elevated

pressures, what then would happen to the material when the outside water

pressure goes above the crushing stress level of the material? The gas

that fills the voids in the material would begin to compress, the material

would begin to yield, and as the outside pressure increases the material

would deform more and more, thus failing the material and destroying its

usefulness before it could be loaded by a shock-wave input. Waterproofing

is not the complete answer but would improve the effectiveness of the mate-

rials at lower water pressures.

As shown in Figure 5.23, there are considerable differences in the ef-

fectiveness of the sealers studied. The two most promising appeared to be

liquid latex and neat cement slurry. The neat cement slurry, upon harden-

ing, allowed no water into the sample. The liquid latex allowed just small

quantities but is probably more effective than the results indicate. The

same material has been used on laboratory specimens of many different mate-

rials to prevent moisture from entering the material and has been 100 per-

cent effective. Both the neat cement slurry and the latex can be easily

applied to the surface of the walls of a tunnel in rock in order to seal it

before the backpacking is placed against it.

There are many commercially available products that can be used as

surface sealers. Those evaluated in this study were used only because they

were readily available in the area in which the investigation was conducted.

A proper evaluation should be made of each sealer considered for use in

backpacking operations.

111

Page 114: REPORT NO. 6-763 - digital.library.unt.edu

SUMMARY OF ULTRASONIC PULSE VELOCITY (V) VERSUS CEMENTCONTENT (C) RELATIONS, V = aCb +2 Sesty , ft/sec

Age No. of Equation Correlation StardardObser- Coefficients Coefficient Error ofvations Estimate

a b Sesty

ft/sec

156

172

172

172

593 0.778

671 0.770

772 0.741

844 0.724

0.879

0.929

0.953

0.960

390

315

256

234

112

TABLE 6.1

days

7

14

28

60

Page 115: REPORT NO. 6-763 - digital.library.unt.edu

800 *I. .Y.

\ CFo- 42,000 (/ - n/ 3 f ./ PS/

600

&4o ~ 0__ _ _ _ _ _ _ _ __ _ __ _ _ __ _ _ _

80 85 90THEORETICAL POROSITY, n

95 100

Figure 6.1 Yield stressneat cellular concrete.

e 00

a-400

w

U

-J 200w

0-

6 10

versus theoretical porosity relation for a

14 18

(+c( I+C )

22 26 30

Figure 6.2 Relation between yield stress and the design parameter,

dc/(1 + k) .

113

(n0.

U)W

W:

200

'100- - - ---- -------------

9,6

75

0~y=0.02436

U

800

0 1

Page 116: REPORT NO. 6-763 - digital.library.unt.edu

24 1 4

22 26 30 34FRESHLY MIXED DENSITY, PCF

Figure 6.3 Relations between design parameter, dc/(1 + k) , and freshlymixed density for various water-cement ratios.

(I+0.20pc 3

G0 \ 6 2 .

3Pc

/

SPEC/F/C GRAVTY 3./--

'r t

GRAV/T Y= 3.2

I0 14 18

(I+k)

SPEC/F/C

22

x

26 30

Figure 6.4 Proposed relation between stress ratio anddesign parameter, dc/(1 + k) , for cellular concrete.

11i

FJ1 LIMITS OF ACTUAL TEST DATAIi II

12

14 18 38 42 46

16,000

CAl 12,1000wJ2

0

8 4000

06

8

201 ' '

r I - T- - I I I

I E I I I 1/

10

0"

44A

A

Page 117: REPORT NO. 6-763 - digital.library.unt.edu

Figure 6.5 Rapid loadingversus slow loading rela-tion for the average stressto 40 percent deformationcharacterization, 0.40 *

u

I

LL

H

U0J

JDa-

UZ0

-J

0

W

Id

O

lb J

inac,)

mH-W10

QD

iooo

RAP/D SO2W62 O~ -800

600

400

200

00 200 400 600

AVERAGE STRESS, 60.40 DETERMINED

BY SLOW LOADING TEST, PSI

60000

500C

4000

3000

2000A fl I AI4I

CEMENT CONTENT, PCT

800

Figure 6.6 Ultrasonic pulse velocity versus cement content

relations for neat cellular concrete .

115

1440 v Iv 3

Page 118: REPORT NO. 6-763 - digital.library.unt.edu

200

175

150

/I

/0.1 0.2 0.3

W 3/2 J[7x o- 4

0.4 0.5

Figure 6.7 Secant modulus of elasticity versus modulusparameter relation.

116

0

WATER- CEMENT /RATIO 0

O 0.660 +A 0.76

o 0.86

E _ (0 .0 8 75 W '.3 65(fr )0.455 t25) X 103 A

0

q00

00

o0

/ D /

0

0-

-u

~IW

25

1 00

75

50

25

00 0.6

Page 119: REPORT NO. 6-763 - digital.library.unt.edu

CHAPTER 7

CONCLUSIONS AND RECOMMENDATIONS

7.1 CONCLUSIONS

Based on the results of the testing of this investigation and the in-

formation obtained from published reports and papers reviewed during the

investigation, the following specific conclusions appear warranted:

1. The strength of moist-cured neat cellular concrete is principally

a function of the concrete density and water-cement ratio, and the specific

gravity of the cement. From the data of this study, the yield stress was

determined to be

d 3

ay= 0.2436 (1 d k)(7.1)

A more universal design approach was suggested such that

do ba d k(7.2)

Q C l+ k

for all cements.

Neat cellular concretes made at densities from approximately 18 to

50 pcf and water-cement ratios from approximately 0.6 to 1.1 (by weight)

possess the strength-deformation characteristics required for a suitable

backpacking material regardless of the loading rate applied to the con-

crete. Average crushing stress levels from 20 to 1,000 psi at 28 days for

slow-loading rates can be readily obtained depending on the mixture pro-

portions. Strengths in excess of 1,000 psi, with deformations to 40 per-

cent before locking, also appear to be feasible.

2. Cellular concrete is load and/or strain rate sensitive. For the

rapid-loading system and techniques used in this study, crushing stress

level increases from 95 to 30 percent were observed for the low-strength

(20 psi) and high-strength (1,000 psi) concretes, respectively. The shape

of the stress-deformation curve for cellular concrete does not appear to

change with increased rates of loading.

117

Page 120: REPORT NO. 6-763 - digital.library.unt.edu

3. Cellular concrete appears to possess a multiple-shot load-

resistance capability provided the initial loadings do not completely crush

the material. Each concrete design has a certain deformation capability.

The portion of that capability not used to accommodate medium movements as-

sociated with earlier shock loadings is available to accommodate additional

loadings.

4. The modulus of rupture of cellular concrete is dependent on the

mixture proportions with higher cement contents and lower water contents

producing higher flexural strengths. The ratio of flexural strength to

compressive yield strength varied from 0.16 to 0.33, which is not unrea-

sonable for low-density cellular concretes.

5. The compressional wave velocity (as measured by ultrasonic pulse

techniques) of neat cellular concrete appears to be directly influenced by

the cement gel content of the concrete. Increased gel contents due to the

continuing hydration of the cement result in increased velocities. In-

creased gel contents, due to increased density (obtained by adding more ce-

ment per unit volume and decreasing the air content) also produce increased

velocities. Free moisture in the concrete also appears to influence the

wave velocity, but only at early ages of the concrete. At later ages

(z 28 days) the moisture effects are not readily apparent. Twenty-eight-

day age concrete produced wave velocities from approximately 3,000 to

6,000 ft/sec depending on the concrete proportions.

6. The modulus of elasticity of moist-cured cellular concrete can be

approximated by the relation E = W1.533 ft in lieu of actual test meas-

urements. This function appears to be a lower bound for the data of this

study. Moduli from 20,000 to 220,000 psi were measured for the concretes

studied. Poisson's ratio for the moist-cured cellular concretes varied

between 0.19 and 0.25.

7. Cellular concretes with higher cement contents than other cellular

concretes at comparable densities begin to stiffen earlier. Based on

Proctor penetration tests, no measurable resistance to load was encountered

before 7 hours age of the concrete regardless of its proportions. This

stiffening may be accelerated in prototype situations due to higher ambient

temperature curing. A measure of "walkability," as defined herein, may be

118

Page 121: REPORT NO. 6-763 - digital.library.unt.edu

useful in the preparation of specifications for concrete surface accessi-

bility and form removal.

8. The presence of horizontal cold joints in cellular concrete used

as backpacking does not appear to be a problem. The benefits of surface

roughness and special curing during joint preparation are minimal. The

as-cast roughness with air curing should be adequate. Additional free

moisture for curing a joint is not recommended.

9. Density increases, which result in strength increases, do occur

with increasing lift height. This is due primarily to the change in air

content brought about by the compressive action of the superincumbent loads

while the concrete is still in the unhardened state. Lift heights should'

be restricted to some value that is consistent with the allowable stress

differences (brought on by the density changes) that the backpacked liner

in question can accommodate and the quality control that can be achieved

for the cellular concrete placement.

10. Elevated temperatures can cause collapse of the air-bubble system

of the cellular concrete while it is in the unhardened state. This col-

lapse results in localized "potholing" or general subsidence of the un-

hardened cellular concrete, which produces density increases and hence

changes in physical properties. These elevated temperatures can be present

in the air behind sealed bulkheads used as the formwork during placing of

the concrete. They can also exist in the lower regions of a lift of un-

hardened concrete that is either influenced by the heat of a hardened lift

of concrete adjacent to it or by the temperatures developed in the new lift

itself because of excessive placement times. The problems can be avoided

by using (a) cooled mixing water and, if possible, cement, (b) minimum

handling and placing times, (c) low heat, coarser ground cements, (d) re-

stricted total placement times to periods that do not allow internal tem-

peratures to become excessive, and (e) adequately cooled (by air blowing)

surface of adjacent sections of hardened concrete and the ambient air in

which the fresh cellular concrete is to be placed. Care must be exercised

when using approaches (a) and (c) so that the stiffening behavior of the

cement paste is not delayed beyond the time when the bubble structure of

the preformed foam begins its normal breakdown.

119

Page 122: REPORT NO. 6-763 - digital.library.unt.edu

11. Cellular concretes at densities less than 35 pcf are extremely

vulnerable to water infiltration at very low pressures. At densities from

35 to 70 pcf, the concretes are still quite permeable, the permeability de-

creasing with increasing density. Saturated backpacking loses its deforma-

tion capability. The flow of water into cellular concrete also tends to

erode the same, thus damaging its structural integrity. Waterproofing the

concrete improves its effectiveness at lower water pressures, but by itself

is not a solution to the saturation problem. Structures backpacked with

cellular concrete should be built in media where there is no water avail-

able for saturation of the concrete. In a water-bearing medium, water can

be prevented from reaching the cellular concrete by using conventional con-

struction techniques.

7.2 RECOMMENDATIONS

Additional information on the physical properties of cellular con-

cretes made with different cements should be developed. Emphasis should be

placed on cements that are coarsely ground and whose constituents will

produce low-early heat.

The effects of concrete and curing temperature on all aspects of con-

struction to include rate-of-hardening and physical characteristics should

be studied in depth. Criteria for cellular concrete backpacking specifi-

cations should be developed.

The effects of rate sensitivity on the performance of cellular con-

crete should be explored for the entire range of rise times, amplitudes,

and durations that might be expected in a prototype situation.

120

Page 123: REPORT NO. 6-763 - digital.library.unt.edu

APPENDIX A

DEVELOPMENT OF A LABORATORY TEST METHODFOR LOW-DENSITY CONCRETE BACKPACKING

The following observations, reasoning, and experimental results are

presented as an insight to the development of the test method and proce-

dures used in the study of cellular concrete when used as a backpacking.

These results and suggestions can be readily extended to the testing of

other types of backpacking materials.

A.1 CONSTRAINMENT

The behavior of backpacking when subjected to shock-wave loading is

complicated and has not yet been precisely defined. The following observa-

tions as to expected backpacking behavior are somewhat simplified but can

be considered adequate as a first approximation.

Consider the backpacking as completely filling the void between a

buried structure and a rock opening (Figure A.l). The backpacking will be

constrained at the outer surface by the rigid rock mass and at the inner

surface by a structure that may vary in stiffness from flexible to very

rigid. The traveling compressive shock wave in the rock, impinging on the

rock-backpacking interface, is partially reflected, thus establishing ten-

sile stresses in the rock that will cause the rock to fracture. The frac-

tured rock is imparted some kinetic energy by the shock wave. It then

leaves the interface and moves into the backpacking until its energy is

dissipated. Some translation of the structure may also occur. In both

cases, crushing of the backpacking will occur at the interface of the mov-

ing element and the backpacking. More severe rock fracturing and back-

packing crushing would be expected at the interface of first contact by the

shock wave than at the opposite side of the section.

Because of the speed of the shock wave, the entire backpacked opening

will become loaded in compression in a very short time interval. The uni-

formity of the loading across the opening is dependent on the decay history

of the loading wave. A reasonable assumption is that the entire section

will be loaded in somewhat uniform compression shortly after initial

121

Page 124: REPORT NO. 6-763 - digital.library.unt.edu

loading and at a time when the fractured rock elements will still be driv-

ing into the backpacking mass.

Neglecting translatory motions of the structure and the fracturing of

the rock for the moment, consider the backpacking to be a thick-walled

cylinder of semi-infinite length behaving elastically under both internal

and external compressive loading. From Lame's equations for thick-walled

cylinder stresses (Figure A.2), the general case for tangential stresses

can be expressed as:

2 2 2a iri porn (i oroi 1 (A.1)t = 2 2 + 2 2 (

r - r. r - r. r

where

p. = internal pressure

p0 = external pressure

r. = internal radius

r = external radius (r > r.)

r = radius to point of interest (r > r > r.)

Rewriting, where pi = p+ 4

2 2tpr. r

at -po + 2 2 1 + (A.2)ro - r.i ro- 2

= -p + K(Ap)0 -

where 2 2r. r

K= 2 1 +2(A.3)ro - r.

o i r

K = a positive constant depending on cylinder geometry and pointof interest

The sign convention is that a positive sign indicates tension while a neg-

ative sign indicates compression.

122

Page 125: REPORT NO. 6-763 - digital.library.unt.edu

When p. < p0 , at is always a compressive stress. When p. > p ,

Ap is a positive value and at may represent either a tensile or com-

pressive stress, depending on the relative values of p and p. for a

given geometry. It is expected that the resistance offered by the proto-

type structure (and represented by p.) will be something less than the

shock-wave overpressure (represented by p0), hence the first case will

prevail. An element of backpacking at any distance r will then be sub-

jected to compressive tangential stresses.

The use of Lame's equations infers that the internal and external

pressures are statically applied and of known constant magnitudes, where,

in fact, the inferred situation exists only when any instant of time is

isolated and the pressures existing at that time are determined. For a

finite time interval, both p and p. will be continually changing and,

hence, so will at . The sense of the tangential stress will remain com-

pressive, however, regardless of its magnitude.

The compressive tangential stresses have the effect of providing some

lateral constraint to a backpacking element that is being additionally

loaded by the driving pieces of fractured rock. To reproduce realistic

compressive constraining stresses or forces in a backpacking evaluation

test would be difficult in view of the many variables and unknowns asso-

ciated with each prototype. A simple solution, and the one pursued for

this study, is to use cylindrical backpacking samples and enclose the

sample in a steel pipe. The steel pipe, being much more rigid than the

backpacking, resists the lateral expansion of the cylinder once loading has

begun and thus provides some degree of constraint to the material while it

is being tested.

The actual relation between the prototype compressive constraining

forces and the constrainment provided by the steel pipe cannot be defined

due to the lack of information on prototype behavior. However, it is be-

lieved that the overall effects of constrainment by the pipe contribute to

the performance of the backpacking in such a manner that the results ob-

tained from this type of evaluation test more closely approach that of the

actual behavior of the prototype backpacking than if no constrainment were

provided at all.

123

Page 126: REPORT NO. 6-763 - digital.library.unt.edu

A.2 SPECIMEN AND TEST PREPARATIONS

The cylindrical specimen of backpacking that is placed in the con-

straining pipe should be of a size that is conveniently available to almost

anyone. For low-density concretes, the 6- by 12-inch cylinder is an ideal

size. Standard cylinder casting procedures can be followed for these con-

cretes with the exception that the concrete should not be vibrated or ex-

cessively consolidated.

The curing of the low-density concrete cylinders should not be done in

an environment where free moisture can come in contact with the concrete.

This includes moist-curing rooms. Because of the porous and absorptive

nature of these concretes, free moisture readily penetrates into the con-

crete and fills the voids necessary for satisfactory performance as a back-

packing. The concrete should, instead, be cured in sealed plastic bags.

Shortly after sealing, the humidity in the bag approaches 100 percent and

the specimen still cures adequately with no additional free moisture being

added to the system.

In preparing the cylinder for testing, the top and bottom 3 inches of

each cylinder should be sawed off and discarded, thus avoiding surface ir-

regularities due to casting, bleeding, and handling. In most instances,

the sawing can be done with a handsaw. Care must be taken to ensure that

the ends of the cylinder remain perpendicular to the sides.

The confining pipe should be of split-wall construction (Figure A.3)

so that the specimen can be easily enclosed in or removed from the pipe.

The pipe requires a nominal 6-inch inside diameter and should have walls no

thinner than 1/4 inch. Closure of the pipe around the specimen can be ef-

fected by two closure bolts set 180 degrees apart at the midpoint of the

pipe height. Other arrangements are also possible. Reproducibility in

testing can be achieved by torquing each of the closure bolts on the pipe

to the same value just prior to testing. For two-bolt closure (Figure A.3),

experimentation has indicated that a closure torque of 5 ft-lb was adequate

to obtain reproducible results with a minimum of additional triaxial com-

pressive forces due to the torquing. If desired, the constraining pipe can

also be bolted to a fixed baseplate.

124

Page 127: REPORT NO. 6-763 - digital.library.unt.edu

After closure of the pipe is complete, the specimen is ready to be

tested. This is done by forcing an appropriate piston into the concrete at

a desired rate of specimen deformation.

A.3 PISTON SIZE

To represent the rock fragments that will be driven into the back-

packing, a loading piston with a flat, circular end area was determined,

from practical considerations, to be most desirable. Three different

size pistons were studied: 3-, 4-, and a nominal 6-inch diameter (Fig-

ure A.4). The 3-inch-diameter piston was also studied for two-side taper

configurations.

By forcing any of the pistons into a low-density concrete sample at a

constant rate, a stress-deformation test record similar to that shown in

Figure A.5 will be obtained. Stress is determined as the load acting on

the area of the piston face; and deformations are determined as the dis-

placement of the contact face of the loading piston into the specimen with

respect to the original height of the specimen and are usually expressed as

percentages. This constrained stress-deformation curve (Figure A.5) is

characterized by four values of the curve: (1) yield stress, a ; (2) de-

formation at yield, e , percent; (3) average stress Q0.40 between E

and 40 percent deformation E0.40 ; and (4) stress a0.4 0 at 40 percent

deformation. The values of items (1), (2), and (4) can be read directly

from the test record. Item (3), the average stress, is determined as:

(area under curve between Ey and E0.400.40 1O 0 .4 0 - Ey)

One mixture design of cellular concrete was selected for the piston

study. Three rounds of concrete were cast with samples from each round

being evaluated for each of the piston configurations. The results are

shown in Figure A.6. The deformation rate was 0.3 in/min.

The results indicate that higher stress values are achieved with

smaller sized pistons. The test records also reveal that the 6-inch pis-

ton tests "bottom" at smaller deformations than the other piston tests.

Figure A.7 shows a typical set of test records for the three sizes of

125

Page 128: REPORT NO. 6-763 - digital.library.unt.edu

pistons. The taper effect on the 3-inch piston did not significantly af-

fect the test results.

If the mode of resistance of a test specimen is only normal compres-

sion, the magnitude of the observed stresses should be the same regardless

of the area of the sample loaded. In the case of the 6-inch piston on the

constrained 6-inch cylinder, normal compression was the predominant resist-

ance mode. When the smaller diameter pistons were used, the test became a

punching test and the resistance mode became a combination of normal com-

pression and shear accompanied by horizontal compressive components due to

the constrainment. It is this combination of compression and shear that

resulted in the higher observed stress values for smaller sized pistons. A

penetrating rock projectile will be resisted by both shear and compressive

forces and, hence, would be best represented by a punch-type test.

The bottoming of the stress-deformation record occurs when the slope

of the crushing plateau begins to increase rapidly. Ideally, this should

begin to occur when most of the voids under the loaded area have been

crushed and the remaining solid material begins to resist compression with

little additional deformation. Some increase in the shear resistance may

also develop and, in the case of the 6-inch piston, may be the predominant

mode of resistance. The frictional sidewall resistance that develops when

the 6-inch piston is used becomes so great that the lower portion of the

specimen is never deformed. This does not produce a desirable test result.

The sidewall friction effect will probably persist even when the piston

edge is moved slightly away from the constraining pipe. For this reason,

5-inch pistons were not considered.

Based on the above observations, it was believed that a piston that

loaded the most area so as to obtain the greatest compressive resistance

and yet minimized the sidewall friction effects so that a more realistic

bottoming point could be discerned should be used for the test method. As

the 4-inch piston as shown in Figure A.4 appeared to satisfy these require-

ments, its use was adopted.

A.4 DEFORMATION RATES

The rate-of-deformation studies were conducted using a 30,000-pound

126

Page 129: REPORT NO. 6-763 - digital.library.unt.edu

universal testing machine operated at controlled rates of loading head

travel. A 4-inch piston was affixed to the loading head through a ball and

socket arrangement that allowed easy alignment of the piston. The same

cellular concrete mixture used in the piston size study was used in this

evaluation. Three rounds of 12 cylinders each were tested. From each

round, three 6- by 6-inch cylinders were tested at a base rate of piston

travel of 0.18 in/min and in accordance with procedures discussed above.

The remaining nine cylinders were tested in groups of three at three dif-

ferent but faster rates of piston movement. Figure A.8 shows the test re-

sults. The strength ratio is the value of tha average stress to 40 per-

cent deformation, Q0.40 , for the faster rate of deformation for a given

round divided by the corresponding value for the base rate of that round.

Only at rates of 10 in/min or greater did the mean strength values at

faster rates of deformation become significantly different from the cor-

responding base rate values. The data in Figure A.8 indicate that a

strength increase with increasing deformation trend is developing as was

expected. For testing purposes, it is suggested that deformation rates be

kept to less than 1 in/min to minimize the deformation rate sensitivity

effects in the concrete.

127

Page 130: REPORT NO. 6-763 - digital.library.unt.edu

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ,~ G R O U N D S U R F A C E

ROCK - .-

- -BACKPACKING

STRUCTURAL *"L INER **

- - * - 0 e " ,,' **L /NER

0 o 1 / , OPEN/NG

0

Figure A. 1 Rock-b ackpacking -struicture configurati on.

Page 131: REPORT NO. 6-763 - digital.library.unt.edu

Ur +dCGr

FOR A NONROTATING CYL INDER

_ irt Got+(P-Ptrzr

N+

rir ri-r2 r2

- Pi r-Pro (Pi-P )r2 r?c0r- r r - r2 r

Figure A.2 Thick-walled cylinder stresses.

Page 132: REPORT NO. 6-763 - digital.library.unt.edu

. c r A t '2.wri1 ~l1 "Y.iE

- xc ~ -I- ~%

Figure A.3 Split-wall confining pipe.

wii

I

----tl'rI"'rr-rtrnfrWtStStfhfMSuittarar4~LL~fl~IUIUSPSISr

Figure A.4 Loading pistons.

130

IK /44

wi

Page 133: REPORT NO. 6-763 - digital.library.unt.edu

0. 4

ui o.4

z

Er 1 0(40E - Ey& E0.40

0 10 20 30 40 50 80 70DEFORMATION, PCT

Figure A.5 Typical constrained stress versus deformation relation.

3 0 0 ,

I-ZUbJa -

0z

I-

()Wi

w4a

OA

La i

zoo

100

0 8 16 24 32 40

LOADED AREA OF PISTON, IN 2

Figure A.6 Effect of piston diameter on stress.

131

Page 134: REPORT NO. 6-763 - digital.library.unt.edu

500

EACH CURVE WAS OBTAINED /USING A DIFFERENT DIAMETERLEADING PISTON

400

//

300

BOTTOMING PO/NT3-/N PISTON

200/

4-/N PSTON

6-IN P/STON

100

010

Figure A.7

20 30 40 50 60DEFORMATION, PCT

Effect of piston size on bottoming point.

I I I I ' ' I I I II. I I 'I 'I ' I ' 'II I ' I 'I

0.5 1.0 5 10

DEFORMATION RATE, IN /MIN

Figure A.8 Rate of deformation effects.

132

,)

0

0V

70

1.2

<i.Lx J

z

Z L .

-0 0.

0.8 L0.

_ _ ---- - - - -- --- ----ii ____IT- T --- + + - +

50

0>

,i

Page 135: REPORT NO. 6-763 - digital.library.unt.edu

APPENDIX B

TEST DATA

133

Page 136: REPORT NO. 6-763 - digital.library.unt.edu

1000

800

0600

004

200

0118

- T4

- 4 -

i.ti. T

S + f + - - -.-- t ,+-.-' - .- - -- 1- -t - - _ h- - . . _--- -+ - . - - - 4 - , - - - - t -} - - - -a- r t . 4-t f4f-

-- -a- - - - - - -- 1-4. +

- j a + -- a -- - t t .- - - - - - -l . -- a-. - -- r . - - - - - - - -- _ _ - - -- - -r - - - "-- - -. . -' r r - Y . ,- t r +. + - t . - - - - - 4 + -

. }. --- + i - - r-- r ... . + ----.---- 1-----. t . . - ---..---- }--1- . - 1 r . ... , Y--. .- 1 - ---- { -r- -

i4t.. r t - -* - ' - - - --- * - - { - - . - ' - - --- F r-r 1 . *--- - -_ ' -. . . . _ ' _ -- ' t+- . +- -++ -- . -- 1- a- T -- t --

-- - 'tI 41 "rh+t 4 4+.f +

- ; , .. F . .. r_-L+--.1 -+ -- -- . .-.-- r - -. - -- 6 t r -. , . -:--1- - r

t }+--

.- J- }:1 -: . . .. .. . .

4':44*1

t$'Kr ittLI4'

r r-r r 4 t+ +. S Y +.1 -? Y

22 26 30 34 38Freshly Mixed Density, pcf

46

Figure B.l Yield stress versus freshly mixed density relation forcellular concrete with an 0.66 water-cement ratio.

50

Page 137: REPORT NO. 6-763 - digital.library.unt.edu

1000

22 26 30 34 38 42Freshly Mixed Density, pcf

Figure B.2 Average stress versus freshly mixed density relation forcellular concrete with an 0.66 water-cement ratio.

-T -F .. ... . ... -.----------

..91

... - ..... :.... ...-...--. - .+- .- .- ..-.- . -j-.- - -- - .- - - . --. -- - -. - -- - -- ".- --- I+- -- ---

I --

-= -_. . . - -. _ _- - - - - - - - - - - - - - - - - - - - - - - --- - - - - - - 1i

I -- - --- -- - - - ---- - --- -- - -- -

t -~ 'it t

...---

- 7 -: - -'..j..' - ---- --- ---- -- t > ----- -- -I

- - -- - - - o -- - - - -- - - - -- - --- - - -- - - -- - --- - -

-T - -- ---- ---" ---- ---* --* - t -L .I- . -- -- -- -- - -I-- ' -T 1 .---* + T * t

0800

0

a" 600

4

0

00

4"

al)

bO0

w 200

j1

018 50

3

Page 138: REPORT NO. 6-763 - digital.library.unt.edu

~- - - S- - - - - - - --4;

1000

800

. i

.. :__. .. S

. .

,

. , .d. .

.. . . ."

:1 . : . ' :

: . ;__.

. .; ....

..___.

:; ' ; . .

, . . . .

r : . . .

,..

...

. ...

i...

:_ _1_:..

. .,.. ..,...

.,:. .. .

t

{~~ 4$

_

. ,

y

.:

. ,

1

+ i t j _,

!,ii.

.r ,

.,,, 1

,.

4.

-44

*1T

- - . ----- --- --.-.- ------11 T-.

- .. . _ . . . . . . . . . .- _ _ ", .'_ _.-._ .a -. . ....._ -__ _ 7:-+ II : 1 4: : , .

- -- e--I---i-.--------.-. -.-- --. 1--- - n-n---e-..-----s--e---. -- ---. -- -. - --

1- . 1

.. ... 7

I.t7. I1II .j . . ,. I: . .

22 26 30 34 38 42 46Freshly Mixed Density, pef

Figure B.3 Stress at 40 percent deformation versus freshly mixed density relationfor cellular concrete with an 0.66 water-cement ratio.

-

/

HW-

S600

eOI400

s200C,,

0L

18 50

T

i

-- --t-- i -- f i a I e l i . 0 ! 1 , , 1 1 ! , , ! 1 1 1 !

.

. I.

.i

. .

..

. i..

.:.1 .

. I.

' T

I i - i - . I . , - I . , I ,' .- 4----- i 1 i or--- -4- A W 1 A I - - - 1 : - I . . -+

-V V

-- - -

.... ,

}.

.. ,..,

,

-+ ,

_a a

.. .

i ' '

+ I

.' 1

77' a J .,

i r ..

- T--

. .

+ .

" .

. _ 1

t a

I''

Page 139: REPORT NO. 6-763 - digital.library.unt.edu

1000

800

22 26 30 34 38Freshly Mixed Density, pcf

42

Figure B.4 Yield stress versus freshly mixed density relation forcellular concrete with an 0.76 water-cement ratio.

. .. .:a . . .t- l . +; 4 et -+ :-t 4 4-+ - - - i 1 - -2 -'4-4.- + - - -4'2-

.a..J....-...-...

1 4 -I

- - - - } ^ -- - -_ !-... _ I I - - _ _-- - " - - -- { _ . .-- _- - - - -*-'--- - --- _--- - - - -- -.-- - - - r- a -- ----- -- ----e -.-

- . . .4I

V.- i I-tt V;.J14.lr'

;7-: .A .. .| . -- -- -j-- .-

- -. 44 - . .- .- - - . +'-

- -- + a-j -- -t

- - -~~- -~ --

I I i'

. .

. .1 trt:t.

4. . . -

__ _ .J.L --- -'

.94m

6000)0)0$44.'C,,

V"4S~ #00

HU

200

018 50

Page 140: REPORT NO. 6-763 - digital.library.unt.edu

q - p , p .,, p - p .,. I - p - P I.4 -

. - - . - -

S .. . ..... . .

1000

+I-

---.. r .- -

" -1

4

aS0

* 800

04600

4'

00

t-i 4 .

I1-1

| ; 1 --.-

1

I

I

30

.: .

4Tf

C _4 $; .

9.II .

.. 1 ,

,.. ,

.....r.._ .

...

.. ; .

;_ '

.. ., ..

... .

I

_:_: _._I :... --

.,.

...

. ..

. i. ..

: . j : .

... :';

_. _._.r r_._.__

.... ; ..... ;..

:.ice* .7

. .f

. . ; . . .

34

.. . . . .-- -

.1 4

:.J:

I _

"

: .

. i . ,

.

___.

. .

. ..

__ . _ .

.

,.

. . .4 . ..

.: . . . .

>2Ii. 4K

.. f.t t

-r

1-- ................-- -T-

IT T I

iP-1 - -t

38

...

-i -t7

,.-F. i .

46 50Freshly Mixed Density, pcf

Figure B.5 Average stress versus freshly mixed density relation

for cellular concrete with an 0.76 water-cement ratio.

-

-

I

r

.

I '

. .

_ _ L

:'.I .

. j.

.

{i

I.i .

:__. i. J

. :.:

. .

.,

. . ..... ,. ..

. -_.

~

. 4,

.'.' .:

4 . T

4i .

S\.0 WjtLoA D tt61

.. .

:I;K

-~1 -

-+t

! !

4 i s

-,-

...:I

...

-, -} .

... 'i.

. r .

. I .

... _L

: ..

..

'

,:T::,:. ....

F .....

... . .

... .., ::.

.. .

-_.-._-- .l..Tr.

.

f r

I .

.4

I-

00

i I

.

_ .. . _ I_ _ .. i _ ._

. i I 1 .

j

I .

.

I I I I .

1 1 .

i

1

I

i 1

.. ... .. 1 _. .. ._. I _ ,

I .

i

,.:..I..:'I.

. .

;.. 'Q

.. ... ..

-, 4

tt-i

'tI018 22 26

-7-7

- .-- ' -I I }L___ _ r " . ... N r -= u F ." " w i 1- -- =----- ---.- ...-- -- _ .

- ---- ' -- f-r--- '-}------ i-

4-'l. . - I I - -:.rTr-- -i------- ------ a-

_J__ .__.___} ______; !- - Ti

it. - . I . - I - . I . I . . . . . - .. - , . - I I I - . . - . I . obawAsumbloftLI ; i

1

[ ; : . _ 1 I i

ILI-L

L.- I4-

* 14~

_. 1 t1 _.1

ttt

Page 141: REPORT NO. 6-763 - digital.library.unt.edu

1000

800

26 30 34 38 42 46Freshly Mixed Density, pcf

Figure B.6 Stress at 40 percent deformation versus freshly mixedfor cellular concrete with an 0.76 water-cement ratio.

density relation

4-- -- ----- -f ---1---- I

. -- - - - -- - - - - - - -- -- -- - - -- - - - -- --. -- -- - -- -e - .- - -* ------ - -- -4 { - - _

- - ---.. :. .x. .:.:.:. .__

--- ------ --- -t---- -- '-i -- -- -I

-4-.--- ---- - r - -- * -- -T- ----

-I -- - j--

1 $- -'+1- -----=- --i a .--t . --4 - ---- -t - , -' ! -y ?- -

- r * -.. '" ---*' ----t . -' ---.--t -- -. ' -r --L --:-i-

HWo

g* 600eM

0

41

400

4.1

iw 200

0183 50

Page 142: REPORT NO. 6-763 - digital.library.unt.edu

500

400

- -1

_ I

4 I

- 9

44

I I t

" -

-I

. .. - - -

-4 . . : - .-S... .,

22

jc Li ~

-r -

f .

x1,11. 1

...

.1

.

}.t. . . I

_ -1 I .

s +. -.. _ L.

I '

. _

t _.i. _: 1

1 .. .. .. _

+_ ..

-"

.. .

:l ....

.7

. .

j . ., i

.

- .-- -

4-.

11

i- !i- -V" --.126

- -1-

.-..

----- .

. t ! .

" .

.

. , i .

.... s_

=:.. ,

:: ::

::; .

.fi.

I .V

.: :

.,

,, f

.;_ ; .. ,

- ... .

.24

1-

. .-4-.1 + .

4-1-

14 i i

_ ._i __._ . 1

. .

I .

:

! t._4 _ -._1 .

.4._

...I.. .

- -

.. :;.

..

. , .

::

.

. . ..........--.. .."" r- 7- -

-- 4 --- 4 ---- --- +- -' -=-i '

-- u u u --.

---+ --; -.T _ _ .--- --f- ---'i i i i a |

' 1 + I II i ! i t I I i I i 1 A : 1 1 1 I II-

T.

? 7 ; ' TTF f i1 .}.iyl

- --- - -i+-

-I -- - r - -.;C - i ] I- ?"- -.-.-- - : y iIi T 111

I1 - - . - .t -

_r --- i -=-li - Igr -r a-- I i 1"' f f y rt-. "- ._ :- } I } f I I I I i' I I I I I I I -- --

---- -i r -- : ' ------ I -1----4- ------- 4-+---r---i-i----- -T T --- +----;- -- r--------f 4-i- - +H.

S-4- 1-

- -_ --. . - + . - f l - 4 + - - ---

. .. .. . . . .. . I ? I r i ! I I 1 1 1 i I I I I I w 1T ii !II IT ,IT.I I I i I ' I_ Ii L ' 1

I

Ask" ()

. . ; .}

; i..

;. .,_

+; .

... ,

.,..

... ,

.:

Fr.

i:::;:}:i

. ... ., ,,.i

. . , .. .

.H ..

:.:.

:. ,.,

_

.

.. ,

.,...;

F .;

.1.; -I

+ -,.

,.

. . ;.

Y '

-e f

r

'r ;

" r

i , .

- i-

l

" 4-: I

il1

I

F -

I

I

I.

1

i.

I -

--

y,{ 1

. .

i .

w

H

0

...

1'

.: ,

' {

I I

1

T

1t tt

'

_.; .,

. ,

i,

. . ,

.;.

-- r-r-

; ,

;_:._.

.. .

- -L; '

.e, ,,+ ,

f ; 1 . _

. ,

- 1" ..

i _

4 I

",-

. j.

;..

_.j

1

f

1 L

i

L 4:._

r y +

1 i f

. .

.t ;T

- -. -.. ...- - 1 ?

i . ! ti.::

.

.-

50

100

18 42

Figure B.7 Yield stress versus freshly mixed density relation for

cellular concrete with an 0.86 water-cement ratio.

- - -

- - .-- ---- - . - - -

. . . 4 .-t

+1 1.:

-

J.J

i

Ia ;

-

=#

1t

h+

i : ' t-

.. a

.1 - r

4 ,

1

"t-r

' f -

} I .

1 .4

t T

.r.4

-4*

- -U,3 0

200

.. rte .y.. Lam,

'f

L i

.

y

.

J

,

+ 1

.

.

1 i

--T

L

1 .. .-

a -.

:,i

t _C

.

_ .

i-

.

--.

i -1 -

h + -

T If

F t

Ir

ft

I 4

.. d.t'1

J .1

rlJ{

a

-F--f tt

T- 1

r

-t -

F

30 34 38

Freshly Mixed Density, pc f

Page 143: REPORT NO. 6-763 - digital.library.unt.edu

500

* 4&00

0.

300

4.'

0

'" 300

d

0

loo

I~~~~~~ ,. YF,1 1 144 1P.1 11* ,4I44I.!.44P

. I.t--. . -I 1 . --- - -

.'.... . .f..4Ii-f-j-14 t- t1H P

...1 +

__41.

4 4 . .

4 4 I--

-- - - -- - -

*1- l -

4 I

T -j

I'! I

-~ ..-.. -;. - - e

4 -... 4 I

-71 1

- -K- 1 --.-

- - - - - -...1 .

! 1-;i-K-1J 1

- $1 + 44

_ Ti

" i

. .

J _.

- r

-

_+ ;

-4

-.---

4 :

--1 -1

-r- -'

K

it,..

i

J

.

- J-r:

I :;i!

i-,ar

1 - -

- -}

-- .

-. -- -. -- ;. .

.1 Y I

I

1

}.

" {

1 I 1

f

-

K--4-

44-I

K It4

1..

4.I

- +

ti,r.

.,

-- _ - i ,

.. ,,I

L

44-

_i..J -

-Ti~J -T i !T* I'-r 1- :

-

-- L

-. .- +

yt - t

it-

-. -1 '-- -

-

~1--f--r

-+

-.

.4

,.;K

- .4.

l" 1t1 -. . .

-

- -f -t -

-L--

Lti

-_ 1

- 1 4

+ -'- -'-4 F I

ttt

-2-

,

IJ-

t1

- ,

.I . ! . - . -

I - -4

WIH-.i;t-

-I - -

- - -

4i4-

--. t t 1- -_ 1-i t ;

- t

-

-

4

-4- .

- -

-1.4.-

-j.

1--

If--

-4-

- I

F--41I-

-+- -

- 44

I -

. 4n-

4 - -

4 .. . . .'. - - S _ _ '-* . ' - . , ar

22 26 4630 34 38Freshly Mixed Density, pcf

Figure B.8 Average stress versus freshly mixed density relation forcellular concrete with an 0.86 water-cement ratio.

-. .-.- f.. ..4.. ... .--. .

H

H

4 - --4 I

-$

i-t - i l

}-i

}-

14--4-

-r

-tJi 4

a f"

i

1 ! .

j ,

- r 4 ! !

I,:t;,

i 1

--lt

18

t -4 -

-414

+1-

1--

1 i t

-i -

-ir-"4

-

so

I . .. . .. .. . .. .. . .. . .r7r

--- - - I 'lII i---t---- - ' - -

- .._! . :-fi

dq--- , = ZF = 0 xf - , . Z i I I ZF m i a 4 A . . i . K i : ! m ! , 1 ! , i ! 1 -. m ! , 1 ! " I I ! 0 ! 1 ! ! . 1 ! ! a 0 1 1 ! ; mI I I I i 1 1 1 i t 1 I l i ._P 11 4V-# r

i i

T- - -...- --

r l 11 1 I I l 1 1 11 L 1 1 _111 111

rTTT771TTT

-_ _ - a --- r t 1 1 4

FA

." !____

4

__lI_]__-

- ... --.- ! . ---- - --- -r----}-; - - - --- -- - -- T--- ----- ;:} r - _ -_ - - -- ,F 44+ ++ t+ + ----f

HH

.--- ---- 4

- -

. -

.. +

i'.I'

._ .

'i

. -

: I..

1 1

-

i 1

.

-

.- =

__ .1T

1

+ -- -- + -L 44 i t

a J

4" t -j

" r "

" t

. 1 J

l 1

1 1

"

1' +- -

T

1

T .

L J

r

::.

.,.

. --

;.. ;

"Tr

ZI _

l .. r- -

.

, .[' - .

x ,..

i..

_ ,. i

i ..

lrr * i

.

i- .

... i.

.,.

.

... ,

..

.. i ,

.. i

-

714i t.. t r. : 1 r l t t r

I IT4 4 !1 t, t'

-f

-i

4

- --

Page 144: REPORT NO. 6-763 - digital.library.unt.edu

500

400

300

4'

0I

H A

200

100

0

16

- - - - - -_-- - - _ -_--.- - - - - -_---- ------- - - - ." - {} -

- -- --- ---

- 1i. -....-..-

---- - - - ---- - -- - ------- ---i , I -- - - -- .r r a - - ----- _ "

_ __ _ __ I _ _ _ _ __,

-. . -..- - ri "--t . I L 1.. 11 .- - - - r t , . T-r- -- --

} j- 1- - -- - - ~ -- - - ---- -- - - + -

.. .+ t- r 44 -1 -F JT + 1_ u 1

TIT L+

- .4 1: . i - t - -t- -T

- 4 t4. . . . - - . . . . . . . . - a -. t -- t -i

22 26 30 34 38Freshly Mixed Density, pcf

Figure B.9 Stress at 40 percent deformation versus freshly mixed density relationfor cellular concrete with an 0.86 water-cement ratio.

503

Page 145: REPORT NO. 6-763 - digital.library.unt.edu

500

400

26 30 34 38Freshly Mixed Density, pcf

42 46

Figure B.10 Yield stress versus freshly mixed density relation forcellular concrete with an 0.96 water-cement ratio.

. :i.-F -r -r ---~ -.T-t-rr+r- -

4 4 t. I -, .+.+ .... . -. 'I -i i-

-+-- --

t --

- + I - -I 1 4t. . . -LI. . . -+ - . - . ..- -! [ --

1 }- .r ---'-.N'4 -t t-1 r-.!J- -.- -J--,2

+ - - i - , - - - - -i - - -- -- ' + - ' ~ "

-t : i t+. + .14i.1.-

- * . a , . ---.- t . +l-+ r+- - +-t . -1-t- -

- ------'- -. -. -- --- L d-. - tt4 tE - --- 4 +1 - -- .- . ---- - - -- - - - - --- -

.r- l - -1-{-4-.. -1-- -- -- -- + T .4 { t-r' --, --.- -. .. ++

1411

77-

!- +- 1 -. - - - -- }- + - - +.---. - ' - - .-- - ' '- - - - - -J -,_ +-+ l-t -- +- y 4t- - +.--+ -

- -.- 7--l

Frrt

.11

- - - - - -- -- -- - -.-- - - - - - -- -- -- - -- - --- 4 t- H+- -

- - - - : - - - - - - - - - - - - . - - -- 7 7- - -7e -4 - +

.940

30000a,

"4

200

H

W

100

018 22 50

Page 146: REPORT NO. 6-763 - digital.library.unt.edu

500-i I - - - - - - - - - - -

1 --J 'v-~-

V ~ --- -- -v- - -'

- -I. I-- ---- -- --j- ---- ----I- - - -

- - - -- o- --

--- -- - -- - -

-I- -

- -1;

Il1l

!I.

ag 400

g.F1

0

4, 300

0

0.200

UU4

id

18

- -

-I--H

1'-

I i i - i

. I

i

. _ _..' i .... ..

i

.

. .. _ 11

. i

_ . _.....1_ __..

I

..

l

" I I

"--- - -- t-+

. ..

I "

. _ ... _ : __, y

i

. _ .. 1

j . . I

I , %I

f._.. _ .. . . i

_:..:. ,

.: I

;.

-,-----

. " -

22 26 30 34 38 42Freshly Mixed Density, pcf

Figure B.11 Average stress versus freshly mixed density relation forcellular concrete with an 0.96 water-cement ratio.

46 50

-f-:-

- -

-H

- -

Page 147: REPORT NO. 6-763 - digital.library.unt.edu

500

400

22 26 30 34 38Freshly Mixed Density, pcf

Figure B.12 Stress at 40 percent deformation versus freshly mixed density relationfor cellular concrete with an 0.96 water-cement ratio.

4- L. . . . r . - " = .-.. -t ..-.- t .. - :.L-. '- - . i -- +. - . - i t 1 t r 4- - - '-1' - - - - --. S --- +- -- -

F r , !' '.m-

. - --- f+ - - - 4- - - - -i . -- ] - - - - - - 4 - - -- - - t - - -- - - - . .

.. . -.. . . .. - . p '- . . ..- _ _- + _.--... T+-- - - -_-. t-e. .r ' F -- ' . -+ L- - - +"4.. . -..- .. t -F --- * --

r _+- F-- -- t -- it - - - T- ' ' i / * -+t-4---# .- i -' r .' _ }+r-i r- + --. $-r-- +- - -f t- --- - - -- r +- -- - - - --

S . - .+ . . - --r- + + ----- - -t--4- 1 -t----- , -- - --- -

L+- -

y - -4-*-tL'+- ' YT- -1}-' r1 y' 4' * ---+ T-'t --r1T _-r .-- --+-ri-- -*- r --t --

V i -i4_-_,.. . . . - -_ - ---- L - -- -

T74h.d

rW-__t..

. r.1...}. . - r a- .r. a-----.-+- - -r-t - -- + . - 4 -t * f-. .r- -+r -T y r t, - t-- r--L- - - -- 4.---- - -- -

L -4 44i

- . - -, - .-. .- . j . . -- - -. .,---.L----a . -.[- - - -* ---------- .- -------+ .- - - -- - , ---. s. .

T17-

1 w7 11+ t+ 4Ltrf- --~tt 4 tip ~ 4 ftVat,

7 7 ~ -F

-ar. ... L. .L.+-L1. -L. - -- y_ .1 ---- . .. _ -- .-- _:--_ -- t F--- + -- 4 + L -Y----L- . - - -+ - - -+

- -- - -- -+-- - -- '.- - 1- -1-'-}L-1---T-

-- - - - ---- - - + +-.-- - - - - - -- . -. - -

142

L + F-+---t. . . . . . .. l. t .-... .. r-r J - .1- }-

-4 T-_ - -a, f L 1 - - r .----- 1 ---- a -- t- - - - - -- *-r ------ -- L , ----

- -1 } + } -1t+-- + } t t i T i F1 : _; } 1 1 .- -_t 1- -* - - -t - --- -!--- - -$ - -{ +- + 1 t -' + } -'-a-.- - 4- - r - -- f.- - -- r - -: - - .

} L } r1 . t . 1 1. 4 . . . .. . .t ,- L a .G -.-. .- 1 - - j_-- -l -I - - - -1 L +- - - 1-1t - - -- - - - - - - - - - - -

.. L... .. +.. . -4 . . . . . .- .# -}- r - - ' - - - - ' - ' -- -r ---- -- -- f- --- f--_ -_- - T-

4 !-w-_ - -- 'T -ti--i-4 *- - +- L -- x _- -' ++# }t- 4 . L . t +... L '- . r-

L,6

L -} - . -- - . . -- - -. - . . - -- - -T + -- -- - - -b - -- - -+ - - - - --T r - -

t t _ - : .. . L 1 - - -t - 1 - -. i.- - - L-- .- L - F 1 - - - - - - --- - - - _ -.-- -

Lt+.- T1 + +- 1- -+-+-t - - .------ 1 - ---

-} - ---- T - - -- - --- - -5 0

30 -- 3 - --

-... . ... ... ..

H4.\Jl

830004I+0

4200

00*

08 42 46 50

Page 148: REPORT NO. 6-763 - digital.library.unt.edu

4. t .. I- - t -" - 1- .1 - 4 -4 - -f-4 i * - 'i +1 + .. . 9 ,. . 4 .. 4- 4. -4- + - 4 -. + + . .*-

- 4 4 - -- --L - .-1 - + -L- --a 4 - - -.4 - -

4001

22 26 30 34 38Freshly Mired Density, pcf

42 46

Figure B.13 Yield stress versus freshly mixed density relation forcellular concrete with a 1.06 water-cement ratio.

500

+44,

--{ _- t -a-- L . " r ! , " ' : : ' ,- + -: ------,-.- - -_-- -.- -}- + . -, -+ 4 A I +. -t -- - -- - -+ -+-+ + .J i i . - - - - -+ : - - - - - - . +-- . r -.'- - ++-r-. - -+ . . - + e+ + + - - - -+ t

- . ---- 4J - - - - ! ,4l } . - - ,--'- -1 _ j + -1 - I- - .+ - -_+ - - - . 1- 4I - - - . . - - L - . . 1. - - 4 a i Y+ L e + -+ e t+ + + r ---? T

. . .i.a-..... -..--... 1-2 .-. . - ..-- . ...-. . . . . ,---------------t---.----------

J_ - . .4 .. 1 . 4 . . 1.1 .- l "- . - . - . . - - . .. t . .. 1 - -. " - . -" - 1.- - 1t L " 1.- - t i i + - - - -i- 3 --

rttt- .JJ .. "r L. + .1..... . -..........-... ,...s...a....... +- 1. .)- .e+ I .. . r+ -t --

_. L L . .. . .. ,.. ."+. ..- ar .- .. , .. L . ... .... ...- ..-. --- r ...- "- " , t+e. -- 4 -ty t.. - !.-+.-4 -- fth - -. .J4 --- -1 V-. 1 +- T ! - - - + r o e 4 - A i e -' - - - - y - - - - 9 - - - - -* - - -"- 1 -r- " - , - --- tt t j - i 6- t-- -+

f -1+ t- J J - F - j - - . +- -+ 1 . + -- +-+: -} ! - -- +-}I t ' * ' * * - - . - - - . * ' - - * ' ' - . ' - - i e - + . 4 e - - 0 e t 4 . 4 4 4-- - _} 1 .F .1.i +.} . - " } .- : r f.I + + . .. j - .I . - - - -------i .--- .-J = + ---T +-.--"- e --J e : .1 +-t"-"- --T-" g- + -, --

- J- 4 - 4 - f -- -J -} - 1 l -. - . -J1 1 1+ - - - a 1 + 2 . - 5 - . - - - i - - - - - -. : ---+ ---7*+ -1 }-+.4A --4 -j7yI ..L.L+ .it

- -- } .+ 4. - . + } , .+ - . .1 +. ... ! -_ - - J. -" . .. .1 -J - .. - .1 . ., -, - -, - -. ,-+ - - " -r t -r -J--4- -". -r -4 t

-.- f--} r+- -. t- --J- -- - - - , : y 1 ' .I , , . . .l . . . . . ..J , ..- . .. -. .. - ., ! . a . . l ..- .I4 .-- 4 - - 4 -+ y

-+-- - -+-t---+ -4-r+-t -

1. r1t 1

-t tt .. f. {-. . . -_.. . .. ; - + - - - - - - +.-- --...-- -_-- - -IU - - *- i * t*-

-- iIr - - - - - -t -- H e - -H+

-4 i -i -4+ - ++ ------ -- -'i * ** * ' -- --' --- '' -.-1 --'.1 1 >- '-+++

. i . t . .. . .4 ....' .-........-..............-..-QI '- .K. .-; t ..+ i

.. . ... 4 * t ---* * -' ' -t ---*- -' -s --' ---' -' -' -------1 -----1- --- }- -t -t4e..i. .. -4.. .... ... .. ., ...: .... -. ... .... .- .-- -- ; .-+ I- t -T --*--t -f-* -t + F

.i .; g .. .+ . i t . . . . . . . .... ... .. .s .... ..-. ... . ., 4 .... .. i -i . ----.-' -' 1- -i- t* -I * -

300

14

200

H

100

0

118 50

'~~~~~~~~~~~~~~~~~~ 11 lit ''''' e ''+t''-* '+ -

-A

Page 149: REPORT NO. 6-763 - digital.library.unt.edu

1;

. _. __.

_.'--1 _ - --

.j.

. .

...

-- J- - --

. ,

i.

r..._ . .+ - - --

. .

- .. +I 1 -h 11 _ - - -

: . : ..- - . .

. IL

*g 400

4-1

0S300

0

0

S200

S00

-~

I

-.-.. - --.I . -.--

1 _ t

,t .

_ r s_. _.

. .. f.:

..

.

. I .

. ,

.

-

...

. . _ L __ _....

.i

" I

. ,

. .

. .

.

.

.... :._

,

_w . ___

. ...

_ .

:t.:

.

,;.

;...,

.,....

.

I I-

y

-- - - t -- -

I

. - -.

-

-- - - . - .- --

S

II

:-J::

j 1

-T-

1'T

1H'j a

.

1 j'

22 26 30 34 38 42Freshly Mixed Density, pcf

Figure B.14 Average stress versus freshly mixed density relation forcellular concrete with a 1.06 water-cement ratio.

500

46

. .. l .

................. =

1 .

i4

H4:-

1 I_ h 1 ___l ___i * h l l 1 l i 1 101

18 50

, r

iT I ! I I I I I I ! I I I I I I. . I ,

4-.-.

MCI' = !q,1 i

1

i.:..i._::I:.

-J

.. 1 "- _ ' '._;__.,1 . = . -1 + - . _}_ r _ l m -r - -_1 - - - ;,-r,_,--_ _'t _ -- T __ . __

-

-F-+-- .- 1-

mbommoodolmom1i 6

L

{I

-..- -. ..I-2. > -.

- L -- -

-1 --

L..

04

-r -- .-- - . --

-.-7

- ..2

Page 150: REPORT NO. 6-763 - digital.library.unt.edu

500

400

22 26 30 34 38 42 46Freshly Mixed Density, pef

Figure B.15 Stress at 40 percent deformation versus freshly mixed density relationfor cellular concrete with a 1.06 water-cement ratio.

L ..- - --

7 -

S--- -- - 1 - --- - - - - --- -

S-it

- r --- -t $j --- --- --' -- ----- -"- --- ---- - ------- --- ---

-- tt-- ------- - -- - - -S

----- -7-- -- - - - - - ..-. --

H

Go

i

300.4

0

ca

200

004

0B 50

Page 151: REPORT NO. 6-763 - digital.library.unt.edu

1000

800

200

18

..I. _ ., ._ II::

:1:::

- - F-

-1~ EL2_I j:.-1-:1-

-- - -- - -- - - -- -- - - - ------- --- -- -------- --- -fT--

_ _- --- -- -- - - -- - --- ----- - --

-- 1- ----- - -

t i . . . . . . - -- - - -- - - - - . - . -. .- -. -.-.

j - j J- - [ j ---_-_*-H

22 26 4630 34 38Freshly Mixed Density, pct

50

Figure B.16 Yield stress versus freshly mixed density relation forrapidly loaded cellular concrete with an 0.76 water-cement ratio.

~ 600

Co

P4

>+ *00H

L 1 1 I 1 1 I - -- --- - -+- { I 1 E I 1f }

- - -

" _ '

_ [

t

I f T

-- - -

.__-{:

---- ;-

Page 152: REPORT NO. 6-763 - digital.library.unt.edu

1000

22 26 30 34 38Freshly Mixed Density, pcf

46

Figure B.17 Average stress versus freshly mixed density relation forrapidly loaded cellular concrete with an 0.76 water-cement ratio.

-.....-.- T I.--T- -

- -..t ..}. .. .--- - - - - - -- ----- ----- ---- - -- - -- - - - - - -.. -- -.

-.--. - --.-- . v

--.- - -- -- .. .--.-- - -.-.. -------- - - - - - - - - - - -e . - - - -.- -.- - .-- -- ------------------ -----

1 . .. . .- ; . . . . . . . . . . -...- -

--- - -.-----.--.-.--.-.. -.---- ------ ------- ----. -. ..---.---.-- ------. - --------

- - -_ - - - -

---- ---- - -i---

r _ _ _ I A,_. :._ tIr " 1 -'

--II

800

sa

4J

$1

0

00

aO

4J

4'

200

H

0

0H8 5042

Page 153: REPORT NO. 6-763 - digital.library.unt.edu

1000

800

0.

V. 600

4 00

- -LP4 -

-.

I.

.1.:

,.. ..

Yijt-

.1 .

:I..

.1.I ..- 1:---

- --.-

-

Kb4

- 1 -

..:- -

1::

-m i m - -II I I -

42 46

Figure B.18 Stress at 40 percent deformation versus freshly mixed density relationfor rapidly loaded cellular concrete with an 0.76 water-cement ratio.

-A - & 1--

- -

- Tt:I:t::~ I;:I: 1 II L1Jf~~I14L5LL

L.. IiiiiII..L.'LLI- .. .--.... I. .. . . .

r---- --- - - - - ;-----I- + Ire: -I +" -- --- - -- " }

4I

4...

* : -

. ;.

.f J

. .

1 1 1

i .

._:

. .

i J { .

H

H

1 1 i 1 { .. .....jj.*

T

.+{

a .

" .

t i

t f

t .

T 'f

1 F

" f 1 f

+ f {

. y a

i .

. J

" {

1

. + .

a L 1

f {,

'.

i

-}- +

l t-.

;..

i"

.

.:

. 1

1

. '

" " 4

1 } 4 1

- - -- --

-

I-

- I

.:. -- -.- 1

-

-- I..

: . : 1 . . _ :-'i

.

+:k:

.;a

+

'. -

0&18 26 30 34 38

Freshly Mixed Density, pef50

--- " -

. :...

. ; .

:. j

.1

.. ...

,

:. ..

. .. .

' 1 i

t

.

-. 1

-

-r

- 2 -,

V.- -------

-1 T - " 1 -T- _ F -- -- F. - -- - - --- - - - _

i i . i m i A 1 m m . ...T r T f 1.r & 4-- 1+. T . 1 4.-- --I

-0-r--- -t- -t -t

i ,_.1 L

1-L-Li!I'"II. ':I i.I1:iIII

.-

" J

- -

-4

.1..

1-1

.. .

i

j .

. !

7

. I

. _ J

} -

.{.

}..

-

... .

t

l : .

.....

.

- ---

.;

-. ._.

.

t,

; 'I

i

- - 1 -.-.I- . - t o-m ._

I

1-

-I-

-+.

* --1

Page 154: REPORT NO. 6-763 - digital.library.unt.edu

1000

goo

22 26 30 34 38Freshly Mired Density, pef

Figure B.19 Yield stress versus freshly mixed density relation for rapidlyloaded cellular concrete with an 0.86 water-cement ratio.

- - - - ------ - - - -- - - - -- - - --------- - - -

- -L----- ~- - - - - - - - -- - - . . .-.. . . . . . . .- - - - - --- -

... .. _.. .

....

......................- : :::: T: j7 {

- - --- - -.- -- -. --- - ----- -- -- -- - -- -- -- -- -_ _ .- _ . ..«1 .

.... :r j....I

-- --

-t" Ft -t[ _ -- - * - -- --- - -------- -- ----- - -- ' - - t

. -t 1I . + - -. . 1- -:-j---:--;.--- - ----i.---- - --- --- - -

. 1 1.-+--- -------+--------------.- --.---- -I-

-- -- ,..--- -- It-- - - --- ----. - -- - - - - - - .

600

w

40

p* 600Hk-lNo

200

113 50

E

Page 155: REPORT NO. 6-763 - digital.library.unt.edu

1000

22 26 30 34 38Freshly Mixed Density, pcf

*2

Figure B.20 Average stress versus freshly mixed density relation forrapidly loaded cellular concrete with an 0.86 water-cement ratio.

800

'600

0

41500

20

- - - +. -t- -{ - -«-r .4 -+- _ _ . r t i t- - _ - 2 - " + - - - - - - - _ - - -- . .- - - - _ - - . . _ _-- - _. _ - - 1 - _ - - --- -+ ---- --- T., ..2 ..3 .+-af t 4 t i - , t - T + ' * - - * ' - - - - -- - - .-- -...- - - - -- - - -- I-- + -r -

111S . . -. -- t ' - - - - -- - t 4 -+.t , -. . -.+ +.- - _ ._- - - -- - - - + - - - _-- - - _ -- -_ - ---. _.- - -- - -- -- _ -_-, -

-$-.y -. --.- $ T- } ;.? I .. - : : : : -- * -- t -- -a ' - - - - - - - - - - - - - -:-: - - - - - --.-- -. - - - - - . . - --. 4-. ---. -

7 1a I I 1 - {+ - i - V 4- + + - + 1 - . - + - - " -l + . ' { - - - - - - - -- _ - - - - - - - - - --------f -+ ----.

-'- -- -- - - - - - - - - - - -

ft S ~ t~ It17t71!-. --- . - . . .-- -----------

........................ ...... ......-.....-...-....... ....-...---- --- - -- '- - - - - - ---- ---- - - - - -

r r

r t

-. ...--- t.t- + + --- + 1- - -- - -. , -- ?. - - 1 - - .. -. . - - . . - - - - - - - - - . . - - - - - - - - - . . . . - . - . . - -. . ...'.-1 1 }. {+...-.

-t +,- -- 4 -4 - .! - + +4 -- -- 1{-+ -+ ,-+ -- 1 -- "----- -- ; -- _..- . -- -- . - i - I...t-. 1--} . .- 1 4 -r...

-t - 1 + - - t - -r -t o - i 3 - 4 , '- - --.t i - - - -- t -- -1- - - -1- - -.- --. ---. . +.-._+ + t . +l r } f 4 l r +. . - .-. . .... ..

-f-} +- -4 {t" , ii.t e 2- -- e- : -- 4 - -7--_ -1.+.. ...... .:..1... ..- . .r-..1.. .. t .. .

t-4 + -- . - 4- i + - l ? . 1 - ' - ' -i t -}4.} 1 . .'-- - - - - -- '4-. * * $-.-a _

H\J1

018 so

Page 156: REPORT NO. 6-763 - digital.library.unt.edu

1000

800

600.4

OO

0

,~200

22 26 30 34 38Freshly Mixed Density, pef

Figure B.21 Stress at 40 percent deformation versus freshly mixed density relationfor rapidly loaded cellular concrete with an 0.86 water-cement ratio.

+= "I" 111 "

_... .. _. . - *: 1 i{...t J . , . ."}.i. . ... . _ . - L. + ; 1+ . , 1_ ~+ tt

- - t t+.- t 4 {It - 4

7 r- -t

----

-4 i 1:" rat- - -- 4- - -- L} -i-

- - - - -:- -" a '+ -F-}

t - -'I

1

t-- :-1- -: { -1- t"-r -;-i_ 1 .4- - - i It

4 -

-. -T - .. }jl ... ... a ... -i ' 1 - i j1/ Fjin... -1« -- -+-- --- - --- - - - + 1 ._, al --.-- . -- +-;

-r .- -7 7 . -: .. {.t. , -.- J 1-- --- - .-Ii - - - r - -'-t-- * - + -i i ' I

- _ 1 - - . : L . l #. , *-i i it4 ; -i . J- - .: - - - - .. ? - -. - l- - - 4 ' I *}-

- , t4 - t - t - _ - }. t 1 ,. . r P -i --..- :t. * + ' I r r Y----- +} . +, t .

-- r- 1 1f r

: i:7 1+ tlji 4r '44{

-- 4 4 - -- +

-_ _- _- _- _-_-1-_-_-_- _--_-_ ... . .. ..t.l ' i 1 L i..K IJ. t L. -**--- - - -- - - - - - - - -* -- - -- --l-ls

H,J,

-

018 503

Page 157: REPORT NO. 6-763 - digital.library.unt.edu

* a [U u * P 1

-)- - , . .I - } -I tP4i-..-t h1-ft

- :4:,'+. . .4- J s . - ~ i .. .-- ,. - t - .- - 1-. -+I . , ~- * * J . : ,- J 1---- - - -}-.--_ t-i-_- -, - - -

. ..- I- t - -- - - - t- .{_r1t $111-

.+ 1 ]4 . .. C & .}.;. +.} .rI '-, - + +----- t +-i- -t- -+ -- + - +4 I+ t > - 9 j-4- + - -_ , +

-- 7 j, I t 41--+. - -+}- t-- -4w-,+ t--S - 4 4 --- 4 -t j-- 4 4 .

.- ^ -r am-- -41 - ,-2 K- Ji} 1 .t--- r - . - - 4-

_4--

- -1- - - 4- -t 4 -- t - +---ft -- 1- --

- + +ii} -9--+{ r -tL- - . Y. ti t a --T Y t - -

4t T - -- ' *-. - * - -- -- -- - ' - * t4

L- - . - - --- i - <- --- - - -- - - ; - --- +- -;:+>--

4-. ;- i' -t l-1 1- -4._ + - -1 -} i - t - - + -} -

I f r- -- -- -

-2 t-r yt- -i it - I 4t- 4 4+ +44i- L jj-

44-4--j-t tJ

4 - K t - -

.- + 4: + 1+ . 4 4 t t * - 0 1 - + -- + + --- ++4 t - t-

-- 1-t -. ,i. +l}-,-,"-"- -t-,- f-{ 4{ L++-.j--r +4 K4 - -+----.+t - { -J-

.' - - -- +-

- -l i -1 L, . }. .... .J.} .. - -l $. + -. . 4 .4-- , .r . .. } . - - 1 "- +-

- i 4t - +- + ;. +- t - Ir-- - - -- I

4r-1 .J1.--{+ +I -+ + I+ i I 1 + 1 - - i

-{ -r+ .i . } . . y t1 J-_ - +} -- I-

. r .t-- .. + - I . . - - - 4 -

.. .t.ai .. + . -. I 1t - -- er-1 .1. t, 4 - i ? - - 4 j:+ra144,+1:1I . .Jy.r "+ - -- , } a + - - 1 . - + y ..

- + - - '4.4-t-.+++ +- K -1 t "+ - -I . - - 1 -4 - 1+

- - -1 + t - + F u r T+ -4 + . t $ 4 l t -- - - - t J + + - -14 1

22 26 30 34 38Freshly Mixed Density, p f

Figure B.22 Yield stress versus freshly mixed density relation for rapidlyloaded cellular concrete with an 0.96 water-cement ratio.

800

La

44J

00H\ii\J1

200

18 46 so

I Ann

Page 158: REPORT NO. 6-763 - digital.library.unt.edu

1000

Freshly Mixed Density, pcf

Figure B.23 Average stress versus freshly mixed density relation forrapidly loaded cellular concrete with an 0.96 water-cement ratio.

22 26 30 34 38 42

t + + 1 4

"-

-" r --

';4-r4

.. +4 .. a- ...... 4., y .. i J . -t .+--{+ 1t .' ,- _- - - +.:: -j t. 1 .-- t+ 1:- . + - +_ -t-i-4- - G -i-- --

+ T--._ . + . -" . 4 a 4 , . . . t.-4t - -- t -. -a- _. - _ , +. I T - - 4 - d -

.. I - . ..'- . . . .l. -+ yI.. . . + - - 4 - -- -- ,--. -- 4 . 4-. ,- -- - 4 4- - +- - . . 4 - -- 4-- - --- 4-, - -p 4 - 4- - -

T4-1

4 4 ~ -+ 441:

1.4 i4rm f S

.. - Y J .. } . . . . i1 . y . .+ . }. . . .. a } - .. ; . . :.. i .--- - - - 4 - 4 -..-----. t._., _- _-- ,---. a - 1 -y--+ .". + *1 .44+ .Y+ f -

11

-. 4-f . .,.. -. . 1 .. ... i .. -. 41 , {- .- t-1---r ,- -i++ - -4 +a ' 4a:: . y . . .+.a... .. . . f. ; . . , . .} ' .. .{ j . .. { . .. : ... ;. t. .... 1.+ 1 ,f.-a { - +}r-.t ?- - - 4

- .t r. i .. .. A 4 .i. -+ - ... i ; : , ,{ t i#..- . . . . . .. . . . . ".--: - - ---- t - + - - a - - -- - 1

t. - 1.i , i ... .. . .. .+ . .r ., . ~. . . - 1 . . a . . . . .. _, . . . . 1 . -. $ Y . . . . _i..s. . j. t ' .. i I - - , . . .. 4 . } _. . - _

F-. {..-4-4iit- X+ + -: +. j -1 - . -+ ;-t - -- 1-:7-. - ; --- '-- -. I -i - ; i - *}--. y Y--T 4 - 4

-t X' .' I {-? +11- .- -t--r ----- --- - ----a +44 - + s---4- - --

-- T.-4. -. r. -- X ,-- + -. +-- }- i- I- -1, ;--- + '-- -- 1-' -.- t - --

-~ } }.,.1 aH -- - 2-- - --- i ', . {} , I+ } ++4 7 t

-l - - : ,-- - -- 4 1- ++ -{ +.- + 1 y t- -t r* --- - - - 1-. - . - +-- 1-4

- 1 . t .-! 144 4 - - 4+ --- 4--4- . -- . - --- ,

._+ ... _. .4 4 - } T} . . .. ' . .4 .. 1 {+.4. t. 4 . . .y +11 . . l -. ,. L# { - "--. ~~~~~~.i .r .t.-- , . . . . . , 4 4 .

--. { { +.g-a tt-_1 *} .-{-+--+- }+-J- 1 1 -t- -. , t +- . e + '- -{ -t- . + }- ---

- ++ . It i + - - - r- 4 1 - . . - 44 . J- -- -+ - .- . , -l -1.+ - -

-L iei- --- 2- -- +4--- 444+-- -T--', -- -{-}.+ + { --- } 41 + - 4 - 4 - - - - -_- -A

-r - I . - - f --l 4 -t - a t ? 7 1.1 j} 4 - 41 . t + . 4 j - , . , j j - i . ?.+. i.4

a800

oe

d~ 6000

0

0

a

b00

S 2 0

H

ON

018 so

Page 159: REPORT NO. 6-763 - digital.library.unt.edu

1000

800

9 600

40

w

-~ ~ 400

0

0

18

4

i 1T

Q~F T2S71 , N T J

~LI

~iIH7Ih.., ., ........4...

....

" "_

... ,

. . -+

:.I

= 1

... T

. .

;; +

._: 1

.,

.;

;;

..

r }

.

"r

;

y ... .

_: .

..

. .

i .

" i

I

_itt 1

. . .

I

L L .II A64hII I'

1

..

. . . :V

I-.

I : : ; .V.: .

,. - j. >.

__L

-. :.1:.

I ! .

i

i ::-

i.

i _ i .

is. . ; . . .. .

... : . . .

. . f

.:t

. : ; .

.

::::j_ :_. ,.

.. .,.

.:..

_ .. __

I. ? f

____ - F - ! ! ~! ! F P TW~~ F - ! F

22 26 30 34 38 42 46Freshly Mixed Density, pcf

Figure B.24 Stress at 40 percent deformation versus freshly mixed density relationfor rapidly loaded cellular concrete with an 0.96 water-cement ratio.

50

.I

. .

.I

' f

r - ;- 1 +---- - -

. ,...

. .

.I ..

.... ; . _ .

.i....

. .

,,..

..

...

i

f

.. .. i

. f .

.

j

i

. i .

.

. .

.. i

"I

. .. ;

I

I

- 1.L

t '

. ::

J..ij

I..

. .. .

i1

-I-

An

- *77 -7 t7'

-4-

- -

:: :.

" I

.:

..

__ _ , ... _

Page 160: REPORT NO. 6-763 - digital.library.unt.edu

1000

800

22 26 4630 34 38Freshly Mixed Density, pcf

Figure B.25 Yield stress versus freshly mixed density relation for rapidlyloaded cellular concrete with a 1.06 water-cement ratio.

- I} I o

{-I

2AL --- -K~.V ~-K- -

S600

41

a)e

4 400

H

CC)

200

018503

Page 161: REPORT NO. 6-763 - digital.library.unt.edu

1000

22 26 30 34 38 42Freshly Mixed Density, pcf

Figure B.26 Average stress versus freshly mixed density relation forrapidly loaded cellular concrete with a 1.06 water-cement ratio.

a800

w0

'~600

4.5

0

0

4. 400

b0

200

H

018 50

- - --- --I- ---

- - -- .-- ---

-I _ 1+

77 17 ? _ _. . . .1... -- * *t-

. . -. . . . .."". . . . .

Page 162: REPORT NO. 6-763 - digital.library.unt.edu

...1 . ...

T -- 1 - -

1000

800

.

-- - - -

. * +-

' J. 1 1 r a

i . +

l - C - a T .

. .} 1 ...

.

f f

h---

ie.

a

w'.

A1

0W

4O

NN

b

co.

-.4-

.i;..

.. .,.

--. .- -

. ; .

. .. .

.t..

-1--- -

-:

-. --.- :

------

-- -4

. ~ .. . . . .

. } .. 1

. ' . ...-

. .a

O

I I

.. /.

....

. . ..

. ..

..

. . _ } . . . .

.,:.

I

-t:".

- ..- - -

. . . . . . .

r 1 1

mu ma mm m. mimi mu m' mi mini ini m mi m - m mm. mu m

26 42 50

Figure B.27 Stress at 40 percent deformation versus freshly mixed density relationfor rapidly loaded cellular concrete with a 1.06 water-cement ratio.

4...:.

----H --

H

0

..

Ii.

.4''

600

400

200

t.i:}}

ajjiiii4a

4.''

}tf

r a.

rt"J

FP i. i.

1 1

1

r

t

1

f

i.li

i I I

-,

1

j

l i

.}

i ,,

. .

TIt

i f

JT

0f18

t .. .. . . . .... . . . . . . . . . .

" - ---- ---

i7 1 i22 30 34 38

Freshly Mixed Density, pef

r

. . I I . I . I . I - - - . I I I . I I - I . I . - - I I . I I I ' . - - T T .

II

11

..

- r

-- I- ----- -.- --

.- .-.--. ...-. ..- -..-. -..------.- .- .

i t - -t- -- t - -{-

i i i i i , , i : ; 1 1 1 1 1 m 1 1 ; .1 i R A -

i i v i i I i , i i . i a 0 . i - v . i . . i . - i -4 - i - - i I --+ - -

-- r----__Z;Tm

.,.,

.

--... ;

...

... ,

,...

:.,.

.

:,;.

,.:}

.L;

-=..4-0-..L-c--

i

- ---r - -

- t --

TT-r.-_ i

_. -:

:_

-

.. .. .

- +

i

.f. . ..1'

.

.

_

1.1,

.;

,,.

tt,

- --- 1

li

.

t

. . . . . ,

-I-e - -- --- e

. a

a " } .

a «

" I

" a

+ 1'-

.. I..:.

.. . { I . ,,,...-

t - ... .

: :C

r- --....

-. - -'

I j

1 1

I

. 1

} . .

L : :

,

.

i

I

---- --

.

__I

.

. i

Page 163: REPORT NO. 6-763 - digital.library.unt.edu

018

V t i- T . r. . ! . .t r- a. _- 4 i.i .}-" - + - - .- .- .f . , - --- r - + - , - - - - r- - - --- r - 1 . . + --- t -- -- 1 +--} . 4 1 -

- .---- -,tr y.. - 4--- --- 1t-t I r .t-.1 . .- 2- -4 J ~].t14

.a a n-m. . . -a I ' n n m .- " t.. ... ~ *-r-'-_ . -*a *-.': .''+ +- . - ,- -:- - - -+-- - - -, - . -- 4-4-4t+t-

22 26 30 34 38Freshly Mixed Density, pcf

42 46

Figure B.28 Modulus of rupture versus freshly mixed density relationfor cellular concrete with an 0.76 water-cement ratio.

0~

0.

H

H

I50

fi i i , : I I I : A . : 1 : 1 i i i i I "

AA

- :. -- 2,i :t:a ', ,- ,*.. . . , . .. .. , - .-4-.. ..,-- 4 ,.-

+++- t 1.I..T.4 - ;. - . ~ - 1 Y . t--- t . ry .++ . . : .- 1 . a -1 -}+ - a -r---1 1 }. F'- 1--" .!.+_ - + -Y - ---- L i4-i --- 4-- -- -' 4

-} -- r -{a+4 4- r 1-- * - a - -. - 1 a " - . + _ i+ . - - - . - - - - - - - . . . f . -t o w . -- i . -- - 4 - - a _ L -. 4 4- --{ -

-- 0 - -- +-e-i a-+ 1 , -+ -- + ,-1 + 1 +l - -. _ .f :-- - 1 -- +-+y -+ -*- - 'i1--- r r- +- i + . L - i. -+- k -l+--

94- J- +-t-' -~4 + ++4? TAIi 1 ,+ , -. . - -.- +- 4 4 -. + - - . i +. - «- - t - , * * '.r. .- . t . ._- - a *r : - ' ' --- - - + f - } f * - -+ - J T 4 -- --- 4 '---.-+ - , -. +. .-++ -+ -

L {a -a _-- 1'- -.. 1 t + .: -i t- +- - t- -4f--I+ - I a+ - --- J r--: -- ++e .. 4---+4+y -g. . t--'- f-.+ }-g -- ii +-

++ .- -. -J - + + .. a+ a . -+-. f -i -4 4 - -+ -e - - -- + '- - ' --- 1- - y am .-- * -' " -i---a .-. -- +- r* +.+ - ' 4 . a i 4- +- - --

. - --' - -- - 4 -- - -- - +-+- -- - -- '+ : - -- - ' . + +

T " . -42S i i ti. I i -80+ i .. *.1 . 2 + It - .. " } a I -+ T.

. 1 .. L .L44| r 4 ----e ' '-4 -j+ 4- +: t V-'-- -' -- -- * '- ' - + ,- ,,',+ -' -4'. -44-' - 1 -- 4- t 9 Y4+- - 4- - - -- - -+ + - - - .-- - +- --. ' + - . - 44- -- -.{-4-4

.- 14., . . -. . 4 +..1- .- -...... ,a..ia.--+ -. 4- . 1 + ti J _t ti _4 -F-.- - + - J-a ..- 1 --.4--.- .-44.4-

-4----- -'-- --+t f--i.44-...4 . . ..4 -... .4 .'tpt+.5S + + .It. i44-+ i-- .4.y -. 4- .. 4.4 ' - - { y- -+" - - a 4--{ + + ' - ---4-- . * -- -- - :. +1 - *+ { ' "*+ } i ce *- - -1 -- t- -- r . 4 4 -4+

4 --- + - - '... - - + 4 - - - , - - - -+ - e e e t a

- .1 + ..".. .s..i . .-+.~ l +1 . - - .:- -. . - - - -- - --. - - .: + 1 -! . .--4 - '--

4+-- t -*4 -++ -- -4 -++- 4' +-- -1i-+, -- t-- --- }f-. -- }}-} -- - -- -- t-- r-} as-2 r +r }}-+ -I + 0 - +- 4A f- }-

6a .;.7 1. .+i . - . y .4- . . . - . - - . . - - - . ... : . . -I .L -. 1 . } + - "- -i .+. +y - - - - - - 4 - - - t - - - '4 -l } -a + --+'

+ ---+----4 4j- ---,'-----4--- - - -+4 t-' + +: tlt- e1- ''- - ---- ' - ' *4'--r '-i - 4!e+ , i-+ -'-'-4, + - 4 f-44 ~- t' --

--- t-4 - - -

+- 114-+ -2. - -- 0- -- - - - ' -- - ' - - -* --

.J 11 ..'.i.'.. .V.,-i --- -.. -. --- --. ----v-iii. .---- A4 -4 4-- .-

1 -- t-- -+

Page 164: REPORT NO. 6-763 - digital.library.unt.edu

L

22

Freshly Mixed Density, pcf42 46 50

Figure B.29 Modulus of rupture versus freshly mixed density relationfor cellular concrete with an 0.86 water-cement ratio.

0

4'

H0)-

inn

- - -- j 4 - 1- - + + -*. - - - + - -Y - - - 'mi-- - + -- + - - . - -. Y-

... "+} . }... . la4 .p -} }-+1 i+: --- -:-1 -++---}- t } 4 -. - 4-. -aed* -. + _ :+ .---. -. --- l -- * }1-- -- 1 .- -. _t- i -4--.L--- --+- -+- -

-... - - - L- . I -+ i+ . f }, }- } - - + . - l -t . {'+. - ' ' - ' r -. . - - +. '- - r -# * - 1 , ta+ -- --- f -

t 44 44' 4ft1 -- t- 4- --- i . L jt:;s . :.: - 4 4 4-- - - 4 -- -- -. -. -- ,, -- - .- -- t-.44

-+ -+1" --- '. -4t-t- --4' -ht-- ---- +-

- .4-4 -. +. .- . - - + - + - - . - - 4 + - - -. .

. - -- . -. '- --y.4' -- -- . - - . I 14-- . -- +

8 0 ' + 4

J + ,tt +

1 - . +4 +4 -W '- 4- 1 - - . ._-... -+. . . f -4- +.- 1;J4 t 4 --- - - F 1.,

wa J i -- ... 4 :. 1 . .. ., . ... . . . ... . .... ,.... . .. . ... ..+.. + . 4 .- + . - -}} a-- « 1 . -. -r _-- - _ . . -. -- _ + - " ,-*- -- 1 _. i l l.-- -. . -+ - * + + Y .ti lt-' } - ----1. * i I *-. .4 -t 4 -- -* 14 ----- -

, - -- - - - - + t-+ + 4 -t1 3 - .- +- '1 . ,-a-. : - - . - - , - -4-1- - - - 1 - . - . - ' -r "+ r. , . + -, . ++ -r - -- t 4 I -- e- - -+ t ----i+ 4 j, 7s 1 7l7

<- . i -! - . - . - - .-- . - - -. .4. - + t.- - 1 i +-- L A fl + - - f - -

- V - t- - i- . {- - { - 4 - { . . - - . .. - - . . . . . . . . .. . . . .. . . . . - - a . ... . : . . . + , r _-- . t +- i t + i t i -t i t b -

-f+. ..2. 44 -. --+ ---

{ -- -t; .PtTla: t i--+- - +4+- 44-- -.4-- -.. --

- -+ 1 1 . 4 -+.1 . . . . . . . . .. . . . . . . . . . . . .. .. . . . t .1 , . r. . l i i -- . . - 1 - T- - 1 . - - -

40 + t { 1:_+ , t

+ 1+ liLl 1 .1t + ---

L+ . .il + . : . . . . . . . . . .{. . .*. . . . . . . .,. . . . . . . . ,.-. ... . - L... :. r« l i . . + .. .i - r.

+ + }- .-i . } l.. i t, , . . .l . , . . . . .1 1 . ,{ .. . . . . . . .. . .. .. . . , . . t i ; , . . - --lt -- 4a- -

14 -r l a. . . .. .. . .: . . . . . . . . . i , ; . , s . . . - . .! - - I.- YI 4 - t - + + 1- '--- r +- , 1 1 +- . .- + -

....-.. . .

20 tr'

1tF } t .1-i- ++. .+. U+ 4 l 4j I

18 26 30 34 38

Page 165: REPORT NO. 6-763 - digital.library.unt.edu

.t 4 - - -- r-j-4-F H } 11 -t-t +- - - *-,-+4 - --. t } - - 1 t-r - - +"-t-- 'i- -t.. + . ' . ... . -- . - .1--- + -- i .- 1-{ - + +r 4 - - +f - . -- -'-t t t -

- - -4 -j- 4., -,- i - i -1 -- i - -1 -1 4- -.i - 4 i a -4 - - 4 4 - -+ -e - -4 +

100

80

J4 t

4.- , .1 J l. . . .. . 2. - - . - - - 1-' - - - {. - : - t - i . + i + -t + ,t , - .+ 1 a } - - + ! r - - -+-.}' .-

+ + - - - - - - - . - '-' ''.- - - - '' t+--

:- a._ .-_- e-- I-h--

- -. - -- -A 4a ... .- a- -- -+ -

. .J. . . . . . . . . . - - .-- - - - - - --: :- + , * - . - - - - t - ' +- ' - 1 t 4 - + - - 4

- 4 . s . a . - - . - - - - - . --- ----. -- -- -- -* - --- -' ' ' -- ' 4 i i -t - * e- z-4t --T

30 34 38Freshly Mixed Density, pcf

Figure B.30 Modulus of rupture versus freshly mixed density relationfor cellular concrete with an 0.96 water-cement ratio.

4-4 4t1 '~

, -,-,-1 { r i . . , } ,-,- , L . - : :I - - - - - -. t -t- t 1 .}-t i i i i i i

. .P . 4 + -r - + - + +- -

.-.-.. '-+.j. .-----+ - , 1 +. -+-- -t1 , + .-4-- --W 4 t

.- - - -- 4-+4t 1+ - ++ . -1 ' .- L- . -_'- --- 'i I - + - t - + . -L - J . +" -

11 - - .- t t - 1 --t ' ' ' --- *} --' --' ' 3 4 t -i t -i + . ---,r--. --+ + --4-.a. .+ ... : ?

. - ; . . - ' 1-- - - - - ' 4 ' T - *i-s - i-y y a i- + -$ - - + Y +- - - - -9- -+ --+- -- T ----i-'----4 -'-9-1 4-- -- +

4 t .. -4 . , . - . . .E ; a - - - . , 4 4 - . . + - . - . -t - -i 4 -4. t t ' + t ' + + - - + - -- -

sd

4 40.

x"

HJON

18

44-41,111. 11 .111111 lH

I I I I I I Irl

H.+ + f4 4 -4-++--+r+ +-e-t-4 - +++. -- ++-+-+- r- -I 1 1 4-H-t _ .r_ r1I .- 1 + - f1 i.. L .}.._ t t-+-t . - } tr - .- rte Y }- 1 -" .t. r +-* i-a .*. I Y. . f' r" 1

44 { -i't " T t F r t t } t f +

- + 1 r. i. y .a i r-} Y t i" t +. + {r t' Y i t -

:. f i {- i 1; . f r f 1 " 1.. I "Y +-"i L r { t L 1 1 'f-Y t } a+ f y

t-t

42 46 5022 26

I

-t f+ f11--;. 1, 1 f 1--i-H

Page 166: REPORT NO. 6-763 - digital.library.unt.edu

100

80

22 26 30 34 38Freshly Mixed Density, pcf

Figure B.31 Modulus of rupture versus freshly mixed density relationfor cellular concrete with a 1.06 water-cement ratio.

+-'- - 4 - : +- 4+4 - 1

.--t+4- -- 4 -

t1't-- -,-$-{t. .4 - +. +- .1. --- --.tJ I -f - - . - .---.' ... rt - 4-4+ } i . . i - r . . .l--..I } .L ..... . }. . ,. , } y - _. .- :- - t - « -- t . +--}.Y - -

-+l- 4 - - -- - .I --+ -I. .}}+--' - .. l -'- , - -i - *+ -+t - I +- . -' + - i-- - - - 5 4 - ' T - 4 -*

4 . -. I4Y+4 .. ' . r- -4. ly - .. *-+ --.- Fi L- - . . . :.-. 1 i . - , .. t . .y f- - + - . - . -

4-1- -++-a- -- +- +--. ---- 1- - r - .-.-- r a- + +- - -1 J-..+ll- -+ +++

- 4 -f

+y-+ii -it .i + }

1L %

A}

-+-.r - - .. r .. r r+ . . :, . .} .,-. .t - -+ -. - 4 - + -i--- -- -- -- - --- - .-- -- ,- . - -. - + - +- t-el - - - + - f" ---

.--.

.

+

.I

..

, .L

.;

I,

..

.

.i

.I

.

.i

.

.}

,...

J ..

_

-e...

,...,

4. +

t

-

-+-i-

-

---

t-i-

+- T - 1 1 -- -Lt i++f + {--. 1 r -- 1-- r - - - -i 1 - F.. ; . .} - - -- +- -+ - +- -- 4 L t t + + i -' t-t+ --- - -- Y - - - - - + . - + -- r I 1 T-. i- -+ .- l-- } r . - L-- - - - - - - - .}i - 4 j - - - - . - - i-- -- } _-.- -.-. -+' -- J-- +

- ,+ t- r! + -

. - -- . - -- - - - - . - - - 1 -- - --t -+-+ - - -+ 1 - - t - + - 1 0

- T - -1

- 1+ - f--. + L a - - + - a t-: - -. +i- --- - I, t . L . I,- . . . . . .1 . i J. - 4 } -- . I. - (+ { . " " - -- -

,

'60-

0.

00

0

H

20

0.18 46 50

Page 167: REPORT NO. 6-763 - digital.library.unt.edu

25U

-

t - 1-ti

it]t[4 -Th i-I

1T :1.1.4- 11 141414 jj7it f

It htt f* ttttt

1 4 -U4II L 4 t-

-I--

000

k

V

U4

0

U)

0t i-t +1HF F-H+H

t44~ko1Th TE i-44~V

(] -

1 . ti 17-i

tit 4- I-HI1' ti1UtL~~~'t~

*24. 44 144. 2444

26

j 17I

} !t t4

ILL-1-1

30 34 38 42 46Freshly Mixed Density, pcf

Figure B.32 Modulus of elasticity versus freshly mixed density relationfor cellular concrete with an 0.66 water-cement ratio.

1nn

15

t ttt

n[+n410U

*1i41-. "L

h4-

U

18 22 50

,-"4

- r - -

PF

Y LA 1 1 I 1 1 I I 1 1 1 I 1 1 1 1 1 1 1 1 I I I I I I I I l l 1 1 1 I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 . l 1 L L I

1 -t1i qll ILI L

1 a + - TIT i t ,JkT,_f a1t 1 ,1+ + + +f f

4 4' 4

-J- 444 4 4a4

. . . . . . . . . .i--f--f --

t

1 1 1 1 1 1 1 i 1 i 1 m 1 1 1 1 1 1 0 ! i . i i ! 1 1 1 1 1 ! 1 1 1 i 1 m ! M 1 i I I i 1 A I ! 1 1 l 1 1 1 .

.1... . t .+t .

e Jl{J {{{ Jilf{viii+ il a 1 r ii i ii r

t --i i i i i i i i t- i m - i I i 0 1 1 1 1 1 m 1 1 1 1 1 i 0 1 1 0 1 i 0 ! i i i i i 2 i 4 i i m i ! :bo l h I i i i ,

-4 444f}"_

tfiR.

.t

}

+ +

.

+ +

i'-'1J

I-tq

Vl

^iI

. t t-

r t t t t-t i- 44+

ljt4 t ti I 4 t4- i i. I} It r. 1 -!-7-

,. mot. i t +-+ t 1 t -! .: .* } 1

+41

.7 1wlHi -7;

Page 168: REPORT NO. 6-763 - digital.library.unt.edu

Cr.

4 114tU i i .i [Li+t-'It

44

.i

titI I-r4jjj- I 44 1 -4t -44 j IZ .44

tiMml

I i i i!i i 1111111! I -.. .. I . -].R 14 1i i'1;111111I1 ,;i v ! i.i li; Ai ;4411;71111111' -4 iT ;l4 ii:1i .; i;T;:1i- i 4m

H-f ; '.rl fl .i

tLfYi 't~ s

26

i

{U2fifLN4IL

30

i

~t~t -

00

0

U,

0x,

34 38Freshly Mixed Density, pef

42

[T4

46

Figure B.33 Modulus of elasticity versus freshly mixed density relationfor cellular concrete with an 0.76 water-cement ratio.

-f--i--I --tlff25

20

l-ttt-4

IlIt-II

WIi--lt~t Ptl 1

.. 44f-

- ! 1 1 -{- -- t - -l t - - 4 +

-- I +- +j- I - "--4 -- -4 t - - - - -

-- 4fil4

+5 . 4 4 t-

144 -L-

- 4 - - - t- - -1 - --o . +- - . , -- -- - - --,

'1. .. . . .' . . . _-.. - Y t - ---4. 4 ..... l

HO~N

IN'

22 50

TT -+Hi-jX1.1 ${ :-

+ -1 44 1 1 -- f ' H ' l . l l m i--1- - ++ +-+i f -f +-{- H } -I

{ -- ,4 4

-4,+...r ! +,4t

444 .. -

4I

-i

(

L y

-a

_+

I

i

I 1 1

-4 4 1 4-1 1-- 41' '--1Jl 4 41 1" ! 4 1r;.. 1

I I

i

.n

1Sr

18

Page 169: REPORT NO. 6-763 - digital.library.unt.edu

250 }

-- -- -l - - - - --- A - ----tA

-- - ------ -t --1- --} ----{

-t -- -- . . t J t -- - -. + -1-, - ---- ------

- - - - - -} - -tt "} } - T-.l!t +_I,- -{. -. . ---- -1. . -- -. a i - -"- - - - J-1-# t.- -.- -

: - - - - - - - -1 ---I- -+ ---1 --+-

- -1- - ---I-{-+ -

151

-+ -T -i {_. t- M-jt I

1t01--$-1-- - -I -t-f--} }--I. 1.i l - 1 -- y - + y -t TL -

1- - - 1 t - I ; } -t . " .- . + } .. ' t t -- +

t. t- F---! --------- f -f T f 1 to---rr- + - a+ 1t } - 1 -t- -1 - I --

- - . _ - + + } } r t :; } r t - - +- 1 +- -- } - r-1 T

-. - - - -,- .- t- --- }i-Y- , " 1aY. .,- - 1

T14

18 22 26 30 34 38 42 46 50Freshly Mixed Density, ocf

Figure B.3)4 Modulus of elasticity versus freshly mixed density relationfor cellular concrete with an 0.86 water-cement ratio.

000

.4

U)

0

Page 170: REPORT NO. 6-763 - digital.library.unt.edu

-4-p-- I i ik

::: :: : :T::::

- - 1 -- -- --- - +--- - -- - -- f - --- .t- -- - -1*- ---

- " i - ::22 -i~

i2n .

T J _- L 4 1 -- --

I T t

00

0

0

30 34 38Freshly Mixed Density, pef

Figure B.35 Modulus of elasticity versus freshly mixed density relationfor cellular concrete with an 0.96 water-cement ratio.

2 50xFt 2F

I

.__.. _- -

50

..- .- . .- .--... ---

18 22 26 42 46 50

...........-- }---------i -- 1--------i --

-

" I i " I ~~~I 4 I "i , .I .} _.+_.

'---- t-- - "- +---

.- - -- t. __ -- -- t - -_

L L1 V _ L _.

---- +T---- ------------- -- ,--------_ -- .-. -- 1 ----- 1 L

- -- r - - -

--

-

7.:7

I sn

Page 171: REPORT NO. 6-763 - digital.library.unt.edu

APPENDIX C

OBSERVATIONS ON THE EQUATIONOF STATE OF CELLULAR CONCRETE

The mechanism of attenuation of pressure waves in cellular concrete

has been studied previously from the rigid mechanical point of view that

is applicable for the lower rates of loading as contained in this report.

For loading rates sufficiently rapid that wave mechanics influence the

behavior of the material, the mechanism of attenuation may be appreciably

altered. Wave propagation experiments with cellular concrete have indi-

cated the shock structure of cellular concrete to consist of an elastic

precursor followed by a slower crushing wave (Reference 20). The pressure

associated with the elastic precursor is a function of the input pressure

of the incident wave and is observed to exceed the static yield strength

of the cellular concrete for higher impact velocities. This indicates that

this material, prior to locking, may transmit stresses to a structure in

excess of the elastic yield stress. From a few tests conducted on cellular

concrete, data were produced relating to wave propagation velocities,

width of the transition zone for a step pressure input, and rate of decay

of stress waves in cellular concrete.

C.1 THEORETICAL CONSIDERATIONS

The description of elastic-plastic wave propagation in a material is

predicated on a constitutive relation of the material behavior and the

equations of motion. In the simplest cases, a strain rate independent

behavior leads to many important simplifications that allow computation of

stress and strain relations in a fairly straightforward manner. In this

instance, the Hugoniot jump conditions for one dimension involving stress

(a) and strain (e) are given as

a = pUu (C.l)

E U= U (C.2)U

where

p = density ahead of the wave

169

Page 172: REPORT NO. 6-763 - digital.library.unt.edu

U = velocity of propagation of the wave

u = particle velocity behind the wave front

This description of materials behavior is essentially hydrodynamic; and for

very soft materials where shear stresses and strain rate dependence are

negligible, these equations should be a fair approximation.

In the elastic range, the relations are essentially the same but are

derived from considerations of elastic behavior, where U = C , the ve-

locity of propagation of elastic waves.

In the case of an elastic-plastic wave reflecting from a liner, the

stresses delivered to the liner can be derived by making the assumption of

purely elastic behavior of the liner. Under these simplifying conditions,

reflected stresses at the liner can be determined from the behavior of the

shock-absorbing concrete under shock loading.

C.2 EXPERIMENTAL METHOD

The shock behavior of cellular concrete was studied from the wave

propagation point of view using impact experiments conforming to one-

dimensional strain conditions. Continuous measurements of propagation and

particle velocities were made using an induction wire transducer. Plane

impacts were produced using a gas-operated gun to launch a flat plate onto

the specimen. The gas gun has a 2-inch bore, 10-foot launch tube, and a

pressure chamber designed for 12,000 psi (Reference 21). Both the weight

of the projectile and breech pressure can be varied to attain different im-

pact velocities.

Test specimens were prepared with induction wires placed at varying

depths from the impact surface along the centerline of the axis of loading

as shown in Figure C.l. The specimen was then placed in a dc magnetic

field such that any axial motion caused the effective length of the wire

to cut lines of magnetic flux thus producing an emf or voltage propor-

tional to the velocity of motion. The output voltage from each wire,

therefore, was recorded as a function of time. The amplitude of the signal

was calibrated in units of particle velocity and the time displacement

between each wire was a measure of the propagation velocity.

170

Page 173: REPORT NO. 6-763 - digital.library.unt.edu

C.3 EPERIMENTAL RESULTS

The observed particle velocity records for three signal wires are

shown in Figure C.2. The test configuration for shots 1 and 2 was such

that the cellular concrete was impacted directly. The first two shots in-

dicate the existence of an elastic forerunner wave preceding a plastic-

wave. However, this forerunner cannot be distinguished from an air shock

effect since the range facility was not evacuated in this case. An effort

was made to vent the gun barrel at the sample interface; however, it was

difficult to determine if this was sufficient to eliminate all effects of

an air cushion. Therefore, a 1/8-inch-thick aluminum plate was affixed to

the impact surface of the specimen to permit the range facility or barrel

to be evacuated to approximately 10 microns. The records produced using

this test configuration are shown in Figure C.3. Signals for two wires

that were spaced at 12.7-mm intervals from the impact surface at a faster

sweep rate, which was selected to show the elastic portion of the wave

structure, are shown. These same signals were displayed at slower sweep

rates for observing any plastic wave structure. No plastic wave structure

was observed on any of these four tests for a period of observation cover-

ing 200 psec. Propagation velocities correlate closely with the sonic ve-

locity or the velocity predicted from the slope of the elastic portion of

a static stress-strain relation for the samples tested.

The observed pressure-time histories shown in Figure C.4 as computed

from the measured velocity histories show a decay in pressure of approxi-

mately 50 percent over a propagation distance of 12.7 mm. This rate of

decay is not expected to be constant with distance from the impact surface.

Additional data points as a function of distance from impact surface would

be required to determine this. It is possible that this apparent decay is

a function of the test conditions; however, a correlation between this and

wave reflections for this test geometry has not yet been achieved. One

point in question is the velocity of release waves emanating from the outer

edges of the projectile input surface that could diminish the region of

one-dimensional strain. More experiments are required to establish the

contribution due to test geometry.

171

Page 174: REPORT NO. 6-763 - digital.library.unt.edu

Under certain conditions, an interposed layer of foamed or distended

material may substantially reduce peak pressures transmitted to a struc-

tural wall. The initial shock front does not seem to occupy the rela-

tively narrow zone usually imagined to exist in solids. Therefore, it may

be more accurate to say the pressure attenuation effect is related to a

broadening of the condensing front. Beneficial effects can also be derived

from the existence of forerunners similar to elastic precursors in solid

materials since these carry off momentum from the crushing wave and deliver

it to the structure at a lower pressure.

172

Page 175: REPORT NO. 6-763 - digital.library.unt.edu

PCMAGNETIC

INDUCTION WIRES AXIAL

PROJECTILE

S

I M

)LE

SPECIMEN

MAGNETIC POLE

Figure C.1 Schematic of experimental setup.

173

1

I

Page 176: REPORT NO. 6-763 - digital.library.unt.edu

o A AxUW

U,

B-30 30

F-A- 0acc

a-

0 0

250 4-EC 250 SEC -TIME, $SEC

SHOT I -IMPACT VELOCITY = 50 FPS SHOT 2- IMPACT VELOCITY = 75FPS

NOTE: LOCATION OF ZERO POINTS IS ARBITRARY.THE STACKING OF CURVES A, B, AND CIS DONE ONLY TO SHOW THE CHANGEIN WAVE PROFILES.

Figure C.2 Particle velocity versus time histories.

174

"

Page 177: REPORT NO. 6-763 - digital.library.unt.edu

rA8

0

SHOT 3 - IMPACT VELOCITY = 75 FPS

16

8B-

0

24 4E

-IS A

o BJ

0

SHOT 5-IMPACT VELOCITY =150FPSCL

24

16

8

0 8 16 24 32TIME, ).SEC

SHOT 6-IMPACT VELOCITY = 200 FPS

40

NOTE: ZERO OF CURVE A IS ARBITRARY BUTCURVE B IS IN THE PROPER TIMELOCATION WITH RESPECT TO A.

Figure C.3 Particle velocity versus time histories whenimpacted with aluminum driver plate.

175

A

B

. InI

oo--

I

Page 178: REPORT NO. 6-763 - digital.library.unt.edu

0.

0.

0.

0.

0.

c.0J

S0.

Y o

U)U)W

F-

0.1

I

6

A4 -

B

2

0

8

6

A

4 -B

2

00

NOTE:

8 16 24 32TIME, ).ASEC

ZERO OF CURVE A IS ARBITRARYBUT CURVE B IS IN THE PROPERLOCATION WITH RESPECT TO A.

Figure C.4 Pressure versus time histories.

176

AB

- -I

4

2

0

6

4

2

0

B

600

300

0

.uu

600

300

0

A

0.

0.

o.;

CA)

wW:

900

800

300

0

1200

900

600

300

004C

Page 179: REPORT NO. 6-763 - digital.library.unt.edu

REFERENCES

1. ACI Committee 523; "Guide for Cast-In-Place Low Density Con-crete"; Journal, American Concrete Institute, September 1967, Vol. 64,No. 9, Pages 529-535; Detroit, Mich.; Unclassified.

2. G. C. Hoff; "Shock-Absorbing Materials; Backpacking Materialsfor Deeply Buried Protective Structures"; Technical Report No. 6-763,Report 1, March 1967; U. S. Army Engineer Waterways Experiment Station, CE,Vicksburg, Miss.; Unclassified.

3. G. C. Hoff, W. F. McCleese, and J. M. Holzer; "Shock-AbsorbingMaterials; Aging of Backpacking Materials"; Technical Report No. 6-763,Report 4, November 1968; U. S. Army Engineer Waterways Experiment Station,CE, Vicksburg, Miss.; Unclassified.

4. G. C. Hoff; "Shock-Absorbing Materials; Selection of a SuitableLow-Density Concrete for Backpacking for a Proposed Field Test"; TechnicalReport No. 6-763, Report 3, April 1968; U. S. Army Engineer Waterways Ex-periment Station, CE, Vicksburg, Miss.; Unclassified.

5. G. C. Hoff; "Operation Flint Lock, Shot Pile Driver; Grouting andMaterials Control"; Miscellaneous Paper C-69-7, March 1969; U. S. Army En-gineer Waterways Experiment Station, CE, Vicksburg, Miss.; Unclassified.

6. T. C. Powers and T. L. Brownyard; "Studies of the Physical Prop-erties of Hardened Portland Cement Paste"; Journal, American Concrete In-stitute, 1947, Vol. 43, Pages 101-132, 249-336, 469-504, 549-602, 669-712,815-880, 933-992; Detroit, Mich.; Unclassified.

7. T. C. Powers; "The Physical Structure and Engineering Propertiesof Concrete"; Research Department Bulletin 90, July 1958; Research and De-velopment Laboratories of the Portland Cement Association, Chicago, Ill.;Unclassified.

8. T. C. Powers; "The Nonevaporable Water Content of HardenedPortland-Cement Paste--Its Significance for Concrete Research and ItsMethod of Determination"; ASTM Bulletin No. 158, May 1949, Pages 68-76;American Society for Testing Materials, Philadelphia, Pa.; Unclassified.

9. G. Wischers; "Einfluss einer Temperaturanderung auf dieFestigkeit von Zemetstein und Zementmortel mit Zuschlag-StoffenVerschiedener Warmedehnung"; Schriftenreihe der Zementindustrie VereinDeutscher Zementwerke E. V., Dusseldorf, March 1961, Page 50.

10. T. C. Hansen; "Cracking and Fracture of Concrete and CementPaste"; ACI Publication SP-20, 1968, Pages 43-66; American Concrete In-stitute, Detroit, Mich.; Unclassified.

11. A. Auskern; "A Model for the Strength of Cement-Polymer andConcrete-Polymer Systems"; BNL 13493R-2, March 1969; Brookhaven NationalLaboratory, Upton, N. Y.; Unclassified.

177

Page 180: REPORT NO. 6-763 - digital.library.unt.edu

12. M. Polivka, J. W. Kelly, and C. H. Best; "A Physical Method forDetermining the Composition of Hardened Concrete"; ASTM Special TechnicalPublication No. 205, 1958, Pages 135-152; American Society for TestingMaterials, Philadelphia, Pa.; Unclassified.

13. R. C. Valore, Jr.; "Cellular Concretes; Part 2, PhysicalProperties"; Journal, American Concrete Institute, Vol. 50, No. 10,June 1954, Pages 817-836; Detroit, Mich.; Unclassified.

14. F. C. McCormick; "A Rational Procedure for Proportioning Pre-formed Foam Cellular Concrete Mixes"; Ph. D. Dissertation, 1964; Universityof Michigan, Ann Arbor, Mich.; Unclassified.

15. A. Pauw; "Static Modulus of Elasticity of Concrete as Affectedby Density"; Journal, American Concrete Institute, Vol. 57, No. 12,1960-1961, Pages 679-688; Detroit, Mich.; Unclassified.

16. ACI Committee 318; "Proposed Revision of ACI 318-63, BuildingCode Requirements for Reinforced Concrete"; Journal, American ConcreteInstitute, Vol. 67, No. 2, February 1970, Pages 77-186; Detroit, Mich.;Unclassified.

17. ACI Committee 213; "Guide for Structural Lightweight AggregateConcrete"; Journal, American Concrete Institute, Vol. 64, No. 8, August1967, Pages 433-469; Unclassified.

18. T. W. Reichard; "Creep and Drying Shrinkage of Lightweight andNormal-Weight Concretes"; NBS Monograph 74, March 1964; U. S. Departmentof Commerce, National Bureau of Standards, Washington, D. C.; Unclassified.

19. G. C. Hoff, W. F. McCleese, and A. A. Bombich; "Project BigPapa - Phase III, Cellular Concrete Fragmentation Acceptors"; MiscellaneousPaper No. 6-973, February 1968; U. S. Army Engineer Waterways ExperimentStation, CE, Vicksburg, Miss.; Unclassified.

20. B. R. Sullivan; "Dynamic Compaction of Porous Concrete";Miscellaneous Paper C-68-9, November 1968; U. S. Army Engineer WaterwaysExperiment Station, CE, Vicksburg, Miss.; Unclassified.

21. D. L. Ainsworth and B. R. Sullivan; "Shock Response of Rock atPressures Below 30 Kilobars"; Technical Report No. 6-802, November 1967;U. S. Army Engineer Waterways Experiment Station, CE, Vicksburg, Miss.;Unclassified.

178

Page 181: REPORT NO. 6-763 - digital.library.unt.edu

DISTRIBUTION LIST FOR TECHNICAL REPORT NO. 6-763

No. ofAddress Copies

Army

Chief of Engineers, Department of the Army, Washington, D. C. 20314ATTN: ENGME-RD 1

ENGME 1ENGCW-E 1ENGCW-Z 1ENGMC-E 1ENGMC-ED 1ENGAS-I 1ENGAS-I, Library 1ENGNA 1

Chief of Research and Development, Department of the Army, Washington, D. C. 20310 3 copies ofATTN: Director of Army Technical Information Form 1473

Chief of Research and Development, Department of the Army, Washington, D. C. 20310ATTN: CRDNCB 1

CRDES 1

Division Engineers, U. S. Army Engineer Divisions, Continental United States Cy to ea

Commandant, U. S. Army Air Defense School, Fort Bliss, Tex. 79906 1

Commandant, U. S. Army Command & General Staff College, Fort Leavenworth, Kans. 66027 1ATTN: Archives

Commandant, Army War College, Carlisle Barracks, Pa. 17013 1ATTN: Library

Commanding General, Aberdeen Proving Ground, Aberdeen, Md. 21005 4ATTN: Director, Ballistic Research Laboratories

Commanding General, The Engineer Center, Fort Belvoir, Va. 22060 1ATTN: Assistant Commandant, Engineer School

Commanding General, USA Missile Command, Huntsville, Ala. 35809 1

Commanding General, USA Munition Command, Dover, N. J. 07801 1

Commanding General, U. S. Continental Army Command, Fort Monroe, Va. 23351 1

Commanding General, U. S. Army Materiel Command, Washington, D. C. 20310 2ATTN: AMCRD-DE-N

Commanding Officer, Picatinny Arsenal, Dover, N. J. 07801 1ATTN: ORDBB-TK

Commanding Officer, U. S. Army Aviation Materiel Laboratories, Fort Eustis, Va. 23604 1

Commanding Officer, U. S. Army Combat Developments Command, Institute of Nuclear Studies 2Fort Bliss, Tex. 79916

Commanding Officer, U. S. Army Mobility Equipment Research and Development Center 1Fort Belvoir, Va. 22060ATTN: Technical Documents Center, Building 315

Commanding Officer, U. S. Army Nuclear Defense Laboratory, Edgewood Arsenal 1Edgewood, Md. 21040ATTN: Technical Library

179

Page 182: REPORT NO. 6-763 - digital.library.unt.edu

No. ofAddress Copies

Army (Continued)

Department of the Army, CE Ballistic Missile Construction Office, P. O. Box 4187 1Norton AFB, Calif. 92409

Director of Civil Defense, Office of the Secretary of the Army, Washington, D. C. 20310 2ATTN: Mr. George Sisson (RE-ED)

Director, Nuclear Cratering Group, U. S. Army Corps of Engineers, Lawrence Radiation Laboratory 1P. O. Box 808, Livermore, Calif. 94550

Division Engineer, U. S. Army Engineer Division, Ohio River, P. O. Box 1159, Cincinnati, Ohio 45201 1ATTN: ORDED-FL

Technical Library, USAMERDC, Bldg 314, Fort Belvoir, Va. 22060 1

Director, U. S. Army CRREL, P. O. Box 282, Hanover, N. H. 03755 1ATTN: Mr. K. Boyd

Director, U. S. Army Construction Engineering Research Laboratory, P. O. Box 4005, Champaign, Ill. 61820ATTN: Library 1

Dr. D. Birkimer 1

District Engineer, U. S. Army Engineer District, Omaha, 6012 U. S. Post Office and Court House 1215 N. 17th Street, Omaha, Nebr. 68101ATTN: MROGS-B

President, U. S. Army Air Defense Board, Fort Bliss, Tex. 79906 1

Superintendent, U. S. Military Academy, West Point, N. Y. 10996 2ATTN: Library

U. S. Army Engineer Division, Missouri River, P. O. Box 103, Downtown Station, Omaha, Nebr. 68101 1ATTN: Mr. L. Underwood

Navy

Chief of Naval Operations, Navy Department, Washington, D. C. 20350ATTN: OP-75 2

OP-03EG 1

Chief of Naval Research, Navy Department, Washington, D. C. 30390 1ATTN: Code 118

Commandant of the Marine Corps, Navy Department, Washington, D. C. 20380 2ATTN: Code A04E

Commander, Naval Facilities Engineering Command, Navy Department, Washington, D. C. 20370ATTN: Code 04 1

Code 03 1

Commander, Naval Ordnance Systems Command, Washington, D. C. 20360 1

Commanding Officer, Nuclear Weapons Training Center, Atlantic Naval Base, Norfolk, Va. 23511 1ATTN: Nuclear Warfare Department

Commanding Officer, Nuclear Weapons Training Center, Pacific, Naval Station, North Island 2San Diego, Calif. 92136

Commanding General, Marine Corps Development and Education Command, Quantico, Va. 22134 2ATTN: Director, Development Center

Commanding Officer & Director, U. S. Naval Civil Engineering Laboratory, Port Hueneme, Calif. 93041 2ATTN: Code L31

180

Page 183: REPORT NO. 6-763 - digital.library.unt.edu

No. ofAddress Copies

Navy (Continued)

Commanding Officer, U. S. Naval Civil Engineer Corps Officer School, U. S. Naval Construction Battalion 1Center, Port Hueneme, Calif. 93041

Commanding Officer, U. S. Naval Damage Control Training Center, Naval Base 1Philadelphia, Pa. 19112ATTN: ABC Defense Course

Commanding Officer, U. S. Naval Weapons Evaluation Facility, Kirtland Air Force Base 1Albuquerque, N. Mex. 87117ATTN: Code WEVS

Commanding Officer, U. S. Naval Weapons Laboratory, Dahlgren, Va. 22448 1ATTN: TE

Commander, U. S. Naval Ordnance Laboratory, Silver Spring, Md. 20910ATTN: 241 1

243 1240 1

Commander, U. S. Naval Ordnance Test Station, China Lake, Calif. 93555 1

Director, U. S. Naval Research Laboratory, Washington, D. C. 20390 1

President, U. S. Naval War College, Newport, R. I. 02840 1

Special Projects, Navy Department, Washington, D. C. 20360 1ATTN: SP-272

Superintendent, U. S. Naval Postgraduate School, Monterey, Calif. 93940 1

Air Force

Air Force Flight Dynamics Laboratory, Wright-Patterson AFB, Dayton, Ohio 45433 1ATTN: Mr. Frank Janik, Jr.

Air Force Institute of Technology, AFIT-L, Building 640, Wright-Patterson AFB, Ohio 45433 1

Commander, Air Force Logistics Command, Wright-Patterson AFB, Ohio 45433 2

Air Force Systems Command, Andrews Air Force Base, Washington, D. C. 20331 1ATTN: SCTSW

Air Force Technical Applications Center, Department of the Air Force, Washington, D. C. 20333 1

Air Force Weapons Laboratory, Kirtland AFB, N. Mex. 87117ATTN: Library 2

WLDC 1WLDC/R. W. Henny 1

Director, Air University Library, Maxwell AFB, Ala. 36112 2

Commander, Strategic Air Command, Offutt AFB, Nebr. 68113 1ATTN: OAWS

Commander, Tactical Air Command, Langley AFB, Va. 23365 1ATTN: Document Security Branch

Space and Missile Systems Organization, Norton AFB, Calif. 92409 1ATTN: SAMSO (SMQNM)

Headquarters, USAF, Washington, D. C. 20330 1ATTN: AFRSTG

181

Page 184: REPORT NO. 6-763 - digital.library.unt.edu

No. ofAddress Copies

Air Force (Continued)

Director, Air Research and Development Command Headquarters, USAF 1Washington, D. C. 20330ATTN: Combat Components Division

Director of Civil Engineering, Headquarters, USAF, Washington, D. C. 20330 1ATTN: AFOCE

Director, U. S. Air Force Project RAND, Via: U. S. Air Force Liaison Office, The RANDCorporation, 1700 Main Street, Santa Monica, Calif. 90406ATTN: Library 1

Dr. Harold L. Brode 1Dr. Olen A. Nance 1

Other DOD Agencies

Administrator, National Aeronautics & Space Administration, 400 Maryland Avenue, S. W. 1Washington, D. C. 20546

Assistant to the Secretary of Defense (Atomic Energy), Washington, D. C. 20301 1

Commandant, Armed Forces Staff College, Norfolk, Va. 23511 1ATTN: Library

Commandant, National War College, Washington, D. C. 20310 1ATTN: Class Rec. Library

Commandant, The Industrial College of the Armed Forces, Fort NcNair 1Washington, D. C. 20310

Commander, Test Command, DASA, Sandia Base, Albuquerque, N. Mex. 87115 2ATTN: TCCOM, TCDT

Defense Documentation Center (DDC), Cameron Station, Alexandria, Va. 22314 (NO TOP SECRET TO 20THIS ADDRESS)ATTN: Mr. Myer Kahn

Director, Defense Atomic Support Agency, Washington, D. C. 20301 5ATTN: SPSS

Director of Defense Research and Engineering, Washington, D. C. 20301ATTN: Technical Library 1

Mr. Frank J. Thomas 1

Director, Advanced Research Projects Agency, Washington, D. C. 20301 1ATTN: NTDO

Director, Defense Intelligence Agency, Washington, D. C. 20301ATTN: DIAAP-IK2 1

DIA-AP8B-l 1

Director, Weapons Systems Evaluation Group, Washington, D. C. 20305 1

Langley Research Center, NASA, Langley Field, Hampton, Va. 23365 1ATTN; Mr. Philip Donely

Manager, Albuquerque Operations Office, USAEC, P. O. Box 5400, Albuquerque, N. Mex. 87115 1

Manager, Nevada Operations Office, USAEC, P. O. Box 1676, Las Vegas, Nev. 89101 1

National Aeronautics & Space Administration, Man-Spacecraft Center, Space Technology Division 1Box 1537, Houston, Tex. 77001

National Military Command System Support Center, Pentagon BE 685, Washington, D. C. 20301 1ATTN: Technical Library

182

Page 185: REPORT NO. 6-763 - digital.library.unt.edu

No. ofAddress Copies

Other DOD Agencies (Continued)

U. S. Atomic Energy Commission, Washington, D. C. 20545 1ATTN: Chief, Classified Tech Lib, Tech Information Service

U. S. Documents Officer, Office of the United States National Military Representative-SHAPE 1APO New York 09055

Other Agencies

Aerospace Corporation, 1111 E. Mill Street, San Bernardino, Calif. 92408 1ATTN: Dr. M. B. Watson

Agbabian-Jacobsen Associates, Engineering Consultants, 8939 South Sepulveda Boulevard 1Los Angeles, Calif. 90045

Applied Theory, Inc., 1728 Olympic Blvd, Santa Monica, Calif. 90404 1ATTN: Dr. John G. Trulio

AVCO Corporation, Research and Advanced Development Division, 201 Lowell Street 1Wilmington, Mass. 01887ATTN: Mr. R. E. Cooper

Battelle Memorial Institute, 505 King Avenue, Columbus, Ohio 43201 1ATTN: Dr. P. N. Lamori

Bell Telephone Laboratories, Inc., Whippany Road, Whippany, N. J. 07981 1ATTN: Mr. R. W. Mayo

The Boeing Company, P. O. Box 3707, Seattle, Wash. 98124 1ATTN: Technical Library

Defence Research Establishment, Suffield, Ralston, Alberta, Canada 1

Denver Mining Research Center, Building 20, Denver Federal Center, Denver, Colo. 80225 1ATTN: Dr. Leonard A. Obert

Dynamic Science Corporation, 1900 Walker Avenue, Monrovia, Calif. 91016 1ATTN: Dr. J. C. Peck

Edgerton, Germeshausen & Grier, Inc., 95 Brookline Avenue, Boston, Mass 02129 1ATTN: D. F. Hansen

Engineering Physics Company, 12721 Twinbrook Parkway, Rockville, Md. 20852ATTN: Dr. Vincent J. Cushing 1

Mr. W. Danek 1

General American Transportation Corporation, General American Research Division 17449 North Natchez Avenue, Niles, Ill. 60648ATTN: Dr. G. L. Neidhardt

General Electric Company, Missile and Space Vehicle Department, Valley Forge Space Technology 1Center, Goddard Boulevard, King of Prussia, Pa. 19406

General Electric Company, TEMPO, 816 State Street, Santa Barbara, Calif. 93101 1ATTN: Mr. Warren Chan (DASIAC)

Chief, Structural and Applied Mechanics Branch, Bureau of Public Roads, Federal Highway 1Administration, Washington, D. C. 20591ATTN: Mr. F. J. Tamanini

IIT Research Institute, 10 West 35th Street, Chicago, Ill. 60616 1ATTN: Dr. T. Schiffman

183

Page 186: REPORT NO. 6-763 - digital.library.unt.edu

No. ofAddress Copies

Other Agencies (Continued)

Lockheed Missile and Space Company, Lockheed Aircraft Corporation, 111 Lockheed Way 1Sunnyvale, Calif. 94086ATTN: Dr. R. E. Meyerott

Los Alamos Scientific Laboratory, P. O. Box 1663, Los Alamos, N. Mex. 87544 1ATTN: Report Librarian

Physics International Company, 2700 Merced Street, San Leandro, Calif. 94577ATTN: Dr. Charles Godfrey 1

Mr. Fred M. Sauer 1

Sandia Laboratories, P. O. Box 5800, Albuquerque, N. Mex. 87115 1ATTN: Mr. C. W. Gulich

Southwest Research Institute, 8500 Culebra Road, San Antonio, Tex. 78228 1ATTN: Dr. Robert C. DeHart

General Atomic, Division of General Dynamic Corp., P. O. Box 111, 10955 John Jay Hopkins Dr. 1San Diego, Calif. 92112ATTN: Dr. K. D. Pyatt, Jr.

URS Corporation, 1811 Trousdale Drive, Burlingame, Calif. 94010 2ATTN: Mr. Harold Mason

Paul Weidlinger, Consulting Engineer, 110 East 59th Street, New York, N. Y. 10022 1ATTN: Dr. M. L. Baron

College and Universities

University of Arizona, Tucson, Ariz. 85721ATTN: Dr. Donald A. DaDeppo, Department of Civil Engineering 1

Professor Bruce G. Johnston, Dept of Civil Engineering 1Dr. George Howard, College of Engineering 1

University of California, Lawrence Radiation Laboratory, P. O. Box 808 2Livermore, Calif. 94550ATTN: Technical Information Division

University of Illinois, Urbana Campus, Department of Civil Engineering, Urbana, Ill. 61801 1ATTN: Professor N. M. Newmark

Massachusetts Institute of Technology, Division of Sponsored Research, 77 Massachusetts AvenueCambridge, Mass. 02139ATTN: Dr. Robert J. Hansen 1

Dr. Robert V. Whitman 1

University of Michigan, Civil Engineering Department, Ann Arbor, Mich. 48104 1ATTN: Professor Leo Legatski

University of New Mexico, Eric H. Wang Civil Engineering Research Facility, P. O. Box 188 2University Station, Albuquerque, N. Mex. 87106ATTN: Dr. Robert Crist

University of Texas, Balcones Research Center, Austin, Tex. 78712 1ATTN: Dr. J. Neils Thompson

The George Washington University, Nuclear Defense Design Center, School of Engineering and Applied 1Science, Washington, D. C. 20006

University of Virginia, Charlottesvillle, Va. 22901 1ATTN: Dr. F. C. McCormick

184

Page 187: REPORT NO. 6-763 - digital.library.unt.edu

UnclassifiedSecurity Classification

DOCUMENT CONTROL DATA - R & D(Security classification of title, body of abstract and indexing annotation must be entered when the overall report is claailied)

1. ORIGINATING ACTIVITY (Corporate author) 12a. REPORT SECURITY CLASSIFICATION

UnclassifiedU. S. Army Engineer Waterways Experiment Station 2. GROUP

Vicksburg, Mississippi

3. REPORT TITLE

SHOCK-ABSORBING MATERIALS; Report 2, CELLULAR CONCRETE AS A BACKPACKING MATERIAL

4. DESCRIPTIVE NOTES (Type of report and inclusive dates)

Report 2 of a series9. AUTHOR(S) (First name, middle initial, laat name)

George C. Hoff

6. REPORT DATE 7a. TOTAL NO. OF PAGES 7b. NO. OF REFS

June 1971 184 21Sa. CONTRACT OR GRANT NO. 9a. ORIGINATOR'S REPORT NUMBER(S)

b. PROJECT NO. Technical Report No. 6-763, Report 2

c- Nuclear Weapons Effects Research 9b. OTHER REPORT NO(S) (Any other numbers that may be assignedSubtask SC 210

d.

10. DISTRIBUTION STATEMENT

Approved for public release; distribution unlimited..

11. SUPPLEMENTARY NOTES 12. SPONSORING MILITARY ACTIVITY

Defense Atomic Support AgencyWashington, D. C.

13. ABSTRACT

The use of low-density cellular concrete, having an oven-dry unit weight of 50 pcf orless, as a backpacking material for deeply buried protective structures was studied.Cellular concrete was found to be suitable for this type of application. A number ofphysical properties of cellular concrete were determined to provide input to designcodes. Constrained compressive crushing stress levels from 20 to 1,000 psi for slowrates of loading were observed. Rapid-loading tests and equation of state measure-ments were also made to determine the rate sensitivity of the concrete. Compressionalwave velocities from 2,000 to 6,000 ft/sec were also measured. Modulus of elasticityvalues from 20,000 to 220,000 psi were measured for concretes in the as-cast conditionwith respect to moisture. Flexural strength to compressive strength ratios from 0.16to 0.33 were observed. Early age stiffening characteristics of cellular concrete werealso studied. Some design procedures based on the data analysis are suggested. Somepossible areas of difficulty during prototype use of cellular concrete as a backpack-ing, such as lift heights, cold joints, temperature problems, and water-saturationproblems, are also explored. Lift heights should not exceed those that cause an in-crease in density over the desired density by more than a stipulated amount in thelower portion of the lift. The effects of joint roughness and curing on the jointperformance are minimal. Temperatures over about 120 F tend to cause collapse of thestructure of unhardened low-density cellular concrete. In a free-water environment,saturation of the cellular concrete is inevitable unless steps are taken to preventthe water from reaching the concrete. Suggestions for doing this are offered.

DD po 473 NEPLACKS P FORM 17. 1 JAN 4. WHICH IsI.Nov es 'OS'OLK "FOR ARMY USE. 185 UnclassifiedSecurity Clessification

Page 188: REPORT NO. 6-763 - digital.library.unt.edu

UnclassifiedSecurity Classification

114. LINK A LINK [ LINK C

ROLE WT ROLE WT ROLE WT

Backpacking

Cellular concretes

Shock absorption

186

- I I I - I -

UnclassifiedSecurity Classification

Page 189: REPORT NO. 6-763 - digital.library.unt.edu
Page 190: REPORT NO. 6-763 - digital.library.unt.edu
Page 191: REPORT NO. 6-763 - digital.library.unt.edu

w

&

Page 192: REPORT NO. 6-763 - digital.library.unt.edu

TIversity of T208 W. Rorin Stro-UWbagaa trvQj ,