risk assessment and allocation for effective project...

52
June 27, 2012 Risk Assessment and Allocation for Effective Project Delivery and Management Dr. Khalid Bekka HDR Decision Economics Informing and Supporting the Decision Making Process

Upload: others

Post on 18-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

June 27, 2012

Risk Assessment and

Allocation for Effective

Project Delivery and

Management

Dr. Khalid Bekka

HDR Decision Economics

Informing and Supporting the Decision Making Process

Page 2: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

2

Agenda

Accounting for Uncertainty and the Use of Risk

Management

HDR‘s Risk Management Process

Impediments and Procurement Traps

Risk Allocation and Project Delivery Method

Case Studies:

Texas DOT- North Tarrant Expressway

Washington State DOT – SR 520 Bridge Program

Utah DOT- Mountain View Corridor

Alaska DOT – Northern Rail Extension

NYC MTA – Signals Replacement Program

Open Discussion

Page 3: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

3

My Background in Risk Management and P3

Over 20 years of experience in infrastructure

economic, financial, and risk assessment;

Led financial risk assessment for more than 30 toll

road projects for USDOT and bond insurers,

including development of Public Sector

Comparator Framework for agencies in Arizona

and Florida

Conducted risk analysis for over 200 infrastructure

investment in the US and Canada, including

bridges, highways, rail, ports, airports, tunnels,

water treatment facilities, and convention centers

Prepared reports for US FTA, FHWA, FRA, FAA,

DOJ, and DHS that have been submitted to

congressional committees, GAO and OMB

Developed and Conducted Risk Management for

Mega Programs including Ground Zero in New

York City, and Katrina Rebuild Program in New

Orleans.

Page 4: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

4

• Over 40% of all infrastructure projects, and over 80% of major infrastructure, exceed their budget or schedule;*

• With the financial turmoil, funding constraints, volatile commodity prices, and policy/regulation changes, conventional planning methods are no longer sufficient;

• Credible, transparent, and comprehensive processes become critical for effective infrastructure planning; and

• Credibility means that decision-makers must know the nature and magnitude of risks to determine their risk tolerance so that they make effective decisions.

New Realities and the Need for Risk

Assessment

-45%

-30%

-15%

0%

15%

30%

45%

60%

75%

$0 $20 $40 $60 $80

$100 $120 $140 $160 $180 $200 $220 $240 $260 $280 $300

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

Hot rolled bars, plates, and structural shapes

12M Change

* Flyvbjerg et al. (2005)

Page 5: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

5

An Integral Part of Project Management

Project Management

Plan

Project Communi-

cations

Project Schedule

Cost Control

Project Procurement

Risk Management

Project Staffing (HR)

Project QA-QC

Project Scope

Page 6: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

HDR‘s Risk

Management

Process

6

Page 7: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

7

Integrating Risk Analysis, Value

Engineering, and Risk Response Principles

Investigate

Functional analysis

Speculate

Evaluate

Develop

Improve

Performance

Learn About Project

Identify Risks

Strategize

Qualify and Quantify

Develop Response

Anticipate Risk

VE / Risk Response Cost Risk Assessment

Both use a consensus-based team approach

Page 8: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

8

HDR‘s Risk Management Process

* Project/Program Risk

Assessment

* Quantification of Cost and

Schedule Risks

Step 2:

Risk Response

Prioritization /

Financial Planning

Risk Allocation/ Project

Delivery Method

Alternatives

Step 3:

Risk Analysis on

Response Strategies

Step 1:

Baseline Risk

Assessment

Development of Alternative

Solutions and Risk Response

Strategies

Assessment of Threats and

Opportunities Related to

Response Strategies

Step 4:

Tracking, Monitoring,

and ControlContinuous Risk Tracking,

Monitoring, and Reporting

Decision Support

Page 9: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

9

Comprehensive Identification of Risks

Construction schedule risks;

Third-Part Agreements;

Environmental Risks;

Utilities Risks;

Drainage Risks;

Traffic Management;

Market Conditions Risks,

Procurement Risks;

Project Management Risks,

Right of Way Risks;

Performance Standards; and

Financial Risks.

Page 10: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

10

Risk-Adjusted Cost Estimates

BID PRICE 02/07 ($219 M)

Baseline

Non-Escalated

Baseline

Escalated

$150.3 $172.8

100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

0%

$135 $155 $175 $195 $215 $235 $255 $275 $295 $315

Total Project Cost ($Millions)

Pro

bab

ility

of

No

t Ex

cee

din

g

$170.9

$186.9

$192.3

$195.9

$199.6

$202.7

$209.3

$206.2

$212.0

$214.9

$217.5

$220.5

$223.3

$226.1

$228.9

$232.7

$236.9

$242.0

$247.7

$255.1

$281.5

Page 11: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

11

Risk-Adjusted Schedule Projection

Feb-2018

Jan-2019

Mar-2020

Bas

elin

e En

d D

ate

Jun

- 2

01

8

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

2017 2018 2019 2020 2021 2022 2023 2024

Pro

bab

ility

of

No

t Ex

cee

din

g

Project Timeline

Project Completion Date

Page 12: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

12

Risks Prioritization

$0,2

$0,3

$0,3

$0,3

$0,6

$0,9

$0,6

$0,2

$0,9

$1,2

$3,2

$0,2

$0,2

$0,3

$0,3

$0,3

$0,6

$0,9

$0,9

$1,8

$3,2

$0,0 $0,5 $1,0 $1,5 $2,0 $2,5 $3,0 $3,5

Co7b: Interference from other projects (28)

Rw4: Objections to Right of Way appraisal (1)

Tr1b: False work placement and removal (28)

Tr2b: Conflicting lane closures (28)

Rw7: Delays in ROW acquisition (1)

Rw1b: ROW unable to certify before advertising (1)

Ma2b: Other construction projects in region limit supply of labor (28)

Rw12: Other Delays in ROW Acquisition (1)

Co6: Discovery of unknown utilities during construction (28)

Rw17: Utility relocation may not happen in time (22)

Expected Increase in Cost

Millones

Top Cost Impacts on Cost - Event Costs and Schedule Delay Costs

Schedule Cost (Delay & Escalation) Event Cost

Page 13: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

13

Risk Response Categories

• Avoidance is a change to the project scope to

eliminate the impact of a risk.

• Transference of a risk to another party who is more

capable at handling the risk (such as the contractor

or insurance company).

• Mitigation is seeking to lessen the impact of a specific

risk items, which may involve the consumption of

additional time and/or money.

• Acceptance is recognition by the project team of a

specific risk and decision to not take action to deal

with the risk.

Page 14: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

14

Risk Analysis on Response Strategies

Mitigation Value

Page 15: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

15

Adequate and Continuous Reporting

Page 16: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

16

Financial Planning Support

• The framework integrates risk-

adjusted cost estimation with

cash flow modeling

• The process allows for the

assessment of various project

prioritization on cash flow and

risk exposure

• Risk-Based budgeting

thresholds determined on

project by project basis, which

depends on project size and

level of risk

• The projections can then be

shown for the program as a

whole or for individual or a set

of projects

Page 17: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

Impediments and

Procurement Traps

Page 18: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

18

Address/Resolve Regulatory Impediments

• Interoperability

• Conversion of Existing Roads/

Highways

• Violation Processing

• Eminent Domain/Condemnation

• Negotiation after Selection

Page 19: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

19

Selection Process is Critical

• Specify Minimum Submission Requirements – Financial and Technical Qualifications – Financial Component – Demonstrate Technical Feasibility

• Specify Evaluation Process

• Balance Need for Confidentiality and Public Disclosure

• Process for Ensuring Price Reasonableness in Negotiated Transaction if price is not ―locked in‖ at selection

• Ensure Involvement of Local Stakeholders

Page 20: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

20

Procurement “Traps”

• Pre-quality Teams

• Low Bid versus Best Value Evaluations

• Design-Bid versus Design-Build and Design-Build-Operate-Maintain

• Warranties, Maintenance, Long-Term Operational Arrangement

• How Much Design should DOT Provide?

• Land Acquisition: Advance, Donated, Shared with Private Partners

• Utility Relocation

Page 21: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

21

Competition is Critical

• Alternate Technical Concepts

• Innovative Design

• Compensation for Ideas

• Present Value Proposal Cost

• One-on-One Meetings to Discuss Details Prior to Proposals

• Realistic Time — Value of Money

• Confidentiality

Page 22: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

Risk Pricing and Allocation

Page 23: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

23

Establishing Risk Allocation Policy

Objective

• Allocate individual risk

factors to the party

best suited to manage

them

• Develop contract

language to effectively

manage risks through

allocation

Benefit

• Understand which

parties will manage each

risk

• Improved understanding

of potential change

orders

• Minimize cost premiums

for risks from contractors

for risk factors best

handled by owner

Page 24: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

24

Risk Allocation Methodology

• Identify risks associated with project in baseline risk

assessment

• Identify mitigation strategies during risk response

step

• Assist in determining the ―ownership‖ of risks based

on characteristics of the risk

Goal: Optimal Risk

Transfer that

Maximizes

Value for Money

Page 25: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

25

Criteria For Risk Allocation

Individual Risks should be

allocated to:

- The party best able to manage

it: The party that is most capable

to predict and prevent the risk.

- The least risk-bearing cost

partner: The risk bearer must be

the party that can promptly deal

with the risk via existing system

and resources

- The party with the most

efficient and effective

mechanism: The risk bearer

must be the party that can deal

with the risk with most

economical and effective method

Design

ROW

Geotechnical

Environmental

Utilities

Schedule

Construction

RISK ALLOCATION

ITEM Owner Contractor

Page 26: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

26

Assigning the Risk Bearer

Key Risk Risk

Register

Handling Ability

Controlling Ability

Influence Ability

Risk Liability

Owner Agent

?

Procurement Cost

Page 27: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

27

Procurement Cost

Risk Allocation

Productivity Costs

Transactional Costs

Risk –Bearing Costs

Incentives and

Allowances

Contractual Organization, Institutional Guaranties

Risk Premium for

Supporting Risks

Transferring too many risks or not transferring the right risks leads to higher procurement costs.

Page 28: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

28

Handling

Cost ($)

Risk Exposure

Costs ($) Liability Cost($)

Transactional

Cost ($ and

Time)

Costs under Financing Options

• Risk Expected Value

• Number of Bidders/ Competitive

Premium

• Risk-Bearing Risk

• Insurance and Bonding

Cost Avoidance/Benefits

Comprehensive Assessment for

Optimum Strategy

Public

Net Present

Value ($)

Discounting

(%)

Total Cost

Avoidance/

Benefits and Risks

($)

Total

Costs ($)

Private

Net Present

Value ($)

NPV Optimal

Risk Transfer

Level

Page 29: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

29

Risk Allocation – Design & Site Risks

Type of Risk Risk

Grantor Concessionaire Shared

Detailed Design approvals and consents

Working (Construction) Drawings Delay in final approval of detailed design

Feasibility Approvals and consents with State responsibility Changes in

design and construction standards during the Construction Period                            

Land acquisition within right-of-way

Obtaining consent to use additional land (permanent additional right-of-way)

that is Identified prior to commercial close

Environmental

Water/air/soil pollution – unknown pre-existing

Land acquisition within right-of-way

Obtaining consent to use additional land Identified after commercial close

Obtaining Ministerial or owner consent to use additional land (temporary

use of land for construction purposes)

Procuring fill sites and other offsite land required

Access risks

Site Security

Cultural/archaeological/ heritage

Geotechnical and ground/soil conditions

Past mine workings

Undisclosed Latent defects (Existing infrastructure)

Allocation

Design Risks          

          

Site Risks

          

          

Page 30: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

30

Risk Allocation – Construction Risks Type of Risk Risk

Grantor Concessionaire Shared

Quality assurance and quality control

Achieving Construction Standards and Specifications

Fit for purpose manuals, approvals and statutory certificates

Cost overrun and delay not caused by a relief or compensation event

Delays due to Concessionaire changes

Injunctions against construction: due to Concessionaire failure

Workplace Health and Safety

Construction security (bonding by subcontractors)

Sub-contractor insolvency

Latent defects (disclosed defects with existing infrastructure)

Water/air/soil pollution – known pre-existing or arising from work

Defective materials

Delays caused by agencies other than State (e.g. utilities)

Delays caused by State

Delays due to State‘s changes

Labour disputes

Labour and material availability

Project management / integration / delay

Time and costs to satisfy commissioning

Damage to works, however caused except as excluded

Damage/injury to third parties

Damage/loss to utilities identified by Grantor

Damage/loss to utilities not identified by State

Adequacy of insurance

Patent infringement

Cost associated with works for Railways, Canals etc.

Patent infringement

Cost associated with works for Railways, Canals etc.

Injunctions against construction: due to alignment           

Allocation

Construction Risks

          

                     

Page 31: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

31

Risk Allocation –Performance Risks Type of Risk Risk

Grantor Concessionaire Shared

Labour and material availability

Future interchanges or additional lanes

Damage to works, however caused, except as excluded

Overloaded Vehicles

Obtaining and maintaining licenses to comply with regulatory requirements

Interface with sub-contractors

Change in scope of service specifications by public sector

Off road incidents

Meeting handback standards

Workplace Health and Safety

Labour disputes

Vandalism

Water/air/soil pollution

Third party claims and accidents

Expansion for traffic accommodation at ramps and interchanges due to

traffic growth, or signalization

Development Around Project Site Requiring Further Over Bridges or Under

Passes or other Demographic Changes

Traffic accidents

Damage caused by unauthorised tyres e.g. spikes

Damage/injury to third parties

Increased legal load limits

Traffic Management

Allocation

Performance Risks

                                

                     

          

          

Page 32: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

32

Risk Allocation – Other Risks

Workmen‘s liens

Disputes between designer/contractor/professional team

Weather

Force Majeure during operations

Natural disaster, terrorism, war                      

Intensive or extended event leading to termination

Uninsurable risks (throughout the concession)

Political Force Majeure           

Revenue Risks                      

Incorrect estimates and cost overruns

Increased maintenance due to traffic volume

Equipment used becomes prematurely obsolescent

Actual operating and maintenance costs higher than anticipated                      

External Risks Changes in standards           

Base interest rates to Financial Close

Interest spread risk to Financial Close

Costs of finance on change of requirements

Currency fluctuations                                 

Inflation on Construction Costs

Inflation on Operation, Maintenance, Rehabilitation

Refinancing (if no 2 stage financing)                      

Political Risks Public sector budgeting cycles, changes in law and taxation                      

Default Risks Termination                             

Change in Ownership of Concessionaire

Conflict of Interest Among Shareholders of Concessionaire

Force Majeure Risks

O&M Risks

Strategic Risks

Other Market Risks

          

          

          

      

          

          

Page 33: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

33

Case Study 1: TXDOT Determining Risk Allocation

Page 34: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

34 34

NTE Project Overview

• The North Tarrant Express (NTE) Project runs along IH-820, north of Dallas, TX

• The existing highway includes two general purpose (GP) lanes each direction.

• Through the Base Build and 9 build options, the proposed improvements include three GP lanes in each direction with two managed lanes in each direction

• The NTE is being constructed as part of a concession project.

Page 35: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

35

Risk Allocation Approach

• TXDOT used risk management

to identify project risks and

allocate between contractor

and DOT

• Evaluated various risk

allocation approaches to

understand differences in costs

and risk between parties

• Analysis recommended that

TXDOT manages

environmental and right-of-way

risks and concessionaire to

manage design, construction

and utility risks

TXDOT North Tarrant Expressway

Page 36: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

36

Base C

osts

w/

Co

nti

ng

en

cie

s:

$457

Escala

ted

Base C

osts

w/

Co

nti

ng

en

cie

s:

$502

$462

$494

$526

$537

$597

$654

$544

$604

$662

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$400 $500 $600 $700 $800 $900

Lik

elih

oo

d o

f N

ot

Ex

ce

ed

ing

Cost

Millions

Escalated Base Costs With Budget Uncertainty (Using Base Schedule)

Plus Developer Risk

Risk Allocation Scenarios

• Evaluated two risk allocation scenarios: – Design-Build Contract (DB) – Comprehensive Development

Agreement (CDA)

• Differences in Risk Allocation: – DB: developer assumed risks of

litigation, schedule delays, design changes

– CDA: developer assumed risks to utilities, right of way, unplanned work

– Allocation of other risks did not change between scenarios, with Owner retaining environmental and stakeholder risks and developer owning many of the risks to construction

• DB allocation put more risk on TXDOT

TXDOT North Tarrant Expressway

Base C

osts

w/

Co

nti

ng

en

cie

s:

$457

Escala

ted

Base C

osts

w/

Co

nti

ng

en

cie

s:

$502

$463

$494

$527

$526

$584

$641

$544

$604

$662

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$400 $450 $500 $550 $600 $650 $700 $750 $800

Lik

elih

oo

d o

f N

ot

Ex

ce

ed

ing

Cost

Millions

Escalated Base Costs With Budget Uncertainty (Using Base Schedule)

Plus Developer Risk

DB Allocation

CDA Allocation

Page 37: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

37

Case Study 2: SR 520 Bridge Replacement and HOV Program

Page 38: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

38

SR 520 Bridge Replacement and HOV

Program

• The 12.8-mile program area begins at I-5 in Seattle and extends to SR 202 in Redmond

• The SR 520 Bridge Replacement and HOV Program will enhance safety by replacing the aging floating bridge and keep the region moving with vital transit and roadway improvements throughout the corridor

• Consists of multiple projects, including: – Bridge Replacement and HOV Project

– Floating Bridge and Landings Project

– Eastside Transit and HOV Project

– Pontoon Construction Project

Page 39: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

39

Risk Tracking and Allocation Methodology

1. Conduct individual risk assessments on project-by-project basis

2. Establish Risk Management Plan

3. Establish Risk Management Program

4. Track risks within risk tracking tool

5. Evaluate risk allocation scenarios through risk assessment modeling

6. Roll up project risk information to program level

7. Provide real time project information for decision makers, including forecasted budgets, forecasted schedule, key areas of risk, and contingency requirements

Page 40: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

40

Risk Tracking Tool Facilitates Risk Allocation

• Used by WSDOT as a tool to proactively manage risk in the delivery of this megaproject

• Integration into project team meetings creates a culture of risk management

• Visual displays of risk impact versus risk likelihood demonstrate the risks relative impact to budget and schedule

• Aggregates and reports risk information for individual Projects and for entire Programs

• The tool allows for the capture and storage of risk data including risk allocation between owner and contractor

WSDOT SR 520 Program

Page 41: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

41

Case Study 3: UDOT Mountain View Corridor

Page 42: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

42

Mountain View Corridor

• Located in Salt Lake County, Utah

• Initial construction builds two lanes in each direction with signalized intersections where MVC crosses local roads

• In the future, as improvements are made in subsequent construction phases, MVC intersections will be reconfigured as grade-separated interchanges

• At the ultimate build-out, MVC will be a freeway similar to I-15, extending 35 miles north and south from 1-80 in Salt Lake County to Lehi in Utah County

• Delivered using CMGC delivery method

Page 43: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

43

Mountain View Corridor

Risk Allocation Approach

• Bid Items: Risks best managed by the contractor are allocated as the contractor's responsibility:

– Included 'yield' in the sense of converting tons of gravel/soil into an area coverage for building the road.

– Once the owner and contractor agreed on a yield ratio, it determined total volumes / tons required and then it was up to the contractor to manage

• Price Escalation: risks to price growth uncertainty is shared: – Clauses in the contract for fuel and asphalt kept the owner from paying a premium on

the price. – The contractor would pay the owner if the prices dropped a certain level. The owner

paid out when prices exceeded a certain level.

• Provisional Sums: the owner retained risks for identifiable and quantifiable materials that could be managed as provisional sums.

– These 'sums' are similar to an allowance. – ‗Sums‘ are paid out of the contract amount and thus handled differently than a

change order - because they were a known risk.

• Program Contingency: remaining risks are handled through program contingency – Change order requests that come through are handled from this contingency pool. – This is held in the owner‘s control.

Page 44: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

44

Risk Allocation for

Mountain View Corridor

• Process results in an efficient risk allocation and an optimal risk transfer that maximizes value for money.

• The analysis resulted in a mechanism to track risks and manage contingencies.

• The savings led to an extension of 5 additional miles of roadway

$0

$1

$2

$3

$4

$5

$6

$7

$8

$9

$10

$0

$10

$20

$30

$40

$50

$60

May-09 Nov-09 May-10 Nov-10 May-11 Nov-11 May-12 Nov-12 May-13 Nov-13 May-14

Mo

nth

ly C

on

tin

gen

cy R

ele

ase

d (

$M

)

Tota

l Co

nti

nge

ncy

($

M)

Project Timeline

C1 Released Prov Sums

C1 Released Contract Funds

C2 Released Prov Sums

C2 Released Contract Funds

Total Contingency

Total Prov Sums Contingency

Total Contract Contingency

Page 45: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

45

Case Study 4: Alaska Railroad Northern Rail Extension

Page 46: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

46

Northern Rail Extension Overview

• The Alaska Railroad Corporation (ARRC) is constructing a crossing over the Tanana River in Salcha

• Include the construction of 3,300 ft bridge across Tanana River and related access roads

• Construct 10,700 ft levee and protection system for upstream flood protection

• Delivered using CMGC

Page 47: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

47

Northern Rail Extension Risk Allocation Approach

• Risk management facilitated

discussions between owner

and contractor on risk pricing

• Utilized Independent Cost

Estimator (ICE) along with

Owner and Contractor

estimators to understand how

risks are priced

• Specified risk allocation and

contingent items within

Guaranteed Maximum Price

(GMP) to determine best

allocation of risk

$164.9

$170.1

Ba

se C

ost

: 15

6.4

M

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$120.0 $140.0 $160.0 $180.0 $200.0 $220.0 $240.0 $260.0NRE1 30% Design NRE1 60% Design NRE1 60% Interim-Design

NRE1 90% Design NRE1A 90% Design - Adjusted NRE1A - GMP-1 Design (Base Scenario)

NRE1A - GMP-1 Design (Final) NRE1A - GMP-1 Design (Final)

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

1

2 3

4

5

1

2 3

Risk Assessment Changes over Different Design StagesBase (30%) - high degree of uncertainty in design, quantities and prices. Base = $180.8M.Change #1 (60%): Realize design efficiencies from alternative analysis: upland levee alignment, modification of revetment size and amount of stone; 165 ft, 4 girder simple span TRB configuration. Base = $168.0M.Change #2 (60% - interim): Include additional construction execution risks from CMGC register. Base = $168.0M.Change #3 (90%): New estimate includes: firm pricing for PMs and subs; effects of levee -TRB sequencing ;addtional $6.9m in contingent items; higher escalationfrom potentialdelays with CLOMR. Base = 186.8M.Change #4 (90% - Adjusted): Re-scoped project to NRE1A that reduced quantities of materials and project components to bring base cost down to $157.8M. Additional opportunities to reduce pricing on steel and riprap. Base = 157.8MChange #5 (GMP-1 ): Re-priced and scheduled project to account for changes in contracting and delays. Additional risk of delay is included. Higher cost outlook on escalation is anticipated. Base = 146.6M.Change #6 (GMP-1 ): Based on GMP with re-analyzed and allocated risks. Includes additional contractor risks

6

Page 48: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

48

Case Study 5: MTA NYC Transit: Queens Boulevard Line Interlocking Modernization

Page 49: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

49

MTA NYC Transit: Queens Boulevard Line

Interlocking Modernization

• Initially evaluated

projects as two individual

contracts

• Considered risk

mitigation strategy of

combining into single

contract

• Evaluated both options

through risk assessment

to understand impacts

on overall cost

Contract Description Initial

(Separate) Mitigated

(Packaged)

S-32769 Designing And Furnishing Signal Equipment For 71St-Continental Avenue And Union Turnpike Interlockings Queens Line, IND, Borough Of Queens

$99.5

$327.7 S-32754 Installation Of Signal

Equipments For 71St-Continental Avenue And Union Turnpike Interlockings Queens Line, IND, Borough Of Queens

$257.3

Total $356.9 $327.7

Page 50: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

50

Risk Analysis Results of Standalone

Contracts

• Project Cost at 80th Percentile: – S-32769: $106.0 M – S-32754: $282.3 M – Total: $386.2 M

• Key Risks: – Delays in Award – Contractor coordination – Delays in Design,

Manufacturing, Testing & Delivery of Equipment

– Additional TA Labor services costs (GOs and work trains)

$102.4 M, 50%

$106.0 M, 80%

Tota

l Pro

ject

Co

st B

ase

Esti

mat

e -

Init

ial:

$9

9.6

M

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0.0%

0.2%

0.4%

0.6%

0.8%

1.0%

1.2%

1.4%

1.6%

1.8%

$89.7 $92.2 $94.6 $97.0 $99.5 $101.9 $104.3 $106.8 $109.2 $111.6 $114.0

Prob

abili

ty o

f N

OT

Exce

edi

ng

Pro

bab

ility

of O

ccu

rre

nce

Cost ($M)

S-32769 - Total Project Cost Density Function - Initial S-32769 - Total Project Cost - Initial

Total Project Cost Base Estimate - Initial

$272.3 M, 50%

$282.3 M, 80%

To

tal P

roje

ct C

ost

Ba

se E

stim

ate

-In

itia

l:$

25

7.3

M

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0.0%

0.2%

0.4%

0.6%

0.8%

1.0%

1.2%

1.4%

1.6%

1.8%

$235.0 $242.3 $249.6 $256.9 $264.2 $271.5 $278.8 $286.2 $293.5 $300.8 $308.1

Prob

abili

ty o

f N

OT

Exce

edi

ng

Pro

bab

ility

of O

ccu

rre

nce

Cost ($M)

S-32754 - Total Project Cost Density Function - Initial S-32754 - Total Project Cost - Initial

Total Project Cost Base Estimate - Initial

Page 51: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

51

Risk Analysis Results of Combined Contract

• Reduction in total project cost at 80th percentile: – $386.2 M to $356.9 M

– Savings of $29.3 M

• Combining contracts resulted in base cost reductions as well as reduction in coordination and other risks

$374.8 M, 50%

$386.2 M, 80%

$346.9 M, 50%

$356.9 M, 80%

To

tal P

roje

ct

Co

st

Ba

se

Esti

ma

te -

Init

ial:

$3

56

.9 M

To

tal P

roje

ct

Co

st

Ba

se

Esti

ma

te -

Mit

iga

ted

, $

32

7.7

M

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0.0%

0.5%

1.0%

1.5%

2.0%

2.5%

$308.3 $319.1 $329.9 $340.7 $351.5 $362.3 $373.1 $383.9 $394.7 $405.5 $416.3

Pro

ba

bilit

y o

f N

OT

Exce

ed

ing

Pro

ba

bili

ty o

f O

ccu

rre

nce

Cost ($M)

S-32769C - Total Project Cost Density Function - Initial S-32769C - Total Project Cost Density Function - Mitigated

S-32769C - Total Project Cost - Initial S-32769C - Total Project Cost - Mitigated

Total Project Cost Base Estimate - Initial Total Project Cost Base Estimate - Mitigated

Page 52: Risk Assessment and Allocation for Effective Project ...campus.cgr.go.cr/elearningdesarrollo/noticlics/2012/ed17/presentaci… · DOJ, and DHS that have been submitted to congressional

June 27, 2012

Risk Assessment and

Allocation for Effective

Project Delivery and

Management

Open Discussion

Informing and Supporting the Decision Making Process