risk management in the built environment qualitative and quantitative risk management by professor...

13
Risk Management in the Built Environment Qualitative and Quantitative Risk Management By Professor Simon Burtonshaw-Gunn – licensed under the Creative Commons Attribution – Non-Commercial – Share Alike License http://creativecommons.org/licenses/by-nc-sa/2.5/

Upload: sybil-douglas

Post on 29-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Risk Management in the Built Environment

Qualitative and Quantitative Risk Management

By Professor Simon Burtonshaw-Gunn – licensed under the Creative Commons Attribution – Non-Commercial – Share Alike License

http://creativecommons.org/licenses/by-nc-sa/2.5/

Risk Management in the Built Environment

School of the Built Environment

MSc Construction Management

Risk Management in the Built Environment

Presentation 1: Risk Identification

Professor Simon Burtonshaw-Gunn

Risk Management in the Built Environment

• Risks are usually spoken about using a Condition- Cause- Consequence approach, for example:

• There is a risk that lack of support will cause the project to stall resulting in team being deployed on other work.

• There is a risk that our customer will be unable to specify the internal fit-out requirements in a timely fashion caused by their lack of experience in procuring this type of equipment resulting in delayed payment, project overrun, and delayed initiation of support contracts.

• There is a risk that the client will wish to bring forward the completion date for the project and cause us to execute the work by additional shift working or more resources resulting in an overall cost increase from that contractually agreed.

Risk Management in the Built Environment

Risk = Probability x Consequence

• Probability = Likelihood of… …an incident/accident occurring…loss of control

…the hazard being released(Inevitable through to impossible)

• Consequence = The outcome of the incident/accident following release of the hazard (Death through to no injury)(Environmental catastrophe through to no effect)

In order words . . . the chance (big or small) of harm actually being done

Risk Management in the Built Environment

Probability

Very Low

Low Medium High Very High

Impact Very High 4 6 8 10 12

High 3 5 7 9 11

Medium 2 4 6 8 10

Low 1 3 5 7 9

Risk Management in the Built Environment

Cost Impact

Very High … jeopardise the business budget due to a substantial provision for consequential damages.

High … endanger the project financial viability ie pose a significant margin threat so that substantial re-planning requires the re-assignment of business’s resources sufficient to harm other projects or cause considerable consequential delay costs.

Medium … require significant re-work or the selection of alternative subcontractors or cause significant consequential delay costs and adjustment of the risk-margin balance.

Low … require additional or higher rated resources or a change to alternative suppliers or cause some consequential delay costs.

Very Low: … require adjustment of resource profiles, resulting in non-optimum efficiency.

Risk Management in the Built Environment

Schedule Impact

Very High … cause significant programme completion non-compliance, unrecoverable by re-planning.

High … cause unavoidable programme milestone non-compliance for which re-planning is required.

Medium … cause overrun and certain work for which re-planning is required.

Low … require probable re-work.

Very Low: … require some re-scheduling of tasks.

Risk Management in the Built Environment

Performance Impact

Very High … result is a serious non-compliance or degradation in performance sufficient to terminate the project.

High … cause a problem or degradation in performance so significant that a substantial non-compliance is unavoidable.

Medium … cause partial compliance that requires concessions or difficult negotiations.

Low … cause a problem that requires trade-off studies or negotiations to resolve.

Very Low: … require some adjustment in the solution.

Risk Management in the Built Environment

Impact Definitions

ProjectObjectiv

e

Very Low Low Medium High Very High

0.05 0.1 0.2 0.4 0.8

Cost Insignificantcost increase

<5% cost increase

5-10% cost increase

10 -20% cost increase

> 20% cost increase

Schedule InsignificantSchedule slippage

Schedule slippage

<5%

Overall project

slippage 5 -10 %

Overall project

slippage 10 - 20 %

Overall project

slippage >20 %

Scope Scope decreases,

barely noticeable

Minor Areas of Scope are

affected

Major Areas of Scope are

affected

Scope reduction

unacceptable to client

Project End. Item is

effectively useless.

Quality Quality degradation

barely noticeable

Only very demanding applications are affected

Quality reduction requires

client approval

Quality reduction is unacceptable to client

Project End. Item is

effectively unusable.

Risk Management in the Built Environment

Customer Project management ProcurementCommercial FinancialEngineeringManufacturing System design and integrationTechnologySubcontractor capabilitiesInterfacesRegulatory involvement

EnvironmentalPolitical visibilityNumber of key project participantsComplexityLabour skills availability and productivityFunding/ cost sharingMagnitude / type of contaminationQuality requirementsSitePublic involvementNumber of locations/ site access/ site ownership

Using this list as a starting point give examples of these types of project risk . . . .

Risk Management in the Built Environment

Make/ buy planning, design, production capacity, new tools/ equipment requirements, test requirements, new manufacturing or test processes, incorporating change during manufacture

Manufacturing

Feasibility, technology transfer, complexity, dependencies, resourcing, special standards/ documentation requirements, prototypes, maturity, manufacture, process

Engineering

Profit margin, accurate cost forecasts, payment plan, penalty charges

Financial

Subcontractor agreement, interpretation of Terms and conditions

Commercial

Planning, vendor appraisals, critical lead-times, reliance on single source, component obsolescence, market volatility

Procurement

Planning, resourcing, resource capabilities, dependencies, stakeholders, organization / interfaces, communication, constraints, process, transition and services

Project management

Customer focus, specification quality, changing requirements.

Customer

Typical Examples . . . Project Management Risk

Risk Management in the Built Environment

Tools and Techniques for Risk IdentificationThere are a number of tools and techniques available for use in risk identification, these could be:

• Document review

• Assumptions analysis

• Diagramming techniques

• Checklists – See also supporting information of

“Checklist for Risk Identification”

• Information gathering techniques – brainstorming, interviewing etc

• Learning from experience / previous project close out reviews

Risk Management in the Built Environment

School of the Built Environment

MSc Construction Management

Risk Management in the Built Environment

Presentation 1: Risk Planning and Identification

Professor Simon Burtonshaw-Gunn