rick here is a preliminary version of our presentation to ... · rick here is a preliminary version...

41
1 PrairieIslandNPEm Resource From: Eckholt, Gene F. [[email protected]] Sent: Friday, November 06, 2009 10:15 AM To: Plasse, Richard Subject: Draft Prairie Island ACRS Full Committee Presentation Attachments: ACRS Full Committee Presentation - NRC Draft 11-6-09.pdf Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change and refinement as we go through our dry run process. Let me know if you have any questions. Gene Eckholt Project Manager License Renewal Project Prairie Island Nuclear Generating Plant Phone: 651-388-1121 ext. 4137

Upload: others

Post on 17-May-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

1

PrairieIslandNPEm Resource

From: Eckholt, Gene F. [[email protected]]Sent: Friday, November 06, 2009 10:15 AMTo: Plasse, RichardSubject: Draft Prairie Island ACRS Full Committee PresentationAttachments: ACRS Full Committee Presentation - NRC Draft 11-6-09.pdf

Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change and refinement as we go through our dry run process. Let me know if you have any questions. Gene Eckholt Project Manager License Renewal Project Prairie Island Nuclear Generating Plant Phone: 651-388-1121 ext. 4137

Page 2: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

Hearing Identifier: Prairie_Island_NonPublic Email Number: 1105 Mail Envelope Properties (71AC1869DEB82E47AAC75C450F60546A0BEAD6A322) Subject: Draft Prairie Island ACRS Full Committee Presentation Sent Date: 11/6/2009 10:14:57 AM Received Date: 11/6/2009 10:18:38 AM From: Eckholt, Gene F. Created By: [email protected] Recipients: "Plasse, Richard" <[email protected]> Tracking Status: None Post Office: enex04 Files Size Date & Time MESSAGE 352 11/6/2009 10:18:38 AM ACRS Full Committee Presentation - NRC Draft 11-6-09.pdf 1045347 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:

Page 3: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

1

Prairie Island Nuclear Generating PlantACRS License Renewal Meeting

December 3, 2009

Page 4: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

2

Introductions

Mark Schimmel – Site Vice PresidentGene Eckholt – License Renewal Project ManagerSteve Skoyen – Engineering Programs ManagerLicense Renewal Project Team and Subject Matter Experts

Page 5: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

3

Agenda

IntroductionsBackgroundACRS LR Subcommittee Follow-Up Items

Refueling Cavity LeakageUnderground Medium Voltage CablesCondensate Storage Tank Examinations

Questions

Page 6: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

4

Background

Plant Owner and OperatorNorthern States Power Company – MinnesotaSubsidiary of Xcel Energy

LocationSE of Minneapolis-Saint Paul, MNOn Mississippi River

Page 7: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

5

Background

Construction Permits Issued - June 1968Operating Licenses Issued

Unit 1 - August 1973Unit 2 - October 1974

LRA Submitted – April 2008

Page 8: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

6

Background

Two 2 - Loop PWR Units1650 MWt575 MWe (Gross) per Unit

Westinghouse - NSSS Pioneer Service & Engineering -Architect/EngineerOnce-Through Cooling Supplemented with Four Forced Draft Cooling Towers (Seasonal)Ultimate Heat Sink is Mississippi River via Cooling Water System

Page 9: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

7

Background

Containment DesignSteel Containment Vessel

1-1/2 inch Thick Bottom Head, 1-1/2 inch Thick Shell, 3/4 inch Thick Top Head3-1/2 inch Thick at ECCS Sump (Sump B) PenetrationsSA-516-70 Low Temperature Carbon Steel

Provides Primary Containment Lower Head Encased in Concrete5 foot Annular Gap Between Containment Vessel and Limited Leakage Reinforced Concrete Shield Building

ContainmentElevation

Page 10: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

8

ACRS LR Subcommittee Follow-Up Items

Refueling Cavity Leakage

Underground Medium Voltage CablesCondensate Storage Tank Examinations

Page 11: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

9

Refueling Cavity LeakageBackground

Intermittent Refueling Cavity Leakage Indications in Both Units Since Late 1980s Leak Rate of 1-2 Gallons per HourSeen in ECCS Sump and Regenerative Heat Exchanger RoomSealing Methods Have Stopped Leakage, but not Consistently

Page 12: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

Refueling Cavity Leakage Path

Cavity Photo Overhead

Cavity Photo from NW

Leakage Seen in ECCS Sump and in Regenerative HX Room (below cavity)

ContainmentElevation

Page 13: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

11

Refueling Cavity LeakageLeak Locations

Root Cause Evaluation was Completed in April of 2009Sources of Leakage were Determined to be Embedment Plates for Reactor Vessel Internals Stands and Rod Control Cluster Assembly (RCCA) Change Fixture

Page 14: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

12

Refueling Cavity LeakageLeak Locations

Typical Reactor Vessel Internals Stand Support Typical RCCA Change Fixture Support

Page 15: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

13

Refueling Cavity LeakageRepair Method

Existing 1/4" thk stainless steel cavity liner

New seal weld between baseplate and embedment plate.

Existing cavity liner fillet weld to embedment plateExisting seal weld to

embedment plate not accessible. Failure of weld would result in leak.

Replace existing nuts with fabricated blind nuts seal welded to baseplate.

Side View

Page 16: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

14

Refueling Cavity LeakageFall 2009 Unit 1 Repairs

Reactor Vessel Internals Stands and RCCA Change Fixture Embedment Plates Repaired

Existing Nuts RemovedReplaced with Blind Nuts Blind Nuts Seal Welded to BaseplateSeal Weld Applied Between Baseplate and Embedment PlateWelds Examined by NDE

Page 17: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

15

Refueling Cavity LeakageFall 2009 Unit 1 Repairs

Page 18: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

16

Refueling Cavity LeakageFall 2009 Unit 1 Repair Results

Embedment Plate Repairs Eliminated that Leakage SourceECCS Sump

No Evidence of LeakageMinor Leakage from Regenerative Heat Exchanger Room Ceiling

Appeared After Cavity Flooded 14 DaysEstimated to be 0.05 Gallons per Hour

No Evidence Leakage is Reaching Containment Vessel

Page 19: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

17

Refueling Cavity LeakageFall 2009 Unit 1 Testing and Evaluation

Vacuum Box Testing of Reactor Cavity Liner Plate Seam Welds - No Leakage IdentifiedNDE of Fuel Transfer Tube Welds – No IndicationsEvaluation of Other Possible Leakage Sources

NDE of Liner to Embedment Plate Fillet WeldsOne Porosity IndicationWill be Repaired During Next Unit 1 Refueling Outage

RCCA Guide Box Embedment Plates

Page 20: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

18

Refueling Cavity Leakage2010 Unit 2 Corrective Actions

Repair of Reactor Vessel Internals Stands and RCCA Change Fixture Embedment PlatesRepair of RCCA Guide Box Embedment PlatesNDE of Fuel Transfer Tube WeldsVacuum Box Testing of Reactor Cavity Liner Plate Seam WeldsNDE of Liner to Embedment Plate Fillet Welds Other Repairs and Testing Resulting From Evaluation of 2009 Unit 1 Leakage

Page 21: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

19

Refueling Cavity Leakage2011 Unit 1 Corrective Actions

Repair of RCCA Guide Box Embedment PlatesRepair of Liner to Embedment Plate Fillet Weld Porosity Indication Other Repairs and Testing Resulting From Evaluation of 2009 Unit 1 and 2010 Unit 2 Repair Results

Page 22: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

20

Refueling Cavity LeakageMonitoring & Assessment

Ultrasonic and Visual Examinations of Containment Vessel

Unit 1 and 2 ECCS Sumps (Prior to 2009)Grout RemovedWall Thickness Measurements at or Above NominalNo Corrosion Identified.

Unit 1 ECCS Sump (Fall 2009)Grout RemovedWall Thickness Measurements at or Above NominalNo Corrosion of Rebar or Containment VesselNo Wet Areas or Leakage

Sump Section

Annulus Photo

ContainmentElevation

Page 23: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

21

Refueling Cavity LeakageMonitoring & Assessment

Unit 1 ECCS Sump Fall 2009

Page 24: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

22

Refueling Cavity LeakageMonitoring & Assessment

Ultrasonic and Visual Examinations of Containment Vessel (cont’d)

Unit 2 Annulus (2008)144 Wall Thickness MeasurementsAll Measurements at or Above Nominal

Unit 1 Annulus (2009)80 Wall Thickness Measurements 79 Locations at or Above NominalOne Location Below Nominal 1.5" thickness at 1.492"

Page 25: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

23

Refueling Cavity LeakageMonitoring & Assessment – Commitments

Removal of Concrete from Sump Below Reactor Vessel to Expose Containment Vessel

Next Outages Following Refueling Cavity RepairsInspect (VT and UT) Containment Vessel Petrographic Examination of Removed Concrete Evacuate any Water Observed

ContainmentElevation

Page 26: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

24

Refueling Cavity LeakageMonitoring & Assessment – Commitments

Removal of Concrete Sample Wetted by Borated Water Leakage from Refueling Cavity

Concrete will be Tested For Compression Strength and will Undergo Petrographic Examination

Monitor Areas Previously Exhibiting Leakage for Next Two Outages After Repairs to Confirm That Leakage has not Recurred

Page 27: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

25

Refueling Cavity LeakageLong Term Aging Management

Continue to Manage Aging of the Containment Structures and Vessel Using the Structures Monitoring Program and ASME Section XI, Subsection IWE Program Utilize Corrective Action Program for Evaluation and Correction of New Issues

Page 28: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

26

Refueling Cavity LeakageEvaluation of Potential Degradation

Evaluations have been performed for potential degradation of Steel Containment Vessel, Concrete and RebarEvaluations Concluded:

Containment Vessel Corrosion Behind Concrete in Areas Wetted by Refueling Cavity Leakage is Expected to be MinorNo Significant Effect on Reinforced Concrete That Has Been Wetted by Refueling Cavity Leakage

Page 29: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

27

Underground Medium Voltage CablesManhole Inspection

ACRS LR Subcommittee Questioned Adequacy of Two Year Manhole Inspection FrequencyInspection Frequency is Based on Actual Plant Experience, but not to Exceed Every Two YearsConsistent with GALL XI.E3One Manhole in Scope of License RenewalMultiple Inspections Since September of 2007 Have Shown no Signs of Water Intrusion or Accumulation

Page 30: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

28

Underground Medium Voltage CablesManhole Inspection

Design Precludes Water AccumulationFloor of Gravel and SandApproximately Ten Feet Above Water TableGrade Around Manhole Precludes Significant Rain Water Intrusion

Based on Manhole Design and Actual Plant Experience, Two Year Inspection Frequency is Considered Sufficient

Page 31: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

29

Underground Medium Voltage CablesImpact of Freeze/Thaw Conditions

Prairie Island Operating Experience was Reviewed for Evidence of Accelerated Cable Insulation Aging Related to Freeze/Thaw ConditionsThe Following Organizations were also Contacted:

Monticello Nuclear Generating PlantXcel Energy DistributionEPRINEI License Renewal Electrical Working Group

Accelerated Cable Insulation Aging Related to Freeze/Thaw Conditions has not Been Identified as an Issue

Page 32: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

30

Condensate Storage Tank Examinations

Aboveground Steel Tanks Program Included UT Inspection of the Bottom of 1 of the 3 Condensate Storage Tanks Prior to PEOACRS LR Subcommittee Felt That Inspection of Only 1 Tank to Assure Acceptability of all 3 Tanks was not Adequately SupportedLRA Change Submitted on August 7, 2009 Which Revised the Aboveground Steel Tanks Program to Include UT Inspection of the Bottom of all 3 Condensate Storage Tanks Prior to PEO

Page 33: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

31

Questions?

Page 34: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

32

Supporting Slides

Page 35: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

33

Page 36: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

34

Refueling Cavity LeakagePath

Path to ECCS SumpUnder Refueling Cavity Liner Through Construction Joint Between Floor of Transfer Pit and Wall Behind Fuel Transfer Tube to Inner Wall of Containment VesselTravels Down and Horizontally, Between Containment Vessel and Concrete, to Low Point of Containment Vessel Bottom HeadSeeps Through Grout in ECCS Sump

Path to Regenerative Heat Exchanger RoomOnce Under Liner, Follows Cracks in the Concrete, Seeping Through the Ceiling and Walls of the Regenerative HX Room

ECCS Sump

Page 37: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

35

Origin

ECCSSumpSump C

Fuel Transfer Tube

Regen HX Room

Leak Paths ECCS Sump

Page 38: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

36

ECCS Sump Showing Grout

To 33 (Cont. 3D)

To 34 Insp.

Page 39: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

37

Shield Building Annulus

Page 40: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

38

Plant Electrical Distribution

X

1R

CT12

2R 1CT

161kV 13.8kV (#10)345kV TransmissionSystem

PlantSystem

Cooling Tower

CT11

2RX2RY

IntakeScreenHouse

Unit 2 Unit 1 Cooling Tower Substation

Switchyard Fence

Y

345kV

13.8kV

Non-Safety Related Buses

4kVSafety

Related

4kV

34.5kV

PINGP CLB Scope Expanded LR Scope per Proposed ISG 2008-01

Page 41: Rick Here is a preliminary version of our presentation to ... · Rick Here is a preliminary version of our presentation to the full ACRS. This document is still subject to change

39

Switchyard Scoping Boundary

1R(U1)

CT12(U2)

IntakeScreenHouse

TrainingCenter

2R(U2)

Gen(U1)

1CT(U1)

SpringCreek

ByronRedRock

1

Gen(U2)

BlueLake

RedRock

2

161kV 13.8kV

345kV

Bus 1

Bus 2

#10

TransmissionSystem

PlantSystem

PINGP CLB Scope Expanded LR Scope per Proposed ISG 2008-01

Distribution