reservoir flood mapping background and progress · 2018-04-03 · reservoir flood mapping - team...
TRANSCRIPT
Reservoir Flood MappingBackground and progress
James Cheetham
Senior Analyst, JBA Consulting
2
Overview
• What is RFM and what are the drivers for it?
• Background to the study
• Delivering the Reservoir Flood Mapping project (RFM)
• Improvements incorporated into the new RFM Specification
• Project deliverables
• Conclusions
Reservoir Flood Mapping
“Reservoir flood maps are used to inform people about areas at risk of flooding in the event of a dam or reservoir failure and sudden uncontrolled escape of water.” RFM Specification 2016
• Multiple formats
• Multiple uses
• Multiple applications
3
Teton Dam, USA. Wikipedia
Drivers for RFM
• Flood Risk Regulations require a review of 2009/10 reservoir flood hazard mapping
• Changing requirements• Updated legislation requires risk categorisation of reservoirs
• Use by reservoir owners, undertakers and general public to assess risk
• Spatial planning purposes to identify appropriate development or mitigation downstream from a dam
• Not constrained to the listed uses
4
Background to the RFM Project
5
2008 2010 2014
2015
2016
2017
2018
2019
NRIM+NRIM
NRIM+
Lessons learned
exercise
RFM Tasks
1, 2, 3 & 4
All ~2,000 statutory
reservoirs in England
and Wales using the
2009 RIM spec
NRIM+ was a follow-on
commission for 225
reservoirs in England only –
newly constructed or
missed out of NRIM – also
uses 2009 RIM spec.
• Task 1 – Research in to breach model, reservoir data and 2-D routing model
• Task 2 – Development of an updated RFM specification
• Task 3 – Reservoir data collection exercise
• Task 4 – Reservoir Flood Mapping for large raised reservoirs in England
NRIM = National Reservoir Inundation Mapping
Reservoir Flood Mapping - Team
• Consortium of three consultants
• JBA Consulting• Continuity from NRIM+ and RFM Tasks 1, 2 & 3.
• Experience of large-scale GPU modelling
• NRIM involvement
• Mott MacDonald• Extensive in-house Reservoir Engineer expertise
• NRIM involvement
• BMT• TUFLOW development
• NRIM experience
6
Reservoir Flood Mapping - Hardware
7
• The Grid
• Massive Graphics Processing Unit (GPU) capacity
• Economics of scale
• Secure file access & sharing in a common data location
• Advanced scheduling
• Custom built
Reservoir Flood Mapping – Software
• TUFLOW HPC
• Custom TUFLOW development to deliver the RFM project
• Satisfies Environment Agency 2D hydraulic model benchmarking criteria
• Implements full Shallow Water Equations (SWE)
• Utilises GPU technology – vastly reduced simulation time
• Custom automation tools
• Model setup undertaken in ArcGIS
• Minimises manual interaction and increase standardisation
• Increases efficiency by speeding up repeated process
8
RFM compared to NRIM
9
Category NRIM RFM Improvements
Use of Reservoir
Flood Maps
Single use Multiple uses Expanded range of applications
Modelled
scenarios
Wet day Dry day, fluvial & wet day Far more comprehensive assessment.
3x as many simulations
Digital Terrain
Model (DTM)
5-20m cell size 2m cell size Significantly improved quality of outputs
~6x longer compute time
~6x larger output grids
Reservoir water
level
0.1 or 0.5m
increment
Accounts for catchment &
reservoir characteristics
Far more accurate estimations
Additional analysis effort
Impact
assessment
Likely Loss Of
Life (LLOL)
Detailed assessment Extended range of application of outputs
Additional analysis effort
Model quality SWE on Phase
2 reservoirs
only
SWE on all reservoirs Improved and consistent quality of outputs for
all reservoirs.
Additional effort
Transport
embankments &
large culverts
No specific
treatment
Flood backup and
subsequent breach of
TEs simulated
Improved quality of outputs
Additional analysis effort
Improved RFM Project Outputs – Spatial resolution & representation of hydraulic structures
10
• Improved model spatial resolution
• (RFM 2m, NRIM 5-20m)
• Finer topographic detail
• Results in improved flow route definition
• Improved representation of hydraulic structures
• Greater precision in DTM cuts
• Inclusion of large culverts with representative losses and capacity
• Representation of transport embankment failure
Improved RFM Project Outputs – Representation of transport embankments
• New to RFM
• Road embankment attenuating flow
• Upstream pooling identified
• Profile shows impact of embankment
11
Improved RFM Project Outputs – Wet Day scenario
• The Wet Day scenario represents a significant development in RFM over the NRIM approach
• Includes dynamic modelling of fluvial flooding downstream from a dam
• Intended to reduce storage prior to dam failure
12
Dry Day Wet Day
Wet Day Flood Hydrograph
• The Wet day scenario simulates an event where the dam breaks during a 1 in 1000 year fluvial flooding event in the valley d/s of the dam
• The flood hydrograph (solid blue) is made up of two components:
• Dam break (dotted orange) – relatively short in duration, but with large peak flow and fast wave velocity
• Fluvial (dashed red) – relatively long in duration with smaller peak flow and slower wave velocity
13
Wet Day scenario sensitivity testing
• Feedback from PSG raised concerns over the reliability of wet day maps leading to further sensitivity testing of the methods used• Flood risk potentially underestimated away from the location where
breach and fluvial hydrographs coincide
• Addressed through sensitivity testing that revealed:• Underestimation small for large proportion of reservoirs
• Tools developed to determine underestimation
• Tools run on 300 reservoir outputs to build evidence base
14
Reservoir Flood Mapping – Project deliverables
15
PDF Maps
Wet & Dry Day
Flood Extent
MapsWet & Dry Day
Flood Depth
MapsWet & Dry Day
Flood Velocity
Maps
Wet & Dry Day
Flood Hazard
MapsWet & Dry Day
Property Impact
MapsMultiple breach
composite maps
for all map
types
Flood
Modelling
Summary
Sheet
Digital Deliverables
TUFLOW model
data
GIS
Raster
data
GIS
Vector
data
Consequence
Metrics
RFM deliverables – Dry Day flood extent
16
Reservoir Flood Mapping - Conclusions
• The RFM project is programmed to continue until 2020• Final product available in 2020
• RFM has resulted in revised deliverables that are of a higher quality compared to NRIM and available for a greater number of uses
• RFM is delivering reservoir flood mapping for both dry day and wet day scenarios
• The RFM has been through a comprehensive review process resulting in increased confidence in the wet day mapping
17