request for proposal (rfp) for study, design, develop ... rfp-web-24112012.pdf · & upgrade...
TRANSCRIPT
REQUEST FOR PROPOSAL (RFP)
FOR
STUDY, DESIGN, DEVELOP, PROCURE, IMPLEMENTATION, OPERATE &
MAINTENANCE OF EXCISE E-GOVERNANCE PROJECT (EeGP)
FOR
PROHIBITION AND EXCISE DEPARTMENT,
GOVT. OF ANDHRA PRADESH
NOVEMBER 2012
PREPARED BY
A.P TECHNOLOGY SERVICES LTD.,
4TH FLOOR, B-BLOCK, BRKR BHAVAN, TANKBUND ROAD
HYDERABAD – 500 063.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 2 of of of of 48
Contents
Disclaimer ........................................................................................................................................5
Proprietary & Confidential ..............................................................................................................6
1. General Information ..........................................................................................................7
2. Project Information ............................................................................................................9
2.1. Preamble .............................................................................................................................. 10
2.2. RFP Overview ..................................................................................................................... 11
2.3. Scope of work ..................................................................................................................... 11
2.4. Expected outcomes ............................................................................................................ 12
2.5. Key Functional Areas of the System ............................................................................... 13
2.6. APBCL ROLE ...................................................................................................................... 14
2.7. The objectives for Distiller/Breweries and Vends: ......................................................... 14
2.8. Stakeholders ....................................................................................................................... 15
2.9. Roles and Responsibilities of Stakeholders ................................................................... 15
2.10. Implementing Agency(IA) .................................................................................................. 17
2.11. Responsibilities of Implementing Agency ....................................................................... 17
2.12. Change Management ........................................................................................................ 18
2.13. Training ................................................................................................................................ 18
2.14. Helpdesk .............................................................................................................................. 18
2.15. Operation & Maintenance ................................................................................................. 18
2.16. Software Design, Development, Implementation, Training & Documentation .......... 19
2.17. Procurement of IT infrastructure .................................................................................... 21
2.18. IT Infrastructure Installation .............................................................................................. 21
2.19. Warranty............................................................................................................................... 21
2.20. Operations & Maintenance of Application Software ...................................................... 22
2.21. Project Deliverables ........................................................................................................... 22
2.22. Strategic Control of EeGP ................................................................................................. 23
2.23. Project Implementation Timelines .................................................................................... 23
2.24. Scope of Contract and Provision of Services ................................................................. 24
3. Instruction to Bidders ......................................................................................................26
4. Bid Submission ................................................................ Error! Bookmark not defined.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 3 of of of of 48
5. Bidding procedure ........................................................... Error! Bookmark not defined.
6. Preparation of Bids ......................................................... Error! Bookmark not defined.
7. Bid Opening and Evaluation .......................................... Error! Bookmark not defined. Proposed Methodology and Criteria for Evaluation of proposalsError! Bookmark not defined.
8. General Conditions of Contract (GCC) ........................ Error! Bookmark not defined.
9. Special Conditions of the Contract (SCC) ................... Error! Bookmark not defined.
9.1 Subject Matter of Contract ................................................. Error! Bookmark not defined.
9.1.1 Contract Agreement ........................................................ Error! Bookmark not defined.
9.1.2 Key Personnel for Client ................................................ Error! Bookmark not defined.
9.1.3 Key Personnel for IA ....................................................... Error! Bookmark not defined.
9.2 Contract signing ................................................................... Error! Bookmark not defined.
9.3 “Effective Date” .................................................................... Error! Bookmark not defined.
9.4 Local office: .......................................................................... Error! Bookmark not defined.
9.5 “Go-Live” ............................................................................... Error! Bookmark not defined.
9.6 “Project Co-ordination” ........................................................ Error! Bookmark not defined.
9.7 “Project site” ......................................................................... Error! Bookmark not defined.
9.8 Project Reports .................................................................... Error! Bookmark not defined.
9.9 Payments .............................................................................. Error! Bookmark not defined.
9.10 Payment Schedule .............................................................. Error! Bookmark not defined.
9.11 Contract Price & Payments ................................................ Error! Bookmark not defined.
9.12 Payment Authority ............................................................... Error! Bookmark not defined.
9.13 Penalty .................................................................................. Error! Bookmark not defined.
9.14 Taxes ..................................................................................... Error! Bookmark not defined.
9.15 Price Adjustments ................................................................ Error! Bookmark not defined.
9.16 Advance Payment ............................................................... Error! Bookmark not defined.
9.17 Insurance to men, machine and material ......................... Error! Bookmark not defined.
9.18 Subcontract .......................................................................... Error! Bookmark not defined.
9.19 Infrastructure arrangement by IA ...................................... Error! Bookmark not defined.
10. Exit Management ............................................................ Error! Bookmark not defined.
B. Appendix 1 - Bidder ’s Representative .................................. Error! Bookmark not defined.
C. Appendix 2 - Adjudicator ....................................................... Error! Bookmark not defined.
Annexure A (Bid Checklist) ................................................... Error! Bookmark not defined.
Annexure – B ................................................................................. Error! Bookmark not defined.
Bid security (EMD) form ........................................................................ Error! Bookmark not defined.
Performance Bank Guarantee ............................................. Error! Bookmark not defined.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 4 of of of of 48
Annexure – C ................................................................................. Error! Bookmark not defined.
Stage – I Bidding (Pre Qualification) formats ............................... Error! Bookmark not defined.
General Information of the IA (In case of Single Bidder) ....................... Error! Bookmark not defined.
SOA Software/ Application Development .............................................. Error! Bookmark not defined.
Local Presence (in Andhra Pradesh)........................................................ Error! Bookmark not defined.
Understanding of the Project ................................................................... Error! Bookmark not defined.
Details of Proposed Key Staff committed for the assignment ................. Error! Bookmark not defined.
Hardware, System software and other tools required to implement the proposed solutionError! Bookmark not defined.
Stage – III Bidding (Commercial) formats .................................... Error! Bookmark not defined.
Commercial Proposal ..................................................................... Error! Bookmark not defined.
Compliance/Agreed/ Enclosed/ Deviation Statement .................... Error! Bookmark not defined.
Annexure D .................................................................................... Error! Bookmark not defined.
Annexure E .................................................................................... Error! Bookmark not defined.
Change Control Notice .................................................................. Error! Bookmark not defined.
Annexure F.....................................................................................................................................29
List of Abbreviations ..................................................................................................................48
End of the bid document ................................................................ Error! Bookmark not defined.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 5 of of of of 48
Disclaimer
All information contained in this Request for Proposal (RFP) is provided in good interest and faith. This is not an agreement and is not an offer or invitation to enter into an agreement of any kind with any party. Though adequate care has been taken in the preparation of this RFP document, the interested firms shall satisfy themselves that the document is complete in all respects. The information is not intended to be exhaustive. Interested parties are required to make their own enquiries wherever required. Intimation of discrepancy, if any, should be given to the specified office immediately. If no intimation is received by this office by the date mentioned in the document, it shall be deemed that the RFP document is complete in all respects and the participating firm is satisfied that the RFP Document is complete in all respects.
The Commissioner, Prohibition & Excise department, reserves the right to reject any or all of the applications submitted in response to this RFP document at any stage without assigning any reasons whatsoever. The department also reserves the right to withhold or withdraw the process at any stage with intimation to all who submitted the RFP Application. APTS/Excise dept reserves the right to change/ modify/ amend any or all of the provisions of this RFP document. Such changes would be posted on the websites http://www.apts.gov.in Neither the Department/APTS nor their employees and associates will have any liability to any prospective applicant interested to apply or any other person under the law of contract, the principles of restitution or unjust enrichment or otherwise for any loss, expense or damage which may arise from or be incurred or suffered in connection with anything contained in this RFP document, any matter deemed to form part of this RFP document, the award of the assignment, the information and any other information supplied by or on behalf of Prohibition & Excise Department or their employees and Prime Applicant/ Consortiums or otherwise arising in any way from the selection process for the Assignment. Information provided in this document or imparted to any respondent as part of the RFP process is confidential to Department/APTS and shall not be used by the respondent for any other purpose, distributed to, or shared with any other person or organization.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 6 of of of of 48
Proprietary & Confidential
No part of this document can be reproduced in any form or by any means, disclosed or
distributed to any person without the prior consent of APTS except to the extent required for submitting bid and no more.
The contents of this document are subject to modification based on views
Obtained from the participants in pre-bid conference.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 7 of of of of 48
1. General Information
The Prohibition & Excise Department is looking for an integrated framework, which will cover all the activities involved in making the Liquor sale and distribution in Andhra Pradesh more transparent and efficient. APTS on behalf of Prohibition & Excise Department invites bids for the project of “Study & upgrade existing SRS, Design, Develop, Integrate, Test, Procure Hardware, Deploy, Implement and Operate &Maintain the proposed Excise e-Governance Project (EeGP) for regulation of Liquor Sale in Andhra Pradesh” 1.1. List of Important Dates:
S. No Subject Description
1 Department Name Prohibition & Excise Department, AP, Hyderabad
2 Tender Subject RFP for Study, Design, Develop, Procure & Implementation of Excise e-Governance Project (EeGP).
3 Period Of Contract 5 Years 4 Price of Tender document 20,000/- 5 Tender Category Products and Services
6 EMD / Bid Security (INR) INR 20,00,000 (Twenty Lakhs only) & validity is up to 31-08-2013
7 Implementation cum Performance Security Deposit
10% on the total contract value
8 Period of submission of Implementation cum Performance Security Deposit Validity of PBG
Within 7 days from the receipt of letter of notification of award.
PBG validity beyond 3 months of contract period.
9 Period of signing the contract
Within 10 days from the receipt of letter of notification of award
10 Bid calling date (OCB) 24.11.2012 11 Pre-bid conference date &
time
04.12.2012, 11.30am at APTS
12 Last date for receiving
clarifications
06.12.2012,5.00pm
13 a. Bid Closing date and time 12.12.2012, 3.00pm
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 8 of of of of 48
on e-Procurement web site b. Submission of hard copies of Pre-qualification and Technical bids
12.12.2012 4.30 pm
14 Opening of PQ Bids 13.12.2012, 11.30pm 15 Opening of Technical Bids Will be informed to PQ qualified bidders
16 Technical presentations to the TFC as per GO 3775
Will be communicated to the PQ Qualified Bidders
17 Opening of Financial bids Will be informed to TQ qualified bidders 18 APTS Contact Person General Manager(T2),APTS
19 Address / E-mail id [email protected], [email protected], [email protected]
20 Bid Validity 180 Days after submission of bid from date of submission of bid.
21 Bid Reference No. APTS/CS/Prohibition & Excise/11
If your firm is interested in participation, please ask the contact person for details or visit our web site http://www.apts.gov.in/tenders.html. If your firm is interested in participation, please visit the market place at www.eprocurement.gov.in. The bid document fee is payable only when you indent full copy of the bid document. The quantities mentioned above are only indicative and may vary depending on actual requirement. The Details can also be seen at http://www.apts.gov.in/tenders.html. A complete set of bidding document prepared by APTS may be purchased by interested bidders on submission of a written application addressed to “The Managing Director, AP Technology Services Ltd, BRKR Bhavan, Hyderabad” by paying a non-refundable amount indicated above in section 1.4. The payment can be made in the form of Demand Draft/ Cashier’s Cheque/ Certified Cheque drawn in favor of “The Managing Director, Andhra Pradesh Technology Services Ltd., payable at Hyderabad, India”. The Document, if required can be sent by Courier for out locations for which Rs.500/- for inland to be paid extra along with cost of bidding documents.
Managing Director, APTS
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 9 of of of of 48
2. Project Information
The Department of Prohibition and Excise has been mandated to enforce and regulate
liquor trade in Andhra Pradesh without promoting it. The department has realized that
the increasing workload under the manual system affects efficiency and also hampers
department's revenue collection capacity. Hence the remedy lies in extremely smooth
operating infrastructures and effective communication systems. This requires an
integrated information technology network with an inbuilt facility to collect revenue
electronically from manufacturers, liquor shops and others. It will be connected at one
end with the Treasuries Department.
The major benefits expected to accrue from the system would be;
• Reduction in smuggling and illicit distillation of liquor which help in better revenue mobilization. Automation of the issue of Transport Permits, import permits and other licenses.
• Generation of timely, intelligent reports and comparisons will help managerial control, inventory management, improve efficiency and enable revenue record reconciliation on daily basis.
• Ease of regulatory changes being put in force immediately and also providing transparency to department.
• Control data e.g. performance parameters can be monitored effectively.
The APBCL dealing with liquor will see savings in cost of transfer of funds, reduction of
floats, better stock management improving revenues and less time spent in chasing
paper. The prime job of the Department is to regulate, manufacture the supply of liquor,
intoxicants and narcotics (for medicinal purposes), the statutory powers for which are
discharged under several Excise and other acts.
Apart from this private entrepreneurs have been granted licenses for retail trade of IMFL
& Beer. Besides, Licenses for the consumption of liquor 'on-site' premises like hotels,
restaurants and clubs are also granted by this Department.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 10 of of of of 48
2.1. Preamble
The Department of Prohibition and Excise, Government of Andhra Pradesh has decided
to come up with a comprehensive solution to automate all the processes pertaining to
the Excise Administration in order to arrest revenue leakages and prevent illicit liquor in
Andhra Pradesh. The Department is looking for an integrated framework, which will
cover all the activities involved in making the regulation of Liquor Sale and distribution in
Andhra Pradesh more transparent and efficient.
The ‘‘Excise e-Governance Project’ for regulation of Liquor trade in AP’(herein
after referred as ‘EeGP’ throughout this document), has been initiated by Prohibition &
Excise Department with the objective to make the system more transparent, efficient,
effective and accountable with the help of Information & Communication Technology
(ICT). The project covers the Excise services at Department, APBCL, Distilleries,
Breweries and Retailers.
The Proposed Solution shall be Web based application developed on SOA architecture
using open source technology, that will act as the single point of communication for
Department users, all other stakeholders and Citizens to view the relevant
information of various functionalities based on user permissions.
To implement the project, Prohibition & Excise Department, herein after called as
‘Department’ has decided that it will engage a professional agency to develop the
proposed system including the required infrastructure.
To that end the specifications laid out in this RFP are indicated as the minimum
requirement whereas the bidders are expected to focus on the objectives of this project
and formulate their solution offerings in a manner that enables achieving those
objectives both in letter as well as spirit
The Department has initiated a project ‘Hedonic Path Finder System’(HPFS) which is a
track and trace system. The EeGP needs to be interoperable with HPFS for
seamlessness.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 11 of of of of 48
2.2. RFP Overview
RFP is basically aimed at fulfillment of the following: 1. Study the existing SRS and include the additional requirements, if any. 2. Design, develop, implement and maintain an application based on the updated
SRS. 3. Facilitate integration and interaction with the data from HPFS (Hedonic Path
Finder System). 4. Procurement of necessary hardware required for implementation of the proposed
solution. 5. Integrate the solution with CSCs/e-Seva and Treasuries department 6. Maintain the proposed solution applications for a period of 5 years including
warranty of one (1) year.
2.3. Scope of work
1. Considering the wide geographical scope and operational complexity, scope of
the project is to Study, Update, Design, Develop, Implement, Operate & Maintain
the solution for Excise e-Governance Project.
2. The Implementing Agency (selected bidder will be IA) will be the System
Integrator (supplier of Hardware and Software) of all the Department Functional
Areas; with ‘Excise e- Governance Project’ as a component to the department
portal.
Scope of the IA will perform the following primary tasks.
1. Study, Update (the existing SRS), Design, develop, test, deploy,operate and
maintain an application on SOA architecture with interoperability principles and
standards defined and announced by Government of India/Government of AP
from time to time such as ‘open standards’ and ‘data & metadata standards’.
The application has to be provided with ‘cloud computing’ compatibility as
Government of India is planning to make all the State Data Centers ‘cloud’
enable.
2. The IA has to undertake procurement of the necessary Hardware & other
infrastructure at all the locations of Excise Department, APBCL, DDB and other
offices and functionaries. The IA should study the existing hardware and
procurement requirement of HPFS project, functionary wise and location
wise, before arriving at the requirement and obtaining approval of the
department.
3. Department has prepared SRS for following modules:
• General Functions Module
• Enforcement module
• Manufacturing and Monitoring Module
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 12 of of of of 48
• Administration Module
• APBCL module for wholesale trade
The IA to refer the base SRS, conduct necessary study and update the SRS with latest business requirements for the above modules to reflect the contextual rationality.
1. Provide integration requirements with data from HPFS.
2. Integrate & migrate the existing legacy applications & data & any other excise specific services with the proposed solution.
3. Facilitate interoperability with HPFS for seamless data transfer.
4. Provision of Alerts & Dash Board View.
5. Handhold support by providing a Helpline/ Call Centre functions with IVRS & recording of voice functionality in addition to collection of Data of caller. In addition provide manual support resources (1+4) onsite throughout 1+4 years of AMC.
6. Provision of Trainers Training.
7. Operation & Maintenance of the Overall System Solution (Hardware, System Software, Application Software and other Infrastructure) for 5 Years from Go-Live(including One year warranty on the developed application).
8. Change Management of Application Software, during Operation and Maintenance Phase.
9. Compliance with the SLAs as defined in the Annexure D.
10. The IA shall produce the Proof of Concept (PoC) implementation of the proposed EeGP system for a period of three (3) months at identified pilot location before rollout to all the districts.
2.4. Expected outcomes
1. Online availability of information about Supply and Sale of liquor, Storage, Movement and Distribution along with information pertaining to the support activities such as licensing, regulation, finance and grievances would enable the decision makers at each stage to identify embezzlement.
2. Facilities to enhance the involvement of citizens through easier access to information as well as registration and tracking of grievances would increase transparency and accountability of the System.
3. Assessment of Excise duty to be paid/ paid in real time
4. Online MIS system for prompt and efficient decision making
5. Online availability of Allocation, Sales and Payments related information
6. Transport of Liquor within defined service levels
7. Ease of payment of fees for Vend owner.
8. Ensuring the genuine and correct liquor reach the citizen.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 13 of of of of 48
2.5. Key Functional Areas of the System The prime job of Excise Department is to regulate manufacture, import and supply of liquor, intoxicants and narcotics (for medicinal purposes). The Department grants Licenses to Distilleries/Bottling Plants for manufacturing of IMFL and Beer in Andhra Pradesh, while wholesale liquor trade in AP is mainly in the hands of APBCL. Apart from this private entrepreneurs have been granted licenses for retail trade of IMFL & Beer. Besides, Licenses for the consumption of liquor 'on-site' premises like hotels, restaurants and clubs are also granted by this Department. The key functional areas of the proposed system (Workflow based graphical user interface) for Department users to perform necessary tasks based on user privileges are as mentioned below :
1. Enforce and regulate the Sale and transport of liquor trade in AP without promoting it.
2. Mobilize revenue generation under the multiple heads of taxation that it administers
3. Automation of the issue of Licenses, Transport Permits, Import permits and others which can only be granted by the department.
4. Timely, intelligent reports and comparisons for enforcement and managerial control, inventory management
5. Control data and effective monitoring of ordering patterns for EeGP management
6. Savings in cost of transfer of funds, reduction of floats, better stock management
7. Accuracy in billing and payment
8. Software development for Excise e-Governance Project should consist of ; • Provide facility to Integrate with the data from HPFS. • Integration of services with e-Seva Centers and CSCs. • Licenses, Permits and other certificates which have not been
covered in the existing SRS. Permits and licenses to be associated with digital signature
• The data from the HPFS to be integrated and to be used for generating reports or other functionalities wherever necessary.
9. Arresting of illicit distillation.
10. Making available downloadable application forms & dynamic Status of All Applications received by the Department on the website as per RTI Guidelines,
11. Acceptance of all types of Purchase Requests Online
12. Availability of latest Revenue Status online
13. Payments to Department, DDB and APBCL Online.
14. Consolidate inventory Requirement received from all.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 14 of of of of 48
15. Interfaces for Distilleries, Breweries, Excise Department, DDB, APBCL and others.
16. Retailers and others for uploading relevant Data on to the Central Database.
17. Ability to send alerts, notifications and maintain audit trail log.
18. Accounting, Audit trail, Stock position, Supply and Sales and enforcement formats.
19. MIS Reports and Dash Board views.
20. Generation and Dissemination of specific orders for private and other agencies to view and take necessary steps.
2.6. APBCL ROLE
1. Add ‘retail outlet sale’ functionality to the existing whole sale trade module.
2. Automate process of maintaining Sales Register, Stock Register, Brand wise
Register, Daily Status Report, Weekly Status Report, Daily Sales and Cash
Register for wholesale and retail sale
3. Generate daily/weekly report by Vend wise, Brand wise, size wise, Opening
Balance (Quarts, Pints, Nips), Material Issued, Total, Closing Balance, Sales,
Selling Price, Value.
4. Generate consolidated periodical status reports
5. To facilitate automation of the complete process of flow of inventory (liquor
bottles) from Distillers, Warehouse, retail vendors, APBCL and Excise
Department for the smooth flow & tracking of the inventory.
6. Inventory monitoring system on Excise Department Portal.
7. A dynamic dashboard, which shows the exact inventory and dynamic reports
showing details like fast moving, slow moving, vendor inventory details
8. Facility for APBCL and Excise Enforcement Officers to check the Stock and Sale
figures online
9. Provision for automating Accounting procedures, Sales order processing and
Sales and payments to suppliers.
10. Distinct online provisions for the operations of wholesale and retail vends.
11. Cash Management System (CMS)
12. Payment Gateway
13. ‘Subscribed data sharing’ for suppliers, manufacturers, retailers and others
2.7. The objectives for Distiller/Breweries and Vends: Retail / Vends:
13.1. Out of stock trigger
13.2. Reducing shrinkage
13.3. Reducing inventories
13.4. Locating products
13.5. Real time Supply and Demand data Smart Shelves
13.6. Reverse logistics
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 15 of of of of 48
13.7. Customer convenience
2.8. Stakeholders
Primary Stakeholders 1. Prohibition and Excise Department, is responsible for revenue collection,
regulate the manufacturing, import of liquor, intoxicants and narcotics (for
medicinal purposes) and Licensing the manufacturers, retailers and issuing
permits.
2. APBCL operates whole sale trade and retail sale functions.
3. DDB is responsible for regulating the Distilleries and Breweries.
4. DOE is responsible for enforcement functionalities.
5. Academy is responsible for training activities
6. Department would be primarily responsible in supervising, monitoring and
evaluating the development and implementation of the project.
7. Implementing Agency is responsible to study, update, design, develop and
implement the System, improve the infrastructure that is being proposed.
8. The IA shall be responsible for deployment of servers in the AP State Data
Center.
9. Ensure timely sign-off on the deliverables submitted by IA, wherever required
Other Stakeholders There are many stakeholders who are directly or indirectly related to the system.
The following is a list of key stakeholders:
• Distilleries
• Breweries
• Retailers
• Bars
• Clubs
• Star Hotels
2.9. Roles and Responsibilities of Stakeholders
A clear definition of the roles and responsibilities of all the stakeholders in a
project establishes transparency, accountability, manageability and efficiency in the
project. All the stakeholders are responsible for pursuing the following objectives
besides there specific responsibilities.
Responsibilities: 1. Providing all support to other stakeholders as and when requested
2. Taking the lead in resolving any project issues
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 16 of of of of 48
3. Active participation in all the phases of the project by dedicating time & resources
4. Duly considering the project requirements before making any changes in the
internal operations with respect to processes, services, technology, legal & human
resource areas
5. Strict adherence to the timelines and service level agreements
Distilleries Distilleries would have a major role in the proposed EeGP project ;
1. Cooperation with the department in the development of application.
2. Procurement, installation and provisioning of necessary IT & Non IT
infrastructure on its own
3. Ensure correct and timely data entry and sharing with corporations
4. Ensure timely completion of activities required at Distillery
5. Ensure meeting of all Service Level Agreements
6. Cooperation to Department for resolution of any issue or dispute
APBCL: APBCL and its depots which are involved in sale of liquor are also major players and
their role become critical in the proposed system. Their cooperation is critical for the
success of the project.
1. Cooperation with Department and Implementing Agency for the implementation
of the system
2. Integration of new application with existing applications
3. Ensure correct data entry and sharing
4. Ensure timely completion of activities required at Corporation / Vends
5. Ensure meeting of all Service Level Agreements
6. Cooperation to Department for resolution of any issue or dispute
Points of Sale (POS) All Bars, clubs, Retailers or similar agencies which are involved in sale of Liquor are
also major players and their role become critical in the proposed system. Their
cooperation is critical for the success of the project.
1. Cooperation with Department, for the implementation of the project at POS
2. Cooperation with Distilleries and Breweries for implementation of project Related
activities.
3. Ensure correct data entry and sharing.
4. Cooperation to Department for resolution of any issue or dispute.
Establishment of PMU A PMU shall be established at the Excise department under the Project Director
leadership to supervise the implementation the project. He would be primarily
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 17 of of of of 48
responsible for supporting Department in supervising, managing the Implementing
Agency, monitoring and evaluating the development and implementation of the
proposed project. The PMU shall also arrange for providing the required internet
connectivity through leased line for a dedicated bandwidth as per the
specifications given by the IA.
2.10. Implementing Agency(IA)
Implementing Agency is responsible to study, update, design, develop,
implement and maintain the System. It will also operate and maintain the overall
system solution for the full project duration. As an implementer of the project it
has a major role to play.
2.11. Responsibilities of Implementing Agency
Development and Implementation
1 Study all modules of Excise Department, Updating of the existing SRS and
preparation of SRS for uncovered functionalities. Integration of existing
applications into proposed services based software system. Facilitate to integrate
with the data from barcodes for ‘track and trace’
2 Testing and Implementation of developed modules
3 Installation and commissioning of hardware required
• Installation and commissioning of department server & systems at State Data Centre
• Installation and commissioning of hardware required at all other locations such as Department’s Offices, other offices and units of other organizations.
4 Integration with e-Seva/ CSCs shall be required for delivery of services through
the above channels. The required information about the database and the
procedure to be adopted shall be provided by the department in consultation with
the concerned department delivery mechanism.
5 Mobile service delivery for appropriate services, to be identified by the
department.
Documentation, Maintenance and Support
1. Maintenance, handholding and support to Department
2. Ensure complete documentation related to design/update, development and
implementation work is done and submitted to Department
3. Ensure all milestones are completed within the agreed timeline
4. Ensure meeting of all agreed SLAs
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 18 of of of of 48
5. Ensure quality of deliverables as agreed during the agreement
6. Cooperation with Department and other Stakeholders
7. Periodic progress reports (monthly, quarterly and annually) submission to Project
Director.
8. Cooperation with Department appointed Quality Audit Agency during audits
2.12. Change Management
The IA should support the application for Five years after User acceptance Testing. The
complete Change Management including the change requests and new features
required for the department shall be the part of this activity and are covered under AMC.
No separate change management charges shall be paid.
2.13. Training
IA is responsible to provide trainings on Application Software on the EeGP. IA is
required to train all the Department users connected with EeGP and the designated
ones at the Department to enable them to effectively operate and perform the relevant
services using the software. The IA should provide the complete training plan in the
technical bid. The training shall be on the following.
� Training on the Application Software � System Application Training
2.14. Helpdesk
Call Registration and Completion:
•••• O&M team will acknowledge each call with a unique call no., which is to be used
for reference in future.
•••• IVRS compatible system. Record the voice and collect the details of caller.
•••• Completion of calls will be certified by the user.
•••• O&M Team will prepare the call service slip in triplicate. This will be signed by
the user. One copy will be given to the user, one copy will be furnished to the
Excise Department and the third copy will be retained by Facilitator. Call
monitoring software report supported by these documents will be used to work
out downtime for penalty calculations.
•••• Onsite 24X7 support with 1+4 resources throughout 5 years of AMC.
2.15. Operation & Maintenance
1. Operation & Maintenance of Application Software for a period of 5 years from
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 19 of of of of 48
Go-Live.
2. Software Change & Version Control as per industry standards.
3. IT Infrastructure Operations and Maintenance as per ITIL Standards for a period of 5 Years from Go-Live.
4. Help Desk Support for EeGP Application is to be provided.
5. Ensure shelf life of hardware and system software through necessary replacement and / or upgrade on or before 5th Year of the project period for minimum Shelf life of 3 years
2.16. Software Design, Development, Implementation, Training & Documentation Software Design
The IA shall design the solution architecture & specifications for meeting the system
requirement specifications finalized by the IA and approved by the department. The
solution design shall include, but is not limited to the development of enterprise
architecture, the design of the application architecture, user interface, database
structures, deployment architecture, security architecture and network architecture. The
existing applications needs to be taken into consideration.
The IA should submit the solution design document to the Department and should
obtain the sign off on the design document before commencing the development of
the solution.
Software Development/ Data Exchange
IA shall develop the software based on the functional requirement specifications,
system requirement specifications and design finalized for the functionalities. An
industry-standard methodology shall be adopted for the Software Engineering,
covering the entire SDLC. The IA shall follow the Implementation Model and
Strategy for design and development of Application Modules and to ensure seamless
data exchange by defining data exchange requirements, creating database
schema and designing utilities for data exchange between Excise Database and other
integrated service databases.
Software Testing
The IA shall design the Testing strategy including traceability matrix, Test Cases of the
software developed. The EeGP system will have to undergo a comprehensive testing
that shall include Unit Testing, System Testing, Integration Testing, Performance
Testing, Load and Stress testing. The IA shall obtain the sign-off from the Department
on testing approach and test plan.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 20 of of of of 48
Documentation
The IA shall prepare/update the documents including that of Functional Requirements
Specifications, Systems Requirement Specification, Detailed Design, Test Cases &
Results, User Manuals, Operations Manual, Maintenance Manual, Administrator
Manual, and Security Policy as per acceptable standards.
Hosting Application at State Data Center
Shared SAN storage and tape library back-up from State Data Center as per the sizing requirement by the IA. Other Responsibilities of Implementing Agency
IA shall assess the infrastructure requirements (including Servers, Storage, Networking
and Security) for operationalisation of the EeGP and to provide the functionalities to all
the stakeholders, in full conformance with the SLAs.
The IAs have to perform an independent assessment of the Infrastructure
requirements for EeGP and provide a detailed BOM for the proposed
infrastructure which will meet the SLA requirements as specified in the RFP. The
Department has existing IT infrastructure such as PCs, printers etc. The IA has to
study the existing hardware and other infrastructural items required for the
successful implementation of the project. Further IA has to study the hardware
procurement of HPFS, functionary wise and location wise, and exclude the items
which are already listed in HPFS and procure only the items which are not
included in the HPFS. IA has to take back the old ones and adjust the value of the
same against the cost of the new ones.
IA will ensure that all the Excise Department, APBCL and other offices are well
equipped with respect to IT infrastructure.
Important: All system software licenses would have to be taken in the name of
Prohibition & Excise Department, AP, Hyderabad.
The procurement of hardware and other infrastructural items shall begin after the
successful completion of POC/Pilot.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 21 of of of of 48
2.17. Procurement of IT infrastructure
The IA shall procure & supply the IT Infrastructure for EeGP as proposed by them in
their technical proposal. The IA shall ensure that all the equipment supplied to the
Department is brand new and is free from any defect of any sort.
1. IA may provide certain IT infrastructure like power backup, LAN (only at HQs
etc.) compatible to the EeGP solution proposed by the IA on requirement basis:
Sl
No.
Department / APBCL
No. of
Users
Floor Area
(Approx.)
2. IA is expected to liaise with the network solution provider for provision of the network connecting the above locations including DC / DRC for Intranet and Internet services. This is in addition to all the department and APBCL offices.
3. It is required to connect all the above locations through MPLS based connectivity with the Data Centre and Disaster Recovery sites. The IA is expected to size the network and bandwidth requirement with reasonable spare capacity such that the network can serve additional applications in future and meet the required SLAs as mentioned in the RFP.
4. IA shall ensure configuration of both MPLS and Internet connectivity through the configuration of Quality of Service (QoS).
5. IA need to provide the detailed items, specifications and qty. for all hardware including network components in the BOM format.
2.18. IT Infrastructure Installation
The IA shall be responsible for operationalization of the EeGP from end to end,
which includes installation of IT Infrastructure and connecting the Excise
database to all Data bases. The IA shall deploy the application software along
with Hardware at the Data Centre and sha l l ensure that the application
software services are made accessible to the EeGP users.
2.19. Warranty The IA shall provide comprehensive warranty of one year (1) on developed software & Maintenance support for a period of 5 Years from Go- Live for all components supplied for the EeGP as per the contract. During the AMC period, the IA shall replace any parts/components of the IT Infrastructure supplied for this project if the components are defective and during the entire warranty period IA shall apply all the latest patches/updates for all the software components after appropriate testing. The Hardware warranty shall be for a period of 3 years.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 22 of of of of 48
2.20. Operations & Maintenance of Application Software
The IA shall keep the application software in good working order, meeting the
requirements defined by the Department, perform changes and upgrades to
applications as requested by the Department, within the overall scope of the quality
and quantity of functionalities to be delivered under this RFP. The following is the
broad scope for maintenance and support functions with regard to the software:
Application Software Maintenance
The IA shall rectify all the errors/bugs/gaps/ modification on account of
rule/acts/policy change of Government in the functionality offered by EeGP (vis-à-vis
the SRS signed off by Department, EeGP) at no additional cost during the operations
& maintenance period. For performing any functional changes to system, which are
deviating from the signed-off Functional Requirements/System Requirements, a
separate Change Control Notice (CCN) shall be prepared by IA and shall be
mutually agreed between IA and the Department. No additional cost is permissible
for implementation of such CCN during the project period.
2.21. Project Deliverables
The IA has to submit the list of deliverables to the Department as part of an
assurance to fulfill the obligations under the SLA. IA is responsible to provide all
those deliverables which will be specified in this Project Plan and those agreed by
IA in response to any request from the Department:
S.No. Deliverables
1.
a. Detailed Project plan for Design, Development & Implementation of
EeGP (within 3 weeks from award of contract). The plan should clearly
identify all the milestones and deliverables together with the tasks and
time & resource allocation.
2. a. Training strategy training plan & training material
3. a. System Requirement Specifications (SRS) Document (Updated)
4.
a. Technical / System Design Document including but not limited to
• Logical and Physical Data Base Design
• Logical Data Dictionary and data / file formats
• Component, and Deployment Views of the Application
• Collaboration, class diagrams in UML notations
• Security and Features
• Performance Features
• Interface / Control Design Features
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 23 of of of of 48
b. Traceability Matrix
c. Document on Testing Approach for EeGP Application, along with the
test cases & test results.
5. a. Developed and customized EeGP solution source code
6.
a. List of IT Infrastructure with detailed specification for Servers, Network,
Storage, system Software, including the equipment to be setup at DC,
DRC
b. Establishing the IT & Non-IT infrastructure at all locations
7. a. Security Policy
b. Standard Operating Procedures
8. a. Completion of Training for all the users
b. Updated Training & User Manuals
9.
a. Defect Free EeGP Application Software along with Source Code, Library
files, Components, Setup programs, Documentation, etc.,
b. Updated & Final System Requirements and Design Documents
c. SLA Monitoring & Measurement system using SLA-MMS tool.
10.
a. Call Log / emails & Resolution Reports for Helpdesk
b. Daily / Weekly / Fortnightly / Monthly Performance Monitoring Reports
for the EeGP
11. All licenses in ownership of Excise dept
12. The ownership of source code shall be transferred to the department after
the Acceptance test.
2.22. Strategic Control of EeGP
The application and system as a whole will be tested and certified by a neutral
third party, an Agency identified by the department once before declaring Go-Live
and then periodically (say, every year).
2.23. Project Implementation Timelines
The overall implementation of the EeGP has been envisaged to be for 36 weeks from
start of work by the selected IA as mentioned in the Table below.
S. No Milestone Completion
1 Requirement Study and updation of SRS for integration
services, data exchange with corporate modules (including
data exchange format specs) and publishing of EA.
8 Weeks from the
date of contact
signing.
2 Design of web based Integrated EeGP Solution 4 Weeks
3 Development of Integrated EeGP Solution 12 Weeks
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 24 of of of of 48
4 Setup, Installation & Commissioning of DC, DRC 4 Weeks
5 Acceptance Testing 4 Weeks
6 Training of the staff on EeGP Solution 8 Weeks
Total 36 Weeks from
the date of
contact signing.
As referred above, is the date of EITHER the ‘award of contract’ notification
issued by the Department to selected IA OR the signing of contract between
selected IA and the Department OR the meeting conducted by the Department to
kick-off the project; whichever happens the earliest.
2.24. Scope of Contract and Provision of Services
Scope of contract This MSA shall govern the provision of the Services by the Implementing Agency, listed
hereunder and more fully described, conformance with the SLA, to all the Stakeholders.
It is anticipated that new or renewal agreements may be undertaken by creating a
separate SLA, with schedules and exhibits as required, under this MSA. The time frame,
within which the various activities and tasks relating to the scope of work have to be
executed, is given in 2.23 in scope of work. The IA shall strictly adhere to the schedule
for implementation of the Project”
Period of contract
The MSA shall come into effect on the Effective date and shall continue for a period of 5
years from the “Go-Live” date of the EeGP Project at all the Implementation Sites,
unless terminated earlier in accordance with the terms of this MSA (“Term”).
Scope and provision of the services
1. The provision of Services to the Stakeholders with certainty and speed is of the
essence of the Agreement between the Parties.
2. The Services shall be performed by the Implementing Agency strictly as per the
SLA as detailed in Annexure D of this MSA.
3. No Party to this MSA or the SLA will at any time perform, or omit to perform,
any act which they are aware, at the time of performance, will place the other
Party in default under any insurance policy, mortgage or lease, governing
activities at any location provided by the Department.
4. Implementing Agency shall not accept for its own benefit any trade
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 25 of of of of 48
commission, discount or similar payment in the discharge of its obligation
hereunder. The Implementing Agency shall ensure that its personnel, agents,
consultants etc. similarly shall not receive any such additional remuneration.
5. Implementing Agency acknowledges the relationship of trust and confidence
established between Implementing Agency and the Department by this
Agreement. Accordingly, Implementing Agency’s acts shall always be
consistent with this relationship. Implementing Agency shall always act, in
respect of any matter relating to this Agreement, as an honest and faithful
service provider to the Department. Implementing Agency shall, at all times,
support and safeguard the Department legitimate interests in any dealings with
the contractors, vendors, or other third parties.
Approvals and required consents
The Parties will cooperate reasonably to obtain, maintain and observe all relevant and
customary regulatory and governmental licenses, clearances and applicable approvals
(hereinafter the “Approvals”) necessary for the Implementing Agency to undertake
implementation of the EeGP Project and provide the Services. The costs of such
Approvals shall be borne by the Implementing Agency.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 26 of of of of 48
3. Instruction to Bidders
3.1. General Introductions
Name of the Client : Prohibition and Excise Department, AP,
Hyderabad
Description of the
System for
which bids are
invited
: Study, Design, Develop, Procure,
Implementation, Operate & Maintenance
of Excise e-Governance Project (EeGP)
3.2. General Eligibility
1. Bidders marked/considered by APTS to be ineligible to participate for non-satisfactory past performance, corrupt, fraudulent or any other unethical business practices shall not be eligible.
2. Corrupt, fraudulent and unethical practices means:
i. “Corrupt practice” means the offering, giving, receiving or soliciting of
any thing of value to influence the action of a public official in the process of contract execution and
ii. “fraudulent practice” means a misrepresentation of facts in order to influence a procurement process or the execution of a contract to detriment of the purchaser, and includes collusive practice among Bidders (prior to or after bid submission) designed to establish bid prices at artificial non-competitive levels and to deprive the Purchaser of the benefits of free and open competition:
iii. “Unethical practice” means any activity on the part of bidder which try to circumvent tender process in any way. Unsolicited offering of discounts, reduction in financial bid amount, upward revision of quality of goods etc after opening of first bid will be treated as unethical practice.
3. APTS will reject a proposal for award and also may debar the bidder for future tenders in Andhra Pradesh Technology Services, if it determines that the bidder has engaged in corrupt, fraudulent or unethical practices in competing for, or in executing a contract.
4. Breach of general or specific instructions for bidding, general and special conditions of contract with APTS or any of its user organisations may make a firm ineligible to participate in bidding process.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 27 of of of of 48
3.3. Cost of Bidding & Site Visit
The IA shall bear all the cost associated with the preparation and submission of bid
including prototype presentation. The client/consultant will in no case be responsible or
liable for those costs.
3.4. Pre-bid meeting
All those who have purchased bidding document can participate in pre-bid meeting to
seek clarification on the bid if any. Attending pre-bid meeting is advisable for the IAs.
IAs who fail to attend the pre-bid meeting have no right for to claim the deviations from
the bid document which are not part of the scope of the work.
S.
No.
Bidding Document Reference(s)
(section number/ page)
Content of RFP
requiring
Points of
clarification
All clarifications should be sent either by email from email ID of primary contact person
from the primary contact person to APTS on or before the deadline mentioned in the
RFP. Telephone calls will not be accepted for clarifying the queries. Only 2 primary
contact persons as authorized by the company may participate in the Pre-Bid meeting
and should carry;
1. An Authorization Letter issued from their company.
2. An identity proof issued by their company
It may be noted that participants not carrying the above documents will not be allowed
to attend the Pre-Bid meeting. The participants are advised to be present 30 minutes in
advance to the scheduled time of the Pre-Bid Meeting.
APTS will not be responsible if the bidder has not attended the pre bid event and does
not receive the clarifications. Please note that not attending the Pre–Bid Meeting will not
be a cause for disqualification of a bidder.
3.5. Clarification on bidding document
1. APTS may modify the RFP document by issuing amendment(s). All bidders will be notified of such amendment(s) by publishing on the APTS website, and these will be binding on all the bidders
2. In order to allow bidders a reasonable time to take the amendment(s) into account in preparing their bids, APTS, at its discretion, may extend the deadline for the submission of bids.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 28 of of of of 48
3.6. Address for clarification
Address: Andhra Pradesh Technology Services Limited.
Boorgula Ramakrishna Rao Bhavan, B-block,
4th floor,Tank bund Road,Hyderabad, Andhra Pradesh - 500 063, India.
Telephones 91 (40) 23220305, 91 (40) 23223753
Fax: 91 (40) 23227458, Email: [email protected]
3.7. Amendment of bidding document
1. At any time prior to the deadline for submission of bids, APTS, for any reason, whether at its own initiative or in response to a clarification requested by a prospective bidder, may modify the bidding documents by amendment.
2. All prospective bidders those have received the bidding documents will be notified of the amendment, and such modification will be binding on all bidders.
3. In order to allow prospective bidders reasonable time in which to take the amendment into account in preparing their bids, the APTS, at its discretion, may extend the deadline for the submission of bids.
3.8. Cost of Bid Preparation
The bidder shall bear all costs associated with the preparation and submission of its bid
and APTS shall in no event or circumstance be held responsible or liable for these
costs, regardless of the conduct or outcome of the bidding process. All costs incurred in
connection with participation in the bidding process, including, but not limited to, costs
incurred in participation in meetings/ discussions/ presentations, preparation of
proposal, in providing any additional information required by APTS to facilitate the
evaluation process and in negotiating a definitive contract or all such activities related to
the bid process will be borne by the bidder. This RFP does not commit APTS to award a
contract or to engage in negotiations. Further, no reimbursable cost may be incurred in
anticipation of award.
Bidders shall furnish the required information on their technical and commercial
proposals in the enclosed formats only. Any deviations in format or if the envelopes are
not sealed properly will make the tender liable for rejection.
3.9. Right to Terminate the Process
APTS makes no commitments, explicit or implicit, that this process will result in
a business transaction with anyone. Further, this RFP does not constitute an
offer by the APTS. The bidder’s participation in this process may result in
APTS selecting the bidder to engage in further discussions and negotiations
towards execution of a contract. The commencement of such negotiations
does not, however, signify a commitment by APTS to execute a contract or to
continue negotiations.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 29 of of of of 48
Annexure F
EXISTING HARDWARE DETAILS
Name of the Office
Name of the
Computer &
Configurations
Year of
Supply
No.
Compute
rs
Name of the
Printer
No.
Printe
rs
Year of
Supply
Addl.Commr.
HQRS,Hyderabad Acer 2008 1 Hp 1 2008
Addl.Commr. Acer 2008 1 Hp 1 2008
Secretary Acer 2008 1 Hp 1 2008
JC (Enft) NIL NIL 0 NIL 0 NIL
JC (Director Academy) Acer 2008 1 Samsung 1 2008
JC Distilleries Acer 2008 1 HP 1 2008
AS Services) Acer 2008 1 Samsung 1 2008
AS Hqrs Acer 2008 1 samsung 1 2008
AS (M&A) Acer 2008 1 NIL 0 NIL
AS labels Acer 2008 1 Samsung 1 2008
DC Computers Acer 2008 1 - 0 -
J.D. Technical Acer 2008 1 NIL 0 NIL
PA to CPE Acer 2008 1 Samsung 1 2008
PA to Secy Acer 2008 1 HP 1 2008
A- Section Acer, HCL,HCL
2008 , 2007,
2007 3 HP 3 2008, 2003
B-section Acer, 2008, 1 HP 1 2,003
C-Section Acer, HCL 2008, 2007 2 HP 1 2003
D-Section Acer 2008 1 samsung 1 2008
E-Section Acer, HCL 2008, 2007 2 HP 2 2008, 2003
G-Section Acer, HCL 2008, 2007 2 HP 2 2008, 2003
H-Section Acer 2008 1 HP 1 2003
I-Section Acer 2008 1 HP 1 2008
J-Section Acer 2008 1 HP 1 2003
K-Section Acer, HCL 2008, 2007 2 HP 2 2008, 2003
L-Section Acer, HCL 2008, 2007 2 HP 1 2003
M-Section Acer, HCL 2008, 2007 2 HP 2 2008, 2003
T-Section Acer, HCL 2008, 2007 2 HP 2 2008, 2003
A5 - Section Acer 2008 1 samsung 1 2008
PA to Addl.Commr HCL 2003 1 HP 1 2003
AAO Acer 2008 1 Samsung 1 2008
DoE A- Section Acer, HCL 2008, 2007 2 HP 2 2008, 2003
DoE C- Section Acer 2008 1 HP 1 2008
DoE B- Section NIL NIL 0 NIL 0 NIL
AC STF Acer 2008 1 HP 1 2008
DDBAS Distilleries NIL NIL 0 NIL 0 NIL
A- Section NIL NIL 0 NIL 0 NIL
B-section NIL NIL 0 NIL 0 NIL
LC (Labelling Cell NIL NIL 0 NIL 0 NIL
DC (Enft) Acer 2008 1 NIL 0 NIL
DC - Hyderabad Zenith,Assembles( 2002, 2007 3 HP, MSP, 3 2009,
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 30 of of of of 48
2) TVS 2002,98
DC - Ranga Reddy HCL,Assembled 2009 3 HP, HP 1050 2 2008
DC - Adilabad Assembled 2009 1 Canon 1 2009
DC - Nizamabad Assembled 2006 1 HP 1020 1 2006
DC - Medak HCL 2008 1 Canon 1 2010
DC - Nalgonda
HCL 2010 1
HP Laser jet
M1319f
MFD
1 2010
DC - Mahaboobnagar Wipro 1999, 2005 2 HP,HP 2 1999, 2005
DC - Warangal Wipro 1999 1 - 0
DC - Karimnagar Wipro 1999 1 TVS 1 1999
DC - Khammam Wipro, Comaq 1999, 2008 2 Samsung 1 2008
DC - Kurnool HP 2005 1 HP 1020 1 2005
DC - Chittoor Lenovo 3000 2006 2 HP Laser jet 1 2006
DC - Anantapur Wipro 1999 1 TVS 1 1999
DC - Kadapa HCL 2008 1 HP Laser Jet 1 2008
DC - Nellore HCL 2006 1 Canon 1 2006
DC - Prakasam Dell 2009 1 HP 1 2009
DC - Guntur Dell 2011, 2012 4 HP 4 2011, 2012
DC - Vijayawada HCL 2007 1 HP Laser jet
3050 1 2007
DC - West Godavari HCL,LG 2006 2
TVS, HP -
3050 2 2006
DC - East Godavari Wipro, PCS, HP
1999, 2008,
2008 3
TVS 345 &
HP 2 1999, 2008
DC - Visakhapatnam wipro 1999 1 dotmatrix 1 1999
DC - Vizianagaram Wipro 1999 1 Dot Matrix 1 1999
DC - Srikakulam HCL Pentium R 2006 1 HP Laser jet 1 2006
AC - Srikakulam Zenth 1999 1 TVS 1 1999
AC - Vizianagaram Acer 2005 1 HP 1 2005
AC - Visakhapatnam Zenth 2001 1 TVS 1 2001
AC East Godavari LG 2005 1 HP 1 2005
AC - West Godavari Assenbled 2005 1 HP 1 2005
AC - Krishna Assembled 2005 1 Not working 0 0
AC - Guntur Zenth 1999 1 Dot matrix 1 1999
AC - Ongole Dell 2005 1 Canon 1 2005
AC - Nellore LG 2006 1 EPSON 1 2006
AC - Chittoor Zenth 1999 1 Dot matrix 1 1999
AC - Anantapur Zenith 1999 1 Dot Matrix 1 1999
AC - Kadapa HCL 2009 1 HP 1 2009
AC - Kurnool Wipro 1998 1 TVS-32 1 1998
AC - Adilabad Wipro 1998 1 TVS-32 1 1998
AC - Karimnagar Wipro 1998 1 TVS-32 1 1998
AC - Medak HCL 2009 1 Canon 1 2009
AC - Nizamabad LG 2010 1 Samsung 1 2012
AC - Khammam NIL NIL 0 NIL 0 NIL
AC - Nalgonda Wipro 1998 1 TVS-32 1 1998
AC - Mahabubnagar Wipro 1998 1 TVS-32 1 1998
AC - Warangal Acer 1999 1 TVS 1 1999
AC - Hyderabad PCS 2005 1 HP 1 2006
AC - Ranga Reddy Assenbled 2002 1 HP 1 2005
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 31 of of of of 48
AC - Distilleries Tirupati Acer 2008 1 Samsung 1 2008
AC - Distilleries Kakinada Acer 2005 1 TVS 1 1999
AC - Distilleries
Vijayawada Acer 2008 1 Samsung 1 2008
AC - Distileries
Hyderabad-I NIL NIL 0 NIL 0 NIL
AC - Distileries
Hyderabad-II Acer 2008 1 Samsung 1 2008
Assistant Secretary(Hqrs) Acer 2008 1 Samsung 1 2008
Assistant Secretary(Enft) NIL NIL 0 NIL 0 NIL
ES - Srikakulam Wipro 1998 1 TVS 1 1998
ES - Palasa HCL 2005 1 HP3050 1 2005
ES - Vizianagaram Wipro 1999 1
TVS Dot
matrix 1 1999
ES - Parvathipuram HCL 2005 1 HP 1 2005
ES - Visakhapatnam HCL 2003 1 HP 1 2003
ES - Anakapalli HCL 2006 1 HP 1 2006
ES - Gajuwaka HCL 2006 1 HP 1 2006
ES - Kakinada Wipro 1999 1
TVS Dot
matrix 1 1999
ES - Rajahmundry Assembled 2005 1 Canon 1 2005
ES - Amalapuram NIL NIL 0 NIL 0 NIL
ES - Eluru HCL 2005 1 HP 1 2005
ES - Bhimavaram HCL 2005 1 HP 1 2006
ES - Machillipatnam Dell 2006 1 HP 1 2006
ES - Vijayawada PCS 2009 1 HP 1 2009
ES - Guntur Wipro 1998 1 TVS 1 1998
ES - Tenali Acer 2005 1 HP 1 2005
ES - Narsaraopeta Acer 2003 1 HP 1 2003
ES - Ongole Wipro 1999 1 TVS 1 1999
ES - Markapur PCS 2007 1 HP 1 2007
ES - Nellore NIL NIL 0 NIL 0 NIL
ES - Gudur HP, Micro PVT 2006 2 HP 2 2006
ES - Chittoor Wipro 1999 1
TVS Dot
matrix 1 1999
ES - Tirupati Wipro 1998 1 TVS 1 1998
ES - Anantapur Wipro 1999 1
TVS Dot
matrix 1 1999
ES - Penukonda Samsung 2006 1 NIL 0 NIL
ES - Kurnool Wipro 1999 1
TVS Dot
matrix 1 1999
ES - Nandyal Wipro 1998 1 TVS 1 1998
ES - Kadapa Wipro, PCS, HP 1998, 2006 2
TVS, HP -
3050 2 1998, 2006
ES - Proddatur Assembled 2005 1 HP 1 2005
ES - Hyderabad Wipro, Acer 1998, 2008 2
TVS, HP -
3050 2 1998, 2008
ES - Secunderabad HP 2005 1 HP 1 2005
ES - Dhoolpet Compaq 2006 1 HP 1 2006
ES - Saroornagar Wipro 1998 1 TVS 1 1998
ES - Medchal PCS, Compaq 20,062,009 2 HP 1 2006
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 32 of of of of 48
ES - Rajendranagar Compaq, PCS 2006, 2008 2 HP 2 2006, 2008
ES - Mahabubnagar Assembled 2007 1 HP 1 2008
ES - Nagarkurnool HP 2007 1 HP 1 2007
ES - Gadwal NIL NIL 0 NIL 0 NIL
ES - Nalgonda Wipro 1999 1
TVS Dot
matrix 1 1999
ES - Miryalaguda HP & PCS 2007 2 HP 2 2007
ES - Nizamabad Assembled 2007 1 HP 1 2006
ES - Kamareddy PCS 2006 1 HP 1 2006
ES - Medak Assembled 2005 1 HP 1 2005
ES - Sangareddy Wipro 1998 1 MSP-345 1 1998
ES - Warangal Compaq 2003 1 HP 1 2003
ES - Mahabubabad PCS 2006 1 HP 1 2006
ES - Khammam LG(2) 2003, 2005 2 HP Canon 2 2005, 2003
ES - Kothagudem Assembled 2006 1 HP 1 2006
ES - Karimnagar Assembled 2006 1 HP 1 2006
ES - Godavarikhani PCS 2006 1 HP 1 2006
ES - Jagital HP 2006-2007 1 HP 1 2007-2008
ES - Adilabad Wipro 1999 1
TVS Dot
matrix 1 1999
ES - Mancherial PCS 582 2007 1 HP 1 2007
TOTAL 163 149
Statement showing the list of Check Post in Prohibition and Excise Department
Sl.No. Name of the check Post Name of the District
1 Kodikonda
Ananthapur
2 Thumukunta
3 Vidapanakal
4 Gadakale
5 Malkamarru
6 Obulapuram
7 Rly. Station Gunthakal
8 Naraharipet(ICP)
Chittor
9 Palamaner
10 Punganur
11 Baireddypalli
12 Venkatadrikota
13 Bheemunivaripalem(ICP) Nellore
14 Salura(ICP)
Nizamabad 15 Madnur (Salabathpur)
16 Yamcha
17 Zaheerabad Medhak
18 Purushottamapuram Srikakulam
19 Ichapuram(ICP)
20 Krishna
Mahaboobnagar 21 Nandini
22 Ravulapally
23 Nepapalli East Godavari
24 Eduralanka
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 33 of of of of 48
25 Sunkarapalam
26 Kunta Khammam
27 Bhoraj (ICP)
Adilabad
28 Bhainsa
29 Womkidi
30 Ghampur
31 Laxmipur
32 Madhavaram
Karnool
33 Kosgi
34 Halarive
35 Haoligonda
36 Sirignppa
37 Naguladinne
38 Saluru Vijayanagaram
39 Paravathipuram
Statement Showing the Asst. Commnr. Distilleries, Hyd-1
Sl.No. Name of the Distilleries Location
1 M/s. A.P.Met Bolaram, Medak Dist.
2 M/s. Viva Dolan Spirits Gaganpahad, R.R.Dist.
3 M/s. Aroma Disst. Sanathnagar, Hyd.
4 M/s. Kapitan Disst. Balnagar, Hyd.
5 M/s. Rhizome Disst. Medchal, R.R. Dist.
6 M/s. R.K. Disst. Medchal, R.R. Dist.
7 M/s. Shaw Wallace & Co.
8 M/s. SKOL Breweries Medhak Dist.
9 M/s. Nizam Sugars
10 M/s. N.S.L. Mumbojipally
11 M/s. Paramount Disst.
12 M/s. Bhavani Disst.
13 M/s. Bekelte Hylen
14 M/s. Raichem Industries
15 Excise Officer, Balanagra
16 Excise Officer, Jeedimetla
17 Excise Officer, Patancheruvu
18 O/o The A.C.(D)
Statement Showing the Asst. Commnr. Distilleries, Hyd-II Sl.No. Name of the Distilleries Location
1 M/s. Bagga Disst. Sathamarai, R.R.Dist.
2 M/s. Hyderabad Disst. IDA Uppal, Hyd.
3 M/s. Kamal Wilery Disst. Kothur, Mahaboobnagar
4 M/s. Khoday Industries Shamshabad, R.R.Dist.
5 M/s. Liquor India Ltd. IDA Nacharam, Hyd.
6 M/s. United Spirits Malkajgiri, Hyd.
7 O/o The A.C.(D)II
8 M/s. Indian Chemicals
9 M/s. Paras Collins Shamshabad, R.R.Dist.
10 M/s. Radico Khaitan Ltd. Thimmapur, Mahaboobnagar
11 M/s. Sri Venkateshwara Disst. Toopran, Medhak
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 34 of of of of 48
12 M/s. United Breweries Nacharam, Hyd.
13 Excise Officer, Charminar
14 Excise Officer, Nacharam
15 O/o. The AC(D)II
16 M/s. Priyanka Disst.
17 M/s. Vindale Disst. & Breweries
18 M/s. Parke Devis
19 O/o The AC(D)II
Statement Showing the Asst. Commnr. Distilleries, Thirupati Sl.No. Name of the Distilleries Location
1 M/s. Eagle Disst. Kadapa Town, Kadapa Dist.
2 M/s. Empee Sugars
3 M/s. Esveeaar Disst. Renikunta, Thirupati
4 M/s. Mohan Breweries Pallur(V), Chitoor
5 M/s. O.R. Disst.
6 M/s. Sagar Sugars & Allied Products
7 Excise Officer Industries, Thirupati
Statement Showing the Asst. Commnr. Distilleries, Vijayawada Sl.No. Name of the Distilleries Location
1 M/s. Andhra Sugars
2 M/s. Continental Wines
3 M/s. Durga Liquors Kankipadu, Krishna Dist.
4 M/s. Gowtham Agro Industries Chintalpudi, West Godavari
5 M/s. H.K.V.P.B.C. Ltd.
6 M/s. Jeypore Sugars
7 M/s. K.C.P. Ltd.
8 M/s. Pearl Disst. Singarayakonda, Prakasham Dist.
9 M/s. Sree India Disst.
10 M/s. Sree Rama Disst.
11 Excise Officer Vijayawada
12 O/o The AC(D)
Statement Showing the Asst. Commnr. Distilleries, Kakinada Sl.No. Name of the Distilleries Location
1 M/s. Artos Breweries Ramachandrapuram, E.Godavari
2 M/s. G.M.R. Sankali
3 M/s. Navabharathi Ferro Alloys
4 M/s. N.C.S. Estates
5 M/s. Prag Disst. Rangampet, E.Godavari
6 M/s. Savaraya Sugars
7 M/s. Tem Disst.
8 M/s. United Millineum Bantupalli(V), Sreekakulam Dist.
9 Excise Officer Kakinada
10 O/o The AC(D)
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 35 of of of of 48
List of SHOs
SL.NO REVENUE DIST.
HEADED BY D.C.
NAME OF THE
EXCISE
DIST.HEADED BY
P&ES(WORKING
UNDER DC)
NAME’S OF THE S.H.O’S
WORKING UNDER P&ES /D.C.
TOTLAL
S.H.O.’S
IML DEPOTS/CHECK
POSTS/ BMPP
1 2 3 4 5 6
1 SRIKAKULAM 1.P&ES
SRIKAKULAM
1.SHO SRIKAKULAM
14
1.IML DEPOT
SRIKAKULAM
2.SHO AMUDALAVALASA 2.CHECK POST
PURUSHOTTAPURAM
3.SHO RANASTHALAM 3.CHECK POST
VASUNDARA
4. SHO PONDURU 4.BMPP-1
PATAPATNAM
5.SHO NRASANNAPETA 5.BMPP-II PALASA
6.PALAKONDA 6.BMPP-III SOMPETA
7.SHO RAJAM 7.BMPP-IV
ICHAPURAM
2.PALASA 1.SHO PATAPATNAM
2.SHO KOTHURU
3.SHO TEKKALI
4.SHO KOTABOMMALI
5.SHO PALASA
6.SHO SOMPETA
7.SHO ICHAPURAM
2 VIZIANAGARAM 2.P&ES
VIZIANAGARAM
1.SHO VIZIANAGARAM-I
13
1.CHECK POST
P.KONAVALASA
2. SHO VIZIANAGARAM-II 2.CHECK POST
KONERU
3.SHO BHOGAPURAM 3.IML NELLIMARLA.
4.SHO SHO CHEEPURUPALLI
5.SHO NELIMARLA
6.SHO GAJAPATHINAGARAM
7.SHO S.KOTA
8.KOTHAVALASA
2.P&ES
PARVATHIPURAM
1.SHO BOBBILI
2.SHO THERLAM
3.SHO SALUR
4.SHO PARVATHIPURAM
5.SHO KURUPAM
3 VISHAKAPATNAM 1.P&ES
VISHAKAPATNAM
1.SHO VISHAKAPATNAM-I
17
1.BMPP PADERU
2. SHO VISHAKAPATNAM-II 2.BMPP CHINTAPALLI
3. SHO VISHAKAPATNAM-III 3.BMPP ARAKU
4. SHO VISHAKAPATNAM-IV 4.BMPPNARSIPATNAM
2.P&ES
ANAKAPALLI
1.SHO CHODAVARAM 5.IML DEPOT VIZG-I
2.SHO MADUGULA 6. IML DEPOT VIZG-II
JERRIPOTHULAPALEM
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 36 of of of of 48
3.SHO ANAKAPALLI 7.CHEMICAL
EXAMINER
VISHAKAPATNAM.
4.SHO NARSIPATNAM
5.SHO CHINTAPALLI
6.SHO YELAMANCHILLI
7.SHO PAYAKARAO PETA
8.SHO PADERU
9.SHO ARAKU
3.GAJUWAKA 1. SHO VISHAKAPATNAM-V
(PENDURTHY)
2.SHO GAJUWAKA
3.SHO BEEMILI
4.SHO SABBAVARAM
4 EAST GODAVARI 1.P&ES KAKINADA 1.SHO KAKINADA-I(SOUTH)
19
1.CHECK POST
SUNKARAPALEM
2. SHO KAKINADA-II NORTH 2.BMPP NEELAPALLI
3.SHO PITAPURAM 3.BMPP
SUNKARAOALEM
4.SHO TALLAREVU 4.IML DEPOT EG-I
SAMAIKOTA
5.SHO PEDDAPURAM 5.IML DEPOT EG-2
RAJAMUNDRY
6.TUNI 6.IML DEPOT-3
AMALAPURAM
2.P&ES
RAJAMUNDRY
1.SHO RAJAMUNDRY-INORTH 7. CHEMICAL
EXAMINER,
KAKINADA.
2. SHO RAJAMUNDRY-II
SOUTH
3.SHO ALAMURU
4.SHO RAYAVARAM
5.SHO KORUKONDA
6.SHO RAMPACHODAVARAM
7.SHO ADDALEEGALA
8.PRATHIPATU
3.P&ES
AMALAPURAM
1.SHO RAMCHANRAPURAM
2.SHO AMALAPURAM
3.SHO MUMMIDIVARAM
4.SHO KOTHAPETA
5.SHO RAZOLE
5 WEST GODAVARI 1.P&ES ELURU 1.SHO ELURU
13
1.IML DEPOT
CHANGALLU
2.SHO CHINTHALAPUDI 2.IML DEPOT-2, ELURU
3.SHO BIMADOLE
4.SHO KOVVUR
5.SHO JANGAREDDYGUDEM
6.SHO POLAVARAM
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 37 of of of of 48
7.SHO TADEPALLIGUDEM
2.P&ES
BHIMAVARAM
1.SHO TANUKU
2.SHO PALAKOLE
3.SHO NARASAPURAM
4.SHO BHIMAVARAM
5.SHO AKIVEDU
6.SHO PENUGONDA
6 KRISHNA 1.P&ES
MACHILLIPATNAM
1.SHO MACHILIPATNAM
20
1.IML DEPOT
VIJAYAWADA-1, AUTO
NAGAR
2.SHO BANTUMILI 2.IML DEPOT
VIJAYAWADA -2,
GUDIWADA.
3.SHO AVANIGADDA
4.SHO MOVVA
5.SHO GUDIWADA
6.SHO KAIKALURU
7.SHO MANDAVALLI
8.SHO GANAVARAM
9.SHO VUYYURU
2.P&ES
VIJAYAWADA
1.SHO VIJAYAWADA EAST
2. SHO VIJAYAWADA WEST
3. SHO
VIJAYAWADAPATAMATA
4. SHO
VIJAYAWADABHAVANIPURAM
5.SHO NANDIGAMA
6.SHO MYALAVARAM
7.SHO KANCHIKACHERLA
8.SHO JAGGAIAHPETA
9.SHO NUZIVID
10.SHO TIRUVURU
11.SHO VISSANAPET
7 GUNTUR 1.P&ES GUNTUR 1.SHO GUNTUR –I
20
1.IML DEPOT
GUNTUR-I
2.SHO GUNTUR-II 2.IML DEPOT
GUNTUR-2, TENALI,
3.SHO MANGALAGIRI 3.IML DEPOT
GUNTUR-3,
NARSARAOPETA
4.SHO PEDAKURAPADU 4.CHEMICAL
EXAMINER
GUNTUR(I/C).
5.SHO PRATHIPADU
2.P&ES TENALI 1.SHO TENALI
2. SHO DUGGIRALA
3.SHO REPALLE
4.SHO NAGARAM
5.SHO BAPATLA
6.SHO PONNURU
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 38 of of of of 48
3.P&ES
NARSARAOPETA
1.SHO SATENAPALLI
2.SHO KROSURU
3.SHO NARSARAOPETA
4.SHO CHILAKALURIPETA
5.SHO PIDUGURALLA
6.SHO MANCHERALA
7.SHO VINUKONDA
8.SHO GURAJALA
9.SHO IPUR
8 PRAKASAM 1.P&ES ONGOLE 1.SHO ONGOLE
14
1.IML DEPOT
PERNAMITTA ONGOLE 2.SHO CHIMAKURTHY
3.SHO CHIRALA
4.SHO PARCHOOR
5. SHO ADDANKI
2.P&ES MARKAPUR 1.SHO SHO KANDUKUR
2.SHO SINGARAYA KONDA
3. SHO PODILI
4.SHO DARSI
5. SHO KANIGIRI
6.SHO MARKAPUR
7.SHO YERRAGONDAPALEM
8.SHO GIDDALURU
9.SHO CUMBUM
9 S.P.S.R.NELLORE 1.P&ES NELLORE 1.SHO NELLORE-I
15
1.IML DEPOT
DEVARALAPLEM
NELLORE
2.SHO NELLORE-II 2.B.V.PALEM CHECK
POST.
3.SHO KAVALI
4.SHO UDAYAGIRI
5.SHO VINJAMOOR
6.SHO KOVUR
7.SHO ATMAKUR
8.SHO INDUKURPET
9.SHO BUCHIREDDYPALEM
2.P&ES GUDUR 1.SHO GUDUR
2.SHO VAKADU
3.SHO SULLURPET
4.SHO NAIDUPET
5.SHO VENKATAGIRI
6.SHO RAIPUR
10 CHITTOOR 1.P&ES CHITTOOR 1.SHO CHITTOOR URBAN
18
1.IML DEPOT –I
PULAKALAPATTU
2.SHO CHITTOOR RURAL 2.IML DEPOT –II
TIRUPATI
3.SHO KARVETI NAGAR 3.CHEMICAL
EXAMINER CHITTOOR.
4.SHO MADANAPALLE
5. SHO MULAKALACHERUVU
6.SHO PUNGANUR
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 39 of of of of 48
7.SHO PALAMANER
8.SHO KUPPAM
9.SHO VAYALPAD
10.SHO PILER
2.P&ES TIRUPATI 1.SHO TIRUPATI URBAN
2.SHO TIRUPATI RURAL
3.SHO PAKALA
4.SHO PUTTUR
5. SHO TIRUMALA
6.SHO SRIKALAHASTHI
7.SHO SATHYAVEDU
8. SHO NAGARI
11 ANANTAPUR 1.P&ESS
ANANTAPUR
1.SHO ANATAPUR
18
1.IML DEPOT
GEORGEPET 2.SHO GOTTY
3.SHO GUNTAKAL
4.SHO URAVAKONDA
5.SHO TADIPATRI
6.SHO SINGANAMALA
7.SHO KANEKAL
8.SHO RAYADURY
2.P&ES
PENUKONDA
1.SHO DHARMAVARAM
2.SHO KALYANDURG
3.SHO KAMBADUR
4.SHO C.K.PALLI
5.SHO PENUKONDA
6.SHO PUTTAPARTY
7.SHO HINDUPUR
8.SHO KADIRI
9.SHO TANAKAL
10.SHO MADAKASIRA
12 KURNOOL 1.P&ES KURNOOL 1.SHO KURNOOL
14
1.IML DEPOT
KURNOOL
2.SHO KODURNUR 2.NAGULADINNE
CHECK POST
3.SHO NANDIKOTKUR 3.MADHAVAM CHECK
POST
4.SHO ALUR 4.HOLAGUDA CHECK
POST
5.SHO SDONI 5.P.HARIVANAM
CHECKPOST
6.SHO YEMMIGANUR 6.CHATRAGUDI
CHECKPOST
7.SHO KOSIGI 7.BAPURAM
CHECKPOST
8.SHO PATHIKONDA 8.BMPP
YEMMIGANUR
2.P&ES NANDYAL 1.SHO DHONE 9.CHEMICAL
EXAMINER, KURNOOL
2.SHO ATMAKUR
3.SHO NANDYAL
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 40 of of of of 48
4.SHO ALLAGADDA
5.SHO KOLLAKUNTLA
6.SHO BANAGANAPALLI
13 KADAPA 1.P&ES KADAPA 1.SHO KADAPA
13
1.IML DEPOT KADAPA.
2.SHO RAYACHOTY
3.SHO LAKKIREDDYPALEM
4.SHO RAJAMPET
5.SHO SIDHOUT
6.SHO KODUR
2.P&ES
PRODDATUR
1.SHO YERRAGUNTLA
2.SHO JAMMALAMADUGU
3.SHO PRODDATUR
4.SHO PULLIVENDULA
5.SHO MUDDANUR
6.SHO MYDUKUR
7.SHO BADVEL
14 HYDERABAD 1.P&ES
HYDERABAD
1.SHO NAMPALLY
11
1.IML DEPOT –I,
PEERJADIGUDA
2.SHO GOLCONDA 2.IML DEPOT-II,
KOMPALLY.
3.SHO AMEERPET.
2.P&ES
SECUNDERABAD
1.SHO SECUNDERABAD
2.SHO MUSHEERABAD
3.SHO MAREDPALLY
4.SHO KACHIGUDA
3.P&ES DHOOLPET 1.SHO DHOOLPET
2.SHO NARAYANAGUDA
3.SHO CHARMINAR
4.SHO MALAKPET
15 RANGAREDDY 1.P&ES
SAROORNAGAR
1.SHO SAROORNAGAR
17
1.IML DEPOT –
RANGAREDDY
2.SHO HAYATHNAGAR 2.IML DEPOT-
BORAMPET
3.SHO IBRAHIMPATNAM 3.IML DEPOT JALPALLY
4.SHO MAHESHWARAM 4.IML DEPOT DEVARA
YANJAL.
5.SHO UPPAL
6.SHO GHAYKESAR
2.P&ES MEDCHAL 1.SHO MEDCHAL
2.SHO MALKAJGIRI
3.SHO QUTHUBULLAPUR
4.SHO BAL;ANAGAR
3.P&ES RAJENDRA
NAGAR
1.SHO RAJENDRA NAGAR
2.SHO CHEVELLA
3. SHO PARGI
4.SHO SHERILINGAMPALLY
5.SHO VIKARABAD
6.SHO MARPALLY
7.SHO TANDUR
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 41 of of of of 48
16 MAHABOOBNAGAR 1.P&ES
MAHABOOBNAGAR
1.SHOMAHABOOBNAGAR
16
1.IML POST TIMAJIPET
2.SHO JADCHERTLA 2.KRISHNA CHECK
POST
3.SHO SHADNAGAR 3.KRISHNA CHECK
POST
4.SHOKODANGAL 4.NANDINI CHECPOST
2.P&ES
NAGARKURNOOL
1.SHO NAGARKURNOOL 5.NANDINI CHECK
POST
2.SHO KOLLAPUR 6.RAVALAPALLY
CHECK POST
3.SHO ACHAMPET 7.BMPP BALGERA
4.SHO TELKAPALLY 8. BMPP BALGERA
5.SHO KALWAKURTY 9.BMPP NARAYANPET
6. AMANGAL. 10. BMPP
NARAYANPET
3.P&ES GADWAL 1.SHO GADWAL
2.SHO ALAMPUR
3.SHO WNARPARTY
4.SHO KOTHKOTA
5.SHO NARAYANPET
6.SHOATMAKUR
17 NALGONDA 1.P&ES NALGONDA 1.SHO NALGONDA
15
1.IML DEPOT-I
NALGONDA
2.SHO HALIYA 2.IML DEPOT-
IIKONDAMADUGU.
3.SHO DEVARAKONDA
4.SHONAMPALLY
5.SHO BHONGIR
6.SHORAMANAPET
7.SHO ALAIR
2.P&ES
MIRYALAGUDA
1.SHO NAKREKAL
2.SHO SURYAPET
3.SHO THUNGATHURTHY
4.SHO CHANDOOR
5.SHO MIRYALAGUDA
6.SHO HUZURNAGAR
7.SHO KODAD
8.SHO MOTHKUR
18 NIZAMABAD 1.P&ES
NIZAMABAD
1.SHO BHEERNGAL
10
1.IML DEPOT
MADAPUR (V)
MAKNOOR (M)
2.SHO ARMOOR 2.SALOORA CHECK
POST
3.SHO NIZAMABAD 3.MADHURU CHECK
POST
4.SHO BODHAN 4.YAMCHA CHECK
POST
5.SHO MORTHAD 5.CHEMICAL
EXAMINER,
NIZAMABAD.
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 42 of of of of 48
2.P&ES
KAMAREDDY
1.SHO BICHKUNDA
2.SHO BANSWADA
3.SHO KAMAREDDY
4.SHODOMAKONDA
5.SHO YELLAREDDY
19 MEDAK 1.P&ES MEDAK 1.SHO MEDAK
11
1.IML DEPOT
CHINNAGHAPUR
2.SHO RAMAYAMPET 2.ZAHEERABAD CHECK
POST
3.SHO SIDDIPET 3.ZAHEERABAD BMPP
4. SHO MIRDODDI
5.SHO GADWAL
2.P&ES
SANGAREDDY
1.SHO SANGAREDDY
2.SHO PATANCHEERU
3.SHO ZAHEERABAD
4.SHO NARAYANKHED
5.SHO ANDOLE
6.SHO NARSAPUR
20 WARANGAL 1.P&ES WARANGAL 1.SHO WARANGAL URBAN
17
1.IML DEPOT
SINGARAM (V) WRL
2.SHO WARANGAL RURAL 2.CHEMICAL
EXAMINER,
WARANGAL.
3.SHO HANAMKONDA
4.SHO KAZIPET
5.SHOGHANPUR
6.SHO JANGOAN
7.SHO CHERIAL
8.SHO WARDHANNAPET
9.SHO KODAKANDLA
2.P&ES
MAHABUBABAD
1.SHO MAHABUBABAD
2.SHO THRRUR
3.SHO NARSAMPET
4.SHO GUDUR
5.SHO GUDUR
6.SHO ETURNAGARAM
7.SHO PARKAL
8.SHO BHOOPALPALLY
21 KHAMMAM 1.P&ES KHAMMAM 1.SHO KHAMMAM
14
1.CHECK POST CHATTI
2.SHO NALAKONDAPALLY 2.IML DEPOT, WYRA,
KHAMMAM.
3.SHO WYRA
4.SHOMADHIRA
5.SHO SATHUPALLY
6.SHOYELLANDU
7.SHOSINGARENI
2.P&ES
KOTHAGUDEM
1.SHO KOTHAGUDEM
2.SHO PALVANCHA
3.SHO ASWARAOPET
4.SHO BHADRACHALAM
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 43 of of of of 48
5.SHO BURGAMPAHAD
6.SHO MANUGURU
7.SHO VENKATAPURAM
22 KARIMNAGAR 1.P&ES
KARIMNAGAR
1.SHO KARIMNAGAR URBAN
16
1.IML DEPOT
KARIMNAGAR. 2.SHO KARIMNAGAR RURAL
3.SHO HUSNABAD
4.SHO HUZURABAD
5.SHO JAMMIKUNTA
2.P&ES
GODAVARIKHANI
1.SHO PEDDAPALLY
2.SHO SUTHANANBAD
3.SHO GODAVARIKHANI-I
4.SHOGIDAVARIKHANI-II
5.SHO MANTHANI
3.P&ES JAGITAL 1.SHO JAGITAL
2.SHO SIRSILLA
3.SHO YELLAREDDYPET
4.SHOVEMULAWADA
5.SHO DHARMAPURI
6.SHO METPALLY
23 ADILABAD 1.P&ES ADILABAD 1.SHO ADILABAD
11
1.IML DEPOT-I
2.SHO ICHODA 2. IML DEPOT –II
MANCHERIAL
3.SHO UTNOOR 3. BHORAJ CHECK
POST
4.SHO NIRMAL 4.BHORAJ CHECK POST
5.SHO SHAINSA 5.LAXMIPUR
CHECKP[OST
2.P&ES
MANCHERIAL
1.SHO MANCHERIAL 6.GHANPUR
CHECKPOST
2.SHO ASIFABAD 7.GHANPUR
CHECKPOST
3.SHO KAGAZNAGAR 8.BHAINSA CHECK
POIST
4.SHO BELIAMPALLY 9.WANKIDI CHECK
POST
5.SHO CHENNUR 10.WANKIDI CHECK
POST.
6.SHO LUXETTIPET
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 44 of of of of 48
Statement Showing the List of Various Sections and Peshi's in Hqrs., Nampally
Sl.No. Name of the Section/ Peshi No.of Computers
1 CPE Peshi 1
2 Secy. Peshi 1
3 Addl. CPE 1
4 Addl. CPE Hqrs. 1
5 A.S.(Services) 1
6 DoE Peshi 1
7 J.C. Enft. Peshi 1
8 A-Section 2
9 A5 2
10 B 2
11 C 2
12 D 2
13 E 2
14 G 2
15 H 2
16 I 2
17 J 2
18 K 2
19 L 2
20 M 2
21 N 1
22 T 2
23 Care Taker 1
24 Record Room 1
DoE Sections
1 A 2
2 B 2
3 C 2
4 Control Room 2
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 45 of of of of 48
Name of the Chemical Examiners and their locations
Sl.No Name of the Chemical Examiner Districts Covered
1. Chemical Examiner at
Visakhapatnam
Vzag, Vizianagaram and Srikakulam
2. Chemical Examiner at Kakinada East, West Godavari and Krishna
3. Chemical Examiner at Guntur Guntur, Prakasam and Nellore
4. Chemical Examiner at Chittoor Chittoor and Anantapur
5. Chemical Examiner at Kurnool Kurnool and Kadapa
6. Chemical Examiner at Hyderabad Hyderabad, Ranga Reddy and Mahabubnagar
7. Chemical Examiner at Nizamabad Nizamabad, Medak and Nalgonda
8. Chemical Examiner at Warangal Warangal, Khammam, Karimnagar and Adilabad
Name of the Deputy Commissioner’s and their Locations:
Sl.No Designations Locations
1. Deputy Commissioner Srikakulam
2. Deputy Commissioner Vizianagaram
3. Deputy Commissioner Visakhapatnam
4. Deputy Commissioner East Godavari
5. Deputy Commissioner West Godavari
6. Deputy Commissioner Krishna
7. Deputy Commissioner Guntur
8. Deputy Commissioner Prakasam
9. Deputy Commissioner Nellore
10. Deputy Commissioner Chittoor
11. Deputy Commissioner Kadapa
12. Deputy Commissioner Anantapur
13. Deputy Commissioner Kurnool
14. Deputy Commissioner Hyderabad
15. Deputy Commissioner Ranga Reddy
16. Deputy Commissioner Mahabubnagar
17. Deputy Commissioner Nagonda
18. Deputy Commissioner Nizamabad
19. Deputy Commissioner Medak
20. Deputy Commissioner Warangal
21. Deputy Commissioner Khammam
22. Deputy Commissioner Karimnagar
23 Deputy Commissioner Adilabad
24. Deputy Commissioner DC(Computers), Hyderabad
25 Deputy Commissioner DC(Enforcement), Hyderabad
Name of the Assistant Commissioner’s and their Locations:
Sl.No. Designations Locations
1. Assistant Commissioner Srikakulam
2. Assistant Commissioner Vizianagaram
3. Assistant Commissioner Visakhapatnam
4. Assistant Commissioner East Godavari
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 46 of of of of 48
5. Assistant Commissioner West Godavari
6. Assistant Commissioner Krishna
7. Assistant Commissioner Guntur
8. Assistant Commissioner Prakasam
9. Assistant Commissioner Nellore
10. Assistant Commissioner Chittoor
11. Assistant Commissioner Kadapa
12. Assistant Commissioner Anantapur
13. Assistant Commissioner Kurnool
14. Assistant Commissioner Hyderabad
15. Assistant Commissioner Ranga Reddy
16. Assistant Commissioner Mahabubnagar
17. Assistant Commissioner Nagonda
18. Assistant Commissioner Nizamabad
19. Assistant Commissioner Medak
20. Assistant Commissioner Warangal
21. Assistant Commissioner Khammam
22. Assistant Commissioner Karimnagar
23. Assistant Commissioner Adilabad
24. Assistant Commissioner AC(STF) Hyderabad
25. Assistant Commissioner AC Distilleries, Hyderabad-I
26. Assistant Commissioner AC Distilleries- Hyderabad-II
27. Assistant Commissioner AC Distilleries, Vijayawada
28. Assistant Commissioner AC Distilleries, Tirupati
29. Assistant Commissioner AC Distilleries, Kakinada
30. Assistant Commissioner Assistant Secretary (Enft)
31. Assistant Commissioner Assistant Secretary (Hqrs)
Note: Remaining (07) Posts of A.C.’s cadre are allotted to Depots and Depot Managers in APBCL.
Name of the Officers in Head Quarters
Sl.No. Designation Location
1. Commissioner of Proh. & Excise Hyderabad
2. Secretary to CPE Hyderabad
3. Director of Enforcement Hyderabad
4. Additional Commissioner Hyderabad
5. Additional Commissioner (Hqrs) Hyderabad
6. Asst. Secretary (Services) Hyderabad
7. Asst. Secretary (Hqrs) Hyderabad
8. Asst. Secretary (m&A) Hyderabad
9. Asst. Secretary (Labels) Hyderabad
10. LAPP Hyderabad
11. Joint Commissioner (Distilleries) Hyderabad
12. Joint Commissioner (Enft) Hyderabad
13. Joint Commssioner (GM Excise) Hyderabad
14. Joint Commissioner (Director Academy) Bandlaguda, Hyderabad
15. Deputy Commissioner (Enft) Hyderabad
16. Deputy Commissioner Academy Hyderabad
17. Deputy Commissioner (Computers) Hyderabad
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 47 of of of of 48
Director of Distilleries and Breweries:
Sl.No Designation Locaton
1. Commissioner of Distilleries & Breweries Hyderabad
2. J.D. Distilleries Hyderabad
3. J.D. Technical Hyderabad
Hardware Procurement through Hologram Project:
Sl.No Offices No. Of Systems Required
1. Excise stations 350
2. Enforcement 100
3. Head Quarters 10
4. DC 23
5. ES 58
6. Miscellanea 10
7. Depot 39*(*Likely to go upto 50)
8. C.O. 10
*The number of work stations at each depot may be 4(four) at the minimum amd 6(Six) at the maximum
apts Confidential and Proprietary RFP – Excise e-Governance Project (EeGP) for Prohibition & Excise Department
APTS : One Stop-Shop Solution provider for e-Governance. Page: 48 of of of of 48
List of Abbreviations ist of Abbreviations ist of Abbreviations ist of Abbreviations
For full details , the bidder to purchase RFP document
available at IV-Floor, APTS, BRKR Bhavan,
Hyderabad,AP.
S. No. Abbreviation Description
1 AI Application Identifiers
2 APTS Andhra Pradesh Technology Services Ltd
3 ASCII American Standard Code for Information Interchange
4 CCD Charge Couple Device
5 CMT Change Management Team
6 CPU Central Processing Unit
7 CVC Central Vigilance Commission
8 ECE Electrolytic Chemical Etching
9 EDGE Enhanced Data rates for GSM Evolution also known as EGPRS
10 EeGP Excise e-Governance Project
11 EMD Earnest Money Deposit
12 EMIS Excise Management Information System
13 GCC General Conditions of Contract
14 GoAP Government of Andhra Pradesh
15 GoI Government of India
16 GPRS General packet radio service
17 GSM Global System for Mobile Communications: originally from Groupe
Special Mobile
18 HTTPS Hypertext Transfer Protocol over Secure Socket Layer
19 IA Implementing Agency
20 ICT. Information & Communication Technology
22 IIP Internet Imaging Protocol
23 NA Not applicable
24 SCC Special Conditions of the Contract
25 SCM Software Configuration Management
26 TCPC Technical Cum Purchase Committee
27 LOI Letter of Intent