request for proposal for the design, build, finance ... · design, build, finance, construction,...
TRANSCRIPT
Page 1 of 195
REQUEST FOR PROPOSAL
FOR THE
DESIGN, BUILD, FINANCE, CONSTRUCTION, DEVELOPMENT,
IMPLEMENTATION, OPERATION AND MAINTENANCE OF THE
JAN SUVIDHA KENDRA, AT Rest House Khandala on Khandala
Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA
[Details of the Project]
Executive Engineer. Public Works Division,Satara
REQUEST FOR PROPOSAL E-TENDER NOTICE NO.4.3 FOR 2017-2018
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_______________________.__________________________________
Page 2 of 195
PUBLIC WORKS DEPARTMENT
Government of Maharashtra Request for Proposal No _________________
(“Request for Proposal”)
FOR
DESIGN, BUILD, FINANCE, CONSTRUCTION, DEVELOPMENT,
IMPLEMENTATION, OPERATION AND MAINTENANCE OF THE JAN
SUVIDHA KENDRA, AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol
S.H.142 Road km.1/00 Tal.Khandala Dist.Satara MAHARASHTRA
The Public Works Department, ________________________________________, Government of
Maharashtra invites bids from eligible bidders who satisfy the requirements of terms and conditions
of the Request for Proposal, including without limitation, the technical and financial eligibility
requirements, and / or who have already qualified in the Expression of Interest (EOI) bearing No.
___________________ dated _____________, as per the terms and conditions laid down in this
Request for Proposal and the Concession Agreement, as set out in Section II of the Request for
Proposal document.
The following persons may be contacted for visiting the Site(s) with prior intimation:
Name: ____________________________
Contact Details : ___________________________
Email: ______________________________
Copies of the Request for Proposal can be downloaded from www.maharashtra.etenders.in
from 21.04.2017 to 05.05.2017 between 10:00 hours to 23:00 hours (Indian Standard Time) on
payment of Rs. 5,000/- (Rupees five thousand only) through the online e – payment gateway.
A Pre – Bid Meeting with the Bidders will be held on 28.04.2017 at Pune in the office of Chief Engineer, Public Works Region,
Pune. The bids will be opened in the presence of the Bidders in the office of Superintending Engineer, Public Works Circle,
Satara.
The date of opening for the technical bid shall be: 15.05.2017 and the date of opening of the
financial bid shall be: 16.05.2017
Bids shall be submitted online on at: www.maharashtra.etenders.in, or before 09.05.2017 till
23:00 hours. Late or delayed submissions will not be accepted.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 3 of 195
Designation of the issuing authority,
OFFICE OF EXECUTIVE ENGINEER,
PUBLIC WORKS DIVISION, SATARA.
______________________,
_________________,
_________, PIN -_______,
Ph. No.__________,
Email - ______________________
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 4 of 195
TABLE OF CONTENTS
SECTION - I
DISCLAIMER.......................................................................................................................6
INVITATION FOR BIDS.......................................................................................................9
GENERAL INFORMATION ............................................................................................................9
PROJECT BACKGROUND ............................................................................................................12
BACKGROUND OF JAN SUVIDHA KENDRAS ................................................................................12
GENERAL TERMS AND CONDITIONS FOR THE TENDER PROCESS ...................................16
EVALUATION OF BIDS...............................................................................................................16
MINIMUM ELIGIBILITY CRITERIA................................................................................................16
BIDS TO BE SUBMITTED BY A JOINT VENTURE OR BY SINGLE BIDDERS:.......................................17
FEE AND DEPOSITS TO BE PAID BY THE BIDDER .........................................................................20
SUBMISSION OF FOREIGN DOCUMENTS AND OTHER REQUIREMENTS ..........................................23
USING NET WORTH AND / OR EXPERTISE OF HOLDING / PARENT COMPANY.................................23
ONE BID PER BIDDER ................................................................................................................24
BID PREPARATION AND COSTS ..................................................................................................24
DUE DILIGENCE, INSPECTION AND INVESTIGATION ....................................................................24
VALIDITY OF BIDS.....................................................................................................................24
RIGHT TO REJECT BIDS .............................................................................................................25
MISREPRESENTATION AND / OR FRAUD AND / OR BREACH OF TERMS AND CONDITIONS ..............25
AMENDMENTS TO THE RFP ........................................................................................................25
GOVERNING LAW AND JURISDICTION ........................................................................................26
TENDERING PROCEDURE AND SCHEDULE .......................................................................27
GENERAL REQUIREMENTS ........................................................................................................27
PRE – BID MEETING .................................................................................................................27
PREPARATION AND SUBMISSION OF BIDS.................................................................................27
SCHEDULE OF THE TENDER PROCESS .......................................................................................28
LANGUAGE AND CURRENCY ......................................................................................................29
GENERAL RESPONSIBILITIES OF THE BIDDER...........................................................................29
SUBMISSION OF BIDS...............................................................................................................30
MODIFICATION AND / OR WITHDRAWAL OF BIDS .....................................................................31
OPENING OF THE BIDS .............................................................................................................32
EVALUATION OF BIDS...............................................................................................................32
CONFIDENTIALITY ...................................................................................................................37
ACCEPTANCE OF BIDS ..............................................................................................................37
EXECUTION OF THE CONCESSION AGREEMENT .........................................................................37
BIDS OF OTHER BIDDERS .........................................................................................................38
MISCELLANEOUS ......................................................................................................................38
PRESCRIBED FORMATS ....................................................................................................40
A.
B.
C.
LETTER OF APPLICATION AND INTEREST ...........................................................................40
GENERAL INFORMATION ON THE BIDDER ..........................................................................42
FORMAT FOR FINANCIAL BID ............................................................................................43
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 5 of 195
D.
E.
AFFIDAVIT ........................................................................................................................45
FORMAT FOR POWER OF ATTORNEY FOR SIGNING OF APPLICATION AND OTHER REQUIRED
DOCUMENTS ............................................................................................................................47
F.
G.
H.
I.
J.
K.
FORMAT FOR BID SECURITY AS BANK GUARANTEE ............................................................48
POWER OF ATTORNEY BY EACH MEMBER OF THE JV IN FAVOUR OF LEAD MEMBER ............51
FORMAT OF PARENT / HOLDING COMPANY DEED OF GUARANTEE ......................................52
FORMAT OF SELECTED BIDDER GUARANTEE TOWARDS SPC...............................................55
DRAFT JOINT VENTURE AGREEMENT .................................................................................58
FORMAT OF DEED OF GUARANTEE (IN CASE OF JV) TOWARDS SPC (IF APPLICABLE AND
AFTER LOA)..............................................................................................................................63
L. POWER OF ATTORNEY BY THE LEAD MEMBER OF THE JV IN FAVOUR OF ITS DULY
AUTHORIZED REPRESENTATIVE ................................................................................................66
M. FORMAT OF LETTER OF AWARD ........................................................................................67
SECTION – II The Concession Agreement…………………………………………………………69
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 6 of 195
SECTION – I
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 7 of 195
DISCLAIMER
The information contained in this Request for Proposal (“RFP”) document or subsequently provided
to bidders, whether verbally or in documentary form by or on behalf of (Executive Engineer, Public
Works Division, Satra. or any of its employees or its advisors, is provided to bidders on
the terms and conditions set out in this RFP and the Concession Agreement as set out in Section
– II hereto, and any other terms and conditions subject to which such information is provided.
This RFP is not an agreement and is not an offer or invitation to any other party. The purpose of this
RFP is to provide the bidders with information to assist the formulation of their bid submission. This
RFP does not purport to contain all the information each bidder may require. This RFP may not be
appropriate for all persons and it is not possible for (Executive Engineer, Public Works Division, Satara) and their
employees and / or advisors to consider the investment objectives,financial situation and particular needs of each
bidder. Certain bidders may have a better knowledge
of the proposed Project than others. Each recipient must conduct its own analysis of the information
contained in this RFP or to correct any inaccuracies therein that may appear in this RFP and is
advised to carry out its own investigation into the proposed Project, the legislative and regulatory
regimes which applies thereto and by and all matters pertinent to the proposed Project and to
seek its own professional advice on the legal, financial, regulatory and taxation consequences of
entering into any agreement or arrangement relating to the proposed Project.
The Executive Engineer, Public Works Division, Satara and their employees and their
advisors make no representation or warranty and shall incur no liability under applicable laws for
any loss, expense or damage, accuracy, reliability or completeness of the RFP, which may arise from
or be incurred or suffered in connection with anything contained in this RFP, any matter deemed to
form part of this RFP, the award of the Project, the information and any other information supplied
by or on behalf Executive Engineer, Public Works Division, Satara or their employees, any
consultants or otherwise arising in any way from the selection process for the Project. The
information given is not intended to be an exhaustive account of statutory requirements and should
not be regarded as a complete or authoritative statement of law. The Executive Engineer, Public
Works Division, Satara hereby accepts no responsibility for the accuracy or otherwise for
any interpretation or opinion on law expressed herein. The Executive Engineer, Public Works
Division, Satara also accepts no liability of any nature whether resulting from negligence
or otherwise howsoever caused arising from reliance of any bidder upon the statements or any
information contained in this RFP.
The Executive Engineer, Public Works Division, Satara may in its absolute discretion, but
without being under any obligation to do so, can amend or supplement the
information/clauses/articles in this RFP. The information that the Executive Engineer, Public Works
Division, Satara. is in a position to furnish is limited to this RFP, along with any
amendments/ clarifications thereon. This RFP and the information contained herein are confidential
and for use only by the person to whom it is issued. It may not be copied or distributed by the
recipient to third parties (other than in confidence to the recipient's professional advisors). In the
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 8 of 195
event that the recipient does not continue with the involvement in the Project in accordance with RFP
the information contained in the RFP shall not be divulged to any other party. The information
contained in the RFP must be kept confidential. Mere submission of a responsive Bid/ Proposal does
not ensure selection of the bidder as the Concessionaire. The issue of this RFP does not imply that
the Executive Engineer, Public Works Division, Satara is bound to select a bidder or to
appoint the successful bidder, for the execution of the scope of work and other requirements, and
the Executive Engineer, Public Works Division, Satara reserves the right to reject all or
any of the bidders or bids without assigning any reason whatsoever.
The bidder shall bear all costs associated with or relating to the preparation and submission of its bid
including but not limited to preparation, copying, delivery fees, expenses associated with any
demonstrations or presentations which may be required by the Executive Engineer, Public Works
Division, Satara or any other costs incurred in connection with or relating to its bid. All
payment of such costs and expenses will lie with the bidder and the Executive Engineer, Public Works
Division, Satara shall not be liable in any manner whatsoever for the same or for any
other costs or other expenses incurred by a bidder in preparation or submission of the bid, regardless
of the conduct or outcome of the bidding process.
The bidder on submission of the first bid shall be deemed to have acknowledged and undertaken that
based on the terms and conditions of the RFP, the bidder shall execute the works which are suitable
for the Project and shall recommend the same in its bid after taking into consideration the effort
estimated for implementation of the same. If any duties, responsibilities and / or obligations not
specifically described in the RFP and / or the Concession Agreement are an inherent, necessary or
customary part of the deliverables, performance of any duties, responsibilities and / or obligations
and are required for proper performance or provision of the deliverables or services in accordance
with the Concession Agreement, they shall be deemed to be included within the scope of the
deliverables, duties, responsibilities and / or obligations, as if such deliverables, duties,
responsibilities and / or obligations were specifically required and expressly described in the RFP and
/ or the Concession Agreement and shall be provided by the bidder as part of the performance of its
duties, obligations and responsibilities.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
�-������
��������/ ��� ���� ���� :- ���� ������, ��.���.�����, ������, �������, ������- 415 001.
�-������ ��������� ����� :- � - ������ ����� � �� 4 �� 2017-2018 (����� ��% ) ('�ल���)
���� ������, ����)�� ���*� �����, ������ 415 001 (������� ���� 02162-233792) �ह���� !����"�� ���#$�� %��&�� '�(��)� �*+� (�� ���,� �-���. , � /�0�����)�� � ������ ����� ��1��20 34� 56*$ (RFP) ���� ���� � ;��5���� �� ������"�� ��#<�,� � �.�. 1 �. 3 ��,� ������ �-������ 5�� �=��� (>� ���) �*ह*�%�� ������ �����, ?ह�,. ����� ���<A, ��#� :- 1) ���)���.ह ��C��20�!� 6��������� ��ह � 5��!����C� 5��&��.ह � ��#����D�
5��!����C� $�����&� E F %��&�� ,�.*������. �$.��,���. 2) ���)���.ह 6������� 6��������� ��ह � 5��!����C� 5��&��.ह � ��#����D� 5��!����C� $�����&� E F %��&�� ,�.'0��.�$.��,���. 3) ��I���.ह '�)�J� 6��������� ��ह � 5��!����C� 5��&��.ह � ��#����D� 5��!����C� $�����&� E F %��&�� ,�.'�)�J�. �$.��,���.
������ K�, :- /.5000/- 12. (>� ���) (��-6�,���) ������ Lघ)N���� ,���' � ��J :- �* 3 ������, ��. ���. �45, ������ ���. �6ल��
�����.15/05/2017 ��) ��5 10.00 �. �����.16/05/2017 ��) ���.17.30 ��).�7� '�ल��� 8घ4:�� .� ल. (;< =�>��)
������ ���6/���� ,6!� “pwd.maharashtra.etenders.in � www.mahapwd.com” �� ��� , 2WJ��� L6 X& ?ह� .
������������ '�/� Y� Z���� � (����� ������ ���6/� Online ���� � � ?ह�, � *`�� ������ !�; � %���� �1�
Payment Gateway �दारे online ��#��� a����,�, ��.%��. �����, ��,��� ���"�� ����� ���� � � ?ह�.
1. ������ ������ (���"�� %* � >� ��� 6��,��� ���� ��c��,.
2. ������, ��� घ�N����C� ������������ 1 �� III �)�$0 ������� ?�� �� ���� � �;�� ��� ,2WJ��� ������6/
)�e� *) �N����C� � ������ 5����, ��� घ�����C� �-������ 5�� �"�� Main portal – “
Maharashtra.etenders.in” �� enrolled ��� ?�f� ?ह�. (����,� 2�,: ��� �-��� Y� Z����.
3. *�(��ह� 26�0������,� ������������ � ������ ����. (02162) 233792 !� ��6# ��&���.
4. 6/c��ह�����,� ��6# c�1,� � 6l�. ���� ������, ��.���.�����, ������. �������, ������- 415 001. OP <� � �� :- (02162) 233792 ���R�� � � :- (02162) 233792 �- .ल �S� :- [email protected]
)�.�.ल.T�/) -117/ 2589 / 2017 ���� ������, ��.���. �����, ������ ���. �6ल. �����. 10 / 04 / 2017.
?6 � ��f����
���� ������ ����)�� ���*� �����, ������
E-TENDER
Division / Office Name :- Executive Engineer, Public Works Division, Satara - 415 001
( Telephone No. 233792 )
e-tender Notice :- E-TENDER NOTICE NO. 4 FOR 2017-2018 (Second Call) ( ONLINE )
The Executive Engineer, Public Works Division, Satara -415001 (Telephone No. 233792) invites tender notice in
RFP form through e-tendering process from contractors registered in the appropriate class with the Government of
Maharashtra, Public Works Department and as mentioned in tender notice Request For Proposal (RFP) for the execution
of works under jurisdiction of this division.
Short Description of Work :- 1) Request for Proposal for the Construction of Jansuvidha Kendra
at Store Room at Wathar Station.
2) Request for Proposal for the Construction of Jansuvidha Kendra
at Store Room at Pusegaon.
3) Request for Proposal for the Construction of Jansuvidha Kendra
at Rest House Khandala.
Blank e-tender form fee :- Rs. 5000/- Respectively. (Via E-payment getway only) (Non
Refundable)
Place, Date and timing of opening :- Dt. 15/05/ 2017 at 10.00 a.m. to Dt. 16 / 05/ 2017 at
Technical-bid and Financial bid. 17.30 p.m. in the office of Superintending Engineer,
P.W. Circle, Satara. (If Possible)
Details of Tender Document is available on website “pwd.maharashtra.etenders.in" and
www.mahapwd.com”. Tender Document shall be uploaded online . Bidders should ensure that, they have uploaded
Tender Document online, and Tender Document fees, and EMD to be paid online only via Payment Gateway
mode. Bidders should ensure that, they have submitted Tender Document fees and EMD online only via Payment
Gateway mode in the name of Executive Engineer, Public Works Division,Satara.
1. Bidders should Submit their offers Online.
2. All eligible/ interested Bidders who want to participate in tendering process should compulsory get enrolled on
e-tendering portal https://maharashtra.etenders.in.
3. For details or any Clarification regarding submission of online tenders if any, Please Contact. Sify
Technotigies Ltd. Nextenders (India) Pvt. Ltd. On 020-25315555 (Pune) and Executive
Engineer, Public Works Division, Satara - 415 001 (Telephone No. 233792 )
4. For Correspondence Name and Address of the Office.
Executive Engineer, Public Works Division,
Satara - 415 001 (Telephone No. 233792 )
Fax No. :- (02162) 233792
Telephone No. :- (02162) 233792
e-mail :- [email protected]
No.AB / Tender / 2589 / 2017
Office of the Executive Engineer,
P.W. Division, Satara.
Date. 10 / 04 / 2017.
Executive Engineer,
Public Works Division, Satara
ह���VW ;��� ����)�� ���*� �����, ������- 415 001
���R�� � �� 02162/233792 Web- www.mahapwd.com & [email protected]
��<�.XY OZ� 1��)ल (RFP) � - ������ ��̂�� � �� 4 �� 2017-2018 (����� ��% ) ('�ल���)
���� ������, ����)�� ���*� �����, ������ 415 001 (������� ���� 233792) �ह���� !����"�� ���#$�� %��&�� '�(��)� �*+� (�� ���,� �-���. , � /�0�����)�� � ������ ����� ��1��20 34� 56*$ (RFP) ���� ���� � ;��5���� '� � ������,� ������ �-������ 5�� �=��� (>� ���) �����, ?ह�,.
a. �.
����� ��� � ������ ������ K�,
�-��� ��#
1 %�;ह� 6�%J *�� �!��6�� $�$��� *��� ��,��� ��.��.117 �.��.164/800 �&� �2(��)�"�� ���)���.ह ��C��20�!� 6��������� ��ह � 5��!����C� 5��&��.ह � ��#����D� 5��!����C� $�����&� E F %��&�� ,�.*������. �$.��,���. (On the basis of Design, Build, Finance, Development, Implementation,
Operation and Maintenance to be done by the Concessionaire )
Y6�� 5,000/- ������ ����� ��1��20 34� 56*$ (RFP)
���� ���� � ;��5����
2 3 0� �*J 6������� s�& ��.��.147 �2,� �.��.46/00 �&� �2(��)�"�� ���)���.ह 6������� 6��������� ��ह � 5��!����C� 5��&��.ह � ��#����D� 5��!����C� $�����&� E F %��&�� ,�.'0��.�$.��,���. (On the basis of Design, Build, Finance, Development, Implementation,
Operation and Maintenance to be done by the Concessionaire )
Y6�� 5,000/- ������ ����� ��1��20 34� 56*$ (RFP)
���� ���� � ;��5����
3 '�)�J� *������ ��ह�,6�� ��) ���� � �!�*J ��.��.142 �2,� �.��.1/00 �&� �2(��)�"�� ��I���.ह '�)�J� 6��������� ��ह � 5��!����C� 5��&��.ह � ��#����D� 5��!����C� $�����&� E F %��&�� ,�.'�)�J�. �$.��,���. (On the basis of Design, Build, Finance, Development, Implementation,
Operation and Maintenance to be done by the Concessionaire )
Y6�� 5,000/- ������ ����� ��1��20 34� 56*$ (RFP)
���� ���� � ;��5����
�-�����.�. �.5��_
1. ������ >� ��� )�e� *) �N���� � ��&� �����.21/04/2017 ��J ��J� 10.00 ��. ,� �����.05/05/2017 ��J ��/�.23.00 ��$�6�t,
2. >� ��� ���������� ,���/ ��u� L6ि2W, ������� a��,� ����� � ��J (������ ���� ��6 �̀a)
��� �����%�&�,� ,���/ ��u� �����.28/04/2017 �*$� 11.00 ��$�6�t, >� ��� K�� ��. ��w� a����,�, ��.%��. 5����! �����, 6��� ����� ��� ��, L6ि2W, ����,.
3 ������������ >� ��� ������ ,��� �N����C� हx! (Hash) ���� �N���� ����� (,���/ � ?zW ������ a��,� ����� � ��J)
�����. 09/05/2017 �*$� ��J ��/� 23.00 ��$�6�t,.
4 >� ��� Super Hash �N����C� � ��&� �����. 09/05/2017 �*$� ��J ��/� 23.01 6���� �����. 11/05/2017 ��6��� 14.00 ��$�6�t,.
5 ������������ >� ��� ������ ,6!� (,���/ � ?zW ) Decryption � Reencyption ������� � ��&�.
�����. 11/05/2017 �*$� ��J ��6��� 14.01 6���� ��.12/05/2017 ���� 17.30 ��$�6�t,.
6 ��<�.XY OZ� 1��)ल (RFP) Lघ)N���� �C��, ����� � ��J
�*b3 �����, ��. ���. �45, ������, ����� ��� ��, �����.15/05/2017 �*$� ��J� 10.00 ,� �����.16/05/2017 �*$� ����. 17.30 ��$�6�t, >� ��� Lघ)N��, ��,� . (!1� ��;���)
�06 :- 1. ��# 6�/ /�"�� ������������ ������6/ )�e� *) �N����C� � ������ 5����, ��� घ�N����C� � ������ 5�� �"��
Main Portal- pwd.maharashtra.etenders.in" ���0�� enrolled ��� ?�f� ?ह�.
2. ������������ �� ���� � �;�� ��� ,2WJ��� >� ��� ���� ���� �����, � �)$�0 5���6/ ��,��, �N�������,
�ह� !��/a)��� a�;��� (����� '� � ������� ������� ��6# ��&���.
Sity Technotigies Ltd. Nextender (India) Pvt.Ltd. on 020-30187500 (Pune)
3. ������������ ������ �����, ��# �2,��$ >� ��� ���� ��� a�����# ��ह� . ,��� %���� �� >� ��� ����
��� a�����# ��ह� , >� ��� *�� ������ ��� )�e� *) �����C� e-payment gateway c���� *�� ������ ������
K�, �-������ ��J�6/����� ���� � �;�� ����� � ��J6�t, ���� ��� ?�f� ?ह�. aD�W� >� ��� ������
Lघ)N��, ����� ��ह� ����� �-� Z����.
4. �,� a0� � !,� �-������ ���D������ 6ह����� ��J,� . ��� ������ � aW�� ��# �-������ *�,�ह� ��� � ��,�
�u �N���� a�&��� �<� a�&��� ����� ��'�� C�� � � ?ह�,.
5. ��� ������ �-������ ����� ���#$�� %��&�� ������"�� www.mahapwd.com �� ��0���0��� ��%���0��
L6 X& ?ह�.
)�.�.ल.T�/) -117/ 2589 / 2017 ���� ������, ��.���. �����, ������ ���. �6ल. �����. 10 / 04 / 2017.
?6 � ��f����
���� ������ ����)�� ���*� �����, ������
GOVT. OF MAHARASHTRA
Public Works Division, Satara - 415 001
Phone No. 02162/233792
Web - www.mahapwd.com & [email protected]
REQUEST FOR PROPOSAL E-TENDER NOTICE NO. 4 FOR 2017-2018 (Second Call)
Sealed online RFP forms e-tenders for the following work are invited by the Executive
Engineer, Public Works Division, Satara - 415 001 (Telephone No. 233792) from the contractors
Registered with Government of Maharashtra Public Work Department in appropriate class and as
mentioned in tender notice Request For Proposal (RFP) for the execution of works under
jurisdiction of this division, for following works ;
Sr.
No.
Name of Work Cost of
e-tender For
m Fee Rs.
Class of
Contractor
1
Request for Proposal for the Construction of
Jansuvidha Kendra at Store Room at Wathar Station
on Belhe Pabal Loni Shikrapur Jejuri Lonand Satara
S.H.117 Road km. 164/800 Tal.Koregaon.
Dist.Satara.
(On the basis of Design, Build, Finance,
Development, Implementation, Operation and
Maintenance to be done by the Concessionaire)
Rs. 5000/-
As per mentioned
in detailed e-
tender notice for
Request for
Proposal (RFP)
2
Request for Proposal for the Construction of
Jansuvidha Kendra at Store Room at Pusegaon on
Phaltan Mol Pusegaon Aundh S.H.147 Road
km.46/00 Tal.Khatav.Dist.Satara.
(On the basis of Design, Build, Finance,
Development, Implementation, Operation and
Maintenance to be done by the Concessionaire)
Rs. 5000/-
As per mentioned
in detailed e-
tender notice for
Request for
Proposal (RFP)
3
Request for Proposal for the Construction of
Jansuvidha Kendra at Rest House Khandala on
Khandala Koregaon Rahimatpur Karad Sangli Shirol
S.H.142 Road km.1/00 Tal.Khandala. Dist.Satara.
(On the basis of Design, Build, Finance,
Development, Implementation, Operation and
Maintenance to be done by the Concessionaire)
Rs. 5000/-
As per mentioned
in detailed e-
tender notice for
Request for
Proposal (RFP)
E-tender time table
1 Download Period of online Tender Dt. 21/04/2017 at 10.00 am. to Dt.05/05/2017 upto 23.00 p.m.
2 Last date and time for online raising of technical points for clarification (Pre-bid Meeting)
Online or in the office of the Chief Engineer, P.W. Region Central Building, Pune on or before Dt. 28/04/2017 upto 11.00 a.m.
3 Submit Hash to Create online Tender by Contractor (Technical and financial Bid Last date and time)
Dt. 09/05/2017 upto 23.00 p.m.
4 Period for online Super Hash generation (for Office use only)
Dt. 09/05/2017 at 23.01 Hrs to Dt. 11/05/2017 upto 14.00 p.m.
5 Period of online Decryption and Re-encryption for tender details by Contractor.
Dt. 11/05 /2017 at 14.01 pm. to Dt. 12/05/2017 upto 17.30 p.m.
6 Place, Date and timing of opening Technical-bid and Financial bid.
Dt. 15/05 /2017 at 10.00 am. to Dt. 16/05/2017 upto 17.30 p.m. in the office of Superintending Engineer, P.W. Circle, Satara. (If Possible)
Note :-
1. All eligible/ interested Bidders who want to participate in tendering process should
compulsory get enrolled on e-tendering portal http://maharashtra.etenders.in and further need
to empaneled online on sub portal "http//pwd.maharashtra.etenders.in" in the appropriate
category applicable to them.
2. Contact details for difficulties in submission of online tenders if any.
Sify Technotigies Ltd. Nextenders (India) Pvt. Ltd. On 020-30187500 (Pune)
3. It is compulsory for all participates to submit all document online. It is also compulsory to
submit The EMD shall be paid via Online mode only. In case of failure online offer will not
be opened.
4. Other term and condition displayed in online e-tender forms. Right to reject any or all online
bid of work without assigning any reasons thereof is reserved.
5. Above Tender Notice is displayed on P.W.D. website www.mahapwd.com
No.AB / Tender / 2589 / 2017
Office of the Executive Engineer,
P.W. Division, Satara.
Date. 10 / 04 / 2017.
Executive Engineer,
Public Works Division, Satara
Page 9 of 195
1.
INVITATION FOR BIDS
1.1.
1.1.1.
1.1.2.
GENERAL INFORMATION
The Public Works Department, the Government of Maharashtra (the “Authority”),
represented by the Executive Engineer, Public Works Division, Satara intends to
develop Jan Suvidha Kendra and the Project (as defined under the Concession
Agreement) including without limitation the construction of toilets in general and ladies
toilets with drinking water and other public amenities at location mentioned in Schedule –
IV of the Concession Agreement.
This Request for Proposal (“RFP”) is for the Project design, finance, inspection, survey,
development, construction, implementation, operation and maintenance of the Jan
Suvidha Kendra at the Site (as defined under the Concession Agreement) mentioned in
Schedule – IV of the Concession Agreement, from the following eligible bidders (the
“Bidders”) or who have already qualified under the Expression of Interest (EOI) bearing
No ____________________ dated ____________________:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
Individuals;
Partnership firms, within the meaning of the Indian Partnership Act, 1932;
Limited Liability Partnerships, within the meaning of the Limited Liability Partnership
Act, 2008;
Company and / or corporations, within the meaning of the Companies Act, 2013;
Statutory corporations, incorporated under any act and / or statute of the
Government of India or any state government;
A registered society under any any act and / or statute of the Government of India
or any state government;
An association of persons, within the meaning of the Income Tax Act, 1961; and,
(viii) A joint venture entity (whether or not having separate legal personality) of two or
more of the above.
1.1.3.
Multiple Bidders may also bid under a joint venture arrangement, in accordance with the
requirements of this RFP and shall submit the duly executed joint venture agreement, in
the form and format as set out in this RFP, to the Authority. The invitation for bids is also
open to foreign bidders, provided that they are bidding under the joint venture
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 10 of 195
arrangement, with at least one (1) Indian Bidder as part of such joint venture
arrangement, with such Indian Bidder as the Lead Member (as defined under the
Concession Agreement)
1.1.4.
1.1.5.
1.1.6.
1.1.7.
1.1.8.
1.1.9.
The selected Bidder shall duly incorporate a special purpose vehicle, as a private company
under the provisions of the Companies Act, 2013 in order to execute the Project and
perform its duties, obligations and responsibilities in this regard. The special purpose
vehicle (herein after called as the “Concessionaire”) shall enter into the Concession
Agreement (the “Concession Agreement”) in the form and format as set out in Section
– II hereto, for the design, finance, inspection, survey, development, construction,
implementation, operation and maintenance of the Project, for the Concession Period (as
defined under the Concession Agreement) as mentioned in this RFP.
A single stage bidding process shall be conducted for determination of the Selected Bidder
(as defined under the Concession Agreement). The Bidders would be required to meet the
minimum threshold technical qualification conditions and qualify for undertaking the
Project as set out in this RFP. This qualification assessment would be carried out as part
of the current bidding and evaluation process. The financial bids of only those Bidders that
possess the minimum technical qualification conditions as set out under this RFP and
have been submitted in compliance with the requirements as stated herein would be
opened and evaluated.
The RFP contains information about the Project, the Site, bidding process, proposal
submission, the evaluation of bids, qualification, financial proposal requirement and the
award of the Project.
Copies of the RFP can be downloaded from www.maharashtra.etenders.in from
21.04.2017 to 05.05.2017 between 10:00 hours to 23:00 hours (Indian Standard Time)
on payment of Rs. 5,000/- (Rupees five thousand only) through the online e – payment
gateway.
A Pre – Bid Meeting with the Bidders shall be held on 28.04.2017 at 11:00 A.M. in the
office of Chief Engineer, Public Works Region, Pune.
The bids will be opened in the presence of the prospective parties in the office of
Superintending Engineer, Public Works Circle, Satara The date of opening for
the technical bid shall be:15.05.2017 and the date of opening of the financial bid shall
be: 16.05.2017
1.1.10. The Bids shall be submitted online on or before 09.05.2017 (“Proposal Due Date”) till
23:00 hours. Late or delayed submissions will not be accepted. The Authority, may in its
sole discretion, amend the Proposal Due Date.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 11 of 195
1.1.11. In case applicants need any further information about the Project or need access to any
other documents related to the Project and / or the Site, as available with the Executive
Engineer, P.W. Division Satara or any other information, they are requested to
contact below:
OFFICE OF EXECUTIVE ENGINEER,
PUBLIC WORKS DIVISION,
SATARA.
__________
___________, PIN -415001,
Phone Number 02162-233792
Email - [email protected]
1.1.12.
All capitalized terms used but not defined herein, shall have the meanings as ascribed to
such terms, under the Concession Agreement as set out in ‘Section – II’ hereto.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 12 of 195
2.
PROJECT BACKGROUND
2.1
2.1.1
2.1.2
2.1.3
2.1.4
2.1.5
BACKGROUND OF JAN SUVIDHA KENDRAS
Maharashtra state has a wide network of roads which includes State Highways, major
district roads, and other roads. A lot of people travel through these roads daily, in which
women travelers comprise a large number. Facility for resting, restaurants and toilets are
available on the State transport bus stands or road side hotels like dhabas. Yet taking
into account the hygiene and privacy factors, many of the above mentioned facilities are
in inhumane condition, leave alone provision of adequate security measures for the
women travelers during the night time.
To address these issues, the Government of Maharashtra has entrusted the Public Works
Department with the requisite authority, in public interest, for the execution of the
Project titled “Design, Build, Finance, Construction, Development, Implementation,
Operation and Maintenance of the Jan Suvidha Kendra, at Rest House Khandala,Maharashtra” for
the design, build, finance, construction, development, implementation, operation and
maintenance of Jan Suvidha Kendras (the “Jan Suvidha Kendras”), proposing to
provide certain essential facilities, in public interest, including but not limited to toilet
facilities, park – like areas, parking areas, vehicle service areas, restrooms, shops,
telephone and internet facilities, ATMs, restaurants, water purifiers, sanitary napkin
disposal systems, solar systems, external and internal beautification, internal roads,
compound wall, sewage treatment plant, effluent treatment plants, CCTV surveillance
system, other security measures for safety of the Users, etc. in accordance with the
requirements of this RFP, the Concession Agreement under Section – II hereto,
applicable laws and applicable permits and clearances.
This Jan Suvidha Kendra is a public facility which shall have the facilities as set out under
the Concession Agreement, under Section – II hereto, at which drivers and passengers
can rest, service their vehicles or refuel without exiting on to secondary roads. The
maximum built up area and minimum built up area of the proposed facility for the
construction of the Jan Suvidha Kendra and execution of the Project shall be
categorically stated, by the Bidders, as part of the bid submission.
The scope of the Project and the duties, responsibilities and obligations of the
Concessionaire are set out under Schedule – I of the Concession Agreement.
As a part of this process the Authority has identified the Site, the details of which are set
out in Schedule – IV of the Concession Agreement, for the construction of such Jan
Suvidha Kendra, the Project and for the performance of the duties, responsibilities and
obligations of the Concessionaire. The Site shall be provided to the Concessionaire, on leave
and license basis for a period of fifteen (15) years (“Concession Period”), in accordance
with the terms and conditions of the Concession Agreement. In consideration of the grant
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Sr. No. District Name of road Location Available
area of land
(sq. metres)
1 Satara. Khandala Koregaon
Rahimatpur Karad
Sangli Shirol S.H.142
Road km.1/00
Tal.Khandala
Rest House
Khanda
11202.19
Page 13 of 195
of the Site in accordance with the terms as stated in the Concession Agreement, the
Bidder has to pay the License Fees (as defined under the Concession Agreement) to the
Authority, on being awarded the Project, and such other payments as required in
accordance with the terms and conditions of the Concession Agreement. The
Concessionaire has to provide the services to the Users (as defined under the Concession
Agreement) as are required under this RFP, during the Concession Period.
2.1.6
2.2
2.3
On the completion of the Concession Period the Project, the Site and all Assets (as
defined under the Concession Agreement) therein, shall be handed over by the
Concessionaire to the Authority, in accordance with the terms and conditions of the
Concession Agreement. The Concessionaire shall only use the Site for the execution of the
Project and for the performance of its duties, obligations and responsibilities as stipulated
under the RFP and the Concession Agreement. Any use of the Site for any other purpose
not stipulated under the RFP and the Concession Agreement, without prior permission /
approval of the Concessionaire, shall be liable for severe action from the Authority and in
such event, the Authority shall have the discretion to terminate the Project without any
claims and / or liabilities to the Concessionaire. In the event, that the availability of land
at the Site is less than that as stipulated in the RFP, the Concessionaire shall submit a
plan to accommodate to the extent of such land at the Site, as available.
LOCATIONS OF SITES FOR JAN SUVIDHA KENDRA:
The following are the proposed locations of the Site as proposed for Jan Suvidha Kendra
and the Project in Public Works Division, Satara.
PROJECT STRUCTURE, SOURCE OF FUNDS AND SOURCE OF REVENUE
(a) The scope of work of the Concessionaire includes without limitation the design,
build, finance, construction, development, implementation, operation and
maintenance of the Jan Suvidha Kendra and the Project and such other duties,
obligations and responsibilities of the Concessionaire, as set out in the Concession
Agreement, to be performed by the Concessionaire in accordance with Applicable
Laws (as defined under the Concession Agreement), Clearances (as defined under
the Concession Agreement) and Good Industry Practice (as defined under the
Concession Agreement).
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 14 of 195
(b)
(c)
(d)
The Concessionaire shall propose to the Authority, the various facilities as proposed
to be built at the Jan Suvidha Kendra, in keeping with, the scope of work as set out
under Schedule – IV of the Concession Agreement, the requirements of the Jan
Suvidha Kendra, the Site, the Clearances and Applicable Laws.
The Concessionaire shall pay the Licence Fees to the Authority for the use of Site
during the Concession Period and shall make such other payments as required in
accordance with the terms and conditions of the Concession Agreement. All Taxes
(including service tax and GST) applicable and/or payable on the Licence Fees and
the annual incremental premium shall be borne and discharged by the
Concessionaire at actuals as per the instructions of the Authority.
The Concessionaire shall have the exclusive right, license to develop the Jan
Suvidha Kendra and the Project, subject to conditions as mentioned in the RFP and
the terms and requirements of the Concession Agreement. The Concessionaire can
charge from the Users (as defined under the Concession Agreement) of the Jan
Suvidha Kendra and the Project, the Commercial Charges (as defined under the
Concession Agreement) and generate such other sources of revenue and to recoup
its investments, as proposed to the Authority during the tender process, including
but not limited to the following:
(i)
(ii)
(iii)
(iv)
Commercial Charges from proposed shops, facilities, ATM centers, rentable
space other than mobile towers.
Commercial Charges from displaying advertisements at the Jan Suvidha
Kendra and the Project.
Commercial Charges from restaurants, food stalls to be built, vehicle repair
centers, etc. at the Jan Suvidha Kendra and the Project.
Apart from the above, any other revenue stream can also be proposed by
the Bidder to the Authority, during the tender process. However the same
has to be approved by the Authority before implementation. The Bidder shall
provide such other information, in this regard, as may be requested by the
Authority.
(e)
(f)
The Concessionaire shall prepare a detailed Project Report (as defined under the
Concession Agreement) with the requisite design specifications and other
information, and pursuant to its approval, complete the Project within the stipulated
Implementation Period of _________________________
The Concessionaire can charge from the Users of the Jan Suvidha Kendra and the
Project, the Commercial Charges and generate such other sources of revenue to
recoup its investments, as proposed to the Authority during the tender process.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 15 of 195
However the same shall be approved by the Authority / Engineer in charge before
implementation.
2.4
2.5
END OF THE CONCESSION PERIOD
At the end of the Concession Period, by efflux of time or premature termination for
any reason whatsoever, all rights and / or benefits accorded under the Agreement
shall cease to have effect and the Jan Suvidha Kendra, the Project and the Site including
without limitation the assets (i.e. both movable and immovable assets, whether provided
by the Authority or brought in by the Concessionaire during the subsistence of the
Agreement), thereof shall transfer back to the Authority as per the provisions of the
Concession Agreement. All the movable and immovable assets attached shall revert to
the Authority without any obligation on Authority to pay or adjust any consideration or
make any other payment to the Concessionaire.
SCOPE OF WORK
The scope of work of the Concessionaire includes without limitation the design, build,
finance, construction, development, implementation, operation and maintenance of the
Jan Suvidha Kendra and the Project and such other duties, obligations and responsibilities
of the Concessionaire as set out in the Concession Agreement in accordance with
Applicable Laws, Clearances and Good Industry Practice as more particularly set out in the
Concession Agreement.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 16 of 195
3.
3.1.
GENERAL TERMS AND CONDITIONS FOR THE TENDER PROCESS
EVALUATION OF BIDS
The evaluation of the bids by the Bidders shall be broadly conducted as follows:
(a)
(b)
STEP 1 – Opening of technical proposals and short – listing of Bidders on the basis
of such technical evaluation; and,
STEP 2 – Opening of financial proposals of technically qualified Bidders and final
selection of the selected bidder as set out under this RFP.
3.1.1.
3.1.2.
The entire bidding process has been explained elaborately in Clause 4 of Section – I of this
RFP.
The Project shall be awarded to the technically qualified Bidder scoring the maximum
points under the tender evaluation process, conducted in accordance with the requirements
as set out under the RFP. The bids to be submitted by the Bidders shall include the
following information and other information as may be requested by the Authority from
the Bidders, from time to time:
(a)
(b)
(c)
The bid shall consist of the detailed project plans of the proposed facilities to be
constructed at the Jan Suvidha Kendra and the Project, the documents and / or
information as required under this RFP and such other information as may be
requested by the Authority from the Bidder.
The bid shall consist of the Bidder’s quote of the Licence Fees that the bidder shall
pay to the Authority, for use of the Site for the period of the Concession Period,
upon due selection and award of the Project.
The bid shall consist of the facilities as proposed to be constructed by the bidder,
including without limitation, facilities for parking, drinking water, toilet facilities,
sanitary requirements for women in accordance with the scope of work, as set out
under the Schedule – IV of the Concession Agreement.
3.1.3.
3.2.
The selected bidder shall be issued the Letter of Award (“LoA”) in the form and format as
set out in Clause 5 (M). After issuance of the LoA, by the Authority, in writing the selected
bidder shall duly incorporate the Concessionaire and the Concessionaire shall enter into
the Concession Agreement with the Authority within 45 (forty – five) days of the date of
issuance of the LoA or the date as mutually agreed between the Authority and the
selected Bidder.
MINIMUM ELIGIBILITY CRITERIA
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 17 of 195
3.2.1.
3.2.2.
The Bidder should be legally competent to enter into a contract as per Applicable Laws.
Only those Bidders who satisfy both the following conditions (“Minimum Eligibility
Criteria”) and submit other relevant documents and / or information as per Clause 5 and
other provisions of Section – I of this RFP shall be declared “Eligible” for the Project.
(a)
Technical Eligibility Criteria
Experience in the construction, development / operation and maintenance of
projects mentioned in ‘a’ and ‘b’.
a.
b.
Construction / development of at least one (1) number of either Jan
Suvidha Kendra like facility which shall include toilet facilities, restaurant
facilities and parking facilities etc. / public toilet or community toilet and its
satisfactory operation and maintenance for a minimum period of three (3)
years before the Proposal Due Date;
AND
Operation and maintenance of at least one (1) Jan Suvidha Kendra like
facility for a minimum of two (2) years and / or three (3) numbers of either
public toilets or community toilets for a minimum period of three (3) years
before the Proposal Due Date.
(b)
Financial Eligibility Criteria
The audited financial statements, by a duly appointed auditor, along with the
statement if the auditor and such information as requested by the Authority, in
support of these shall be furnished:
a.
b.
The Bidder should have minimum average annual turnover of Rs. 3 crores
(Rupees three crores only) for the last three years (i.e. 2013 – 14 to 2015 –
16);
AND
The Bidder should have minimum net worth of Rs. 3 crores (Rupees three
crores only).
3.3.
3.3.1.
BIDS TO BE SUBMITTED BY A JOINT VENTURE OR BY SINGLE BIDDERS:
There can be a maximum of 3 (three) members in a Joint Venture (JV) arrangement.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 18 of 195
3.3.2.
3.3.3.
3.3.4.
3.3.5.
The Lead Member of a JV, independently, shall be required to satisfy the Technical
Eligibility Criteria mentioned in Clause 3.2.2 (a). However, for the Financial Eligibility
Criteria, as laid down in Clause 3.2.2 (b), the aggregate financials of the JV members
shall be considered. Any material changes in the membership of a Bidder will be rejected by the Authority.
Proposals submitted by a joint venture must include duly executed joint venture
agreement, in the form and format as set out under Clause 5(J) of this RFP, between the
various Joint Venture (“JV”) members stamped in accordance with Applicable Laws, which
describes the responsibilities and proposed equity commitments of each member in
the JV. One of the JV members would be required to be nominated as the Lead
Member and the same shall also be mentioned in the Joint Venture (JV) Agreement.
The selected Bidder shall, inter alia form a special purpose vehicle (“SPC”), a private
company registered in India in accordance with Applicable Laws, for the implementation
of the Project and the performance of the duties, obligations and responsibilities as
envisaged under the Concession Agreement. The SPC shall be formed within 30 (thirty)
days of the date of the Letter of Award. The SPC would enter into the Concession
Agreement and subsequently carry out all the duties, obligations and responsibilities of
the selected Bidder and undertake the Project as stipulated in the Concession
Agreement. The proposed shareholding of the members of the JV or the Bidder in the
SPC must be in compliance with the criteria specified in this RFP. However, the
membership structure of the Bidder shall not be changed by the Bidder without
Authority’s prior written approval.
In addition to the above obligations, the Lead Member of the JV / the selected Bidder
shall maintain a minimum equity shareholding in the SPC as mentioned below:
(a)
(b)
The Lead Member / selected Bidder shall hold fifty – one percent (51%) Equity (as
defined under the Concession Agreement) in the Concessionaire till the expiry of
two (2) years from the date of issuance of the Implementation Completion
Certificate (as defined under the Concession Agreement); and,
The Lead Member / selected Bidder shall continuously hold at least, twenty – six
(26%) percent Equity of the Concessionaire for the entire Concession Period.
3.3.6.
Members of the JV shall be liable jointly and severally for the execution of the Project in
accordance with the terms of the Concession Agreement and a statement to this effect
shall be included in the Joint Venture (JV) Agreement mentioned under Clause 3.3.3
above, as well as in the bid and in the Concession Agreement. The Authority may require
such documents / undertakings / indemnities, as it may deem fit, from JV
members and the Bidder before or at the time of issuance of LoA / execution of the
Concession Agreement.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 19 of 195
3.3.7.
3.3.8.
3.3.9.
Each of the JV members shall be required to furnish a Deed of Guarantee as per the
format laid down in Clause 5(K), towards the SPC, including a resolution from the Board
of Directors of such JV members (in case of a company) or in other cases, by duly
authorized signatories of such entity in order to amount to a legal and binding obligation on
behalf of the JV members, pledging their financial strength and technical support and
their expertise towards the development of the Project and the performance of the
duties, responsibilities and obligations as envisaged under the Concession Agreement .
The single Bidder may also apply for the implementation of the Project. The single Bidder
would enter into the Concession Agreement and subsequently carry out all the
responsibilities of the selected Bidder and undertake the Project as stipulated in the
Concession Agreement. The single Bidder shall be required to furnish a Deed of
Guarantee as per the format laid down in Clause 5 (I), including a resolution of the
Board of Directors (in case of a company) from such Bidder or in other cases, by duly
authorized signatories of such entity in order to amount to a legal and binding obligation on
behalf of the single Bidder, pledging its financial strength and technical support and its
expertise towards the development of the Project.
The Lead Member nominated at the time of submission of the bids shall continue to be
the Lead Member of the SPC. Such Lead Member shall hold authorization in the form of
Power of Attorney. The bids must designate one or more person(s) to represent the
Bidder in its dealings with the Authority / the Engineer – in – charge. Unless specifically
informed to the contrary, prior to such performance, the Authority will assume that the
person(s) designated is authorized to perform all tasks, including, but not limited to,
providing information, responding to inquiries and entering into contractual
commitments on behalf of the Bidder or the JV as the case maybe. Any and all
limitations on the authority of the designated person(s) should be detailed in the bids.
The Lead Member should execute a Power of Attorney, in the form and format as set
out in Clause – 5 (L), in favour of the designated person(s), who shall represent the
Bidder. The Proposal must designate one or more person(s) to represent the Bidder in
its dealings with Engineer – in – charge. Unless specifically advised to the contrary,
Engineer – in – charge shall assume that the person(s) designated is authorized to
perform all tasks, including, but not limited to, providing information, responding to
inquiries and entering into contractual commitments on behalf of the single / individual
Bidder as the case maybe. Any and all limitations on the authority of the designated
person(s) should be detailed in the Proposal. The Bidder shall be required to give a
guarantee for the Project, if selected, in the form and format as set out in Clause – 5
(I) of this RFP.
3.3.10.
Each member of the JV shall submit a signed letter (on the official letter head) with
the bid, which states that the said member:
(a)
Has reviewed the entire bid;
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 20 of 195
(b)
(c)
(d)
Is in accord with each key element of the bid, including, but not limited to, its
technical and price components, description of the member's responsibilities and
commitments to the Project, and the designated person(s) who will represent the
JV during the negotiation process. Any exception or qualification, for whatsoever
reason, should be addressed in the enclosed letter;
Has participated in only one bid for this Project; and,
Each of the JV members will be jointly and severally liable to the Authority for
the purposes of execution of the Project.
3.3.11.
3.4.
3.4.1.
All information that may adversely affect the performance of the duties, responsibilities
and obligations, in accordance with the Concession Agreement, of a Bidder or any JV
member – including without limitation ongoing litigation, financial distress, or any other
such matter – must be disclosed to the Authority. The bidders shall provide such
evidence of their continued eligibility satisfactory to the Authority as the Authority shall
reasonably request from time to time. The Authority reserves the right to verify all
statements / information submitted to confirm the Bidder’s claim on experience,
performance of equipment offered and capabilities to perform the Project. The Authority
may inspect such works of Bidders. Bidder shall co – ordinate and arrange for visit to
such works. However all expenses of the Authority / Authority's representative will be
borne by the Authority.
FEE AND DEPOSITS TO BE PAID BY THE BIDDER
BID SECURITY
(a)
(b)
(c)
The bid shall be accompanied by an initial Bid Security, in original, for a value of
Rs. 50,000/- (Rupees fifty thousand only) in the following manner:
A bank guarantee issued by a scheduled bank, in accordance with the Reserve
Bank of India Act, 1934, in favour of Executive Engineer, Public Works
Division, Satara. and in the format given in Clause 5 (F).
The Bid Security shall be valid for a minimum period of 180 ( one hundred and
eighty) days from the Proposal Due Date. On a request from the Engineer – in –
charge, the Bidders would be required to extend the validity of the Bid Security on
the same terms and conditions.
The Bid Security of the selected Bidder shall be returned after the signing of the
Concession Agreement.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 21 of 195
(d)
(e)
Any Bid submitted without the Bid Security in the form as specified in the RFP shall
be summarily rejected.
The Bid Security of Bidders whose bid is rejected on account of being non –
responsive or non – reasonable in accordance with the RFP, shall be returned /
refunded within a period of sixty (60) days from the date of intimating the
rejection of the bid by the Authority to the Bidder. The Bid Security may be
encashed and appropriated by the Engineer – in – charge as liquidated damages
as genuine pre-estimate of the loss caused to the Authority, including but not
limited to, the occurrence of the following events at the sole discretion of the
Authority:
a.
b.
c.
d.
If the Bidder withdraws his Bid after the Proposal Due Date;
If the Bidder fails to accept and rectify the errors as intimated by the
Authority, within five (5) days from the date of such intimation;
If the selected Bidder fails within the specified time limit to furnish the
required Performance Security;
If a Bidder engages in a corrupt practice, fraudulent practice, coercive
practice, undesirable practice or restrictive practice;
In this regard, the terms “corrupt practices”, “fraudulent practices”,
“coercive practices”, “undesirable practices” and “restrictive
practices” shall have the following meanings:
“corrupt practice” means the offering, giving, receiving, directly or
indirectly, of anything of value to influence the action of a public official in the
bidding process;
“fraudulent practice” means a misrepresentation or omission of facts in
order to influence the bidding process;
“coercive practice” means harming or threatening to harm, directly or
indirectly, persons or their property to influence their participation in the
bidding process;
“undesirable practice” means establishing contact with any person
connected with or employed by the Authority with the objective of
canvassing, lobbying or in any manner influencing or attempting to influence
the bidding process; and,
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 22 of 195
“restrictive practice” means forming a cartel or arriving at any
understanding or arrangement among bidders with the objective of restrictive
or manipulating a full and fair competition in the bidding process.
e.
f.
g.
h.
i.
j.
k.
l.
m.
Non – compliance with the requirements of the RFP or any other document
referred to herein or issued pursuant thereto or any Applicable Laws relevant
for the tender process;
Cancellation and / or rejection of the Bid by the Authority, for any reason
whatsoever;
Submission of more than one bid by the Bidder;
Non – extension of the bid validity period and / or the period of validity of
the Bid Security, at the request of the Authority, in accordance with the
terms and conditions of this RFP;
Any conditions and / or qualifications imposed by the Bidder, during the
submission of the bids and / or the conduct of the bidding process;
At any time, a misrepresentation is made or discovered by the Authority;
the Bidder does not provide, within the time as may be specified by the
Authority (and if not specified within a reasonable period of time), the
supplemental information as sought by the Authority for evaluation of the
Bid;
The selected Bidder fails to incorporate the SPC within the stipulated time
period as per the RFP; and/or
If the selected Bidder fails within the specified time limit to execute the
Concession Agreement and/or the Land Licence Agreement and/or the
Selected Bidder Guarantee towards SPC.
Further, if on occurrence of any event, which in the sole discretion of the Authority,
should lead to the encashment and appropriation of the Bid Security as liquidated
damages as genuine pre-estimate of the loss caused to the Authority, it shall lead to the
disqualification of the Bidder for participating in any tender process conducted by the
Authority for a period of one (1) year starting from the date of appropriation of the Bid
Security, in accordance with the decision of the Authority in this regard.
The Bid Security of only the first three (3) ranked Bidders with the highest marks at the
end of the bid evaluation process would be retained till the Concession Agreement is
executed with the SPC. The Bid Security of the other Bidders would be returned within
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 23 of 195
60 (Sixty) day of opening of Financial Proposals. The Bid Security of the selected Bidder
shall be retained till the Concession Agreement is executed.
3.4.2.
3.5.
3.6.
PERFORMANCE SECURITY
The Selected Bidder, for due and faithful performance of its obligations under the
Concession Agreement, shall be required to provide a Performance Security of Rs.9,16,400/-
(Rupees Nine lakhs SixteenThousand Four Hundred only) to Executive Engineer, Public Works Division,
Satara within 30 (thirty) days of receipt of the LoA from the Executive Engineer, Public Works Division,
Satara.
This Performance Security shall not be refunded to the Concessionaire except upon
successful completion of Concession Period, after issuance of the Agreement Completion
Certificate (as defined under the Concession Agreement) in accordance with the terms
and conditions of the Concession Agreement.
SUBMISSION OF FOREIGN DOCUMENTS AND OTHER REQUIREMENTS
If the Bidder is submitting any documents, created or originating from outside the
Republic of India, such as work experience certificate(s), financial detail(s), Power Of
Attorney(s), Undertaking(s), documentary evidence(s), qualifying document(s), etc. then
the Bidder, before any such Foreign Document(s) are sent to India for the purpose of
applying towards this Project, shall be required to get each and every page of such
Foreign Document(s), duly authenticated / embossed / legalized / apostilled from the
Indian Embassy / Indian High Commission situated in the country from where such
foreign document(s) were created or are originating from. Such authentication /
embossment / legalization / apostillization from the Indian Embassy / Indian High
Commission shall also apply to all such document(s) that are in a language other than
English, which shall be compulsorily be required to be translated (as the true translated
copies of the original) by a duly certified / authorized / qualified translator, supported by
the affidavit of the said translator, certifying the correctness of the English translation.
The bidder shall not be from an ineligible source country i.e. the one with which (i) as a
matter of law or official regulation, India prohibits commercial relations, or (ii) by an act
of compliance with a decision of the United Nations Security Council taken under Chapter
VII of the Charter of the United Nations, India prohibits any import of goods or any
payments to persons or entities in that country.
USING NET WORTH AND / OR TECHNICAL SUPPORT / EXPERTISE OF HOLDING /
PARENT COMPANY
The Bidders who have used the net worth and/ or technical support / expertise of their
holding / parent company to satisfy the Minimum Eligibility Criteria shall be required to
furnish a Deed of Guarantee as per format attached in Clause 5(H) from their holding
/ parent company (including a resolution from the Board of Directors of such holding/
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 24 of 195
parent company) pledging their financial strength and technical support and their
expertise towards the development of the Project, apart from authorizing the said Bidder
to take part in the bidding process. Failure to furnish such Deed of Guarantee
(accompanied by a Board Resolution) from the holding / parent company by the Bidder
along with their bid may entail automatic disqualification of their proposals by the
Authority.
3.7.
3.8.
3.9.
3.10.
3.10.1.
ONE BID PER BIDDER
Each Bidder shall submit only one bid for each Project. Violation of this requirement
shall lead to disqualification of the Bidder along with the JV it is the part of and may lead
to the disqualification of the Bidder for participating in any tender process conducted by
the Authority for a period of one (1) year starting from the date of appropriation of the
Bid Security. The bid shall be unconditional. The Bids accompanied by any conditions
shall be liable to be rejected without citing any reasons thereof.
BID PREPARATION AND COSTS
All Bidders are required to submit a detailed bid in accordance with the guidelines set
forth in this RFP. Bidders should provide information sought herein in the prescribed
formats in order to enable the Authority to accurately establish and interpret the
information provided. The cost of preparation of the bids and all related expenses shall
be borne solely by the Bidders.
DUE DILIGENCE, INSPECTION AND INVESTIGATION
The Bidders shall be deemed to have conducted a due diligence exercise with respect to
all aspects of the Project, including a detailed survey of the Project, the Site and
information/ data provided by the Authority in this RFP, when they submit the bids.
Interested Bidders are invited to visit and inspect the Site at their own expense. Failure
to investigate the Site(s), whereupon the Jan Suvidha Kendra and the Project shall be
constructed or subsurface conditions shall not be a valid ground to relieve the
Bidder subsequently after the Proposal Due Date nor shall it relieve the Bidder from any
responsibility for estimating the difficulty or costs of successfully completing the Project.
VALIDITY OF BIDS
The Bid shall remain valid for a period not less than one hundred eighty (180) days
from the Proposal Due Date (“Bid Validity Period”). The Authority reserves the right to
reject any or all bids, without being required to ascribe any reasons thereof. Validity of bid
shall be extended for a specified additional period at the sole discretion of the Authority,
without being required to ascribe any reasons thereof. Such Bidders will not be allowed
to modify its bids, but would be required to extend the validity of his Bid Security for
the period of extension.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 25 of 195
3.10.2.
3.11.
3.11.1.
3.12.
3.13.
3.13.1.
For the avoidance of any doubt, it is hereby clarified that the Bid Validity Period of the
selected Bidder shall be extended automatically, till the date of execution of the
Concession Agreement.
RIGHT TO REJECT BIDS
The Authority reserves the right to reject any / all bids and / or withdraw the invitation
of bids at any stage without citing any reason whatsoever. Nothing contained herein
shall confer any right upon a Bidder or create any obligation/ liability upon the Authority
of any type whatsoever. At any time prior to issuance of the LoA, the Authority reserves
the right to accept or reject any bid, or to annul the bidding process and reject all bids at
his sole discretion without assigning any reason thereof, and without thereby incurring
any liability to the affected bidder or bidders or any obligation to inform the affected
bidder or bidders of the grounds for the Authority’s action. The Authority shall not in any
circumstance, way or manner whatsoever be liable to the selected Bidder for any
consequential loss or damage including loss of profits. The Authority shall be the sole
judge in the selection of the qualified bidders as well as the selected Bidder.
MISREPRESENTATION AND / OR FRAUD AND / OR BREACH OF TERMS AND
CONDITIONS
If it is discovered at any point of time that the Bidder has suppressed any material fact or
given a false statement or has done misrepresentation or fraud or has violated any of
the terms of this Bid, the Bid shall be cancelled by the Authority. In such an event, the
Bidder will not be entitled to any compensation whatsoever, or refund of the Bid Security
and / or any other amount paid to the Authority by the Bidder.
AMENDMENTS TO THE RFP
At any time prior to the Proposal Due Date, Engineer – in – charge may, for any reason,
whether at its own initiative or in response to clarifications requested by a Bidder,
modify the RFP through the issuance of corrigenda, addenda and / or the common set
of deviations. This shall be hosted on the website of the Authority and shall be binding
upon the Bidders. The corrigenda, addenda and / or the common set of deviations shall
also include the pre – bid minutes. However, the Authority reserves all rights to issue
corrigenda, addenda and / or the common set of deviations without being required to
conduct the Pre – Bid Meeting prior to any issuance of such corrigenda, addenda and /
or the common set of deviations. The bidding documents (including the RFP, any
addenda, corrigenda and / or other ancillary documents and clarifications) should be
read as a whole, and the bidder shall at all times be presumed to have full knowledge of
the bidding documents and shall agree to be in full compliance of the requirements of
the bidding documents as amended and / or revised from time to time.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 26 of 195
3.13.2.
3.14.
In order to give the Bidders, reasonable time in which to take a corrigendum, addendum
and / or the common set of deviations into account, or for any other reason, Engineer –
in – charge may, at its sole discretion, extend the Proposal Due Date.
GOVERNING LAW AND JURISDICTION
The governing law for this RFP shall be the laws in force in India from time to time. The
courts at Satara, Maharashtra shall have exclusive jurisdiction over all disputes arising under, pursuant to
and / or in connection with this RFP and the tender process hereunder. For the avoidance of any doubt, it is hereby
clarified that this jurisdiction clause shall not apply to any dispute resolution process conducted after the
execution of the Concession Agreement. Any dispute after the execution of the Concession
Agreement will be resolved as per the provisions of the Concession Agreement.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 27 of 195
4.
TENDERING PROCEDURE AND SCHEDULE
4.1.
GENERAL REQUIREMENTS
The Bidders shall be required to send their queries, on the RFP and / or the Project, online
or by post to the Engineer – in – charge, Public Works Division,
Satara. email address:
______________________________________________________ at least 7 (seven) days
prior to the date of the Pre – Bid Meeting.
4.2.
PRE – BID MEETING
(a)
(b)
(c)
The purpose of the Pre – Bid Meeting will be to clarify and discuss issues with
respect to the Project, the RFP or any other related issues;
The Bidder or his authorized representative is invited to attend a Pre – Bid
Meeting, which shall take place at the conference room of the Chief Engineer,
Public Works Region, Pune.
The Bidders and / or their designated representatives are invited to attend the Pre
– Bid Meeting at their own cost, to be held on 28.04.2017 at Pune the
Conference Room of the Chief Engineer, Public Works Region
Pune.
4.3.
PREPARATION AND SUBMISSION OF BIDS
(a)
(b)
(c)
(d)
(e)
Completed bids shall be accepted as per schedule of tender process as provided in
this RFP;
The Authority, at its sole discretion, reserves the right, but is not obliged, to
extend the Proposal Due Date by issuing an addendum and / or corrigendum;
Bidders shall furnish the information strictly as per the formats given in Clause 5
of this RFP without any conditions, qualifications and / or ambiguity. The
Authority shall not be held responsible if the failure of any Bidder to provide the
information in the prescribed formats results in lack of clarity in interpretation and
consequent disqualification;
In case of a JV, wherever required, the Bid must contain such information
individually for each member of the JV;
In case of a JV, the members shall submit a Joint Venture (JV) Agreement
conveying their intent to jointly bid for the Project and in case the Project is
awarded to them, to form the SPC that will subsequently carry out all its
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
PARTICULARS TIMELINES
1. Commencement of availability of the RFP 21.04.2017 at 10.00 am to 05.05.2017 at
23.00 pm.
2. Pre – Bid Meeting Online or in the office of the Chief
Engineer, P.W. Region Central Building,
Pune on or before Dt. 28/04/2017 upto
11.00 a.m.
3. Proposal Due Date Dt. 09/05/2017 upto 23.00 p.m.
4. Last date of submission of Bid Security and
the Deed of Guarantee by Parent Company
(if applicable)
Page 28 of 195
responsibilities as the Concessionaire. The Memorandum of Association shall also
include the nomination of the Lead Member in the JV and clearly outline the
proposed shareholding and responsibilities of each member at each stage;
(f)
(g)
(h)
(i)
(j)
All Bids shall be signed by the duly authorized signatory of the Bidder. In case of a
JV, the Bid shall be signed by the duly authorized signatory of the Lead Member.
Bidders shall submit a supporting Power of Attorney authorizing the authorized
signatory of the Bid to submit such bid on behalf of the Bidder and ratifying all
acts, deeds, matters and things lawfully done by the said attorney. In case of a JV,
such Power of Attorney shall be signed by all members of the JV and shall be
legally binding on all of them;
The authorized signatory shall initial the Bid on each page. The authorized
signatory shall initial each page of the RFP including without limitation the
Concession Agreement and submit the duly signed RFP to the Authority along with
the Bid. The authorized signatory shall also initial all the alterations, omissions,
additions, or any other amendments made to the Bid;
All witnesses and sureties shall be the persons of status and probity and their full
names and addresses shall be stated below their signature. All signatures in the
Bid shall be dated;
Bidders are required to submit online one original set of the Bid, including the RFP
and any corrigendum and / or addenda issued to them; and,
Any Bidder which submits or participates in more than one Bid for the said Project
shall be disqualified and shall also cause the disqualification of all the JV(s) in
which it is a member.
4.4.
SCHEDULE OF THE TENDER PROCESS
The schedule of the tender process shall be as per the tentative timelines specified below:
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
5. Opening of the Technical Bid
6. Declaration of Technically Qualified Bidders
7. Opening of the Financial Bid of Technically
Qualified Bidders
8. Issuance of Letter of Award to the selected
Bidder
9. Last date for:
(i) incorporation of the Concessionaire;
(ii) submission of the Performance
Security by the selected Bidder; and
(iii) submission of the Selected Bidder
Guarantee towards SPC.
10. Execution of the Concession Agreement
11. Execution of the Land License Agreement
Page 29 of 195
4.5.
4.5.1.
4.5.2.
4.6.
4.6.1.
LANGUAGE AND CURRENCY
The Bid and all related correspondence and documents shall be written in English
language. If any supporting document attached to the Bid is in any other language, the
same will be supported by an English translation (duly authenticated / attested /
apostilled from Indian Embassy in respective countries).
The currency for the purpose of the Bid shall be Indian Rupees (INR).
GENERAL RESPONSIBILITIES OF THE BIDDER
It would be deemed that prior to the submission of the Bid, the Bidder has made a
complete and careful examination of:
(a)
(b)
The requirements of the Jan Suvidha Kendra, the Project and the Site and other
information as set forth in this RFP;
The Bidder shall be solely responsible for the complete and careful examination of
the various aspects of the Project including but not limited to the following:
a.
The existing facilities and structures (if any), access roads and public
utilities, water availability, etc. in the vicinity of the Project; and,
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 30 of 195
b.
c.
d.
e.
All other matters that might affect the Bidder’s performance under the
terms of this RFP, including all risks, costs, liabilities and contingencies
associated with the Project;
The Bidders prior to submitting their Bid for the Project, are expected to visit
and examine the Site(s) and surroundings at their own expenses, the Site
will be offered by Engineer – in – charge “as is where is” basis and
ascertain on their own responsibility all requisite information, technical data,
traffic data, etc.;
It shall be assumed that all these factors were accounted for by the Bidder
while quoting his bid. The bidder shall be deemed to have full knowledge of
the Site whether the Bidder inspects it or not; and,
The Authority shall not be liable for any mistake or error or neglect by the
Bidder in respect of the above. Bids that are not substantively responsive to
the requirements of this RFP will be rejected.
4.7.
4.7.1.
4.7.2.
SUBMISSION OF BIDS
An authorized representative of the Bidder shall initial all pages of the original Bids. The
signed technical and financial Bids shall be marked as “ORIGINAL”;
The Bids must be sent online on www.maharashtra.etenders.in and received online
no later than the time and the date indicated in the RFP, or any extension to this date in
accordance with the terms and conditions of this RFP. Any Bid received by the Authority
after the deadline for submission shall be returned unopened.
.
4.7.3. The Technical Bid shall be marked as the “TECHNICAL BID” contain the following:
Relevant documents (like Certificate of Incorporation, Memorandum of Association and
Articles of Association (for companies), Deeds (for partnership firms, trusts and limited
liability partnerships), Joint Venture (JV) Agreement (if applicable), audited financial
statements of last three financial years and evidence of experience like client certificate,
work orders etc., details of financing arrangements etc.) confirming the Minimum Eligibility
Criteria, as set out in this RFP:
(a)
(b)
(c)
(d)
Letter of Application and Interest (as per Clause 5 (A));
General Information on the Bidder (as per Clause 5 (B));
Power of Attorney for Signing of Application (as per Clause 5 (E));
Affidavit (as per Clause 5 (D));
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 31 of 195
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
Original RFP Document duly signed (on each page) by an authorized representative
as a token of acceptance;
Power of Attorney by Each Member of the JV in Favour of Lead Member (as per
Clause 5 (G));
Power of Attorney by the Lead Member of the JV in favour of its duly authorized
representative (as per Clause 5 (L));
Deed of Guarantee (as per Clause 5 (H)), if applicable;
A letter (on company’s letter head) from all the JV members as laid down in
Clause 3.3.8;
All other required submissions, if the Bidder is applying through JV or as a single
Bidder and as stated in this RFP;
A copy of Joint Venture agreement (if applicable);
A copy of the Bid Security, in original.
4.7.4.
4.7.5.
4.7.6.
4.7.7.
4.8.
4.8.1.
4.8.2.
Further the bidder should submit original of the Bid Security and the Deed of Guarantee of
the parent / holding company to the Authority within 2 (two) days of the Proposal Due
Date at the prescribed address.
The original and all copies of the Technical Bid shall be submitted online on
www.maharashtra.etenders.in. Further, the original Financial Bid shall be submitted
online on www.maharashtra.etenders.in clearly marked as “FINANCIAL BID”
followed by the name of the Project.
The Bids must be sent online on www.maharashtra.etenders.in and received online
no later than the Proposal Due Date, or any extension to this date in accordance with
RFP.
Any Bid received by the Authority after Proposal Due Date will be liable for rejection by
the Authority, without being required to provide any reasons whatsoever.
MODIFICATION AND / OR WITHDRAWAL OF BIDS
No Bid shall be modified or withdrawn by the Bidder after the Proposal Due Date.
Withdrawal of a Bid during the interval between Proposal Due Date and expiration of the
Proposal Validity Period would result in encashment and appropriation of the Bid Security.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 32 of 195
4.9.
4.9.1.
4.9.2.
OPENING OF THE BIDS
The Bids received shall be opened by the Authority or its representative in the presence
of the Bidders at on dates as mentioned in this RFP, unless intimated otherwise.
The Authority reserves the right to reject any Bids, without being required to ascribe any
reasons whatsoever, including but not limited to the following events:
(a)
(b)
(c)
(d)
(e)
(f)
It is not signed, sealed and marked as stipulated under this RFP;
The information and documents have not been submitted as requested and in the
formats specified in the RFP;
There are inconsistencies between the Bids and the supporting documents;
There are conditions proposed by the Bidder in its Bids;
The Bids provide the information with material deviations and / or reservations;
Any non – compliance with the requirements as stated under this RFP.
4.9.3.
A material deviation and / or reservation shall mean a deviation and / or reservation which
as per the Authority:
(a)
(b)
(c)
Affects in any material manner the scope, quality, or performance of the Jan
Suvidha Kendra and the Project, or,
Limits in any material way, inconsistent with the RFP, rights or the Bidder’s
obligations, or,
Would potentially affect and / or unfairly prejudice the competitiveness of the Bids
of other Bidders who have submitted substantially responsive bids
4.10.
4.10.1.
EVALUATION OF BIDS
The evaluation shall be conducted in two (2) steps as follows:
In STEP 1, the Bid Security shall be first checked by the Authority. Bids without the
appropriate Bid Security shall be rejected. Then the submission(s) submitted online shall
be checked. All Bidders who have in the opinion of the Authority, duly provided the Bid
Security will be considered responsive enough to be considered for the next steps of
evaluation.
Marking for Technical Evaluation:
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Sr. No. Evaluation Point and Criteria Maximum Marks
1. Specific experience of the Concessionaire, as
sole entity or Joint Venture, relevant to the
Project:
20 Marks
a. Construction of Jan Suvidha Like facility.
One Project
Two Projects
Three or More Projects
10 Marks
6 marks
8 marks
10 marks
b. Operation and Maintenance of above facility.
One Project
Two Projects
Three or More Projects
10 Marks
6 marks
8 marks
10 marks
2. Providing maximum facilities in proposed
construction to be quoted by the Concessionaire.
20 Marks
3. Providing maximum free facilities like mineral
water, toilet and other sanitary requirements for
women.
20 Marks
4. Key Professional staff for the Assignment. 5 Marks
5. Quality management standards in design,
construction and operation and maintenance
services; safety standard in construction, new
methodologies, novel concepts, etc.
5 Marks
Page 33 of 195
In order to be technically qualified, the Bidders have to obtain minimum fifty (50) marks
out of a maximum of hundred (100) marks, as per the mechanism of marking as set out
below:
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
6. Presentation: The bidders shall give a
presentation in Power point format with
walkthrough and shall include detail
methodology for execution of the Project,
planning for the operation and maintenance of
Jan Suvidha Kendra for the Concession Period,
deployment of the team, financial capability,
financial analysis and arrangement to finance the
Project and subsequent planning for provision of
premium to Authority (these shall include
detailed cash flows, the parameters considered
in calculating the premium, revenue resources
considered, etc.) It is clarified that the bidder
shall propose to construct and build the best
facilities. The marking under this head will be
linked to the quality of materials, fittings and
overall structures used therein for the entire
facilities of the Project.
30 Marks
TOTAL 100 Marks
Page 34 of 195
The Technical Bid will be given a weightage of seventy (70%) percent out of the
aggregate of marks (“Aggregate Marks”) awarded in both steps of the tender process to
be awarded to the Bidder and the method of evaluation of technical qualification of the
Bidders shall follow the procedure as given above. The Financial Bids of only those Bidders
who qualify technically and who score minimum fifty (50) marks out of a maximum of
hundred (100) marks will be declared as qualified in STEP 1 of the tender evaluation
process.
4 . 1 0 . 2 . In STEP 2 of the tender evaluation process, the Financial Bids submitted online of only
those Bidders who have qualified through STEP 1 of the tender process shall be opened
by the Authority in presence of the duly authorized representatives of the Bidders, who
choose to attend the same. The bidder getting the maximum Aggregate Marks shall be
qualified.
Marking for Financial Evaluation:
1.
Providing maximum Licence Fees to
Government for use of land for the
Rs.______________ Lakh to be
quoted by the Concessionaire.
Concession Period to be quoted by the
Concessionaire.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 35 of 195
The Bid with the maximum License Fees may be given a score of hundred (100) marks out
of a maximum of hundred (100) marks and the other Bids shall be given scores that are
inversely proportionate to their quoted License Fees.
The financial Bid shall be allocated a weightage of thirty (30%) percent out of the
Aggregate Marks.
In order to calculate the Aggregate Marks, the Authority will use the following formula:
Aggregate Marks = T (w) x T (s) + F (w) x EC / MEC x 100
Where,
T (w) stands for weight of the Technical Bid
T (s) stands for marks awarded for the Technical Bid
F (w) stands for weight of the Financial Bid
EC stands for Evaluated Cost of the Financial Bid
MEC stands for Maximum Evaluated Cost of the Financial Bid
The Bids will be ranked in terms of Aggregate Marks scored by each Bidder. The Bid with
the highest Aggregate Marks may be considered for award of the LoA and shall be called
for negotiations, if required.
All Taxes (including service tax and GST) applicable and/or payable on the Licence Fees
and the annual incremental premium shall be borne and discharged by the Concessionaire
at actuals as per the instructions of the Authority.
4 . 1 0 . 3 . In the event that two or more Bidders quote exactly the same for the Project, then the
Authority reserves the right either to:
(a)
(b)
(c)
Identify the selected Bidder by the draw of lots, which shall be conducted, with
prior notice, in the presence of the Bidders;
Selecting the Bidder who has provided for maximum utilisation of the available
space at the Site, keeping in mind the aims and objectives of the Project, while
maintaining compliance with all relevant rules, guidelines and Applicable Laws; or,
Take any such measure as may be deemed fit in its sole discretion, including
annulment of the bidding process.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
A Chief Engineer, PW Region , Pune. Chairman
B Superintending Engineer, PW Circle , Satara. Member
C Dy. Chief Architect , Pune. Member
D Executive Engineer PW Division , Satara. Member, Secretary
E Other technical expert or financial expert as
decided by the Chairman
Member
Page 36 of 195
4.10.3.1. In the event that the Bidder (“First Ranked Bidder”) with the highest Aggregate Marks,
withdraws or is not selected for any reason in the first instance (the “First Round of
Bidding”), the Authority may invite all the remaining Bidders to revalidate and / or
extend their respective Bid Security, as necessary, and match the Bid of the First Ranked
Bidder at a second round of bidding (the “Second Round of Bidding”). If in the
Second Round of Bidding, only one Bidder matches the Bid of the First Ranked Bidder, it
shall be the selected Bidder. If two or more Bidders match the said First Ranked Bidder in
the Second Round of Bidding, then the Bidder who has provided for the maximum
utilisation of the available space at the Site, keeping in mind the aims and objectives of
the Project, while maintaining compliance with all relevant rules, guidelines and
Applicable Laws shall be the selected Bidder.
4.10.3.2. In the event that no Bidder offers to match the First Ranked Bidder in the Second Round
of Bidding as specified in Clause 4.10.3.1 of this RFP, the Authority may, annul the
bidding process and in its discretion, invite fresh Bids.
4.10.4.
4.10.5.
4.10.6.
4.10.7.
The Authority would have the right to review the Bids and seek clarifications where
necessary. The response from the Bidder(s) shall only be in writing but no material
change in the substance and / or the content of the Bids would be permitted. It is
clarified that Bidders are free to make suggestions but are not allowed to submit any
conditional bids to the Authority.
The Bids (Financial and Technical) should be unconditional and any conditionality
attached with the Bid may result in the rejection of the Bids.
Financial Bids of Bidders who do not qualify the STEP 1 of the tender evaluation
process shall not be opened.
The Bids submitted shall be evaluated by the Project Evaluation Committee as
mentioned hereunder:
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 37 of 195
4.11.
4.12.
4.12.1.
4.12.2.
4.12.3.
4.12.4.
4.13.
4.13.1.
CONFIDENTIALITY
Information relating to the examination, clarification, evaluation and recommendation for
the short – listed Bidders shall not be disclosed to any person not officially concerned
with the process.
ACCEPTANCE OF BIDS
The Authority shall issue LoA to the selected Bidder for the Project.
The selected Bidder is required to send his acceptance of the LoA within seven (7)
days from the date of its receipt as acknowledgement of the same.
The Authority shall retain the right to withdraw the LoA in the event of the selected
Bidder failure to accept the LoA within the time limit as specified in the above clause.
In such event, the Authority may encash the Bid Security of the selected Bidder.
EXECUTION OF THE CONCESSION AGREEMENT
The Concessionaire is required to sign the Concession Agreement within forty – five (45)
days of issuance of the LoA in writing or the date as mutually agreed between the Parties
for the execution of the Concession Agreement. But prior to execution of the Concession
Agreement, the selected Bidder must satisfy the following conditions, within a period of
thirty (30) days from the date of the LoA:
(a)
(b)
(c)
The selected Bidder has submitted the requisite Performance Security, in original,
to the Authority;
Formation of a SPC, as per the provisions laid down in Clause 3.3.4, within thirty
(30) days from the date of the LoA by the selected Bidder.
Furnishing of Deed of Guarantee by the selected Bidder, in case of a JV, then as
per format provided in Clause 5 (K) and to be provided by all the JV members
towards the SPC or if a single Bidder, then as per format provided in Clause
5(I) hereto.
The Authority shall not execute the Agreement until these conditions have been satisfied.
4.13.2.
The selected Bidder shall not make any delays in submission of all requisite documents,
as detailed out in Clause 4.13.1 of this RFP and in the event that the selected Bidder
requests for extension then the Authority should have right to declare such other Bidder
who has obtained the second highest Aggregate Marks among all eligible Bids, as
selected Bidder.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 38 of 195
4.13.3.
4.13.4.
4.13.5.
4.14.
4.14.1.
4.14.2.
4.15.
Failure to meet the conditions, as laid down in Clause 4.12 of this RFP within the
prescribed time limit (including extension, if any) shall result in breach of the terms of
this RFP and the Authority shall be entitled to cancel the LoA without being liable, in any
manner whatsoever, to the Bidder and shall be entitled to appropriate the Bid Security
and any other amounts deposited till such time in lieu of liquidated damages, as genuine
pre – estimate of the losses caused to the Authority.
The cost of any stamp duty, registration charges and any other related legal
documentation charges and other incidental charges payable under Applicable Laws, for
execution of the Concession Agreement shall be borne by the selected Bidder.
In case of failure to sign the Concession Agreement within the stipulated time for any
reason whatsoever, the Authority shall retain the right to cancel the LoA and encash the
Bid Security of the selected Bidder and any other amount deposited till that time without
being liable in any manner whatsoever to the selected Bidder.
BIDS OF OTHER BIDDERS
The Authority shall return the Bid Security received from the Bidders who have not
qualified in STEP 1 of the tender evaluation process, within 180 (one hundred and
eighty) days of the opening of the Technical Bid. The Bid Security shall be returned
without payment of any interest, charges, duties and / or fees by the Authority.
The Bid Security received from all the short listed Bidders after STEP 2 of the tender
evaluation process (except the first three ranked Bidders at the end of the tender
evaluation process) shall be returned within 60 (sixty) days from the date of opening of
Financial Bid, and returned thereafter, without payment of any interest, charges, duties
and / or fees by the Authority.
MISCELLANEOUS
The Authority, in its sole discretion and without incurring any obligation and / or liability,
reserves the right at any time to:
(a)
suspend
and / or
cancel
the
bidding process
and / or
amend
and / or
supplement the bidding process or modify the dates or other terms and conditions
relating thereto;
(b)
(c)
Consult with any Bidder in order to receive any clarifications;
retain any information and / or evidence submitted to the Authority by or on behalf of,
and / or in relation to any Bidder; and / or,
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 39 of 195
(d)
independently verify, disqualify, reject and / or accept any and all submissions or
other information and/ or evidence submitted by or on behalf of any Bidder.
It shall be deemed that by submitting the Bid, the Bidder has agreed to the terms and
conditions of this RFP and has released the Authority, its employees, agents and
advisers, irrevocably, unconditionally, fully and finally from any and all liability for claims,
losses, damages, costs, expenses or liabilities in any way related to or arising from the
exercise of any rights and / or performance of any obligations hereunder, pursuant
hereto and / or in connection with the bidding process and waives, to the fullest extent
permitted by applicable laws, any and all rights and / or claims it may have in this RFP.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 40 of 195
5.
PRESCRIBED FORMATS
A.
LETTER OF APPLICATION AND INTEREST
(To be submitted and signed by the Bidder’s Authorized Signatory)
To
The Executive Engineer,
Public Works Division, Satara.
_______________,
_________
Sub: Request for Proposal (“RFP”) bearing No. __________________________ for the Project
titled “Design, Build, Finance, Construction, Development, Implementation,
Operation and Maintenance of the Jan Suvidha Kendra, at Rest House Khandala,
Maharashtra”
Sir,
1.
Being
duly
authorized
to represent and act for and on behalf of.……………
(hereinafter referred to as the “applicant”), and having studied and fully understood all
the information provided in the RFP, the undersigned hereby applies for and on behalf of
the Bidder for “Design, Build, Finance, Construction, Development,
Implementation, Operation and Maintenance of the Jan Suvidha Kendra, at
Rest House Khandala , Maharashtra” according to the terms and conditions of the RFP issued by
the Authority.
2.
3.
4.
Our Technical and Financial Bids are as per the requisite formats along with the supporting
documents, duly filled and signed on each page are enclosed in separate sealed envelopes
as specified.
The Bid Security shall be submitted in original in accordance with the requirements of the
RFP.
Engineer - in - charge and its authorized representatives are hereby authorized to conduct
any inquiries / investigation to verify the statements, documents and information submitted
in connection with the application and to seek clarifications regarding any financial and
technical aspects. This letter of application will also serve as authorization to any individual
or authorized representative of any institution referred to the supporting information, to
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 41 of 195
provide such information deemed necessary and requested by you to verify statements and
information provided in the application or with regard to the resources, experience and
competence of the applicant and the Bidder.
5.
6.
Engineer – in – charge and its authorized representatives may contact the following
persons for any further information:
Name of the person(s): ________________________________
Address: ___________________________
Phone: ______________ Fax:____________
This application is made with full understanding that:
a.
b.
The Authority reserves the right to reject or accept any Bids, cancel the bidding
process, and / or reject all Bids.
The Authority shall not be liable for any of the above actions and shall be
under no obligation to inform the applicant of the same.
7.
8.
9.
10.
We, the undersigned declare the statements made and the information provided in the duly
completed application forms enclosed, as complete, true and correct in every detail.
We hereby confirm that we have read, understood and accepted all the detailed terms and
conditions of this RFP and Project related information as required for the Bid. We have also
visited the proposed Project sites and surroundings, for the assessment and have made our
own due diligence and assessment regarding the Project.
We agree to keep our Bid valid for one hundred eighty (180) days from the Proposal Due
Date (as may be changed from time to time) thereof and not to make any modifications in
its terms and conditions after the Proposal Due Date. We hereby agree to abide by and
fulfil all the terms, conditions and provisions of the RFP.
This application is made with the full understanding that the validity of bid submitted by us
will be subject to verification of all information, terms and conditions submitted at the time
of bidding and its final acceptance by the Authority. We agree that, without prejudice to
any other right or remedy, the Authority shall be at liberty to encash the said Bid Security
absolutely.
Authorized signatory:
Name and seal of Bidder:
Date:
Place:
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Sl. No. Name of Member Proportion of Equity to
be
Role*
1 held in the
2 JV
3
Page 42 of 195
B.
GENERAL INFORMATION ON THE BIDDER
1.
(a)
(b)
(c)
Name :
Country of incorporation :
Address of the corporate headquarters and its branch office(s), if any,
India :
2. Details of individual(s) who will serve as the point of contact / communication for
Engineer - in - charge within the Company:
(a) Name
(b) Designation
(c) Company
(d) Address
:
:
:
:
(e) Telephone Number:
(f) Fax Number
(g) E-Mail Address
:
:
3.
In case of JV:
a. The information above (at 1 and 2) should be provided for all the members of the
JV.
b. Information regarding role of each member should be provided:
* Specify whether Lead Member / ordinary Member
Signed
(Name of the Authorised Signatory)
For and on behalf of
(Name of the bidder)
Designation:
Place:
Date:
To be enclosed:
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 43 of 195
1. Documents certifying Bidder’s legal status i.e. certificate of incorporation / registration.
2. In case of a JV, JV Agreement& Power of Attorney signed by each JV partner,
clearly indicating the lead partner.
3. Latest brochures/ organization profiles, etc.
C.
FORMAT FOR FINANCIAL BID
(To be submitted and signed by the Bidder’s Authorized Signatory)
To
The Executive Engineer,
Public Works Division, Satara.
__________________
________________
Sub: Request for Proposal (“RFP”) bearing No. __________________________ for the Project titled
“Design, Build, Finance, Construction, Development, Implementation, Operation
and Maintenance of the Jan Suvidha Kendra, at Rest House Khandala Maharashtra.”
Sir,
We hereby submit our Financial Bid for the captioned Project in response to this RFP issued
by the Executive Engineer, Public Works Division, Satara.
We are making this Bid after taking into consideration all the terms and conditions stated in the
RFP, and after careful assessment of the Site, all risks and contingencies and all other conditions
that may affect the financial proposal.
We also hereby confirm the following:
a. This Financial Bid is being submitted by [NAME OF BIDDER] in accordance with the
conditions stipulated in the RFP.
b. We have examined in detail and understand and agree to abide by all terms and conditions
stipulated in the RFP issued by the Authority as amended, and in any subsequent
communication sent by the Authority. Our Financial Bid is consistent with all requirements
of submission stated in the RFP and in any subsequent communication. Our Financial Bid is
as follows:
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Free facilities to be first year us –
a. 30 years.
Page 44 of 195
Sr.
Details
No.
1
2
3
Detail Facilities to be provided by us in the proposed Construction.
a. …(give description of facilities like toilets, water, ATM,
restaurants, etc. )
b. …
c.
…
d. …
e. .. Providing maximum Licence Fees to the Authority for use of land for the
Concession Period
Government for theprovided byand percentage hike in subsequent
years for…(give description of services)
b. …
c.
…
/Nos./
Amount in
INR
d. ..
e. …
Total
We agree to keep our Bid valid for a period 180 (one hundred and eighty) days from the
Proposal Due Date.
Authorized signatory
Name and seal of Bidder
Date: Place:
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 45 of 195
D.
AFFIDAVIT
(To be given separately by each JV member, in case of a JV or otherwise by the
Bidder on a Stamp Paper of Rs. 100/- and should be notarized)
I ,.…………………..………., S/o …………..…………..………….., Resident of …………..……………….,
the ……………... (insert designation) of the ………………………..….. (insert name of the single
Bidder/JV Member if a JV), do solemnly affirm and state as under :
1. That I am the authorized signatory of …………..(insert name of company /JV member)
(hereinafter referred to as “Bidder/JV Member”) and I am duly authorized by the
Board of Directors of the Bidder/JV Member to swear and depose this affidavit on behalf of
the Bidder/JV member.
2. That I have submitted information with respect to our eligibility for the project titled
“Design, Build, Finance, Construction, Development, Implementation, Operation
and Maintenance of the Jan Suvidha Kendra, at Rest House Khandala ,Maharashtra.”
(hereinafter referred to as “Project”) and I further state that all the said information
submitted by us is accurate, true and correct and is based on our records available with us.
3. That I hereby affirm to furnish any information, which may be requested by Authority to
verify our credentials/information provided by us under this Bid and as may be deemed
necessary by the Authority.
4. That if any point of time including the Concession Period, in case the Authority requests
any further/additional information regarding our financial and/or technical capabilities, or
any other relevant information, I shall promptly and immediately make available such
information accurately and correctly to the satisfaction of the Authority.
5. That I fully acknowledge and understand that furnishing of any false or misleading
information by us in our RFP shall entitle us to be disqualified from the tendering process
for the said Project. The costs and risks for such disqualification shall be entirely borne by
us.
6. That, we fully acknowledge and understand that in case any false or misleading
information, as furnished by us in our RFP, is found at a later stage after the execution of
the Concession Agreement, it shall entitle Engineer – in – charge to terminate the said
signed Concession Agreement between the Parties. The costs and risks for such termination
shall be entirely borne by us.
That all the terms and conditions of the Request for Proposal (RFP) have been duly complied
with.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 46 of 195
DEPONENT
VERIFICATION:
I, the above named deponent, do verify that the contents of paragraphs 1 to 6 of this affidavit
are true and correct to my knowledge. No part of it is false and nothing material has been
concealed.
Verified at ………………………, on this …………………. day of………….…….., 201____.
DEPONENT
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 47 of 195
E.
FORMAT FOR POWER OF ATTORNEY FOR SIGNING OF APPLICATION AND
OTHER REQUIRED DOCUMENTS
(To be notarized)
Know all men by these presents, we/ I ……………………………………. (name and address of the
registered office) do hereby constitute, appoint and authorize Mr./Ms.…………………..(name and
residential address) as our attorney, to do in our name and on our behalf, all such acts, deeds
and things necessary in connection with or incidental to our Bid for the Project envisaging
“Design, Build, Finance, Construction, Development, Implementation, Operation and
Maintenance of the Jan Suvidha Kendra, at Rest House Khandala , Maharashtra.” at
___________(location), (State Maharashtra) in the Union of India, including signing and
submission of all documents and providing information/responses to the Authority, representing
us in all matters before the Authority, and generally dealing with the Authority, in all matters in
connection with our Bid for the said Project.
We hereby agree to ratify all acts, deeds and things lawfully done by our said attorney pursuant
to this Power of Attorney and that all acts, deeds and things done by our aforesaid attorney shall
always be deemed to have been done by us.
For…………………………………………. Accepted
…………………...(Signature)
(Name, Title and address) of the Attorney
Note:
The mode of execution of the Power of Attorney should be in accordance with the procedure, if
any, laid down by the applicable law and the charter documents of the executant(s) and when it
is so required the same should be under common seal affixed in accordance with the required
procedure.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 48 of 195
F.
FORMAT FOR BID SECURITY AS BANK GUARANTEE
BID SECURITY FORMAT
(to be valid for 180 days from the Proposal Due Date)
UNCONDITIONAL AND IRREVOCABLE BANK GUARANTEE
Bank Guarantee No.: Dated ________________
Issuer of Bank Guarantee:
Name of the bank _____
_____________
________________
(hereinafter referred to as the “Bank”)
Beneficiary of Bank Guarantee: Executive Engineer, Public Works Division,
Satara.
Nature of Bank Guarantee:
Unconditional and irrevocable Bank Guarantee.
Context of Bank Guarantee:
In pursuance of Clause 3.4.1 of Section 1 of the Request for Proposal Document dated
(hereinafter referred to as the “RFP” inclusive of Agreement) for the “Design, Build, Finance,
Construction, Development, Implementation, Operation and Maintenance of the Jan
Suvidha Kendra, at Rest House Khandala , Maharashtra.” (hereinafter referred to as the “Project”),
provided however, such context of the Bank Guarantee or reference to the Concession
Agreement in this Bank Guarantee shall in no manner to relied upon at any stage to adversely
affect or dilute the unconditional and irrevocable nature of this Bank Guarantee. The contract
of Bank Guarantee is an independent contract between the Bank and Executive Engineer, P.W.
Division, Satara and is not dependent upon execution or performance of any
Agreement between Executive Engineer, P.W. Division, Satara and
(Name of the Bidder).
Operative part of the Bank Guarantee:
1.
At the request of the (Name and Address of the Bidder), we_________, (Name and
Address of the bank), hereinafter referred to as the “Bank”), do hereby unconditionally and
irrevocably affirm and undertake that we are the Guarantor and are responsible to the
Executive Engineer, P.W. Division, Satara i.e. the beneficiary on behalf of the
Bidder, up to a total sum of Rs. 137500/- (Rupees One Lakh Thirty Seven Thousand Five
Hundred only), such sum being payable by us to the Executive Engineer, P.W. Division, Satara.
immediately upon receipt of first written demand from Executive Engineer, P.W.Division, Satara.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 49 of 195
2.
3.
4.
5.
6.
7.
8.
We unconditionally and irrevocably undertake to pay to the Executive Engineer, P.W.
Division, Satara on an immediate basis, upon receipt of first written demand
from the Executive Engineer, P.W. Division, Satara and without any cavil or
argument or delaying tactics or reference by us to Bidder and without any need for the
Executive Engineer, P.W. Division, Satara prove the failure on the part of the Bidder to repay the
amount of ------------- or to show grounds or reasons for the demand or the sum specified
therein, the entire sum or sums within the limits of Rs. _______________ only).
We hereby waive the necessity of the Executive Engineer, P.W. Division, Satara demanding the said
amount from Bidder prior to serving the Demand Notice upon us.
We further agree and affirm that no change or addition to or other modification to the terms
of the Agreement, shall in any way release us from any liability under this unconditional and
irrevocable Guarantee and we hereby waive notice of any such change, addition or
modification. We further agree with the Executive Engineer, P.W. Division,
Satara that the Executive Engineer, P.W. Division, Satara shall be the
sole and the exclusive judge to determine that whether or not any sum or sums are due
and payable to him by Entrepreneur, which are recoverable by the Executive Engineer,
P.W. Division, Satara by invocation of this Guarantee.
This Guarantee will not be discharged due to the change in constitution of the Bank or the
Bidder. We undertake not to withdraw or revoke this Guarantee during its currency/
validity period, except with the previous written consent of the Executive Engineer, P.W.
Division, Satara.
We unconditionally and irrevocably undertake to pay to the Executive Engineer, P.W.
Division, Satara any amount so demanded not exceeding Rs.
_______________________ (Rupees ________________ only), notwithstanding any dispute
or disputes raised by Bidder or anyone else in any suit or proceedings before any dispute
review expert, arbitrator, court, tribunal or other authority, our liability under this Guarantee
being absolute, unconditional and unequivocal. The payment so made by us under this
Guarantee to the Executive Engineer, P.W. Division, Satara shall be a valid
discharge of our liability for payment under this Guarantee and the Bidder shall have no claim
against us for making such payment.
This Bank guarantee shall be payable at city of the Public Works Division, Satara at
Satara branch of the bank ____________________ This unconditional and irrevocable Guarantee shall remain in full force and effect and shall
remain valid until (180 days from the Proposal Due Date).
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 50 of 195
Notwithstanding anything contained herein :
1. Our liability under this Bank Guarantee shall not exceed Indian Rs.
__________________ (Rupees ____________________ only).
2. This unconditional and irrevocable Bank Guarantee shall be valid w.e.f.
_________________ (Date of Submission of Bid) to _____________________.
We are liable to pay the guaranteed amount or any part thereof under this
unconditional and irrevocable Bank Guarantee only and only if Executive Engineer, P.W.
Division, Satara serves upon us a written claim or demand on or before ________.
Authorized Signatory For Bank
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Party % Shareholding
Page 51 of 195
G.
POWER OF ATTORNEY BY EACH MEMBER OF THE JV IN FAVOUR OF LEAD
MEMBER
POWER OF ATTORNEY
TO WHOMSOEVER IT MAY CONCERN
(To be notarized)
WHEREAS, we have decided to participate in the bidding process for the “Design, Build,
Finance, Construction, Development, Implementation, Operation and Maintenance of
the Jan Suvidha Kendra, at __________, Maharashtra” (the “Project”) as member of
_________________[name of the JV] independently, we, __________________name of
authorising company/agency], a ______________ incorporated under the laws of
______________, the registered address of which is ___________________________, to
lawfully represent and act on our behalf as the Lead Member of the JV to sign any qualification
statement, proposal, conduct negotiations, sign contracts, incur liabilities and receive
instructions for us and on our behalf and execute all other necessary matters in connection with
the Project. We hereby confirm that we are jointly and severally liable, together with other
members of the JV, to the Engineer – in – charge for all of the obligations of the JV in respect of
our qualification statement, technical and financial proposal for the Project, in accordance with
the RFP
hereof.
for the Project issued on ______________________ and as amended prior to date
We
hereby
ratify
and
confirm
that
all
acts
done
by
our
said
attorney
___________________________ (name of the Lead Member) shall be binding on us as if the
same has been done by us personally. We hereby also ratify and confirm that if we are selected
as the Successful Bidder, we shall incorporate a Company under The Companies Act, 1956 as per
the following shareholding pattern:
IN WITNESS WHEREOF, we have hereunto set our respective hands this ________ day of
___________________ 201___ in the presence of the following witnesses
_________________________________________
Name, Signature of the Authorized Signatory
Witness 1
Witness 2
Signature
Name
Address
-------------
--------------
--------------
Signature
Name
Address
-----------
------------
---------
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 52 of 195
H.
FORMAT OF PARENT / HOLDING COMPANY DEED OF GUARANTEE
FORMAT OF PARENT / HOLDING COMPANY DEED OF GUARANTEE (TO BE MADE ON
STAMP PAPER OF REQUISITE VALUE AND NOTORISED AND SHALL BE ADDRESSED
TO AUTHORITY)
DEED OF GUARANTEE
THIS DEED OF GUARANTEE executed at ___________ this _____________ day of____________
by M/s ____________________ (mention complete name) a company duly organized and
existing under the laws of (insert jurisdiction / country), having its Registered Office at
_______________ hereinafter called the “Guarantor” which expression shall, unless excluded by
or repugnant to the subject or context thereof, be deemed to include its successors and permitted
assigns.
WHEREAS
A.
B.
C.
D.
Executive Engineer, P.W. Division, Satara The “Engineer – in – charge”
which expression shall unless excluded by or repugnant to the context thereof, be deemed
to include its successor and assigns), invited Bids / proposals for the Project titled “Design,
Build, Finance, Construction, Development, Implementation, Operation and
Maintenance of the Jan Suvidha Kendra, at Rest House Khandala ,Maharashtra.” by issuing
Request For Proposal (“RFP”) bearing No. _____________________ (including its
addendums) to the prospective “Bidders” to implement the said Project for and on behalf
of the Engineer – in – charge.
M/s_____________ (mention compete name), a company duly organized and existing
under the laws of India (insert jurisdiction / country), having its Registered Office at
(give complete address) hereinafter called the “Subsidiary”, which expression shall, unless
excluded by or repugnant to the subject or context thereof, be deeded to include its
successor and permitted assigns, ( is a Subsidiary of the Guarantor, which has in response
to the above mentioned RFP document (including its addendums) is submitting its Bid /
Proposal to Executive Engineer, P.W. Division, Satara to fulfill the condition
that the Subsidiary shall arrange a guarantee from its Parent / Holding company,
guaranteeing due and satisfactory performance of the work covered under the said RFP
document (including its addendums) or any change made in may be deemed appropriate
by the Executive Engineer, P.W. Division, Satara at any stage.
The Guarantor represents that they have gone through and understood the requirement of
the above said RFP document (including its addendums) and are capable of and committed
to provide technical, financial and such other supports as may be required by the
Subsidiary for the successful execution of the same.
The Guarantor is executing this Deed of Guarantee in favour of Executive Engineer, P.W.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 53 of 195
Division, Satara wherein the Guarantor and the Subsidiary shall be jointly
and severally liable towards the Project and the Guarantor shall also be pledging /
providing technical, financial and such other supports as may be necessary to the
Subsidiary for performance of the work relating to the said Project as per the RFP
document (including its addendums) and as per the Agreement contained in the RFP
document.
E.
Accordingly, at the request of the Subsidiary and in consideration of and as a
requirement for Executive Engineer, P.W. Division, Satara to enter into
agreement(s) with the Subsidiary, the Guarantor hereby agrees to give this guarantee
and undertakes as follows:
1.
2.
3.
4.
The Guarantor (Parent / Holding Company) unconditionally agrees that in case of
non-performance by the Subsidiary of any of its obligations in any respect, the
Guarantor shall, immediately on receipt of notice of demand by Executive
Engineer, P.W. Division, Satara, take up the Project without any
demur or objection, in continuation and without loss of time and without any cost
to Executive Engineer, P.W. Division, Satara and duly perform
the obligations and responsibilities of the Subsidiary to the satisfaction of Executive
Engineer, P.W. Division, Satara, In case the Guarantor also fails
to discharge its obligations herein and is not able to complete the Project
satisfactorily, Executive Engineer, P.W. Division, Satara, shall
have absolute rights for effecting the execution of the Project from any other
person at the risks and costs of the Guarantor. The Guarantor also undertakes to
make good any loss that may be caused to Executive Engineer, P.W.
Division, Satara ,for any non-performance or unsatisfactory
performance by the Guarantor or the Subsidiary of any of their obligations.
The Guarantor agrees that the Guarantee herein contained shall remain valid and
enforceable till the satisfactory execution and completion of the Project (including
discharge of the warranty obligations) awarded to the Subsidiary till the completion
of the Concession Period (including any extension).
The Guarantor shall be jointly with the Subsidiary, as also severally responsible for
the satisfactory execution and performance of Project during the currency of the
“Agreement” to be entered amongst the Subsidiary and Executive Engineer, P.W.
Division, Satara.
The Guarantor represents that this Guarantee has been issued after due
observance of the appropriate laws in force in India. The Guarantor hereby
undertakes that the Guarantor shall obtain and maintain in full force and effect
all the governmental and other approvals, permits and consents that are necessary
and do all other acts and things necessary or desirable in connection therewith or
for the due performance of the Guarantor’s obligations hereunder
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 54 of 195
5.
6.
7.
8.
The Guarantor also agrees that this Guarantee shall be governed and construed
in accordance with the laws in force in India and subject to the exclusive jurisdiction
of the courts of only Pune, Maharashtra, India.
The Guarantor hereby declares and represents that this Guarantee has been
given without any undue influence or coercion from any person and that the
Guarantor has fully understood the implications of the same.
The Guarantor represents and confirms that the Guarantor has the legal capacity,
power and authority to issue this Guarantee and that giving of this Guarantee and
the performance and observations of the obligations hereunder do not contravene
any existing law or any judgment.
The Guarantor represents and confirms that in pursuance to Para / Point 7, the
Guarantor has submitted and provided to Executive Engineer, P.W. Division, Satara (with this
Deed of Guarantee), a valid Board Resolution duly
authorizing the Guarantor to pledge / provide technical, financial and such other
supports as may be necessary for performance of the work relating to the said
Project as per the RFP and Agreement
For and on behalf of (Parent / Holding Company)
M/s
Witness:
1.
2.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 55 of 195
I.
FORMAT OF SELECTED BIDDER GUARANTEE TOWARDS SPC
Format of Successful Bidder Guarantee towards SPC (if applicable and after
LOA) (To Be Made On Stamp Paper of requisite value and notarised)
DEED OF GUARANTEE
THIS DEED OF GUARANTEE executed at _________ this _______ day of _____________ by
___________________________________________ (mention complete name) a company duly
organized and existing under the laws of ________________________ (insert jurisdiction /
country), having its Registered Office at _____________________ hereinafter called the
“Guarantor” or the “Successful Bidder”, which expression shall, unless excluded by or
repugnant to the subject or context thereof, be deemed to include its successors and permitted
assigns.
WHEREAS
A.
Executive Engineer, P.W. Division, Satara or “Engineer –in- charge ”, which
expression shall unless excluded by or repugnant to the context thereof, be deemed to
include its successor and assigns), invited Bids / Proposals for the “Project” –
“Construction
ladies toilets
of Jan Suvidha Kendra and construction of toilets in general and
with drinking water and other public amenities along state
highways.” by issuing Request For Proposal (“RFP”) document (including its addendums)
to the prospective “Bidders” to implement the said Project.
B.
C.
M/s _______________________(mention compete name), a company duly organized and
existing under the laws of India (insert jurisdiction / country), having its Registered Office
at _____________________ (give complete address) hereinafter called the special
purpose company, the “SPC”, which expression shall, unless excluded by or repugnant to
the subject or context thereof, be deemed to include its successor and permitted assigns,
(is an Associate of the Guarantor, and has been formed for the development of the Project
with one of the condition that the SPC shall arrange a guarantee from its Parent / Holding
Company, i.e. Guarantor, guaranteeing due and satisfactory performance of the work
covered under the said RFP document (including its addendums) or any change made in
may be deemed appropriate by the Executive Engineer, P.W. East Division at any stage.
The Bid / Proposal submitted by the Guarantor was accepted by Executive Engineer,
P.W. East Division, and this Guarantor was declared the selected Bidder. Accordingly,
the Guarantor is executing this Deed of Guarantee towards / in favour of its SPC after
the issuance of Letter of Award (LOA) dated ______________ by Executive Engineer,
P.W. Division, Satara to the Guarantor / Successful Bidder.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 56 of 195
D.
E.
F.
The Guarantor represents that it has gone through and understood the requirement of
the above said RFP document (including its addendums) and are capable of and
committed to provide technical, financial and such other supports as may be required by
the SPC for the successful execution of the same.
The Guarantor is executing this Deed of Guarantee in favour of Executive Engineer,
P.W. East Division, wherein the Guarantor and the Associate shall be jointly and severally
liable towards the Project and the Guarantor shall also be pledging / providing technical,
financial and such other supports as may be necessary to the Associate for
performance of the work relating to the said Project as per the RFP document (including
its addendums) and as per the Agreement contained in the RFP document.
Accordingly, at the request of the Associate and in consideration of and as a requirement
for Executive Engineer, P.W. East Division to enter into agreement(s) with the SPC, the
Guarantor hereby agrees to give this guarantee and undertakes as follows:
1.
2.
3.
4.
The Guarantor (Parent / Holding Company) unconditionally agrees that in case of
non-performance by the SPC of any of its obligations in any respect, the Guarantor
shall, immediately on receipt of notice of demand by Executive Engineer, P.W.
East Division, take up the Project without any demur or objection, in continuation
and without loss of time and without any cost to Executive Engineer, P.W. East
Division and duly perform the obligations and responsibilities of the SPC to the
satisfaction of Executive Engineer, P.W. East Division. In case the Guarantor also
fails to discharge its obligations herein and is not able to complete the Project
satisfactorily, Executive Engineer, P.W. East Division shall have absolute rights for
effecting the execution of the Project from any other person at the risks and costs
of the Guarantor. The Guarantor also undertakes to make good any loss that may
be caused to Executive Engineer, P.W. East Division for any non-performance or
unsatisfactory performance by the Guarantor or the SPC of any of their obligations.
The Guarantor agrees that the Guarantee herein contained shall remain valid and
enforceable till the satisfactory execution and completion of the Project (including
discharge of the warranty obligations) awarded to the SPC till the completion of the
Concession Period (including any extension).
The Guarantor shall be jointly with the SPC, as also severally responsible for the
satisfactory execution and performance of Project during the currency of the
“Agreement” to be entered amongst the SPC, Executive Engineer, P.W.Division, Satara.
The Guarantor represents that this Guarantee has been issued after due
observance of the appropriate laws in force in India. The Guarantor hereby
undertakes that the Guarantor shall obtain and maintain in full force and effect
all the governmental and other approvals, permits and consents that are
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 57 of 195
necessary and do all other acts and things necessary or desirable in connection
therewith or for the due performance of the Guarantor’s obligations hereunder.
5.
6.
7.
8.
9.
The Guarantor also agrees that this Guarantee shall be governed and construed in
accordance with the laws in force in India and subject to the paragraph 6 below
(Dispute Resolution), the courts of Satara, Maharashtra, India shall
have exclusive jurisdiction.
The provisions of the Dispute Resolution clause set out in the Concession
Agreement shall be deemed to have been incorporated herein and shall mutatis
mutandis apply this Guarantee.
The Guarantor hereby declares and represents that this Guarantee has been
given without any undue influence or coercion from any person and that the
Guarantor has fully understood the implications of the same.
The Guarantor represents and confirms that the Guarantor has the legal capacity,
power and authority to issue this Guarantee and that giving of this Guarantee and
the performance and observations of the obligations hereunder do not contravene
any existing law or any judgment.
The Guarantor represents and confirms that in pursuance to Para / Point 7, the
Guarantor has submitted and provided to Executive Engineer, P.W. East Division.
(with this Deed of Guarantee), a valid Board Resolution duly authorizing the
Guarantor to pledge / provide technical, financial and such other supports as may
be necessary for performance of the work relating to the said Project as per the
RFP and Agreement
For and on behalf of (Parent / Holding Company
Witness
1.
2.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 58 of 195
J.
DRAFT JOINT VENTURE AGREEMENT
(To Be Made On Stamp Paper of requisite value and notarized)
This Joint Venture Agreement (the “AGREEMENT”) made at
on this day of
, 201__
BY AND AMONGST
M/s {Lead Member (JV Member 1)}, a _____________________ incorporated under
(name of the relevant act/law of under which registered in the country of registration) and having
its registered office / a company incorporated under the Laws of __________________
(hereinafter referred to as “ ”, which expression shall unless repugnant to the context or
meaning thereof be deemed to mean and include its successors in interest, subsidiaries and
assigns) of the ONE PART;
AND
M/s (JV Member 2), a incorporated under the ________________ and having its registered office /
a company incorporated under the Laws of ________________________-(hereinafter referred to
as “ ”, which expression shall unless repugnant to the context or meaning thereof be
deemed to mean and include its successors in interest, subsidiaries and assigns) of the SECOND
PART;
AND
M/s (member 3), a company incorporated under the ____________________ and having its
registered office / a company incorporated under the Laws of ______________- (hereinafter
referred to as “ ”, which expression shall unless repugnant to the context or meaning
thereof be deemed to mean and include its successors in interest, subsidiaries and assigns) of the
THIRD PART ( ____________________-, and shall be individually referred to as the “Party” and
jointly referred to as the “Parties” or “JV Members”).
WHEREAS:
1.
2.
Executive Engineer, P.W. Division, Satara and invited Bids/
Proposals from registered Partnership Firms, Company and Joint Venture for the work of
“Design, Build, Finance, Construction, Development, Implementation,
Operation and Maintenance of the Jan Suvidha Kendra, at Rest House Khandala,
Maharashtra.” (hereinafter referred to as the “Project”).
M/s. ______________________,M/s. ______________ and M/s. ______________have
agreed to consolidate their resources and experience, and apply jointly as a Joint Venture
(hereinafter referred to as the “Joint Venture”), vide this Joint Venture Agreement, for
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 59 of 195
the purpose of developing and completing the Project, within time frame stipulated in the
Request for Proposal Document (hereinafter referred to as the “RFP”).
3.
M/s ___________________, M/s _________________ and M/s ________________ have
therefore agreed to enter into this Joint Venture Agreement in respect of the
submission of the Bid/Proposal for the Project on the terms set out below.
NOW THEREFORE IN CONSIDERATION OF THE PREMISES AND THE MUTUAL
CONVENANTS HEREIN CONTAINED THE PARTIES HEREBY AGREE AS FOLLOWS:
1.
2.
The recital herein contained shall constitute and integral and operative part of this
AGREEMENT.
The Parties hereto agree to consolidate their resources and hereby form a Joint Venture
to jointly prepare, submit and Bid for the Project, which has financing and commercial
benefits, as detailed in the RFP document issued by Executive Engineer, P.W.
Division, Satara for the implementation/execution/ maintenance and
operation and completion of the Project.
3.
The Parties hereto agree that
shall be the Lead Member and
and
shall be the JV Members 2 & 3 respectively of the Joint Venture.
4.
5.
6.
The Parties shall mutually and jointly take all the decisions in respect of the Project on
behalf of the Joint Venture. (Lead Member) shall be authorized to act on behalf of the
Joint Venture as their representative for up gradation, implementation/execution and
completion of the Project.
undertakes that it has the necessary qualification to fulfill technical and
financial capability criteria for the up gradation, implementation/execution and completion of
the Project as detailed in the RFP Document {including the draft Agreement (Section-II of
the RFP document)}.
For the purpose of execution of the Project, in the event of award of the Project to the Joint
Venture, the Parties will set up a Special Purpose Company (“SPC”), formed under the
Companies Act, 1956. The common equity shareholding pattern of the SPC shall consist of
% shares to be held by , % shares to be held by , and % shares to
be held by . (Lead Member) shall individually and compulsorily hold such minimum
equity stake, as per the requirements of the RFP, in the SPC till the end of the Concession
Period. On successful award of the Project, the SPC shall enter into “Agreement”) with
Executive Engineer, P.W. Division, Satara (as per the RFP Document), which
shall specify the terms and conditions of the development and completion of the Project and
shall carry out all the responsibilities in the terms of the RFP. The registered office of the
Joint Venture/SPC shall be located at ____________
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Name Type of Role & Responsibility
of
Member
MemberJV Member 1
(Lead Member)
JV Member 2
JV Member 3
Page 60 of 195
7.
,
and
shall be jointly and severally liable for the Development/
Construction, implementation, operation and maintenance of the Project in accordance with
the terms of the RFP Document. It is further unanimously agreed by the Parties that the
Lead Member, along with other JV Members in the SPC shall:-
A.
B.
C.
D.
Coordinate the day to day activities of the Joint Venture/SPC;
Undertake to be jointly and severally liable/responsible for all the obligations and
liabilities relating to the Project, in accordance with the terms of the RFP Document
and the Agreement with Executive Engineer, P.W. Division, Satara.
till the end of the Concession Period;
complete all works assigned under the RFP Document (including Agreement) within
the time period stipulated in the RFP document; and
execute individual/independent Deed of Guarantee by all JV Members, towards the
SPC, in favour of Executive Engineer, P.W. Division, Satara for the
pledging / providing technical, financial and such other supports as may be necessary
for the performance of works assigned under the RFP Document (including draft
Agreement) within the time period stipulated in the RFP document.
8.
9.
10.
11.
The role and the responsibility of each Party for the Construction/ implementation, operation
& maintenance and execution of the Project shall be as follows: All the basic/fundamental terms and conditions of this AGREEMENT shall be incorporated in
the Article of Association of the SPC (to be incorporated by the Parties). Any other terms and
conditions to the extent not agreed upon by the Parties in this AGREEMENT (and which are
not contradictory to the basic/fundamental provisions of this AGREEMENT) shall be mutually
agreed upon by the Parties and incorporated in the Article of Association of the SPC
Confidentiality – All information, document, etc. exchanged between the Parties related to
this agreement or the preparation of any bid or the performance of the Project shall remain
confidential and shall not be revealed to third parties for a certain time period to be agreed
upon. Unless otherwise required by law, the Parties undertake not to disclose to any third
party or any else and / or use any Information, without prior consent of the other Party.
Term and Duration – This AGREEMENT shall come into effect on the date of submission
of the Bid/Proposal for the up gradation, implementation/execution and completion of the
Project. This AGREEMENT shall terminate upon the successful completion of the Project and
may be extended further for such period as may be required by the Executive Engineer,
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 61 of 195
P.W. Division, Satara This AGREEMENT can be terminated only upon Joint
Venture’s/SPC’s Bid for the Project is conclusively rejected by the Executive Engineer, P.W.
Division, Satara.
12.
13.
14.
15.
16.
17.
18.
19.
Costs/Expenses – All out-of-pocket expenses/costs of and incidental to this AGREEMENT
including stamp duty and registration fees, if any shall be borne and paid by the Parties in
proportion to their shareholding in the SPC. Each Party shall pay and bear their own
advocated/solicitors fees in the preparation of this AGREEMENT.
Governing Law – This AGREEMENT shall in all respect be governed, construed and
interpreted in accordance with laws of Republic of India.
Settlement of Disputes – Any disputes arising out of this AGREEMENT shall be amicably
settled by the authorized representatives of the Parties, failing with any such disputes shall
be resolved by Arbitration in accordance with the Arbitration and Conciliation Act, 1996,
by one or more arbitrators appointed in accordance with the said Act. This Clause shall
survive the termination of this AGREEMENT.
Language of Arbitration shall be English. The seat of the Arbitration proceedings shall be in
______________, India. The Parties jointly and severally undertake that the up gradation,
implementation/execution and completion of the Project shall not be affected during the
dispute(s) or the settlement of dispute(s) period. The Award rendered by the Arbitral
Tribunal shall be final and binding upon the Parties.
In the event of a dispute between the Parties over the subject of this AGREEMENT,
the prevailing party shall be entitled to reasonable advocates/solicitors’ fees and costs
incurred in the resolution of such dispute.
Amendments – This AGREEMENT can be amended or suppressed by further agreement
made in writing at the request of any of the Parties after unanimous approval by the
Parties and by obtaining prior consent and written approval from Executive Engineer, P.W.
Division, Satara.
Notices – Any notices, requests, demands or any communications from any party to the
other party under this Agreement shall be by Regd./Speed mail or facsimile transmission
sent to the addresses as indicated in this Agreement. Any party may change its address but
shall promptly inform Executive Engineer, P.W. Division, Satara and the
other Parties/JV Members of any such change.
Language – The official language of this AGREEMENT and all future agreements shall
be English
Assignment – None of the Parties to this AGREEMENT shall have the right to assign its
benefits or liabilities under this AGREEMENT to any other company, firm or person without
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 62 of 195
obtaining prior consent and written approval of Executive Engineer, P.W. Division, Satara.
20.
Entire Agreement – This Agreement constitutes the entire agreement between the Parties
and supersedes all prior writings, agreements or understandings relating to the subject
matter thereof.
IN WITNESS WHEREOF the Parties hereto have caused this AGREEMENT to be executed
by their duly authorized representatives the day and year first above written.
SIGNED AND DELIVERED BY
By ________
Title ________
Date _________
Witness
1.
2.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 63 of 195
K.
FORMAT OF DEED OF GUARANTEE (IN CASE OF JV) TOWARDS SPC (IF
APPLICABLE & AFTER LOA)
(To Be Made On Stamp Paper of requisite value and notarised)
DEED OF GUARANTEE
THIS DEED OF GUARANTEE executed at _____________ this _____________ day of 20____ by
______________________ (mention complete name) a company duly organized and existing
under the laws of (insert jurisdiction / country), having its Registered Office at
______________________________ hereinafter called the “Guarantor” or the “Joint Venture
(JV) Member- (1/2/3)”, which expression shall, unless excluded by or repugnant to the subject
or context thereof, be deemed to include its successors and permitted assigns.
WHEREAS
A. Executive Engineer, P.W. Division, Satara. which expression shall unless excluded by
or repugnant to the context thereof, be deemed to include its successor and assigns),
invited Bids / Proposals for the Project titled “Design, Build, Finance, Construction,
Development, Implementation, Operation and Maintenance of the Jan Suvidha
Kendra, at Rest House Khandala , Maharashtra” by issuing Request For Proposal (“RFP”)
document (including its addendums) to the prospective “Bidders” to implement the said
Project for and on behalf of the Authority.
B. M/s (mention compete name), a company duly organized and existing under the laws
of India (insert jurisdiction / country), having its Registered Office at (give
complete address) hereinafter called the Special Purpose Company “the SPC”, which
expression shall, unless excluded by or repugnant to the subject or context thereof, be
deemed to include its successor and permitted assigns, ( is an Affiliate of the Guarantor,
and has been formed for the development of the Project with one of the condition that
the SPC shall arrange guarantees from its Joint Venture (JV) Members, i.e. Guarantors,
guaranteeing due and satisfactory performance of the work covered under the said RFP
document (including its addendums) or any change made in may be deemed appropriate
by the Executive Engineer, P.W. Division, Satara at any stage.
C. The Bid / Proposal submitted by the Joint Venture (JV) Members i.e. (i) , (ii)
and (iii) [Guarantors] was accepted by Executive Engineer, P.W. Division, Satara on behalf
of Executive Engineer, P.W. Division, Satara.
and the Guarantors were declared the “Successful Bidder”. Accordingly, this Guarantor
i.e. Joint Venture (JV) Member- (1/2/3) is executing this individual Deed of Guarantee
towards / in favour of this SPC after the issuance of Letter of Award (LOA) dated by
Executive Engineer, P.W. Division, Satara to the Successful Bidder.
D. The Guarantor represents that it has gone through and understood the requirement of the
above said RFP document (including its addendums) and are capable of and committed to
provide technical, financial and such other supports as may be required by the SPC for the
successful execution of the same.
E. The Guarantor is executing this Deed of Guarantee in favour of Executive Engineer,
P.W. Division, Satara wherein the Guarantor (along with other Joint
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 64 of 195
Venture (JV) Members) and the Affiliate (SPC) shall be jointly and severally liable towards
the Project and the Guarantor shall also be pledging / providing technical, financial and
such other supports as may be necessary to the Affiliate (SPC) for performance of the
work relating to the said Project as per the RFP document (including its addendums) and
as per the Agreement contained in the RFP document.
F. Accordingly, at the request of the Affiliate and in consideration of and as a
requirement for Executive Engineer, P.W. Division, Satara to enter into
agreement(s) with the SPC, the Guarantor hereby agrees to give this Guarantee and
undertakes as follows:
1. The Guarantor (JV Member-1/2) unconditionally agrees that in case of non-
performance by the SPC of any of its obligations in any respect, the Guarantor shall,
immediately on receipt of notice of demand by Executive Engineer, P.W. Division, Satara take
up the Project without any demur or objection, in
continuation and without loss of time and without any cost to Executive
Engineer, P.W. Division, Satara and duly perform the obligations and
responsibilities of the SPC to the satisfaction of Executive Engineer, P.W. Division, Satara In case
the Guarantor also fails to discharge its obligations herein
and is not able to complete the Project satisfactorily, Executive Engineer, P.W. Division Satara ,
shall have absolute rights for effecting the execution of the Project
from any other person at the risks and costs of the Guarantor. The Guarantor also
undertakes to make good any loss that may be caused to Executive Engineer, P.W.
Division, Satara for any non-performance or unsatisfactory performance by
the Guarantor or the SPC of any of their obligations.
2. The Guarantor agrees that the Guarantee herein contained shall remain valid and
enforceable till the satisfactory execution and completion of the Project (including
discharge of the warranty obligations) awarded to the SPC till the completion of the
Concession Period (including any extension).
3. The Guarantor shall be jointly with the SPC, as also severally responsible for the
satisfactory execution and performance of Project during the currency of the
“Agreement” to be entered amongst the SPC, Executive Engineer, P.W. Division, Satara.
4. The Guarantor represents that this Guarantee has been issued after due observance of
the appropriate laws in force in India. The Guarantor hereby undertakes that the
Guarantor shall obtain and maintain in full force and effect all the governmental
and other approvals, permits and consents that are necessary and do all other acts
and things necessary or desirable in connection therewith or for the due performance
of the Guarantor’s obligations hereunder.
5. The Guarantor also agrees that this Guarantee shall be governed and construed in
accordance with the laws in force in India and subject to the paragraph 6 below
(Dispute Resolution), the courts of Satara Maharashtra, India shall
have exclusive jurisdiction.
6. The provisions of the Dispute Resolution clause set out in the Concession Agreement
shall be deemed to have been incorporated herein and shall mutatis mutandis apply
this Guarantee.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 65 of 195
7. The Guarantor hereby declares and represents that this Guarantee has been given
without any undue influence or coercion from any person and that the Guarantor has
fully understood the implications of the same.
8. The Guarantor represents and confirms that the Guarantor has the legal capacity,
power and authority to issue this Guarantee and that giving of this Guarantee and the
performance and observations of the obligations hereunder do not contravene any
existing law or any judgment.
9. The Guarantor represents and confirms that in pursuance to Para / Point 7, the
Guarantor has submitted and provided to (Executive Engineer, P.W. Division,
Satara (with this Deed of Guarantee), a valid Board Resolution duly authorizing the
Guarantor to pledge / provide technical, financial and such other supports as may be
necessary for performance of the work relating to the said Project as per the RFP and
Agreement
FOR & ON BEHALF OF
_________________________
Witness:
1.
2.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 66 of 195
L.
POWER OF ATTORNEY BY THE LEAD MEMBER OF THE JV IN FAVOUR OF ITS
DULY AUTHORIZED REPRESENTATIVE
POWER OF ATTORNEY
TO WHOMSOEVER IT MAY CONCERN
(Notarized)
WHEREAS, the ----------[name of the JV] has decided to participate in the bidding process
for the “Design, Build, Finance, Construction, Development, Implementation,
Operation and Maintenance of the Jan Suvidha Kendra, at Rest
House Khandalala_,
Maharashtra” (the “Project”) with us as the Lead Member, we hereby authorize, (i) ---- ------
-----[Name], an Indian inhabitant, with PAN No. ____________________and residing at
___________________ (ii) (if required), , to lawfully represent and act on our behalf as our
authorized representative to sign any qualification statement, proposal, conduct negotiations,
sign contracts, incur liabilities and receive instructions for us and on our behalf and execute
all other necessary acts, deeds, matters and things in connection with the Project.
We hereby ratify and confirm that all acts done by our said attorney(s) ------ (name(s)) shall be
binding on us as if the same has been done by us personally.
IN WITNESS WHEREOF, we have hereunto set our respective hands this ---------day of --------
201___ in the presence of the following witnesses
_________________________________________
Name , Signature of Authorized Signatory
Witness 1
Witness 2
Signature
Name
Address
-------------
--------------
--------------
Signature
Name
Address
-----------
------------
---------
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 67 of 195
M.
FORMAT OF LETTER OF AWARD
(to be issued on letterhead of the Executive Engineer, Public Works
Division, Satara in duplicate as per the RFP)
No. [___________________]
OFFICE OF EXECUTIVE ENGINEER,
PUBLIC WORKS, SATARA DIVISION
Dated: [___________________, 20___]
To,
[Name of Authorized Signatory of the selected Bidder]
[Designation of Authorized Signatory of the selected Bidder]
[Name of selected Bidder]
[Registered Address of the selected Bidder]
Re:
(1) (2)
The Request for Proposal (“RFP”) dated ___________________________ bearing
RFP No. ________________________ issued by the Executive Engineer, Public
Works Division, Satara. the Government of Maharashtra for the
“Design, Build, Finance, Construction, Development, Implementation,
Operation and Maintenance of the Jan Suvidha Kendra, at Rest House Khandala,
Maharashtra” (“Project”);
The Bid submitted by you on ____________________________ in response to the
RFP.
Sub:
The Letter of Award.
Dear Sir,
We refer to the Bid submitted by you on _____________________ in response to the RFP.
Based on the Bid submitted by you, we hereby convey our decision to declare you, [Name of Entity]
as the ‘Selected Bidder’ as per the terms and conditions of the RFP.
This declaration and award are subject to the fulfilment of the following terms and conditions by
you within the prescribed time as follows:
(a)
You shall, within 7 (seven) days of the receipt of this Letter of Award, sign and return the
duplicate copy of the Letter of Award in acknowledgement thereof.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
_________________________________________________________
Page 68 of 195
(b)
(c)
(d)
(e)
(f)
You shall incorporate a company a project company (“SPC”) as a special purpose vehicle,
for carrying out the Project prior to the execution of the Concession Agreement
(“Agreement”) on or before _______________________________.
You shall have submitted the Selected Bidder Guarantee towards SPC in the form and
format set out in the RFP on or before _______________________________, in
accordance with the requirements of the RFP.
You shall submit or shall have procured that the SPC submits the Performance Security on
or before _______________________________, in accordance with the requirements of
the RFP prior to execution of the Concession Agreement.
You shall have procured that the SPC duly sign and execute (i) the Concession Agreement;
(ii) the Land Licence Agreement, as per the requirement of the RFP on or before
_______________________________. For the said purpose, the authorised signatory of
the SPC shall be present on the execution date at the Office of the Executive Engineer,
Public Works Division , Satara with: (i) photo identity issued by any
Government authority confirming identity of such person along with a self – attested
photocopy; (ii) original certified true copy of a resolution passed by the board of directors of
the SPC authorising the Authorised Representative to execute the said agreements and do
all such acts as may be necessary or incidental thereto.
You shall fulfil and take all necessary actions to fulfil each of the Conditions Precedent
within the period prescribed therefor in the Concession Agreement.
The Office of the Executive Engineer, Public Works Division , Satara reserves the
right to extend the time, at its sole discretion, for compliance of any of the aforesaid conditions.
In the event, the selected Bidder fails to comply with or breaches any of the aforesaid conditions or
any other provisions of the RFP, the Office of the Executive Engineer, Public Works Division, Satara may, unless it
consents to extension of time for submission thereof, may appropriate and encash the Bid Security and/or terminate
this Letter of Award. Capitalised words and phrases used herein but not defined shall bear the same meaning as ascribed to the same under
the RFP and the Concession Agreement attached thereto.
________________
OFFICE OF THE EXECUTIVE ENGINEER,
PUBLIC WORKS DIVISION SATARA.
REQUEST FOR PROPOSAL FOR THE CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House
Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 69 of 195
SECTION – II
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 70 of 195
DRAFT CONCESSION AGREEMENT
FOR THE
DESIGN, BUILD, FINANCE, CONSTRUCTION, DEVELOPMENT,
IMPLEMENTATION, OPERATION AND MAINTENANCE OF THE
JAN SUVIDHA KENDRA, AT Rest House Khandala on Khandala Koregaon Rahimatpur
Karad Sangli Shirol S.H.142 Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
[Details of the Project]
Executive Engineer. Public Works Division, Satara
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 71 of 195
TABLE OF CONTENTS
DEFINITIONS AND INTERPRETATION.................................................................................... 77
Definitions............................................................................................................................................ 77
Relation between the Parties ............................................................................................................. 84
Measurements and Arithmetic Conventions ...................................................................................... 86
Ambiguities within Agreement ........................................................................................................... 86
Priority of Documents ......................................................................................................................... 86
SCOPE OF THE PROJECT ........................................................................................................... 88
CONCESSION ............................................................................................................................. 90
Grant of Concession............................................................................................................................. 90
Actions in Support of the Concession ............................................................................................... 92
Concession Period .............................................................................................................................. 93
Implementation Period ...................................................................................................................... 93
CONDITIONS PRECEDENT ....................................................................................................... 97
Obligations for satisfaction of Conditions Precedent for the Concessionaire.................................... 97
General Obligations to satisfy Condition Precedents ........................................................................ 98
Non – satisfaction of Conditions Precedent....................................................................................... 99
COMMERCIAL CONSIDERATION........................................................................................... 101
Commercial Charges ......................................................................................................................... 101
Performance Security ....................................................................................................................... 101
OBLIGATIONS OF THE AUTHORITY DURING THE IMPLEMENTATION PERIOD............... 102
General Obligations of the Authority during the Implementation Period ...................................... 102
OBLIGATIONS OF THE CONCESSIONAIRE DURING THE IMPLEMENTATION PERIOD.... 103
Obligations of the Concessionaire during the Implementation Period ........................................... 103
Minimum Equity Requirements ........................................................................................................ 106
GENERAL OBLIGATIONS IN RELATION TO THE PROJECT AGREEMENTS ......................... 107
FORMATION AND MEETINGS OF THE COMMITTEE ............................................................. 109
COMPLETION OF IMPLEMENTATION .................................................................................... 111
OPERATIONS AND MAINTENANCE PERIOD ......................................................................... 114
AGREEMENT COMPLETION CERTIFICATE............................................................................. 120
REPRESENTATIONS AND WARRANTIES ............................................................................... 121
VARIATIONS AND CHANGE OF SCOPE .................................................................................. 124
TERMINATION FOR EVENTS OF DEFAULT AND SUSPENSION............................................ 126
CONSEQUENCES OF TERMINATION ...................................................................................... 130
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 72 of 195
Termination Payment for Termination by the Authority...................................................................... 130
Other rights and obligations upon Termination................................................................................... 133
Limitation of Termination Payments by the Authority ......................................................................... 134
FORCE MAJEURE ...................................................................................................................... 135
Force Majeure Events ......................................................................................................................... 135
Non – Political Force Majeure Events.................................................................................................. 135
Indirect Political Force Majeure Event................................................................................................. 136
Political Force Majeure Event .............................................................................................................. 136
Exceptions applicable to the Concessionaire ...................................................................................... 136
Exceptions Applicable to the Authority................................................................................................ 137
Effect of Force Majeure before the issue of Notice to Commence....................................................... 137
Effect of Force Majeure after Compliance Date .................................................................................. 137
Allocation of costs during the subsistence of Force Majeure ............................................................... 138
Termination Notice ............................................................................................................................. 138
Termination Payments for Force Majeure Events ............................................................................... 138
Dispute Resolution.............................................................................................................................. 138
Liability for other losses, damages etc. ............................................................................................... 138
Duty to Report.................................................................................................................................... 138
Excuse from performance of obligations............................................................................................. 139
DISPUTE RESOLUTION ........................................................................................................... 140
PERIODICAL AUDIT AND INSPECTION................................................................................. 142
FINANCING DOCUMENTS ....................................................................................................... 143
TAXATION AND CONFIDENTIALITY ...................................................................................... 144
PROJECT REVENUES AND COMMERCIAL CHARGES ............................................................ 146
TRANSFER OF THE PROJECT .................................................................................................. 147
MISCELLANEOUS PROVISIONS ............................................................................................. 149
Governing Law and Jurisdiction .......................................................................................................... 149
Waiver…............................................................................................................................................. 149
Exclusion of implied warranties........................................................................................................... 149
Severability......................................................................................................................................... 149
Entire Agreement ............................................................................................................................... 150
Custody of Documents ....................................................................................................................... 150
Copyright............................................................................................................................................ 150
Use of the Authority's Documents ...................................................................................................... 150
Compliance with Laws and Directives................................................................................................. 150
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 73 of 195
Joint and Several Liability ................................................................................................................... 151
Notice………………………………………………………………………………………………………………………………..151
Language ………………………………………………………………………………………………………………………….151
No Assignment .................................................................................................................................. 152
No Termination ................................................................................................................................. 152
Counterparts ...................................................................................................................................... 152
SCOPE OF WORK AND SPECIFICATIONS .............................................................................. 155
FORMAT OF PERFORMANCE SECURITY ................................................................................ 171
CALCULATION METHOD FOR PREMIUM ............................................................................... 173
THE SITE ................................................................................................................................... 176
FORMAT OF AUDIT REPORT ................................................................................................... 177
SCHEDULE – VI CERTIFICATE BY EXECUTIVE ENGINEER AT TIME OF COMPLETION OF
IMPLEMENTATION .................................................................................................................. 180
FORMAT FOR WORKING OF PREMIUM PAID ....................................................................... 182
CONSENT FOR SUB LETTING .................................................................................................. 183
FORMAT FOR AGREEMENT COMPLETION CERTIFICATE..................................................... 184
FINANCIAL MODEL AND VARIOUS FORMATS FOR CALCULATION OF TERMINATION
PAYMENT .................................................................................................................................. 185
PROVISIONAL COMPLETION CERTIFICATE ......................................................................... 186
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 74 of 195
CONCESSION AGREEMENT
THIS CONCESSION AGREEMENT (the “Agreement”) is entered into on this the
________________ day of _______________________ at ____________________________
BETWEEN
PARTIES:
THE GOVERNOR OF MAHARASHTRA, through the Executive Engineer, Public Works
Division , Satara. (hereinafter referred to as the “Authority”) which expression
shall, unless the context otherwise requires, include its administrators, successors and assigns)
of the ONE PART1;
AND
___________________________________ LIMITED, a company within the meaning
of the Companies Act, 2013 with Corporate Identification Number (C.I.N.)
1
accordance with the instructions below:
Note 1: The provisions are to be retained in the draft Concession Agreement forming part of Bidding Documents and shall be suitably modified by the Bidders after the issue of Letter of Award (LOA) in order to reflect the bid-specific particulars in the Concession Agreement. The provisions in curly brackets are to be retained in the Concession Agreement if applicable based on bid – specific conditions.
Note 2: Blank spaces are to be retained in the draft Concession Agreement and shall be suitably filled by the Bidders after the issue of LOA in order to reflect bid – specific particulars in the Concession Agreement. However, blank spaces shall be retained in all Schedules which contain formats that are to be used after the Concession Agreement is executed.
These instructions are to be removed prior to execution of the finalized Concession Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 75 of 195
__________________________
and
having
its
registered
office
at
_______________________________________________________ (hereinafter referred to as
the “Concessionaire” which expression shall, unless the context otherwise requires, include its
successors and permitted assigns) of the OTHER PART.
The Authority and the Concessionaire are hereinafter, collectively referred to as, the “Parties”
and each, individually as a “Party”.
RECITALS:
WHEREAS:
A.
B.
C.
D.
E.
The Authority, seeks to construct ‘Jan Suvidha Kendras’ for the benefit of the users of
the State Highway (SH) No _________, which shall inter alia include general and
ladies toilets, provide clean drinking water and provide other public amenities, under
the work titled “DESIGN, BUILD, FINANCE, CONSTRUCTION, DEVELOPMENT,
IMPLEMENTATION, OPERATION AND MAINTENANCE OF THE JAN SUVIDHA
KENDRA, AT Rest House Khandala MAHARASHTRA” and seeks to involve private
participation on design, build, finance, construct, implement, operate, maintain and
transfer basis.
The Parties are entering into this Agreement on the mutual understanding that the
design, build, finance, construction, development, operation and maintenance of the
Project (hereinafter defined) and / or the performance of any of the obligations of the
Concessionaire under this Agreement shall be entirely self – funded by the
Concessionaire and the Concessionaire shall not enter into any financing arrangement
with any lenders, banks to financial institutions in connection with the Project
(hereinafter defined) and / or shall not create any interest, title, lien, charge and / or
Encumbrance (hereinafter defined) over any of the Assets (hereinafter defined) of the
Project (hereinafter defined), at any time during the subsistence of the Agreement.
The Authority had accordingly invited proposals by its Expression of Interest No.
________ dated ________________________ (the “Expression of Interest” or “EOI”)
for short listing of bidders for the Project (hereinafter defined) at Rest House Khandala from
eligible bidders. After the shortlisting of certain bidders, the Authority, in consideration of
public interest, decided to invite proposals from all bidders under a Request for Proposal
by setting out the technical and commercial terms of selection of the selected bidder for
the performance of the duties, obligations and responsibilities in relation to the Project
(hereinafter defined).
The Authority, in consideration of public interest, had accordingly invited proposals from all
bidders by its Request for Proposal (“RFP”) No ________________ and had prescribed the
technical and commercial terms and conditions to be satisfied by the selected bidder for
undertaking the Project (hereinafter defined).
The bidders acknowledged and confirmed that they had undertaken due diligence and
audit of all aspects of the Project (hereinafter defined) including without limitation the
technical and financial viability and legal due diligence and on the basis of its
independent satisfaction decided to submit proposal as per the terms, conditions and
requirements of the RFP.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 76 of 195
F.
G.
H.
I.
J.
After evaluation of the bids received, the Authority had accepted the bid of the
selected bidder (the “Selected Bidder”) and issued its Letter of Award No.
_________________ dated _______________________ (hereinafter called the
“LOA”) to the Selected Bidder requiring, inter alia, the execution of this Agreement
within 45 (forty – five) days of the date of issue thereof.
The Selected Bidder has since promoted and incorporated the special purpose vehicle,
____________________________________________________ LIMITED as a limited
liability company under the Companies Act 2013, and has requested the Authority to
accept the Concessionaire as the entity which shall undertake and perform the
obligations and exercise the rights of the Selected Bidder under the LOA, including the
obligation to enter into this Agreement pursuant to the LOA for executing the Project
(hereinafter defined).
After the issue of the LOA, the Selected Bidder has duly submitted the Deed of
Guarantee/s to the Authority in favour of the Concessionaire and has provided the
Performance Security of Rs. ____________ lakhs (Rupees ___________ only) to the
Authority in accordance with the requirements in this regard under the RFP.
By its letter dated ______________________________, the Concessionaire has also
made the same request as the Selected Bidder to the Authority to accept it as the
entity which shall undertake and perform the obligations and exercise the rights of the
Selected Bidder including the obligation to enter into this Agreement pursuant to the
LOA. The Concessionaire has further represented to the effect that it has been
promoted by the Selected Bidder for the purposes hereof.
The Authority has agreed to the said request of the Selected Bidder and the
Concessionaire, and has accordingly agreed to enter into this Agreement with the
Company for the design, build, finance, construction, development, implementation
operation and maintenance of the Project (hereinafter defined), subject to and on the
terms and conditions set forth hereinafter.
NOW THEREFORE, in view of the offer, mutual promises and consideration set out under this
Agreement, the sufficiency and adequacy of which is hereby acknowledged, the Parties hereby
agree to be bound by the provisions of this Agreement, and hereby agree as follows:
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 77 of 195
ARTICLE – 1
DEFINITIONS AND INTERPRETATION
1.1.
(a)
(b)
(c)
(d)
Definitions
In this Agreement, unless repugnant to the context or meaning thereof, the following
words and expressions shall have the meanings hereinafter respectively assigned to them:
“Agreement” means and includes this signed Agreement (including the schedules
thereto), the LOA, the RFP including without limitation the written clarification(s),
addendums, amendments, corrigenda, addenda, clarifications, proforma/s, declarations
and exhibits thereto, the bid submitted by the Selected Bidder dated ______________,
201__ including all annexures and other documents submitted along with that and all
documents, drawings, information, representations, warranties and undertakings made
by the Selected Bidder during the bid evaluation process as per the RFP.
“Agreement Completion Certificate” means the certificate issued under Article 12 of
this Agreement.
“Applicable Laws” means all laws which are applicable to the Project and / or the
Concessionaire extending to the State of Maharashtra having been enacted or brought into
force by Government of India and / or the Government of Maharashtra including
regulations and rules made there under, and judgments, decrees, injunctions, writs and
orders of any court of record, applicable to this Agreement and the exercise, performance
and discharge of the respective rights and obligations of the Parties hereunder, as may
be in force and effect during the subsistence of this Agreement.
“Assets” means all physical and other assets relating to and forming part of the Project
and / or Site including without limitation the movable and immovable properties
(excluding the underlying land, the Site and structures existing as per inspection report
provided by the Authority) thereof, as the case may be, including:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
rights over the Project and / or the Site in the form of Clearances;
the drawings, user manuals, plans, maps, survey reports and other documents, by
whatsoever name called, including the Project Report, pertaining to the Project,
the Site and any tangible assets therein;
tangible assets such as civil works and equipment including foundations,
embankments, electrical systems, communication systems and administrative
offices;
all rights of the Concessionaire under any agreements in relation to the Project
and / or the Site;
financial assets, such as receivables, security deposits etc.;
insurance proceeds; and,
the Clearances in relation to the Project, the Site and / or the obligations of the
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 78 of 195
Concessionaire under this Agreement.
(e)
(f)
(g)
“Associates” means in relation to either Party and/or Joint Venture (JV) Members, a
person who controls, is controlled by, or is under the common control with such Party
or Joint Venture (JV) Member. As used in this definition, the expression “control”
means with respect to a person, the ownership, directly or indirectly, of more than 50%
of the voting shares of such Person, the power to direct the management and policies
of such Person, whether by operation of law or by contract or otherwise and / or the
power to directly or indirectly, appoint the majority of the directors on the Board of
Directors whether by operation of law, by contract or otherwise, of such Person.
“Book Value” shall mean the written down value in the audited books of the
Concessionaire of a specific asset or class of asset in accordance with generally
accepted accounting principles and applicable accounting standards.
“Change in Law” means the occurrence of any of the following events after the
Proposal Acceptance Date:
(i)
(ii)
(iii)
(iv)
(v)
Enactment of any new Applicable Law;
The repeal, modification or re – enactment of any existing Applicable law;
the commencement of any Applicable law, which has not entered into effect as of
the Proposal Acceptance Date;
a change in the interpretation or application of any Applicable Law, by a judgment of
a court of record which has become final, conclusive and binding, as compared to
such interpretation or application by a court of record prior to the Proposal
Acceptance Date; or,
the enactment, commencement and / or imposition of any new Taxes or duties
which were not in existence on the Proposal Acceptance Date. It is specially clarified
that a change in the rate of a Tax or duty shall not be considered a Change in Law, if
the tax or duty itself was in existence on the Proposal Acceptance Date.
(h)
“Clearances” means:
(i)
(ii)
in relation to the Clearances which are required to be obtained by the
Government, all clearances, consents, licenses, approvals, permits, exemptions,
no objection certificates, registrations, filings or other authorisations of whatever
nature, which is necessary for commencement of the construction of the Project;
or
in relation to the Clearances which are required to be obtained by the
Concessionaire or otherwise applicable, all clearances, consents, licenses,
approvals, permits, exemptions, no objection certificates, registrations, filings or
other authorisations of whatever nature, which is necessary for effective
implementation of the Project and required to be obtained or maintained under
Applicable Laws in connection with the construction, operation and maintenance
of the Project, the Site and / or the Assets, as the case may be, during the
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 79 of 195
subsistence of this Agreement.
(i)
(j)
(k)
(l)
(m)
(n)
(o)
(p)
“Commercial Charges” means the charges and / or fees that shall be levied by the
Concessionaire and / or its duly authorised agents and representatives, from various
Users of the Project, on and after the Compliance Date, in accordance with the
requirements of the Project Report and the terms and conditions of this Agreement and
after obtaining prior written consent from the Authority.
“Competent Authority” means any agency, authority, department, ministry, public or
statutory Person of the Government of Maharashtra or Government of India, or any
local authority, or any department, division or other sub-division thereof with authority
over aspects of implementation of the Project having jurisdiction over all or any part of
the Project, the Site and / or the Assets or the performance of all or any of the services
or obligations of the Concessionaire under or pursuant to this Agreement and includes
any commission, board, authority, agency or municipal and other local authority or
statutory body including Panchayat under the control of the Government of India or the
Government of Maharashtra, as the case may be, and having jurisdiction over all or any
part of the Project, the Site and / or the Assets, as the case may be.
“Compliance Date” means the date on which all the Condition Precedents are
satisfied or an earlier date that the Parties may by mutual consent determine, in
accordance with Article 4 of this Agreement. For the avoidance of doubt, every
Condition Precedent shall have been satisfied or waived prior to the Compliance Date
and in the event all Conditions Precedent are not satisfied or waived, as the case may
be, the Compliance Date shall be deemed to occur only when each and every Condition
Precedent is either satisfied or waived, as the case may be.
“Concession Period” shall mean the Implementation Period and a period of fifteen
(15) years commencing on and from the date of Implementation Completion Certificate,
unless extended by the Authority, whose decision shall be final and binding in this
regard, and / or in accordance with the terms of this Agreement, in which event, the
Concession Period shall stand extended accordingly. For the avoidance of doubt, it is
hereby clarified that, in the event of any sooner determination of this Agreement, in
accordance with the terms of this Agreement, the Concession Period shall end on the
Transfer Date.
“Conditions Precedent” means the conditions set out in Article 4 hereof.
“Cost” means all expenditure properly incurred (or to be incurred) by the
Concessionaire, on the Project, the Site and / or the Assets, including overheads and
similar charges, but does not include profit.
“Day” means calendar day, “Month” means 30 (thirty) days and “Year” means 365
days. For the avoidance of any doubt, it is clarified that Year shall mean 366 days in the
case of a leap year.
“Directive” means any present or future requirement, instruction, direction, order, rule
or regulation issued by any Competent Authority which is legally binding or which is
notified by the Authority or the Government of Maharashtra to the Concessionaire, and
any modification, extension or replacement thereof from time to time in force.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 80 of 195
(q)
(r)
“Encumbrances” means any encumbrances such as mortgage, charge, pledge, lien,
hypothecation, security, interest, assignment, privilege or priority of any kind having the
effect of security or other such obligations and shall include without limitation any
designation of loss payees or beneficiaries or any similar arrangement under any
insurance policy pertaining to the Project, the Site and / or the Assets, physical
encumbrances or encroachments on the Project, the Site and / or the Assets where
applicable herein.
“Engineer – in – charge” means the Executive Engineer, Public Works Division
________________________________ having its office at
_______________________________________________.
(s)
(t)
(u)
(v)
(w)
(x)
“Equity” shall mean the sum expressed in Indian Rupees representing the paid – up
equity share capital of the Concessionaire for meeting the equity component of its
financial obligations under this Agreement, and for the purposes of this Agreement shall
include compulsorily convertible instruments or other similar forms of capital, which
shall compulsorily convert into equity share capital of the Concessionaire.
“Financial Model” means the financial model as approved by the Authority and
adopted by the Concessionaire setting forth the capital and operating costs of the
Project and revenues there from on the basis of which the financial viability of the
Project has been determined by the Concessionaire, and includes a description of the
assumptions and parameters used for making calculations and projections therein.
“Financial Year” means the year commencing from 1st April of any calendar year to
the 31st March of the next calendar year except in the first and the last calendar year of
the subsistence of this Agreement. In the first year of subsistence of this Agreement, it
means the period from the Compliance Date to the 31st March of the next calendar year.
In the last year of subsistence of this Agreement, it means the period from 1st April to
the Transfer Date.
“Force Majeure” or “Force Majeure Event” shall mean an act, event, condition or
occurrence specified in the Article 17.
“Good Industry Practice” means those practices, methods, techniques, standards,
skill, diligence and prudence which are generally and reasonably expected and accepted
from a reasonably skilled, prudent and experienced operator engaged in in the same
type of undertaking as envisaged under this Agreement. It would include good
engineering practices in the design, construction, installation, and project management
which would be expected to result in the performance of its obligation by the
Concessionaire and in operation and maintenance of the Project, the Site and the
Assets in accordance with this Agreement, Applicable Laws and Clearances in a reliable,
safe, economical and efficient manner and in compliance with all requirements of
environmental law.
“Implementation Completion Certificate” means the certificate issued under
Article 10.1.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 81 of 195
(y)
(z)
(aa)
(bb)
“Implementation Period” or “Time for Completion of Implementation” means
the period from the Compliance Date to the date of issue of Implementation Completion
Certificate, wherein the designing, building, financing, constructing and development of
the Jan Suvidha Kendra has been duly completed and the Project shall be made
operational, as per Schedule- I and all other applicable provisions of this Agreement.
“Independent Auditor/ Valuer” shall have the meaning as ascribed in this
Agreement.
“Jan Suvidha Kendra” shall have the meaning as ascribed to such term in the RFP
and to be designed, built, financed, constructed, implemented, developed, operated
and maintained in accordance with the terms of this Agreement.
{“Joint Venture (JV) Members” shall mean the members of the joint venture,
constituted for the purpose of bidding under the RFP, if applicable, comprising of the
following members: ____________________________,
__________________________ and _________________________________ (if
applicable)}.
(cc)
(dd)
(ee)
(ff)
“Land Licence Agreement” means the land licence agreement executed/to be
executed by the Authority in favour of the Concessionnaire in relation to the Site,
substantially in the form and format set out in Schedule – XII.
“Lead Member” shall mean the lead member among the Joint Venture (JV) Members,
and in the event there are no Joint Venture (JV) Members, the Selected Bidder;
“License Fees” shall mean the license fees, quoted by the Selected Bidder as set out in
the LOA, as payable by the Concessionaire, in consideration of the grant of leave and
license, right of way and constructive possession of the Site, for the purpose of
performance of its duties, obligations and responsibilities under the Agreement. For the
avoidance of any doubt, it is clarified that the Concessionaire shall be liable to pay an
incremental annual premium over and above the License Fees initially paid in
accordance with the requirements of Article 3 of this Agreement and the said
incremental annual premium shall form part of the License Fees.
“Material Adverse Effect” means consequences of events outside the control of the
Affected Party (as defined under Article 17.1 of this Agreement) which:
(i)
(ii)
(iii)
render any right vested in a Party by the terms of this Agreement ineffective;
significantly impairs or frustrates the ability of any Party to observe and perform
in a timely manner its obligations under this Agreement; or,
frustrates a material provisions of this Agreement or any of the Project
Agreements.
(gg)
“Operation and Maintenance Period” is the period commencing from the
Operations Date and shall expire at the end of the Concession Period.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 82 of 195
(hh)
(ii)
(jj)
(kk)
“Operations Date” or “Date of Issuance of Implementation Completion
Certificate” means the date on which the Authority issues an Implementation
Completion Certificate for the Project and the Concessionaire commences the
commercial operation for the Project.
“Party” means any of the parties to this Agreement.
“Performance Security” means a Bank Guarantee for an amount prescribed by the
Authority of and shall be in the format as set out in Schedule – II, from a scheduled
bank approved by the Authority.
“Person” means any natural person, firm, corporation, company, partnership, joint
venture, trust, government, state or agency of a state or any association or partnership
(whether or not having separate legal personality) of two or more of the above and
shall include successors and assigns.
(ll)
“Project” means
the design,
build, finance, construction, development,
implementation, operation and maintenance of the Jan Suvidha Kendra at the Site in
accordance with the provisions of this Agreement, and includes without limitation:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
preparation and submission of the Project Report of the design, build,
construction, development, implementation and commissioning of the Jan
Suvidha Kendra and the Site; and,
completion of the development of the Jan Suvidha Kendra, as per the Project
Report and the provisions of the Agreement and its commissioning; and,
operation and maintenance, as per the terms and conditions of the Agreement
and Schedules hereof, and,
insurance on the Project, the Site and the Assets, for the purposes of providing
the services on a continuous basis; and,
transfer of the Jan Suvidha Kendra, the Project, the Site and Assets (i.e. both
movable and immovable assets, whether provided by the Authority or brought in
by the Concessionaire during the subsistence of this Agreement), in good and
operational condition, to the Authority at the end of the Concession Period or on
prior termination of the Agreement, in accordance with the Specifications, Good
Industry Practice and the terms and conditions of this Agreement; and,
all works, services, duties, obligations and responsibilities relating to or in respect
of the Scope of the Project and the scope of work as set out under Schedule – I
of this Agreement.
(mm)
“Project Agreements” means, collectively, this Agreement, and any other agreements
entered into by the Concessionaire with any Third Party in accordance with the
requirements of this Agreement, in each case as amended, supplemented or otherwise
modified from time to time.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 83 of 195
(nn)
(oo)
(pp)
(qq)
(rr)
(ss)
(tt)
(uu)
(vv)
(ww)
(xx)
(yy)
“Project Insurance” means the insurance taken out by or on behalf of the
Concessionaire pursuant to the provisions and requirements of this Agreement.
“Project Report” means the project report including the drawings of each and every
site, as submitted by the Concessionaire as per Article 4.3 of this Agreement.
“Project Revenues” means all sources of revenues, as specified in Article 22 of the
Agreement, accruing to the Concessionaire from the operation of the Project, in
accordance with the terms and conditions of this Agreement.
“Proposal Acceptance Date” means the date of execution of this Agreement.
“RFP” shall have the meaning as ascribed to it in Recital - D.
“Schedules” mean the schedules to this Agreement.
“Site” means the real estate described in Schedule – IV and in respect of which rights
of leave and license, right of way and constructive possession shall be provided and
granted by the Authority to the Concessionaire, in consideration of the payment of the
License Fees by the Concessionaire, under the terms and conditions of this Agreement,
for the performance of the duties, responsibilities and obligations of the Concessionaire
under the terms and conditions of this Agreement. For the avoidance of doubt, it is
hereby acknowledged and agreed that references to the Site shall be construed as
references to the real estate required for the Project.
“Specifications” means the specifications and standards relating to the quality,
standards, specifications and other requirements for the Project, the Site and / or the
Assets, as set forth in Schedule – I, and any modifications thereof, or additions thereto,
submitted by the Concessionaire to and expressly approved by the Authority.
“Taxes” shall include all statutory dues, taxes, duties, levies, cesses, surcharges,
charges, interest, penalties and any statutory levies including import duties, Central
Sales Tax (CST), State Sales Tax, Value Added Tax (VAT), Goods and Services Tax
(GST), octroi, entry tax, cess and stamp duty to be imposed on and / or assessed on
the Concessionaire at the time of performance of obligations, duties, roles and
responsibilities as provided under the Agreement by all municipal, local bodies, state or
national government authorities or any other government authority in connection with
the obligations, duties, roles and responsibilities of the Concessionaire as provided
under the Agreement.
“Tender”/”Bid”/”Proposal” means the tender, bid and / or proposal as submitted by
the Selected Bidder to the Authority and as accepted by the Authority vide the LOA.
“Termination Date” means the date on which this Agreement terminates by efflux of
time or on the issuance of a Termination Notice.
“Termination Notice” means the communication issued in accordance with this
Agreement by the Authority to the Concessionaire for terminating this Agreement
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 84 of 195
(zz)
(aaa)
(bbb)
(ccc)
(ddd)
(eee)
1.2.
“Termination Payment” means the amount payable, under and in accordance with
this Agreement, by the Authority to the Concessionaire upon the termination of this
Agreement. For the avoidance of doubt, it is expressly agreed that the amount payable
shall be subject to the limitations as specified under this Agreement.
“Third Party” means any Person, real or judicial, or entity other than the Parties to this
Agreement
“Total Project Cost” means the Total Project Cost as approved by the Committee and
certified by the Engineer-in-charge in the certificate issued as per format given in
Schedule – VI of this Agreement.
“Transfer Date” means the date of completion of the Concession Period by efflux of
time in accordance with the terms and conditions of this Agreement including but not
limited to the satisfaction of the requirements as set out in Article 23 of this Agreement
or termination of the Agreement by a Termination Notice.
“Users” means Person(s) / tourists using the Project.
“Variation” means a modification, improvement or change in the Scope of the
Agreement, services, and facilities etc. to be carried out by the Concessionaire, such
that the cost of implementing the modification, improvement or change can be
recovered through a 30 (thirty) day adjustment of the Concession Period.
Relation between the Parties
Nothing contained herein shall be construed as establishing a relation of principal and
agent as between the Authority and the Concessionaire. The Concessionaire, subject to
this Agreement, has the complete charge over its agents, representatives, contractors,
personnel, if any, in performing this Agreement and shall be fully responsible for the
Agreement being performed by them or on their behalf hereunder.
The principles of interpretation of the provisions of this Agreement are as follows, unless
the context otherwise requires:
(i)
(ii)
(iii)
(iv)
Any reference to a statutory provision shall include such provision as is from time
to time modified or re – enacted or consolidated so far as such for modification or
re – enactment or consolidation applies or is capable of applying to any
transactions entered into hereunder;
Reference to laws of Government of Maharashtra laws of India or Indian Laws or
regulation having force of law shall include the laws, acts, ordinances, rules,
regulations, guidelines or byelaws which have the force of law in State of
Maharashtra;
The headings are for convenience and reference only and shall not be used in and
shall not affect, the construction or interpretation of this Agreement;
Terms and words beginning with capital letters and defined in this Agreement
including the Schedules;
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 85 of 195
(v)
(vi)
(vii)
Words importing Person or Parties shall include firms and corporations and any
organization having legal capacity to sue and be sued in its name;
Words importing the singular shall include the plural and vice-versa where
the Concession requires;
The words “include” and “including” are to be construed without limitation and
shall be deemed to be followed by “without limitation” or “but not limited
to” whether or not they are followed by such phrases;
(viii) References to the terms “construction” or “building” include, unless the
context otherwise requires, investigation, design, developing, engineering,
procurement, delivery, transportation, installation, processing, fabrication,
testing, commissioning and other activities incidental to the construction, and
“construct” or “build” shall be construed accordingly;
(ix)
(x)
(xi)
(xii)
References to the term “development” include, unless the context otherwise
requires, construction, renovation, refurbishing, augmentation, upgradation and
other activities incidental thereto, and “develop” shall be construed accordingly;
Any reference to any period of time shall mean a reference to that according to
Indian Standard Time;
References to any gender shall include the other and the neutral gender;
“lakh” means a hundred thousand (100,000) and “crore” means ten million
(10,000,000);
(xiii) Any reference to day shall mean a reference to a calendar day;
(xiv) Any reference to month shall mean a reference to a calendar month;
(xv)
The Schedules of this Agreement form an integral part of this Agreement and will be
in full force and effect as though they were expressly set out in the body of this
Agreement;
(xvi) Any reference at any time to any agreement, deed, instrument or document of
any description shall be construed as reference to that agreement, deed,
instrument or other document as amended, varied, supplemented, modified or
suspended at the time of such reference;
(xvii) References to recitals, Articles, sub – articles or Schedules in this Agreement shall,
except where the context otherwise requires, be deemed to be references to
recitals, Articles, sub-articles and Schedules of or to this Agreement;
(xviii) Any
Agreement,
consent,
approval,
authorisation,
notice,
communication,
information or report required under or pursuant to this Agreement from or by
any Party shall be valid and effective only if it is in writing under the hands of duly
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 86 of 195
authorised representative of such party, as the case may be, in this behalf and not
otherwise;
(xix) Any reference to any period commencing “from” a specified day or date and “till”
or “until” a specified day or date shall include both such days and dates; provided
that if the last day of any period computed under this Agreement is not a business
day, then the period shall run until the end of next business day;
(xx)
The damages payable by either Party to the other of them as set forth in this
Agreement, whether on per diem basis or otherwise, are mutually agreed genuine
pre-estimated loss and damage likely to be suffered and incurred by the Party
entitled to receive the same and are not by way of penalty;
(xxi) Time shall be of the essence in the performance of the Parties’ respective obligations.
If any time period specified herein is extended, such extended time shall also be of
the essence;
(xxii) The Parties hereby agree that the Parties have contributed equally to the
drafting and the preparation of this Agreement. The rule of construction, if any,
that an agreement should be interpreted against the parties responsible for the
drafting and preparation thereof, shall not be applicable;
1.3.
1.4.
Measurements and Arithmetic Conventions
All measurements and calculations shall be in metric system and calculations done in 2
decimals places, with the third digit of 5 or above rounded up and below 5 belong down
except in fee calculation which shall be rounded off to nearest Rupee Hundred (100).
Ambiguities within Agreement
In case of ambiguities or discrepancies within this Agreement, the following shall apply:
(i)
(ii)
(iii)
(iv)
(v)
Between two Articles or more of this Agreement, the provisions of specific Article
relevant to the issue under the consideration shall prevail over those in other
Articles;
Between the Articles and the Schedules, the Articles shall prevail, save and except
as expressly provided in the Articles or the Schedules;
Between the written description on the Drawings and the Specifications and
Standards, the latter shall prevail;
Between the written description on the Drawing and the specific written dimension,
the latter shall prevail; and,
Between any value written in numerals and that in words, the later shall prevail.
1.5.
Priority of Documents
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 87 of 195
This Agreement, and all other agreements and documents forming part of or referred to
in this Agreement are to be taken as mutually explanatory and, unless otherwise
expressly provided elsewhere in this Agreement, the priority of this Agreement and
other documents and agreements forming part hereof or referred to herein shall, in the
event of any conflict between them, be in the following order:
(a)
(b)
this Agreement; and,
all other agreements and documents forming part hereof or referred to herein;
i.e. the Agreement at (a) above shall prevail over the agreements and documents at (b)
above.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 88 of 195
ARTICLE 2:
SCOPE OF THE PROJECT
The scope of the Project (the “Scope of the Project”), as required to be performed by the
Concessionaire as per the terms, conditions, covenants and requirements of this Agreement
and in accordance with the Applicable Laws, Specifications, Clearances and Good Industry
Practice, shall mean and include during the Concession Period:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
Surveying, investigation, planning, preparing and submitting the Project Report including
the drawings as provided by the Authority of the Project as per the laid down provisions
of the Agreement and schedules hereof. The Project Report shall clearly mention the
Specifications to be adopted, facilities to be provided to the Users of the Project and the
Jan Suvidha Kendra, planning for operation and maintenance as well as the space
planned for advertising as per Applicable Laws. The Project Report shall be approved by
the Authority prior to commencement of construction.
Construction and commissioning after approval to Project report, installation of the toilet
Units for men and women as per the Specifications, construction of internal roads,
approach roads, landscaping, children’s play parks, electrification, solar systems, sewage
treatment plant, effluent treatment plant and the Project Report approved by the
Authority and in accordance with the provisions of this Agreement (including the
schedules).
Operation and maintenance of the toilet units and overall Project, on a regular basis, in
accordance with the provisions of this Agreement and the schedules hereof.
Performance and fulfilment of all other obligations in accordance with the provisions of
this Agreement and matters incidental thereto or necessary for the performance of any
or all of the obligations of the Concessionaire under this Agreement and its Schedules
thereof.
Provision for providing clean drinking water and clean toilet use in consideration of the
Commercial Charges, if applicable. Provision for water ATM, sanitary napkin vending and
disposal machines in consideration of the Commercial Charges, if applicable.
Provision of all electrical works including external electrification, installation of CCTV
cameras for whole campus surveillance.
(vii) Sewage treatment, rain water harvesting for the entire Project.
(viii) Any other services as may be desired by the Authority and intimated to the
Concessionaire.
(ix)
(x)
Timely payment of the License Fees to Authority as per the terms and conditions of this
Agreement.
Suggestion box in order to enable submission of suggestions by Users and a Complaints
Register has to be maintained by the Concessionaire in the Project in accordance with
the requirements of this Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 89 of 195
For the avoidance of any doubt, it is clarified herewith that in addition to the Scope of the
Project, the Concessionaire shall be required to carry out any incidental works and services as
required and to comply with all the provisions of the Agreement, the schedules to the
Agreement and as per the requirements of Applicable Laws and Clearances while completing
the design, build, construction, implementation, development, operation and maintenance of
the Project.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 90 of 195
ARTICLE 3:
CONCESSION
3.1
3.2
3.2.1
3.2.2
3.2.3
Grant of Concession
Subject to and in accordance with the terms and conditions set forth in this
Agreement, the Authority hereby grants the concession to the Concessionaire in order
to conduct the design, build, finance, construct, develop, implement, operate and
maintain the Project, the Site and / or the Assets commencing on and from the
Compliance Date, in order to perform its duties, responsibilities and obligations in
accordance with this Agreement, the Scope of the Agreement, the Specifications and
Good Industry Practice. The Authority will execute the Land Licence Agreement in
favour of the Concessionaire in the form and format set out in Schedule – XII hereto.
It is expressly agreed and understood by the Parties that this is a bare license and
nothing herein contained shall ever be construed to create any interest, right of
tenancy, sub – tenancy, leases or sub – leases in favour of the grant of concession and
the juridical possession of the Site shall at all times remain vested with the Authority
and the Concessionaire shall at no time claim any right, title or interest, whether as
tenant, sub – tenant or any other similar status, in the Site or any part thereof. It
should also be clarified that the Concessionaire shall not assign, sublet, transfer and /
or create any lien and / or encumbrance under this Agreement, and / or the Concession
granted under this Agreement on the whole or any part of the Project, nor transfer,
lease or part possession thereof, save and except as expressly permitted by the
Authority in writing, in accordance with the terms and conditions of this Agreement.
Licence Fees to be paid for the Concession period:
The Concessionaire shall pay the Licence Fees for the Concession Period in accordance
with the terms and conditions of this Agreement.
The Concessionaire shall be liable to pay an annual incremental premium, over and
above the payment of the License Fees, in consideration of the grant of the concession
as per Article 3.2.1 above, to the Authority, within thirty (30) days from the
commencement of the Financial Year. Notwithstanding anything to the contrary, the
decision of the Authority in this regard, shall be final and binding on the
Concessionaire. The annual incremental premium, including any revisions and / or
amendments thereto, shall be calculated in accordance with the following:
The same is calculated at Rs. ______ per year, assumed to be increased by _______%
for every year, discounted at Return on Investment of ____% and calculated at
_______________% of market value of land (calculated at five (5) times2 of ready
reckoner rate). In case it is observed by the Committee constituted as per Article 9 of
the Agreement that, ready reckoner rate or market value of land has increased beyond
such _______% as mentioned above, and the Authority is entitled to get additional
premium from the Concessionaire, then in that case Authority shall calculated such
2
calculation of land acquisition cost, detailed explanation is given in instructions of financial model.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 91 of 195
amount of additional premium as per the Financial Model prepared at the time of
submission of the bid by the Selected Bidder.
3.2.4
3.2.5
3.2.6
3.2.7
3.2.8
In case there is negative growth in ready reckoner rate, there shall not be any
reduction in premium payable by the Concessionaire for the relevant Financial Year and
there shall not be any refund for that Financial Year. For the avoidance of any doubt, it
is clarified that the calculations shall be done only for years having positive growth in
ready reckoner value of the Site, and in the absence of any positive growth in the
ready reckoner value of the Site during the relevant Financial Year, the premium paid
during the immediately preceding Financial Year shall be payable by the Concessionaire
to the Authority.
Calculation method for premium, minimum amount of premium shall be calculated as
per Schedule III of this Agreement.
Amount of License Fees payable by the Concessionaire shall be taken into consideration
and per year premium shall be calculated as per the Financial Model for further
calculations.
For avoidance of doubt, financial cash flow of the Concessionaire for calculation of
premium is being attached with this Agreement as Schedule – VII of this Agreement.
Subject to and in accordance with the terms and conditions set forth in this
Agreement, the concession hereby granted shall entitle the Concessionaire, with the
exclusive right to undertake the following, in accordance with the provisions of this
Agreement, the Scope of the Agreement, the Applicable Laws, Specifications, Good
Industry Practice and the Clearances:
(i)
(ii)
(iii)
(iv)
(v)
To implement the Project as per the Scope of the Agreement more
specifically set out in Article 2 hereto and the schedules of this Agreement;
To design, build, construct, install, finance, implement, operate, maintain the
Project and regulate the use by Third Parties of the Project (which should be
clearly and unambiguously informed to the Concessionaire) during the
Concession Period;
To enjoy leave and license, right of way and constructive possession to the Site
for a period that shall be co-terminus with the Concession Period;
To have access and liberty to develop, upgrade, finance, operate and maintain
the proposed Project with the associated facilities and services at the Site during
the Concession Period in accordance with the provisions of this Agreement and
schedules thereof, Applicable Laws, Clearances and Good Industry Practice. Any
development made by the Concessionaire on the Project, the Site and / or the
Assets in respect of the Project shall be deemed to be the property of the
Authority and the Concessionaire relinquishes all his rights in such property in
favour of Authority;
Exclusive right and authority, during the Concession Period, to carry out the
specified activities in relation to the Project;
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 92 of 195
(vi)
(vii)
Use of the Project to determine, demand, levy, collect, enforce, retain and
appropriate Commercial Charges and to periodically revise the same in
conformity with the market rates, with prior consent of the Authority in writing;
Manage, operate and execute rights over all or any part of the Assets without
any limitation or restriction other than those expressly set out in this Agreement;
(viii) To fulfil its obligations under this Agreement, undertake activities by itself,
without appointing any contractors, sub – contractors etc.;
(ix)
(x)
Make applications for obtaining of all the Clearances from the Competent
Authorities for performance of the duties, obligations and responsibilities of the
Concessionaire under this Agreement, as and when required;
Exercise such other rights as the Authority may determine as being necessary or
desirable for the purposes incidental and necessary for designing, constructing,
installing, financing, implementing, managing, operating, running and
maintaining the Project; and,
(xi)
Bear and pay all expenses, costs and charges incurred in the fulfilment of all
the Concessionaire’s obligations under the terms and conditions of this
Agreement.
3.2.9
For the avoidance of any doubt, it is hereby clarified that notwithstanding anything to
the contrary as stated under this Agreement, nothing contained herein, including the
act of granting permission to upgrade the Project at the Site shall vest or create any
proprietary interest in the Project or any part thereof including any construction or
installation etc. installed in the structure of the Project in favour of the Concessionaire
or any person claiming through or under the Concessionaire. The Concessionaire shall
not in any manner sell, transfer, assign, mortgage, charge, create lien or otherwise
Encumber or deal with the Project in any manner. The Concessionaire acknowledges,
accepts and confirms that the covenant contained herein is an essence of this
Agreement.
3.2.10 All Taxes (including service tax and GST) applicable and/or payable on the Licence Fees
and the annual incremental premium shall be borne and discharged by the
Concessionaire at actuals as per the instructions of the Authority.
3.3
Actions in Support of the Concession
(i)
(ii)
The Authority shall recognize and undertake not to, in any manner, violate or
cause breach of the terms of this Agreement
The Authority undertake not to terminate or repudiate this Agreement prior to
the expiry of the Concession Period otherwise than in accordance with the
provisions of this Agreement;
(iii)
The Authority shall provide assistance and recommendations
to the
Concessionaire so as to enable the Concessionaire to obtain the requisite
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 93 of 195
Clearances from the Competent Authority(ies), including Government of
Maharashtra, in support of the Concessionaire’s applications for Clearances
that may be needed from time to time for the implementation of the Project.
Provided that the Concessionaire shall make the requisite applications and is
in compliance with the necessary conditions for the grant of such Clearances.
3.4
3.4.1
3.4.2
Concession Period
During the Concession Period the Concessionaire is authorized to design, build,
construct, implement and develop the Project and to operate and maintain the Project
in accordance with the provisions hereof. Provided that in the event of early
termination, the Concession Period shall be limited to the period commencing from the
Compliance Date and ending with the Transfer Date.
It is hereby agreed between the Parties that:
(i)
(ii)
In the event of the Concession Period being extended by Authority beyond the
period of fifteen (15) years from the Compliance Date, in accordance with the
provisions of this Agreement, the Concession Period shall stand extended
accordingly; and,
In the event of termination, the Concession Period shall mean and be limited to
the period commencing from the Compliance Date and ending with the Transfer
Date.
3.4.3
3.5
At the end of the Concession Period or sooner termination of this Agreement for any
reason whatsoever, all rights given under this Agreement shall cease to have effect and
the Project, the Site and the Assets, in good and operational condition, shall stand
transferred to the Authority without any obligation of Authority to pay or adjust any
consideration or other payment to the Concessionaire. On expiry of the Concession
Period and / or sooner termination of the Agreement, in accordance with the terms of
this Agreement, all rights accorded to the Concessionaire under this Agreement shall
cease to be in effect and the Project, the Site and / or the Assets shall be transferred
to the Authority in accordance with Article 23 of this Agreement.
Implementation Period
The Implementation Period or the Time for Completion of Construction shall be a
period of _______________ months, commencing from the Compliance Date, wherein
the Concessionaire shall be required to comply with the following obligations:
(i)
(ii)
Complete the design, build, construction, implementation and development of
the Project, as per the Project Report as approved by the Authority and also, in
accordance with the provisions laid down in the Schedule - I of this Agreement.
Procure full insurance cover for the Project, the Site and the Assets, in compliance
with the following requirements: The Concessionaire shall effect and maintain at its
own cost, during the Concession Period, such insurances for such maximum sums as
may be required under this Agreement and the Applicable Laws, and such
insurances as may be necessary or prudent in accordance with Good Industry
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 94 of 195
Practice. The Concessionaire shall also effect and maintain such insurances as may
be necessary for mitigating the risks that may devolve on the Authority as a
consequence of any act or omission of the Concessionaire during the Concession
Period. The Concessionaire shall procure that in each insurance policy, the Authority
shall be a co – insured and that the insurer shall pay the proceeds of insurance to
the Authority in the event of termination. Within 5 (five) days of obtaining any
insurance cover, the Concessionaire shall furnish to the Authority, notarised true
copies of the certificate(s) of insurance, copies of insurance policies and premia
payment receipts in respect of such insurance, and no such insurance shall be
cancelled, modified, or allowed to expire or lapse until the expiry of at least 45
(forty five) days after notice of such proposed cancellation, modification or non –
renewal has been delivered by the Concessionaire to the Authority. All insurance
policies in respect of the insurance obtained by the Concessionaire shall include a
waiver of any and all rights of subrogation or recovery of the insurers thereunder
against, inter alia, the Authority, and its assigns, successors, undertakings and
their subsidiaries, affiliates, employees, insurers and underwriters, and of any
right of the insurers to any set – off or counterclaim or any other deduction,
whether by attachment or otherwise, in respect of any liability of any such
Person insured under any such policy or in any way connected with any loss,
liability or obligation covered by such policies of insurance. The Concessionaire
hereby further releases, assigns and waives any and all rights of subrogation or
recovery against, inter alia, the Authority and its assigns, undertakings and their
subsidiaries, affiliates, employees, successors, insurers and underwriters, which
the Concessionaire may otherwise have or acquire in or from or in any way
connected with any loss, liability or obligation covered by policies of insurance
maintained or required to be maintained by the Concessionaire pursuant to this
Agreement or because of deductible clauses in or inadequacy of limits of any
such policies of insurance. Without prejudice to the provisions as contained
hereinabove, the Concessionaire shall, during the Concession Period, procure and
maintain adequate insurance cover including but not limited to the following:
1.
2.
3.
4.
loss, damage or destruction of the Project, the Sites and the Assets in the
care and custody of the Concessionaire;
the Concessionaire’s general liabilities arising out of the Agreement;
the workmen’s compensation insurance; and,
any other insurance that may be necessary to protect the Concessionaire and
its employees, including all Force Majeure Events, in accordance with Article
17 of this Agreement, that are insurable and not otherwise covered in items 1
to 3 above.
(iii)
(iv)
It is hereby agreed between the Parties that the Concessionaire should not alter
/ change any civil structure including utilities of the Project, the Site and the
Assets unless as agreed and approved by the Authority in writing during the
Concession Period.
The Concessionaire guarantees that the Time for Completion of Implementation
for the Project shall be achieved in accordance with the provisions of this
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 95 of 195
Agreement and not later than the Implementation Period from the Compliance
Date, for any reason whatsoever. In the event that the Concessionaire does not
ensure that the Time for Completion of Implementation for the Project is not
achieved within the Implementation Period and / or in accordance with the terms
and conditions of the Agreement, and the delay has not occurred as a result of
breach of this Agreement by the Authority or due to a Force Majeure Event, the
Concessionaire shall pay to the Authority, damages in an amount calculated at
the rate of 2% (z two per cent) of the Performance Security for each day’s delay
until due fulfilment. For the avoidance of any doubt, it is hereby clarified that
such right of the Authority to payment of damages by the Concessionaire, as set
out under this Article, shall not be in prejudice to any other rights and / or
remedies of the Authority, under this Agreement and / or Applicable Laws and /
or in equity. The Time for Completion of Implementation for the Project may be
extended, on prior written consent of the Authority. For the avoidance of any
doubt, it is hereby clarified that, in the event of such prior written consent of the
Authority, the Implementation Period shall also stand extended accordingly. In
the event that the Concessionaire does not ensure that the Time for
Completion of Implementation for the Project is not achieved within the
Implementation Period and / or in accordance with the terms and conditions of
the Agreement, and the delay has not occurred as a result of breach of this
Agreement by the Authority or due to a Force Majeure Event, the Authority shall
also have the right to terminate the Agreement, for a Concessionaire Event of
Default, by giving 15 (fifteen) days prior notice to the Concessionaire.
(v)
Extension of time : The Concessionaire may apply for an extension of the Time
for Completion of Implementation if it is or shall be delayed or likely to be
delayed beyond the expiry of the Implementation Period, either before or after
the Time for Completion of Implementation, by any of the following causes:-
1.
2.
3.
4.
5.
6.
Variation;
A Force Majeure Event;
Change of Scope;
A cause of delay giving an explicit and express entitlement to extension of
time under any Articles in this Agreement, unless the Concessionaire has not
complied with such Article;
Any delay, impediment or prevention by the Authority; and,
Any delay caused by Competent Authorities in providing the Clearances
pertaining to the performance of duties, obligations and responsibilities of the
Concessionaire.
(vi)
The Concessionaire shall at all times use its best endeavours to minimize any delay
in the performance of its obligations under this Agreement, whatever may be the
cause of such delay. For the avoidance of any doubt, it is hereby clarified that the
decision to extend the Time for Completion of Implementation is an option and
not an obligation and that the decision of the Authority regarding waiver of any
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 96 of 195
delay caused by the Concessionaire and any extension in the Concession Period
and / or extension in the prescribed time period under this Agreement shall be
final and binding on the Concessionaire.
(vii)
If the Concessionaire intends to apply for an extension of the Time for Completion
of Implementation, the Concessionaire shall give notice to the Authority of such
intention as soon as possible and in any case within 10 (ten) days of the start of
the event giving rise to any such delay (other than for Change of Scope), together
with any other notice required by this Agreement and relevant to such cause. Any
such notice shall state the extent and anticipated delay and its anticipated effect
on the Time for Completion of Implementation, and shall specify the steps the
Concessionaire proposes to take to minimise such delay. The Concessionaire shall
keep such true and accurate records as may be necessary to substantiate any
application, at a location acceptable to the Authority and shall provide such other
information as may reasonably be requested by Authority. The Concessionaire shall
provide and permit the Authority to inspect all such records.
(viii) Within 10 (ten) days of the first day of such delay (or such other period as may
be agreed by the Authority), the Concessionaire shall submit full supporting details
of its application. Except that, if the Concessionaire cannot submit all relevant
details within such period because the cause of delay continued for a period
exceeding 7 (seven) days, the Concessionaire shall submit interim details at
intervals of not more than 10 (ten) days (from the first day of such delay) and
full and final supporting details of its application within 14 (fourteen) days of the
last day of delay.
(ix)
Provided that the Concessionaire has complied with this Article, the Authority shall
proceed in accordance with Article 14 to determine either prospectively or
retrospectively such adjustment as may be due, taking into account all relevant
circumstances. The Authority shall notify the Concessionaire accordingly. When
determining each extension of time, Authority shall review its previous
determinations and may revise, but shall not decrease, the extension, and provided
that the extension of time is not a consequence of any negligence, default or
breach of Agreement by the Concessionaire or those for whom it is responsible.
However, the Concessionaire shall not be entitled to an extension of the Time for
Completion of Implementation, to the extent that the delay in respect of which the
extension of time is requested is attributable to any negligence, default or breach
of this Agreement by the Concessionaire or those for whom it is responsible, as
determined by the Authority or any expert, as appointed by the Authority for this
purpose.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 97 of 195
ARTICLE 4:
CONDITIONS PRECEDENT
4.1
4.2
Subject to the express provisions to the contrary under this Agreement, or unless the
context otherwise requires, the rights and obligations under this Agreement shall take
effect only upon fulfilment of all the Conditions Precedent set out in Articles 4.2 and 4.3 of
this Agreement, on or before the expiry of a period of 60 (sixty) days from the Proposal
Acceptance Date. However, the Authority may at any time at its sole discretion and in
writing, waive fully or partially any of the Conditions Precedent of the Concessionaire.
Obligations for satisfaction of Conditions Precedent for the Authority
The Authority shall have:
(i)
(ii)
(iii)
(iv)
Handed over to the Concessionaire, the constructive possession of the Site free
from Encumbrances. This Conditions Precedent on the part of the Authority shall
be fulfilled only after all other Conditions Precedent of both the Parties are
met/fulfilled and / or waived off as per this Article. However, it is being clarified
that the Authority shall hand over the Site in “as is where is” basis to the
Concessionaire;
Carried out inspection (wherein one (1) representative of Authority, and
Concessionaire shall be mandatorily present) of the Site and prepared a detailed
report on the Site to be transferred, by the Authority, to the Concessionaire for
the development of the Project. It is being clarified here that the Site shall be
checked, verified, confirmed and signed by the representatives of the Parties and
shall be considered as final. It is hereby agreed by the Parties that such
verification and / or confirmation shall not be unreasonably withheld, and
nothing in this Article shall prejudice the fact that the Site shall be provided by
the Authority, on “as is where is” basis. The copies of the same shall be kept
by the Authority, and Concessionaire;
Issued government orders or gazette notifications, if necessary, for implementing
the Project; and,
Shall obtain all Clearances as required for construction at the Site.
4.3
Obligations for satisfaction of Conditions Precedent for the Concessionaire
The Concessionaire shall have:
(i)
(ii)
Submitted the Project Report including detailed drawings of the Project and the
Site to the satisfaction of the Authority, and within a period of 30 (thirty) days
from the Proposal Acceptance Date. The Project Report submitted by the
Concessionaire should include a technical details of the various facilities
proposed to be used in the Project;
Incorporated the comments/ observations (if any) on the Project Report of the
Project, as proposed by the Authority and submitted for approval, within a period
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 98 of 195
of 15 (fifteen) days from the date of receipt of comments / observations from
the Authority. However, it is clarified here that the Concessionaire shall not start
the implementation until and unless the Authority approves the Project Report of
the Project again after carrying out necessary comments/ observations (if any),
which shall not be unduly delayed;
(iii)
(iv)
(v)
(vi)
(vii)
Submit the Total Project Cost to the Authority for perusal;
Provided an undertaking that all of the representations and warranties of the
Concessionaire set forth in Article 13 of this Agreement are true and correct as
on date of this Agreement and as on the Compliance Date and shall be true and
correct till the expiry of the Concession Period;
Provided the Authority with certified true copies, by an authorised officer of the
Concessionaire, of its Memorandum of Association and Articles of Association of
the Concessionaire;
Shall obtain all Clearances (not relating to construction at the Site) for
commencement of performance of the obligations, duties and responsibilities of
the Concessionaire;
Provided the Authority, certified true copies, by the Director of the
Concessionaire, of all resolutions adopted by the Board of Directors of the
Concessionaire authorising the execution, delivery and performance of this
Agreement by the Concessionaire; and,
(viii) The Concessionaire has provided the Performance Security to the Authority in
accordance with the requirements of the Agreement, prior to the Proposal
Acceptance Date.
Provided that upon request in writing by the Concessionaire, the Authority, may, at its
sole discretion and in writing, waive fully or partially any or all the Conditions Precedent
set forth in this Article.
4.4
General Obligations to satisfy Condition Precedents
(i)
(ii)
Each Party hereto shall use all reasonable endeavours at its cost and expense to
procure the satisfaction in full of its respective Conditions Precedent set out
above within 60 (sixty) days of Proposal Acceptance Date. The Parties undertake
to provide to each other all reasonable assistance, co – operate with each other
and to use all reasonable endeavours to ensure that the Conditions Precedent
are satisfied as soon as possible.
Upon satisfaction in full of all Conditions Precedent for a Party, the other Party
shall forthwith issue to such Party a Certificate of Compliance with Conditions
Precedent (the “Certificate of Compliance”) specifically setting out that the
Conditions Precedent as per the relevant Article of this Agreement has been duly
complied with.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 99 of 195
(iii)
(iv)
The later of the date of issue of Certificate of Compliance to the Concessionaire
or the Authority shall be the Compliance Date, whereupon the obligations of the
Parties under this Agreement shall commence and whereon the Authority shall
issue the notice to commence to the Concessionaire which shall set out the
Compliance Date of this Agreement. For the avoidance of any doubt, it is hereby
clarified that any investigations, surveys etc. of whatsoever nature, which the
Concessionaire elects to carry out prior to the Proposal Acceptance Date, shall be
entirely at the risk and cost of the Concessionaire. The Concessionaire shall not
be permitted to commence the work and perform any of its duties, obligations
and responsibilities under this Agreement at any part of Site prior to the issuance
of notice to commence by the Authority.
Each Party shall bear its respective costs and expenses of satisfying such
Conditions Precedents unless otherwise expressly provided for under this
Agreement.
4.5
Non – satisfaction of Conditions Precedent
(i)
(ii)
(iii)
Without prejudice to any other provision under this Agreement and subject to
compliance with the requirements under Article 22 of this Agreement, the Parties
expressly agree that in the event, the Compliance Date does not occur, for any
reason whatsoever, before 60 (sixty) days from the Proposal Acceptance Date or
the extended period provided under this Agreement, all rights, privileges, claims
and entitlements of the Concessionaire under or arising out of this Agreement
shall be deemed to have been waived by, and to have ceased with the
concurrence of the Concessionaire, and the Agreement shall be deemed to have
been terminated by mutual agreement of the Parties. Provided however, that in
the event of non – occurrence of the Compliance Date is for reasons attributable
to the Concessionaire, the Performance Security shall be encashed and
appropriated by the Authority as liquidated damages as genuine pre – estimate
of damages caused to the Authority. For the avoidance of any doubt, it is hereby
clarified by the Parties that the right of the Authority to encash and appropriate
the Performance Security, shall not be in prejudice to any other rights and / or
remedies available with the Authority under the terms and conditions of this
Agreement, under Applicable Laws and under equity.
In the event that the Concessionaire has fulfilled its Conditions Precedent and
Authority has not procured fulfilment of any or all of the Condition Precedents
set forth in Article 4.2 within the period specified in respect thereof, the
Authority shall not be liable to pay any damages to the Concessionaire. The
Parties hereby agree that, in the event that the Authority, has not complied with
the Conditions Precedent within the period of 60 (sixty) days from the Proposal
Acceptance Date, the Authority shall provide a notice to the Concessionaire in
writing, providing for extension of the said period for due satisfaction of the
Conditions Precedent, and such period of compliance shall stand extended
accordingly as if mutually agreed by the Parties in writing.
In the event the Authority has terminated this Agreement under Article 4.5 (i)
due to non – fulfilment of Conditions Precedent by the Concessionaire, the
Authority shall not be liable in any manner whatsoever to the Concessionaire or
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 100 of 195
its contractors, agents and employees. In addition to this, the Authority shall
have the right to encash and appropriate the Performance Security as liquidated
damages as genuine pre – estimate of damages caused to the Authority. For the
avoidance of any doubt, it is hereby clarified by the Parties that the right of the
Authority to encash and appropriate the Performance Security, shall not be in
prejudice to any other rights and / or remedies available with the Authority
under the terms and conditions of this Agreement, under Applicable Laws and
under equity.
(iv)
(v)
In the event that (a) the Concessionaire does not procure fulfilment of any or all
of the Conditions Precedent as set forth under this Agreement, within a period of
60 (sixty) days from the Proposal Acceptance Date, and (b) the delay has not
occurred as a result of breach of this Agreement by the Authority or due to Force
Majeure, the Concessionaire shall pay to the Authority, liquidated damages, as a
genuine pre – estimate of damages, in an amount calculated at the rate of 2%
(two per cent) of the Performance Security for each day’s delay until the
fulfilment of such Conditions Precedent.
It is hereby agreed between the Parties, that the Parties may extend the period
for fulfilling the Conditions Precedent by mutual agreement in writing.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 101 of 195
ARTICLE 5:
COMMERCIAL CONSIDERATION
5.1
Commercial Charges
(i)
(ii)
(iii)
The Concessionaire shall have to maintain true and accurate books of accounts,
in accordance with Indian GAAP and Good Industry Practice, of all the records of
its Commercial Charges, receipts, income, expenditure, payments, assets,
liabilities and revenue collection, directly and / or indirectly, from the Project
including without limitation collection of any charges, fees, surcharge, tariff
collection, advertisement display collection and such other charges and / or fees
as collected from the Users of the Project, by whatsoever name called, after the
issuance of the Implementation Completion Certificate for the Project and the
same will be shared with the Authority at the end of each quarter of the
Financial Year.
The Concessionaire shall provide to the Authority, 2 (two) copies of its balance
sheet, cash flow statement and the profit and loss account statement, along with
a report thereon by its duly appointed auditors, within 60 (Sixty) days of the
close of the Financial Year to which they pertain.
The Authority may, at its sole discretion, extend the Concession Period. In such
event, the Concession Period shall stand extended accordingly.
5.2
Performance Security
(i)
(ii)
(iii)
The Concessionaire shall provide the Performance Security, amounting to Rs.9,16,400/-
(Rupees Nine Lakh Sixteen Thousand Four Hundred Only) to the Authority, prior to the Proposal
Acceptance Date, in the format as specified in Schedule – II of this Agreement and shall ensure that the
Performance Security shall be duly maintained for the entire Concession Period.
The Performance Security shall be from a scheduled bank approved by the
Authority, payable on demand without any demur, reservation, caveat, protest
and / or recourse at Rest House Khandala Maharashtra.
Upon occurrence of a Concessionaire Event of Default, the Authority shall,
without prejudice to its other rights and remedies hereunder or in law, be
entitled to encash and appropriate the Performance Security as liquidated
damages, which shall be genuine pre – estimate of the losses caused to the
Authority in this regard. Upon such encashment and appropriation from the
Performance Security, the Concessionaire shall, within 10 (ten) days replenish, in
case of partial appropriation, to its original level, the Performance Security and in
case of appropriation of the entire Performance Security, provide a fresh
Performance Security and the Concessionaire shall, within the time so granted
replenish or furnish to the Authority a fresh Performance Security as aforesaid,
failing which the Authority shall be entitled to terminate this Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 102 of 195
ARTICLE 6:
OBLIGATIONS OF THE AUTHORITY DURING THE IMPLEMENTATION
PERIOD
6.1
General Obligations of the Authority during the Implementation Period
It shall be the obligation of the Authority to ensure that the following are made
available to the Concessionaire or duly executed by the Authority:
(i)
(ii)
(iii)
All litigation involving the Site, prior to Compliance Date and wherein the actions
have been filed against the Authority, the same shall be contested and
conducted solely by the Authority. The Concessionaire shall be in no way held
responsible or liable as a reason thereof for such litigation involving the Project.
The Authority shall indemnify the Concessionaire and shall hold it free of any
claim or consequent cost that may arise as a result of any such litigation;
The Authority shall bear and be responsible for all costs, expense or charges
incurred in making available the Site in accordance with Article 4, including any
compensation required to be paid for acquisition of such Site; and,
The Authority shall ensure that from the date of the notice to commence and till
the expiry of the Concession Period, the Concessionaire has access to the Site for
the purpose of carrying out the Concessionaire's obligations under this
Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 103 of 195
ARTICLE 7:
OBLIGATIONS OF THE CONCESSIONAIRE DURING THE
IMPLEMENTATION PERIOD
7.1
Obligations of the Concessionaire during the Implementation Period
The Concessionaire shall observe, undertake, comply with and perform, in addition to and
not in derogation of its obligations elsewhere set out in this Agreement, the following:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
Comply with and observe at all times the requirements of all Clearances,
approvals and Applicable Laws in the performance of its obligations under this
Agreement;
Submit 5 (five) copies each of the Project Report of the Project containing the
detailed and accurate visual representation of the internal and external facilities
of the Project to the Authority; along with the Financial Model and the calculation
of annual incremental premium;
Carry out its duties, responsibilities and obligations strictly in accordance with the
Project Report as approved by the Engineer –in – charge, the terms and
conditions of this Agreement and the schedules thereto, and all duties,
responsibilities and obligations not mentioned in this Agreement but which may
be inferred to be necessary for safe, reliable and efficient implementation and
operation of the Project in accordance with Applicable Laws, Clearances and / or
Good Industry Practice;
Undertake to achieve Time for Completion of Implementation not later than the
Implementation Period, provided that the Concessionaire shall not be in breach
of the terms and conditions of this Agreement, unless any non – fulfilment or the
delay in fulfilment of its obligation are caused by (i) the occurrence of an event
of Force Majeure or (ii) an event of default of the Authority;
Be responsible for all liabilities arising out of design, construction, development,
furnishing, implementation, operation and maintenance of the Project. The
Concessionaire shall plan, organise and execute its duties, obligations and
responsibilities under this Agreement so that there is least disruption to the
traffic movement on adjoining roads and minimal inconvenience to the
neighbouring residents and pedestrians. The Authority and shall assist the
Concessionaire in all respects with reference to such duties, obligations and
responsibilities, but the provision of assistance or denial thereof shall not release
the Concessionaire from its obligations under this Agreement;
To be responsible for safety, soundness and durability of the Project, including
other services forming part thereof and their compliance with the Applicable
Laws and Clearances.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 104 of 195
(vii)
To ensure that no damage is caused to the existing roads, drainages, public
utilities etc. through any activities of the Concessionaire and / or any of its
agents, representatives, employees etc.;
(viii) To install full safety measures which aim at reduction in injuries, loss of human
life and damage to property resulting from accidents on account of the Project,
the Site and / or the Assets, irrespective of the person(s) at fault at the Site
during the Implementation Period and post the Implementation Period;
(ix)
(x)
(xi)
The Project shall not obstruct traffic, pedestrian movement, and should not
cause any difficulties to smooth functioning and operability of the roads in the
area;
To ensure that the Project construction should not create unsecure public spaces
in or around it causing safety concerns to the adjoining areas, for any reason
whatsoever;
To provide all assistance to the expert/ Independent Auditor/ arbitrator as
appointed under this Agreement, as may be required for the performance of
their duties and services in accordance with the terms and conditions of this
Agreement and Applicable Laws;
(xii)
To
duly
supervise,
monitor
and
control
the
activities
of
its
sub
–
contractors/labourers, employees, agents and employees under their respective
Project Agreements as may be necessary and subject to the written consent of
the Authority;
(xiii) To effect and maintain, or cause to be effected and maintained, at its own
expense, insurance policies as may be required to be maintained by the
Concessionaire, under the terms and conditions of this Agreement, under
Applicable Laws and/ or such insurances that are necessary or desirable in
accordance with Good Industry Practice;
(xiv) To take all reasonable precautions for the prevention of accidents on or about
the Project and make provision for all reasonable assistance and emergency first
aid and medical aid to accident victims in the Project, at all times;
(xv)
To ensure the due completion of all duties, obligations and responsibilities of the
Concessionaire as per the duly approved Project Report;
(xvi) Labour: The Concessionaire shall make its own arrangements for the
engagement of all its staff and labour, local or otherwise, The Concessionaire
shall be solely responsible for the liability, cost, and responsibility for all the laws
relating to labour employed by Concessionaire and for their conditions under this
Article. However, it is being clarified here that the Concessionaire shall be under
no obligation to recruit any or part of the staff and labour from amongst persons
in the service of the Authority;
(xvii) Shall be solely and primarily responsible to Authority for observance of all the
provisions of this Agreement on behalf of the Concessionaire, its employees and
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 105 of 195
representatives or any person acting under or for and on behalf of the
Concessionaire as fully as if they were the acts or defaults of the Concessionaire;
(xviii) Shall be liable for and shall indemnify, protect, defend and hold harmless
Authority, Authority’s officers, employees and agents from and against any and
all demands, claims, suits and causes of action and any and all liability, costs,
expenses, settlements and judgements arising out of the failure of the
Concessionaire to discharge its obligations under this Agreement and to comply
with the provisions of Applicable Laws and Clearances;
(xix) The Concessionaire shall acknowledge and recognise that time is of the essence
of this Agreement and that the performance of its obligations shall be construed
accordingly;
(xx)
The Concessionaire shall comply with suggestion, corrections, quarries of audit
and inspection as per Article 19 of this Agreement;
(xxi) The Concessionaire shall make reasonable efforts to maintain harmony and good
industrial relations among the personnel employed by it in connection with the
performance of its obligations under this Agreement;
(xxii) The Concessionaire shall ensure and procure that the Concessionaire and its
agents, representatives, personnel and labour shall comply with all Clearances
and Applicable Laws in the performance by them of any of the Concessionaire’s
obligations under this Agreement;
(xxiii) The Concessionaire shall not do or omit to do any act, deed or thing which may
in any manner be in violation of any of the provisions of this Agreement;
(xxiv) The Concessionaire shall ensure that the personnel engaged by it in the
performance of its obligations under this Agreement are at all times properly
trained for their respective functions;
(xxv) The Concessionaire should provide the copies of the Maintenance Manual in
accordance with Article 11 of the Agreement and shall comply with the
comments and / or instructions of the Authority with regards to the Provisional
Maintenance Manual as provided by the Authority;
(xxvi) The Concessionaire shall have the obligation and the Authority shall have the
right to appoint an expert, at its sole discretion, at any time during the
subsistence of this Agreement for the purposes of inspection and monitoring of
the Project, the Site and / or the Assets. The expert, as appointed by the
Authority, shall be responsible to check, verify and authenticate the progress by
the Concessionaire on the Project and the performance of the duties, obligations
and responsibilities of the Concessionaire under this Agreement;
(xxvii) The Concessionaire shall have the obligation and the Authority shall have right to
conduct the inspection of the Project, the Site and / or the Assets, for the
purpose of audit, once in every period of 180 (one hundred and eighty) days
from the Compliance Date, in accordance with the requirements of Article 19 of
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 106 of 195
this Agreement. It is expressly agreed that the Concessionaire shall, at all times,
be responsible and liable for all its obligations under this Agreement
notwithstanding anything contained in the Project Agreements or any other
agreement, and no default under any Project Agreement or agreement shall
excuse the Concessionaire from its obligations or liability hereunder;
7.2
Minimum Equity Requirements
(i)
The minimum shareholding of the Joint Venture (JV) Members (“Minimum
Equity Requirements”), in case of Joint Venture (JV), or Selected Bidder in the
Equity of the Concessionaire shall be as follows:
1.
2.
The Lead Member/Selected Bidder shall hold fifty – one (51%) percent Equity
in the Concessionaire till the expiry of two (2) years from the date of issuance
of the Implementation Completion Certificate; and,
The Lead Member/Selected Bidder shall continuously hold at least, twenty –
six (26%) percent Equity of the Concessionaire for the entire Concession
Period.
(ii)
(iii)
At no stage shall any change in the Equity of the Concessionaire be made by the
Joint Venture (JV) Members or by any of the Associates without obtaining prior
written approval from Authority. On an application made for the purpose, the
Authority may permit such change of Equity of the Concessionaire, provided that
the Authority is satisfied that the proposed changes shall be in the interest of the
implementation of the Project in future and would not be detrimental to any of
the rights and / or benefits of the Authority. For the avoidance of any doubt, it is
hereby clarified that no such change in the Equity of the Concessionaire shall be
permitted by Authority which would directly or indirectly result in non –
compliance with the Minimum Equity Requirements.
In case any such change in composition of Joint Venture (JV) Members has been
agreed upon, the modified Joint Venture (JV) Members would be required to
submit a revised Joint Venture Agreement to the Authority, prior to such change.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 107 of 195
ARTICLE 8:
GENERAL OBLIGATIONS IN RELATION TO THE PROJECT AGREEMENTS
8.1.
8.2.
8.3.
The Concessionaire shall procure that each of the Project Agreements contains
provisions that entitle the Authority to step into such agreement, in its sole discretion,
in substitution of the Concessionaire in the event of termination or any Concessionaire
Event of Default (the “Covenant”). For the avoidance of doubt, it is expressly agreed
that in the event the Authority does not exercise such rights of substitution within a
period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements
shall be deemed to cease to be in force and effect on the Transfer Date without any
liability whatsoever on the Authority and the Covenant shall expressly provide for such
eventuality. The Concessionaire expressly agrees to include the Covenant in all its
Project Agreements and undertakes that it shall, in respect of each of the Project
Agreements, procure and deliver to the Authority an acknowledgment and undertaking,
in a form acceptable to the Authority, from the counter party(s) of each of the Project
Agreements, where under such counter party(s) shall acknowledge and accept the
Covenant and undertake to be bound by the same and not to seek any relief or remedy
whatsoever from the Authority in any event of termination or Concessionaire Event of
Default.
The Concessionaire shall submit to the Authority the drafts of all Project Agreements or
any amendments or replacements thereto for its review and comments, prior to the
execution of such Project Agreements and the Authority shall have the right but not the
obligation to undertake such review and provide its comments, if any, to the
Concessionaire within 30 (thirty) days of the receipt of such drafts. The Concessionaire
shall not enter into any Project Agreements without obtaining the prior written consent
of the Authority. No review and / or observation of the Authority and / or its failure to
review and / or convey its observations on any document shall relieve the
Concessionaire of its obligations and liabilities under this Agreement in any manner nor
shall the Authority be liable for the same in any manner whatsoever. The
Concessionaire shall procure and ensure that all Project Agreements shall be subject to
the terms and conditions of this Agreement and the term of such Project Agreements
shall be co – terminus with this Agreement. The Concessionaire shall procure and
ensure that with regards to such Project Agreements in the event of any breach of the
terms of this Agreement, Applicable Laws, Clearance and / or Good Industry Practice,
the Concessionaire shall have the right to terminate such Project Agreement, in
accordance with the instructions of the Authority, which shall be final and binding on
the Concessionaire.
The Concessionaire shall obtain prior written consent of the Authority, for entering into
any Project Agreements with Third Parties and / or entering into any arrangement for
sub – lease, sub – license, assignment or in any manner create an Encumbrance on the
Project, the Site and / or the Assets in the prescribed form as mentioned in Schedule
VIII of the Agreement. The Concessionaire shall provide such information as may be
requested by the Authority in this regard including without limitation information
relating to the Third Party, the portion of the Project that is the subject matter of such
Project Agreement and / or the proposed use of the portion of the Project that is the
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 108 of 195
subject matter of such Project Agreement, within a period of 7 (seven) days from the
date of such request by the Authority. The consent to be provided by the Authority
shall not be unreasonably withheld, otherwise than for the reason that the use of such
portion of the Project, the Site and / or the Assets shall be made and / or potentially, in
the opinion of the Authority, could be made for any restricted activities and / or in
violation of the terms and conditions of this Agreement and / or in violation of
Applicable Laws. The decision of the Authority is final and binding on the
Concessionaire.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
A Chief Engineer, PW Region, Pune. Chairman
B Superintending Engineer PW Circle, Satara. Member
C Dy. Chief Architect, Pune. Member
D Executive Engineer PW Division, Satara. Member
E Dy. Engineer PW sub – division, Koregaon. Member, Secretary
F Other technical expert or financial expert as required. Member
G Duly authorized representative of the Concessionaire Member
Page 109 of 195
ARTICLE 9:
FORMATION AND MEETINGS OF THE COMMITTEE
9.1.
Formation and Meetings of the Committee
(i)
(ii)
(iii)
(iv)
A committee shall be formed for taking decisions on certain matters relating to
the Project. The committee shall be constituted as follows: The Committee shall at all times comprise of seven (7) members, out of which,
the Concessionaire shall be entitled to appoint one (1) member and, the
Authority shall be entitled to appoint six (6) members, as set out in this Article of
this Agreement. Each Party shall be entitled to remove and / or replace its
representative member on the Committee which has been appointed by such
Party including the representative members as set out above in the table. The
Chief Engineer, Public Works Region , Pune.
shall act as the chairman of the Committee.
The Committee shall have the functions as set out under this Article of the
Agreement including of deliberation, analysis, consideration and making
recommendations in relation to the said matters. In this regard, the Committee
shall primarily rely on information and documents provided by the
Concessionaire. The recommendations of the Committee shall be final and
binding on the Concessionaire.
Each of the Parties shall provide all necessary support and co – operation, as
may be required by the Committee, to carry out its functions. Each Party shall
take all practicable steps and shall do all such other acts, deeds and things as
may be necessary or desirable including, without limitation, obtaining internal
and external approvals and authorisations, to ensure that the recommendations
of the Committee are complied with and implemented in a timely manner. The
Concessionaire shall ensure and direct its representative directors on the Board
of the Concessionaire to act in the manner to ensure implementation of the
recommendations of the Committee. The meetings of the Committee shall be
convened and held as may be required.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 110 of 195
(v)
(vi)
(vii)
A meeting of the Committee can be convened by any member by giving a
written notice of fourteen (14) days to each of the members of the Committee.
Each notice of meeting shall specify the time, date and venue of the meeting and
be accompanied by an agenda setting out, in reasonable detail, the items of
business proposed to be transacted thereat together with necessary background
and other information and any relevant papers. A notice of meeting may be sent
by hard copy courier, fax or email PDF.
Participation in the proceedings of the Committee may be by either of the
following methods: (i) physical presence; (ii) telephonic participation; (iii) video
or web conferencing. No meeting of the Committee shall be held unless at least
two (2) representative members of the Authority and at least one (1)
representative member of the Concessionaire are present.
The decisions of the Committee including for instructions, comments and / or
recommendations to the Concessionaire, shall be taken by simple majority of its
members present and voting, provided that no decision shall be taken without
approval of two (2) representative members of the Authority.
(viii) The proceedings and minutes of a validly held meeting of the Committee shall be
recorded in writing and circulated to each Party with initials of the Chairman.
(ix)
This Committee shall deliberate and take decisions on the following matters:
1.
2.
3.
The audit and inspection as per Article 19 of this Agreement.
Finalisation of the Total Project Cost for the purpose of certificate to be
issued by Authority as per Schedule – VI of this Agreement.
Any other matter and / or item which may be decided to be delegated to
the Committee, from time to time, by the Authority.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 111 of 195
ARTICLE 10:
COMPLETION OF IMPLEMENTATION
10.1.
Issuance of the Implementation Completion Certificate
(i)
(ii)
The duties, obligations and responsibilities of the Concessionaire during the
Implementation Period under this Agreement shall not be considered to be
completed until the Implementation Completion Certificate, stating that the
Concessionaire has completed its duties, obligations and responsibilities during
the Implementation Period as laid down under this Agreement, has been signed
and delivered by the Authority.
The Concessionaire shall submit all reports, documents, memoranda and
information, as may be requested by the Authority, so as to sufficiently enable
the Authority to provide the Implementation Completion Certificate. The
Implementation Completion Certificate may be given by the Authority within 20
(twenty) days after the completion of all the following steps, to the satisfaction
of the Authority:
1.
2.
3.
4.
The Concessionaire has provided the Project Report and the Project Report
has been approved by the Authority;
The Concessionaire has provided a detailed inventory of the Assets brought in
by the Concessionaire during the Implementation Period;
The Concessionaire has completed and tested the safety, durability and
operability of all the works as required to be completed by the
Concessionaire, as per Applicable Laws with due Clearances from Competent
Authorities, as specified by the Authority , external expert appointed by the
Authority; and,
The Concessionaire has duly completed its duties, responsibilities and
obligations as required to be completed by the Concessionaire, during the
Implementation Period, to the satisfaction of the Authority including without
limitation the performance of the duties, obligations and responsibilities of
the Concessionaire under Article 7 of this Agreement to the satisfaction of
the Authority.
(iii)
In pursuance to the issue of the Implementation Completion Certificate, the
Concessionaire shall comply with all its duties, responsibilities and obligations,
under the provisions of the Agreement, under the Clearances, under Applicable
Law and as per Good Industry Practice, as required to be met before and after
the issuance of the Implementation Completion Certificate. Notwithstanding
anything to the contrary, as stated under this Agreement, the decision of the
Authority whether or not to issue the Implementation Completion Certificate shall
be final and binding on the Concessionaire.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 112 of 195
(iv)
The Implementation Completion Certificate shall be given in format specified in
Schedule –VI of this Agreement.
10.2.
Implementation Completion Certificate not a Cessation of Liability
The issuance of the Implementation Completion Certificate under this Article shall not in
any way:
(i)
(ii)
(iii)
(iv)
Alter, vary and / or revise the duties, liabilities, obligations and responsibilities of
the Concessionaire, without the prior written consent of the Authority;
Constitute as a waiver of unfulfilled duties, obligations and responsibilities of the
Concessionaire, without the prior written consent of the Authority;
Bar remedy and rectification of defects and deficiencies in quality and / or
performance; and,
Constitute an acceptance of the performance of the obligations, duties and
responsibilities of the Concessionaire, by the Authority.
10.3.
Provisional Implementation Completion Certificate
(i)
(ii)
The Authority may at its sole discretion, issue a provisional Implementation
Completion Certificate (“Provisional Implementation Completion
Certificate”) to the Concessionaire, in the form and format as set out in
Schedule – XI of this Agreement, and submit an inspection report (the “Punch
List”) for the Project, the Site and / or the Assets specifying the defects and
deficiencies that shall be rectified by the Concessionaire and the time period
within which such items shall be rectified, in conformity with the terms and
conditions of the Agreement, the Specifications, Applicable Laws, Clearances and
Good Industry Practice. Notwithstanding anything to the contrary, as stated
under this Agreement, the Concessionaire shall, no later than 45 (forty - five)
days from the date of issuance of the Provisional Implementation Completion
Certificate, rectify each item in the Punch List and notify the Authority of the
same. The Authority may, in its discretion, inspect the Project, the Assets and /
or the Site and in the event that any defect or deficiency specified in the Punch
List shall have remained without rectification thereof, the Concessionaire shall
pay to the Authority as liquidated damages, 2% (two per cent) of the
Performance Security for each day of delay until all items of the Punch List are
rectified.
The Authority shall also have the right at any time, after the issuance of a
Provisional Implementation Completion Certificate, to revoke such Provisional
Implementation Completion Certificate unilaterally, if the Concessionaire fails to
rectify all defects and / or deficiencies in the Project, the Site and / or the Assets
to its satisfaction and / or fails to remedy all items listed in the Punch List within
such period as provided under this Article of this Agreement. The Provisional
Implementation Completion Certificate shall be deemed to have lapsed on and
from the date of such revocation by notice, in writing, by the Authority and the
Concessionaire shall immediately, cease and desist from carrying on any
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 113 of 195
activities in relation to the Project, which can be carried out, only during the
Operations and Maintenance Period. In the event, that the Concessionaire does
not cease and desist from carrying on such activities, in a timely manner, the
Concessionaire shall be liable to pay to the Authority as liquidated damages, 2%
(two percent) of the Performance Security for each day of delay till the date of
compliance to the satisfaction of the Authority and such non – compliance shall
amount to a Concessionaire Event of Default. The decisions of the Authority,
under this Article of the Agreement, shall be final and binding on the
Concessionaire.
(iii)
The issuance of the Implementation Completion Certificate and / or the
Provisional Implementation Certificate shall be a milestone for the
commencement of the Operations and Maintenance Period of the Project. For
the avoidance of any doubt, it is hereby clarified that in the event, that the
Concessionaire fails to comply with its duties, obligations and responsibilities,
under this Article of the Agreement, after the issuance of the Provisional
Implementation Certificate, the Operations and Maintenance Period for the
Project shall immediately come to a standstill and shall cease to be in force and
effect, from the date of revocation of the Provisional Implementation Certificate
by the Authority and the Concessionaire shall have the obligation to immediately
cease and desist from carrying on any activities in relation to the Project, which
can be carried out, only during the Operations and Maintenance Period.
10.4.
General Obligations regarding rectification
If the Concessionaire is obliged to carry out adjustments, repairs, replacements or
modifications after the issuance of the Implementation Completion Certificate in order to
fulfil its duties, obligations and responsibilities under this Agreement, at his own cost
and expense, the Authority shall permit the Concessionaire to carry out all such
adjustments, repairs, replacements, rectifications and / or modifications as may be
necessary. If the adjustment, repair, replacement or modification cannot be made without
stopping the normal operation of the Project during the Operations and Maintenance
Period, then such request shall only be granted if the Concessionaire's request is
reasonable under all the circumstances, having regard to the Authority’s obligations to
keep the operation of the Project open during all hours of the day. The decision of the
Authority shall be final and binding on the Concessionaire.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 114 of 195
ARTICLE 11:
OPERATIONS AND MAINTENANCE PERIOD
11.1.
11.2.
Commencement and Duration of the Operations and Maintenance Period
The Operations and Maintenance Period of the Project shall commence from the date
of issuance of Implementation Completion Certificate and terminate at the end of the
Concession Period.
Obligations of the Concessionaire during the Operations and Maintenance
Period
(i)
(ii)
(iii)
The Concessionaire shall during the Operations and Maintenance Period, be
responsible for the operation of the Jan Suvidha Kendra and the Project
including without limitation the regular maintenance, operation and cleaning of
the Project, the Site and / or the Assets and its surrounding areas, functioning of
all user amenities, provisions of dedicated personnel, maintenance, supervision
and availability of basic infrastructure requirements such as electricity, proper
drainage, sewage, waste removal, in accordance with the requirements of this
Agreement, Applicable Laws, Clearances and Good Industry Practice.
The Concessionaire shall prepare a repair and maintenance manual (the
“Maintenance Manual”) for the predictive, preventive and curative maintenance
of Project and / or the Assets in conformity with Good Industry Practice. The
Concessionaire shall provide five (5) copies of a provisional maintenance manual
(the “Provisional Maintenance Manual”) to the Authority no later than the sixty
(60) days prior to the Time for Completion of Implementation. The Authority may
review the Provisional Maintenance Manual and convey its comments to the
Concessionaire within a period of 30 (thirty) days from the date of receipt thereof.
The comments and / or the instructions shall be binding on the Concessionaire and
shall be compulsorily complied with. The Concessionaire shall revise the Provisional
Maintenance Manual, as may be necessary, and provide five (5) copies of the
Maintenance Manual no later than the fifteen (15) days from the Implementation
Completion Certificate. The Maintenance Manual shall be revised and updated once
every 3 (three) years and the provisions of this Article shall apply, mutatis mutandis,
to such revision. For the avoidance of doubt, the Parties expressly agree that until
the Maintenance Manual is provided hereunder, the Provisional Maintenance Manual
shall apply. Copies of maintenance manual shall be supplied in hard and soft form.
In the event the Concessionaire does not maintain and / or repair the Project and /
or the Site in conformity with the provisions of this Agreement and the Maintenance
Manual, and fails to commence remedial works within 15 (fifteen) days of receipt of
a notice in this regard from the Authority, the Authority shall, without prejudice to its
rights under this Agreement including termination thereof, be entitled to undertake
such remedial measures at the risk and cost of the Concessionaire, and to recover its
cost from the Concessionaire. In addition to recovery of the aforesaid cost, a sum
equal to 20% (twenty per cent) of such cost as liquidated damages shall be paid by
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 115 of 195
the Concessionaire to the Authority which shall be genuine pre – estimate of the loss
caused to the Authority.
(iv)
(v)
(vi)
(vii)
If in the reasonable opinion of the Authority, the Concessionaire is in breach of its
obligations under this Agreement relating to its maintenance obligations, and such
breach is causing or is likely to cause hardship to the Authority, the Authority may,
without prejudice to any of its rights under this Agreement including termination
thereof, by notice, require the Concessionaire to take reasonable measures
immediately for rectifying or removing such hardship or unsafe condition, as the
case may be.
During the Operations and Maintenance Period, the Concessionaire shall, no later
than 5 (seven) days after the end of each month, furnish to the Authority a monthly
report stating in reasonable details the frequency of the maintenance services
performed by the Concessionaire and the defects and deficiencies that required
rectification. The report shall also include the maintenance obligations as set out in
this Article and the Maintenance Manual. The Concessionaire shall promptly give
such other relevant information as may be required by the Authority.
The Authority shall be entitled to inspect the Project and / or the Site, as the case
may be, for evaluating the compliance with the maintenance obligations as set out in
this Article. It shall make a report of such inspection (the “Maintenance
Inspection Report”) stating in reasonable detail the defects or deficiencies, if any,
with particular reference to such maintenance obligations and notify the
Concessionaire of the same for taking adequate remedial measures in compliance
with the comments and / or instructions of the Authority. The Concessionaire shall
repair or rectify the defects or deficiencies, if any, set forth in the Maintenance
Inspection Report and furnish a report in respect thereof to the Authority within 5
(five) days of receiving the Maintenance Inspection Report.
The duties, responsibilities and obligations of the Concessionaire more
specifically includes without limitation, the following:
1.
2.
The Concessionaire shall be responsible, at his own cost and expense, for
all the maintenance and repairs of the Jan Suvidha Kendra, the Project,
the Site and the Assets. The Concessionaire shall also carry out
rectification of any defects and / or deficiencies in the Jan Suvidha Kendra,
the Project, the Site and / or the Assets during the Operations and
Maintenance Period.
Water supply: The Concessionaire shall ensure availability at all times of
adequate water for drinking purposes, general cleanliness of the Jan
Suvidha Kendra, the Project, the Site and the Assets for its Users. The
supply shall be arranged by Concessionaire. Laying of water line/
connection / payment of usage charges shall be the responsibility of the
Concessionaire. The Concessionaire shall install a water purifier including
RO unit at the drinking point location. The facilities for dispensation of
clean drinking water shall be regularly maintained and cleaned during the
Operations and Maintenance Period, at the sole cost and expense of the
Authority.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 116 of 195
3.
4.
5.
6.
Electricity supply: The Concessionaire shall ensure adequate electricity
supply for proper lighting facilities inside the Jan Suvidha Kendra and the
Project, in accordance with Good Industry Practice. The supply shall be
arranged and paid for by the Concessionaire. Laying of electric cables /
connection / payment of usage charges shall be the responsibility of the
Concessionaire.
Sewage connections: The Concessionaire shall arrange the sewage
connection for Jan Suvidha Kendra and the Project and lay the line at his
own cost for sewage connection.
Landscaping: The Concessionaire shall put plants in and around each
Jan Suvidha Kendra and the Project where space is available as per the
approval of the Authority and maintain the same in good condition at all
times.
Cleaning of Jan Suvidha Kendra and Information Panels: The
Concessionaire shall ensure maintenance and cleaning of the Jan Suvidha
Kendra, the Project, the Site and the Assets and the information panels
and / or displays on the Site, as per the cleaning schedule provided in the
Schedule A. Dedicated cleaning staff shall be provided by the
Concessionaire for the Project. The Concessionaire will ensure that quick
and timely cleaning is carried out by the attendants of the toilet after each
use. The Concessionaire shall ensure that the toilet is properly cleaned
regularly and maintained at all times, in hygienic conditions. The
consumables and other articles required for cleaning and operation of
toilets shall be procured at the sole cost and expense of the
Concessionaire.
7.
8.
9.
Waste Disposal: The Concessionaire shall install litterbins, dustbins and
other waste disposal mechanisms as specified near the Jan Suvidha
Kendra and the Project and disposal of the collected waste, on a timely
basis, shall be the responsibility of the Concessionaire. The solid waste
(including menstrual waste) collected in the toilets or within areas around
the Jan Suvidha Kendra and the Project shall be regularly removed and
disposed in proper manner as per requirements of the Agreement and
Good Industry Practice.
The Concessionaire shall install bio degradation units for disposal of waste
from the Jan Suvidha Kendra and the Project.
Safety and Security: The duty, obligation and responsibility to maintain
the safety and security of the Jan Suvidha Kendra and the Project rests
with the Concessionaire. The Concessionaire shall ensure maintenance of
lighting arrangements to ensure proper illumination of the Jan Suvidha
Kendra including without limitation all the toilet areas as well as various
signboards and display boards. The Concessionaire shall deploy adequate
and well – trained staff and personnel so that minimum one (1) personnel
is available during operational hours for each toilet who shall be
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 117 of 195
responsible for security and safety of toilet, maintenance of basic sanitary
condition inside and around the toilet, regular removal of waste,
maintenance of suggestion booklet, reporting of problems, if any, clearing
of choking (if any) etc. It is suggested that a female attendant is available
during the working hours so as to look after the female section of Jan
Suvidha Kendra and the Project. The staff and the personnel deployed by
the Concessionaire shall be in proper uniform and should be adequately
trained by the Concessionaire regarding his duties as well as for dealing
with the Users.
10.
11.
Maintenance: It will include routine and periodic maintenance works in
the Jan Suvidha Kendra and the Project but shall not be limited to the
following: civil, electrical and mechanical works for the Jan Suvidha
Kendra and the Project, equipment maintenance and servicing. Any
unserviceable fittings or fixtures shall be replaced by the Concessionaire
within 24 hours.
Complaints Register: The Concessionaire shall keep a register (the
“Complaint Register”) in the Project for recording of complaints by
Users. The Complaint Register shall be securely bound and each page
thereof shall be duly numbered. It shall have appropriate columns
including the complaint number, date, substance of the complaint and the
action taken by the Concessionaire. The Concessionaire shall inspect the
Complaint Register before undertaking any maintenance, as the case may
be, and take prompt and reasonable action for redressal of each
complaint. The action taken shall be briefly recorded by the
Concessionaire in the Complaint Register. No later than 2 (two) days from
the end of each week, the Concessionaire shall send to the Authority a
true photocopy each or a soft copy thereof, as the case may be, of all the
pages of the Complaint Register on which any entry has been recorded
during the course of the preceding week, and upon perusal thereof, the
Authority may, in its discretion, advise the Company to take such further
action as the Authority may deem appropriate. The Concessionaire shall
consider such advice and inform the Authority of the remedial action taken
by the Concessionaire. If in the opinion of the Authority, the
Concessionaire has failed to rectify the defects and / or deficiencies and /
or address the grievances of the Users as set out in the Complaints
Register in a satisfactory manner, at any time, the Authority may deliver a
notice in writing to the Concessionaire requiring it to immediately rectify
such defect and / or address such grievances in accordance with the
instructions of the Authority. If the Concessionaire fails to rectify the
defects and / or deficiencies and / or address the grievances of the Users,
then the Authority shall be entitled, in its sole discretion, to take over the
operations of the Project, the Site and the Assets and all the rights and
obligations of the Concessionaire with respect to the Project, the Site and
the Assets to the extent permitted under the Project Agreements, in
substitution of the Concessionaire and that the Concessionaire shall
facilitate the same to the extent permissible under the Project Agreements
and Applicable Law. The Concessionaire undertakes to be bound by the
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 118 of 195
same and not to seek any relief and / or remedy whatsoever from the
Authority upon the exercise of the aforesaid right by the Authority.
12.
13.
14.
15.
16.
17.
Recycling facility: The Concessionaire shall ensure the proper working
and maintenance of water / solid waste recycling facility so that it is
operational at all times.
Display of Information: The Project shall clearly and legibly display all
information relating to the facilities at the Project and the Commercial
Charges that may be charged from Users, at a part of the Project, which
can be accessed by all Users without inconvenience in accordance with
Applicable Laws. The Concessionaire hereby agrees that all applicable
Commercial Charges that are to be levied, shall be duly displayed at all
times at the Project and the Concessionaire shall not charge and / or levy
any Commercial Charges, that are not duly displayed in accordance with
the requirements of this Agreement. The display shall be properly and
regularly maintained to ensure clear visibility and proper aesthetics. The
Concessionaire shall also have the duty, obligation and responsibility to
display such information as may be prescribed by the Authority from time
to time. In case of any damage to the display and / or misrepresentation
of the information as displayed therein, the Concessionaire shall
immediately repair, replace and / or rectify it.
Servicing of equipment and installations: The Concessionaire shall
have the duty, obligation and responsibility to maintain the installations,
equipment and Assets including without limitation the fire – fighting
equipment, inverters, water recycling plant, RO water purifier, vending
machines, etc. installed in the Project and shall regularly service the
installations, equipment and Assets so as to maintain them in accordance
with the Specifications and Good Industry Practice at all times during the
subsistence of the Agreement.
Operational hours: All toilets shall be kept open and operational for all
24 hours of each day except in the event of occurrence of Force Majeure
in accordance with the terms of this Agreement.
Concessionaire to keep the Project clean: The Concessionaire shall
take all necessary care to keep the premises of the Jan Suvidha Kendra
and the Project, in a neat and clean and in sanitary conditions including
without limitation timely and proper cleaning of all splashes and droppings
from white washing, colour washing, painting etc., on walls, floor,
windows, etc. and the surface, consistent with the environment and
cleanliness of a world – class facility and in accordance with Good Industry
Practice.
Special maintenance of the Project: The Concessionaire shall
maintain the Project and the Site, once every three years which includes
external and internal painting, repairs to damaged doors, windows, repairs
to fabrications, leakages and other incidental things as reported by the
Authority.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 119 of 195
18.
19.
20.
Labour: The Concessionaire shall employ employees, personnel, staff,
and labour only after proper police verification is obtained from concerned
police authority. The Concessionaire shall comply with all Applicable Law,
Clearances and Good Industry Practice in this regard.
CCTV: The Concessionaire shall compulsorily install enough CCTV cameras
at the project and give access for online surveillance to authority.
First aid: There must be at least 1 first aid kit at the project which shall
be compulsorily kept in good conditions with all necessary medicines.
21.
No
–
Objection
Certificate
from
Fire
Department: The
Concessionaire must comply with guidelines and norms related to fire
safety and shall obtain take a no objection certificate along with
permission from fire department.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 120 of 195
ARTICLE 12:
AGREEMENT COMPLETION CERTIFICATE
12.1
12.2
12.3
On the Transfer Date, the Authority shall issue the Agreement Completion Certificate,
which shall conclude the Concessionaire's liability under this Agreement. This certificate
shall be issued after the Concessionaire submits to Authority, a request for issue of such
certificate. The request of the Concessionaire to the Authority shall include a detailed
survey of the Project, the Site and the Assets. The Concessionaire shall prepare a
detailed inventory of the Assets (including all movable and immovable assets, whether
provided by the Authority or brought in by the Concessionaire) present within the Jan
Suvidha Kendra. The detailed inventory shall be submitted to the Authority along with
the request for grant of the Agreement Completion Date.
The Performance Security furnished by the Concessionaire shall be released only
after expiry of 30 (thirty) days from date of the issuance of the Agreement
Completion Certificate.
The format for issuance of the Agreement Completion Certificate is attached as
Schedule – IX of this Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 121 of 195
ARTICLE 13:
REPRESENTATIONS AND WARRANTIES
13.1.
Representations and Warranties of the Authority
The Authority represents and warrants to the Concessionaire that:
(i)
(ii)
(iii)
(iv)
(v)
The Authority has full power and authority to execute, deliver and perform its
obligations under this Agreement and to carry out the transactions contemplated
hereby;
The Authority shall take all necessary action in accordance with Applicable Laws to
authorize the execution, delivery and performance of this Agreement;
This Agreement constitutes a legal, valid and binding obligation enforceable against
the Authority in accordance with the terms hereof;
The Authority is subject to civil and commercial laws of India with respect to this
Concession and it hereby expressly and irrevocably waives any sovereign immunity
in any jurisdiction in regard to matters set forth in this Agreement; and,
The Authority has the financial standing and capacity to perform its obligations
under the Agreement
13.2.
Representations and Warranties of the Concessionaire
The Concessionaire represents and warrants to the Authority that:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
It is duly organised, validly existing and in good standing under the laws of the
jurisdiction of its incorporation;
It has full power and authority to execute, deliver and perform its obligations under
this Agreement and to carry out the transactions contemplated hereby;
It has taken all necessary corporate and other actions under Applicable Laws and its
constitutional documents, including its memorandum of association and articles of
association, to authorise the execution, delivery and performance of this Agreement;
It has the financial standing and capacity to undertake the Project;
This Agreement constitutes its legal, valid and binding obligation enforceable against
it in accordance with the terms hereof;
It is subject to civil and commercial laws of India with respect to this Agreement and
it hereby expressly and irrevocably waives any immunity in any jurisdiction in respect
thereof;
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 122 of 195
(vii)
(viii)
(ix)
(x)
(xi)
(xii)
(xiii)
All the information furnished in the Concessionaire’s bid is, and shall be, true and
correct as on the Proposal Acceptance Date and throughout the Concession Period/
subsistence of the Agreement and the Balance Sheet and Profit and Loss Account of
the Concessionaire for each of the Financial Years after the Proposal Acceptance
Date furnished to the Authority shall give true and fair view of the affairs of the
Concessionaire. If in case any false or misleading information, as furnished by the
Concessionaire (as a bidder) in its bid, is found at a later stage after the signing of
the Agreement, it shall entitle Authority to terminate the Agreement between the
Parties. The costs and risks for such termination shall be entirely borne by the
Concessionaire;
It shall furnish a copy of the audited accounts of the Concessionaire within 60 (sixty)
days of the close of each Financial Year after the Proposal Acceptance Date and any
material change subsequent to the date of such accounts shall be notified to the
Authority by the Concessionaire within 15 (fifteen) days of its occurrence and
warrants that the accounts and the information furnished as aforesaid shall be true
and correct;
The execution, delivery and performance of this Agreement will not conflict with,
result in the breach of, constitute a default under or accelerate performance required
by any of the terms of the Concessionaire’s Memorandum of Association and Articles
of Association or any Applicable Laws or any covenant, agreement, understanding,
decree or order to which it is a party or by which it or any of its properties or assets
is bound or affected;
The Concessionaire has no knowledge of any violation or default with respect to any
order, writ, injunction or any decree of any court or any legally binding order of any
Competent Authority which may result in any Material Adverse Effect or impairment
of the Concessionaire’s ability to perform its obligations and duties under this
Agreement;
The Concessionaire has complied with all Applicable Laws and has not been subject
to any fines, penalties, injunctive relief or any other civil or criminal liabilities which in
the aggregate have or may have Material Adverse Effect on its financial condition or
its ability to perform its obligations and duties under this Agreement;
The aggregate equity share holding of the Joint Venture (JV) Members and their
Associates (in case of a Joint Venture (JV)) or equity share holding of the Associates
(in case of individual bidder) in the Equity of the Concessionaire are in accordance
with the Minimum Equity Requirements as stipulated under Article 7 of this
Agreement;
Each Joint Venture (JV) Member was and is duly organised and existing under the
laws of the jurisdiction of its incorporation and has full power and authority to
consent to and has consented to the Concessionaire entering into this Agreement
and has agreed to and unconditionally accepted the terms and conditions set forth in
this Agreement;
(xiv) All rights and interests of the Concessionaire in the Project shall pass to and vest in
the Authority on the Transfer Date free and clear of all liens, claims, and
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 123 of 195
encumbrances without any further act or deed on the part of the Concessionaire or
the Authority and that none of Assets including materials, supplies or equipment
forming part thereof shall be acquired by the Concessionaire subject to any
agreement under which a security interest or other lien or Encumbrance is retained
by any person save and except as expressly provided in this Agreement;
(xv)
No representation or warranty by the Concessionaire contained herein or in any
other document furnished by it to the Authority, or to any Competent Authority in
relation to Clearances contains or will contain any untrue statement of material fact
or omits or will omit to state a material fact necessary to make such representation
or warranty not misleading; and,
(xvi) The Concessionaire warrants that no sums, in cash or kind, have been paid or will be
paid by or on behalf of the Concessionaire, to any person by way of commission or
otherwise for securing the award of the Project or entering into of this Agreement or
for influencing or attempting to influence any officer or employee of the Authority.
13.3.
Obligation to Notify Change
(i)
(ii)
(iii)
(iv)
In the event that any of the representations or warranties made/ given by the
Concessionaire ceases to be true or stands changed, it shall promptly notify
Authority of the same.
Such notification shall not have the effect of remedying any breach of the
representation or warranty that has been found to be untrue or incorrect nor shall it
adversely affect or waive any obligation of the Authority under this Agreement.
The Concessionaire acknowledges that prior to the execution of this Agreement, the
Concessionaire has, after a complete and careful examination, made an independent
evaluation of the RFP including any addenda and / or corrigenda thereof, the
Agreement, Specifications, Site, existing structures, local conditions, physical
qualities of ground, subsoil and geology and all information provided by the
Authority or obtained procured or gathered otherwise, and has determined to its
satisfaction the accuracy or otherwise thereof and the nature and extent of
difficulties, risks and hazards as are likely to arise or may be faced by it in the course
of performance of its obligations hereunder. The Authority makes no representation
whatsoever, express, implicit or otherwise, regarding the accuracy, adequacy,
correctness, reliability and / or completeness of any assessment, assumption,
statement or information provided by it and the Concessionaire confirms that it shall
have no claim whatsoever against the Authority in this regard.
The Concessionaire acknowledges and hereby accepts the risk of inadequacy,
mistake or error in or relating to any of the matters set forth in the Article
hereinabove and hereby acknowledges and agrees that the Authority shall not be
liable for the same in any manner whatsoever to the Concessionaire, the Selected
Bidder and its Associates or any person claiming through or under any of them.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 124 of 195
ARTICLE 14:
VARIATIONS AND CHANGE OF SCOPE
14.1.
Variations and adjustments
(i)
(ii)
(iii)
(iv)
The Concession Period shall not be adjusted for changes in the cost of labour,
materials or other matters. The Concession Period shall only be adjusted as
expressly and explicitly stated in the Articles to this Agreement and there shall be
no other implied adjustments for any other reasons whatsoever.
Subject to the Change in Law, the Concessionaire shall be liable to pay all
applicable Taxes, duties, levies, as per the Applicable Laws.
If the Concessionaire suffers (or will suffer) delays or incurs (or will incur)
additional costs or loss in revenue resulting from such Changes in Law, made
after the Proposal Acceptance Date, the Concessionaire shall give notice to the
Authority. After receipt of such notice, the Authority shall proceed in accordance
with Article 13 of this Agreement to agree or determine any adjustment to the
Concession Period to which the Concessionaire is entitled, and shall notify the
Concessionaire accordingly. The Concession Period shall be adjusted taking into
account any increase or decrease in the costs resulting from Changes in Law
specifically in relation to the Project, made after the Proposal Acceptance Date.
The guiding principle in the operation of this Article shall be so as to place the
Concessionaire in subsequently the same legal, commercial and financial position
as it was prior to such Change in Law. The decision of the Authority shall be final
and binding on the Concessionaire.
14.2.
Change of Scope
(i)
(ii)
(iii)
The Authority may, notwithstanding anything to the contrary contained in this
Agreement, require the provision of additional works and services with regards to the
Project and / or the Site, which are not included in the scope of the Agreement as
contemplated by this Agreement (“Change of Scope”). Any such Change of Scope
shall be made in accordance with the provisions of this Article and the costs thereof
shall be expended by the Concessionaire which shall be compensated by adjustment
to the Concession Period in accordance with this Article.
In the event of the Authority determining that a Change of Scope is necessary, it shall
issue to the Concessionaire, a notice specifying in reasonable detail the works and
services contemplated thereunder (the “Change of Scope Order”), any instructions
to the Concessionaire for the execution of such works and services and the manner of
execution of such works and services.
Upon receipt of a Change of Scope Order, the Concessionaire shall, with due diligence,
comply with the instructions of the Authority and carry out such works and services,
promptly, in accordance with such Change of Scope Order. For the avoidance of
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 125 of 195
doubt, it is hereby clarified that a breach of the requirements of the Change of Scope
Order, shall amount to a breach of the duties, responsibilities and obligations of the
Concessionaire under the terms and conditions of this Agreement.
(iv)
On due performance of the duties, obligations and responsibilities of the
Concessionaire, in accordance with the Change of Scope Order, to the satisfaction of
the Authority, the Concessionaire may request the Authority to adjust the Concession
Period accordingly and provide sufficient information for such adjustment, upon which
the Concession Period may be adjusted at the option of the Authority. For the
avoidance of any doubt, it is hereby clarified that that such adjustment in accordance
with this Article shall not be an obligation on the Authority but an option with the
Authority.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 126 of 195
ARTICLE 15:
TERMINATION FOR EVENTS OF DEFAULT AND SUSPENSION
15.1
Termination for Concessionaire Event of Default
15.1.1 For the purposes of this Article, “Cure Period” means the period specified in this
Agreement for curing any breach or default of any provision of this Agreement by the
Concessionaire and shall:
(i)
(ii)
(iii)
commence from the date of issuance of a notice by the Authority to the
Concessionaire asking the latter to cure the breach or default specified in such notice;
not relieve the Concessionaire from liability to pay damages or compensation under
the provisions of this Agreement; and,
not in any way be extended by any period of suspension under this Agreement.
15.1.2 Each of the following events or circumstances, to the extent not caused by a default of
the Authority or Force Majeure, and if not cured within the Cure Period as may be
specified hereunder (the “Default Notice”) from the Authority, shall be considered for
the purpose of this Agreement as Events of Default of the Concessionaire
(“Concessionaire Events of Default”):
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
The Concessionaire is in breach of its obligations under this Agreement, which has a
Material Adverse Effect upon the Authority or the Project and such event is not cured
within a period of ten (10) days from the date of occurrence of such event.
The Concessionaire is in breach of any representation or warranty made under this
Agreement or it repudiates this Agreement and such event is not cured within a period
of ten (10) days from the date of occurrence of such event;
The Concessionaire fails to meet the progressive milestones as provided for in this
Agreement;
The Concessionaire abandons the Project or any of its material obligations as provided
under this Agreement;
The Concessionaire fails to maintain Performance Security under Article 5.2 or any
replenishment or furnishing of fresh Performance Security in the event of partial
appropriation by the Authority;
The Concessionaire does not comply with its Minimum Equity Requirements under
Article 7.2 of this Agreement;
Any transfer pursuant to law of either (a) the rights and/or obligations of the
Concessionaire under this Agreements and/ or (b) all or material part of the Assets or
undertaking of the Concessionaire; except (i) to the extent permitted by this
Agreement or (ii) where any such transfer, in the reasonable opinion of the Authority,
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 127 of 195
does not affect the ability of the Concessionaire to perform its obligations under this
Agreement;
(viii)
(ix)
(x)
In the event a resolution is passed by the shareholders of the Concessionaire for the
voluntary winding up of the Concessionaire;
The Concessionaire is adjudged bankrupt or insolvent or if a trustee or receiver is
appointed for the Concessionaire or for any of its property that has a material bearing
on the Project;
Any petition for winding up of the Concessionaire is admitted by a court of competent
jurisdiction or the Concessionaire is ordered to be wound up by court, except if such
petition is for the purpose of amalgamation or reconstruction, provided that as part of
such amalgamation and reconstruction, the property, assets and undertaking of the
Concessionaire are transferred to the amalgamated or reconstructed entity and that
the amalgamated or reconstructed entity has unconditionally assumed the obligations
of the Concessionaire under this Agreement and Project Agreements, and provided
that:
1.
2.
3.
The amalgamated entity or reconstructed entity has the technical and
financial capabilities and the operating experience necessary for the
performance of its obligations under the this Agreement and Project
Agreements;
The amalgamated entity or resulting entity has the financial standing to
perform its obligations under this Agreement and Project Agreements and
has a net worth at least as that good as that of the Concessionaire as on
the Compliance Date; and,
The Project Agreements remain in full force and effect;
(xi)
(xii)
(xiii)
The Concessionaire assigns this Agreement or any of its rights or obligations under the
Agreement, where such assignment is not in accordance with the terms and conditions
of the Agreement;
In the event of failure of Concessionaire to score minimum seventy – five (75%)
percent or more than seventy – five (75%) percent points for any three times of audit
inspection by the Authority in accordance with Article 19 of this Agreement;
The Concessionaire has employed any staff/labour/employee for whom a proper police
verification has not be done or any staff/labour/employee not permitted under the
terms and conditions of this Agreement and such event is not cured within a period of
fifteen (15) days from the date of occurrence of such event;
(xiv) The Concessionaire has created any charge, lien, interest and / or Encumbrance on
the Project, the Site and / or the Assets to any financial institution/ bank and / or any
Person, with or without knowledge of the Authority;
(xv) The Concessionaire has not performed any of its duties, responsibilities and obligations
under this Agreement, Clearances, Applicable Laws and Good Industry Practice, and
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 128 of 195
such event is not cured within a period of ten (10) days from the date of occurrence of
such event;
(xvi) the Concessionaire does not achieve the Time for Completion of Implementation by
the Implementation Period or any extended period thereof;
(xvii) when it is discovered by the Authority that the Concessionaire or the Selected Bidder
and their respective officers, employees, agents and advisers have:
1.
2.
not acted in a bonafide manner during the bidding process and the
execution of this Agreement; and / or,
directly or indirectly or through an agent, engaged in corrupt, fraudulent,
coercive, undesirable or restrictive practices in the bidding process or the
execution of the Jan Suvidha Kendra and / or the Project or other works
under this Agreement; and / or,
For the purposes of this sub – clause, the terms set forth are defined as follows:
“corrupt practice” means the offering, giving, receiving, directly or indirectly, of
anything of value to influence the action of a public official in the bidding process
or the execution of the Project or other works under the Agreement;
“fraudulent practice” means a misrepresentation or omission of facts in order
to influence the bidding process, or to obtain payments from the Authority for the
execution of the Project or other works under the Agreement;
“coercive practice” means harming or threatening to harm, directly or
indirectly, persons or their property to influence their participation in the bidding
process or in discharging their duties in the execution of the Project or other
works under the Agreement;
“undesirable practice” means establishing contact with any person connected
with or employed by the Authority with the objective of canvassing, lobbying or in
any manner influencing or attempting to influence the bidding process or the
monitoring, inspection or reporting the execution of the Project or other works
under the Agreement; and,
“restrictive practice” means forming a cartel or arriving at any understanding
or arrangement among bidders with the objective of restrictive or manipulating a
full and fair competition in the bidding process.
15.2
Termination by the Authority
Without prejudice to any other right or remedies which the Authority may have under
this Agreement, upon occurrence of a Concessionaire Event of Default, the Authority
shall be entitled to terminate this Agreement by issuing a Termination Notice to the
Concessionaire; provided that before issuing the Termination Notice, the Authority
shall by a notice inform the Concessionaire of its intention to issue such Termination
Notice and grant 15 (fifteen) days to the Concessionaire to make a representation,
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 129 of 195
and may after the expiry of such 15 (fifteen) days, whether or not it is in receipt of
such representation, issue the Termination Notice.
15.3
15.4
15.5
15.6
Survival of rights
Notwithstanding anything to the contrary contained in this Agreement, any termination
pursuant to the provisions of this Agreement shall be without prejudice to the accrued
rights of the Authority including its right to claim and recover money damages, specific
performance, insurance proceeds, and other rights and remedies, which it may have in
law or contract. All obligations of Concessionaire under this Agreement, including
transfer requirements, shall survive the termination to the extent such survival is
necessary for giving effect to such rights and obligations.
Suspension
Upon occurrence of a Concessionaire Event of Default, the Authority shall be entitled,
without prejudice to its other rights and remedies under this Agreement, under law or
equity, including its rights of termination hereunder, to (i) suspend all rights of the
Concessionaire under this Agreement including the Concessionaire’s right to charge and
/ or levy Commercial Charges, and other payments pursuant hereto, and (ii) exercise
such rights itself and perform the obligations hereunder or authorise any other person
to exercise or perform the same on its behalf during such suspension (the
“Suspension”).
Authority to act on behalf of the Concessionaire
During the period of Suspension, the Authority may, at its option and at the risk and
cost of the Concessionaire, remedy and rectify the cause of Suspension. The Authority
shall, on behalf of the Concessionaire, appropriate any Commercial Charges and other
revenues under and in accordance with this Agreement and shall deposit the same in an
account to be opened by the Authority’s nominee for this purpose. The Authority shall
be entitled to make withdrawals from such account for meeting the costs incurred by it
for remedying and rectifying the cause of Suspension, and for defraying the expenses
on maintenance of the Project, the Assets and / or the Site. During the period of
Suspension hereunder, all assets and liabilities in relation to the maintenance of the
Project, the Assets and / or the Site, shall continue to vest in the Concessionaire in
accordance with the provisions of this Agreement and all things done or actions taken,
including expenditure incurred by the Authority for discharging the obligations of the
Authority under and in accordance with this Agreement and the Project Agreements,
shall be deemed to have been done or taken for and on behalf of the Concessionaire
and the Concessionaire undertakes to indemnify the Authority for all costs incurred
during such period. The Concessionaire hereby licenses and sub – licenses respectively,
the Authority or any other person authorised by it under this Article to use during
Suspension, all intellectual property belonging to or licensed to the Concessionaire.
Revocation of Suspension
For the avoidance of doubt, the Parties expressly agree that the Authority may, in its
discretion, revoke the Suspension at any time, whether or not the cause of Suspension
has been rectified or removed hereunder.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Sr. No. Particulars Amount (Rs.)
i) premium paid towards land rent, apportioned to
remaining operation period, As per table T-1 and
T-2 as below
15,68,130
ii) 50% depreciated value of the building
(Structure) (As per table T-3 as below)
62,50,000
Sub Total A 78,18,130
Reduced by
a) Debit for cost of wear & tear required to get the
building at good working condition
5,00,000
b) Debit for incomplete work, if any 0
Sub Total B 5,00,000
Page 130 of 195
ARTICLE 16:
CONSEQUENCES OF TERMINATION
16.1
Termination Payment for Termination by the Authority
16.1.1 Upon Termination by the Authority, during the Operations and Maintenance Period, in
accordance with the provisions of Articles 15, the Concessionaire shall peacefully hand
over the possession of the Project, the Site and the Assets in proper working
condition and the Performance Security shall be encashed by the Authority.
16.1.2 The Concessionaire shall be entitled to get Termination Payment as mentioned below:
(i)
(ii)
Fifty (50%) percent premium paid towards land rent, apportioned to the balance
of the Operations and Maintenance Period; and,
Fifty (50%) percent depreciated value of the structures of the Jan Suvidha
Kendra and the Project.
16.1.3 For the avoidance of any doubt, it is clarified that the Termination Payment, as payable
by the Authority, shall be reduced by the following:
(i)
(ii)
Debits for cost of wear and tear required to get the structures of the Jan Suvidha
Kendra and the Project up to good working condition; and,
Debits for any incomplete work of the Concessionaire.
For illustration, the Concessionaire is assumed to have paid Licence Fees of Rs. 45.00
lacs, with a Performance Security of Rs. 6.00 lacs for Concession Period of 15 years,
has incurred a cost of Rs. 150.00 lacs towards construction of Building, Rs. 70.00
towards furniture and interior and the Project is terminated at end of the fifth (5th)
year. Now, at the time of termination, there is some cost of wear and tear of Rs. 5.00
lakhs.
Then in that case, termination payment shall be as follows:
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad
Sangli Shirol S.H.142 Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 131 of 195
Termination Payment Due ( Sub Total A- Sub
Total B)
Table T-1
Working for calculation of Premium
At the time of Bid
73,18,130
Year Period Rent Increas ROI % NPV
From
01-06-
To
31-05-
e for
the year
1 17 18 380016 0% 12% 339300
01-06- 31-05-
2 18 19 418017 10% 12% 333241
01-06- 31-05-
3 19 20 459819 10% 12% 327290
01-06- 31-05-
4 20 21 505801 10% 12% 321446
01-06- 31-05-
5 21 22 556381 10% 12% 315705
01-06- 31-05-
6 22 23 612019 10% 12% 310068
01-06- 31-05-
7 23 24 673221 10% 12% 304531
01-06- 31-05-
8 24 25 740543 10% 12% 299093
01-06- 31-05-
9 25 26 814597 10% 12% 293752
01-06- 31-05-
10 26 27 896057 10% 12% 288506
01-06- 31-05-
11 27 28 985663 10% 12% 283354
01-06- 31-05-
12 28 29 1084229 10% 12% 278295
01-06- 31-05-
13 29 30 1192652 10% 12% 273325
01-06- 31-05-
14 30 31 1311917 10% 12% 268444
01-06- 31-05-
15 31 32 1443109 10% 12% 263651
Present Value of Land
Rent
450000
0
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest House Khandala on
Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 132 of 195
Table T-2
Working for calculation of Premium
At the time of Termination
Year Period Period Rent Increase ROI % NPV
From
31-05-
To
30-05-
in
Years
for the
year
1 22 23 1.00 380016 0% 12% 339300
31-05- 30-05-
2 23 24 1.00 418017 10% 12% 334154
31-05- 30-05-
3 24 25 1.00 459819 10% 12% 327290
31-05- 30-05-
4 25 26 1.00 505801 10% 12% 321446
31-05- 30-05-
5 26 27 1.00 556381 10% 12% 315705
31-05- 30-05-
6 27 28 1.00 612019 10% 12% 310917
31-05- 30-05-
7 28 29 1.00 673221 10% 12% 304531
31-05- 30-05-
8 29 30 1.00 740543 10% 12% 299093
31-05- 30-05-
9 30 31 1.00 814597 10% 12% 293752
31-05- 30-05-
10 31 32 1.00 896057 10% 12% 289297
31-05- 31-05-
11 32 32 0.00 985663 10% 12% 776
01-06- 31-05-
12 32 32 - 1084229 10% 12% 0
01-06- 31-05-
13 32 32 - 1192652 10% 12% 0
01-06- 31-05-
14 32 32 - 1311917 10% 12% 0
01-06- 31-05-
15 32 32 - 1443109 10% 12% 0
Present
Value of
Land Rent
50% OF
ABOVE
31,36,26
0
15,68,13
0
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 133 of 195
Table T-3
100% depreciated value of the building
Valuation of the project
Estimated useful life of the building
Operation period utilised
Balance Useful Life of Project
Depreciation on utilised period
Rate of depreciation of Straight Line Method
Amount of Depreciation for utilised period
Depreciated Value of the Building
50% of Depreciated Value of the building
Rs.
Years
Years
Years
% p.a.
50%
15000000
30
5
25
3.33%
2500000
12500000
62,50,000
16.1.4 The Financial Model shall be prepared on the Proposal Acceptance Date and shall be
attached with this Agreement.
16.1.5 For value of premium to be repaid, one can refer to financial model prepared at the
time of bid submission, and for the purpose of Article 15 of this Agreement, premium
paid towards land rent, apportioned to remaining concession period would mean,
present value of balance premium of land rent at the time of bid submission.
(i)
(ii)
All payments due to the Concessionaire as calculated under Article 15.1 shall be
made within 30 (thirty) days of termination of the Agreement.
However, if the termination by the Authority on account of the Concessionaire
Event of Default is during the Implementation Period then the Concessionaire
shall not be entitled for any Termination Payments. However, the Performance
Security shall be encashed by the Authority.
16.2
Other rights and obligations upon Termination
Upon termination of this Agreement for any reason whatsoever, the Authority shall:
(i)
(ii)
(iii)
(iv)
be deemed to have taken possession and control of the Project, the Site and the
Assets forthwith which are deemed to be or which should have been in
possession of the Concessionaire;
take possession and control of all materials, stores, implements, plants and
equipment on or about the Project and the Site;
be entitled to restrain the Concessionaire and any person claiming through or
under the Concessionaire from entering upon the Project and the Site or any part
of the Project premises;
require the Concessionaire to comply with the transfer requirements set forth in
Article 23 of this Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 134 of 195
16.3
Limitation of Termination Payments by the Authority
Termination payment, due and payable under this Agreement, shall be limited to Rs.
______________________ (Rupees ______________________ only), as the
case may be, and the Authority shall at no time be liable to pay the termination
payment in excess of Rs. ______________________ (Rupees
______________________ only). Provided that the liability of the Authority to make
the termination payment hereof is subject to the fulfilment of the transfer requirements in
accordance with Article 23 of this Agreement. For the avoidance of doubt, it is expressly
agreed that the termination payment shall constitute full discharge by the Authority of its
payment obligations in respect thereof hereunder. Upon termination on expiry of the term of
this Agreement by efflux of time, no termination payment shall be due and payable to the
Concessionaire. The Concessionaire expressly agrees that the termination payment under this
Article shall constitute a full and final settlement of all claims of the Concessionaire on account
of termination of this Agreement for any reason whatsoever and that the Concessionaire shall
not have any further right or claim under any law, treaty, convention, contract or otherwise.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 135 of 195
ARTICLE 17:
FORCE MAJEURE
17.1
Force Majeure Events
In this Agreement, "Force Majeure" means an occurrence of an event in India of any or
all of the Non-Political Force Majeure Event, Indirect Political Force Majeure Event and
Political Force Majeure Event described in Articles 17.2, 17.3 and 17.4 of this Agreement,
respectively hereinafter which prevents the Party claiming Force Majeure (the “Affected
Party”) from performing its obligations under this Agreement and which act or event:
(i)
(ii)
(iii)
Is beyond the reasonable control of and not arising out of the fault or negligence
of the Affected Party or the failure of such Party to perform its obligations
hereunder;
The Affected Party has been unable to prevent by the exercise of due diligence
and reasonable efforts, skill and care; and,
Has a Materially Adverse Effect on the Project.
17.2
Non – Political Force Majeure Events For the purposes of Article 17.1, Non – Political Force Majeure Events shall mean one or
more of the following acts or events:
(i)
(ii)
(iii)
(iv)
(v)
Acts of God or events beyond the reasonable control of the Affected Party which
could not reasonably have been expected to occur, extreme adverse weather or
environmental conditions, lightning, earthquakes, heavy rains, cyclones, tempest,
whirlwind, landslides, storms, floods, volcanic eruptions or fire;
Radioactive contamination or ionising radiation;
Strikes or boycotts (other than those involving the Concessionaire, contractors,
or their respective employees/ representatives or attributable to any act or
omission of any of them) interrupting supplies and services to the Project for a
continuous period exceeding 7 (seven) days in an Financial Year, and not being
an Indirect Political Event set forth in Article 17.3;
Any judgment or order of any court of competent jurisdiction or statutory
authority in India made against the Concessionaire in any proceedings for the
reason other than failure of the Concessionaire to comply with any Applicable
Law or Clearances or on account of breach thereof, or of any contract, or
enforcement of this Agreement or exercise of any of its rights under this
Agreement by the Authority; or,
Any other event or circumstance of a nature analogous to the foregoing, to the
extent that insurance is available at a reasonable cost to cover the occurrence of
any of the natural events. The Concessionaire will ensure that it has insured
itself against such risks.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHAKENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 136 of 195
17.3
Indirect Political Force Majeure Event
For the purposes of Article 17.1, Indirect Political Force Majeure Events shall mean one or
more of the following acts or events by or on account of the Authority, Government of
India or any other Competent Authority:
(i)
(ii)
(iii)
An act of war (whether declared or undeclared), invasion, armed conflict or act
of foreign enemy, unexpected call up of armed forces, blockade, embargo,
rebellion, riot, religious strife, bombs or civil commotion, sabotage, terrorism
which prevents collection of Commercial Charges by the Concessionaire for a
period exceeding a continuous period of 7 (seven) days in an Financial Year;
Industry wide or state wide or nationwide strikes or industrial action for a period
exceeding a continuous period of 7(seven) days in an Financial Year; or
Any public agitation which prevents collection of Commercial Charges by the
Concessionaire for a period exceeding a continuous of 7 (seven) days in a
Financial Year.
17.4
Political Force Majeure Event
For the purposes of Article 17.1, Political Force Majeure Events shall mean one or more of
the following acts or events by or on account of the Authority, Government of India or
any other Competent Authority:
(i)
(ii)
Expropriation or compulsory confiscation, by any Competent Authority of any
Assets or rights of the Concessionaire or of the contractors; or,
Any unlawful or unauthorised or without jurisdiction, revocation of, or refusal to
renew or grant without valid cause any consent or approval required by the
Concessionaire or any of the contractors to perform their respective obligations
under the Project Agreements (other than a consent, the obtaining of which is a
condition precedent) provided that such delay, modification, denial, refusal or
revocation did not result from the Concessionaire’s or any contractor’s inability or
failure to comply with any condition relating to the grant, maintenance or
renewal of such consents or permits.
17.5
Exceptions applicable to the Concessionaire
The Concessionaire shall not have the
right to consider any of the following
circumstances to be an event of Force Majeure that would suspend the performance or
excuse the non –performance of its obligations under this Agreement other than the
circumstances resulting from an event of Force Majeure:-
(i)
(ii)
Delay in performance by the Concessionaire, subcontractor(s), agents and
employees of the Concessionaire; or,
Breakdown or ordinary wear and tear of materials, equipment machinery or parts
relating to the Project.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA
KENDRA AT Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 137 of 195
17.6
Exceptions Applicable to the Authority
The Authority shall not have the right to consider any of the following circumstances to
be an event of Force Majeure that would suspend the performance or excuse the non-
performance of its obligations under this Agreement:
(i)
(ii)
(iii)
the expropriation, confiscation, nationalisation or requisition of the Project,
Assets by the Authority;
the imposition of any blockade, embargo, import restrictions, rationing or
allocation by the Authority or any Competent Authority; or,
any delay or difficulty in handing over the Jan Suvidha Kendra as a result of any
intervention or directive of the Authority or any Competent Authority.
17.7
Effect of Force Majeure before the issue of Notice to Commence
Upon occurrence of any Force Majeure Event prior to the issuance of the notice to
commence, the following shall apply:
(i)
(ii)
(iii)
There shall be no Termination by the Concessionaire;
The Compliance Date shall be extended by the period of which such Force
Majeure event shall subsist, at the sole discretion of the Authority; and,
The Parties shall bear their respective costs arising out of such Force Majeure
Event.
17.8
Effect of Force Majeure after Compliance Date
Upon occurrence of any Force Majeure Event after the Compliance Date, the following
shall apply:
(i)
(ii)
(iii)
(iv)
There shall be no Termination of this Concession Agreement by the
Concessionaire;
Where the Force Majeure Event occurs before the issue of Implementation
Completion Certificate or Provisional Implementation Completion Certificate, the
Concession Period shall be extended by the period for which such Force Majeure
Event shall subsist, at the sole discretion of the Authority;
Where the Force Majeure Event occurs after the issuance of Implementation
Completion Certificate, the Concessionaire shall make all reasonable efforts to
collect Commercial Charges, but if he is unable to collect Commercial Charges
during the subsistence of such Force Majeure Event, the Concession Period shall
be extended by the period for which collection of Commercial Charges remains
suspended on account thereof; and,
All cost arising out or concerning such Force Majeure Event shall be borne in
accordance with provisions of Article 17.9.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 138 of 195
17.9
17.10
17.11
17.12
17.13
17.14
Allocation of costs during the subsistence of Force Majeure
Upon occurrence of a Force Majeure Event after Compliance Date, the costs attributable
to such Force Majeure Event and directly relating to the Project (the Force Majeure Costs)
shall be borne by the Concessionaire from the insurance cover procured for such purpose,
in accordance with the requirements of this Agreement.
Termination Notice
If the Force Majeure Event subsists for a period of 270 (two hundred seventy) days or
more within a continuous period of 365 (three hundred sixty five) days, either Party may
in its sole discretion terminate this Agreement by giving 30 (thirty) days Termination
Notice in writing to the other Party without being liable in any manner whatsoever, save
and except as per the provisions of in Article 17.11.
Termination Payments for Force Majeure Events
Upon Termination of this Agreement pursuant to Article 17.10, no termination payment
shall be made by the Authority to the Concessionaire and the Concessionaire shall be
entitled to receive and appropriate, the proceeds of any amounts under insurance policies.
After expiry of 30 (thirty) days from such Termination Notice under Article 17.10 of this
Agreement, in the event that there is no contravention of the terms and conditions of
this Agreement, Applicable Laws, Clearances and Good Industry Practice, the
Performance Security, if subsisting, shall be released to the Concessionaire.
Dispute Resolution
In the event that the Parties are unable to agree in good faith about the occurrence or
existence of a Force Majeure Event, such dispute shall be finally settled in accordance
with the Dispute Resolution procedure as under Article 18, provided however that the
burden of proof as to the occurrence or existence of such Force Majeure event shall be
upon Party claiming relief and/or excuse on the account of such Force Majeure Event.
Liability for other losses, damages etc.
Save and except as expressly provided in this Article neither Party hereto shall be liable in
any manner whatsoever to other Party in respect of any loss, damage, cost, expense,
claims, demand and proceedings relating to or arising out of occurrence or existence of
any Force Majeure Event or exercise of any right pursuant to this Article.
Duty to Report
The Affected Party shall discharge the following obligations in relation to reporting the
occurrence of a Force Majeure Event to the other Party:
(i)
The Affected Party shall not claim any relief for or in respect of a Force Majeure
Event unless it shall have notified the other Party in writing of the occurrence of
the Force Majeure Event as soon as reasonably practicable, and in any event
within 7 (seven) days after the Affected Party knew or ought reasonably to have
known of its occurrence and the probable Material Adverse Effect that the Force
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHAKENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 139 of 195
Majeure Event is likely to have occurred on the performance of its obligations
under this Agreement
(ii)
Any notice pursuant to this Article 17.14 shall include full particulars of:
1.
2.
3.
4.
The nature and extent of each Force Majeure Event which is the subject of
any claim for relief under this Article 17 with evidence in support thereof;
The estimated duration and effect or probable effects which such Force
Majeure Event is having or will have on the Affected Party’s performance of
its obligations under this Agreement;
The measure which the Affected Party is taking or proposes to take to
alleviate the impact of such Force Majeure Event; and
Any other information relevant to the Affected Party’s claim.
(iii)
For so long as the Affected Party continues to claim to be affected by such Force
Majeure Event, it shall provide the other Party with regular (and not less than
weekly) written reports containing information as required by this Article 17.14,
and such other information as the other Party may reasonably request the
Affected Party to provide.
17.15
Excuse from performance of obligations
If the Affected Party is wholly or partially unable to perform its obligations under this
Agreement because of Force Majeure Event, it shall be excused from performance of
such of its obligations to the extent it is unable to perform on account of such Force
Majeure Event provided that:
(i)
(ii)
(iii)
The suspension of performance shall be no greater scope and of no longer
duration than is reasonably required by the Force Majeure Event;
The Affected Party shall make all reasonable efforts to mitigate or limit damage
to the other Party arising out of or as a result of the existence or occurrence of
such Force Majeure Event and to cure the same with due diligence; and,
When the Affected Party is able to resume performance of its obligations under
this Agreement, it shall give to the other Party written notice to that effect and
shall promptly resume performance of its obligations hereunder.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 140 of 195
ARTICLE 18:
DISPUTE RESOLUTION
18.1
Amicable Resolution
18.1.1 Any dispute, disagreement, difference, controversy or claim arising out of, relating to or
in connection with this Agreement (including any question regarding its existence,
validity, interpretation, performance, breach or termination) and any dispute relating to
any non- contractual obligations arising out of or in connection with it (a “Dispute”)
shall, so far as is possible, be settled amicably.
18.1.2 If a Dispute arises, a Party may serve a written notice on the other Party commencing
a formal consultation period of thirty (30) days within which the Dispute should be
resolved (“Consultation Period”). During the Consultation Period, the Chief Engineer
of the concerned Public Works Region on behalf of the Authority and the CEO/MD of
the Concessionaire, shall be obligated to promptly meet with each other, at a place to
be mutually decided by the Parties. Each Party shall bear their own costs and expenses
for attending such a meeting.
18.2
Arbitration
If the Dispute is not resolved by end of the Consultation Period, the Dispute shall be
referred to and finally resolved by a binding arbitration in accordance with the
Arbitration and Conciliation Act, 1996. The arbitration shall be conducted as follows:
(a)
(b)
(c)
Any Party raising the Dispute and invoking the arbitration shall send a written
notice of Dispute (“Arbitration Notice”) to other Party.
The arbitration shall be conducted by a sole arbitrator, who will be mutually
appointed by the Parties within a period of thirty (30) days from the date of the
Arbitration Notice. In the event, the sole arbitrator is not appointed by the
Parties within the said time period, the sole arbitrator will be appointed by the
court in accordance with the Arbitration and Conciliation Act, 1996.
All proceedings in any such arbitration shall be conducted in English.
(d)
The seat of
the
arbitration
proceedings
shall
be
Pune,
Maharashtra.
(e)
(f)
(g)
The arbitrator shall be free to award costs as may be appropriate.
The arbitral award shall be a reasoned award and shall be in writing.
The arbitral award shall be final and binding on the Parties. The Parties
undertake to carry out the award without delay.
18.3
Performance during Dispute
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 141 of 195
The Authority shall have the right to take over the possession and control of the
Project, the Site and the Assets after the issuance of the Termination Notice
irrespective of any Dispute raised by the Concessionaire regarding such Termination or
otherwise. Pending the settlement/adjudication of the said Dispute, the Authority shall
have right to operate and manage the Project. Further, the Concessionaire shall continue
to perform all other obligations pending the settlement/adjudication of any Dispute
under this Article.
18.4
This clause shall survive termination of this Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 142 of 195
ARTICLE 19:
PERIODICAL AUDIT AND INSPECTION
19.1.
19.2.
A bi – annual audit of the Project and the Jan Suvidha Kendra shall be conducted by a
Person designated by the Committee formed as per Article 9 of this Agreement. This
audit shall be conducted at least two (2) times in a year and there shall be gap of at
least 4 months between two (2) consecutive audits. The gap between two (2)
consecutive audits by such Person, designated by the Committee, should not be
beyond eight (8) months in any case. Report as per format specified in Schedule – V
of this Agreement shall be prepared and submitted to the Parties. The Authority shall
have the right to terminate the Agreement, in the event of the Concessionaire failing
to achieve at least 75% of the total marks, for three or more times, during the audit
of periodical audit conducted by the Authority, in accordance with this Article.
The Authority and / or its representative shall have the discretion to inspect the Project
at any point time during the Concession Period and shall give intimation of any wrong
done or shortfall for the operations / constructions. This inspection shall be in addition
to the periodical audit conducted throughout the Concession Period.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 143 of 195
ARTICLE 20:
FINANCING DOCUMENTS
20.1.
20.2.
The Authority hereby confirms that it shall not enter into any substitution agreement with
any banker, financial institution and / or any Person and the Concessionaire thereby shall
make provisions of funding for the Project, the Site and the Assets on its own financial
credibility and financial security.
The Concessionaire further hereby undertakes to the Authority that the Concessionaire
shall not offer the Site given to it under this Agreement as security and / or create any
charge, lien, interest and / or any Encumbrance to any bank / financial institution / any
Person for any reason whatsoever.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 144 of 195
ARTICLE 21:
TAXATION AND CONFIDENTIALITY
21.1. Local Taxation
(i)
(ii)
The duties, responsibilities and obligations of the Concessionaire under this
Agreement shall include payment of all Taxes, charges towards import license, toll,
customs duties, import duties, business taxes, etc., that may be levied in
accordance with the Applicable Laws as per the applicable rates. Nothing in this
Agreement shall relieve the Concessionaire from its responsibility to pay any Taxes
that may be levied in India on profits made by it in respect of this Agreement
Under the provisions of the Income Tax Act, 1961, the Authority is required to
deduct tax at source at the rates prevailing in case any payments are made to the
Concessionaire as envisaged under this Agreement.
21.2.
21.3.
21.4.
Income Taxes on Staff, Labour, Employees and Personnel
The Concessionaire's staff, employees, personnel and labour will be liable to pay personal
income taxes in India in respect of their salaries, commissions and wages as chargeable
under Applicable Laws and the Concessionaire shall make such deductions in respect of
such taxes as required by law.
Confidentiality
“Confidential Information” shall mean all non – public information of the Project and /
or the Authority which is accessible by or is available to the Concessionaire whether in
writing, oral, graphic, visual or any other tangible, intangible or electronic form including,
without limitation, any and all information relating to the Project (whether past, present, or
future) including without limitation the financial data, financial results and projections,
costs and prices, details and data of Concessionaire’s suppliers, dealers, distributors,
customers, retainers, employees and consultants (whether past, present or prospective),
technologies, technical and business strategies, business and marketing plans, marketing
and sales techniques, pricing and other strategies, computer programs, software tools,
source codes, object codes, protocols, product descriptions, development schedules,
product positioning, choices of product names, trade secrets or know how, customer
information and intellectual property rights, in relation to the Project, the Assets and the
Site, as well as any such information not generally known to third parties or received from
others that the Concessionaire is reasonably expected to treat as confidential. The
Concessionaire shall not, at any time, before the expiry or termination of this Agreement,
without the consent of the Authority, divulge or suffer or permit its officers, employees,
or agents to divulge to any Person (other than to any of its or their respective officers or
employees who require the same to enable them to properly to carry out their duties),
any Confidential Information and any other information relating to the negotiations
concerning the RFP, the Agreement, the operations, contracts, commercial or financial
arrangements or affairs of the Authority or any proprietary information of the Authority.
Exceptions to Confidentiality
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 145 of 195
The restrictions imposed by Article 21.3 shall not apply to the disclosure of any
Confidential Information:
(i)
(ii)
(iii)
(iv)
Which now or hereafter is released into the public domain, otherwise than as a
result of a breach of an undertaking of confidentiality or which is obtained with no
more than reasonable diligence from sources other than the Concessionaire;
Which is required by Applicable Laws, to be disclosed to any Person who is
authorised by Applicable Laws to receive the same;
To a court, arbitrator or administrative tribunal in the course of proceedings before
it to which the Concessionaire is a party; or,
To any consultants, banks, financiers and / or advisers to the Concessionaire, or in
accordance with the duties, obligations and responsibilities of the Concessionaire
under this Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 146 of 195
ARTICLE 22:
PROJECT REVENUES AND COMMERCIAL CHARGES
22.1.
Levy and Appropriation of Commercial Charges
(i)
(ii)
(iii)
The Concessionaire shall levy, collect, appropriate Commercial Charges from the
Project, the Site, shops, establishments, stalls, advertising boards, restaurants,
etc. for the period in accordance with the provisions of this Agreement.
Save and except as otherwise stated under this Agreement, on and from the
Operations Date and until the last date of the Concession Period, the
Concessionaire or its subcontractors shall levy, collect, and appropriate
Commercial Charges, as set out in Article 22.2 of this Agreement.
The Authority expressly recognises that the right of the Concessionaire or its
subcontractors to levy, demand, collect, retain, and to appropriate Commercial
Charges in accordance (i) with the terms of this Agreement and (ii) to exercise
all rights and remedies available under Applicable Laws and under this
Agreement for the recovery of the Commercial Charges.
22.2.
Types of Project Revenue
(i)
(ii)
(iii)
Income from User charges, fees and Commercial Charges
The Concessionaire shall be allowed to charge for the use of the Project
including the stalls, ATM, Restaurant, vehicle repair facility, etc. but shall not
charge the Users Commercial Charges for such services as intimated by the
Authority which shall be mandatorily be provided free of cost to the Users.
Income from Display of Advertisements
The Concessionaire can charge Commercial Charges for the purposes of
advertisements in accordance with Applicable Laws, subject to prior written
consent of the Authority. The display of advertisements at any part the Project,
the Site and the Assets shall be as per the instructions of the Authority. In the
event, that the Concessionaire is instructed to remove and / or take down any
advertisement, on the Project, the Site and the Assets, the Concessionaire shall
be liable to remove such advertisement, within a period of seven (7) days from
the date of such request, failing which it shall amount to a Concessionaire Event
of Default. The Concessionaire may sub – license out the advertisement boards
to the advertisers with prior written consent of the Authority in accordance with
the terms and conditions of this Agreement.
Miscellaneous
Apart from the above, the Concessionaire shall be well within its right to
generate revenues for other activities subject to prior written consent of the
Authority, Applicable Laws, Clearances and the terms and conditions of this
Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 147 of 195
ARTICLE 23:
TRANSFER OF THE PROJECT
23.1
Transfer of Project
(i)
(ii)
(iii)
(iv)
(v)
On the Transfer Date, the Concessionaire shall, transfer and assign to the
Authority or its nominated agency, as the case may be, the Project, the Site
and the Assets, free and clear of any charges, liens, interest and Encumbrances
created or suffered by the Concessionaire after the Compliance Date of all the
Concessionaire’s right, title, benefits and interest in and to the Project, the Site
and the Assets. The Concessionaire shall also deliver to the Authority or its
nominated agency on such date such project reports, manuals, plans, design
drawings, reports, accounts and other information as may be required by the
Authority or its nominated agency to enable it to continue the operation of the
Project either directly or by its nominated agency. The labour, employees and
personnel of the Concessionaire shall continue to be the employees, labour and
personnel of the Concessionaire and the transfer of all the movable and
immovable assets shall not in any manner affect their status as employees, labour
and personnel of the Concessionaire and they shall have no claim to any type of
employment or compensation from the Authority or its nominated agency.
The Concessionaire shall to the extent possible assign to the Authority or its
nominated agency at the time of transfer all unexpired guarantees and warranties
by subcontractors and suppliers and all insurance policies. The Concessionaire shall
ensure that any rights, which are to be so assigned, are capable of assignment and
the counterpart to the Concessionaire has approved such assignment under the
terms and conditions of the relevant Project Agreement.
The Concessionaire shall, to the extent possible at the time of transfer, assign to
the Authority or its nominated agency all contracts, equipment contracts, supply
contracts and all other contracts relating to the Project, the Site and the Assets
entered into by the Concessionaire and subsisting at the time of transfer except
any agreements and / or contracts with employees, labour and / or personnel.
At least 60 (Sixty) days prior to the Transfer Date, the Authority shall be entitled
to appoint any consulting engineer to assess the condition of the Project, the Site
and the Assets. Such consulting engineer shall be entitled to have free access to
inspect the Project, the Site and the Assets, provided that such inspection is
reasonable and is carried out with minimum disruption to normal operation of the
Project, the Site and the Assets.
Until the Transfer Date, all risks shall lie with the Concessionaire for loss of or
damage to the whole or any part of the Project, the Site and the Assets, unless
such loss or damage is due to an act or omission of the Authority in contravention
of its obligations under this Agreement
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 148 of 195
(vi)
(vii)
The Concessionaire shall provide fair and just compensation to its labour,
employees and personnel as required under Applicable Laws or under this
Agreement, and shall indemnify the Authority against any claims from any such
labour, employees and personnel for their loss of office, redundancy, loss of
employment or otherwise. The Authority shall accept absolutely no liability on
account of any matter pertaining to the Concessionaire's employees, staff, labour
etc.
On the Transfer Date, the Concessionaire shall hand over the Project, the Site and
the Assets and all other movable and immovable assets forming part thereof, to
the Authority or its nominated agency at zero cost or expense to the Authority.
(viii) Upon the issuance of the Agreement Completion Certificate by the Authority, the
obligations and the rights of the Concessionaire under this Agreement shall
terminate vis-à-vis the Authority and the Authority or its nominated agency shall
take over the Project, the Site and the Assets and the operation and maintenance
of the Project, the Site and the Assets and any other rights or obligations arising
out of this Agreement which either expressly or implicitly survive termination of
this Agreement. Provided that the Concessionaire may continue with any other
business operations arising other than in connection with this Agreement and
provided further that the Concessionaire shall no longer act in its capacity as
Concessionaire in relation or pursuant to this Agreement.
(ix)
On completion of the transfer by the Concessionaire to the Authority, the
Authority shall issue an Agreement Completion Certificate to the Concessionaire in
accordance with the requirements of this Agreement. The Agreement Completion
Certificate will have the effect of constituting evidence of transfer of all rights,
titles and interests in the Project by the Concessionaire, and their vesting in the
Authority hereto.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 149 of 195
ARTICLE 24:
MISCELLANEOUS PROVISIONS
24.1
24.2
Governing Law and Jurisdiction
This Agreement shall be construed and interpreted in accordance with and governed by
the laws of India. Subject to the provisions of Dispute Resolution clause of this
Agreement, and the courts of Satara, Maharashtra shall have jurisdiction over all matters arising out of, in
connection with or relating to this Agreement.
Waiver
Waiver by either Party of any default by the other Party in the observance and
performance of any provisions of or obligations under this Agreement:
(i)
(ii)
(iii)
Shall not operate or be construed as a waiver of any other or subsequent default
hereof or of other provisions of or obligations under this Agreement;
Shall not be effective unless it is in writing and executed by a duly authorised
representative of the Party; and
Shall not affect the validity or enforceability of this Agreement in any manner.
Neither the failure by either Party to insist on any occasion upon the performance of the
terms, conditions and provisions of this Agreement or any obligation there under nor time
or other indulgence granted by a Party to the other Party shall be treated or deemed as
waiver of such breach or acceptance of any variation or the relinquishment of any such
right hereunder.
24.3
24.4
Exclusion of implied warranties
This Agreement expressly excludes any warranty, condition or any other undertaking
implied at law or by custom or otherwise arising out of any other agreement between
the Parties or any representation by either Party not contained in a binding legal
agreement executed by both Parties.
Severability
If for any reason whatsoever, any provision of this Agreement is or becomes invalid,
illegal or unenforceable or is declared by any court of competent jurisdiction or any
other legal and valid instrumentality to be invalid, illegal or unenforceable, the validity,
legality or enforceability of the remaining provisions shall not be affected in any
manner, and the Parties will negotiate in good faith with a view to agreeing upon
one or more provisions, which may be substituted for such invalid, unenforceable or
illegal provisions, as nearly as is practicable. Provided that, failure of the Parties to
agree upon any such provisions shall not be a subject matter to dispute resolution
under this Agreement or otherwise.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHAKENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 150 of 195
24.5
24.6
24.7
24.8
24.9
Entire Agreement
This Agreement and the Schedules together constitutes a complete and exclusive
understanding between the Parties of the terms and conditions of the agreement
between the Parties on the subject hereof and no amendment or modification hereto
shall be valid and effective unless such modification or amendment is agreed to in
writing by the Parties and duly executed by persons especially empowered in this behalf
by the respective Parties.
Custody of Documents
The Project Report and other documents, manuals, memoranda and / or any other
information in relation to the Project, the Site and the Assets (“Design Documents”), as
may be required by the Authority, shall be in the custody and care of the Concessionaire.
Unless stated otherwise in this Agreement, the Concessionaire shall provide four (4)
copies for the use of the Authority.
Copyright
The Concessionaire, as beneficial owner, hereby transfers to the Authority copyright and
registered design and all other property rights subsisting in or accruing to the
Concessionaire, in relation to the Design Documents made or to be made by or on behalf
of the Concessionaire, during the Concession Period for which such copyright subsists in
such works. The Authority hereby grants to the Concessionaire non-exclusive royalty-free
licence to use such documents and drawings solely for the purpose of complying with its
obligations under this Agreement.
Use of the Authority's Documents
Copyright in the technical requirements and other documents issued by the Authority to
the Concessionaire shall (as between the Parties) remain the property of the Authority.
The Concessionaire may, at its cost, copy, use and communicate any such documents for
the purposes of this Agreement They shall not, without the Authority's consent, be used,
copied or communicated to a Third Party by the Concessionaire, except as necessary for
the purposes of this Agreement
Compliance with Laws and Directives
(i)
(ii)
The Concessionaire shall, in all matters arising in the performance of this
Agreement, comply with, give all notices under, and pay all Taxes, levies and
other similar charges required by the provisions of any Central or State law or
Directive or any regulation of any legally constituted public authority having
jurisdiction over the Project, the Site and the Assets. The Concessionaire shall
comply with all Applicable Laws.
In the performance of this Agreement, the Concessionaire shall ascertain and
comply with all relevant laws and Directives. The Authority will provide such
reasonable assistance as may be requested by the Concessionaire in ascertaining
the nature and extent of such relevant Applicable Laws and Directives.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 151 of 195
(iii)
(iv)
The Concessionaire shall indemnify the Authority, the Authority’s officers,
employees and agents against all governmental penalties and fines payable to a
Competent Authority, together with any reasonable legal expenses incurred in
connection therewith, to the extent arising out of any failure of the Concessionaire
or its employees to comply with any law or directive applicable to the Project,
the Site and the Assets during the performance of the duties, obligations and
responsibilities of the Concessionaire.
If the Concessionaire or the Authority finds any divergence between any Applicable
Law or Directive and the technical requirements under this Agreement, it shall give
to the Concessionaire a written notice specifying the divergence and proceed in
accordance with the terms and conditions of this Agreement.
24.10
24.11
Joint and Several Liability
If the Concessionaire is a joint venture of two or more Persons, all such Persons shall
be jointly and severally liable to the Authority for the fulfilment of the terms of this
Agreement. The composition or the constitution of the Joint Venture (JV) Members
shall not be altered without prior approval of the Authority and as per the specific
provisions in this regard provided in this Agreement.
Notice
Any notice to be given under this Agreement shall be deemed to have been duly given
upon receipt when in writing and delivered in person, by facsimile transmission, by telex
or by courier, addressed as follows:-
(a)
If to the Authority:
In the case of the Authority, all notices shall be given by facsimile or e-mail and
by letter delivered by hand and be addressed to the Engineer – in – Charge,
Public Works Division, Satara. Government of Maharashtra and to such other person as the Authority
may from time to time designate by notice to the Concessionaire.
(b)
If to the Concessionaire:
Address: ______________________________
Attention: _____________________________
Fax No: _______________________________
Phone: ________________________________
Any Party may change its address provided above for the purpose of this
Agreement by giving written notice to the other Parties of such change in the
manner hereinabove provided.
24.12
Language
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 152 of 195
The language of this Agreement is the English language. All correspondence, drawings,
designs, design data, Tests reports, certificates, specifications and information shall be
in the English language. All other written and printed matter required for
Implementation, operation and maintenance shall be executed in the English language.
Instructions and notices to the public and staff and all other signs and information
notices shall be in English and Marathi language only.
24.13
24.14
24.15
No Assignment
This Agreement shall not be assigned by the Concessionaire to any Person, save and
except with the prior consent in writing of the Authority, which consent the Authority
shall be entitled to decline without assigning any reason. The Concessionaire shall not
create nor permit to subsist any Encumbrance, or otherwise transfer or dispose of all or
any of its rights and benefits under this Agreement or any Project Agreement to which
the Concessionaire is a party except with prior consent in writing of the Authority, which
consent the Authority shall be entitled to decline without assigning any reason.
No Termination
The Parties hereby agree that the Concessionaire shall not exercise its rights, under
Applicable Laws and / or equity, to terminate this Agreement, without the prior written
consent of the Authority.
Counterparts
This Concession may be executed in 2 (two) counterparts, each of which when
executed and delivered shall constitute an original of this Agreement.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
Page 153 of 195
IN WITNESS WHEREOF the Parties have caused this agreement to be executed on the day
and year first hereinabove written and in the manner hereinafter mentioned.
SIGNED, SEALED AND DELIVERED for and on
behalf of the GOVERNOR OF MAHARASHTRA,
by the Executive Engineer, Public Works Division
Satara.
Witnesses:
1.
2.
SIGNED, SEALED AND DELIVERED by the within
named CONCESSIONAIRE,
____________________________
LIMITED, by the hand of
________________________________, its
authorized signatory in whose presence the
Common Seal of
________________________ LIMITED has
been affixed hereto pursuant to the resolution
passed by its board of directors on
________________________________.
Witnesses:
1.
2.
FINAL DRAFT CONCESSION AGREEMENT FOR CONSTRUCTION OF JANSUVIDHA KENDRA AT Rest
House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142 Road km.1/00
Tal.Khandala Dist.Satara, MAHARASHTRA.
I Scope of Work
II Format of Performance Security
III Calculation Method of Premium
IV The Site
V Format of Audit Report
VI Format of Certificate by Executive Engineer at Time of Completion
of Implementation
VII Format for Working of Premium Paid
VIII Consent for Subletting
IX Format for Agreement Completion Certificate
X Financial Model
XI Provisional Completion Certificate
XII Land Licence Agreement
Page 154 of 195
LIST OF SCHEDULES
Page 155 of 195
SCHEDULE – I
SCOPE OF WORK AND SPECIFICATIONS
The Concessionaire shall be required to develop Jan Suvidha Kendra for the Project titled
“Design, Build, Finance, Construction, Development, Implementation, Operation and
Maintenance of the Jan Suvidha Kendra, at Rest House Khandala Maharashtra”
The Concessionaire shall be required to conceptualize and design, build, finance, construct,
develop, implement, operate and maintain world – class, aesthetically pleasing, hygienic and
modern Jan Suvidha Kendra and the Project including without limitation the toilets, facilities for
provision of clean drinking water and having all required fittings, equipment and fixtures at the
Site including without limitation:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
Gents toilets – Urinals – 14 Nos. minimum - W/c - min. 4 including Women’s toilet – 10
Nos. Min. with sanitary napkin disposal system and physically challenged 1 Unit (unisex)
Drinking water with RO and water ATM facility.
Kitchen and restaurant facility with furniture.
Shops for general stores, ATM, food plaza, etc.
Shop for servicing of vehicles.
Security centre.
External and Internal beautification.
Children’s play area.
Internal roads,
Compound wall,
Sewage treatment plant and effluent treatment plant.
Provision of electrical work shall include but not limited to the following –
i)
ii)
iii)
iv)
v)
Street lights.
Solar lights
Internal electrical installations, with inverter facility.
CCTV installation
External electrifications including transformers, DG sets, etc.
m.
n.
Paving, parking place, park etc.
External water supply.
The following are the parameters that shall be ensured by the Concessionaire:
I.
JAN SUVIDHA KENDRA :
a.
b.
The Jan Suvidha Kendra shall have provision for required toilet seats men and
women as specified in the norms and specifications.
The Jan Suvidha Kendra shall be constructed in accordance with the following:
Area of the Site (in
square feet)
11202.19 Square Metre
Built up area (in square
feet)
699.27 Square Metre
Minimum Built – up
Area (in square feet)
Maximum Built – up
Area(in square feet)
Page 156 of 195
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
The Concessionaire shall develop toilets, to have other basic facilities, such as
hand washing, solid and menstrual waste disposal, baby pad changing table,
proper ventilation, lighting, security system for privacy shall have to be provided
for functional requirement.
Toilets shall have easy accessibility for handicapped and secure accessibility for
women. For persons with physical disabilities the design should provide facilities
such as ramp for access, hand rail inside the Jan Suvidha Kendra, etc., as per
specifications.
Standard area covered under the toilet shall be as per the drawings provided by
the Engineer – in – charge. Number of seats can be increased or decreased
depending upon the specific requirement and availability of space with the
approval of Authority.
Design should be user friendly, rugged, vandalism – proof and fire resistant to
ensure safety of equipment and installations as well as the Users.
Design should also take care of the requirements of maintenance and proper
accesses for cleaning of drains should be provided. Such accesses should be
leakage proof to ensure proper hygiene.
The specifications to be adopted for finishing items such as flooring, wall lining
etc. shall have to be of water resistant materials of 1st quality. Flooring to be anti
– slip and with proper drainage system.
For safety / rescue, break – ins of (internal) toilet doors should be part of design.
Green concepts in design such as use of natural lighting / ventilation, scientific
disposal of waste shall be encouraged.
The words “Jan Suvidha Kendra” in English and Marathi should be prominently
displayed on one panel in front on a properly lighted Billboard of minimum size
2’x8’.
The signage for entry for men, women and physically challenged should be
prominently displayed on the respective entry gates in English, Hindi and
symbols.
Page 157 of 195
m.
On the inside of the toilet, there should be information panels, prominently and
clearly displaying dos & don’ts, safety instructions, identification details of the
toilet, cleaning schedule, details about complaint registration system in place,
telephone number, e – mail address of Concessionaire’s nodal person for
receiving complaints, and telephone number of Engineer – in – charge, official
number for escalating the complaint (if not attended). These information panels
should be in Marathi and English. The information panels should be of good
quality, screen printed and sufficient size (small stickers not acceptable). The
mounting should be rugged and tempering proof.
II.
DEVELOPMENT CONTROLS:
The Concessionaire shall be required to construct the project only in the allotted
space/land as per prevailing byelaws, government rules, design and specifications
approved by the competent authority. Necessary Clearances regarding approach roads
to Project shall be taken from the Competent Authorities.
Following are the conditions that should be ensured:
A.
Common Instructions:
a.
b.
c.
d.
e.
f.
g.
h.
The construction / installation should be exactly as per the design, plan
and specification as mentioned in Project Report and as approved by the
Authority.
The septic tank in the Jan Suvidha Kendra should be constructed in such a
location to provide access to the vacuum truck to remove the septage if
sewer system is not present.
The toilet construction should not create unsecure spaces in or around it
causing safety concern.
Proper sewage connection to be ensured so that no water logging or
unhygienic conditions are created in or around the toilet.
The area around the toilet to be restored in proper manner and no debris,
building material, garbage, broken pavement / kerb – stones / interlocking
tiles / CC should remain within 10 meters of the toilet so constructed.
During the construction, the Concessionaire (or his contractors) shall ensure
proper upkeep for collecting debris and proper scientific disposal of debris.
Land / space for off-site pre – fabrication (if required) shall be organized by
Concessionaire at his own cost.
Construction / Installation should be of high quality and finish to ensure
proper cleaning, maintenance hygiene, prevent water logging and blockages
and to facilitate ease of maintenance.
Page 158 of 195
i.
j.
k.
l.
m.
n.
Lighting system should be adequate and all fixtures should be vandalism –
proof.
Plumbing should be of good quality UPVC / CPVC, water conserving, and
vandalism – proof.
Electricity and water connection from utility agency shall be obtained by the
Concessionaire.
Adequate fire – safety measures complying with all fire safety norms shall be
installed and maintained.
Concessionaire not only depending on the roof top tanks, has also required
to plan underground storage (of water) and pumping arrangements as per
capacity given.
In areas where frequent breakdown / load – shedding of electricity
(Concessionaire need to make an assessment of such locations),
Concessionaire may also be required to plan Inverter arrangements.
Generator causing air and noise pollution shall not be allowed to be used as
an alternate source of electricity except in exceptional circumstances.
B.
Instructions for displaying Advertisement for Concessionaire
a.
b.
c.
d.
e.
The Concessionaire shall be required to include the advertisement boards
design to the proposed sites in the Project Report shall be submitted to
Authority;
No Advertisement shall be displayed by the Concessionaire until the Jan
Suvidha Kendra has been made operational. Further, the Concessionaire
shall loose the right to display advertisement whenever the toilet, for any
reason, becomes non – operational;
70% of outside space in the plot assigned can be utilized for Advertisement
purpose; and,
The specific parameters with respect to height the display should be as per
laid down in the outdoor advertisement policy approved by Hon’ble
Supreme Court / High Court / Government Resolution thereof. The
advertisement shall also be strictly in accordance with the specific
provisions as laid down in the Authority, Acts, Bye-laws, all other terms &
conditions of allotment and outdoor advertisement policy of Authority.
The minimum specifications of the display shall be as follows:
i.
ii.
Material: All structures/frame to be made of galvanized steel.
The structure / frame to be treated with hot dip or hot sprays
galvanization.
Page 159 of 195
iii.
iv.
v.
vi.
vii.
viii.
All screws and nuts to be made of stainless steel and there should be
spot welding at all the nuts to prevent vandalism.
The structure / frame should be dimensioned to withstand local wind
gusts according to regulations.
The structure / frame to be properly powder coated for protection
against rusting.
All materials should be non – flammable.
All sharp corners should be eliminated.
Parts used should not be fragile and safety secured to its foundation
with 20 mm anchor fasteners or chemical fasteners which make the
furniture more stable and joint fasteners not visible from outside.
f.
Mandatory display of certain information on the advertisement site: The
advertiser shall display the following information on a board of size 2 feet by
1.5 feet on front side:
i.
ii.
Jan Suvidha Kendra / logo
Site location name
C.
CIVIL AND JOINERY WORK:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
RCC structure.
Plinth 600mm.
External walls 230mm in AAC Block masonry
Internal walls 115mm
Internally 20mm neeru finished plaster
Externally 20mm sand faced plaster
1000 X 1000 mm Rustic Finished Vitrified Tiles
600 X 600 mm Glazed Vitrified tiles for Dado in Kitchen, washing area.
600 X600mm Rustic Tiles for flooring in Toilets.
ACP/ metacular sheets/GRC sheets/ tensile roof sheets.
UPVC doors and all window frames.
Toughened glass doors, partitions (frontage of shops).
Page 160 of 195
m.
n.
o.
p.
q.
r.
s.
t.
u.
v.
w.
x.
y.
z.
aa.
bb.
Sliding windows with glass and UPVC frames.
Perforated sheet for Rolling shutters.
Parryware/hindware/ Kohler Sanitary appliances with soft close toilet seats.
Jaguar plumbing accessories with sensor systems.
UPVC/CPVC pipes for piping.
Rain water harvest to bore.
STP with waste water treatment tank.
Solar lights/ LED Lights in entire campus.
Fixed granite furniture in pantry.
Enough CCTV camera.
LED lights in centre.
Under ground water tank of 1,00,000 litres capacity. And 50,000 litres
capacity overhead tank.
Covered shed for generator, gas storage in separate compartment with
piped gas connections in kitchen.
Lustre paint internally and apex paint externally.
Concrete floored roads for parking and in premises.
GRC screen walls @ 15 sqmts.
D.
Toilet Unit:
a.
b.
c.
d.
e.
Basic structure shall comprise of AAC / brick masonry and RCC roof slab to
be constructed as per relevant IS codes.
Cement plaster in ratio of 1:4 (one cement: 4 coarse sand) shall be provided.
Flooring shall comprise of granite / Vitrifiedas per the specifications and the
colour as approved by Authority.
8” x 12” glazed tile dado up to 7”-00” height shall be provided except in the
store and entrance area. The make & colour shall be as approved by
Authority.
Min. 4” high skirting shall be provided of the same material as of the flooring.
Page 161 of 195
f.
g.
h.
i.
j.
k.
l.
m.
Granite frames for all doors and windows.
Door shutter of min 35mm thick with granite frame and panel of pre -
laminated board shall be provided. FRP doors for toilet blocks shall be
provided.
Anodised aluminium sliding window shall be provided.
Wash hand basins shall be provided in the counters as indicated in the
drawing.
The counter shall be of granite.
Approaches to the toilets shall be provided from pathways and adjoining
areas as feasible. Such approaches shall be laid with precast paver blocks of
at least 40mm thickness.
External finish shall be of factory manufactured precast tile cladding of the
size and colour to be approved by Authority.
Internal wall surface shall be finished with good quality plastic emulsion
paint of make and shade to be approved by Engineer – in – charge.
E.
Fittings and fixtures:
a.
b.
c.
d.
e.
f.
g.
The ceramic fixtures shall be of first quality white / coloured and of the
reputed makes such as Jaguar / hindware / Kohler etc. as approved by
Authority.
Round / oval wash hand basins shall be provided.
First quality C.P. fixtures and fittings shall be of the reputed make such as
Jaquar, Hindware/ Kohler etc. as approved by Authority.
The required numbers of EWC and one Indian Type Orissa Pan WC with
flushing valve shall be provided. The men and women section should not be
together and should be separate. The pans should be manufactured by a
company which has Bureau of Indian Standards approval. Arrangements for
use by physically challenged person be also made or a separate WC facility
which is friendly for physically challenged person be carved out in the toilet
block.
Liquid soap dispenser shall be provided for wash hand basin for ladies &
gents use.
Mirrors with full width of counter of wash hand basin of Belgium / Modi
Float make shall be provided.
Page 162 of 195
h.
i.
j.
Water filter with RO, water cooler or Mineral water dispenser shall be
provided for drinking water.
At least two hand driers shall be provided of the make as approved by
Authority.
All other accessories shall be provided of the make to be got approved from
Authority.
F.
Electrical:
a.
b.
c.
d.
e.
Concealed conduit pipe with standard copper wire (ISI marked) shall be
provided.
Plate type switches and accessories of standard make such as Legrand /
MK, Anchor, etc.
Electrical layout drawings shall be approved by Authority.
Exhaust fans/ fresh air fans of any of the reputed makes such as Crompton
Greaves / Havells / BAJAJ, etc. shall be provided.
Arrangement of alternate source of energy (Solar energy) shall be provided
with compatible electric layouts, fittings & fixtures.
G.
General:
a.
Tensile structure as per drawing shall be provided.
Double wall
polycarbonate sheet roofing shall be provided over the skylight etc. as per
the drawings approved by Authority.
b.
c.
d.
e.
f.
Water proofing treatment as per PWD specifications shall be provided over
the roof in addition to the terracing.
The external treatment of the walls such as GRC ( ) shall be got approved
from Authority.
The illumination of the advertisement panel shall be as per the requirement
and as permitted by the civic authorities.
The layout and facilities provided shall be universal design.
The Jan Suvidha Kendra built should be physically challenged friendly.
Note: The make and colour of all fittings and fixtures shall be subject to
approval of Authority.
The allotment of work is subject to modifications in the specifications and
compliance of guidelines as may be prescribed from time to time.
Page 163 of 195
III.
Construction Guidelines:
The following are the construction guidelines shall be incorporated and implemented in
the Project Report and shall be submitted by the Concessioner for approval of Authority:
a.
b.
c.
d.
e.
f.
The inside height of Toilet complex should be as per drawings. The layout of the
toilet block would depend on the availability of space and other local conditions.
The sketch plan in the Project Report of the proposed toilet blocks of each site
indicating the minimum specifications to be adopted along with tentative key plan
etc. are enclosed. The Concessionaire shall prepare the working drawings based
on the site, ground and infrastructure details in consultation with Authority and
get it approved from competent authority (ies) before start of construction
activity.
The floor should slope gently towards the floor trap. The floor of W.C area should
be sunk to avoid the flow of water outside the W.C area.
Internal finishing shall be done as approved by Authority.
All water pipes, drainage and waste pipes would be concealed.
The lay out plan containing sites, orientation etc. of latrines and urinals and
showing plumbing lay out and various fixtures like taps, water closets, cisterns,
sinks, mirror etc. including electrical fixtures as also materials to be used for
different purpose should be got approved from Authority. The plan should also
show disposal of sewage and sewerage drains.
g.
The
Concessionaire
is
entirely
responsible
for
the
design,
construction/installation, maintenance and removal of all temporary works
employed. The Concessionaire shall be responsible for the safety of the works,
operatives, adjoining property, structures of services and compliance with
appropriate regulations and codes of practice.
h.
i.
The areas around each toilet block shall be constructed / installed/ developed by
proper approaches from pedestrian pathways and from all sides as feasible and
paved by paving blocks and same shall be maintained by the Concessionaire and
free from any obstructions and encroachments. The adjoining areas upto 10
mtrs. From the external face of the toilet block subject to availability of area,
shall be landscaped, kept green & maintained. The area shall be kept well lighted
by the Concessionaire at his cost.
During construction/installation, all services or utilities on or adjoining the Project
site which are required to be maintained operational shall be protected from
movement, subsidence or damage from any cause whatsoever by adequate
temporary props, struts, shores and protective screens to the
installed/developed.
j.
The Concessionaire shall be responsible for adhering to safety regulations for
Users and workman’s as notified under Law.
Page 164 of 195
k.
l.
m.
n.
o.
p.
q.
r.
s.
PVC insulated cables shall be used in general for internal wiring purposes as per
Bureau of Indian Standard (BIS) amended up to date and mentioned in the IS
Standard.
All Civil/building/structural works shall conform to Public Works Department
(PWD) specifications for class-1 building works and standards as given in the
National Building Code (NBC) guidelines.
The Concessionaire shall construct structurally sound and aesthetically appealing
facilities to the satisfaction of the Authority as per working drawings approved by
the competent authority. However, in areas where deviations are necessitated
due to space or locational constraints, the Authority shall permit variation.
After completion of each facility, the Concessionaire shall provide 5 sets of
Project Reports including plans/Drawings of various services provided therein e.g.
electricity, water supply, sewerage, drainage etc., indicating covered area,
advertisement area along with inventory of various fittings and fixtures.
The Concessionaire shall plant flowering and other shrubs in the campus and
water them subject to the plan approved by the Authority.
The electricity and water charges for construction, running and maintenance of
toilet including the adjoining area shall be borne by the Concessionaire and will
be paid directly to the concerned authorities by the Concessionaire.
Proper arrangement shall be made by the Concessionaire to avoid any hindrance
to the traffic during construction, operation and maintenance of the Public
Conveniences. Diversion of traffic, if required, shall be arranged by the
Concessionaire as per traffic police requirements at his own cost.
The Concessionaire shall obtain necessary electricity, water and sewerage
connections from the respective authorities in his / her own name and shall be
responsible for clearance of all the dues for the contract period, in time. On the
part of the Authority, only a ‘No Objection Certificate’ shall be issued on a specific
request, to enable the Concessionaire to obtain electricity / water / sewerage
connections in his / her name or in the name of his / her firm. Proper sewerage /
drainage treatment shall be done by the Concessionaire, wherever required.
The Concessionaire shall take all precautions to avoid any accidents during
construction / repair / maintenance / operation of the toilet blocks, electrical /
sanitary fittings and fixtures. If any accident occurs during construction / repair /
maintenance / operation of Public Conveniences / fittings and fixtures, the
Concessionaire shall be directly responsible for the damages or any other
consequences, whatsoever and Authority shall be kept harmless.
IV.
Operation and Maintenance Guidelines:
a.
The Jan Suvidha Kendra shall remain open 24 hours a day including Sunday and
holidays except under exceptional circumstances when this is not possible.
Utility Service Output Maximum Tolerance
Level
Permissible time
limit for
repairs/
Toilet floor Smooth and free
from cracks, chipping
or any other similar
damage.
Keep clean, dry,
without any litter,
stain etc.
Nil rectifications Repaired/ rectified
within 7
day.
Debris/garbage/othe
r litter shall be
removed
immediately upon
detection
Damaged/dysfunctio
nal
dustbins/spittoons
shall be
repaired/replaced
immediately upon
Page 165 of 195
b.
c.
d.
e.
f.
g.
The designated premises shall be serviced, cleaned and maintained according to
the Authority’s requirements on all 7 days of the week with no exceptions except
in the case of Force Majeure as specified in this Agreement.
The liquid soap shall be made available at free of cost at all time during
operation.
The Concessionaire shall make own arrangement for security of the toilet block
and its fixtures.
The Concessionaire shall furnish the names of the persons who have been
appointed as attendant/caretaker for the toilet blocks and their names will be
registered with the Authority. The said attendant/caretaker of the Concessionaire
shall not allow any other person to occupy the toilet blocks.
The Concessionaire shall ensure that each toilet structure displays a sign saying
“built and maintained by M/s < Concessionaire > for Authority along with the
logo of Authority and well lit “Community toilet” prominently on the walls. The
height of these letters shall be at least 15 cms.
The Concessionaire will not allow any person to use Public Convenience for
residential purpose or for stocking of any material etc, and not keep any animal
in or around the complex other than two attendants – cum – sweepers at each
toilet block, one for men and second for women to ensure continuous service.
V.
Maintenance schedule and standards
The Concessionaire shall adhere to the conditions set out in Table 1 and Table 2
below: Table - 1
the detection
Advertising
panels and
supporting
structures
No Cracks,
breakages or
corrosion of metal
surfaces
No stains
No
defaced/discoloured
surface
Not more than 5% of
surface shall be
damaged/defaced/discol
oured, subject to, the
damaged/defaced/discol
oured area not
exceeding a maximum
area of 1 Sqm in one
single patch.
Repaired/rectified
within 7
days from detection
Chairs/seats Shall be clean and
free from Damage
Nil Repair/replace in 2
days
Information
boards/sign
ages
Visible legible and
functional
Nil Obstructions shall
be
removed
immediately upon
the detection
Dirty information
boards/signage
shall be cleaned
immediately upon
the detection
Damaged
information
boards/signage
shall be
repaired/replaced
within 24 hours of
detections
Page 166 of 195
No. Particulars Specifics
1 Replacement of worn/damaged all plumbing
fittings on regular basis as and when damaged
broken/
Bib cocks, Urinal push cocks,
all
CP fittings, Orissa pans,
European water closets,
wash basins urinal pans,
flush tanks, float valves, GI
pipe fittings, Nahani Traps,
Gratings
2 Replacement of damaged/spoiled all
electrical fixtures on regular basis as and
when damaged/broken
Light fixture, Electrical
bulbs, bulk headlights, fuses,
MCB’s, Meters.
3. Regular repairs as and when damaged Water lifting pumps and
accessories,
water level controller
Page 167 of 195
Lights
All lights fully
functional and
illumination as per
construction
requirements
100% of the light shall
be fully functional
Any faulty light
bulb/tube shall be
repaired/replaced
within 24 hours of
detection
Table – 2
4. Attending regular repairs Clearing the blockages in
water closest/sanitary line.
5. Replacement of other fixtures Towel rods/ring, C.P soap
Dispensers, Broken mirrors,
CP paper holders
6. Replacement of pipes damages/ Broken All exposed GI, soil pipes,
PVC pipes.
7. Replacement of RO unit
Page 168 of 195
VI.
Maintenance of Records
The Concessionaire shall maintain all the records of:
a.
b.
c.
d.
The bills paid to service providers like water and power supply etc.;
Record on number of Users using the Jan Suvidha Kendra;
A Suggestion Book for the Users; and,
The Concessionaire shall maintain proper books of accounts of the advertisements displayed
from time to time submit details of the same at time of making payment of advertisement
tax and produce the relevant books of accounts, as and when specifically required by the
Authority.
The toilet unit should be kept odour free by carrying out the following activities:
a.
b.
c.
d.
Timely cleaning of all the sanitary fixtures by the management staff;
Use of air fresheners in the WC and the urinal area;
Use of exhaust fans in all passages and corridor of the Jan Suvidha Kendra;
Design of the Jan Suvidha Kendra will provide for maximum natural ventilation and lighting;
and,
No PARAMETERS YES N
O
N
A
I CATEGORY A
1 Water supply
Page 169 of 195
e.
Greening and landscaping around the Jan Suvidha Kendra and the adjacent walls to
discourage the misuse of its surroundings and improve ambience.
The toilet block must be kept dry at all times in the following manner:
a.
b.
c.
d.
The sanitary fixture will be dry at all times so as to give the same quality to all
customers.
The seat for the EWC will be kept dry.
All the fixtures will be kept clean at all times so as to give every customer the same
quality of cleanliness of the facility.
Periodic flushing of the urinal, and periodic cleaning by the staff using standard
cleaning agents and procedures.
e.
Periodic cleaning of the WC’s by the
staff using standard cleaning agents and
procedure.
Public convenience will be provided with good quality consumables, including the following:
a.
b.
c.
The liquid soap/soap cakes of standard quality and make, which will be provided in the
wash basins;
The public convenience rolls will be of standard quality and make; and,
The quality of hand driers are maintained in proper condition for the customer’s
usage.
The consumables to be available at all times and will be replaced as soon as required. To
facilitate this, enough stock of the consumables for at least a week will be made available at all
times. This will include:
a.
b.
c.
d.
Replacement of all consumables as and when required.
Repair any defective fixture before next use and all replacement shall be of original
specifications and design.
Provide clean and dry consumables for each customer.
The Concessionaire shall have kept and maintain at the public convenience an
inspection card containing the following details:
2 Electricity
3 Drinking Water
II CATEGORY –B
1 Toilet Block - Interior; Odour free
2 Flooring; Dry & Clean
3 Consumables: Adherence to quality
recommended
4 Exhaust fans & automatic hand driers
5 Advertisement - adherence to standards
6 Consumables: Stock as per standards
7 Dress code / Uniform - Adherence to standards
8 Availability of cleaning equipments
9 Book keeping - Suggestion Book & complaint
register
III CATEGORY –C
1 Walls; Dry & Clean
2 Washbasin Dry & Clean
3 Litterbins; Clean
4 Windows; Clean
5 Door; Clean
6 Glass (Windows & ventilators); Clean
7 Mirror; Clean
8 Waiting area; Clean
9 Litterbin clean
10 Landscaping Maintenance
11 External building Surface Clean
12 Surroundings Clean
13 Tickets format - adherence to standards
14 Book keeping - Consumables stock
15 Behaviour of staff
16 Communication
Page 170 of 195
Page 171 of 195
SCHEDULE – II
FORMAT OF PERFORMANCE SECURITY
(Bank Guarantee)
PERFORMANCE BANK GUARANTEE OF CONCESSIONAIRE
Bank Guarantee No.:
Dated:
Issuer of Bank Guarantee:
Name of the Bank
____________
____________
(hereinafter referred to as the “Bank”)
Beneficiary of Bank Guarantee:
Executive Engineer, Public Works Division, Satara.
Nature of Bank Guarantee:
Unconditional and irrevocable Bank Guarantee.
Context of Bank Guarantee
Performance during Concession Period in respect of draft Agreement to be executed amongst the
Executive Engineer, Public Works Division, Satara (“hereinafter referred to as the
Authority), and (hereinafter referred to as the “Concessionaire”) for the Project titled “Design, Build,
Finance, Construction, Development, Implementation, Operation and Maintenance of the Jan
Suvidha Kendra, at Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, Maharashtra” (hereinafter referred to as the “Project”),
provided however, such context of the Bank Guarantee or reference to the Agreement in this Bank
Guarantee shall in no manner be relied upon at any stage to adversely affect or dilute the unconditional
and irrevocable nature of this Bank Guarantee. The title of this Guarantee i.e. “Performance Security”
shall in no manner and at no stage be relied upon to adversely affect or dilute the unconditional and
irrevocable nature of this Bank Guarantee. The Contract of Bank Guarantee is an independent Contract
between the Bank and Executive Engineer, Public Works Division, Satara and is not
dependent upon execution or performance of any Agreement amongst Executive Engineer, Public Works
Division, Satara and __________________________________ (name of the Concessionaire).
Operative part of the Bank Guarantee:
1.
At the request of the Concessionaire, we __________
,
(name and address of the bank),
hereinafter referred to as the “Bank”), do hereby unconditionally and irrevocably affirm and
undertake that we are the Guarantor and are responsible to the Executive Engineer, Public
Works Division, Satara i.e. the beneficiary on behalf of the Concessionaire, up to
a total sum of Rs. ____________________________ (Rupees _____________________________
only), such sum being payable by us to (short form of the ULB _____________________),
immediately upon receipt of first written demand from the Executive Engineer, Public Works Division, Satara.
Page 172 of 195
2.
3.
4.
5.
6.
7.
We unconditionally and irrevocably undertake to pay to the Executive Engineer, Public Works
Division, Satara demand from and without any cavil or argument or delaying tactics
or reference by us to Concessionaire and without any need for the Executive Engineer,
PWDivision, Satara to convey to us any reasons for invocation of the Guarantee or
to prove the failure to perform on the part of the Concessionaire or to show grounds or reasons for
the demand or the sum specified therein, the entire sum or sums within the limits of Rs.
______________________ (Rupees ________________________________ Only).
We hereby waive the necessity of the Executive Engineer, PW.________ Division, ________
demanding the said amount from Concessionaire prior to serving the Demand Notice upon us.
We further agree and affirm that no change or addition to or other modification to the terms of the
Agreement, shall in any way release us from any liability under this unconditional and irrevocable
Guarantee and we hereby waive notice of any such change, addition or modification. We further
agree with the Executive Engineer, P.W.Division, Satara form of the ), that the shall be the sole
and the exclusive judge to determine that whether or not any sum or sums are due and payable to
him by Concessionaire, which are recoverable by the ( ), by invocation of this Guarantee.
This Guarantee will not be discharged due to the change in constitution of the Bank or the
Concessionaire. We undertake not to withdraw or revoke this Guarantee during its currency/
validity period, except with the previous written consent of the ______________________.
We unconditionally and irrevocably undertake to pay to the_____________ , any amount so
demanded not exceeding Rs. _______________ (Rupees __________________________ only)
notwithstanding any dispute or disputes raised by Concessionaire or anyone else in any suit or
proceedings before any dispute review expert, arbitrator, court, tribunal or other authority, our
liability under this Guarantee being absolute, unconditional and unequivocal. The payment so
made by us under this Guarantee to the ______________, shall be a valid discharge of our liability
for payment under this Guarantee and the Concessionaire shall be a valid discharge of our liability
for payment under this Guarantee and the Concessionaire shall have no claim against us for
making such payment.
This unconditional and irrevocable Guarantee shall remain in full force and effect and shall remain
valid until ___________. This Bank guarantee shall be payable at city of the Public Works
Division, Satara at Satara branch of the bank ____________________
Notwithstanding anything contained herein:
1.
2.
3.
Our liability under this Bank Guarantee shall not exceed Indian Rs. __________________
(Rupees _________________________________ only).
This unconditional and irrevocable Bank Guarantee shall be valid w.e.f. to ____________.
We are liable to pay the guaranteed amount or any part thereof under this unconditional and
irrevocable Bank Guarantee only and only if the Executive Engineer, P.W.Division, Satara serves
upon us a written claim or demand on or before ______________.
Authorized Signatory for Bank
Sr. No. Particulars Unit Amount
1. Ready Reckoner rate of the land area as per IGR
Calculations
Rs. 12,50,000
2. Multiplier for Land valuation 5
3. Market value of land (Sr. No. 1 X Sr. No. 2) 62,50,000
4. Rental income % in the area
(This may vary from place to place according to location
of the land)
8%
5. Annual premium for year 1 (Sr. 3 X Sr. 4) 5,00,000
6. Rate of interest considered for calculating present value
of rent
12%
7. Present value of rent calculated as Table P-1
Page 173 of 195
SCHEDULE – III
CALCULATION METHOD FOR PREMIUM
Premium shall be calculated for as per following method:
This example is for illustration purpose, one should run financial model for the calculation.
Table P-1
Year From
Period To
Rent Increase for the year
IRR % NPV
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
01-06-17
01-06-18
01-06-19
01-06-20
01-06-21
01-06-22
01-06-23
01-06-24
01-06-25
01-06-26
01-06-27
01-06-28
01-06-29
01-06-30
01-06-31
31-05-18
31-05-19
31-05-20
31-05-21
31-05-22
31-05-23
31-05-24
31-05-25
31-05-26
31-05-27
31-05-28
31-05-29
31-05-30
31-05-31
31-05-32
500000
550000
605000
665500
732050
805255
885781
974359
1071794
1178974
1296871
1426558
1569214
1726136
1898749
0%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
446429
438457
430627
422937
415385
407967
400682
393527
386500
379598
372819
366162
359623
353202
346894
Present Value of
Land Rent
Working for incremental revenue in case of increase in market value of the property
Table P-2
5920809
Ye
ar
Period
Ready
reckoner
rate at the
begining of
the year
Multip
lier
( Land
Aquisit
ion
Value)
Rent
al
Inco
me
(%)
Revise
d
Rental
Incom
e
Original
Rental
income
considered
for financial
model
Differe
nce
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
From To Rs
1 01-
06-17
31-
05-18 1250000 5.00
6,250,0
00
8.00
% 500,000 500000 0
2 01-
06-18
31-
05-19 1406250 5.00
7,031,2
50
8.00
% 562,500 550000 12500
3 01-
06-19
31-
05-20 1582031 5.00
7,910,1
56
8.00
% 632,813 605000 27813
4 01-
06-20
31-
05-21 1779785 5.00
8,898,9
26
8.00
% 711,914 665500 46414
5 01-
06-21
31-
05-22 2002258 5.00
10,011,
292
8.00
% 800,903 732050 68853
6 01-
06-22
31-
05-23 2252541 5.00
11,262,
703
8.00
% 901,016 805255 95761
7 01-
06-23
31-
05-24 2534108 5.00
12,670,
541
8.00
%
1,013,6
43 885781 127863
8 01-
06-24
31-
05-25 2850872 5.00
14,254,
358
8.00
%
1,140,3
49 974359 165990
9 01-
06-25
31-
05-26 3207231 5.00
16,036,
153
8.00
%
1,282,8
92 1071794 211098
10 01-
06-26
31-
05-27 3608134 5.00
18,040,
672
8.00
%
1,443,2
54 1178974 264280
11 01-
06-27
31-
05-28 4059151 5.00
20,295,
756
8.00
%
1,623,6
61 1296871 326789
12 01-
06-28
31-
05-29 4566545 5.00
22,832,
726
8.00
%
1,826,6
18 1426558 400060
13 01-
06-29
31-
05-30 5137363 5.00
25,686,
817
8.00
%
2,054,9
45 1569214 485731
14 01-
06-30
31-
05-31 5779534 5.00 28,897, 8.00
% 2,311,8 1726136 585678
Page 174 of 195
Page 175 of 195
669
14
01-
31-
32,509,
8.00
2,600,7
15 06-31 05-32 6501975 5.00 877 % 90 1898749 702041
In the above table P-2, department will change the amount in column (4).
Sr.
No. District Name of road Location
Available
area of
Land ( Sq.
M)
P.W. Circle Satara.
1. Satara Khanda on Khandala Koregaon
Rahimatpur Karad Sangli Shirol
S.H.142 Road km.1/00 Tal.Khandala
Dist.Satara.
AT Rest House Khanda 11202.19
Page 176 of 195
SCHEDULE – IV
THE SITE
No PARAMETERS Maximum
Marks
Marks
Obtained
I Group A - 101
1 Drinking Water 30
RO In working condition 6
Regular Servicing of RO 6
Cleaning of water storage tank 6
Water glass availability 6
Leakages and cleanliness at Water drinking area 6
2 Toilet Facility 30
Toilet Block - Interior; Odour free 6
Condition of CP Fixture, pipes, washbasin, Mirror 3
Flooring; Dry & Clean 3
Exhaust fans & automatic hand driers 3
Soap Dispenser 3
Availability of cleaning equipment 3
Storage Tank and Water Supply 3
Leakages of Water Tap, plumbing Leakages 3
Cleaning Register 3
3 Parking 10
Parking space availability 3
Parking management 2
Condition of Shed 3
Condition of Pavement, Marking 2
4 Electrification in premises 10
Lighting in Parking area 2
Lighting in Toilets 2
Lighting in Canteen 2
Lighting in Porch 2
Lighting on Advertising Area 2
5 Overall Cleanliness 21
Overall Premises, Odour free 10
Dress code / Uniform for housekeeping staff- Adherence to
standards
5
Dustbin 6
Page 177 of 195
SCHEDULE – V
FORMAT OF AUDIT REPORT
Check list and Mark list for Audit
Page 178 of 195
II
1
Group B
Structure
Status of Fabricated Structures -
Advertising Flex,
Parking Shed,
Entrance Gate,
Mobile Tower
5
5
5
5
99
20
2
3
4
5
III
Civil Work
External Walls
Internal Wall
Compound Wall,
External Paints
Internal Paints
Doors, Windows, Shutters, Ventilators
Underground Water tank
Roof, Ceiling, Tensile structure
Electrical
Overall Internal Electrical Installations
Street lights
D G Set, inverter, power back up Misc
Landscaping
Children Play area
Book keeping - Suggestion Book & complaint register
Information and Display Board
Behaviour of staff
Communication
Canteen
Sufficient Furniture in restaurant
Cleanliness in Restaurant area
Cleanliness in Kitchen area
Licence from Food & Drug Authority
Quality of Food
Consumables: Stock as per standards
Consumables: Adherence to quality recommended
Total Group A + Group B
4
4
4
4
4
4
4
4 4
4
4
3
3
3
3
1
1 3
3
3
3
3
3
3
32
12
14
21
200
Sr. No. Particulars Negative marks
1. Employed any labour not permissible as per Article
10 of this agreement
40 marks
2. Has not taken any of necessary permission as
required as per Article 10 of this agreement
40 marks
3. Has done any activity beyond sanction design/plan,
in contravention with Applicable Laws, the terms
and conditions of this Agreement, the Clearances
and Good Industry Practice.
40 marks
4. Has done construction / development beyond the
land allotted to Concessionaire
40 marks
Page 179 of 195
** There shall be a negative marking on event occurring as follows,
Page 180 of 195
SCHEDULE – VI
CERTIFICATE BY EXECUTIVE ENGINEER AT TIME OF COMPLETION OF
IMPLEMENTATION
(Format of Certificate to be issued by Executive Engineer as per the Agreement for
Implementation completion of construction work of Jan Suvidha Kendra and
achievement of commercial operation date)
------ On the letter head of the Executive Engineer --------
Date _____
To,
Name and Address of Concessionaire
Sub : Issuance of Implementation completion certificate for Jansuvidha Kendra located at
Rest House Khandala on Khandala Koregaon Rahimatpur Karad Sangli Shirol S.H.142
Road km.1/00 Tal.Khandala Dist.Satara, MAHARASHTRA.
Ref: 1. Work order / LOA issued for said project, by this office no.____ dated ___
2. Your request letter no.____ dated____
3. Report from Deputy Engineer, Public Works Sub-Division, Khandala dated _____
Sir,
This is to certify that, work allotted to you for construction / Implementaion of Jansuvidha
Kendra at Rest House Khandala has been successfully completed by you. Details of the same are as
follows;
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Bid Due Date
Reference Date for Bid Price
Appointed Date
Construction Period
COD
Operations Period
Concession Period
Concession Period Closure
One time Premium paid towards land rent at the time of Bid
Amount of Performance Security deposit not to be released
till termination
Whether project constructed on allotted land?
Is construction as per specification?
(If not, same shall be reported in this letter with a separate
annexure)
Whether all services are working?
(If not, same shall be reported in this letter with a separate
annexure)
Project Completion cost (Excluding cost as per sr no.
9, Interest during construction if any)
Breakup of the same is as follows
a. Cost of Civil Structure
Page 181 of 195
b. Cost of Furniture
c. Cost of Kitchen Equipments
d. Other structure (if Any)
You may start operations immediately on the receipt of this letter.
Executive Engineer,
P W Division,Satara.
Page 182 of 195
SCHEDULE – VII
FORMAT FOR WORKING OF PREMIUM PAID
Working for calculation of Premium
At the time of
Bid
Year Period Rent Increase ROI % NPV
From To for the
year
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
01-06-17
01-06-18
01-06-19
01-06-20
01-06-21
01-06-22
01-06-23
01-06-24
01-06-25
01-06-26
01-06-27
01-06-28
01-06-29
01-06-30
01-06-31
31-05-18
31-05-19
31-05-20
31-05-21
31-05-22
31-05-23
31-05-24
31-05-25
31-05-26
31-05-27
31-05-28
31-05-29
31-05-30
31-05-31
31-05-32
380016
418017
459819
505801
556381
612019
673221
740543
814597
896057
985663
1084229
1192652
1311917
1443109
0%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
10%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
12%
339300
333241
327290
321446
315705
310068
304531
299093
293752
288506
283354
278295
273325
268444
263651
Present Value of
Land Rent 4500000
Name of tenant
Status of Tenant Individual / Partnership Firm
Communication address
Permanent Address
Contact Person
Contact Number
Email Id
Name of Business activity
Business activity
Number of labour / staff employed at the unit
Female staff employed
Business hours
Period of agreement From ----------- to ------------
Page 183 of 195
SCHEDULE – VIII
CONSENT FOR SUB LETTING
-------- on the letter head of Executive Engineer Public Works Division,Satara.
To,
Name and Address of Concessionaire
Sub: Issuance of No Objection certificate for sub letting of unit no. ___ at Jansuvidha Kendra
located at Rest House Khandala
Ref: 1. LOA issued for said project, by this office no.____ dated ___
2. Your request letter no.____ dated ____
Sir,
With reference to your request letter for obtaining permission of sub letting of unit no. ___ at
Jansuvidha Kendra located at Rest House Khandala, this office is issuing you the No
Objection certificate, credentials of the same are as follows,
You may please note that, period of agreement mentioned above shall be ending with earliest
of following,
a. Termination date of the project ( if any)
b. Concession Period Closure
c. End of agreement date as per your agreement with your tenant.
In case of any event prior to end of your agreement with your tenant, where you are required
to hand over the project to the department, the tenant is required to vacate the premises
allotted to him without any claim.
1. Bid Due Date
2. Reference Date for Bid Price
3. Appointed Date
4. Construction Period
5. COD
6. Operations Period
7. Concession Period
8. Concession Period Closure
9. One time Premium paid towards land rent at the time of Bid
10. Details of structure and furniture handed over to authority
has been annexed herewith as separate annexure along with
photographs
Page 184 of 195
SCHEDULE – IX
FORMAT FOR AGREEMENT COMPLETION CERTIFICATE
------ On the letter head of the Executive Engineer Public Works Division,Satara.
Date _____
To,
Name and Address of Concessionaire
Sub : Issuance of agreement completion certificate for Jansuvidha Kendra located at
Rest House Khandala
Ref: 1. Work order / LOA issued for said project, by this office no.____ dated ___
2. Your request letter no.____ dated____
3. Report from Deputy Engineer, Public works Sub-Division, Khandala dated _____
4. Implementation completion certificate issued by this office no. __ dated ____
Sir,
This is to certify that, work allotted to you for construction / Implementation of Jansuvidha
Kendra at Rest House Khandala has been successfully completed by you and Concession / agreement
/ operation period for the same has been completed. Details of the same are as follows;
This certificate has been issued in accordance with the Concession Agreement dated
_____________________________
For,
Executive Engineer,
Public Works Division, Satara.
Authorised representative of Concessionaire
_________.
Page 185 of 195
SCHEDULE – X
FINANCIAL MODEL AND VARIOUS FORMATS FOR CALCULATION OF
TERMINATION PAYMENT
Page 186 of 195
SCHEDULE – XI
PROVISIONAL COMPLETION CERTIFICATE
(Format of Certificate to be issued by Executive Engineer as per the Agreement for
Provisional Completion of construction work of Jan Suvidha Kendra)
------ On the letter head of the Executive Engineer, Public Works Division, Satara.
Date _____
To,
Name and Address of Concessionaire
Sub : Issuance of Provisional Completion Certificate for Jansuvidha Kendra located at
Rest House Khandala
Ref:
1. LOA issued for said project, by this office no.____ dated ___
2. Your request letter no.____ dated____
3. Report from Deputy Engineer, Public works Sub-Division, Khandala dated _____
Sir,
This is to certify that, work allotted to you for construction / Implementation of Jansuvidha
Kendra at Rest House Khandala has been successfully completed by you. Details of the same are as
follows;
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Bid Due Date
Reference Date for Bid Price
Appointed Date
Construction Period
COD
Operations Period
Concession Period
Concession Period Closure
One time Premium paid towards land rent at the time of Bid
Amount of Performance Security deposit not to be released
till termination
Whether project constructed on allotted land?
Is construction as per specification?
(If not, same shall be reported in this letter with a separate
annexure)
Whether all services are working?
(If not, same shall be reported in this letter with a separate
annexure)
Project Completion cost (Excluding cost as per sr no.
9, Interest during construction if any)
Breakup of the same is as follows
Page 187 of 195
d.
e.
f.
g.
Cost of Civil Structure
Cost of Furniture
Cost of Kitchen Equipments
Other structure (if Any)
You may start operations immediately on the receipt of this letter, subject to completion of the
punch list items and the terms and conditions of the Concession Agreement dated
__________________________
Executive Engineer,
P W ___ Division,
_________.
Page 188 of 195
SCHEDULE – XII
LAND LICENCE AGREEMENT
THIS LAND LICENCE AGREEMENT (the “Agreement”) is entered into on this the
________________ day of _______________________ at ____________________________
BETWEEN
PARTIES:
THE GOVERNOR OF MAHARASHTRA, through the Executive Engineer, Public Works
Division , Satara. (hereinafter referred to as the “Licensor”) which expression
shall, unless the context otherwise requires, include its administrators, successors and assigns)
of the ONE PART;
AND
___________________________________ LIMITED, a company within the meaning
of the Companies Act, 2013 with Corporate Identification Number (C.I.N.)
__________________________ and having its registered office at
_______________________________________________________ (hereinafter referred to as
the “Licensee” which expression shall, unless the context otherwise requires, include its
successors and permitted assigns) of the OTHER PART.
The Licensor and the Licensee are hereinafter, collectively referred to as, the “Parties” and
each, individually as a “Party”.
WHEREAS
(A)
(B)
The Licensor and the Licensee have entered into a Concession Agreement dated
_____________________ (the “Concession Agreement”) whereunder the Licensee
has agreed to “DESIGN, BUILD, FINANCE, CONSTRUCTION, DEVELOPMENT,
IMPLEMENTATION, OPERATION AND MAINTENANCE OF THE JAN SUVIDHA
KENDRA, AT Rest House Khandala, MAHARASHTRA” (“Project”).
The Licensor is the owner of the land (along with the buildings, constructions or
immovable assets thereon) at Rest House Khandala, Maharashtra as described
and delineated in the Annex-I hereunder (the “Site”) and now desires to grant leave
and licence rights in respect of all the Site to the Licensee and the Licensee desires to
take on leave and licence basis from the Licensor, the Site for the purposes of
undertaking the Project as per the terms and conditions of the Concession Agreement.
NOW THEREFORE, in consideration of the promises and covenants herein set forth and for
other good and valuable consideration, the receipt, adequacy and legal sufficiency of which are
hereby acknowledged, the Parties mutually agree as hereunder.
1.
Definitions and Interpretation
Page 189 of 195
1.1
1.2
Definitions
In this Land Licence Agreement, the following words and expressions shall unless
repugnant to the context or meaning thereof, have the meaning hereinafter
respectively assigned to them:
“Applicable Permits” means all clearances, permits, authorizations, consents and
approvals required to be obtained or maintained under applicable laws in connection
with the Site and the Project during the subsistence of the Land Licence Agreement;
“Encumbrance” means any encumbrance such as an easement, right of way, licence,
mortgage, charge, pledge, lien, hypothecation, pre-emptive right or security interest,
assignment, privilege or priority of any kind having the effect of security or other such
obligations, whether or not registered and howsoever arising, including by statute or
common law;
“Licence Fees” shall have the meaning as ascribed to it in the Concession Agreement;
“Site” shall have the meaning set forth in Recital (B); and
“Term” shall have the meaning set forth in Clause 3.
Interpretations
In this Land Licence Agreement, except to the extent that the context requires
otherwise:
(a)
(b)
(c)
(d)
the Recitals and the Annexes to this Land Licence Agreement form integral part
of this Land Licence Agreement and will be of full force and effect as though they
are expressly set out in the body of this Land Licence Agreement;
the terms of this Land Licence Agreement should be read in consonance with and
not in derogation with the terms of the Concession Agreement;
the rules of interpretation in Clauses 1.2, 1.3, 1.4 and 1.5 of the Concession
Agreement shall apply, mutatis mutandis, to this Land Licence Agreement; and
the words and expressions beginning with capital letters and defined in this Land
Licence Agreement shall have the meaning ascribed thereto herein, and the
words and expressions used in this Land Licence Agreement and not defined
herein but defined in the Concession Agreement shall, unless repugnant to the
context, have the meaning ascribed thereto in the Concession Agreement.
2.
2.1
2.2
Grant of Licence and possession
The provisions of this Land Licence Agreement shall take effect and become binding on
the Parties on the date first above written (“Effective Date”).
In consideration of the Licence Fee and the obligations, undertakings, covenants and
warranties of the Licensee under the Concession Agreement, the Licensor grants on
leave and licence basis to the Licensee and the Licensee hereby accepts the said leave
and licence from the Licensor, on an ‘as is where is’ basis, free from Encumbrances, of
Page 190 of 195
all that piece and parcel of the Site as more particularly described and identified in
Annex-I hereto to develop, operate and maintain the Site, together with all and
singular rights, liberties, privileges, easements, benefits, rights of way, paths, passages
whatsoever in or appurtenant to the Site or any part thereof, and to hold, possess, use
and enjoy the Site and / or any part thereof, in accordance with the provisions of this
Land Licence Agreement, solely for the purposes of the Project in accordance with the
provisions of the Concession Agreement.
2.3
3.
4.
5.
5.1
5.2
It is expressly agreed and understood by the Licensee that this is a bare license and
nothing herein contained shall ever be construed to create any interest, right of
tenancy, sub – tenancy, leases or sub – leases in favour of the Licensee and the
juridical possession of the Site shall at all times remain vested with the Licensor and the
Licensee shall at no time claim any right, title or interest, whether as tenant, sub –
tenant or any other similar status, in the Site or any part thereof.
Term
The Licence granted in pursuance of this Land Licence Agreement shall be for the
period upto the Transfer Date or earlier termination in terms of the Concession
Agreement (the “Term”).
Licence Fee
The Licensee shall pay the Licence Fees in accordance with the provisions of the
Concession Agreement.
Use of Site
During the Term of this Land Licence Agreement, the Licensee agrees to use the Site
only for the carrying out the Project in accordance with the Concession Agreement.
The Parties agree that the Licensee may, with the approval of the Licensor, and in
addition to the above stated purposes, utilise the Site for any other purpose(s), which
in the Licensee’s opinion is:
(a)
(b)
(c)
(d)
conducive or incidental to operation and management of the Project;
enhances the efficiency of the Project;
improves the commercial viability of the Project; and/or
facilitates further investment in and around the Site.
5.3
6.
The Land Licence Agreement shall be co-terminus with the Concession Agreement.
Upon termination, of the Concession Agreement, possession of the Site shall be handed
over to the Licensor in terms of the Concession Agreement.
Licensee’s obligations and covenants
Licensee hereby covenants, agrees and represents that:
Page 191 of 195
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
(j)
(k)
upon execution of this Land Licence Agreement and subject to the terms
thereof, the Licensee shall accept the Site in the condition it is handed over and
undertakes to use the same only for the purposes as enlisted in Clause 5 of this
Land Licence Agreement;
this Land Licence Agreement has been duly authorized, executed, and delivered
by the Licensee after fulfilling all legal formalities and constitutes its legal, valid
and binding obligation;
during the Term of the Land Licence Agreement, the Licensee shall pay the
Licence Fee in accordance with terms and conditions set out in this the
Concession Agreement and shall observe and fulfil each of its obligations and
covenants set forth herein;
during the Term of the Land Licence Agreement, the Licensee shall undertake
the development of the Site, and other works which in the reasonable opinion
of the Licensee would be required for and in relation to the Project, and obtain
necessary approvals/clearances from the appropriate authorities for the same;
at its own cost and expense, the Licensee shall obtain all utilities such as water,
electricity and from the appropriate authorities;
it shall obtain and keep current all Applicable Permits that may be required
under the applicable laws;
it shall pay all taxes, service tax, cesses, assessments and levies in respect of
the Site, which are leviable at any time during the Term of the Land Licence
Agreement;
it shall not create any lien, charge or Encumbrance on the Site, except as
permitted in this Land Licence Agreement, without prior approval of the
Licensor;
it shall, indemnify the Licensor in respect of any charges, deposits and other
monies levied by third parties for and in relation to the provision by such third
parties to the Licensee of water, electricity, telephone, communication and
other facilities and in relation to any and all third party claims made with
respect to the Site;
it shall (i) keep and maintain the Site and the buildings and structures thereon
in good and habitable condition at all times, (ii) provide office space for about
10 officials/staff in the administrative building for the purpose of maintenance
monitoring office by the Licensor and (iii) shall ensure that the Site shall be free
from encroachments at all times and to the extent that there occur any
encroachments on the Site, it shall make diligent efforts to remove such
encroachments from the Site, as soon as practicable;
it shall take all necessary care to keep the premises neat and clean and in
sanitary conditions consistent with the environment and cleanliness of a world
class facility; and
Page 192 of 195
(l)
it shall, after expiry or termination of the Land Licence Agreement, forthwith
hand over possession of the Site to the Licensor.
7.
8.
Stamp duty and registration charges
Subject to the exemption or waiver, if any, granted by the Licensor or any other
authority, the Parties agree that all stamp duties and registration charges payable in
respect of the Licence contemplated herein shall be to the account of and borne by the
Licensee.
Indemnities and limitation of liability
The Licensee shall fully indemnify, defend and hold harmless the Licensor, its officers,
servants, agents, against any and all suits, proceedings, actions, demands, claims and
liabilities, which may be incurred or suffered by the Licensor and which may arise out of
or as a result of any of the following causes:
(a)
(b)
(c)
any breach by the Licensee of any of its obligations, covenants, agreements,
representations or warranties set forth in this Land Licence Agreement;
any loss of property, damage to property, personal injury or death occasioned
to or suffered by any person, to the extent that the damage to or loss of
property or the personal injury or death is caused willfully or negligently by the
Licensee; and
any breach, violation or non-compliance by the Licensee of any applicable laws
and/or Applicable Permits.
9.
10.
11.
12.
12.1
Assignment
The Licensee shall not, without the Licensor’s prior written consent, transfer, assign, or
grant any form of security over any of its rights or obligations under this Land Licence
Agreement.
Governing and Jurisdiction
The provisions of the Governing Law and Jurisdiction clause as set out in the
Concession Agreement shall be deemed to have been incorporated in this Land Licence
Agreement and shall mutatis mutandis apply to this Land Licence Agreement.
Dispute Resolution
The provisions of the Dispute Resolution clause as set out in the Concession Agreement
shall be deemed to have been incorporated in this Land Licence Agreement and shall
mutatis mutandis apply to this Land Licence Agreement.
General Provisions
Entire Agreement
The Concession Agreement and this Land Licence Agreement together with the
Annexes, constitutes the entire agreement between the Parties with respect to the
Page 193 of 195
subject matter and the transaction envisaged in this Land Licence Agreement. The
terms, conditions and provisions of this Land Licence Agreement shall be subject to and
subservient to the provisions of the Concession Agreement at all times and in the event
of any inconsistency between the provisions of the Concession Agreement and the Land
Licence Agreement, the Parties agree that the terms, conditions, provisions and
requirements of the Concession Agreement shall prevail.
12.2
Waiver
12.2.1 Waiver, including partial or conditional waiver, by either Party of any default by the
other Party in the observance and performance of any provision of or obligations under
this Land Licence Agreement:
(a)
(b)
(c)
shall not operate or be construed as a waiver of any other or subsequent
default hereof or of other provisions of or obligations under this Land Licence
Agreement;
shall not be effective unless it is in writing and executed by a duly authorised
representative of the Party; and
shall not affect the validity or enforceability of this Land Licence Agreement in
any manner.
12.2.2 Neither the failure by either Party to insist on any occasion upon the performance of the
terms, conditions and provisions of this Land Licence Agreement or any obligation there
under nor time or other indulgence granted by a Party to the other Party shall be
treated or deemed as waiver of such breach or acceptance of any variation or the
relinquishment of any such right hereunder.
12.3
12.4
12.5
Severability
If for any reason whatever, any provision of this Land Licence Agreement is or becomes
invalid, illegal or unenforceable or is declared by any court of competent jurisdiction or
any other instrumentality to be invalid, illegal or unenforceable, the validity, legality or
enforceability of the remaining provisions shall not be affected in any manner, and the
Parties will negotiate in good faith with a view to agreeing to one or more provisions
which may be substituted for such invalid, unenforceable or illegal provisions, as nearly
as is practicable to such invalid, illegal or unenforceable provision. Failure to agree upon
any such provisions shall not be subject to the Dispute Resolution Procedure set forth
under this Land Licence Agreement or otherwise.
Specific Performance
In the event of default or breach in performance of obligations by any Party, the Party
not in default or breach shall be entitled, without prejudice to its other rights and
remedies, to seek and enforce specific performance of this Land Licence Agreement.
Expenses
Each Party shall pay its own costs and expenses (including, without limitation, the fees
and expenses of its agents, authorised representatives, advisors, counsel and
Page 194 of 195
accountants) necessary for the negotiation, preparation, execution,
performance of and compliance with this Land Licence Agreement.
delivery,
13.
Notices
The provisions of the Notice clause as set out in the Concession Agreement shall be
deemed to have been incorporated in this Land Licence Agreement and shall mutatis
mutandis apply to this Land Licence Agreement.
ANNEX - I
Description of the Site at Rest House Khandala, Maharashtra
All that piece and parcel of the land admeasuring _________________ acres including the
buildings, structures and works thereon located at
Rest House Khandala , Maharashtra bearing Survey No.
__________________________________________________ in the Registration District of
____________________ with the following delineation:
Bounded by:
North: _______________________________________________
South: _______________________________________________
East: _______________________________________________
West: _______________________________________________
Page 195 of 195
IN WITNESS WHEREOF THE PARTIES HAVE EXECUTED AND DELIVERED THIS LAND
LICENCE AGREEMENT AS OF THE DAY, MONTH AND YEAR FIRST ABOVE WRITTEN.
SIGNED, SEALED AND DELIVERED for and on
behalf of the GOVERNOR OF
MAHARASHTRA, by the Executive Engineer,
Public Works Division , Satara.
Witnesses:
1.
2.
SIGNED, SEALED AND DELIVERED by the within
named CONCESSIONAIRE,
____________________________
LIMITED, by the hand of
________________________________, its
authorized signatory in whose presence the
Common Seal of
________________________
has been affixed hereto pursuant to the
resolution passed by its board of directors
on
________________________________.
Witnesses:
1.
2
LIMITED