rick here is a preliminary version of our presentation to ... · rick here is a preliminary version...
TRANSCRIPT
1
PrairieIslandNPEm Resource
From: Eckholt, Gene F. [[email protected]]Sent: Friday, November 06, 2009 10:15 AMTo: Plasse, RichardSubject: Draft Prairie Island ACRS Full Committee PresentationAttachments: ACRS Full Committee Presentation - NRC Draft 11-6-09.pdf
Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change and refinement as we go through our dry run process. Let me know if you have any questions. Gene Eckholt Project Manager License Renewal Project Prairie Island Nuclear Generating Plant Phone: 651-388-1121 ext. 4137
Hearing Identifier: Prairie_Island_NonPublic Email Number: 1105 Mail Envelope Properties (71AC1869DEB82E47AAC75C450F60546A0BEAD6A322) Subject: Draft Prairie Island ACRS Full Committee Presentation Sent Date: 11/6/2009 10:14:57 AM Received Date: 11/6/2009 10:18:38 AM From: Eckholt, Gene F. Created By: [email protected] Recipients: "Plasse, Richard" <[email protected]> Tracking Status: None Post Office: enex04 Files Size Date & Time MESSAGE 352 11/6/2009 10:18:38 AM ACRS Full Committee Presentation - NRC Draft 11-6-09.pdf 1045347 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:
1
Prairie Island Nuclear Generating PlantACRS License Renewal Meeting
December 3, 2009
2
Introductions
Mark Schimmel – Site Vice PresidentGene Eckholt – License Renewal Project ManagerSteve Skoyen – Engineering Programs ManagerLicense Renewal Project Team and Subject Matter Experts
3
Agenda
IntroductionsBackgroundACRS LR Subcommittee Follow-Up Items
Refueling Cavity LeakageUnderground Medium Voltage CablesCondensate Storage Tank Examinations
Questions
4
Background
Plant Owner and OperatorNorthern States Power Company – MinnesotaSubsidiary of Xcel Energy
LocationSE of Minneapolis-Saint Paul, MNOn Mississippi River
5
Background
Construction Permits Issued - June 1968Operating Licenses Issued
Unit 1 - August 1973Unit 2 - October 1974
LRA Submitted – April 2008
6
Background
Two 2 - Loop PWR Units1650 MWt575 MWe (Gross) per Unit
Westinghouse - NSSS Pioneer Service & Engineering -Architect/EngineerOnce-Through Cooling Supplemented with Four Forced Draft Cooling Towers (Seasonal)Ultimate Heat Sink is Mississippi River via Cooling Water System
7
Background
Containment DesignSteel Containment Vessel
1-1/2 inch Thick Bottom Head, 1-1/2 inch Thick Shell, 3/4 inch Thick Top Head3-1/2 inch Thick at ECCS Sump (Sump B) PenetrationsSA-516-70 Low Temperature Carbon Steel
Provides Primary Containment Lower Head Encased in Concrete5 foot Annular Gap Between Containment Vessel and Limited Leakage Reinforced Concrete Shield Building
ContainmentElevation
8
ACRS LR Subcommittee Follow-Up Items
Refueling Cavity Leakage
Underground Medium Voltage CablesCondensate Storage Tank Examinations
9
Refueling Cavity LeakageBackground
Intermittent Refueling Cavity Leakage Indications in Both Units Since Late 1980s Leak Rate of 1-2 Gallons per HourSeen in ECCS Sump and Regenerative Heat Exchanger RoomSealing Methods Have Stopped Leakage, but not Consistently
Refueling Cavity Leakage Path
Cavity Photo Overhead
Cavity Photo from NW
Leakage Seen in ECCS Sump and in Regenerative HX Room (below cavity)
ContainmentElevation
11
Refueling Cavity LeakageLeak Locations
Root Cause Evaluation was Completed in April of 2009Sources of Leakage were Determined to be Embedment Plates for Reactor Vessel Internals Stands and Rod Control Cluster Assembly (RCCA) Change Fixture
12
Refueling Cavity LeakageLeak Locations
Typical Reactor Vessel Internals Stand Support Typical RCCA Change Fixture Support
13
Refueling Cavity LeakageRepair Method
Existing 1/4" thk stainless steel cavity liner
New seal weld between baseplate and embedment plate.
Existing cavity liner fillet weld to embedment plateExisting seal weld to
embedment plate not accessible. Failure of weld would result in leak.
Replace existing nuts with fabricated blind nuts seal welded to baseplate.
Side View
14
Refueling Cavity LeakageFall 2009 Unit 1 Repairs
Reactor Vessel Internals Stands and RCCA Change Fixture Embedment Plates Repaired
Existing Nuts RemovedReplaced with Blind Nuts Blind Nuts Seal Welded to BaseplateSeal Weld Applied Between Baseplate and Embedment PlateWelds Examined by NDE
15
Refueling Cavity LeakageFall 2009 Unit 1 Repairs
16
Refueling Cavity LeakageFall 2009 Unit 1 Repair Results
Embedment Plate Repairs Eliminated that Leakage SourceECCS Sump
No Evidence of LeakageMinor Leakage from Regenerative Heat Exchanger Room Ceiling
Appeared After Cavity Flooded 14 DaysEstimated to be 0.05 Gallons per Hour
No Evidence Leakage is Reaching Containment Vessel
17
Refueling Cavity LeakageFall 2009 Unit 1 Testing and Evaluation
Vacuum Box Testing of Reactor Cavity Liner Plate Seam Welds - No Leakage IdentifiedNDE of Fuel Transfer Tube Welds – No IndicationsEvaluation of Other Possible Leakage Sources
NDE of Liner to Embedment Plate Fillet WeldsOne Porosity IndicationWill be Repaired During Next Unit 1 Refueling Outage
RCCA Guide Box Embedment Plates
18
Refueling Cavity Leakage2010 Unit 2 Corrective Actions
Repair of Reactor Vessel Internals Stands and RCCA Change Fixture Embedment PlatesRepair of RCCA Guide Box Embedment PlatesNDE of Fuel Transfer Tube WeldsVacuum Box Testing of Reactor Cavity Liner Plate Seam WeldsNDE of Liner to Embedment Plate Fillet Welds Other Repairs and Testing Resulting From Evaluation of 2009 Unit 1 Leakage
19
Refueling Cavity Leakage2011 Unit 1 Corrective Actions
Repair of RCCA Guide Box Embedment PlatesRepair of Liner to Embedment Plate Fillet Weld Porosity Indication Other Repairs and Testing Resulting From Evaluation of 2009 Unit 1 and 2010 Unit 2 Repair Results
20
Refueling Cavity LeakageMonitoring & Assessment
Ultrasonic and Visual Examinations of Containment Vessel
Unit 1 and 2 ECCS Sumps (Prior to 2009)Grout RemovedWall Thickness Measurements at or Above NominalNo Corrosion Identified.
Unit 1 ECCS Sump (Fall 2009)Grout RemovedWall Thickness Measurements at or Above NominalNo Corrosion of Rebar or Containment VesselNo Wet Areas or Leakage
Sump Section
Annulus Photo
ContainmentElevation
21
Refueling Cavity LeakageMonitoring & Assessment
Unit 1 ECCS Sump Fall 2009
22
Refueling Cavity LeakageMonitoring & Assessment
Ultrasonic and Visual Examinations of Containment Vessel (cont’d)
Unit 2 Annulus (2008)144 Wall Thickness MeasurementsAll Measurements at or Above Nominal
Unit 1 Annulus (2009)80 Wall Thickness Measurements 79 Locations at or Above NominalOne Location Below Nominal 1.5" thickness at 1.492"
23
Refueling Cavity LeakageMonitoring & Assessment – Commitments
Removal of Concrete from Sump Below Reactor Vessel to Expose Containment Vessel
Next Outages Following Refueling Cavity RepairsInspect (VT and UT) Containment Vessel Petrographic Examination of Removed Concrete Evacuate any Water Observed
ContainmentElevation
24
Refueling Cavity LeakageMonitoring & Assessment – Commitments
Removal of Concrete Sample Wetted by Borated Water Leakage from Refueling Cavity
Concrete will be Tested For Compression Strength and will Undergo Petrographic Examination
Monitor Areas Previously Exhibiting Leakage for Next Two Outages After Repairs to Confirm That Leakage has not Recurred
25
Refueling Cavity LeakageLong Term Aging Management
Continue to Manage Aging of the Containment Structures and Vessel Using the Structures Monitoring Program and ASME Section XI, Subsection IWE Program Utilize Corrective Action Program for Evaluation and Correction of New Issues
26
Refueling Cavity LeakageEvaluation of Potential Degradation
Evaluations have been performed for potential degradation of Steel Containment Vessel, Concrete and RebarEvaluations Concluded:
Containment Vessel Corrosion Behind Concrete in Areas Wetted by Refueling Cavity Leakage is Expected to be MinorNo Significant Effect on Reinforced Concrete That Has Been Wetted by Refueling Cavity Leakage
27
Underground Medium Voltage CablesManhole Inspection
ACRS LR Subcommittee Questioned Adequacy of Two Year Manhole Inspection FrequencyInspection Frequency is Based on Actual Plant Experience, but not to Exceed Every Two YearsConsistent with GALL XI.E3One Manhole in Scope of License RenewalMultiple Inspections Since September of 2007 Have Shown no Signs of Water Intrusion or Accumulation
28
Underground Medium Voltage CablesManhole Inspection
Design Precludes Water AccumulationFloor of Gravel and SandApproximately Ten Feet Above Water TableGrade Around Manhole Precludes Significant Rain Water Intrusion
Based on Manhole Design and Actual Plant Experience, Two Year Inspection Frequency is Considered Sufficient
29
Underground Medium Voltage CablesImpact of Freeze/Thaw Conditions
Prairie Island Operating Experience was Reviewed for Evidence of Accelerated Cable Insulation Aging Related to Freeze/Thaw ConditionsThe Following Organizations were also Contacted:
Monticello Nuclear Generating PlantXcel Energy DistributionEPRINEI License Renewal Electrical Working Group
Accelerated Cable Insulation Aging Related to Freeze/Thaw Conditions has not Been Identified as an Issue
30
Condensate Storage Tank Examinations
Aboveground Steel Tanks Program Included UT Inspection of the Bottom of 1 of the 3 Condensate Storage Tanks Prior to PEOACRS LR Subcommittee Felt That Inspection of Only 1 Tank to Assure Acceptability of all 3 Tanks was not Adequately SupportedLRA Change Submitted on August 7, 2009 Which Revised the Aboveground Steel Tanks Program to Include UT Inspection of the Bottom of all 3 Condensate Storage Tanks Prior to PEO
31
Questions?
32
Supporting Slides
33
34
Refueling Cavity LeakagePath
Path to ECCS SumpUnder Refueling Cavity Liner Through Construction Joint Between Floor of Transfer Pit and Wall Behind Fuel Transfer Tube to Inner Wall of Containment VesselTravels Down and Horizontally, Between Containment Vessel and Concrete, to Low Point of Containment Vessel Bottom HeadSeeps Through Grout in ECCS Sump
Path to Regenerative Heat Exchanger RoomOnce Under Liner, Follows Cracks in the Concrete, Seeping Through the Ceiling and Walls of the Regenerative HX Room
ECCS Sump
35
Origin
ECCSSumpSump C
Fuel Transfer Tube
Regen HX Room
Leak Paths ECCS Sump
36
ECCS Sump Showing Grout
To 33 (Cont. 3D)
To 34 Insp.
37
Shield Building Annulus
38
Plant Electrical Distribution
X
1R
CT12
2R 1CT
161kV 13.8kV (#10)345kV TransmissionSystem
PlantSystem
Cooling Tower
CT11
2RX2RY
IntakeScreenHouse
Unit 2 Unit 1 Cooling Tower Substation
Switchyard Fence
Y
345kV
13.8kV
Non-Safety Related Buses
4kVSafety
Related
4kV
34.5kV
PINGP CLB Scope Expanded LR Scope per Proposed ISG 2008-01
39
Switchyard Scoping Boundary
1R(U1)
CT12(U2)
IntakeScreenHouse
TrainingCenter
2R(U2)
Gen(U1)
1CT(U1)
SpringCreek
ByronRedRock
1
Gen(U2)
BlueLake
RedRock
2
161kV 13.8kV
345kV
Bus 1
Bus 2
#10
TransmissionSystem
PlantSystem
PINGP CLB Scope Expanded LR Scope per Proposed ISG 2008-01
Distribution