report no. gr 82-9, hydraulic model study of choke canyon ... … · 4 title and subtitle 5 report...

39
HYDRAULIC MODEL STUDY OF CHOKE CANYON DAM SPILLWAY AND STILLING BASIN August 7982 Engineering and Research Center S. Department of the Interior Bureau of Reclamation Division of Research Hydraulics Branch

Upload: others

Post on 06-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

HYDRAULIC MODEL STUDY OF CHOKE CANYON DAM SPILLWAY AND STILLING BASIN

August 7982 Engineering and Research Center

S. Department of the Interior Bureau of Reclamation

Division of Research Hydraulics Branch

Page 2: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

4 T I T L E A N D S U B T I T L E 5 R E P O R T 3 A T E

Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin

7 A U T H O R I S I 8 . P E R F O R M I N G O R G A N I Z A T I O N R E P O R T N O .

Robert L. George GR-82-9

9 P E R F O R M I N G O R G A N I Z A T I O N N A M E A N D A D D R E S S 1 1 0 . WORK U N I T N O .

Bureau of Reclamation Engineering and Research Center 1 1 . C O N T R A C T O R G R A N T N O .

Denver, Colorado 80225 13. T Y P E O F ' ? € P O R T A N D P E R I O D

C O V E R E D 2 S P O N S O Q I N G A G E N C Y N A M E A N D A D D R E S S

Same

1 1 4 . S P O ~ ! S O R I I I G A G E N C Y C O D E

I ' 5 . S U P P L E M E N T A R Y N O T E S

Microfiche and or hard copy available at the E&R Center, Denver, CO

16 A B S T R A C T

A 1:80 scale hydraulic model of the Choke Canyon Dam spillway and stilling basin was studied. The dam will be 35 meters high and have a crest length of 5640 meters. The spillway chute is 112.2 meters wide and has a Froude number of about 4.4 at the stilling basin entrance. The stilling basin was designed to criteria developed for low Froude number flows. A modified entrance channel was developed as the model was tested. Stilling basin walls were shortened as a result of model studies. A 14-meter apron having 32 meters of riprap extended downstream from the end sill was recommended. The design worked well for all discharges and scour was limited to an area downstream from the riprap.

17. K E Y WORDS A N D D O C U M E N T A X A L Y S I S

3 . D E S C R I P T O R S - - / *scour/ approach channelslspillway approach1 *guide walls1 slopes1 *stilling basin

5 . I D E N T I F I E R S - - Choke Canyon Dam, TX

18. D l S T R l ! 3 U T I O N 5 7 A T E M E N T 19 S E C U R I T Y C L A S S 2 1 . N O . O F P A G E ! ( T H I S R E P O R T 1

U N C L A S S I F I E D 30 23. S E C U R I T Y C L A S S 2 2 . P R I C E

( T W ; P A G E )

J

- G P O 831 - 3 1 6

Page 3: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

GR-82-9

HYDRAULIC MODEL STUDY OFCHOKE CANYON DAM

SPILL WAY & STILLING BASIN

byRobert L. George

.81 METRIC

Hydraulics BranchDivision of Research

Engineering and Research CenterDenver, Colorado

August 1982

UNITED STATES DEPARTMENT OF THE INTERIOR * BUREAU OF RECLAMATION

Page 4: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

ACKNOWLEDGMENTS

The hydraulic model study described in this report was

conducted in the Hydraulic Structures Section and was

reviewed by E. 1. Carlson, Head of the Hydraulic

Research Section, in the Hydraulics Branch. Engineers

involved in design of Choke Canyon Dam made valuable

suggestions during the study.

As the Nation's principal conservation agency, the Department of theInterior has responsibility for most of our nationally owned publiclands and natural resources. This includes fostering the wisest use ofour land and water resources, protecting our fish and wildlife, preser-ving the environmental and cultural values of our national parks andhistorical places, and providing for the enjoyment of life through out-door recreation. The Department assesses our energy and mineralresources and works to assure that their development is in the bestinterests of all our people. The Department also has a major respon-sibility for American Indian reservation communities and for peoplewho live in Island Territories under U.S. Administration.

Page 5: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

CONTENTS

Acknowledgments. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Purpose. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Conclusions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

The Model. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Model similitude parameters. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Model tests. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Preliminary tests. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Entrance modifications. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Stilling basin. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Radial gate calibration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Safety boom. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Bibliography. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

FIGURES

1 Location map for Choke Canyon Dam. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

2 Sketch of low Froude number stilling basin. . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3 Drawing of the model. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

4 Model as designed originally. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Sa Scour around left inlet wall, Qp = 7080 m3/s tested for 8.94 hours. . . . . . . . . . .

5b Scour around right inlet wall, Qp = 7080 m3/s for 8.94 hours. . . . . . . .. . . . . . .

6 Scour pattern with straight dikes, Qp = 7080 m3/s tested for 8.94 hours. . . . . . .

7 Sketch of model with 30° wingwalls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

iii

Page

11

1

1

2

23

445678

9

10

10

11

13

14

14

15

16

Page 6: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

CONTENTS-Continued

Figure

8 Scour around right 30° wingwall with 100-m dike,Qp = 7080 m3/s for 8.94 hours. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

9 Scour around left 30° wingwall with 100-m dike, Qp = 7080 m3/s for8.94 hours. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

10 Scour in vicinity of 30° wingwall with 200-m dike,Qp = 7080 m3/s for 8.94 hours. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

lla Scour with segmented right inlet wall, Qp = 7080 m3/s for 8.94 hours. . . . . . . . .

Scour with segmented left inlet wall, Qp = 7080 m3/s for 8.94 hours. . . . . . . . . .llb

12 Model discharging 0.083 m3/s(Qp = 4750 m3/s),equivalent to1000-year flood. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

13a Scour from 300-mm (24 m prototype) radius inlet wall with 400-mm wall(32 m prototype) extension at 90° to left inlet wall. . . . . . . . . . . . . . . . . . . . . . .

13b Scour from 300-mm (24 m prototype) radius inlet wall with 21O-mm(16.8 m prototype) extension at 120° to right inlet wall. . . . . . . . . . . . . . . . . . .

14 Recommended design of inlet walls and approach channel. . . . . . . . . . . . . . . . .

15a Scour pattern with sidewalls shortened 5.48 m and original apron,Qp = 7080 m3/sfor 8.94 hours. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

15b Scour pattern with sidewalls and apron shortened 5.48 m,Qp = 7080 m3/s for 8.94 hours. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

16 Scour pattern with 2-1/2:1 side slopes around sidewalls and basinshortened 5.48 m, Qp = 7080 m3/s for 8.94 hours. . . . . . . . . . . . . . . . . . . . . . .

17 Long-term scour test, Qp = 7080 m3/s for 53.7 hours. . . . . . . . . . . . . . . . . . . . . .

18 Scour after 8.94 hours at Qp = 7080 m3/s with 14-m apron. . . . . . . . . . . . . . . . .

19 Scour after 8.94 hours with 14-m apron and 32 m of riprapdownstream, Qp = 7080 m3/s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

iv

Page

17

17

18

19

19

20

21

21

22

23

23

24

24

25

25

Page 7: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

CONTENTS-Continued

Figure

20 Scour after 33.5 hours, 14-m apron and 32-m of rip rap downstream,Qp = 7080 m3/s, (3.75 h model) . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . .

21 Scour after 49.2 hours, 14-m apron and 32 m of riprap downstream,Qp = 7080 m3/s, (5.50 h model) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

22 Final design of Choke Canyon Dam stilling basin. . . . . . . . . . . . . . . . . . . . . . . . .

23 Spillway discharge curves. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

24 Sketch of Choke Canyon Dam model safety boom. . . . . . . . . . . . . . . . . . . . . . . .

25 Choke Canyon Dam safety boom in place, Qp = 7080 m3/s . . . . . . . . . . . . . . . . .

v

Page

26

26

27

29

30

30

Page 8: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI
Page 9: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

PURPOSE

A hydraulic model study of Choke Canyon Dam spillway and stilling basin, requested by

the Embankment Dams Section, Dams Branch designers, was performed to provide in-

formation needed for design. The model study was initiated to verify stilling basin

design, flow conditions, and scour in the spillway approach channel. A spillway rating

curve for the seven 15 000- by 7230-mm radial gates was developed. Scour in the

downstream channel was studied.

INTRODUCTION

The damsite is located on the Frio River in south central Texas about midway between

Corpus Christi and San Antonio. It is 5.6 km above the confluence of the Frio and

Nueces Rivers (fig. 1).

The main purpose of the dam is to provide municipal and industrial water to Corpus

Christi and adjoining areas. The reservoir also will provide some flood control and

recreational benefits. Choke Canyon reservoir will have a total capacity of 880.6 X

106m3 at the normal water surfce of 67.21 m. The active capacity will be 860 X 106 m3.

An embankment 35 m high and 5640 m long will form the reservOIr. The embankment

will be a homogeneous earthfill. A 112.8-m-wide concrete spillway will pass major flood

flows. Immediately downstream from the stilling basin, the outlet channel turns to the

right and conveys flow to the original river channel.

A 51. Anthony Falls [1]* type stilling basin, a design developed at St. Anthony Falls

Hydraulic Laboratory using chute blocks, basin floor blocks and an end sill, was con-

sidered during preliminary model calculations. It was not used because a scour hole

would develop downstream and deep scour in the outlet channel was unacceptable.

*Numbers in brackets refer to the bibliography.

Page 10: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Drawing model dimensions are in millimeters unless noted and prototype dimensions are

shown in meters unless noted.

CONCLUSIONS

1. A low Froude number stilling basin was designed and tested in a hydraulic model for

the choke Canyon Dam (fig. 2). As designed, the spillway and stilling basin operated ex-

cellently. During model tests, a modified stilling basin was developed that eliminated

5.48 m of the prototype sidewalls and retained a 14-m apron, resulting in a lower cost.

2. The design recommended for Choke Canyon Dam has a concrete apron 14 m long,

downstream from the end of the stilling basin, followed by a 32-m-Iong section of riprap.

3. The approach channel recommended for the prototype spillway is 125 m wide at

elevation 54.40 meters mean sea level. The inlet walls and approach channel are shown

on figure 14.

4. The spillway discharge rating curve with all 7 radial gates opened equally is shown

on figure 23.

THE MODEL

The model was constructed to a length scale of 1:80 and is shown on figure 3. The

original model inlet walls and entrance channel were modified to obtain lower velocities

and to eliminate excessive scour along the inlet walls at each side of the spillway en-

trance. Figure 4 shows the model as designed originally. The head box contained the

reservoir portion of the model. Topography of the reservoir was formed by smoothing the

sand to the same shape as the prototype.

'1""'

Page 11: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

The prototype approach channel is a trapezoidal channel having a bottom width of

125.0 m and 2:1 side slopes. The entrance channel was set at a prototype elevation of

54.40 m.

The spillway is an overflow crest having seven 15 000- by 7230-mm radial gates. Spillway

width is 112.2 m. A chute built on a 3-percent slope is located immediately downstream

of the gate section and is followed by a vertical curve which connects to the stilling basin.

The stilling basin was designed to Bureau of Reclamation criteria [2] developed for low

Froude number flows.

Below the stilling basin, the outlet channel curves to the right. The bottom width is

112.2 m and the side slopes are 2:1. There is no slope to the outlet channel which is

at elevation 41.0 m. About 450 m of the prototype channel downstream from the

stilling basin were included in the model. This reach modeled the effect of the

curved channel on the stilling basin.

Model Similtude Parameters

The model was constructed to an undistorted scale of 1:80 and was evaluated usmg

the Froude law of similtude. Model discharges were scaled from the prototype by

the following relationship:

where(

1

)

5/2Qm =

80Qp (1)

Qm = model discharge

Qp = prototype discharge

The maximum Qp of 7080 m3/s was represented by a 0.124-m3/s Qm discharge.

Spillway velocities and discharges were represented accurately at the 1:80 model

3

Page 12: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

scale. All model elevations were measured with respect to mean sea level (metric

scale).

Sand used in the model was scaled-based on settling velocity [3]-to nearly the

same size as the largest soil and rock at the damsite. Smaller size sediment at the

damsite was less than 75 pm (passing a No. 200 seive). The laboratory had a limited

amount of 75 pm sediment and it was placed at the downstream end of the stilling

basin. Consequently, scour around the inlet walls indicated where scour would

occur in the prototype for the largest material and these areas should be protected.

Scour below the stilling basin represented the expected prototype conditions, and

scour holes in the model bed indicated places that would need to be modified or

protected.

MODEL TESTS

Preliminary Tests

Initial tests indicated that. the spillway and stilling basin functioned well for all

discharges. However, a sharp drawdown occurred around the inlet walls of the en-

trance channel and scour occurred at the base of the walls and deposited sediment in

the stilling basin. All tests for comparing scour are for a maximum Qm = 0.124 m3/s

for 1 hour (Qp = 7080 m3/s for 8.94 hours) unless otherwise noted. One hour model

time was selected because the rate of the material removed had stabilized and little

scour (model observation) appeared to occur after an hour. Figures 5a and 5b show

the extent of scour along the inlet walls for the model as designed originally. As a

result of this scour, alternate designs for the approach channel and walls were

developed and tested.

4

Page 13: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Entrance Modifications

The first entrance modification proposed by the designers was a dike formed by ex-

tending the 2:1 side slopes above the normal water surface. Figure 6 shows scour

around the inlet walls and erosion of the dikes. The approach velocity was too high

in the channel and the dike was destroyed.

A second alternative was straight wingwalls at 300 to the approach channel con-

nected by circular arcs as shown on figure 7. Neither the straight wingwalls nor

wingwalls having various lengths of dikes was acceptable as shown on figures 8

through 10. The approach channel was subsequently widened to 125 m and made

1.683 m deeper to decrease the entrance velocities.

The deepened and widened approach channel decreased the velocity enough to

minimize the transport of sediment into the stilling basin. A segmented wall

resembling an ellipse was installed in the model and the maXImum model discharge

of 0.124 m3/s (Qp = 7080 m3/s) was run for 1 hour. Scour was significantly less

than any previous run. Figures lla and llb show the smaller amount of scour. Next

a 300-mm (24-m prototype) radius arc for 1200 was installed having a 3:1 side slope

at the wall and a transition to the 2:1 side slopes in 200 mm (16-m prototype). After

this configuration was operated for several hours, the 3:1 slope had scoured to

nearly a 3-112:1 slope. Therefore, the side slopes were cut to 3-1/2:1 at the inlet

walls and then transitioned to 2:1 side slopes upstream in a length of 400 mm (32-m

prototype). Figure 12 shows a discharge of 0.083 m3/s (Qp = 750 m3/s), the

equivalent of a 1000-year flood with the 3-1/2:1 side slopes. Note that the

drawdown is minimal. Scour from the maximum probable flood Qm = 0.124 m3/s

(Qp = 7080 m3/s) was slight (figs. 13a and 13b).

The design recommended for the inlet channel is the deepened and widened channel

having 24.0-m radius inlet walls and short wingwalls extending beyond the curves.

Figure 14 shows the recommended design of the inlet walls, and approach and en-

trance channels.

5

Page 14: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Stilling Basin

The original design of the stilling basin is shown on figure 2. This design worked

well throughout the range of discharges tested with less than 2 meters of vertical

scour downstream from the apron. Several different floods were tested, from less

than the lO-year return frequency up to the maximum probable flood of 7080 m3/s.

The largest scour occured at Qm = 0.124 m3/s (Qp = 7080 m3/s) discharge and had

stabilized in about an hour of model time (8.94 h prototype). There was a slight

asymmetry to the scour pattern with more scour occurring on the left side of the

channel.

The designers suggested a test be performed usmg a discharge simulating a

lOOO-year flood (4750 m3/s) and that the length of the stilling basin site walls be

shortened so that this flood would still be contained in the basin. Tests were made

with stilling basin sidewalls shortened 5.48 m. These tests developed scour holes

downstream from the end sill, with the scour hole on the left side about 2 m deeper

than the right side. Figure 15 compares the scour with the sidewall cut back 5.48 m

from the original design with and without the downstream apron. Note the scour

hole on the left is about 2 m deeper than the right. Each contour line represents a

I-m difference in elevation.

As water flowed around the channel bend downstream from the stilling basin, it

. became superelevated and caused an upstream current along the left bank between'

the curve and the stilling basin. The upstream current mixed with water leaving the

stilling basin, and a scour hole was caused by the resulting vortex.

Several tests were made to obtain a solution to the scour along the left side of the

channel.

A 2-1/2:1 side slope around the inlet sidewall replaced the 2:1 side slope. A transition

to the 2:1 slope downstream from the stilling basin was made in 400 mm (32-m pro-

totype). Figure 16 shows the scour from a 1- hour test at the maximum probable

6

Page 15: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

flood Qm = 0.124 m3/s (Qp = 7080 m3/s). Figure 17 shows the scour from a model

discharge that was allowed to run until equilibrium was obtained. This run

represented 53.7 hours in the prototype (6-h model).

A wall 14 m long along the left side provided an acceptable solution but was longer

than the original design. A more economical solution was desired. A low wall,S m

high and 14 m long, also was tried unsuccessfully.

Because scour was occurring along the floor of the stilling basin, the apron was ex-

tended 14 m downstream. Scour for this design with discharge of 7080 m3/s for 8.94

hours was acceptable (fig. 18). A 32-m-Iong blanket of riprap was placed

downstream of the apron for additional protection. This configuration was tested

and scour measurements were observed at 1, 3.75, and 5.50 hours model times (8.9,

33.5, 49.2 h prototype). Figures 19 to 21 show the scour that resulted from these

tests. Performance of the basin shortened by 5.48 m from the original design, and

with rip rap installed downstream was acceptable for the maximum design flood and

smaller floods.

The recommended design for the stilling basin was a concrete apron extending 14 m

beyond the end sill with a 32-m-Iong rip rap section downstream. The final design

(fig. 22) has an 8.8-m apron and 30 m of riprap. A savings was realized from the

shortened walls.

Radial Gate Calibration

The radial gate seat is 0.214 m below the spillway crest. All gate openmgs are

referenced to vertical distances above the crest for the model tests. Gate opening

curves at I-m intervals and for free discharge, were developed and scaled to pro-

totype values (fig. 23). Figure 23 represents the discharge capacity curve for the

gated structure with all seven gates opened equally. Gates were set at a particular

7

Page 16: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

gate opening and the model was operated at a constant discharge until the water

surface remained stable. Data were recorded for the water surface and discharge.

Several discharges were tested for each gate opening to develop each curve. Each

discharge was run for about 1 hour model time-generally long enough to maintain

a stable water surface upstream of the dam in the model.

Safety Boom

A safety boom upstream from the spillway crest was designed and tested in the

model. The final layout for the safety boom and anchors is shown on figure 24.

Figure 25 shows the safety boom at the maximum probable flood, Qm - 0.124 m3/s

(Qp = 7080-m3/s). After the model boom was installed, several tests were run to

check if the safety boom affected the discharge curves. The discharge curves did not

change.

8

Page 17: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

flood Qm = 0.124 m3/s (Qp = 7080 m3/s). Figure 17 shows the scour from a model

discharge that was allowed to run until equilibrium was obtained. This run

represented 53.7 hours in the prototype (6-h model).

A wall 14 m long along the left side provided an acceptable solution but was longer

than the original design. A more economical solution was desired. A low wall,S m

high and 14 m long, also was tried unsuccessfully.

Because scour was occurring along the floor of the stilling basin, the apron was ex-

tended 14 m downstream. Scour for this design with discharge of 7080 m3/s for 8.94

hours was acceptable (fig. 18). A 32-m-Iong blanket of riprap was placed

downstream of the apron for additional protection. This configuration was tested

and scour measurements were observed at 1, 3.75, and 5.50 hours model times (8.9,

33.5, 49.2 h prototype). Figures 19 to 21 show the scour that resulted from these

tests. Performance of the basin shortened by 5.48 m from the original design, and

with riprap installed downstream was acceptable for the maximum design flood and

smaller floods.

The recommended design for the stilling basin was a concrete apron extending 14 m

beyond the end sill with a 32-m-Iong rip rap section downstream. The final design

(fig. 22) has an 8.8-m apron and 30 m of riprap. A savings was realized from the

shortened walls.

Radial Gate Calibration

The radial gate seat is 0.214 m below the spillway crest. All gate openmgs are

referenced to vertical distances above the crest for the model tests. Gate opening

curves at 1-m intervals and for free discharge, were developed and scaled to pro-

totype values (fig. 23). Figure 23 represents the discharge capacity curve for the

gated structure with all seven gates opened equally. Gates were set at a particular

7

Page 18: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

gate opening and the model was operated at a constant discharge until the water

surface remained stable. Data were recorded for the water surface and discharge.

Several discharges were tested for each gate opening to develop each curve. Each

discharge was run for about 1 hour model time-generally long enough to maintain

a stable water surface upstream of the dam in the model.

Safety Boom

A safety boom upstream from the spillway crest was designed and tested in the

model. The final layout for the safety boom and anchors is shown on figure 24.

Figure 2S shows the safety boom at the maximum probable flood, Qm - 0.124 m3/s

(Qp = 7080-m3/s). After the model boom was installed, several tests were run to

check if the safety boom affected the discharge curves. The discharge curves did not

change.

8

Page 19: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

BIBLIOGRAPHY

[1] Blaisdell, F. W., "Development and Hydraulic Design, Saint Anthony Falls

Stilling Basin," Trans., Am. Soc. Civ. Eng., vol. 113, Paper No. 2342, pp. 483-

561, 1948.

[2] George, R. 1., "Low Froude Number Stilling Basin Design," REC-ERC-78-8,

16 pp., Bur. Reclam., 1978.

[3] Enger, P. F., "Hydraulic Model Studies of Bartley Diversion Dam-Progress

Report No.3 on General Studies of Headworks and Sluiceway Struc-

tures," Missouri River Basin Project, Nebraska, Laboratory Rep. Hyd-384,

February 1954.

9

Page 20: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

. (f)

~\ :)

::!' :

Figure I.-Location map for Choke Canyon Dam.

AIL-~'"

-0.94 -.JAPLAN

~::::~ r

r--l

rT:6E3~ 410,~E~983. }--274 ~ 3154~

J---,I

"~'%~:;;e

I:

'''' ,;1"

""J ""

~.I

m

SECTION A-A

Figure 2.-Sketch of low Froude number stilling basin-Choke Canyon Dam-original design.

10

Page 21: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

\ P L A N OF S P I L L W A Y CREST $ C A L L I B

D I M E N S I O N S i N mm

~ 1 13 7 1 5 -- . ~ ~ - ~ --- --- t , 0g6

P L A N VIEW SCnLF I 4 0

DlMFN510NS i N METERS UNLESS N O T E D

\

-- s = "03-- - - s i b 1 4 5 9 E L 3 6 1 , - - - L.- P----

<-ST& 3,s t l 3 7 5

E L 3 0 3 k I*' '* _~ P I s i n 236 i L 298 -- L-~-. J , -~ -~~ -- . I 1~ - :\

! V F R I l C 4 1 C U R Y t

I C 181

, , s r r , 5 9 5 EL i , e , -5111 2216 EL 818

r--- - ~

671-

N O T E S O r l g t n o f c a o r d n o t e i , nor theas t carr ier o t heod box

3 E T A I L A - A $'ALE i d

D I M E N 5 1 0 N S I N n m

Figure 3.-Drawing of the model-showing the original model design.

I I

Page 22: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 4.-Model as designed originally. The inlet walls were modified as was the approachchannel. P801-D-79816

13

Page 23: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 5a.-Scour around left inlet wall, Qp = 7080 m3/s tested for8.94 hours-model as designed originally. Contour lines in meters.P801-D-79817

Figure 5b.-Scour around right inlet wall, Qp = 7080 m3/s tested for8.94 hours-model as designed orginally. Contour lines in meters.P801-D-79818

14

Page 24: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 6.-Scour pattern with straight dikes, Qp - 7080 m3/s tested for 8.94 hours.P801-D-79819

15

Page 25: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

425

457.3

_El 550 ""

'".0

'"

~...

'"

El 393.7

430.5

El 393.7

A- --<1--

25.5

-<JA

1410

"-DAM CREST

STA 262.9

El 332.7

1410

~r

~El311.8

466.8

------~

j21

SANDEL 311.8

1562.1

PLAN

SCALE 1'8

El 527

~ ------

------

263.2

I.

SECTION A-AHALF SCALE

~

------

wooo

183

375

_El 550~

- ~

NOTE: ALL DIMENSIONS mm

95.3

------

El 332.7

Figure 7.-Sketch of model with 30° wingwalls.

16

------------

Page 26: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 8.-Scour around right 30° wingwall with 100-m dike,Qp = 7080 mats for 8.94 hours. P801-D-79820

Figure 9.-Scour around left 30° wingwall with 100-m dike,Qp = 7080 mats for 8.94 hours. P801-D-79821

17

Page 27: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 1O.-Scour in vicinity of 30° wingwall with 200-m dike, Qp8.94 hours. P801-D-79822

7080 m3/s for

18

Page 28: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

~r.."..~

Figure lla.-Scour with segmented right inlet wall, Qp = 7080 m3/sfor 8.94 hours. P801-D-79823

",/\"

t~"A

.....

Figure llb.-Scour with segmented left inlet wall, Qp = 7080 m3/s for8.94 hours. P801-D-79824

19

Page 29: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 12.-Model discharging 0.083 m3/s (Qp = 4750 m3/s), equivalent to lOOO-yearflood.P801-D-79825

20

Page 30: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 13a.-Scour from 300-mm (24 m prototype) radius inlet wall with4OO-mm (32 m prototype) extension at 900 to left inlet wall.P801-D-79826

Figure 13b.-Scour from 300-mm (24 m prototype) radius inlet wall with21O-mm (16.8 m prototype) extension at 1200 to right inlet wall.P801-D.79827

21

Page 31: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

----

NN

34.00

36.584- EL 13.65 "'"STAO+OO

R 24.000

TRANSITION 3 ~:I TO

2:1 SIDE SLOPES

60.256

2:1

34.440

2: I SLOPE TOPS OUT ATEL 64.00

112.200

It. DAM CREST EL 60.810

ST A 5 + 00.000

PIERSGATE SEATEL 60.596

INLET WALLS

32.000

30.000

--

', EL 73.65

-2:1

HYDRAULIC MODEL LENGTHSCALE I: 80

Figure 14.- Recommended design of inlet walls and approach channel- Choke Canyon Dam.

ENTRANCE CHANNEL EL 56.08

~EL

~t

54.40~

APPROACH CHANNEL

125.000

PLANSCALE 1:8

ALL DIMENSIONSIN METERS

Page 32: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

,.

~ I J III ~J ~J

Figure 15a.-Scour pattern with sidewalls shortened 5.48 m and originalapron, Qp = 7080 mats for 8.94 hours. P801-D-79828

J ~} Jj

Figure 15b.-Scour pattern with sidewalls and apron shortened 5.48 m,

QE = 7080 mats for 8.94 hours. Contour lines represent I m.PtlOl-D-79829

23

Page 33: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 16.-Scour pattern with 2-1/2:1 side slopes around side-walls, basin shortened 5.48 m, Q = 7080 m3/s for 8.94 hours.P801-D-79830

p

Figure 17.-Long-term scour test, Qp = 7080 m3/s for 53.7 hours(6-h model time). P801-D-79831

24

Page 34: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 18.-Scour after 8.94 hours at Qp = 7080 m3/s with 14.m apron.P801-D.79832

Figure 19.-Scour after 8.94 hours with 14-m apron and 32 m of riprapdownstream, Q = 7080 m3/s. Contour lines represent 1 meter.P80I-D.79833

p

25

Page 35: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Figure 20.-Scour after 33.5 hours, 14-m apron and 32-m of nprapdownstream Qp = 7080 m3/s,(3.75 h model). P801-D-79834

Figure 21.-Scour after 49.2 hours, 14-m apron and 32 m of nprapdownstream, Qp = 7080 m3/s, (5.50 h model). P801-D-79835

26

Page 36: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

,--I 0 0 m Riprap an symmli i ta lo&ul E i p i l l v o y -

SECTION C-C

SECTION 8 -8

~ " S P o r o a o u f i e t wirh R " S P urnin a d ~ e f with colked ioints . p - S T D 6+03 .0W Calked joints - - ST4 6 t03.WO

Cr J

' 8 " P e d o r o k d ' S P d r o r n -i--~ .,_-_, ,

AnchOr bori notshown ----- Anchor ban not shown/

S E C T I O N 0 - D SECTION E - E SECTION F - F

Floor t h i c k n e i ~

t i i Arlchar Dorr

NOTES 08meniiOns unless O ~ ~ P ~ Y I I P tho*" ore I m e t e r s i i o f i o n i ond elevat loni ore in m e t e r s

SECTION G - G Tor geoeral nottr and reference drowmqr see Ow9 1012-0-74

H Y L F PLDN DETAIL X

' ' ST& 6 + jl.LX70 .- ( id 5 *,'090- ~ S I B 6625. i00 F i A 6*36.150 - s i l 6 'U?OO L i ' ~

- -2 . ~--- , , , . ." . , Drto8i Y ' - " 0.750

511 61 56.000

, , r , ,

5 P droln

/ ( "<h" i b o r r no1 $how" COnciele pad

embedded into f o ino i i on - ~ ~ - ,-

DETAIL Y

"ii b n i h o r b o i i I

D E T A I L 2

SECTION A - A 8 "crm

@ nuunvr rvlnr SbfETY Y l i / E D 5 T l r r S

O C D l F i i l E h i O i ,Hi i l i i i F i o i e U e C l " OF R E C L I * l l r l D N

N U E C E S R i V E R P R O J S C T - T E X L 1 S

C H O K E C A N Y O N D A M SPILLWAY

FLOOR STA 5 + 9 3 . 5 0 0 TO STA 6 i 5 6 . 0 0 0

~ .,., o... ... "C"

e..,"... *DLD..DD CC.D.C" lS #.-I I 1012-D-90

Figure 22.-Final design of Choke Canyon Dam stilling bunin. 27

Page 37: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

71

70

69

68

67E

Z0I- 66c(>ILl...JILl

6!S0::

N 0\0>0::ILl

64rnILl0::

63

62

61

60

70.96 MAXIMUMWATER SURFACEELEVATION

V V jY V

/ y~/ ">9

~~S / / y'"~I

V~<IISj I,

1/ 1/1/

+J........

..../

I

'" / /....'"!I J /

il 1/ / / /"/"'"

il 1/ / '1~:.;\..o~~~~~I

I<:r /"

II / '1 /',/

GATE OPENING IS VERTICAL DISTANCE ABOVE SPILLWAY CREST// 7 GATES OPENED EQUALLY

~'I

L1SPILLWAY CREST ELEVATION 60.810

'" GATE SEAT ELEVATION 60.596Q..0

.../ien

~/VLJ

/I-- //

VSPILLWAY CREST

ELEVATION 60.810

-

I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I!S90 1000 2000 40003000 !Sooo 6000 7000

DISCHARGE. m3/s

Figure 23.-Spillway discharge curves-Choke Canyon Dam.

Page 38: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

2000

~1850 ~

~;;;,

~/~

~t

Note:All dimensions mm

Figure 24.-Sketch of Choke Canyon Dam model safety boom.

Figure 25.-Choke Canyon Dam model safety boom in place, QpP801-D-79836

7080 m3/s.

GPO 836.. 917

30

Page 39: Report No. GR 82-9, Hydraulic Model Study of Choke Canyon ... … · 4 TITLE AND SUBTITLE 5 REPORT 3ATE Hydraulic Model Study of Choke Canyon Dam Spillway and Stilling Basin 7 AUTHORISI

Mission of the Bureau of Reclamation

The Bureau of Reclamation of the U.S. Department of the Interior is responsible for the development and conservation of the Nation's water resources in the Western United States.

The Bureau's original purpose "to provide for the reclamation of arid and semiarid lands in the West" today covers a wide range of interre- lated functions. These include providing municipal and industrial water supplies; hydroelectric power generation; irrigation water for agri- culture; water quality improvement; flood control; river navigation; river regulation and control; fish and wildlife enhancement; outdoor recreation; and research on water-related design, construction, mate- rials, atmospheric management, and wind and solar power.

Burea~~ programs most frequently are the result of close cooperation with the U.S. Congress, other Federal agencies, States, local govern- ments, academic institutions, water-user organizations, and other concerned groups.

A free pamphlet is available from the Bureau entitled, "Publications for Sale". I t describes some of the technical publications currently available, thei~ cost, and how to order them. The pamphlet can be obtained upon request from the Bureau of Reclamation, Attn 0-922, P 0 Box 25007, Denver Federal Center, Denver CO 80225-0007.