revision of qualification procedures for high voltage and extra high
TRANSCRIPT
![Page 1: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/1.jpg)
2/5/2010 1
Revision of Qualification Procedures for High Voltage and Extra High Voltage AC Extruded Underground Cable Systems
Tutorial vor the ICC Educational Session on November 11 2009 in
Scottsdale, AZby Wim Boone
![Page 2: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/2.jpg)
2/5/2010 2
Table of contents Introduction Long duration test EHV (150-500kV) Extension of prequalification test (EQ) Long duration test HV (30-150kV) Functional Analysis Conclusions
![Page 3: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/3.jpg)
2/5/2010 3
Introduction Innovative changes are necessary to improve
the product, to remain competitive There is little incentive for the manufacturer
to make improvements, if the expensive long term testing has to be repeated
CIGRE WG B1-06 was asked to provide recommendations to qualify a modification to a cable system, without making the full set of tests, which are currently specified in standards
WG B1-06 has published Technical Brochure 303 in 2006
![Page 4: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/4.jpg)
2/5/2010 4
Terms of reference WG B1-06 AC extruded cables 30-500 kV- Review and complete qualification procedures (type
tests, PQ tests)- Prepare innovative solutions, without jeopardizing the
system reliability- Evaluate whether present long term tests can be
replaced by shorter ones- Examine if a modification to a cables system can be
qualified without making the full set of tests- The conclusions have been offered to IEC for
further standardisation
![Page 5: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/5.jpg)
Reference standards IEC 62067, October 2001,Power cables with
extruded insulation and their accessories for rated voltages above 150 kV (Um=170kV) up to 500 kV (Um=550kV)-Test methods and requirements
IEC 60840, April 2004,Power cables with extruded insulation and their accessories for rated voltages above 30 kV (Um=36kV) up to 150 kV (Um=170 kV)-Test methods and requirements
![Page 6: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/6.jpg)
2/5/2010 6
PQ tests Focus on PQ tests, because of costs and time PQ test recommended by CIGRE and
incorporated in IEC 62067 Only those manufacturers whose products
have passed the PQ tests have been allowed to participate in subsequent EHV cable projects
![Page 7: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/7.jpg)
2/5/2010 7
Experience with HV cable syst. In general experience is good A new generation HV XLPE cables “slim
design” is developed with similar technology and higher operating stresses, as high as EHV XLPE cables
The experience with slim design HV cables is still limited
![Page 8: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/8.jpg)
2/5/2010 8
Experience with EHV cable syst.
For more details (see tutorial on service experience)
XLPE cable is at present preferred transmission type cable (availability, leakage)
Experience with EHV XLPE cable is still limited, althoughapplication of EHV XLPE cable is fast growing
(see next table)
![Page 9: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/9.jpg)
2/5/2010 9
Application of EHV extruded cable systems . Country Rated
Voltage /kV
Conductor size/mm²
Route lengths/km
Commissionning year
Denmark(Copenhagen:South
400 1600 Cu 22 1997
Denmark(Copenhagen:North
400 1600 Cu 12 1999
Germany (Berlin/ BEWAG 400 1600 Cu 6.3 1998
Germany(Berlin/ BEWAG 400 1600 Cu 5.5 2000
Japan (Tokyo) 500 2500 Cu 39.8 2000
UAE (Abu Dhabi) 400 800 Cu 1.3 2000
Spain (Madrid) 400 2500 Cu 12.8 2004
Denmark (Jutland) 400 1200 Al 14.5 2004
United kingdom (London) 400 2500 Cu 20 2005
The Netherlands (R’dam) 400 1600 Cu 2.25 2005
Austria (Wienstrom) 380 1200 Cu 5.2 2005
![Page 10: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/10.jpg)
2/5/2010 10
Long duration test EHV cable systems Long duration test=PQ test was introduced to
compensate for lack of experience with EHV XLPE cables
The PQ tests checks the performance under realistic conditions:
- Design concept- Long term performance (heat cycling
+overvoltage)- Installation aspects
![Page 11: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/11.jpg)
2/5/2010 11
Long duration test PQ test shows in particular critical position of
the joints; impulse test at the end of the test Although manufacturers are learning from
problems in early PQ tests results , PQ test is considered to be necessary
![Page 12: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/12.jpg)
2/5/2010 12
Main items of PQ test to be considered for revision
Range of approval in relation with calculated nominal stresses
The duration of heating cycle voltage test
PD tests Procedure in case of component failure
during test Final control at the end of the test
![Page 13: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/13.jpg)
2/5/2010 13
Range of approval New PQ test has to be performed in
case of higher system voltage with higher insulation screen stress than in the qualified system
![Page 14: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/14.jpg)
2/5/2010
Heating cycle test The duration of the voltage application (1.7
Uo) is an important factor because of accessory failures
At present the duration is 180 heat cycles (8/16) up to 95 gr.C max.(with large conductor and installed in the soil 1 cycle takes more than 1 day)
The duration of the voltage application should remain 1 year=8760h
![Page 15: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/15.jpg)
2/5/2010 15
PD tests Reduction of insulation thickness may result in
considerable higher stress at defects, voids, fissures, increasing risk of PD activity
Consequently the size of defects has to be reduced accordingly
PD tests are therefore a necessary tool as an early warning for degradation and subsequent failure
![Page 16: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/16.jpg)
2/5/2010 16
System component failure Repair/replacement of a failed accessory
during test is allowed
Repair of cable failure is not allowed, unless failure has been caused by external incident or the cable has already been prequalified
![Page 17: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/17.jpg)
2/5/2010 17
Final control test After the test has been completed an impulse test
has to be performed on the whole test loop The whole test loop has to
do with the desirability to check the insulating properties at the interfacesin the accessories and the cable.
An impulse test on the cable only, as was done in the past, is not sufficient
![Page 18: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/18.jpg)
2/5/2010 18
Changes in a prequalified system
What changes are “substantial” in such a way that the PQ test has to be repeated?
Functional Analysis Method correlates the function performed by a certain item to the test required to check that function.
![Page 19: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/19.jpg)
2/5/2010 19
Changes in a prequalified syst.(2)
Some small changes do not require the repetition of a full PQ
Some major changes require the repetition of the full PQ test
Some changes require the performance of a simplified long term-test, called Extension of Prequalification test (EQ)
![Page 20: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/20.jpg)
2/5/2010 20
Situations of changes in a prequalified system
The exchange of components (cable or accessories), already prequalified in systems from different manufactures or from different plants from the same manufacturer
The modification to cable components The modification to accessory
components within the same family
![Page 21: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/21.jpg)
2/5/2010 21
Evaluation of changes in a prequalified system
.
Cableand/oraccessory
Already qualified on another cable system within the same or higherinsulation screen stress
Already qualified on another cable system with a lower insulation screen stress (calculated) or not qualified
cable non electrical Type Test(TT) + Extension ofqualification test (EQ)
electrical and nonelectrical TT +Prequalification Test (PQ)
Joint EQ TT + PQMetalenclosedTermination
EQ TT + PQ
OutdoorTermination
EQ TT+PQ
![Page 22: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/22.jpg)
2/5/2010 22
Tests because of modifications to a cable in a prequalified EHV cable systemComponent Modification Proposed
testConductor Copper to Aluminium
Larger cross-sectionTT and PQTT
Insulation Change of base resinChange in cross linking package(peroxide/antioxidant)Nature of polymer (XLPE, LDPE, HDPE, EPR)Higher conductor stress, no increase ofinsulation screen stressIncrease of insulation screen stressNew extrusion line or transfer of extrusionline with earlier experience in-houseNew extrusion line, or transfer of extrusionline without earlier experience
TTTT
TT and PQTT
TT and PQTT
TT and PQ
![Page 23: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/23.jpg)
Component Type of modification Proposed test
Joint Higher calculated electrical stress design and construction Compound of main insulation body Changing nature of polymer, (EPR, Silicone….)Material of semi-con electrodesFixation of cable ends on either side of the joint
EQ
PQ
EQ
EQEQ
Tests because of modifications to an accessory within the same family in a prequalified EHV cable system
![Page 24: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/24.jpg)
2/5/2010 24
Principles of the Extension of PQ test (EQ)
60 thermal cycles witout voltage 20 cycles with 2Uo+PD+hot impulse test The 60 daily cycles + 20 cycles are intended
to allow relaxation of mechanical stresses trapped in the cable during manufacture, resulting in retraction of the XLPE insulation
The retraction of the cable insulation within an accessory can initiate PD activity
![Page 25: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/25.jpg)
2/5/2010 25
Retraction of XLPE insulation and PE oversheath. .
-5.0
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
0 10 20 30 40 50 60 70 80
Number of heat cycles
Retra
ction
(mm)
Retraction of oversheath
Retraction of insulation
Evolution of the retraction
In addition the heat cycles are producing a radial expansion and retraction of the cable insulationand of the accessory components that can also influence the interfacial pressure in accessories.
![Page 26: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/26.jpg)
2/5/2010 26
Recommendations to IEC 62067 New cable systems:- Maintain 1 year PQ test- Allow in case of an accessory failure the
continuation and completion of the PQ test for the undisturbed component
- Perform PD tests during PQ test- Perform impulse test at the end of the test on
the complete test loop- Maintain unchanged present range of TT and
PQ approval
![Page 27: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/27.jpg)
2/5/2010 27
Recommendations to IEC 62067
Exchange of a prequalified component:- Introduce a simplified long term test of
60+20 cycles in case of exchange of prequalified components with other components or in case of less significant modifications of cable or accessory
![Page 28: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/28.jpg)
2/5/2010 28
Long duration test HV cable systems
Traditionally EHV cables are operating at higher stresses than HV cables
Due to good experience with EHV cables, HV cables are being produced with reduced insulation thickness (slim design)
Higher stresses at main insulation and at interfaces between cables and accessories
![Page 29: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/29.jpg)
2/5/2010 29
Increase of Electric stress with system voltage
1
10
100
10 100 1000
Voltage level (kV)
Wor
king
str
ess
(kV
/mm
)
Impulse stresses
AC stresses
![Page 30: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/30.jpg)
2/5/2010 30
Arguments pro Long term test High electric stresses increase failure risk Shrinkage is only stabilized after 80 cycles New accessory
designs are coming Failures in high
stress cables
![Page 31: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/31.jpg)
2/5/2010 31
Arguments against long term test
Many manufacturers have good experience so far
Reluctance of some utilities, to test entire syst. if they buy their HV cables and accessories separately
Longterm test is costly
![Page 32: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/32.jpg)
2/5/2010 32
Range of PQ test For prefabricated joints , mainly impulse
stresses at the cable interface are critical For taped or field-molded joints also AC and
impulse stresses at the conductor are critical Therefore the PQ test is recommended for
cable systems with conductor stresses higher than 8kV/mm and insulation screen stresses above 4 kV/mm
![Page 33: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/33.jpg)
2/5/2010 33
Recommendations to IEC 60840
Intoduce the following PQ test: Voltage, 1.7 Uo 180 heating cycles, to max. 95 degr C Cooling to ambient PD tests Impulse test on the complete loop Examination of the test loop
![Page 34: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/34.jpg)
2/5/2010 34
Exchanges and modifications The procedure and the sequence of EQ
tests are the same as for the EHV cable systems
![Page 35: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/35.jpg)
2/5/2010 35
Functional Analysis International standards are necessary for
both manufacturers and customers An advantage of International standards is
the world wide acceptance of the test evidence
A disadvantage of international standards is the limited incentive of manufacturers to make incremental improvements, as this requires a complete repetition of the type testing
![Page 36: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/36.jpg)
Functional Analysis (2) According to IEC 62067 the PQ test
need to be repeated in case of “substantial” changes
There is no agreed method to decide what is substantial
![Page 37: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/37.jpg)
2/5/2010 37
Functional Analysis (3) In the Functional Analysis method a process
is developed, where the significance of a change can be evaluated and the need for further testing agreed:
- PQ test- EQ test- Type test- Other test
![Page 38: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/38.jpg)
2/5/2010 38
Functional Analysis Method Consider the functions performed by
each part of a cable or accessory construction and indicate how each function is tested
Consider a number of possible changes that can be made and indicate what additional testing might be required
![Page 39: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/39.jpg)
2/5/2010 39
Functional Analysis Tables Table for cable
components Table for Joint
components Table for Termination
components
![Page 40: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/40.jpg)
2/5/2010 40
Functional Analysis TableStructure of the table with 5 columns: Component Function Specification/threat Test to ckeck the functionality Comments
![Page 41: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/41.jpg)
2/5/2010 41
Cable components Conductor Inner semiconducting screen Insulation Outer semiconducting screen Longitudinal water tight layer Metal screen Oversheath
![Page 42: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/42.jpg)
2/5/2010 42
Functions/properties Electrical conductivity (conductor, screen) Dielectric properties (insulation, oversheath) Mechanical properties Thermal-mechanical properties Chemical properties Interfaces with other components Watertightness Overall properties
![Page 43: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/43.jpg)
2/5/2010 43
Threat for function of conductor Overheating Mechanical deformation due to bending or
pulling during installation Corrosion
High interface resistance with connectors Thermal-mechanical expansion Water penetration
![Page 44: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/44.jpg)
2/5/2010 44
Functional AnalysisFunctional Analysis of a High Voltage Cable and cable components
(Example)
Cable component
Function orProperty
Specification/Threat
Test to check thefunctionality
Comments
A B C D E
Conductor ElectricalConduct.
a.Nooverheatingwith nominalcurrent
-b. Limit temperature with thermal short circuit current
a.Resistancemeasurement
-b. Calculation ofthermal shortcircuit temperature
a For largeconductors ACresistance test shouldbe performed as typetestb. If temperature riseis considereddangerous, a shortcircuit test isproposed as adevelopment test.
![Page 45: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/45.jpg)
2/5/2010 45
Tests not in IEC Short circuit test Examination of XLPE cable insulation in hot oil Examination of protrusions and decontaminants Moisture content in semicon layers Grain size measurement on lead sheath Fatigue test of lead sheath Side wall pressure test on cable Mechanical impact on oversheath Compatibility test of additives and filling material with
cable and accessory material
![Page 46: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/46.jpg)
2/5/2010 46
Conclusions EHV Cable systems:- Maintain PQ test of 1 year- Continuation of PQ test in case of
accessory failure- Impulse test on complete loop- Introduce EQ test mainly in case of
changes of or in accessories: 80 heat cycles, of which 20 will be with 2Uo
![Page 47: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/47.jpg)
2/5/2010 47
Conclusions (2) HV cable systems:- Introduce PQ test of 0.5 year for high
stress cables (8/4 kV/mm)- Continue test in case of accessory
failure during test- Impulse test on complete loop- EQ test for changes/modifications at
components, the same as for EHV
![Page 48: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/48.jpg)
2/5/2010 48
Conclusions (3) Funtional analysis- FA method is recommended to assess
the significance of changes and the selection of related tests
- Lists are made available with appropriate tests in case of changes
- Not only standardized tests but also development tests are being used
![Page 49: Revision of qualification procedures for high voltage and extra high](https://reader038.vdocuments.net/reader038/viewer/2022103106/586ccd4b1a28abd7608be743/html5/thumbnails/49.jpg)
2/5/2010 49
End of presentation Thank you for your attention