retaining wall construction along rainier ave s starting soon! · 2019-12-13 · example retaining...

2
PO Box 34996 Seattle, WA 98124-4996 CONSTRUCTION NOTICE Rainier Ave S Hazard Mitigation Retaining wall construction along Rainier Ave S starting soon! Retaining wall construction along Rainier Ave S starting soon! ¡La construcción del muro de contención a lo largo de Rainier Ave S comenzará pronto! ሬነር ጎዳና ኤስ [Rainier Ave S] ተከትሎ የጥገና ግድግዳ ግንባታ በቅርብ ይጀምራል! حولٍ ء جدار واق ا بناً بدأ قريب سيRainier Ave S! 雷尼爾南大街 (Rainier Ave S) 沿線的護土牆施工工程即 將開始!

Upload: others

Post on 15-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

PO Box 34996Seattle, WA 98124-4996

CONSTRUCTION NOTICERainier Ave S Hazard MitigationRetaining wall construction along Rainier Ave S starting soon!

Retaining wall construction along Rainier Ave S starting soon!

¡La construcción del muro de contención a lo largo de Rainier Ave S comenzará pronto!

ሬነር ጎዳና ኤስ [Rainier Ave S] ተከትሎ የጥገና ግድግዳ ግንባታ በቅርብ ይጀምራል!

!Rainier Ave S سيبدأ قريبًا بناء جدار واٍق حول

雷尼爾南大街 (Rainier Ave S) 沿線的護土牆施工工程即將開始!

LEARN MOREwww.seattle.gov/transportation/rainierhazardmitigationPhone: 206-684-3669Email: [email protected]

Example retaining wall on Rainier Ave S at S Perry St

Cowen Park Bridge Seismic Retrofit Project

CONSTRUCTION SCHEDULEConstruction is anticipated to start as early as Wednesday, December 4, 2019 and last approximately 6 months. This schedule is weather dependent and subject to change.

In order to safely replace the expansion joints, we will need to temporarily close the bridge. We currently anticipate up to 3 weekends of full bridge closures scheduled for spring 2020. We will share more information about anticipated closure dates and detour route in advance.

Thank you in advance for your patience during this work!

WHAT TO EXPECT DURING CONSTRUCTIONWe will minimize construction impacts as much as possible. During construction, please expect:

• Typical weekday work hours of 7 AM – 5 PM, Monday through Friday

• Redirects for people walking and biking across the bridge

- People walking across the bridge will be directed to one side

- People biking will merge with traffic for the duration of construction

• 3 weekend full bridge closures and detours. We will post detours and notify nearby homes 72 hours in advance

• Temporary closure of the upper trail underneath the bridge within Cowen/Ravenna Park

• Noise, dust, and vibrations during work hours• Equipment and construction materials near the

site, including trucks using the access road to the west from Brooklyn Ave NE, to move materials and equipment in and out of the work zone

PROJECT OVERVIEWEarthquakes could have a significant detrimental effect on Seattle's infrastructure. To address this risk to city infrastructure, the City of Seattle established the bridge seismic retrofit program. As part of the Levy to Move Seattle, 16 bridges were selected for seismic retrofits, including the Cowen Park Bridge.

The retrofits will strengthen the bridge so it can better withstand seismic events like earthquakes. This work will include:

• Strengthening the existing arch and end of bridge support columns with fiber wrapping

• Strengthening support beams and reinforcing the interior columns

• Replacing and repairing expansion joints

PROJECT OVERVIEWWe're working to address the long-standing surface slides along segments of Rainier Ave S from S Carver St to the south City limits near S Ryan St that over the years have encroached onto the sidewalk and in some cases into the bike and vehicle lane.

Starting in early 2020, and continuing through early fall, we will construct retaining walls at the locations outlined within the map below. Crews may complete preliminary work in December 2019.

WHAT TO EXPECT DURING CONSTRUCTIONWe will minimize construction impacts as much as possible. During construction, please expect:

• Typical weekday work hours of 7 AM–5 PM, Monday through Friday

• Some vehicle and/or center turn lane restrictions on Rainier Ave S

• Detours around the work area for people walking and biking

• Noise, dust, and vibrations during work hours

Servicios de traducción e interpretación disponibles bajo petición 206-684-3669

如果您需要此信息翻譯成中文請致電 206-684-3669

ስለ ፕሮጄክቱ የበለጠ ለማወቅ ወይም ትርጉም አገልግሎት ለማግኘት ጥያቄ ለማቅረብ ወደዚህ ይደውሉ 206-684-3669

لخدمات ال�جمة التحريرية والشفهية، يُرجى

ا�تصال ع  206-684-3669

Rainier Ave S Hazard Mitigation

S CARVER ST

58TH

AVE

S

60TH

AVE

S

59TH

AVE

S

63RD

AVE

S

62N

D AV

E S

64TH

AVE

S

65TH

AVE

S

66TH

AVE

S

68TH

AVE

S

72N

D AV

E S

S TAFT ST

75TH

AVE

S

61ST

AVE

S

S REDWING ST

WATERS AVE S

S ROXBURY ST

S KEPPLER ST

S PILGRIM ST

S PILGRIM ST

S NORFOLK ST

S COOPER ST

S RYAN ST S RYAN ST

S PERRY ST

S NORFOLK ST

ARROWSMITH AVE S

RAINIER AVE S

CORNELL AVE S

Sidewalk areas cleared of debris (completed)New retaining wall construction (not to scale)

N