![Page 1: Richfield Public Schools - ISD #280...Planned for the week ending July 27, 2018: Schematic Design/Design Development documents to continue. Schematic Design estimate to be finalized](https://reader034.vdocuments.net/reader034/viewer/2022042414/5f2eda64a0113066875278be/html5/thumbnails/1.jpg)
Richfield Public Schools - ISD #280
Weekly Update
July 20, 2018
Page 1 of 2
District Wide
Completed for the week ending July 20, 2018:
� Pilot classroom furniture selections were finalized at the vendor’s showroom.
Planned for the week ending July 27, 2018:
� Estimates on Central, RDLS and RSTEM to be discussed at the Project Oversight Committee
meeting on Wednesday.
Richfield High School
Completed for the week ending July 20, 2018:
� Schematic Design documents estimates continue to be worked on.
� User group meetings continue in select areas.
� Art room cabinetry demolition took place.
� Security monitoring system meeting was held on Thursday.
� Pilot classrooms were finalized and furniture selections were made.
Planned for the week ending July 27, 2018:
� Design Development documents are underway by the Design Team
� Schematic Design estimates continue to be worked on.
� Security monitoring system options to be developed by the vendor met with.
RDLS Elementary
Completed for the week ending July 20, 2018:
� Schematic Design Documents continue being reviewed by IEA for abatement
coordination.
� SD Estimate review continued with Wold and ICS for presentation at POC next week
� Playground ribbon cutting ceremony held! See picture below.
Planned for the week ending July 27, 2018:
� Schematic Design documents estimate to be presented at POC on Wednesday.
� Design Development documents continue to be worked on.
![Page 2: Richfield Public Schools - ISD #280...Planned for the week ending July 27, 2018: Schematic Design/Design Development documents to continue. Schematic Design estimate to be finalized](https://reader034.vdocuments.net/reader034/viewer/2022042414/5f2eda64a0113066875278be/html5/thumbnails/2.jpg)
Richfield Public Schools - ISD #280
Weekly Update
July 20, 2018
Page 2 of 2
Central Education
Completed for the week ending July 20, 2018:
� Revised Schematic Design/Design Development documents continue to be formatted
based on the review of the building utilization meeting discussions.
� Schematic Design Estimate has been reviewed and is ready to present at POC on
Wednesday.
Planned for the week ending July 27, 2018:
� Schematic Design/Design Development documents to continue.
� Schematic Design estimate to be finalized for presentation to the POC on July 25th.
R-STEM Elementary
Completed for the week ending July 20, 2018:
� Schematic Design Documents continue being reviewed by IEA for abatement
coordination.
� SD Estimate review continued with Wold and ICS for presentation at POC next week
� Interior 3rd floor door and hardware installed.
Planned for the week ending July 27, 2018:
� Design Development documents continue to be worked on by the design team.
RDLS PLAYGROUND RIBBON CUTTING