LUSAIL DEVELOPMENT SAFETY TEAM
SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1 SSP09/F01 Date : 05/01/07Issue No: 01 Page : Page 1 of 17
OVERALL SITE RISK ASSESSMENT REGISTER SSP09/F01
Prepared and Issued by:
James Anderson, Senior Safety Manager, Lusail Development Safety Team
Reviewed by:
William Street, Senior Project Manager, Lusail Development Project
Authorised by:
Hazim Alsadek, VP, Engineer, Lusail Development Project Revision History:
Revision Date Description
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
RISK ASSESSMENT REGISTER OF WORK ACTIVITIES – PROFORMA SITE/PROJECT : LUSAIL DEVELOPMENT PROJECT MANAGER: DATE:
Initial Risk Residual Risk No. Task &
Activity Hazard Persons at Risk Risk S L R Control Measures S L R
Risk Owner
Electricity
Electric Shock, Burns Electrocution, Death
Fire/Explosion Burns, Death
Foreign Bodies
Injury to eyes/ Flying objects, Cuts
Noise Tinitus/Noise Induced Hearing Loss
HOT WORK
Pipe Soldering Disc Cutting
Welding
Inhalation of Dust/Fumes
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Injury to Respiratory Tract/ diseases/cancer acute and chronic
• Ensure that all plant and
equipment is tested. • Only suitable tools and
equipment must be used on site• Suitable Fire Extinguisher in
location of hot work • Hot Work Permit issued from
Contractor. 45 min check-work complete.
• Suitable and sufficient PPE to be worn with all hot work activities (Goggles, Gloves, Dust Masks, Ear Defenders,RPE, and specific welding PPE.
• Trained competent persons to only operate or maintain any specialised tools or equipment.
• Carry out hot work activities in well ventilated areas.
• Loose Clothing must not be worn
• Disc cutting to be used on level surface.
• COSHH Assessments for welding, hot cutting Pipe Soldering required.
• Method Statement required for all hot work.
• Remove all combustible materials or liquids from hot works work area prior to any hot work activities commence.
• Training and regular toolbox talks carried out and recorded at regular intervals.
Project/ Construction Manager/s
& Supervisors
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 2 of 17
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 3 of 17
No. Task &
Activity Hazard Persons at Risk Risk Initial Risk Control Measures Residual Risk Risk Owner
Manual Handling Injury to Personnel
2
MOVING OF EQUIPMENT
PLANT & MATERIALS
Collision/Collapse
Consultants,Contractors’ Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Injury to Personnel / Damage to equipment
Risk Assessment carried out prior to heavy work commencing. Mechanical methods to be used where possible, or multiple person lifting.
Project Manager/s
& Supervisors
Manual Handling Back Injury/Strain/Sprain
Collapse/Collision Injury to persons
Falls from Height Injury to Operative
3
MOBILE/ TOWER
SCAFFOLDS
Falls from Materials
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Injury to other persons
• Ensure that scaffold is erected to manufacturer’s instructions.
• Method Statement required for work.
• Certified erectors only to erect scaffold as per training guidance and Instructions.
• Erect Scaffold on firm level surface.
• Min 3.5:1 Height to Base Ratio (Internal) Min 3:1 Height to Base Ratio (External)
• Double handrail with the top hand rail erected to no less then 910mm with the gap between the toe board and mid guard rail and the mid and top guard rail to not exceed 470mm.
• Toeboards should be no less then 150mm,
• Access must be achieved from inside by way of secured ladder.
• No overloading with materials. • Brakes must be applied when
stationary. • No riding of tower scaffolds. No
persons to be on scaffold during movement.
• Scaffold must be inspected prior to erection/weekly/ altered and scaftagged.
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 4 of 17
No. Task & Activity Hazard Persons at Risk Risk Initial Risk Control Measures Residual Risk Risk Owner
Electricity
Electric Shock Electrocution
Fire Injury to Persons Property Damage
4
USE OF PORTABLE ELECTRIC
TOOLS
Manual Handling
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Back injury Strain/Sprain
• All electrical tools must be tested.
• Method statement required for work
• Wear appropriate PPE (Gloves/Goggles/Hearing protection)
• Manual Handling assessment prior to use of tools.
• Lubricate rigid surfaces to prevent friction
• Inspect tools prior to all operations.
• Never use in wet conditions or Confined Spaces/Flammable atmospheres.
Project Manager/s
& Supervisors
Physical
5 USE OF HAND
TOOLS
Falls of materials
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Bruising, cuts & sprains, puncturing, damage to property
• Provision of Toolbags or belts while working.
• Inspecting tools for loose and deficient parts. Report and replace immediately.
• If using tools at height, secure tool to you or scaffold.
• Toe-boards and brick guards/netting in place to prevent accidental dropping of tools or materials.
• Wear appropriate PPE (Gloves/Goggles/Hearing protection/Head Protection and Safety Footwear)
• Monitored job rotation of workforce.
Project Manager/s
& Supervisors
Noise/Vibration
Hand Arm Vibration, Vibration White Finger (VWF), WRULD’s Noise Induced Hearing Loss, Tinitus
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 5 of 17
Initial Risk Residual Risk No. Task &
Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Falls from Height Back Injury, Fractures, Cuts, Bruises, Death
Falls from Materials Head Injury, Death, Fractures, Cuts, Bruises
Slipping/Collapse Back Injury, Fractures, Cuts, Bruises, Death
Falls from Materials Head Injury, Death, Fractures, Cuts, Bruises
6 USE OF
LADDERS
Slipping/Collapse
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Back Injury, Fractures, Cuts, Bruises, Death
• Live Electrical work : Wooden
Ladders only • Ladder must extend 1m beyond
platform, at 75o angle or 4:1 Height to Base ratio.
• Ladder must be placed on firm level base.
• All ladders must be properly tied (not by styles) to a fixed sound structure
• Ladders must be inspected prior to use, and ladders must only be used for short duration light work and inspection, with one hand on the ladder as a minimum at all times. If this cannot be done another work platform is required.
• Tools should be secured to worker by toolbag/tool belt or lanyard.
• Deficient ladders must be destroyed.
• Hard Hats worn especially below ladder.
• Method Statement for work activity.
• If over 9m platform must be provided.
• Only one person on ladder at one time.
• Materials to be hoisted up or carried in toolbag.
• Working position should be not less than 5 rungs from top.
• Ladders must be 1 Industrial ONLY.
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 6 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Falls from Height
Back Injury, Fractures, Cuts, Bruises, Death
Falls of Material Head Injury, Death, Fractures, Cuts, Bruises
7
GENERAL ACCESS
SCAFFOLD
Collapse
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Back Injury, Fractures, Cuts, Bruises, Death
• Erected by Competent CITB Scaffolder.
• Scaffold must be inspected prior to erection/weekly/ altered and scaftagged.
• Firm Level base to be used, with suitable access/egress.
• Double handrail with the top hand rail erected to no less then 910mm with the gap between the toe board and mid guard rail and the mid and top guard rail to not exceed 470mm.
• Toeboards should be no less then 150mm,
• no more than 300mm gap between structure and scaffold.
• No overloading with materials. • Scafftag to be used. • Method Statement required for
work activity.
Project Manager/s
& Supervisors
Inhalation of Dust Fumes Vapours, vaporised metals
Lung Cancers & disease leading to death, asthma, sore eyes, vomiting
Contact with skin Dermatitis, sensitisation, skin diseases leading to cancer
8
Storage & Use of
Hazardous Substances (Oils, Paints, lubricants, sealants, solvents,
welding, wood grinder dusts)
(EH 44) (EH 40)
Contact with eyes
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Visual Impairness acute and chronic, burns. Conjunctivitis
• All substances must have
accompanied Material Safety Data Sheet requested from producer.
• COSHH Assessment on substance required suitable to work.
• PPE must be worn requested on label of tin/drum. If no label is on substance do not use it.
• Method Statement produced with safest possible system of work introduced.
• First Aider on site with adequate first aid facilities.
• All workers aware of hazards
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 7 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Falls of materials
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Death, or serious injury, fractures, bruises, cuts, and possible all of above
from COSHH Assessment. • Ensure adequate ventilation to
move or extract fumes, and respiratory equipment is worn
• Substances being used at height must be secured to fixed structure to prevent tipping or falling of substance.
• Storage of substances must be secure and of good construction with ventilation, placed in cool and shaded area and out of direct sunlight.
• Ensure substance and protective equipment is disposed of in accordance with Material Safety data Sheet.
• Always clean hands and face thoroughly before eating, drinking or smoking. Barrier creams and moisturisers.
• Suitable fire fighting equipment to be suitably located
• Adequate warning signs to be clearly displayed
Fire Property Damage, Injury to personnel, Death
Explosion Death, Property Damage
9
Storage & Use of
Liquefied Petroleum
Gases (LPG) FLAM>200C
Propane Butane or mix
of both
Asphyxiation
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Death or suffocation
• Method Statement required for
work activity. • Always wear gloves and
overalls when handling LPG dueto frosting.
• Adequate ventilation required for use and storage of LPG as it is asphyxiant and anaesthetic.
• No naked flames allowed near LPG.
• Use soapy water to detect leaks. If leak do not use any electrical equipment or
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 8 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Contact with skin
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Frost Burns, loss of limb
appliance with spark.
• LPG to be stored outside on a firm level base, with secure cage. Signs warning of LPG erected outside storage.
• Do not mix with Oxygen or HFL unless 3m gap is evident. 1.5 m distance from any fencing and 3m from any building, drain cellar, or excavation. Do not use in confined spaces, within 2m of lights.
• LPG to remain upright and secure at all times.
• Purpose made secure trolleys for transport of LPG on site.
• Fire Extinguishers in LPG locations.
Fire Property Damage, Injury to personnel, Death
Explosion Death, Property Damage
11
Storage & Use of Highly
Flammable Liquids (HFL)
FLAM<320C Petrol,
Oxygen, Oxyacetylene
MAPP
Contact with eyes
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Burns, Visual impairment.
• Minimum quantities to be held
of HFL on site. • Suitable fire resistant store
required with signage warning of HFL, with bunding, to contain and prevent release of liquids to drains that is 10% + volume stored.
• HFL to be kept in containers 5l capacity for petrol with max 50l and must be 2m from any buildings.
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 9 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Contact with skin
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Frost Burns, loss of limb
• Method Statement required for
work activity. • No naked flames allowed
near HFL, and suitable fire equipment near locations (Dry Powder/Foam).
• Spillages should be soaked up with sand or absorbent
• wearing appropriate PPE from label of tin/drum/cylinder and disposed of by manufacturers instructions.
• All spillages must be reported as incidents.
• Adequate ventilation required for use and storage of HFL.
• Materials Safety Data Sheets to be issued from supplier, and COSHH Assessment done on site.
12 WORKING AT HEIGHT AND
Falls from Height
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Back Injury, Fractures, Cuts, Bruises, Death
• Planned work to ensure safe access, working platform and system of work.
• Method Statement required. • Suitable signs and barriers
below work to inform others of work above.
• Edge protection above 2m with
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 10 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Falls from Materials
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Head Injury, Death, Fractures, Cuts, Bruises
double handrail and toeboards, or brick guards/fans to prevent materials falling.
• Harnesses worn where protection is not possible secured to fixed structure capable of weight.
• PPE including hard hats with chin straps must be worn by all.
• Working Platforms to be erected and used by Competent Persons.
• Roofs should be surveyed in plans prior to work commencing, with routes for safe walking.
• Tools should be suitably secured to prevent the fall of tools
Falls from Materials Head Injury, Death, Fractures, Cuts, Bruises, Burns, skin cancer
Spillages Burns, skin cancer,
13
STORAGE OF
MATERIAL/ PLANT AND EQUIPMENT
ON SITE Collapse/Collision
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives Head Injury, Death,
Fractures, Cuts, Bruises, Burns, skin cancer
• Safe storage of plant, materials and equipment should be detailed in method statement.
• Palletised loads should not exceed two pallets.
• Storage of pipes and cable drums shall be chocked or wedged.
• Compressed gas stored according to manufacturers instructions, upright and secure. No more than 2m high storage. Drums and containers marked up to identify hazards with proper spill control.
• Not to be stored in direct sunlight
Project Manager/s
& Supervisors
14
Use of Pneumatic/ Vibration
Tools (Drills,
Vibration
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Hand Arm Vibration, Vibrational White Finger (VWF), WRULD’s
• All equipment over 85dBA (Hard to hear others >1m normal voice) must ensure that Operatives and others wear ear plugs, over 90dBA ear
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 11 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Noise Noise Induced Hearing Loss, Tinitus
Electricity (Contact with live services)
Electric Shock Electrocution
Foreign Bodies Eye Injury, Loss of Sight, visual impairness
Concrete breakers Grinders
chain saws chop saws)
Inhalation of Fumes/mists
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Lung Cancers & disease leading to death, asthma, sore eyes, vomiting
muffs/defenders. • Risk assessment specific to
noise, and PPE and method statement required for activity.
• If breaking into walls or floors ensure cable detection is carried out prior to break.
• Survey existing drawings for cable runs and pipework. Identification of services carried out live or dead.
• Permit to Work issued for activity, with isolations/lock offs to existing services carried out.
• If tool has high vibration factor in Hz scale, assess duration of activity, and rotation of job to prevent prolonged use.
• exposure assessments required, and health surveillance.
• If short term exposure every few minutes reduction must be achieved, and short breaks frequently taken,
• Suitable PPE worn including padded gloves specific for VWFs. Compressors must be maintained and receive thorough examination.
• COSHH Assessment required for substances used such as lubricating oil.
• RPE and goggles will be required if mist/dust is present.
15 Lifting of Material/
Plant using mobile
Collision/Collapse
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s
Death, Serious Injury, property damage
• All lifting operations must be under control of an ‘appointed person’ who will be competent to take overall responsibility and
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 12 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Falls of material Death, Serious Injury, property damage
crane
Electricity/ overhead power lines
Representatives Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Electric Shock Electrocution
possess a method statement for the work activities.
• A Plan must be produced that considers weight of load, radius of lift, overhead clearance, ground conditions, positioning of crane, and lifting equipment required.
• An assessment of the ground conditions must be carried out by a competent person
• Crane must be sited with min 600mm clearance around. Distance from Overhead cables must be length of jib + 6m, and marked off to stop encroachment.
• Crane must have firm level base with load bearing checks made on ground to support weight of crane and load, shock loading, wind stress and slewing torques.
• Exclusion zones must be set up prior,during and dismantleling of lifting operations
15 Contd
Lifting of Material/
Plant using mobile crane
(PM 54) (PM 15) (PM 16)
Collision/Collapse
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Death, Serious Injury, property damage
• Erection of crane must be carried out by competent crane erectors.
• Operation of mobile cranes must be carried out by a competent certified person.
• Slinging of loads must be carried out by competent
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 13 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Falls of material Death, Serious Injury, property damage
(contd.)
Electricity/ overhead power lines
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Electric Shock Electrocution
certified persons, • Lifting zone should be identified
and cordoned off to prevent lifting over people.
• For cranes over 1 tonne ASLI’s, radius load indicators and motion limit switches must be fitted and operational by audio-visual methods. The SWL must be indicated on crane and never
exceeded. • Test load prior to lift by raising
150mm only. • Load must be correctly slung
and secured. • Loosed materials must be
carried in boxes/containers. • All lifting equipment must be
maintained to manufacturers instructions, generally weekly inspections by operative required. After 12 months a thorough examination (T.E.) or Fork lifting accessories (chains, slings) must have a thorough examination after 6 months and weekly inspection. Each rope must identify SWL.
Ingestion of Lead Lead Poisoning, kidney damage, constipation, weight loss
6
Working with Lead
Lead based paints
Soldering Welding,
cutting lead pipes
Inhalation of Lead
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Nerve and brain damage, teratogenic, lead poisoning
• Method statement for work activity is required with assessments of nature and extent of lead exposure.
• Reduce lead dusts, fumes and vapours where possible. Maximum Exposure Limit 0.15mg Lead /m3 Air over 8hr period must never be exceeded. If blood level is 50micrograms Lead / 100ml blood, workers
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 14 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Absorption of Lead Lead Poisoning, kidney damage, constipation, weight loss
must reduce exposure, if 60 micrograms worker must be signed off work.
• Proper PPE Assessment must be carried out with attention to Respiratory Protective Equipment, goggles.
• Adequate ventilation/extraction must be provided local to lead dusts/fumes/vapours.
• Material Safety Data Sheet and COSHH assessment required for all use and cutting of lead based paints, welding rods etc.
• Damp area and use wet removal of paint. Good hygiene, welfare facilities needed.
Poor operation Injury to person
Poor seal Death, or serious injury
17
Use of PPE (Personal protective
Equipment), RPE,
(Respiratory Protective
Equipment), Safety
Equipment Hard Hats Harnesses Respirator
Masks Breathing Apparatus
Ear Protection
Failure of Equipment
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Death or serious injury
• Employers must provide PPE, RPE, Safety equipment at all times when necessary.
• Ensure that all PPE, RPE is assessed for suitability for job, limitations, capability, compatibility with other PPE. additional hazards.A
• method statement for work activity is produced, with site-specific risk assessments.
• Read manufacturers instructions for weaknesses and correct installation or wear.
• Training or information/instruction should be given on use, storage and maintenance theoretically and practically. Ensure that PPE is adequate for job activity,
• And all operatives exposed are warned by signage and toolbox talk. Ensure that suitable storage is available for Safety equipment on site.
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 15 of 17
Initial Risk Residual Risk No. Task &
Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Faulty Equipment Injury to Persons, death
Contact with Hazardous substances
Burns (hot & cold), serious injury.
Pressure systems
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Explosion / Fire, injury to persons
• Method statement required for installation, with hazards identified at design stage and control measures during construction and on start up provided.
• Connections to existing systems must be under permit to work, with isolations and lock off engaged.
• Warning signage must be in place where necessary
• Guards and emergency stop must be fitted prior to testing and commissioning.
• All plant and equipment must be left in a secure and fail safe operation while unattended.
• PPE must be worn. • Manual handling assessments
required. COSHH.
Project Manager/s
& Supervisors
Faulty Equipment Injury to Persons, death
Contact with Hazardous substances
Burns (hot & cold), serious injury.
Pressure systems Explosion / Fire, injury to persons
18
Installation of new plant and
equipment AHU’s
Chillers, Pipework Ductwork
Generators
Gas Inhalation
PB staff. Contractors’, Sub Contractors’, Visitors, EHS Dept., Public, Client’s Representative
Death, Asphyxiation
• Ensure supplier provides installation team with operating instructions, technical data and limitations.
• Certificate of test and examination required to prove safe operation from manufacturer (Declaration of Conformity).
• No one must enter ductwork under any circumstance.
• A safe system of work must be devised.
• Pressure must not be applied to system until full installation has occurred with Safety devices (PRV’s) installed.
• Only competent persons to pressure test.
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 16 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
19
Installation of Electrical
Wiring and plant
Distribution HV Switchgear
Panels Cables
Electricity Fire
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Electric Shock Electrocution Burns
• Survey must be carried out of all existing electrical circuitry and method statement produced for activity.
• On all new build equipment no work must be carried out live until continuity testing and commissioning has taken place.
• Connections to existing appliances must be carried out under a permit to work procedure.
• Reference to other hazards in this register must be adopted.
• Only competent electricians must be employed to carry out work in accordance with good Wiring practices.
• If live work is unavoidable a separate specific risk assessment will be required
• Suitable fire fighting equipment to be suitably located
Project Manager/s
& Supervisors
Electricity
Electric Shock Electrocution Burns
20
Testing and Commission Electrical t Distribution
Panels Cable
Fire
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Explosion Burns Death
• All work must be carried out under a permit to work system, electrical and general work for others in area.
• Method Statement must be carried out. Test equipment must be insulated, calibrated, and fused.
• Only trained, competent electricians n will be allowed to test circuits.
• Signs must be installed to warn of energisation and restricted access. Live work must be carried out in accordance with good practice
Project Manager/s
& Supervisors
LUSAIL DEVELOPMENT
SAFETY TEAM SSP09/F01 – Overall Site Risk Assessment Register
Lusail Development Safety Team Revision: 1SSP09/F01 Date : 05/01/07 Issue No: 01 Page : Page 17 of 17
Initial Risk Residual Risk No. Task & Activity Hazard Persons at Risk Risk S L R Control Measures S L R Risk Owner
Display Screen Equipment (DSE)
WRULD’s, RSI, Eye Damage, Stress, Headaches,
Electricity Death, Serious injury, burns
Slips, Trips and Falls
Sprains, strains, fractures
21
Office Work
Office Work
Passive smoking, Fire
Consultants,Contractors’, Sub Contractors’, Visitors, Safety Dept., Public, Client’s Representatives
Death, serious injury, burns, cancer.
• All computer workstations must have DSE Assessment carried out. Regular breaks per hour from screen. Eye test if user (>2hours/day).
• No overloading of power circuits, with testing carried out on all mobile equipment.
• Never use equipment unless given instruction to do so.
• Fire fighting equipment, evacuation plan and regular inspection of both carried out.
• Risk Assessment required for office area relating to fire.
• Audible alarms suitably located in office
• Fire wardens and suitable assembly points nominated and signs erected to inform.
• Emergency lighting required and checked monthly.
• All staff and appointed persons must receive regular training and this must be recorded
• Fire drills must be carried out and recorded
• All trailing cables must be protected by trip mat.
• Good housekeeping required not to block exits.
• No smoking or naked flames allowed in office, smoking only permitted in designated areas.
• Any sub contractor working in offices must be controlled and monitored. All office staff and visitors must sign in and out of the building.
• COSHH assessment for materials used in office
Project Manager/s
& Supervisors