respondent memorandum vis 22

53
Twenty Second Annual Willem C. Vis International Commercial Arbitration Moot MEMORANDUM FOR RESPONDENT On behalf of: Against: Mediterraneo Mining SOE Vulcan Coltan Ltd Global Minerals Ltd 5-6 Mineral Street 21 Magma Street Excavation Place 5 Capital City, Mediterraneo Oceanside, Equatoriana Hansetown, Ruritania as RESPONDENT as CLAIMANT as ADDITIONAL PARTY International University “MITSO” Minsk, Republic of Belarus Artem Azamatov •Daria Andronova •Herman Khomchanka• Nastassia Kashchyshyna •Aliaksandra Pakhomava• Stahiy Sviridovich

Upload: janet-nyx

Post on 04-Dec-2015

271 views

Category:

Documents


16 download

DESCRIPTION

MITSO

TRANSCRIPT

Page 1: Respondent Memorandum Vis 22

Twenty Second Annual

Willem C. Vis International Commercial Arbitration Moot

MEMORANDUM FOR RESPONDENT

On behalf of: Against:

Mediterraneo Mining SOE Vulcan Coltan Ltd Global Minerals Ltd

5-6 Mineral Street 21 Magma Street Excavation Place 5

Capital City,

Mediterraneo Oceanside, Equatoriana Hansetown, Ruritania

as RESPONDENT as CLAIMANT as ADDITIONAL PARTY

International University “MITSO”

Minsk, Republic of Belarus

Artem Azamatov •Daria Andronova •Herman Khomchanka•

Nastassia Kashchyshyna •Aliaksandra Pakhomava• Stahiy Sviridovich

Page 2: Respondent Memorandum Vis 22

ii

TABLE OF CONTENT

LIST OF ABBREVIATIONS ..................................................................................................................iv

INDEX OF LEGAL SOURCES.............................................................................................................vi

INDEX OF AUTHORITIES .................................................................................................................vii

INDEX OF CASES AND ARBITRAL AWARDS .............................................................................xi

OTHER SOURCES ...............................................................................................................................xviii

Statement of facts.........................................................................................................................................1

Summary of arguments................................................................................................................................3

PROCEDURAL ISSUE I...........................................................................................................................4

I. THE ARBITRAL TRIBUNAL HAS JURISDICTION OVER GLOBAL MINERALS...........4

1. Global Minerals is a party to the contract and the arbitration agreement contains therein..........4

2. The Guarantee provisions justify the extension of arbitration agreement over Global Minerals5

3. The arbitration agreement can be extended over Global Minerals under the Group of

Companies Doctrine....................................................................................................................................6

3.a. The Group of Companies Doctrine is used in international arbitration to justify the extension

of arbitration agreement..............................................................................................................................7

3.b. The requirements under the Group of Companies Doctrine are fulfilled ...................................8

3.b.i. Global Minerals controls CLAIMANT...........................................................................................8

3.b.ii. Global Minerals and CLAIMANT involvement into the Contract constitutes one economic

reality ..............................................................................................................................................................9

3.b.iii. Global Minerals is bound by the arbitration agreement ...........................................................10

4. Good Faith Considerations justify the extension of arbitration agreement over Global Minerals

.......................................................................................................................................................................11

ISSUES ON MERITS...............................................................................................................................12

II: CLAIMANT IS NOT ENTITLED TO RECEIVE 30 METRIC TONS OF COLTAN

UNDER THE CONTRACT...................................................................................................................12

A. RESPONDENT’s avoidance of the contract on 7 july 2014 is legitimate...................................14

1. CLAIMANT has not fulfilled its obligation under the Contract and under Art. 54 CISG........14

1.a. The amount of money stated in the L/C 1 is not in conformity with the Contract.................16

1.b. The quantity of goods stated in the L/C 1 is not in conformity with the Contract .................16

1.с. The Delivery Term contained in the L/C 1 is not in conformity with the Contract................17

2. Inappropriate L/C 1 amounts to fundamental breach under Art. 25 CISG.................................18

2.a. The breach of established L/C 1 serves as a reason of substantial deprivation

RESPONDENT of what it is entitled to expect under the Contract ................................................19

Page 3: Respondent Memorandum Vis 22

iii

2.b. CLAIMANT could foresee the results of established L/C 1.......................................................19

3. RESPONDENT avoided the Contract on 7 July 2014 abiding by the terms of Art. 72 CISG.19

3.a. The Parties never modify the due date of the performance .........................................................20

3.b. CLAIMANT could foresee the avoidance of Contract as a result of its own violations.........20

3.c. RESPONDENT did not get the adequate assurance of obligation’s performance from

CLAIMANT ...............................................................................................................................................21

B. RESPONDENT rightfully avoided the contract on 9 July 2014...................................................22

1. CLAIMANT committed a fundamental breach of the Contract, by establishing inappropriate

L/C 2............................................................................................................................................................22

1.a. CLAIMANT failed to establish proper Letter of Credit on time................................................23

1.a.i. CLAIMANT had an obligation to notify RESPONDENT about the establishment of L/C

.......................................................................................................................................................................23

1.a.ii. The information upon the establishment of the L/C 2 had reached RESPONDENT’S

office out of business hours for notification..........................................................................................24

1.b. CLAIMANT by inserting a commercial invoice as an additional document in the L/C 2

committed a fundamental breach.............................................................................................................25

2. Late delivery of L/C substantially deprived RESPONDENT from what it expected under the

Contract .......................................................................................................................................................26

PROCEDURAL ISSUE 2 ........................................................................................................................28

III. The order of the Emergency Arbitrator should not be lifted by the arbitral tribunal...............28

1. Under Article 29 (6) b of ICC Rules 2012 the parties did opt out the Emergency Arbitrator

provisions ....................................................................................................................................................28

1. a. The parties can agree to exclusive court jurisdiction to impose interim measures. .................28

1.b. The interpretation of Art. 21 of the Coltan Purchase Contract provides for the exclusive

jurisdiction of courts to grant interim measures....................................................................................29

1.b.i. The rule of literal interpretation must be observed. ....................................................................29

1.b.ii. UNIDROIT Principles 2010 allows interpreting Art. 21 of the Contract against

CLAIMANT ...............................................................................................................................................31

2. The substantive requirements for granting interim measures are not fulfilled. ............................31

2. a. CLAIMANT did not demonstrate urgency ...................................................................................32

2.b. There was no irreparable harm imminent to CLAIMANT..........................................................33

2.c. CLAIMANT has no possibility of success on the merits. ............................................................33

REQUEST FOR RELIEF .......................................................................................................................35

Page 4: Respondent Memorandum Vis 22

iv

LIST OF ABBREVIATIONS

Answer to Req. for Arb. Answer to Request for Arbitration

Art Article

CISG United Nations Convention on Contracts for

the International Sale of Goods (1980)

Coltan Purchase Contract / contract/Contract COLTAN PURCHASE CONTRACT,

concluded between Mediterraneo Mining SOE

and Vulcan Coltan Ltd on the 28th of March,

2014

Digest of case law

UNCITRAL Digest of case law on the United

Nations Convention on the International Sales of

Goods 2012

Dr. iur. Doctor iuris

EA, Emergency Arbitrator

Emergency Arbitrator, appointed by the

President of the International Court of

Arbitration of the International Chamber of

Commerce on the 12th of July, 2014

Ex. Exhibit

ICC 1998 Rules The Rules of Arbitration of the International

Chamber of Commerce (1998)

ICC Rules 2012 The Rules of Arbitration of the International

Chamber of Commerce (2012)

Id (idem) The same

INCOTERMS 2010 The INCOTERMS Rules 2010

infra Reference to the provision discussed later

L/C Letter of Credit

L/C 1 Letter of Credit of 4th July 2014

L/C 2 Letter of Credit of 8th July 2014

M for Cl. Memorandum for CLAIMANT

para/paras Paragraph/ Paragraphs

p. Page

PO 2 Procedural Oder № 2

Prof. Professor

Page 5: Respondent Memorandum Vis 22

v

Req. for Arb Request for Arbitration

supra Reference to the previously written provision

UCP 600 The Uniform Customs and Practice for

Documentary Credits ICC Publication no. 600

DAL UNCITRAL Model Law on International

Commercial Arbitration 1985 with

amendments as adopted in 2006

UNIDROIT Principles/ UNIDROIT 2010

UNIDROIT Principles on International

Commercial Contracts 2010

Page 6: Respondent Memorandum Vis 22

vi

INDEX OF LEGAL SOURCES

United Nations Convention on Contracts for the International Sale of Goods, Vienna

1980

(Cited as: CISG)

[§7, §60, §63, §64, §67, §72, §73, §75, §82, §84, §86,§87, §88, §89, §91, §93, §94, §96, §98,

§102, §103, §105, §111, §113, §117, §118]

CONVENTION ON THE SETTLEMENT OF INVESTMENT DISPUTES BETWEEN

STATES AND NATIONALS OF OTHER STATES

(Cited as: ICSID Convention)

[§ 138]

ICC Uniform Customs and Practice for Documentary Credits

(Cited as: UCP 600)

[§71, §89]

The Rules of Arbitration of the International Chamber of Commerce (2012)

(Cited as: ICC Rules 2012)

[§ 3, 132, 136, 139, 149, 159]

Rules of Arbitration of the International Chamber of Commerce (1998)

(Cited as: ICC 1998 Rules)

[§ 148]

UNCITRAL Model Law on International Commercial Arbitration 1985

With amendments as adopted in 2006

(Cited as: DAL)

[161, 163]

UNIDROIT Principles of International Commercial Contracts 2010

(Cited as: UNIDROIT 2010)

[§85, §113, §118, §144, §154, §155, §156]

Page 7: Respondent Memorandum Vis 22

vii

INDEX OF AUTHORITIES

Adodo, Ebenezer

Letters of Credit: The Law and Practice of Compliance

Ebenezer Adodo

Product: International Commercial Law [ICML], 2014

(Cited as: Letters of Credit: The Law and Practice of

Compliance)

[§75, §79]

Amerasinghe, Chittharanjan International Arbitral Jurisdiction

International Litigation in Practice, 1933

Chittharanjan F. Amerasinghe

(Cited as: Chittharanjan F. Amerasinghe)

[§50]

Baigel, Baruch

The Emergency Arbitrator Procedure under the 2012

ICC Rules: A Juridical Analysis

Baruch Baigel

(2014) 31 Journal of International Arbitration,

(Cited as: Baigel)

[§162]

Ben-Shahar, Omri "Contracts Without Consent: Exploring a New Basis for

Contractual Liability" (2004)

Omri Ben-Shahar

Law & Economics Working Papers Archive: 2003-2009.Paper

28.

(Cited as: BEN-SHANAR)

[§67, §119]

Bix, Brian Consent in Contract Law (2008)

Brian Bix

THE ETHICS OF CONSENT: THEORY AND

PRACTICE, Edited by Alan Wertheimer, Franklin G.

Miller, eds.,

Oxford University Press, 2010;

Minnesota Legal Studies Research Paper No. 08-36.

Page 8: Respondent Memorandum Vis 22

viii

Available at SSRN: http://ssrn.com/abstract=1140256

(Cited as: BIX)

[§119]

Borcky, Ron Understanding and Using Letters of Credit, Part II

Ron Borcky

(Cited as: CRF, Ron Borcky Understanding and Using Letters of

Credit, Part II)

[§120]

DERAINS, Yves

GOODMAN-EVERARD, Rosabel

France. In: ICCA International Handbook of Commercial

Arbitration,

Supplement 26, February, 1998

DERAINS, Yves, GOODMAN-EVERARD, Rosabel

(Cited as: DERAINS & GOODMAN-EVERARD)

[§40]

Drahozal, Christopher Party Autonomy and Interim Measures in International

Commercial Arbitration,

Christopher R. Drahozal

University of Kansas School of Law, August 5, 2011

(Cited as: Drahozar )

[§136]

Hanotiau, Bernard

COMPLEX ARBITRATIONS: MULTIPARTY,

MULTICONTRACT, MULTI-ISSUE AND CLASS

ACTIONS

Bernard Hanotiau

Kluwer Law International, 2005

(Cited as: Hanotiau)

[§53]

Kryvoi, Yaraslau

Piercing the Corporate Veil in International Arbitration

Yaraslau Kryvoi

Global Business Law Review1 (2011): p. 177.

(Cited as: Kryvoi Yaraslau)

[§24]

Monteiro, Felicity “The UCP 600 — Developments In Documentary Credit

Law”

Page 9: Respondent Memorandum Vis 22

ix

Felicity Monteiro

New Zealand Law Journal September 2007

(Cited as: Felicity Monteiro)

[§71]

Müller, Thomas

Extension of arbitration agreements to third parties under

Swiss law

Thomas Müller

(Cited as: Thomas Müller)

[§17]

n/a COMMENTARY ON THE UNIDROIT PRINCIPLES

OF INTERNATIONAL COMMERCIAL CONTRACTS

(PICC)

Edited by Stefan Vogenauer and Jan Kleinheisterkamp,

2009

(Cited as: Commentary on UNIDROIT Principles 2010)

[§110, §157]

n/a UNCITRAL Digest of Case Law on the United Nations

Convention on Contracts for the International Sale of

Goods

UNITED NATIONS COMMISSION ON

INTERNATIONAL TRADE LAW

UNITED NATIONS, New York, 2012

(Cited as: Digest of case law)

[§72, §82, §86, §111, §128]

Schlechtriem, Peter

Schwenzer, Ingeborg

COMMENTARY ON THE UN CONVENTION ON

THE INTERNATIONAL SALE OF GOODS (CISG)

THIRD EDITION

Schlechtriem & Schwenzer

Oxford University Press (2010)

(Cited as: Schlechtriem)

[§66, §68, §86, §101, §127]

Wilske, Stephan Shore, Laurence and Ahrens, Jan-Michael

The group of companies doctrine – where is it heading?

Wilske, Stephan, Shore, Laurence Ahrens, Jan-Michael

American Review of International Arbitration, Vol. 17

Page 10: Respondent Memorandum Vis 22

x

(2006): 74�

(Cited as: Wilske, Stephan, Shore, Laurence Ahrens, Jan-Michael)

[§22]

Winsor, Katrina The Applicability of the CISG to Govern Sales of

Commodity Type Goods

Katrina Winsor

14Vindobona Journal of International Commercial Law and

Arbitration (1/2010) 83-116

Cited as: Katrina Winsor

[§65, §69, §78, §87]

Yesilirmak, Ali Provisional Measures in International Commercial

Arbitration, Ali Yesilirmak (2005)

Kluwer Law International

(Cited as: Yesilirmak)

[§138, §142, §165]

Page 11: Respondent Memorandum Vis 22

xi

INDEX OF CASES AND ARBITRAL AWARDS

CASES

Australia

Downs Investments v. Perwaja Steel

Australia 17 November 2000 Supreme Court of Queensland (Downs Investments v. Perwaja Steel)

Available at:: http://cisgw3.law.pace.edu/cases/001117a2.html]

Cited as: Down Investments Pty Ltd. v. Perjawa Steel SDN BHD

[§72, §128]

Brazil

Itarumг Participaзхes S.A. v Participaзхes em Complexos Bioenergйticos S.A

Available at: http://kluwerarbitrationblog.com/blog/2012/10/26/brazilian-court-clarifies-

jurisdiction-for-interim-measures/

Cited as: Itarumг Participaзхes S.A. v Participaзхes em Complexos Bioenergйticos S.A

[§151]

Canada

Ahousaht Indian Band V Canada (Fisheries and oceans)

Available at: http://www.blg.com/en/newsandpublications/publication_3800

Cited as: AHOUSAHT INDIAN BAND V. CANADA (FISHERIES AND OCEANS)

[§173]

France

Sociйtй Alcatel Business Systems (ABS), Sociйtй Alcatel Micro Electronics (AME) et Sociйtй AGF v.

Amkor Technology

Cour de cassation, Mar. 27, 2007

Cited as: Société Alcatel Business Systems (ABS), Société Alcatel Micro Electronics (AME) et Société

AGF v. Amkor Technology Case

[§10]

Sociйtй Korsnas Marma v. Sociйtй Durand A Auzias

CA Paris, 30 November 1988

The Practice of Arbitration: Essays in Honour of Hans van Houtte

Page 12: Respondent Memorandum Vis 22

xii

Cited as: Société Korsnas Marma v. Société Durand A Auzias

[§15]

Sociйtй Ofer Brothers v. The Tokyo Marine and Fire Insurance Co Ltd

CA Paris

The extension of the arbitration clause to non-signatories — the irreconcilable positions of

French and English courts; Pierre Mayer

Cited as: Société Ofer Brothers v. The Tokyo Marine and Fire Insurance Co Ltd

[§15]

Kis France SA v. SA Societe Generale

France, 31 October 1989,Court of Appeal of Paris

Yearbook Commercial Arbitration Vol. XVI (A.J. van den Berg ed. Kluwer Law and Taxation

Publishers, Deventer/Netherlands 1991): 145 – 149

Cited as: Kis France SA v. SA Societe Generale

[§29]

Sponsor AB v. Ferdinand Louis Lestrade

France, Nov. 26, 1986, Court of Appeal of Pau

Yearbook Commercial Arbitration, Vol. XIII (A.J. van den Berg ed., Kluwer Law and Taxation

Publishers, Deventer/Netherlands 1988): 149 – 151

Cited as: Sponsor A.B. v. Lestrade

[§28]

Germany

Broadcasters case

Germany 24 July 2009 Appellate Court Celle (Broadcasters case) [translation available]

Available at: http://cisgw3.law.pace.edu/cases/090724g1.html]

Cited as: Broadcasters case

[§111]

Machinery case

Germany 31 October 2001 Supreme Court (Machinery case)

Available at: http://cisgw3.law.pace.edu/cases/011031g1.html]

Page 13: Respondent Memorandum Vis 22

xiii

Cited as: Machinery case

[§111]

Pitted sour cherries case

Germany, 3 August 2005 District Court Neubrandenburg

Available at:: http://cisgw3.law.pace.edu/cases/050803g1.html]

Cited as: Pitted sour cherries case

[§111]

Cheese case

Germany, 29 December 1998 Hamburg Arbitration proceeding

Available at: http://cisgw3.law.pace.edu/cases/981229g1.html]

Cited as: Cheese case

[§96]

Italy

Trade usage case

Italy, 21 November 2007, Tribunale [District Court] Rovereto

Takap B.V. v. Europlay S.r.l.

Available at: http://cisgw3.law.pace.edu/cases/071121i3.html]

Cited as: Takap B.V. v. Europlay S.r.l.; Trade usage case

[§111]

Netherlands

Metal ceiling materials case

Netherlands, 25 February 2009

District Court Rotterdam (Fresh-Life International B.V. v. Cobana Fruchtring GmbH & Co., KG)

Available at: http://cisgw3.law.pace.edu/cases/090225n1.html]

Cited as: Metal ceiling materials case

[§111]

Singapore

Win Line (UK) Ltd v Masterpart (Singapore)

The Singaporean High Court

Page 14: Respondent Memorandum Vis 22

xiv

Pte Ltd [2000] 2 SLR 98

Cited as: The Singaporean High Court, Win Line (UK) Ltd v Masterpart (Singapore)

[§31]

Switzerland

Case No. ATF 129 III 727

Tribunal Federal (2003)

Cited as: ATF 129 III 727

[§55]

United Kingdom

R v Harris (1836) 7 C & P 446 [Cited as: R v Harris] [§ 145] Whitely v Chappell (1968) LR 4 QB [Cited as: Whitely v Chappel] [§ 145]

Stellar Shipping Co LLC v Hudson Shipping Lines

[2010] EWHC 2985 (Comm) (18 November 2010).

Available at: http://uk.practicallaw.com/D-012-2036?source=relatedcontent

Cited as: Stellar Shipping Co LLC v Hudson Shipping Lines

[§19]

United States

American Bureau of Shipping v. TencaraShipyard S.P.A.

170 F.3d 349 (2d Cir. 1999)

Cited as: AmericanBureauofShipping v. TencaraShipyard S.P.A.

[§54]

Grigson v. Creative Artists Agency L.L.C.

2000, U.S. Court of Appeals for the Fifth Circuit

210 F.3d 524

Cited as: Grigson v. Creative Artists Agency L.L.C.

Page 15: Respondent Memorandum Vis 22

xv

[§53]

In re Kellogg Brown & Root Inc.,

U.S. Court of Appeals for the Fifth Circuit

166 S.W. 3d at 739.

Cited as: In re Kellogg Brown & Root Inc.

[§54]

J.J. Ryan & Sons v. Rhone Poulenc Textile

United States Court of Appeals for the Second Circuit

863 F.2d 315 (4th Cir. 1988) at 320–21

Cited as: J.J. Ryan & Sons

[§42]

Tepper Realty Company v. Mosaic Tile Company

September 20, 1966, U.S. District Court for the Southern District of New York.

Available at: http://law.justia.com/cases/federal/district-courts/FSupp/259/688/2293417/

Cited as: Tepper Realty Company v. Mosaic Tile Company

[§55]

Re Oil Spill By The Amoco Cadiz Off The Coast of France

On March 16, 1978

United States Court of Appeals for the Second Circuit

MDL Docket No. 376 ND Ill. 1984

American Maritime Cases, 2123-2199.

Cited as: Amoco Cadiz case

[§37]

Thomson-CSF, SA v. American Arbitration Association

Aug. 24, 1995, United States Court of Appeals Second Circuit

64 F.3d 773

Cited as: Thomson-CSF, SA v. American Arbitration Association

Page 16: Respondent Memorandum Vis 22

xvi

[§51]

William Passalacqua Builders, Inc. v. Resnick. Developers South, Inc.

USA, United States Court of Appeals for the Second Circuit933 F.2d 131 (2d Cir.1991)

Available at:

https://apps.americanbar.org/litigation/litigationnews/top_stories/docs/Passalacqua-second-

circuit.pdf

Cited as: Wm. Passalacqua Builders v Resnick Developers

[§31]

YCA 1993

The Federal Court of the Southern District of New York

USA, YCA 1993, pg. 499, US 129

Cited as: YCA 1993, pg. 499, US 129

[§31]

ARBITRAL AWARDS

Arbitration institute of the Stockholm Chamber of Commerce

Award No. 108/1997 (2000)

Stockholm Internation Arbitration Rewiew, 2001 (1)

Cited as: SCC No. 108/1997

[§55]

China International Economic and Trade Arbitration Commission

Hot-dipped galvanized steel coils case

China 16 December 1997 CIETAC Arbitration proceeding

Available at: http://cisgw3.law.pace.edu/cases/971216c1.html

Cited as: CHINA International Economic and Trade Arbitration Commission, People's Republic of China,

16 December 1997

[§96]

Foreign Trade Court of Arbitration attached to the Yugoslav Chamber of Commerce

Aluminum caseSerbia, 9 December 2002

Available at: http://cisgw3.law.pace.edu/cases/021209sb.html]

Page 17: Respondent Memorandum Vis 22

xvii

Cited as: Aluminum case

[§111]

International Chamber of Commerce

Dow Chemical France et al v. ISOVER Saint Gobain

ICC No. 4131 (1984)

Cited as: ICC Award No. 4131

[§27, §34, §42]

Case No. 11160

Final award (2002) in ICC International Court of Arbitration Bulletin Vol. 16 No 2 (2005): 99

Cited as: ICC Bulletin Award No. 11160

[§30]

ICC Case No. 5103

Journal du Droit International (1988)

Cited as: ICC Case No. 5103

[§40]

ICC cases No. 5721

117 Journal du Droit International 1020 (1990)

Cited as: ICC Case No. 5721

[§46]

ICC Case No. 5730

117 Journal du Droit International (Clunet) 1029 (1990)

Cited as: ICC Case No. 5730

[§46]

ICC Case No. 9762

Cited as: ICC Case No. 9762

[§40]

Page 18: Respondent Memorandum Vis 22

xviii

OTHER SOURCES

Black’s Law Dictionary Online

Available at:http://thelawdictionary.org/

(Cited as: Black’s Law Dictionary)

[§12]

Business hours law and Legal definition

http://definitions.uslegal.com/b/business-hours/

Cited as: Business hours law

[§114]

For Law Dictionary by John Bouvier:

Trading (commerce). (n.d.) A Law Dictionary, Adapted to the Constitution and Laws of the United States.

By John Bouvier.. (1856). Retrieved January 15 2015 from

Available at: http://legal-dictionary.thefreedictionary.com/Trading+(commerce)

Cited as: A Law Dictionary, Adapted to the Constitution and Laws of the United States. By John Bouvier

[§89]

Page 19: Respondent Memorandum Vis 22

STATEMENT OF FACTS

CLAIMANT - Vulcan Coltan Ltd. (“Vulcan”) is a broker of rare minerals, in particular coltan,

based in Equatoriana. It is a 100% subsidiary of Global Minerals Ltd (“Global Minerals”), which

brokers rare minerals world-wide and is based in Ruritania.

RESPONDENT- Mediterraneo Mining SOE, is a state-owned enterprise based in

Mediterraneo. It operates all the mines in Mediterraneo including the only coltan mine. In

addition to coltan RESPONDENT extracts copper and gold.

THIRD PARTY- Global Minerals Ltd, brokers rare minerals world-wide and is based in

Ruritania. Global Minerals Ltd has 100% subsidiary company Vulcan Coltan Ltd.

23 March 2014- Mr. Storm, the Chief Operating Officer of Global Minerals, and Mr. Summer,

the Chief Operating Officer of CLAIMANT, approached Mr. Winter, the general sales manager

of RESPONDENT, to enquire about a delivery of 100 metric tons of coltan to CLAIMANT.

27 March 2014 - Mr Storm and Mr Summer who were at the time both in the offices of

CLAIMANT signed the contract and faxed it on 27 March 2014, 15:35 RST to Mr Winter.

28 March 2014- Mediterraneo Mining SOE signed the contract for the delivery of 30 metric tons

of coltan. For the price US dollars 45 per kilogram.

25 June 2014 –RESPONDENT informed CLAIMANT and Global Minerals about free 150

metric tons of coltan.

25 June 2014 - RESPONDENT send a Notice of Transport to CLAIMANT by email.

27 June 2014 at 15:00 RST CLAIMANT and Global Minerals sent a fax to RESPONDENT

asking for the delivery of 100 metric tons, as per the earlier negotiations.

4 July 2014 - Trade Bank faxed a Letter of Credit for 4.500.000 US dollars to RESPONDENT.

7 July 2014 - RESPONDENT sent a letter to CLAIMANT, according to which

RESPONDENT said about avoidance of the contract. The reasons for avoidance were the

following: the Letter of Credit dated 4 July 2014 relates to 100 metric tons of coltan instead of 30

metric tons; the Letter of Credit dated 4 July contains different delivery terms.

8 July 2014 - Trade Bank sent the second Letter of Credit dated 8 July 2014 to RESPONDENT

by courier at 9.00 am RST.

8 July 2014 - The Global Minerals send a copy of the Letter of Credit dated 8 July 2014 issued by

Trade Bank Ltd over US dollars 1,350,000 at 17.42 RST by fax.

8 July 2014 - RESPONDENT received a fax from Global Minerals at 22.42 MST on 8 July 2014.

9 July 2014 – The Letter of Credit was delivered to RESPONDENT at 0.05 MST.

9 July 2014 - RESPONDENT read the fax Letter of Credit in the morning.

Page 20: Respondent Memorandum Vis 22

2

9 July 2014 - RESPONDENT sent a second letter of avoidance by email and courier. The

reasons for avoidance were the following: the action of the second Letter of Credit has expired

on July 8 2014; the new Letter of Credit now requires as an additional document a commercial

invoice.

11 July 2014 – The Secretariat acknowledges the receipt of CLAIMANT`s Application for

Emergency Measures (“Application”), CLAIMANT`s Request for Arbitration (“Request”).

12 July 2014 - The President of the International Court of Arbitration of the International

Chamber of Commerce appointed Ms. Chin Hu as Emergency Arbitrator.

26 July 2014 - Ms. Chin Hu issued the order of the Emergency Arbitrator and sent it by e-mail to

CLAIMANT and RESPONDENT.

8 August 2014 - RESPONDENT sent Answer to Request for Arbitration Counterclaims and

Request for Joinder by Courier.

8 August 2014 - The Secretariat acknowledges receipt of 6 copies of RESPONDENT`s: Answer

to Request for Arbitration, Counterclaims and Request for Joinder and notifies Global Minerals

Ltd. about the Request for Joinder.

8 September 2014 - Reply to the Counterclaim, Answer to Request for Joinder was sent to The

Secretariat of the International Court of Arbitration, International Chamber of Commerce from

Horace Fasttrack, advocate of Vulcan Coltan Ltd and Global Minerals Ltd.

18 September 2014 - The International Court of Arbitration decided that this arbitration will

proceed with respect to the Additional Party; confirmed Dr Arbitrator One as co-arbitrator upon

CLAIMANT`s and the ADDITIONAL PARTY`s joint Nomination; confirmed Ms Dos as co-

arbitrator upon RESPONDENT`s nomination; appointed Mr Henry Haddock as president of

the arbitral tribunal upon the Danubian National Committee's proposal; fixed the advance on

costs at US$ 240 000, subject to later readjustments.

22 October 2014 - The Arbitral Tribunal and the Parties discussed, agreed, and signed the Terms

of Reference and drafted a list of questions that must be considered at the hearing.

3 October 2014 - Letter from the President of the Tribunal Mr. Henry Haddock was sent to

Horace Fasttrack and Joseph Langweiler enclosed Procedural Order No 1.

29 October 2014- Following the Procedural Order No 1 dated 3 October 2014, the Arbitral

Tribunal issued Procedural Order No 2, clarifications and corrections.

Page 21: Respondent Memorandum Vis 22

3

SUMMARY OF ARGUMENTS

1. RESPONDENT respectfully asks the arbitral tribunal to declare that it has jurisdiction over

Global Minerals (PROCEDURAL ISSUE I). Respondent position is that Global Minerals is a

party to the contract and arbitration agreement contained therein. Moreover, even if the arbitral

tribunal decides that the Global Minerals is not a party to the contract, RESPONDENT asserts

that the Guarantee provisions justify the extension of arbitration agreement over Global

Minerals. Also, RESPONDENT states that the arbitration agreement can be extended over

Global Minerals under the Group of Companies Doctrine. And finally, RESPONDENT submits

that Good Faith Considerations justify the extension of arbitration agreement over Global

Minerals.

2. RESPONDENT’s position is that CLAIMANT is not entitled to receive 30 metric tons of coltan

under the contract (ISSUES ON MERITS). RESPONDENT declares that its avoidance of the

Contract on 7 July is legitimate and CLAIMANT is not entitled to receive 30 metric tons of

coltan under the contract. Namely, CLAIMANT has not fulfilled its obligation to establish

proper L/C in compliance with the terms of the Contract, which constitute the fundamental

breach, and allowed for RESPONDENT to avoid the contract. Moreover, as RESPONDENT

insists CLAIMANT did not provide an adequate assurance of its performance, which allowed to

avoid the contract too before the date for performance of the Contract. And then

RESPONDENT rightfully avoided the contract on 9 July 2014. Namely, the late delivery of L/C

2 and the insertion of an additional document to the L/C 2 (commercial invoice), which

RESPONDENT should present to the bank in order to obtain payment, substantially deprive

RESPONDENT of what it expected under the contract. Both of these deviations constitute a

fundamental breach of the contract, which lead to a legitimate avoidance of the Contract by

RESPONDENT in both cases.

3. RESPONDENT asserts that the order of the Emergency Arbitrator should not be lifted by the

arbitral tribunal (PROCEDURAL ISSUE II). RESPONDENT submits that under Art. 29 (6)b

of ICC Rules 2012 the parties did opt out the Emergency Arbitrator provisions. Moreover,

RESPONDENT states that the substantive requirements for granting interim measures are not

fulfilled.

Page 22: Respondent Memorandum Vis 22

4

PROCEDURAL ISSUE I

I. THE ARBITRAL TRIBUNAL HAS JURISDICTION OVER GLOBAL MINERALS

4. Contrary to CLAIMANT`s submission [M for Cl., para 27] RESPONDENT respectfully asks the

arbitral tribunal to declare that it has jurisdiction over Global Minerals. Firstly, RESPONDENT

asserts that Global Minerals is a party to the contract and arbitration agreement contained therein

(1). Secondly, RESPONDENT states that the Guarantee provisions justify the extension of

arbitration agreement over Global Minerals (2). Thirdly, RESPONDENT declares that the

arbitration agreement can be extended over Global Minerals under the Group of Companies

Doctrine (3). And finally, RESPONDENT submits that the Good Faith Considerations justify

the extension of arbitration agreement over Global Minerals (4).

1. Global Minerals is a party to the contract and the arbitration agreement contains therein

5. Contrary to CLAIMANT`S statement [M for Cl., paras 29-31] RESPONDENT asserts that

Global Minerals concluded the Coltan Purchase Contract by signing it and performing its

obligation under the contract. Moreover, RESPONDENT respectfully asks the arbitral tribunal

to declare that Global Minerals is a party to arbitration agreement contained in Coltan Purchase

Contract between CLAIMANT and RESPONDENT.

6. It is obvious for RESPONDENT, that Coltan Purchase Contract had originally been concluded

with Global Minerals and then, at the request of Global Minerals “formally” been transferred to

CLAIMANT [Answer toReq. for Arb, Ex. R 1, para 4].

7. Moreover, Global Minerals performed the buyer`s obligations for Coltan Purchase Contract

under provisions of CISG. Under Art. 54 of the CISG “buyer's obligation to pay the price includes taking

such steps and complying with such formalities as may be required under the contract or any laws and regulations

to enable payment to be made”. The position of RESPONDENT is that Global Minerals’ actions on

providing payment securities should be viewed as a performance of the buyer obligations.

8. Under Art. 4 of the Coltan Purchase Contract the Letter of Credit in the amount of US$

1,350,000 shall be established by the Buyer not later than fourteen days after the Buyer received

the Notice of Transport in regard to shipment [Req. for Arb, Ex. C 1, p.7].

9. At the same time, parties agreed that Global Minerals’ bank will issue the Letter of Credit to

secure the deal, and that Global Minerals signed the contract to “endorsed” it [PO 2, para 12; PO

2, para 17].

10. RESPONDENT asserts that while performing the obligations under the Coltan Purchase

Contract Global Minerals became a party to arbitration agreement. This position is supported by

Page 23: Respondent Memorandum Vis 22

5

the case law, Cour de cassation stated “…[t]he effect of international arbitration clauses extends to the

parties directly involved in the performance of the contract and any disputes that may arise in connection

therewith…” [Société Alcatel Business Systems (ABS), Société Alcatel Micro Electronics (AME) et Société

AGF v. Amkor Technology Case]. As it already mentioned, Global Minerals performed the

obligation under the Contract, and it mean that it becomes a party to arbitration agreement

contained therein.

11. Contrary to the CLAIMANT’S argument [M for Cl., para 32] RESPONDENT states that the fact

that Global Minerals endorsed the contract means that it becomes a party to the Coltan Purchase

Contract.

12. Black’s Law Dictionary defines “endorsement” as “…the signing of a legal document in a legal

capacity…” [Black’s Law Dictionary]. Thus, RESPONDENT declares that Global Minerals signed

the Coltan Purchase Contract by endorsing it.

13. Hence, Global Minerals endorsed the Coltan Purchase Contract to confirm its involvement in

the terms of Coltan Purchase Contract including arbitration clause, and in the present

circumstances Global Minerals is bound by arbitration agreement.

2. The Guarantee provisions justify the extension of arbitration agreement over Global

Minerals

14. Whether the arbitral tribunal decides that Global Minerals is not a party to the contract between

CLAIMANT and RESPONDENT, RESPONDENT declares that contrary to CLAIMANT`S

submission [M for Cl., para 33] Global Minerals is under scope of application of the arbitration

agreement due to its guarantee obligations.

15. RESPONDENT submits that Global Minerals may be bound by the arbitration agreement

contained in a contract which it did not sign. The extension of the arbitration agreement over the

third parties is widely used in case law [Société Korsnas Marma v. Société Durand A Auzias; Société Ofer

Brothers v. The Tokyo Marine and Fire Insurance Co Ltd].

16. RESPONDENT declares that Global Minerals has guarantee obligations in regard to the Coltan

Purchase Contract.

17. In regard to the case mentioned by CLAIMANT [M for Cl., paras 34-35] RESPONDENT

declares that it is not applicable to the present dispute. There should be exceptions when “…the

guarantor has expressed, explicitly or by its conduct, the intention to be bound by the arbitration

clause in the main contract…” [Thomas Müller]. RESPONDENT’s position is that the conduct of

Global Minerals confirms the readiness to be bound by arbitration agreement and such conduct

is observed in subsequent submissions [paras 21-25 infra].

Page 24: Respondent Memorandum Vis 22

6

18. Because of previous experience with the subsidiaries of Global Minerals, RESPONDENT

insisted that Global Minerals should provide sufficient security for the payment obligations

[Answer to Req. for Arb, para 5]. Moreover, RESPONDENT from the very beginning insisted that

Global Minerals should guarantee the fulfillment of such payment obligations and endorsed the

contract to confirm such security provisions [Answer to Req. for Arb, para 7; Answer to Request for

joinder, para 6].

19. In Stellar Shipping Co LLC v Hudson Shipping Lines, the Commercial Court proclaim, that it has

jurisdiction over the Guarantor to the contract between its subsidiary and another party. Given

the close connection between the contract and the guarantee, and between the parties involved,

one would expect them, as rational businessmen, to agree a common method of dispute

resolution. [Stellar Shipping Co LLC v Hudson Shipping Lines].

20. In conclusion RESPONDENT states that the Guarantee provisions justify the extension of

arbitration agreement over Global Minerals.

3. The arbitration agreement can be extended over Global Minerals under the Group of

Companies Doctrine

21. Contrary to CLAIMANT`s assertion [M for Cl, para38] RESPONDENT submits that Global

Minerals Ltd. is a proper party to the contract and must be bound to arbitrate under the Group

of Companies doctrine.

22. According to the definition given by Wilske under the Group of Companies Doctrine, the

arbitration agreement can be extended to “the parent or other affiliate company” of the signatory

of arbitration agreement “provided that such non-signatory was somehow involved in the

conclusion, performance or termination of the contract in dispute” [Wilske, Stephan, Shore,

Laurence Ahrens, Jan-Michael].

23. In the present case Global Minerals is a party of arbitration agreement because of its signature

under the contract containing the arbitration clause and its participation in the negotiation and

fulfillment of the contract [paras 5-13 supra].

24. It is important to consider that the UNCITRAL Working Group on Arbitration sustained that

the group of companies fact pattern might not require a written arbitration agreement, noting

that this theory had been applied repeatedly by arbitral tribunals and even had been approved by

some courts. [Kryvoi Yaraslau].

25. The arbitral tribunal must find that the arbitration agreement can be extended over Global

Minerals under the Group of Companies Doctrine because the Group of Companies Doctrine is

Page 25: Respondent Memorandum Vis 22

7

used in international arbitration to justify the extension of arbitration agreement. (3.a.) and the

requirements under the Group of Companies Doctrine are fulfilled (3.b.).

3.a. The Group of Companies Doctrine is used in international arbitration to justify the

extension of arbitration agreement

26. It is RESPONDENT’S submission that, contrary to CLAIMANT’S allegations [M for Cl., para

41] the Group of Companies Doctrine have a solid foundation and is supported by case law. The

doctrine has been widely accepted amongst arbitrators.

27. The application of the Group of Companies Doctrine is most precisely described in Dow

Chemical case, where the arbitral tribunal held that “the arbitration clause expressly accepted by

certain companies of the group should bind the other companies which, by virtue of their role in

the conclusion, performance, or termination of the contracts containing said clauses, and in

accordance with the mutual intention of all parties to the proceedings, appear to have been

parties to these contract so to have been principally concerned by the disputes to which they

may give rise” [ICC Award No. 4131].

28. It is clear that the civil law jurisdictions undoubtedly been the most favorable to the ‘Group of

Companies’ Doctrine. The French Court of Appeals of Pau even went as far as declaring the

doctrine as a legal rule, where it was stated that “a group of companies indeed possesses,

notwithstanding the separate legal personality pertaining to each of them, a unique economic

reality, which the courts have to take into consideration, when extending the arbitration

agreement over third parties within a group” [Sponsor A.B. v. Lestrade].

29. The doctrine was upheld by the French courts, for example in kis France S.A. the Court of

Appeal of Paris considered that the arbitrators fairly decided that there was a common intention

of all the parties within a group of companies to consider the parent company liable for the debts

of its subsidiaries which therefore allow to extend the arbitration clause over them [Kis France SA

v. SA Societe Generale].

30. Following this line, the ICC arbitral tribunal in Venezuela held that the participation of second

respondent in the preparation and execution of the contract in dispute may determine the

intention of the parties and can be inferred as an extension of the contract and arbitration clause

to the second respondent [ICC Bulletin Award No. 11160].

31. As for common law system, the Win Line case establishes that Singapore is prepared to accept

the Group of Companies Doctrine as valid law within the jurisdiction [The Singaporean High Court,

Win Line (UK) Ltd v Masterpart (Singapore)]. U.S. courts inclined to recognize the extension of an

arbitration agreement to non-signatories. The Federal Court of the Southern District of New

York accepted a group of companies plea, in which it held that “since it had itself invoked the

Page 26: Respondent Memorandum Vis 22

8

arbitration provided for in a chater party of which it was not a signatory, but which it negotiated,

the parent company could not deny being bound by the arbitration clause contained in this

document [YCA 1993, pg. 499, US 129].Also, New York courts have found non-signatories

bound by an agreement to arbitrate where the signatories are their alter egos. [Wm. Passalacqua

Builders v Resnick Developers].

32. Considering Danubian law as lex arbitri contrary to para 49 M for Cl. the arbitral tribunal cannot

exclude the possibility of using the Group of Companies Doctrine only because there have been

no decisions by the Danubian courts on the doctrine so far [PO 2, para 46] as all the

preconditions for application of the Group of Companies Doctrine are met in the present case

[paras 34-48 infra].

33. Hence, The Group of Companies Doctrine has been used for quite some time and in a

considerable amount of awards by arbitral tribunals to justify the extension of an arbitration

agreement to third non-signatory parties.

3.b. The requirements under the Group of Companies Doctrine are fulfilled

34. The Group of Companies Doctrine is a legal theory that enables to enjoin non-signatory parties

to arbitration. It arose out of the Dow Chemical ICC award, where the tribunal held that,

notwithstanding the distinct legal entities of its members, a group of companies constitutes one

and the same economic reality. Moreover, through their involvement in the conclusion,

performance, or termination of the contract, all the parties had consented to the non-signatories’

participation in the arbitration agreement included in the underlying contract [ICC Award No.

4131].

35. Contrary to CLAIMANT assertion [M for Cl., para 51] the RESPONDENT submits that the

arbitral tribunal must find that the requirements under the Group of Companies Doctrine are

fulfilled because Global Minerals controls CLAIMANT (3.b.i.), The Global Minerals and

CLAIMANT`S involvement into the Contract constitutes one economic reality (3.b.ii.) and

Global Minerals is bound by the arbitration agreement (3.b.iii.).

3.b.i. Global Minerals controls CLAIMANT

36. CLAIMANT’S arguments do not prove the absence of control of Global Minerals over

CLAIMANT. Contrary to CLAIMANT's assertion in para 55 M for Cl., first, Global Minerals

«participates in CLAIMANT’S day-to-day operation»: it established a Letter of Credit [Req. for

Arb, Ex. C 5, p.11]. Second, while owning more than 50 percent of the voting stock of another

company ensures control, in our case CLAIMANT is 100 % subsidiary company and has not its

own financial system. The Global Minerals is a parent company and it was clear that all financial

Page 27: Respondent Memorandum Vis 22

9

operations will be created for the account of Global Minerals [Req. for Arb, Ex. C 5, p.11, Ex. C 8,

p.14]. Also, RESPONDENT send most of its correspondence concerning the contract to both

parties and also on the “buyer’s side” correspondence was regularly conducted not only by

representatives from Vulcan Coltan but by Mr Storm, too [Req. for Arb, Ex. C 4, Ex. C 6]. The

Global Minerals Ltd. acts as a guarantor of fulfillment of obligations under the contract, it was

important for it to take part in negotiations and to control CLAIMANT.

37. In 1978, in the Amoco Cadiz case the Court found that Amoco Transport was merely a nominal

owner of the Amoco Cadiz and that Standard Oil controlled the design, construction, operation

and management of the tanker and treated it as if it belonged to Standard Oil [The Amoco Cadiz].

The Court found Standard Oil liable in tort for its negligent supervision of its subsidiaries.

Additionally, the Court saw little rationale for treating Standard Oil differently from its

subsidiaries, which were treated as mere “instrumentalities”. The negligence of the subsidiaries

was therefore assigned directly to the parent. That what should be done to Global Minerals in the

present dispute.

38. Moreover, contrary to para 56 of the M for Cl., RESPONDENT submits that both Mr. .Summer

and Mr. Storm signed the contract and faxed it on 27 March 2014, 15:35 RST to Mr. Winter who

signed it the next day upon arrival in the office [PO 2, para 11, p.64].

39. Hence, RESPONDENT submits that the arbitral tribunal should regard that Global Minerals has

excessive control over CLAIMANT.

3.b.ii. Global Minerals and CLAIMANT involvement into the Contract constitutes one

economic reality

40. The “one economic reality” theory is applicable to the issue of contractual liability. In ICC Case

5103 the tribunal reasoned that “[t]he security of international commercial relations requires that

account must be taken of these economic realities and that all the companies of the corporate

group must be held jointly and severally liable [where] they have directly or indirectly benefited”

from the contract [ICC Case No. 5103]. In a more recent case, the arbitral tribunal relied in part

on the Group of Companies Doctrine to find that a State entity, which was one of the

respondents in the case, could be held liable for the acts of a second respondent in the case, who

represented a sub-division (i.e. the Ministry of Agriculture) of that State entity [ICC Case No.

9762]. Furthermore, scholars writing on the Group of Companies Doctrine have noted that,

“related companies which share a common interest with regard to a specific contract are

presumed to have a common will” by virtue of which the contract is extended to the non-

signatory company [DERAINS & GOODMAN-EVERARD].

Page 28: Respondent Memorandum Vis 22

10

41. Global Minerals and CLAIMANT are related members in a group of companies and their

participation in relation to the contract of sale and arbitration agreement is effectively

inseparable.

42. RESPONDENT submits that contrary to CLAIMANT’s contentions [M for Cl., para 61] despite

the some independence of its individual entities, a group of companies constitutes one and the

same economic reality where the circumstances of a contract’s conclusion, performance, and

termination, and the degree of influence amongst members of the group warrants such an

inference [ICC Award No. 4131]. When the claims against the companies are based on the same

facts and are inherently inseparable, a party which has not signed the arbitration agreement

should be considered bound by the agreement, or else the arbitration proceedings would be

rendered meaningless [J.J. Ryan & Sons].

43. In the present case, the involvement of Global Minerals Ltd. in the relationship with

CLAIMANT constitutes “one and the same economic reality” because Global Minerals Ltd. is

not only 100 % parent company of CLAIMANT, but Vulcan Coltan is entirely dependent upon

Global Minerals [paras 36-39 supra]. The parties manifested their intent that Global Minerals be a

party to the contract of sale and arbitration agreement by involving Global Minerals in the

performance of the contract [para 36 supra]. Moreover, the Letter of Credit was provided by

Global Minerals [Req. for Arb, Ex. C 5, p. 11] and CLAIMANT in its correspondence in regard to

the performance of Coltan Purchase Contract never made CLAIMANT separate from Global

Minerals [Req. for Arb, Ex. C 4, p. 10; Ex. C 6, p. 12].

44. Based on the foregoing, the RESPONDENT requests to declare the arbitral tribunal that Global

Minerals and CLAIMANT involvement into the contract constitutes one economic reality.

3.b.iii. Global Minerals is bound by the arbitration agreement

45. RESPONDENT disagrees with CLAIMANT’s statement that Global Minerals never sought

to be a party to the arbitration agreement [M for Cl., para 66] and considers that Global Minerals

is a party to the arbitration clause because of its signature under the contract containing the

clause and its role in the negotiation and fulfillment of the contract [paras 5-13 supra].

46. In ICC cases No. 5721 and 5730 the arbitral tribunal concluded that the arbitration clause that

had been signed by the subsidiary company also was applicable to the parent company [ICC Case

No. 5721; ICC Case No. 5730].

47. Refuting CLAIMANT’s assertion in para 46 M For Cl. RESPONDENT submits that the

arbitral tribunal should consider the application of the Group of Companies Doctrine because

Global Minerals Ltd. is a party to the contract and arbitration agreement.

48. In conclusion, the basic preconditions of the application of the Group of Companies Doctrine,

Page 29: Respondent Memorandum Vis 22

11

has been established. Accordingly, the Group of Companies Doctrine is applicable to justify the

extension of arbitration agreement over Global Minerals in the present case.

4. Good Faith Considerations justify the extension of arbitration agreement over Global

Minerals

49. Contrary to CLAIMANT assertion [M for Cl., para 75] RESPONDENT states that good faith

consideration has all grounds to draw Global Minerals to the arbitration proceedings.

50. The doctrine of estoppel in broad terms prevents one party from taking advantage of another

when the former by his actions has let the latter to act in the certain manner detrimental to the

latter’s own interests. The principle of good faith is at the root of this doctrine [Chittharanjan F.

Amerasinghe].

51. Courts have recognized estoppel as a basis for permitting a non-signatory to invoke an arbitration

agreement: where a party claims rights as a party under a contract, which contains an arbitration

clause, it may be estopped from denying that it is a party to the arbitration provision [Thomson-

CSF, SA v. American Arbitration Association] (courts are “willing to estop a signatory from avoiding

arbitration with a non signatory when the issues the nonsignatory is seeking to resolve in

arbitration are intertwined with the agreement that the estopped party has signed”).

52. The estoppel wording or approach is used in arbitral awards rendered in Europe, based on the

theory of good faith or the theory of apparent mandate or ostensible authority.

53. The doctrine of estoppel provides two grounds for compelling non-signatories of an arbitration

agreement to arbitrate. The first ground stipulates that a non-signatory is estopped from refusing

to comply with an arbitration clause when it receives a direct benefit from a contract containing

an arbitration clause [Hanotiau]. The second ground states that the application of equitable

estoppel is warranted when the signatory to the contract containing an arbitration clause raises

allegations of substantially interdependent and concerted misconduct by both the non-signatory

and one or more of the signatories to the contract [Grigson v. Creative Artists Agency L.L.C.].

54. Global Minerals became bound and liable by virtue of its conduct during the performance of the

Contract. First, Global Minerals should be estopped from denying it is a party to the arbitration

agreement, as it received a direct benefit from the Contract [Answer to Req. for Arb, Ex. R 1, para

3, p. 40; Answer to Req. for Arb, para 17, p.36; Answer to Req. for Arb, Ex. R 3, p. 43]. Under direct

benefits estoppel, a nonsignatory plaintiff seeking the benefits of a contract is estopped from

simultaneously attempting to avoid the contract's burdens, such as the obligation to arbitrate

disputes [In re Kellogg Brown & Root Inc.].US courts adopted a theory of equitable estoppel and held

Page 30: Respondent Memorandum Vis 22

12

that a party that receives a direct benefit under a contract is estopped from denying that it is party

to the contract`s arbitration clause [American Bureau of Shipping v. Tencara Shipyard S.P.A].

55. Second, given Global Minerals’s conduct and the facts of the case the arbitral tribunal should

find that Global Minerals assumed the contractual obligations of the Coltan Purchase Contract

and therefore should be held liable. Global Minerals by its behaviour and in particular the

endorsement of the contract created the impression that it would “stand behind the contract,

inducing RESPONDENT to sign it” [Answer to Req. for Arb, para. 28, p. 37-38]. It is therefore

reasonable that both CLAIMANT and Global Minerals be held liable for the failure to comply

with the terms of the Coltan Purchase Contract and bound by the arbitration agreement

contained therein, as illustrated by a recent arbitration case in Sweden. A tribunal proceeding

under the SCC Rules found that a non-signatory party, by virtue of its conduct, could be bound

to a contract, including its arbitral clause, and be held liable for breach of that contract [SCC No.

108/1997]. The Swiss Supreme Court recently confirmed an award rendered against a sole

shareholder for damages due by a company and reasoned that despite not being a signatory to the

contract at issue, the shareholder had played an important role in the execution of the contract,

he was aware of the terms of the agreement, and consequently it would be contrary to the

principle of good faith not to consider him a party to the agreement [ATF 129 III 727].Hence,

where a non-signatory claims or exercises rights as a party under a contract, which contains an

arbitration clause, the non-signatory will typically be estopped from denying that it is a party to

the arbitration clause. As one U.S. court put it: “in short, [plaitiff] cannot have it both ways. it

cannot rely on the contract when it works to its advantage and ignore it when it works to its

disadvantage” [Tepper Realty Company v. Mosaic Tile Company].

56. On the conclusion, all preconditions of the good faith doctrine are met. RESPONDENT asserts

that the arbitral tribunal must find that the good faith considerations justify the extension of

arbitration agreement over Global Minerals.

57. Based on the above RESPONDENT states that the arbitral tribunal has jurisdiction over Global

Minerals.

ISSUES ON MERITS

II: CLAIMANT IS NOT ENTITLED TO RECEIVE 30 METRIC TONS OF COLTAN

UNDER THE CONTRACT

58. In regard to issues on merits, RESPONDENT submits that CLAIMANT is not entitled to

receive 30 metric tons of coltan under the contract. RESPONDENT asserts that it rightfully

Page 31: Respondent Memorandum Vis 22

13

avoided the Contract both on 7 July 2014 and 9 July 2014. RESPONDENT rightfully avoided

the Contract on 7 July 2014 due to the fact that CLAIMANT has not fulfilled its obligation to

establish proper Letter of Credit (hereinafter – L/C) in compliance with the terms of the contract

and this failure constitutes a fundamental breach. Thus, RESPONDENT rightfully avoided the

contract.

59. RESPONDENT respectfully asks the arbitral tribunal to hold that RESPONDENT rightfully

avoided the contract on 9 July 2014. The late delivery of L/C 2 substantially deprives

RESPONDENT of what it expected under the contract. The same may apply to the insertion of

an additional document to the L/C 2 (commercial invoice), which RESPONDENT should

present to the bank in order to obtain payment. Both of these deviations constitute a

fundamental breach of the contract, and lead to a legitimate avoidance of the contract by

RESPONDENT.

60. Art. 53 of CISG stipulates that buyer’s obligations are to pay the price for the goods and take the

delivery of goods. Moreover, under Art. 54 of CISG, buyer's obligation to pay the price includes

taking such steps and complying with such formalities as may be required under the contract or

any laws and regulations to enable payment to be made. CLAIMANT failed its obligations under

the contract and CISG, by failing to establish a proper L/C that had to be in a compliance with

the terms of the contract.

61. Under Art. 64(1)(а) CISG, seller may declare the contract avoided if buyer fails to perform, and

this failure amounts a fundamental breach.

62. RESPONDENT agrees with the position of CLAIMANT in paras 88-89M for Cl. in part of

contractual obligations between the parties, namely about amount of coltan which was

established in Art. 4 of Contract [Req. for Arb, Ex C 1, p. 7]. But, notwithstanding to that,

RESPONDENT does not agree with the position of CLAIMANT on the rightfulness of the

avoidance of the contract as:

1) CLAIMANT has not fulfilled its obligations to establish proper L/C, as L/C 1 were established

with several deviations as different sum of money, different quantity of Coltan and different

delivery terms [Req. for Arb, Ex. C. 5, p. 11];

2) CLAIMANT failed to notify RESPONDENT about the establishment of L/C 2 during the term,

stipulated in the contract [Req. for Arb, Ex. C. 1, Art. 4, p. 7];

3) CLAIMANT unilaterally changed the provisions of L/C 2, in particular, added an additional

document - commercial invoice [Req. for Arb, Ex. C. 8, p. 14]. Unilateral insertion of additional

document to the text of L/C 2 should be considered as a fundamental breach of contractual

Page 32: Respondent Memorandum Vis 22

14

relationships among the market of trade commodities and breach of principle of mutual assent.

These breaches lead to the right to avoid the contract.

A. RESPONDENT’s avoidance of the contract on 7 july 2014 is legitimate

63. CLAIMANT in para 90 stated that RESPONDENT’s avoidance of contract on 7 July 2014 is

invalid [M for Cl., para 90]. Contrary to the CLAIMANT’s position RESPONDENT calls the

arbitral tribunal to recognize the avoidance of the Contract on 7 July valid, as CLAIMANT has

not fulfilled its obligation under the contract and under Art. 54 CISG (1), the establishment of

inappropriate L/C 1 by CLAIMANT constitutes a fundamental breach of contract in the sense

of Art. 25 CISG (2). Moreover all requirements under Art. 72 CISG for avoidance were fulfilled

by RESPONDENT, namely the offering of the reasonable period for providing adequate

assurance of CLAIMANT’s performance (3).

1. CLAIMANT has not fulfilled its obligation under the Contract and under Art. 54 CISG

64. CLAIMANT in para 91 asserts that the L/C was established in conformity with the contract and

in line with its obligation under the CISG [M for CL. para 91]. RESPONDENT alleges that

CLAIMANT had no right to change the terms of Letter of Credit of 4th July 2014 (hereinafter –

L/C 1), because such changes inconsistent with Art. 54 CISG.

65. The market of coltan is characterized by high volatility and instability, supply and demand are

highly volatile [Req for Arb, para 4, p. 3], and therefore the principle of strict compliance must

be observed by parties for normal work of this market and for regulation of risk, connected with

instability. In the commodities market strict standards are of particular importance [Katrina

Winsor, para 4.3.2].

66. RESPONDENT submits that CLAIMANT violates the principle of strict compliance, which is

required within the highly volatile market. As Prof. Dr.Ulrich G. Schroeter writes the principle of

strict compliance requires the tendered documents (L/C) to precisely conform to the

contractual specifications [Schlechtriem, p. 432, Art. 25, para 63]. In their contract parties

established clean cut provision that a L/C in the amount of US$ 1,350,000 shall be established

[Req. for Arb, Ex. C 1, p. 7, Art. 4]. Moreover, the exact amount of coltan is agreed between the

parties in Art. 3 of the contract. CLAIMANT did disobey the provisions of contract, changing

the conditions in established L/C 1 in unilateral order and did not take into account that it was

not entitled to make unilateral changes.

67. Under Art. 29 CISG the contract between the parties may be modified by the mere agreement of

the parties. The principle of mutual assent prohibits to change provisions on a unilateral basis

[BEN-SHANAR, p. 1829], as CLAIMANT made by changing the provisions of L/C 1.

Page 33: Respondent Memorandum Vis 22

15

68. Pr. Dr. Florian Mohs notes that duty of both parties is to cooperate and inform [Schlechtriem, p.

812, Art. 54, para 4], but CLAIMANT strove to its interests to get the 100 metric tons of coltan,

as it assented during preliminary negotiations [Req for Arb, p. 3, para 6].

69. Moreover in traditional CIF contract, deviations from the prescribed standard in documentary

performance are prohibited and the ability to cure any defects in the documentation does not

extend to commodities markets [Katrina Winsor, para 4.3.2].

70. In this regard CLAIMANT broke the provisions of contract and established the L/C 1 which

contradicts to contract provisions, therefore CLAIMANT has not fulfilled its obligation under

the contract.

71. As CLAIMANT submitted in para 92-93 M for Cl., the UCP 600 is applicable for contractual

obligations as it is established in Art. 4 of the Contract [Req. for Arb, Ex. C 1, p. 7, Art. 4]. But the

Art. 14(d) of UCP 600 regulates similarity of the documents under Letter of Credit with

international standard banking [Felicity Monteiro], but not with the contract as CLAIMANT

submits in para 93 of M for Cl.

72. Art. 54 CISG fixes that Letter of Credit must be considered as preparation for payment of the

price under the contract [Digest of case law, Art. 54, para 1]. And if party violates these preparative

actions the sufferer could resort to the remedies in Art. 61 CISG, namely Art. 64 CISG of

avoidance [Digest of case law, Art. 54, para 3]. The position that Letter of Credit might be identical

with contract’s provisions for fulfilling its main obligations is supported by Supreme Court of

Queensland in Downs Investments Pty Ltd. v. Perwaja Steel SDN BHD case.The Court found that

“the failure to establish a letter of credit was a failure by the buyer to meet its "obligation to pay

the price of the goods in the meaning of Art. 54 CISG, which in fact states that the buyer's

obligation to pay the price includes taking such steps and complying with such formalities as may

be required under the contract or any laws and regulations to enable payment to be made”

[Down Investments Pty Ltd. v. Perjawa Steel SDN BHD)].

73. Summarizing all mentioned above, RESPONDENT calls the arbitral tribunal to decide that

changes in the L/C 1 made by CLAIMANT contradict to the principle of strict compliance in

commodity trade which is of essence. The deviations in L/C 1, namely the amount of money

stated in the L/C 1 (1.a.),the quantity of goods stated in the L/C 1 (1.b.),the Delivery Term

contained in the L/C 1 (1.c.)constitute the failure to perform obligations under the Contract and

break the provisions of Art. 54 CISG. Therefore inappropriate L/C 1 amounts to a fundamental

breach and gives right to RESPONDENT for contract avoidance.

Page 34: Respondent Memorandum Vis 22

16

1.a. The amount of money stated in the L/C 1 is not in conformity with the Contract

74. CLAIMANT asserts, that the amount of money stated in L/C 1 is in accordance with the

contract provisions [M for Cl., para 94]. In contrast RESPONDENT alleges that the amount of

money, stated in that L/C 1 is not in conformity with the contract for following reasons.

75. Parties entered into contractual obligations, where Art. 4 of the Contract stated that the Letter of

Credit in the amount of US$ 1,350,000 would be established by Buyer [Req. for Arb,Ex. C. 1, p. 7,

Art. 4].Under Art. 54 of CISG, the buyer's obligation to pay the price includes taking such steps

and complying with such formalities as may be required under the contract or any laws and

regulations to enable payment to be made [CISG, Art. 54]. Moreover, in a case of using of Letter

of Credit, if the beneficiary does, however, notice a significant divergence (for example, as to the

mode of availability of the credit, period of its validity, its description of the requisite documents,

the latest time for negotiation, the deliverable quantity of the merchandise, date of shipment, the

sum on the credit and the currency of account), the buyer-applicant will ordinarily be in

repudiatory breach of his obligation to open the bargained Letter of Credit [Letters of Credit: The

Law and Practice of Compliance, Part I, p. 130].

76. In present case, CLAIMANT established L/C 1 that stated larger amount of money, namely US$

4,500,000 [Req. for Arb, Ex. C. 5, p. 11]. A larger sum of money stated in L/C 1, is definitely a

breach of the contract, as buyer failed to comply with the terms of the contract and failed to take

such steps to enable payment to be made. Both of this failure leads to a fundamental breach of

the contract.

1.b. The quantity of goods stated in the L/C 1 is not in conformity with the Contract

77. Contrary to CLAIMANT’s assertion that L/C 1 where the larger quantity of coltan is stated does

not in conflict with the amount agreed between the parties in the contract [M for Cl., para 96],

RESPONDENT submits that the quantity of coltan, stated in L/C 1 breaks the contract

provisions.

78. Parties entered into the contract, where Art. 3 stipulates, that the exact quantity of coltan will be

30 metric tons [Req. for Arb, Ex. C 1, p. 3, Art. 3]. But CLAIMANT established L/C 1, which

determines that RESPONDENT, in order to obtain payment, should present a packing list,

which should state “Coltan - not less than 30 metric tons” [Req. for Arb, Ex. C 5, p. 11]. Such

provision in the L/C 1 does not allow to identify the exact quantity of coltan and breaks the

principle of strict documentary compliance which is of essence in trade commodity [supra para

77]. Moreover, in conjunction with higher amount of price stated in L/C 1 undetermined

Page 35: Respondent Memorandum Vis 22

17

quantity of coltan could lead to manipulative behaviour of CLAIMANT in the future, what is

inappropriate, especially on the market of trade commodities [Katrina Winsor, para 4.3.2].

79. As was also stated before, in practice of using of Letter of Credit as a method of payment, if the

beneficiary does, however, notice a significant divergence (for example, the deliverable quantity

of the merchandise) the buyer-applicant will ordinarily be in repudiatory breach of his obligation

to open the bargained Letter of Credit [Letters of Credit: The Law and Practice of Compliance; para 78].

80. This is RESPONDENT’s position that a significant divergence in a quantity of deliverable

merchandise, made by CLAIMANT in established L/C 1, in addition to wrong sum of credit

leads to a fundamental breach of contract.

1.с. The Delivery Term contained in the L/C 1 is not in conformity with the Contract

81. Contrary to CLAIMANT’s position in paras 100-103 M for Cl. RESPONDENT insists that

parties have never changed the Delivery Term (and RESPONDENT has never expressed the

intention to change the contract provisions), and therefore CLAIMANT was obliged to establish

the L/C 1 with CIF delivery term, but not with CIP, as it did [Req. for Arb,Ex. C 5, p. 11; M for

CL., paras 100-103].

82. CLAIMANT in para 100 submits that the modification took place by the mere agreement of the

parties [M for CL., para 100]. But RESPONDENT asserts that it has never agreed to change the

delivery term. The Notice of Transport was not an offer to modify the delivery term, it was a

mistake of employee [PO2, para 20, p. 66]. And this slip could not be considered by reasonable

person as change of delivery term. Art. 8 CISG should be used to interpret the statements and

other conduct ofthe parties [Digest of case law, Art. 8, para 1]. First of all, Art. 8(1) CISG should be

applicable. In accordance with this provision for the purposes of the CISG statements made by

and other conduct of a party are to be interpreted according to his intent where the other party

knew or could not have been unaware what that intent was [CISG, Art. 8(1)]. Under Art. 8(3)

CISG in determining the intent of a party due consideration is to be given to all relevant

circumstances of the case. In accordance with abovementioned provisions it was reasonable to

suppose that ticking the CIP box in the Notice of Transport [Req. for Arb, Ex. C 2, p.8] is just a

slip because: 1) other provisions of Notice of Transport (for example, choice of ship as a method

of transport, the only available for CIF delivery term, not for CIP), 2) the Contract in Art 5 [Req.

for Arb, Ex. C 1, p. 7] provides the CIF as delivery term 3) after conclusion of contract

RESPONDENT neither has expressed its intention to modify the delivery term nor illustrated

such intention in subsequent conduct.

83. Hence, the ticking CIP box in the Notice of Transport could not be considered as offer to

modify the Contract. These lead to the conclusion, that there was no mere agreement between

Page 36: Respondent Memorandum Vis 22

18

the parties to change the delivery term and CLAIMANT unilaterally changed it, consequently the

delivery term contained in the L/C 1 is not in conformity with the contract.

2. Inappropriate L/C 1 amounts to fundamental breach under Art. 25 CISG

84. RESPONDENT asserts that failure of CLAIMANT to fulfill its obligations under the contract

must be considered by the arbitral tribunal as fundamental breach of contract in the sense of Art.

25 CISG providing legal grounds for RESPONDENT to avoid the contract.

85. Under UNIDROIT principles the non-performance of contract also includes defective

performance [UNIDROIT 2010, Art. 7.1.1]. In present case incorrect letter of credit should be

considered as defective performance of the Contract.

86. Art. 25 CISG defines the terms and nature of fundamental breach. This article also establishes

that not only rude violation but and “the breach of a collateral duty can give rise to a

fundamental breach” [Digest of case law, Art. 25, para 2]. Moreover, the breach must therefore

nullify or essentially depreciate the aggrieved party’s justified contract expectations [Digest of case

law, Art. 25, para3]. This “expectations” must depend on the specific contract and the risk

allocation envisaged by the contract provisions, on customary usages. And using information

above incorrect L/C 1 leads to non-payment, that should be interpreted as depreciation of the

aggrieved party’s justified contract expectations, which regarded fundamental breach and allow to

avoid the contract by RESPONDENT. This position is supported by Dr. Florian Mohs, he

mentions that steps by buyer include and opening of a workable letter of credit, and obligation

to open of a workable L/C is identical with obligation of buyer to pay the price [Schlechtriem, p.

812-813, Art. 54, para 6]. As far as payment of contractual price is principal obligation of the

buyer [Digest of case law, Art. 53, para 1] the violation of this obligation should be considered by

the arbitral tribunal as fundamental breach.

87. Taking into account the fact that while interpreting the CISG regard is to be had to its

international character and the need to promote uniformity in its application [CISG, Art.7(1)] and

the fact that some jurisdictions, for example like English law, takes a strict view of documentary

performance with regard to trade commodities, the arbitral tribunal should find the non-strict

view in documentary compliance as an essential breach of obligations to be in international

sales contract [Katrina Winsor, para 4.3.2].

88. The case of L/C 1 includes several obligations in breach: 1) inconsistencies of L/C’s provisions

with provisions of contract (different amount of money, amount of coltan, and delivery terms)

[Req. for Arb,Ex. C 7 p. 13; Ex C 5 p.11; Ex C 1 p. 7] and 2) as consequence is non-payment

under the contract in the future when RESPONDENT could not get the payment from bank via

lack of conformity of documents that it would represent to a bank in payment. In this regard the

Page 37: Respondent Memorandum Vis 22

19

inconsistency of L/C 1 with contract provisions amounts to fundamental breach under Art. 25

CISG. The breach of established L/C 1 serves as a reason of substantial deprivation

RESPONDENT of what it is entitled to expect under the Contract (2.a.). CLAIMANT could

foresee the results of established L/C 1 (2.b.).

2.a. The breach of established L/C 1 serves as a reason of substantial deprivation

RESPONDENT of what it is entitled to expect under the Contract

89. RESPONDENT asserts that the breach of established L/C 1 serves as a reason of substantial

deprivation RESPONDENT of what it is entitled to expect under the contract. The main goal of

trade is to exchange one thing for another, which includes money for goods, goods for goods,

and favors for goods or money [A Law Dictionary, Adapted to the Constitution and Laws of the United

States. By John Bouvier], and therefore the sense of commerce is get the profit, hence non-receipt of

profit must be considered as fundamental depriving what it is entitled to expect under the

contract. This means that RESPONDENT only expects from CLAIMANT the payment of

price, which was established in the contract. Hence, if RESPONDENT does not get the money

for delivering goods, it will be deprived of what it is entitled to expect under the contract. When

L/C is inconsistent with contractual provisions, RESPONDENT could not get its money, as

RESPONDENT’s documents and their content are differ from those, which appointed by

CLAIMANT in the L/C for payment. This divergence of documents is a balk for payment, as

the bank may refuse to honor [UCP 600, Art. 16(a)]. In this respect CLAIMANT could not fulfill

its obligations to pay the price, because the steps under the Art. 54 CISG will be incorrect and

will not lead to fulfillment of the main obligation of buyer to make the payment of price under

the contract what would result to RESPONDENT in losing the main benefit of, and its interest

in, the contract.

2.b. CLAIMANT could foresee the results of established L/C 1

90. RESPONDENT supposes that argument of CLAIMANT in para 113 M for Cl. should be

admitted by arbitral tribunal as inconsistent, because CLAIMANT issued L/C 1 after the

conclusion of contract, consequently it is CLAIMANT’s responsibility to provide appropriate

L/C, which would confirm the provisions of contract. CLAIMANT definitely could foresee that

defective L/C may lead to detriments for RESPONDENT.

3. RESPONDENT avoided the Contract on 7 July 2014 abiding by the terms of Art. 72 CISG

91. RESPONDENT submits that the avoidance of contract on 7 July 2014 is in conformity with

rules and terms of Art. 72 CISG. RESPONDENT agrees that Art. 72 CISG could be used in this

case, as the avoidance of contract took place before the date of performance of contract (not

Page 38: Respondent Memorandum Vis 22

20

later than fourteen days after the Buyer received the notice of transport from Seller [Req. for

Arb,Ex. C 1, p.7; Ex. C 7, p. 13]). But RESPONDENT insists that the avoidance of contract on

7 July 2014 were legal and did not break the rules of CISG.

92. In this situation, what became the case of avoidance, CLAIMANT:

a) should admit that Parties never modify the due date of the performance (3.a.).

b) should foresee that the non-performance of its obligations under the contract could lead to the

avoidance of contract. Hence, CLAIMANT, consciously changed the terms of L/C 1, should

itself bear responsibility for all future consequences (3.b.).

c) had not provided adequate assurance of performance of contractual obligations for

RESPONDENT in the text of email on 5 July 2014 [Req. for Arb,Ex. C 6, p. 12] (3.c.).

93. These actions, and all mentioned above, allow RESPONDENT to avoid the contract under Art.

72 CISG.

3.a. The Parties never modify the due date of the performance

94. The argument of CLAIMANT in para 116-118 M for Cl. should be admitted by the arbitral

tribunal as inconsistent, because the disputes about modification of the due date of the contract’s

performance between Parties has never arisen. The contract was avoided by RESPONDENT,

because CLAIMANT could not provide the adequate assurance of its performance for

RESPONDENT under Art. 72(2) CISG, but not because the due date of the performance

expired.

3.b. CLAIMANT could foresee the avoidance of Contract as a result of its own violations

95. RESPONDENT insists that CLAIMANT should foresee avoidance of contract as a result of

establishment of L/C 1 which contradicts to the contract provisions.

96. When CLAIMANT established L/C 1, it had known about provisions of contract (namely, Art.

3, 4, 5 of Contract) [Req. for Arb,Ex. C 1, p. 7]. Moreover, the same terms (except CIF) were

indicated in the Notice of Transport by RESPONDENT [Req. for Arb,Ex. C 2, p. 8]. But in spite

of this CLAIMANT established the L/C as it saw fit, derogating from the Contract. If

CLAIMANT did something that was not agreed by both parties, it must take responsibility for all

the consequences. Schiedsgericht Hamburger Freundschaftliche Arbitrage decided that conditioning some

action on new demands beyond those agreed upon is an anticipatory repudiation of the contract

[Cheese case]. And therefore CLAIMANT actions must be identified as foreseeable for

CLAIMANT and as preconditions for avoidance under Art. 72 CISG. Moreover, China

International Economic & Trade Arbitration Commission (CIETAC) adjudged that failure to open a

Page 39: Respondent Memorandum Vis 22

21

conforming letter of credit by buyer is preconditions for avoidance [CHINA International

Economic and Trade Arbitration Commission, People's Republic of China, 16 December 1997].

97. In the line of arguments above, CLAIMANT had to foresee the results of establishment

ofnonconforming L/C and ought to be responsible for this. RESPONDENT has never agreed

on other terms besides those contained in the contract between the parties. Hence, all terms

about L/C and about goods, which both parties agreed on their contract must be used in

contractual relationships between the parties.

98. RESPONDENT would like to mention again that under Art. 53 CISG payment of price under

the contract is the main obligation of buyer, in default which could allow to seller to avoid the

contract. The incorrect L/C deprives RESPONDENT of getting its money by L/C using

documents which it has, because there would be the lack of conformity between documents,

which RESPONDENT has, and those, which would be declared in L/C. Therefore

RESPONDENT could avoid the contract under Art. 72 CISG.

3.c. RESPONDENT did not get the adequate assurance of obligation’s performance from

CLAIMANT

99. RESPONDENT insist that it did not get the adequate assurance of obligation’s performance

from CLAIMANT.

100. The email by Mr. Storm on 5 July 2014 [Req. for Arb,Ex. C 6, p. 12] is interpreted as assurance to

perform obligations of CLAIMANT. This assurance did not certify the RESPONDENT, as it

included only different and incorrect amount of coltan (100 metric tons), unneeded information

about CLAIMANT’s supplier, and the agreement to CIF. These all illustrates that CLAIMANT

had no intention to settle the various disputes amicably [Req for Arb, para 20, p. 36] and still insists

on different provisions about amount of coltan, which does not conform to the contract.

101. In order to accept the assurance RESPONDENT should be confident that provided assurance is

adequate. As was mentioned by Pr. Christiana Fountoulakis, adequacy of assurance must assure the

creditor (seller), that if there really is a fundamental breach in the future, the detriment caused by

the fundamental breach will be financially absorbed [Schlechtriem, Art. 72, para 28, p.978]. And only

when the provided assurance is adequate from an objective point of view, the creditor must

accept it [Schlechtriem, Art. 72, para 29], but in this situation RESPONDENT, from an objective

point of view, did not accept this assurance.

102. RESPONDENT observed the terms after which it could rightfully avoid the contract without

any violations. First of all, RESPONDENT, as it exacts in Art. 72(2) CISG, gave period of time

within notice (voice-mail) to the CLAIMANT for providing adequate assurance of

CLAIMANT’s performance [Req for Arb, para 19, p. 36]. And then, RESPONDENT got the

Page 40: Respondent Memorandum Vis 22

22

email from CLAIMANT [Req for Arb, Ex. C 6, p. 12], which should presumably be considered as

an assurance, but, unfortunately, it did not assure RESPONDENT that CLAIMANT would

perform its obligations under the contract. And after these actions, RESPONDENT declared the

contract avoidance on 7 July 2014 in written form and sent it to CLAIMANT by Courier [Req for

Arb, Ex. C 7, p. 13]. And this avoidance was done before the date of performance. Consequently

RESPONDENT had the right to avoid the contract, as the assurance was weak and could not

assure the RESPONDENT that CLAIMANT will do its obligations under the contract in future.

103. In accordance with all abovementioned RESPONDENT was entitled to avoid the contract on 7th

July 2014 due to a fundamental breach under Art. 25 CISG as far as in traditional CIF contract,

deviations from the prescribed standard in documentary performance are prohibited and the

ability to cure any defects in the documentation does not extend to commodities markets.

B. RESPONDENT rightfully avoided the contract on 9 July 2014

104. RESPONDENT submits that it rightfully terminated the contract by declaration on 7 July 2014

due to a fundamental breach of contract by CLAIMANT. RESPONDENT was no longer

intended to continue the contract with CLAIMANT. But even if the arbitral tribunal would

decide that RESPONDENT had no right to avoid the contract by its declaration on 7 July 2014

RESPONDENT claims the arbitral tribunal to decide that RESPONDENT’s declaration of

contract avoidance on 9 July 2014 was made rightfully. That is true because deviations in Letter

of Credit of 08 July 2014 (hereinafter – L/C 2) issued by CLAIMANT constitute, firstly, the

fundamental breach of contract (1) where late delivery of L/C 2 substantially deprived

RESPONDENT from what It expected to receive under the contract (2). These grounds give

right to RESPONDENT to avoid the contract.

1. CLAIMANT committed a fundamental breach of the Contract, by establishing inappropriate

L/C 2

105. The establishment of the L/C 2 by CLAIMANT constitutes a fundamental breach of contract on

the grounds of Art. 53 and 54 of CISG. Firstly, CLAIMANT failed to deliver the L/C to

RESPONDENT’s office on time, before the terms for establishing of the L/C has expired [Req

for Arb, Ex. C 9 p. 15; Answer to Req for Arb, Ex. R 4. p. 44](1.a.). Secondly, the L/C contained an

additional document - commercial invoice [Req for Arb, Ex. C 8, p. 14](1.b.). Both of these

deviations should be considered as a fundamental breach of the contract, which give

RESPONDENT right to avoid the contract.

Page 41: Respondent Memorandum Vis 22

23

1.a. CLAIMANT failed to establish proper Letter of Credit on time

106. CLAIMANT asserts that it established L/C 2 in accordance with Art.4 of the Contract [M for Cl.,

para 127]. In contrast, RESPONDENT insists that CLAIMANT failed to establish proper L/C

on time, before the term for establishing has expired.

107. Parties have agreed that the term for establishing of the L/C will be regulated by the Art. 4 of the

contract [Req for Arb, Ex. C 1, p.7]. The article stipulates that “the Letter of Credit shall be

established by the buyer not later than fourteen days after the buyer received the notice of

transport” [Req for Arb, Ex. C 1, p. 7, Art. 4]. RESPONDENT sent the Notice of Transport on

25 June 2014, and by simple calculation, the term for establishing of the L/C should end on 8

July 2014. Both parties operate in different time zones [PO2, para 23]. Moreover, there is a

difference in calculating the time limits in Equatoriana and Mediterraneo [PO2, para 44]. Also,

parties was aware about each other business hours [PO2, para 23]. Thus, CLAIMANT made a

mistake in calculating the deadline for establishing of the L/C, asserting that the deadline for

establishing was on 9 July 2014 [M for Cl., para 128]

108. Both parties are citizens of different states, and there are different methods of calculating the

period before the deadline. As CLAIMANT mentioned, in Equatoriana, the period of calculation

starts to run the day after the notification is received, whereas in Mediterraneo, the period of

calculation includes the day in which the notification is received [PO 2, p.69, para. 44; M for CL.,

para 128].

109. RESPONDENT asserts that CLAIMANT has failed to perform its obligations, as CLAIMANT

had an obligation to notify RESPONDENT about the establishment of L/C(1.a.i.), and

furthermore the information upon the establishment of the Letter of Credit had reached

RESPONDENTS office out of the time-work’s frame for notification(1.a.ii.).

1.a.i. CLAIMANT had an obligation to notify RESPONDENT about the establishment

of L/C

110. CLAIMANT asserts, that the contract regulates only the time of establishment of the L/C, not

the time required for the L/C to reach RESPONDENT [M for Cl., para 130]. In its turn,

RESPONDENT insists that the contract include an implied obligation of CLAIMANT to notify

RESPONDENT about the establishment of L/C. The Art. 5.1.1 of UNIDROIT Principles

regulates that the contractual obligations of the parties may be expressed or implied. Moreover,

it restates the widely acceptable principle according to which the obligations of the parties are not

necessary limited to that which had been expressly stipulated by the contract [Commentary on

UNIDROIT Principles 2010, Art. 5.1.1]. Furthermore, under the Art. 5.1.2 of UNIDROIT Principles,

implied obligation step from:

Page 42: Respondent Memorandum Vis 22

24

a) the nature and purpose of the contract;

b) practices established between the parties and usages;

c) good faith and fair dealing;

d) reasonableness.

111. CISG does not regulate the buyer’s obligation to notify seller about buyer’s own performance.

But, under the Art. 7(2) CISG questions concerning matters governed by the CISG which are not

expressly settled in it are to be settled in conformity with the general principles on which it is

based [CISG, Art. 7(2)]. Good faith has been recognized as a general principle of the CISG. This

position is widely supported by courts decisions [Digest of case law, Art. 7, para 13; Broadcasters case;

Metal ceiling materials case]. Moreover, in several cases, courts stated that the general principle of

good faith requires the parties to cooperate with each other and to exchange information relevant

for the performance of their respective obligations [Digest of case law, Art. 7, para 14;Takap B.V. v.

Europlay S.r.l.; Trade usage case; Pitted sour cherries case; Aluminum case; Machinery case]. In this regard

due to the principle of good faith and duty to cooperate, taking into account express and implied

obligations of parties under the contract, CLAIMANT had an implicit obligation under the

contract to notify RESPONDENT about the establishment of L/C. CLAIMANT failed to notify

RESPONDENT about the establishment of L/C.

1.a.ii. The information upon the establishment of the L/C 2 had reached

RESPONDENT’S office out of business hours for notification

112. CLAIMANT in para 137 stated, that parties had counted the deadline using calendar days—

where non-business days are included in calculating the period [M for CL., para 137]. Contrary to

CLAIMANT position, RESPONDENT alleges that parties should use business days as a method

of calculating the period of time for establishing of L/C. RESPONDENT asserts to the fact, that

L/C 2 arrived to RESPONDENT’s office out of RESPONDENT’s ordinary business hours,

and as consequence CLAIMANT failed to perform its obligations.

113. Under Art. 4 of the contract, parties does not stipulate any provision about the time of delivery

of L/C to the RESPONDENT’s office, except provisions that L/C shall be established by the

Buyer not later than fourteen days after the Buyer received the notice of transport in regard to

shipment [Req for Arb, Ex. C 1., p.7]. Art. 54 of CISG stipulates, that buyer's obligation to pay the

price includes taking such steps and complying with such formalities as may be required under

the contract or any laws and regulations to enable payment to be made [Art. 54, CISG]. Art. 5.1.1

of UNIDROIT Principles stipulates, that the contractual obligations of the parties may be expressed

or implied [UNIDROIT 2010, Art. 5.1.1]. Therefore, Art. 5.1.2 of UNIDROIT 2010 distinguishes

several ways how implied obligations step from:

Page 43: Respondent Memorandum Vis 22

25

a) the nature and purpose of the contract;

b) practices established between the parties and usages;

c) good faith and fair dealing;

d) reasonableness [UNIDROIT 2010, Art. 5.1.2].

114. Both of the parties are legal entities [Req. for Arb, para 1-2, p. 2], it would be reasonable to

consider that they have schedule of “open” and “closed” hours. It is commonly known, that this

schedule is called “Business day” [Business hours law]. In this case, it would be unreasonable to use

calendar days, as a method of measuring of time, as both parties are legal entities [supra para 113],

they have entered into the contract of the sales of goods [Req for Arb, Ex. C 1, p. 7], and

definitely, they both was aware that they operate in a different time zones [PO2, para 23].

115. Therefore, CLAIMANT had to notify RESPONDENT, not later than the end of 14th

RESPONDENT’s business day. Hence, CLAIMANT failed to notify RESPONDENT as the

information about the establishment of L/C has reached RESPONDENT out of time frame for

notification about establishment of L/C.

1.b. CLAIMANT by inserting a commercial invoice as an additional document in the L/C 2

committed a fundamental breach

116. CLAIMANT in para 138 stated, that itcould not have committed a breach of contract upon

something that is not regulated within the contract [M for CL., para 138]. Contrary to that,

RESPONDENT asserts, that CLAIMANT by inserting a commercial invoice as an additional

document in the L/C 2 committed a fundamental breach.

117. CLAIMANT should not insert an additional document in establishing of L/C, because parties

have never agreed on the documents that must be presented with the L/C in order to obtain

payment. In Art. 4 of the contract, parties have forgot to agreed on the documents that must be

presented with the L/C [PO2, para 16, p. 65]. Art. 25 CISG states that a breach of a contract is

fundamental if it results in such detriment to the other party as substantially to deprive him of

what he is entitled to expect under the contract [CISG, Art. 25]. Also, there is one more

condition, that should be presented in order to consider a breach as fundamental. A reasonable

person of the same kindin the same circumstances would not have foreseen such a result [CISG,

Art. 25].

118. Art. 29 CISG stipulates, that the contract can be modified only by mere agreement of the

parties. [CISG, Art. 29]. Moreover, the same provisions are contained in Art. 3.2 of UNIDROIT

Principles [UNIDROIT 2010, Art. 3.2]. But, in terms of the contract, there is no any stipulations

on the question which documents should be presented along with the L/C [Req. for Arb, Ex. C 1,

p.7], hence there were no reached agreement between parties on the issue.

Page 44: Respondent Memorandum Vis 22

26

119. One of the major principles of the contractual law is a consent [BIX p. 251]. And it also known,

that one of the pillars of the law of contract formation is the principle of mutual assent.

According to this principle, a contract forms only when the positions of the two parties meet

[BEN-SHANAR, p. 1829].

120. Moreover, there is an international trade practice, which implies an obligation on buyer, to be

prepared to amend or re-negotiate terms of the letter of credit with the seller. And, more

important, is that all parties must agree to amend the document [CRF, Ron Borcky Understanding

and Using Letters of Credit, Part II]

121. In present case, CLAIMANT, by inserting an additional document in the L/C, have not only

breached the contract, but also its actions constitute a breach of a contractual principles, as

CLAIMANT never informed RESPONDENT about the documents, which would be necessary

in order to obtain payment. Thus, parties have not met an agreement on the documents that

must be presented with the L/C in order to obtain payment. Therefore, there is no mutual assent

between parties on this question.

122. Moreover, as there is no consent between parties, RESPONDENT substantially deprived from

what he expect under the contract, and it would be unreasonable for CLAIMANT to argue, that

it has not foreseen that insertion of an additional document, would substantially deprive

RESPONDENT.

123. Furthermore, RESPONDENT never argues that commercial invoice is a core supporting

document for the sales of goods [M for Cl., para 140]. But, RESPONDENT is against of insertion

of an additional document, as it breaches the principles of a contractual law. [supra para 121] In an

absence of an mutual assent between parties on the documents, that should be presented along

with the L/C, in order to obtain payment, it is unfair for CLAIMANT to decide which

documents RESPONDENT should present in order to obtain payment without any consent

between parties. Following this logic, CLAIMANT could insert as many documents as it wish.

124. And therefore, by inserting an additional document to the L/C, CLAIMANT committed a

fundamental breach of the contract.

2. Late delivery of L/C substantially deprived RESPONDENT from what it expected under

the Contract

125. CLAIMANT has asserted that RESPONDENT was not substantially deprived by the late

delivery of L/C 2 [M for Cl., para 146]. In contradiction to this, RESPONDENT asserts that the

late delivery of L/C substantially deprived it.

126. RESPONDENT does not argue on the fact that the parties did not stipulate in their contract

that “time is of the essence” [PO2, para 18, p. 65]. But, RESPONDENT insists, that as coltan is a

Page 45: Respondent Memorandum Vis 22

27

mineral with a highly volatile price and most transactions are heavily document based and involve

payment via L/C generally, a strict compliance with the contractual provisions is required [PO2,

para 18, p. 65]. Due to the fact, that CLAIMANT delivered L/C after then when the term for

delivery has expired, RESPONDENT was substantially deprived of was it expect under the

contract - payment.

127. Prof. Dr.Ulrich G. Schroeter asserts, that a delay in obtaining the required letter of credit by itself

be a fundamental breach of the contract [Schlechtriem, Art. 25, para 66, p. 434]. Also, he adds that,

the same true for cases in which the buyer refuses to provide an agreed letter of credit in time,

although the very purpose of this contractual obligation - as often in cases where documentary

payment terms are used - is to protect the seller from having to ship the goods without the

payment being secured, since this makes him vulnerable to attempts by the buyer to ‘renegotiate’

the price [Schlechtriem, Art. 25, para 66. p. 435].

128. This position is supported by court decisions, as they consider that the refusal to establish a

timely letter of credit was clearly a fundamental breach [Digest of case law, Art. 25, para 6;Downs

Investments v. Perwaja Steel SDN BHD].

129. In present case, RESPONDENT was substantially deprived of what it expected under the

contract - payment, as CLAIMANT presented invalid L/C twice [Req. for Arb,Ex. C 5, p. 11; Ex.

C 8, p. 14]. This invalid establishment, due to the coltan market conditions [Req. for Arb, para 4. p.

3], makes RESPONDENT vulnerable to attempts by CLAIMANT to ‘renegotiate’ the price.

130. Hence, RESPONDENT insists to consider the late delivery of L/C is as a fundamental breach

of the Contract.

131. In summary of all abovementioned arguments on merit issues, RESPONDENT asserts that it

had the right to avoid the contract of 28 March 2014. Firstly, there was a fundamental breach of

contract committed by CLAIMANT that gave right to RESPONDENT to avoid the contract.

The L/C 1 is not in conformity with the terms of the contract, due to the fact, that is stated a

larger sum of money, different quantity of goods to deliver and different delivery terms. Such

deviations should be considered as a breach of a strict compliance principle, committed by

CLAIMANT. Secondly, CLAIMANT failed to notify RESPONDENT about the establishment

of a proper L/C during the contractual term. The notification was dispatched to

RESPONDENT’s office out of ordinary business hours of RESPONDENT. Moreover,

CLAIMANT unilaterally added an additional document to the L/C 2 (commercial invoice).

Unilateral insertion of an additional document should be considered as breach of the contractual

principle of mutual assent, which lead to a right for legitimate avoidance of the contract.

Consequently, RESPONDENT rightfully declared the contract’s avoidance by both declarations.

Page 46: Respondent Memorandum Vis 22

28

PROCEDURAL ISSUE 2

III. The order of the Emergency Arbitrator should not be lifted by the arbitral tribunal

132. RESPONDENT agrees with CLAIMANT that ICC Rules2012 provides that Emergency

Arbitrator Provisions must apply to any arbitration under ICC brought pursuant to an agreement

concluded after 1 January 2012 [M for Cl., paras 4-5].

133. Contrary to CLAIMANT’s submission [M for Cl., para 6] RESPONDENT states that parties did

opt out the Emergency Arbitrator provisions and the Coltan Purchase Contract provides

exclusive jurisdiction for granting interim measures to national courts (1). Moreover the

substantive requirements for granting interim measures were not fulfilled (2).

1. Under Article 29 (6) b of ICC Rules 2012 the parties did opt out the Emergency Arbitrator

provisions

134. RESPONDENT states that the parties agree to exclusive court jurisdiction to impose interim

measures (1.a.) and the interpretation of Art. 21 of the Coltan Purchase Contract provides for

the exclusive jurisdiction of courts to grant interim measures. (1.b.).

1. a. The parties can agree to exclusive court jurisdiction to impose interim measures.

135. It is worth noting, that the parties had an opportunity to assign to the national court

responsibility for granting of interim measures in order to avoid misunderstandings that might

arise and have arisen as a consequence.

136. Of course, the additions to the mandatory provisions of ICC Rules 2012 concerning Emergency

Arbitrator (Art 29: Emergency Arbitrator) designed to enhance the ability of the parties that

cannot wait for constitution of the tribunal to request interim measures, however, a clear

understanding of the expression of will, the ability to read an exception pursuit "between the

lines" are important interpretation conditions under the contract. [Drahozar].

137. The principle of parties autonomy directly allow the parties to grant the power to impose interim

measures to national courts.

138. Only ICSID Convention provides exclusive jurisdiction to arbitrators to grant provisional

measures. Thus, in the case of ICSID Rules, the parties must expressly agree for judicial authority

in the area of interim measures of protection. In contrast, there is no national law that empowers

arbitrators` exclusive jurisdiction to grant provisional measures. Parties may, however, oust the

courts' jurisdiction in regard of interim protection of rights to the extent permitted by national

law [Yesilirmak, page 61].

Page 47: Respondent Memorandum Vis 22

29

139. Under ICC Rules 2010, the procedure of granting interim measures defined clearly enough. Under

Art. 28(1) of ICC Rules 2012unless the parties have otherwise agreed, as soon as the file has been

transmitted to it, the arbitral tribunal may, at the request of a party, order any interim or

conservatory measure it deems appropriate. The arbitral tribunal may make the granting of any

such measure subject to appropriate security being furnished by the requesting party.

140. Based on the conditions determined in Coltan Purchase Contract [Req. for Arb, Ex. C 1, p. 7], the

parties have agreed “otherwise” that in its meaning, excludes the possibility of the arbitral

tribunal to impose provisional measures.

141. The national court has a great strength in the imposition of provisional and conservatory

measures. Due to the fact that the legal nature of the contract is consensual, arbitration will not

be able to bind third parties (banks, agencies, local authorities) to the execute its orders that in its

turn, can fully do national court.

142. Arbitrators have no jurisdiction over third parties to arbitration agreement due to contractual

(consensual) nature of arbitration. In international arbitrations, involvement of such third parties

as banks (as issuers of letters of credit or bank guarantees) and persons (who, e.g. may legally

hold goods in dispute; subcontractors) is sometimes unavoidable. However, since arbitrators'

power derives from arbitration agreement, no arbitral power could be exercised over legal rights

of third parties to arbitration. [Yesilirmak, p. 87]

143. Thus, the parties were able to properly determine the appropriate way to securing the claim in the

Coltan Purchase Contract, however, CLAIMANT has now not only refused formed positions,

but also seeks to challenge existing legal fact.

1.b. The interpretation of Art. 21 of the Coltan Purchase Contract provides for the exclusive

jurisdiction of courts to grant interim measures

144. RESPONDENT reminds the rule of literal interpretation which must be observed (1.b.i.) as well

as application of the UNIDROIT Principles allows RESPONDENT to interpret Art. 21 of the

Coltan Purchase Contract against CLAIMANT (1.b.ii.)

1.b.i. The rule of literal interpretation must be observed.

145. RESPONDENT requests to pay attention on the literal interpretation rule, which provides that

the words of the statute or contract are given their natural or ordinary meaning and applied

without the judge seeking to put a gloss on the words or seek to make sense of the statute or

contract. [R v Harris, Whitely v Chappel]

146. Literal interpretation of the Art 21 of the Coltan Purchase Contract leads to the understanding

that the article is not only establishes the exclusive jurisdiction of the national courts for interim

Page 48: Respondent Memorandum Vis 22

30

measures, but also limits the ability of the Emergency Arbitrator because it never talks about

his\her competence.

147. Under Art 21 of the Coltan Purchase Contract the courts at the place of business of the party

against which provisional measures are sought shall have exclusive jurisdiction to grant such

measures.

148. Article 21 of the Contract was included when the ICC Rules did not contain the Art. 29. Under

Art. 23 of ICC 1998 Rules unless the parties have otherwise agreed, as soon as the file has been

transmitted to it, the arbitral tribunal may, at the request of a party, order any interim or

conservatory measure it deems appropriate. As it can be mentioned from the article – the power

for granting interim measures belongs only to the arbitral tribunal excluding any Emergency

Arbitrator provisions.

149. Moreover, the parties were aware of the changes, made in ICC Rules 2012 [PO2, para 14]. The

actual purpose of inclusion of Art 21 in the Coltan Purchase Contract was to ensure that efficient

interim relief can be obtained without any discussion about the jurisdiction of the courts. [PO 2,

para 13]. It means that CLAIMANT was not seeking for Emergency Arbitrators support, but

trying to shield themselves from the disputes between national court decisions.

150. Moreover, there are court decisions on such issues associated with controversial moments of the

court determination, having the right of imposing an interim measure if there is a problem with

the interpretation of the contract.

151. Thus, the national court of Brazil in the similar case ruled for the first time, on the issue of the

concurrent jurisdiction of national courts and arbitral tribunals with respect to the making of

interim measures by the last and decided that interim measures imposed by courts will prevail

[Itarumã Participações S.A. v Participações em Complexos Bioenergéticos S.A.]

152. In addition, RESPONDENT has always understood the inclusion of Art 21 as a way to limit

interference with arbitration from outside, like sudden intervention of Emergency Arbitrator. A

clear position on this matter is expressed in Req. for Arb, para 10 where stated that

RESPONDENT always understood it to be intended to limit all types of interim relief to that

available from the courts at the respective parties' place of business. These courts are the only

instance which can grant efficient interim relief.

153. Based on the above said, RESPONDENT insists that the Emergency Arbitrator had no

jurisdiction to impose provisional measures, as the contract clearly established national courts

exclusive jurisdiction to grant interim measures.

Page 49: Respondent Memorandum Vis 22

31

1.b.ii. UNIDROIT Principles 2010 allows interpreting Art. 21 of the Contract against

CLAIMANT

154. Contrary to CLAIMANT`S assertion [M for Cl., para 6] RESPONDENT submit that the lack of

clarity with Art 21 of the Coltan Purchase Contract can be interpreted against CLAIMANT in

the thresholds with UNIDROIT Principles.

155. Application of UNIDROIT Principles to the dispute may be interpreted as follows. According to

Art 21 of the Coltan Purchase Contract the substantive law of the contract - the law of Danubia

[Req. for Arb, Ex C 1, p.7], in its turn, Danubia, adopted the UNIDROIT Principles [PO 2, para

42] which allows RESPONDENT to indicate the appropriateness of using those Principles.

156. According to Art. 4.6 of UNIDROIT Principles (Contra proferentem rule) if contract terms

supplied by one party are unclear, an interpretation against that party is preferred. That means

that misunderstanding appeared with Art. 21 of the Coltan Purchase Contract can be interpreted

against CLAIMANT, namely, Art. 21 of the Coltan Purchase Contract by its meaning exclude the

power of Emergency Arbitrator.

157. Inter alia, responsibility for using of unclear terms will lie on the CLAIMANT, due to feature of

interpretation this Principle. A party may be responsible for the formulation of a particular

contract term, either because that party has drafted it or otherwise supplied it, for example, by

using standard terms prepared by others.[Commentary on UNIDROIT Principles 2010].

158. From this provision it is clear that Art 21 of the Coltan Purchase Contract cannot be interpreted

in favor of CLAIMANT referring to the principle Contra proferentem rule.

2. The substantive requirements for granting interim measures are not fulfilled.

159. Art 29(1) of the ICC Rules 2012 provides that a party that needs urgent interim or conservatory

measures that cannot await the constitution of an arbitral tribunal may make an application for

such measures.

160. Contrary to CLAIMANT`S submission [M for Cl., paras 18-19] RESPONDENT states that the

substantive requirements for granting interim measures under Danubian Law were not fulfilled,

CLAIMANT did not demonstrate urgency (2.a) and there was no irreparable harm imminent to

CLAIMANT (2.b). Moreover CLAIMANT has no possibility of success on the merits(2.c).

161. Contrary to CLAIMANT`s assertion [M for Cl., para 18] the application of Art 17A of DAL is

impossible because of the nature of the measures imposed by arbitral tribunal and emergency

measures. Those two components of arbitration must be separated from each other due to the

following: the emergency measures are pre-arbitral by its nature, what separates them from the

real arbitration.

Page 50: Respondent Memorandum Vis 22

32

162. An application for Emergency Measures can only be accepted if it is received by the Secretariat

prior to the transmission of the file to the arbitral tribunal. This provision demonstrates that the

EA procedure is pre-arbitral in nature. The fact that the EA procedure is designed to support a

future arbitration procedure does not mean that it is itself anarbitration procedure. [Bagiel 4.2[a]].

163. For this reason RESPONDENT argues, that drawing parallels between the arbitral tribunal and

Emergency Arbitrator made by CLAIMANT is wrong and Art. 17A of DAL cannot be

applicable for demonstration of fulfillment of all conditions provided by it.

2. a. CLAIMANT did not demonstrate urgency

164. The concept of “urgency” in the arbitration proceedings shall be interpreted broadly, however,

there are several criteria, through using which, it would be quite logical to understand the actual

meaning of urgency and necessity, separating it from the adjacent, unwanted concepts.

165. Urgency is certainly one of the most important requirements for granting provisional measures.

Urgency should be considered along with the requirement of serious or irreparable harm, there

are situations where no urgency exists at all. That means no harm will, in principle, be done for

the period up to the final award if the measure requested is not granted. In such cases, interim

protection is not appropriate at all. [Yesilirmak, page 95].

166. It has been established by CLAIMANT in its submission [M for Cl., para 21] that

RESPONDENT is in the process of negotiating with other customers. As one of the customers,

who is heavily dependent on delivery from Xanadu is looking for a delivery at the beginning of

August, it is very likely that the delivery would have taken place before the Arbitral Tribunal is

established and has had time to deal with the matter. [Order of EA, para 10]

167. CLAIMANT refers only to its own conjectures about the negotiations contesting that the

urgency of the interim measures must be taken [M for Cl. para 21]. The links, provided at the

position of CLAIMANT are incorrect.

168. Participation of RESPONDENT in business negotiations is treated by CLAIMNAT as real

contractual obligations, which, not only in accordance with the law, but also with common sense

is not true. At present, RESPONDENT has not concluded any actual contract for the supply of

coltan, which may belong to CLAIMANT. Moreover, there was a rumour that due to the use of

the innovative technique the increase in the demand for coltan would be much smaller than

originally anticipated. [PO 2, para 30]. RESPONDENT did not deny that it is in negotiations with

buyers [PO 2, para 33], however this cannot be regarded as a real threat or alleged harm.

169. The order made by the Emergency Arbitrator prevents RESPONDENT from disposing of the

coltan presently stocked at its warehouse. Since the order was rendered the price has risen

Page 51: Respondent Memorandum Vis 22

33

considerably and there have been numerous requests by long term customers of

RESPONDENT for additional quantities of coltan. RESPONDENT could, however, not accept

a single one due to the order made by the Emergency Arbitrator. It is highly probable that

because of positive developments in Xanadu, RESPONDENT will only be able to sell the coltan

at a lower price in the future. [Answer to Req. for Arb, para 38].

170. However, the actual contracts that can confirm the presence of the need to adopt interim

measures do not exist, which means that negotiations can not be construed against

RESPONDENT.

171. Based on the abovementioned RESPONDENT insists on fact that the necessity and urgency of

taking emergency measures has not been demonstrated by CLAIMANT.

2.b. There was no irreparable harm imminent to CLAIMANT

172. RESPONDENT argues that the concept of "imminent harm" was not used appropriately by

CLAIMANT. Assumptions, made by CLAIMANT regarding the "urgency" of application for

interim measures [M for Cl., paras 21-22] are closely related to the distorted perception of the

RESPONDENT in negotiations with other representatives of the world market.

173. Also worth noting is that in case AHOUSAHT INDIAN BAND V. CANADA (FISHERIES

AND OCEANS), attempt to bring RESPONDENT of the negotiations has been interpreted by

the court against CLAIMANT.

174. Attempts to output RESPONDENT from negotiations with other market players could cause

both: the actual and reputation harm, which can cause counterclaims. That means that the

RESPONDENT’s right for negotiations cannot be violated through the CLAIMANT’s

conjectures and reasoning.

175. Summarizing, RESPONDENT asserts that CLAIMANT did not demonstrate urgency as well as

there was no irreparable harm imminent.

2.c. CLAIMANT has no possibility of success on the merits.

176. In regard to issues on merits, RESPONDENT submits that CLAIMANT is not entitled to

receive 30 metric tons of coltan under the Coltan Purchase Contract. RESPONDENT asserts

that it rightfully avoided the Coltan Purchase Contract both on 7 July 2014 and 9 July 2014.

RESPONDENT rightfully avoided the Coltan Purchase Contract on 7 July 2014 due to the fact

that CLAIMANT has not fulfilled its obligations under the Coltan Purchase Contract and its

actions constitute the fundamental breach of the Coltan Purchase Contract. Thus,

RESPONDENT rightfully avoided the Coltan Purchase Contract. RESPONDENT rightfully

Page 52: Respondent Memorandum Vis 22

34

avoided the Coltan Purchase Contract on 9 July 2014. The late delivery of L/C 2 substantially

deprives RESPONDENT of what it expected under the Coltan Purchase Contract. The same

may apply to the insertion of an additional document to the L/C 2 - the commercial invoice,

which RESPONDENT should present to the bank in order to obtain payment. Both of these

deviations constitute a fundamental breach of the Coltan Purchase Contract, which lead to a

legitimate avoidance of the Coltan Purchase Contract by RESPONDENT [supra part II].

177. Hence, the substantive requirements for granting interim measures are not fulfilled.

178. Therefore, the order of the Emergency Arbitrator should not be lifted by the arbitral tribunal.

Page 53: Respondent Memorandum Vis 22

35

REQUEST FOR RELIEF

In light of the above submissions, RESPONDENT respectfully requests this Tribunal:

a. To reject all claims raised by CLAIMANT;

b. To find that the arbitral tribunal has jurisdiction over Global Minerals Ltd.;

c. To lift the remaining part of the order made by Emergency Arbitrator against Respondent on

26 July 2014.

Respectfully submitted on January 2015 by

______/s/___________ ______/s/___________

Artem Azamatov Daria Andronova

______/s/___________ ______/s/___________

Nastassia Kashchyshyna Herman Khomchanka

______/s/___________ ______/s/___________

Stahiy Sviridovich Aliaksandra Pakhomava