review of progress and future work sqss sub group 2 august 2006 dti / ofgem offshore transmission...

23
Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Upload: delilah-stewart

Post on 25-Dec-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Review of progress and future work

SQSS Sub Group

2 August 2006

DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Page 2: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Content

• Review of likely boundary between Offshore Generator and Offshore TO

• Cost benefit analysis • Work plan• Data availability and transparency • Other issues

Page 3: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Offshore Ownership Boundary•Reason for review

–Need to understand the scope of the offshore transmission system to understand the required scope of the offshore security standards

• This assessment has taken into account 4 options • Each option has been compared to existing onshore

arrangements, and existing CUSC, STC and charging methodology definitions.

• More detailed paper to be made available for wider consultation.

Page 4: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Option 1; TO to own up to the transmission voltage busbar clamps on the platform transformer circuitOffshore

transmission system

132kV assets

Option 4; TO to own up to the individual wind turbine generator transformer.

Windfarm electrical system

33kV assets

Option 2; TO to own up to the transformer LV disconnectors

Option 3; TO to own up to the disconnector on the busbar side of the circuit breaker on the incoming windfarm circuit

Windfarm electrical system

Single offshore platform

Options considered

Page 5: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Initial Thoughts

• Option 3 is recommended as it:– Best facilitates competition in generation– Simplifies ownership of offshore platforms– Allows the offshore TO to provide Users with

a consistent level of security

• Option 1 could be considered but provides less benefits than Option 3 if more than one Offshore Generator is connected

• Options 2 and 4 are not recommended

Page 6: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Initial Thoughts

• Sub-group intends to develop a detailed paper explaining the recommendation

• Sub-group has assumed that the default offshore ownership boundary will be as its recommendation (Option 3)

• Main Impacts:– Transformer circuits will be included within the

security standards for offshore transmission– Assumption will require a review of the consequential

impact on Grid Code, access rights and charging methodology

Page 7: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Cost-Benefit Analysis

•Concept

•Scope

•Example configurations

•Work progress and key results

•Proposed format of SQSS for offshore transmission

Page 8: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Concept of cost-benefit analysis

Network Capacity and Redundancy

Cost

Investment&Maintenance Costs

Cost of curtailed wind energy and losses

Total Cost

Optimal network

Page 9: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Scope of cost-benefit analysis• Offshore networks

– Switchgear reliability, installation cost, platform cost, ratings, maintenance requirements

– Cable reliability, installation cost, maintenance requirements, ratings, electrical parameters

• Transmission mode (AC vs DC)– Compensation requirements – Losses

• Windfarms– Wind resource characteristics– Typical turbine ratings, availability, cost– Windfarm size– Windfarm distances from shore

• Future value of energy and ROCs • Impact on onshore system operation

– Additional reserve costs

Page 10: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Examples of single AC connections

132 kV

33 kV

Onshore network

132 kV

220kV

33 kV

220 kV

Onshore network

Windfarm electrical system Windfarm electrical system

Shoreline

Page 11: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Example of a shared AC connections

132 kV

33 kV

400 kV

132 kV

Onshore transmission network

400 kV

132 kV

33 kV

132 kV

33 kV

Page 12: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

132 kV

33 kV

400 kV

132 kV

On-shore transmission network

400 kV

132 kV

33 kV

132 kV

33 kV

AC DC

AC DC

AC DC

DC AC

DC AC

DC AC

275 or 400 kV

Example of a shared DC connection

Page 13: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Progress and key results• Methodology for the evaluation of cost and reliability

performance of alternative offshore transmission configurations has been developed

• Key differences between offshore and onshore networks– Significantly higher capex requirements – Technology constraints– Wind generation operates at lower load factors than

conventional plant• Analysis of a range of connection types suggests that

generally lower levels of redundancy can be justified for offshore transmission networks when compared with onshore transmission networks– Justifiable levels of redundancy will be influenced by the size of

the wind farm and its distance from shore– Initial analysis suggests significant benefits in providing flexibility

at the platform and interconnections between offshore platforms in close proximity

Page 14: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Illustrative results

• Numerical values shown are indicative ONLY.

• Studies are NOT complete and key assumptions and electrical, reliability and cost data need validation.

• Comprehensive sensitivity studies are yet to be carried out

Wind farm size (MW)

150

300

450

Distance to shore (km)10 50

600

One circuit

Two circuits

Three circuits

Page 15: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Numerical values are

indicative ONLY

Proposed Table form of SQSS for Offshore Networks/1

Distance from Shore: 10 km

Wind Farm Capacity

Network Capability to be Restored

Range of Power Available Network Capacity Following First Circuit Outage

Available Network Capacity Following Second Circuit Outage

Up to

150MW

0 NIL

Between 150MW and 300MW

X1 NIL

Between 300MW and 450MW

Y1 Z1

Above 450MW U1 V1

Page 16: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Numerical values are

indicative ONLY

Proposed Table form of SQSS for Offshore Networks/2

Distance from Shore 50kM

Wind Farm Capacity

Network Capability to be Restored

Range of Power Available Network Capacity Following First Circuit Outage

Available Network Capacity Following Second Circuit Outage

Up to

300MW

0 NIL

Between 300MW and 450MW

X1 NIL

Between 450MW and 800MW

Y1 Z1

Above 800MW U1 V1

Page 17: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Work plan

Page 18: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Work plan and key dates• Further develop the cost-benefit evaluation models (by 14

August)– Take account of the impact of losses– Quantify the impact of diversity in the windfarm output– Take account of the impact of reactive power effects– Develop models further and carry out sensitivity analysis

• Carry out cost-benefit studies and propose Draft Tables and Processes for forming SQSS for offshore transmission networks for review by the sub-group (by 24 August)

• Submit draft SQSS Generation Connection Criteria for offshore transmission networks to OTEG for consideration (31 August)

• Carry out detailed sensitivity analysis.• Re-assess and refine draft SQSS Generation Connection

Criteria for offshore transmission networks (30 September)• Proposed workplan discussed at subgroup meeting on

28/07/06

Page 19: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Data Availability and Transparency

Page 20: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Data availability

• The study work is conditional on receipt of all data from suppliers and developers

• The sub-group has defined the data requirements and highlighted the data that has not yet been provided

• There is risk that the timescales in the work plan will not be met if this data required is not provided– The current work plan is contingent on all data being

provided by 14th August.

Page 21: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Transparency of data• All results of the cost-benefits evaluations should

be re-producible• All data used in the analysis should be visible• Some of the cost information and wind data is only

being provided to the DTI Centre for Distributed Generation and Sustainable Electrical Energy (under confidentiality agreements).– It is hoped that suitable anonymous, generic,

representative data can be produced from project specific data

• Concern is that the sub-group may not be able to make a recommendation based on the results of the analysis work if the input data was not available to them.

Page 22: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Other Issues

Page 23: Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP

Other issues• Offshore TO/DNO/GBSO Interface

– Sub-group is concerned by the possible implications on the security of an offshore transmission network connected to the onshore transmission network via a distribution network.

– Particular concern relates to differences between the design standards applicable to transmission and distribution networks.

– Sub-group will investigate and provide feedback to OTEG• HVDC

– Sub-group is considering DC connection options as part of the cost benefit analysis work

• Paralleling main onshore GB transmission network through offshore transmission network– The subgroup is un-aware of any proposed windfarm connection that

will parallel any nodes of the GB transmission system.• Islands

– National Grid currently developing Commercial Charging arrangements for Islands connections. Sub group work to concentrate on establishing optimum offshore network technical solution with any commercial arrangements to follow.