Page 1: Rio oil and gas   peregrino field development

1 - Classification: Internal 2010-09-13

Peregrino Development Project

Rio Oil and Gas Conference

September 14th

2010

Charlotte B. Tjølsen –

Peregrino Subsurface Manager

Page 2: Rio oil and gas   peregrino field development

2 - Classification: Internal 2010-09-13

This is Statoil•

Energy company present in 40 countries with 30,000 employees

Producing 1.95 million barrel of

oil

equivalent

(boe) pr day

Booked reserves of 5.6 billion boe

One of the world’s largest net sellers of crude oil

The world's largest operator in waters deeper than 100 metres

World leader in the use of deepwater technology

World leader in carbon capture and storage

The second largest exporter of gas to Europe

Biggest retailer of oil products in Scandinavia

Page 3: Rio oil and gas   peregrino field development

3 - Classification: Internal 2010-09-13

From Norway to the international scene…

Statfjord Gullfaks/ Oseberg Angola Troll Lufeng

Grane Ormen

Lange Peregrino Arctic Marcellus

…1974

2010 →

Page 4: Rio oil and gas   peregrino field development

4 - Classification: Internal 2010-09-13

Harsh environments

Deep water

Heavy oil

Gas value chains

Building growth from a firm strategy

Deliver international growth

Buildenergy

new Maximisethe NCS

values

Page 5: Rio oil and gas   peregrino field development

5 - Classification: Internal 2010-09-13

Statoil in Brazil

Offices in Rio de Janeiro and Niterói

with 200 employees

More than 500 offshore contractors (Peregrino)

Operator for the Peregrino Field in the Campos Basin

Diverse exploration portfolio

Main office: Argentina Building - Botafogo

Page 6: Rio oil and gas   peregrino field development

6 - Classification: Internal 2010-09-13

Peregrino

Located in Campus Basin -

85 km off the coast of Brazil at 100 m depth

Operated by Statoil

Production begins early 2011. Estimated recoverable reserves 300 -

600 million barrels

Build on Statoil’s strengths in extraction and reservoir management

Brazil

Rio de Janeiro

Peregrino

1994

Petrobras discovery well (1-RJS-498)

2000

EnCana 100% in 2nd

bid round

2001

Seismic 3D survey

2002

Seismic 3D survey

2003

Kerr McGee 33.3% farm-in

2004

2 new wells drilled

2005

Kerr McGee increase equity to 50%

2005

2 new wells drilled

2006

Norsk

Hydro acquired EnCana 50% share

2006

Anadarko acquired Kerr McGee

2007

PoD

approved, new seismic and new well

2007

Statoil merged with Norsk

Hydro Oil & Gas division

2007

BM-C-47 awarded

2008

StatoilHydro

acquired Anadarko’s 50% equity share

2009

StatoilHydro

renamed to Statoil

2010

Sinochem

acquires 40% share of Peregrino pending gov.approval

Page 7: Rio oil and gas   peregrino field development

7 - Classification: Internal 2010-09-13

Peregrino Field development solution

Development strategy

Phased development

High liquid handling capacity

High level of reservoir penetration

Produced water re-injection

Drilling rigs and large number of spare slots (23)

Fuel: Produced gas and crude oil

Well requirements

30 horizontal OP with OHGP and screens

ESP & topside booster pumps

7 vertical water injection wells with screens

Page 8: Rio oil and gas   peregrino field development

8 - Classification: Internal 2010-09-13

Producing the Peregrino Field

Oil density: 14°API

Viscosity:

163 cp

GOR: 13 Sm³/Sm³

Porosity: 30%

Permeability: ~7000 mD

Rock compressibility:

25 msips

Reservoir temperature

78 °C

Reservoir pressure

234 bar

High liquid handling capacity is one of the keys to high recovery ~ 20 %

0

50 000

100 000

150 000

200 000

250 000

300 000

350 000

1 4 7 10 13 16 19 22 25 28

Years

bopd

Oil

Water

Liquid

Page 9: Rio oil and gas   peregrino field development

9 - Classification: Internal 2010-09-13

Phased Development Strategy

Phase I Development

Additional 3D seismic (1Q 2007)

Southwest well 2Q 2007 (3-PRG-1)

2 drilling platforms + FPSO

Development drilling Q3 2010

Production start-up Q1 2011

Phase II & III Development

Development drilling

Increased Oil Recovery

Depletion of additional reservoirs

Development of southern area

-

10 km

-

Main

South

-west

N

South

BM-C-47BM-C-7

Page 10: Rio oil and gas   peregrino field development

10 - Classification: Internal 2010-09-13

Main Development contractors

Platform Installation

FPSO

Platforms

PipelinesFlex Risers Power/Signal Cable

Drilling Rigs

Drilling & completion

Page 11: Rio oil and gas   peregrino field development

11 - Classification: Internal 2010-09-13

Peregrino project

milestones

Modules

fabricated

in Corpus Christi

(Texas) and towed

to Brazilian

waters •

Peregrino jackets installed

and lifting jobs

completed

Wellhead

plattforms installed•

Offshore construction and commissioning currently ongoing

Page 12: Rio oil and gas   peregrino field development

12 - Classification: Internal 2010-09-13

Drilling platform

Page 13: Rio oil and gas   peregrino field development

13 - Classification: Internal 2010-09-13

Sailing route from Texas to Brazil

Jacket A

HermodPiles AJacket B

Piles BDeck A

LQ A&B, Deck B and DR2

DR1

Equipment Barge

HERMOD Under Tow

Jacket A MWB403

Piles A L-400

Deck A H405

DR1 Marti J

Jacket B H541

Piles B Juli B

Deck B H406

DR2 C455-3

LQ's A&B C420

Page 14: Rio oil and gas   peregrino field development

14 - Classification: Internal 2010-09-13

Drilling rig

Page 15: Rio oil and gas   peregrino field development

15 - Classification: Internal 2010-09-13

Installation vessel (Hermod)

Page 16: Rio oil and gas   peregrino field development

16 - Classification: Internal 2010-09-13

Jacket A installation

Page 17: Rio oil and gas   peregrino field development

17 - Classification: Internal 2010-09-13

Platforms installed

Peregrino B with Dan Swift Vessel Peregrino A

Page 18: Rio oil and gas   peregrino field development

18 - Classification: Internal 2010-09-13

FPSO modules installed at Keppel FELS

Page 20: Rio oil and gas   peregrino field development

20 - Classification: Internal 2010-09-13

Brasco Shore Base

4 x Supply vessels

2 Helicopters

Main OfficeHeliport

Peregrino Field

Brasco shore base (200 km)

Macaé airport (120 km)

Rio de Janeiro

Macaé

Niteroi

Brasco pipe yard

Page 21: Rio oil and gas   peregrino field development

21 - Classification: Internal 2010-09-13

HSE training of 1100 offshore personnel

High safety standard is top priority

Multicultural

working

environment

Page 22: Rio oil and gas   peregrino field development

22 - Classification: Internal 2010-09-13

PeregrinoMain Field

Peregrino Southwest

Peregrino South

Peregrino SouthDrill in 2010(BM-C-47)

IsoladoMature well proposal 2010Drill from platform

North ExtensionMature well proposal in 2010Drill from platform

Macae CarbonateMature well proposal 2010Production test from platform

Peregrino SouthwestDrill in 2011

Peregrino SouthDrill in 2010 (BM-C-37)

Pre-salt potentialProspect mapping 2010

Testing the upside potential in Peregrino

Page 23: Rio oil and gas   peregrino field development

23 - Classification: Internal 2010-09-13

Identified opportunities:•

Chemical flooding•

AICD (Autonomous inflow control device)•

MLT (Multilateral technology)•

ESP improvements

Short term (- 2010) Mid term (2010 - 2015) Long term (2015+)Displacement stability

Water

Polymer

Gain ESP experience•

Screening of polymers •

Evaluate AICD potential

Full-field polymer flooding•

Full scale AICD•

Drill MLT wells

MLT pilot in suitable well•

Polymer pilot-test•

AICD valve pilot in suitable well

Main objective:•

Optimise field recovery from 20% to 30%•

Reduce field water production/injection

IOR –

Increasing the recovery from Peregrino

Page 24: Rio oil and gas   peregrino field development

24 - Classification: Internal 2010-09-13

MLT –

Multilateral wells

Increase reservoir exposure

Two branches gravel packed with optional branch control

The additional cost of the lateral is approx 1/3 of a normal well

Main risk is to combine ESP and Gravel Pack (GP) with the MLT technology

First installation planned Q4 2011

Page 25: Rio oil and gas   peregrino field development

25 - Classification: Internal 2010-09-13

AICD –

Autonomous inflow control valves

Self adjusting valves restricting the inflow of water in every screen joint

Wells with high water production and good pressure support shows ~10 % increase in production

Main risks/challenges:

Valve design (avoid erosion or plugging)

Combination with gravel packing

First installation planned Q1 2012

050100

1st Qtr 2ndQtr

3rdQtr

4th Qtr

East West North

Page 26: Rio oil and gas   peregrino field development

26 - Classification: Internal 2010-09-13

Summing up

Brazil a country with opportunities

Experience transfer from Norway to the international scene

Proven ability to execute mega projects

Project on track to start up early 2011

Peregrino upsides

Field development

Increased oil recovery

Page 27: Rio oil and gas   peregrino field development

27 - Classification: Internal 2010-09-13