river structures health check - foundry weir, milfordindustries which predate strutt’s textile...
TRANSCRIPT
2018s0632 - Foundry Weir Assessment (Final) v3.0 i
River Structures Health Check - Foundry Weir, Milford
Final Report
March 2019
www.jbaconsulting.com
2018s0632 - Foundry Weir Assessment (Final) v3.0 i
JBA Project Manager
Jeremy Benn
JBA Consulting
No.1 Broughton Park
Old Lane
Broughton
Skipton
North Yorkshire
BD23 3AQ
Revision History
Revision
Ref/Date
Amendments Issued to
Draft v1.0
November 2018
- Rachel Costigan,
DerwentWISE
Final Draft v2.0
December 2018
Edit to fish pass selection justification;
altered hydrology.
Rachel Costigan,
DerwentWISE
Final v3.0
11 March 2019
Minor re-structuring; increase in
emphasis on importance of cost/benefit
& technical performance. Incorporation
of Historical Assessment
Rachel Costigan,
DerwentWISE
Contract
This report describes work commissioned by Rachel Costigan on behalf of DerwentWISE, by a
letter dated 14th May 2018. Katie Burnham, Jon Whitmore and Jeremy Benn of JBA Consulting
carried out this work.
Prepared by .................................. Katie Burnham MSc BSc
Analyst
.................................................... Jon Whitmore BSC MIFM Prince 2
Technical Director
Reviewed by .................................. Jeremy Benn FREng MA MSc CEng CWEM FICE FCIWEM MASCE MIEI
Executive Chair
Purpose
This document has been prepared for the DerwentWISE Landscape Partnership which is hosted
by the Derbyshire Wildlife Trust. DerwentWISE is funded by the Heritage Fund and the 15
organisations within the Partnership.
Key members of the Partnership supporting this project are the Derbyshire Wildlife Trust, the
Environment Agency, the Derwent Valley Mills World Heritage Site, and Historic England (who
have also provided funding for this project).
Acknowledgements
Tania Pells and Rachel Costigan from the DerwentWISE Landscape Partnership provided
background information and facilitated the site visits with landowners. Ian Jackson and Adrian
Farmer were also an invaluable source of knowledge of the history of the weirs and the
associated mills. Jon Needle of Derwent Hydroelectric Power Limited and Julie Wozniczca of the
Trent Rivers Trust also provided useful background information.
2018s0632 - Foundry Weir Assessment (Final) v3.0 ii
Abutment
Upstreamcut-off
Downstreamcut-off
End sillStillingbasin
h
Apron
GlacisHydraulicjump
Erosionprotection
Weir crest
p
Upstream Water Level
Downstream Water Level
Drop inWaterLevel
Not to Scale
Carbon Footprint
A printed copy of the main text in this document will result in a carbon footprint of 58g
if 100% post-consumer recycled paper is used and 73g if primary-source paper is used.
These figures assume the report is printed in black and white on A4 paper and in duplex.
JBA is aiming to reduce its per capita carbon emissions.
Some Conventions
In river engineering, “left bank” and “right bank” are used to denote the position of a
feature as seen when looking downstream.
Distance across a river or weir is usually taken with the left bank as the reference point.
Where there are multiple components to a structure (such as piers) the convention is
to number these consecutively from the left bank.
“Tailwater” and “Headwater” refer to the downstream and upstream water levels on a
weir respectively.
Common terms used for a weir
2018s0632 - Foundry Weir Assessment (Final) v3.0 iii
Executive summary
JBA Consulting was commissioned to undertake an assessment of condition of Foundry
Weir on the River Derwent in Milford, as well as consider the feasibility of installation of
a fish pass and hydropower scheme at the site.
A condition assessment has previously been undertaken of this weir in 2016.1 It found
that all components of the weir and its adjacent structural elements were in a Fair or
Good condition – except for four sections of the iron weir crest plate/board and the
northern sluice gate (which is leaking and gradually deteriorating). There were mature
trees growing out of the river walls upstream of the northern sluice and also
downstream of the right weir abutment and in Pier No.5 of the former footbridge.
The southern (right bank) sluice gate which controls flow into the mill goyt and the
supply of water to the hydroelectric turbine downstream was refurbished in 2017 with
new timbers being installed and general repainting. As a result the condition grade of
this part of the weir structure has changed from 3 (Fair) to 1 (Very Good).
The condition of the weir has not materially changed since 2016. The mature trees and
saplings should be removed and the roots killed using an approved systemic weed killer.
The presence of an operational hydropower scheme downstream means that
opportunities for installation of a further scheme are likely to be limited (Section 5.4).
Several options for fish passage were considered; a Larinier fish pass with dedicated
eel pass facility within the left bank sluice channel and extending downstream from the
sluice gate (which would be removed) is recommended as the preferred option. A
prioritised series of costed actions are recommended (Section 6.2) to enable
recommendations to be taken forward to next stage design.
————————————————————————————————————————
1 Engineering Assessment of Foundry Weir, Milford. Report by JBA Consulting for DerwentWISE, December 2016.
2018s0632 - Foundry Weir Assessment (Final) v3.0 iv
Contents
1 Background 1 1.1 Introduction 1 1.2 Purpose of report 1
2 Historical Assessment 2 2.1 Derwent Valley Mills World Heritage Site 2 2.2 Heritage Designations 2 2.3 Assessment of Significance 2 2.4 Setting 3 2.5 Opportunities for Change without Damaging Sensitivities 3 2.6 Potential Interventions and Degree at Risk 3 2.7 Conclusions and Recommendations 3
3 Description of the weir 5 3.1 Location 5 3.2 Layout 6 3.3 Purpose of structure 8 3.4 Ownership 8 3.5 Ecology 8 3.6 Rights of way 8 3.7 Existing studies 8
4 Condition Assessment 9 4.1 Basis of assessment 9 4.2 Findings 9
5 Fish passage & hydropower 10 5.1 Approach 10 5.2 Hydrology 10 5.3 Flood risk 11 5.4 Hydropower feasibility 12 5.5 Fish pass feasibility 12 5.6 Design criteria 13
6 Conclusions and recommendations 16 6.1 Conclusions 16 6.2 Recommendations 16
Appendices
A Maps 17
B Options appraisal matrix 17
2018s0632 - Foundry Weir Assessment (Final) v3.0
1
1 Background
1.1 Introduction
Derbyshire Wildlife Trust hosts the DerwentWISE Landscape Partnership Project which
is seeking to safeguard and restore the unique landscape of the Lower Derwent Valley.
A key objective of the project is to understand risk to the Derwent Valley Mills World
Heritage Site associated with deterioration of condition of the historic mill weirs, and
to understand whether improvements to fish passage are feasible, and if so, what are
the preferred measures.
1.2 Purpose of report
The purpose of this report is to present an assessment feasibility of the
implementation of fish passage at Foundry Weir complex on the River Derwent north
of Milford. A condition assessment of Foundry Weir was previously completed by JBA
Consulting in 20162.
————————————————————————————————————————
2 JBA Consulting, 2016. "016s4759 - Foundry Weir Milford - Assessment (Final).docx
2018s0632 - Foundry Weir Assessment (Final) v3.0
2
2 Heritage Assessment
This section is a precis from the Heritage Assessment report prepared by Trent and
Peak Archaeology for the DerwentWISE Partnership in March 2019.
2.1 Derwent Valley Mills World Heritage Site
In 2001 Derwent Valley Mills World Heritage Site was inscribed on the World Heritage
List by the United Nations Educational, Scientific and Cultural Organisation (UNESCO).
Sites included on the World Heritage List are protected under the UNESCO Convention
Concerning the Protection of the World Cultural and Natural Heritage 1972 of which
the UK Government is a signatory.
The statement of Outstanding Universal Value for the Derwent Valley Mills World
Heritage Site emphasises the relationship of the industrial buildings and their
associated settlements to the River Derwent, which provides a constant focal point
through the entirety of the World Heritage Site.
As a key component connecting the industrial buildings to the river, the weirs are at
the core of the Outstanding Universal Value of the World Heritage Site.
The management plan for the World Heritage Site has as its core mission:
To maintain the Outstanding Universal Value of the Derwent Valley Mills World
Heritage Site by protecting, conserving, presenting, enhancing and
transmitting its unique culture, heritage, economy and landscape in a
sustainable manner.
Any proposed works which have the potential to cause harm to the Outstanding
Universal Value of the World Heritage Site are unacceptable.
Any proposed works should utilise opportunities for intervention or change which do
not harm the Outstanding Universal Value of the World Heritage Site.
2.2 Heritage Designations
DERWENT VALLEY MILLS WORLD HERITAGE SITE List Entry No.: 1000100
Foundry Weir, Milford falls within the Derwent Valley Mills World Heritage Site. The
Statement of Outstanding Universal Value specifically highlights the importance of the
relationship of the industrial buildings and settlements to the river and topography. It
should therefore be considered that any scheme of works that impacts upon the weir
has the potential to affect the Outstanding Universal Value of the World Heritage site.
RETAINING WALLS TO WEIR ADJACENT TO GLOW WORM FOUNDRY List Entry No.
1087361
The retaining walls of the weir are Grade II* listed.
BELPER & MILFORD CONSERVATION AREA - Amber Valley Borough Council
The Belper & Milford Conservation Area covers the industrial structures and associated
settlements built to house the Strutt factory communities.
2.3 Assessment of Significance
Evidential Value
The Foundry Weir provides evidence of exploitation of the watercourse for a range of
industries which predate Strutt’s textile mills including corn processing and fulling.
The alteration of the structure to power Strutt’s mills provides evidence for the
evolution and expansion of the industrial settlement of Milford. The current weir was
redeveloped immediately after the construction of Belper Horseshoe weir, and also
included flood gates, showing the ongoing innovation of weir construction through the
Derwent valley.
2018s0632 - Foundry Weir Assessment (Final) v3.0
3
As at other sites there is a high potential for survival of the remains of pre-industrial
structures such as mills, fishing weirs or crossing places.
Historical Value
The weir is associated with the later Strutt foundry and Milford Cotton Mills but
predates Strutt’s association with Milford.
Aesthetic Value
Foundry Weir was constructed to divert water to mills further downriver. However,
there are no substantial industrial buildings in the immediate vicinity and no direct
visual association with the mills further downriver.
More recent development on the left bank of the river, despite containing elements of
industrial reference in the architecture is in general unsympathetic and has had a
negative impact on the aesthetic value of the site.
Recent work has cleared out features such as the sluice gates, making the site more
visibly accessible.
Communal Value
The weir is accessible from a public right of way along the left bank of the river, and
its history and purpose is explained by a nearby information board. The site has
recently been cleared and enhanced by the local community and the site is regularly
visited as part of heritage tours.
2.4 Setting
The river is set within a largely ‘natural’ landscape with wooded slopes to the right
bank of the river, and osier beds on the left bank. The modern development on the
left bank has negatively impacted on the setting of the weir, reducing its contribution
to overall significance.
The setting of the weirs makes a substantial contribution to their aesthetic value and
therefore to their significance. Any alteration to the landscape surrounding the weir
has the potential to impact upon its significance and thereby on the Outstanding
Universal Value of the World Heritage Site.
2.5 Opportunities for Change without Damaging Sensitivities
Fish Passage
From a heritage perspective, existing sluice gates and bypass channels could
potentially be utilised to provide a fish passage without harming the Outstanding
Universal Value of the World Heritage Site. Existing watercourses run from upriver of
the duck-bill weirs to upriver of Foundry weir through the former mill site. These water
courses should be investigated as a potential fish passage.
2.6 Potential Interventions and Degree at Risk
The following potential intervention has been identified in this report:
Fish Passage within the left bank sluice channel and removal of sluice gate
The location of a fish passage within the left bank sluice channel would minimise the
impact on the aesthetic value of the weir. However, the removal of the sluice gate
would negatively impact on the evidential value of the structure. In addition, the sluice
gate has been proposed for repair by Derwent Hydro-electric in order to facilitate
maintenance of the weir. Maintenance and conservation of the sluice gate would add
to the integrity and authenticity of the Outstanding Universal Value of the World
Heritage Site and therefore should take precedence over its removal.
2.7 Conclusions and Recommendations
2018s0632 - Foundry Weir Assessment (Final) v3.0
4
As the site lies both within the World Heritage Site and Belper & Milford Conservation
Area, where possible the preference should be for adaptation of existing water courses
to reduce the overall impact on the setting and aesthetic value of the sites, which will
in turn prevent harm to the Outstanding Universal Value of the World Heritage Site.
In order to reduce the impact on the aesthetic values of the structures the introduction
of new materials should be where possible using traditional techniques, and
complementary and sympathetic materials e.g. masonry rather than concrete. The
visual impact of any work should be minimised as far as possible to maintain the
authenticity of the Outstanding Universal Value.
Any impact on evidential value should be minimised, but where necessary should be
mitigated through a process of archaeological evaluation to gain as much information
on the material lost or altered during the works.
The Derwent Valley Mills World Heritage Site Research Framework provides a list of
key questions relevant to archaeological investigation of these sites:
2C – Investigate riverine locations for archaeological traces of early mills and other
historic water management assets
4C – Investigate the impact of natural resources and geography upon the Derwent
Valley textile industry and evaluate the distinctiveness of the Derwent’s resource
base
8D – Investigate the harnessing of hydropower from rivers in the Derwent
catchment and the reconciliation of competing interests
As specific designs are developed, a detailed Heritage Impact Assessment should take
place for each site. This will involve assessing the existing significance values (as
outlined in the criteria above) against the impact that the works will have on those
values. In each case the negative impact on the values should be minimised.
It is recommended that Heritage Impact Assessment takes place during the
development stage of any proposed works in coordination with the engineering group
or contractor to ensure that proposed designs do not harm the Outstanding Universal
Value of the World Heritage Site, and to minimise impact on the individual sites and
structures.
Larger programmes of maintenance and repair should also be subject to a process of
Heritage Impact Assessment.
2018s0632 - Foundry Weir Assessment (Final) v3.0
5
3 Description of the weir
3.1 Location
The foundry weir complex is located at OS NGR: SK 34861 45403 approximately 400m
upstream of Derby road bridge, and 500m upstream of Duckbill Weirs.
Figure 3.1: - Location of Foundry Weir
Contains Ordnance Survey data © Crown copyright and database right 2018.
2018s0632 - Foundry Weir Assessment (Final) v3.0
6
3.2 Layout
The foundry weir has four main components (Figure 3.2), as detailed below.
Figure 3.2: - Components of Foundry Weir structure
1. A concave or ‘horseshoe’ masonry weir crest, with a wide (50m) shallow
sloping weir glacis. The crest extends for approximately 80m across the
channel.
2. Notch in the weir crest, as a result of damage to the weir.
1
2 3
4
2018s0632 - Foundry Weir Assessment (Final) v3.0
7
3. Left bank sluice gate and mechanism, channel downstream of gate joins
back into main channel downstream of the weir apron.
4. Right bank sluice gate, leading into mill run that feds hydropower downstream at Duckbill Weirs.
2018s0632 - Foundry Weir Assessment (Final) v3.0
8
3.3 Purpose of structure
The purpose of the structure historically would have been to maintain upstream water
levels in the mill leat downstream, fed by the right bank sluice gate. The historic water
wheel has since been removed and the leat now feds a new hydroturbine downstream
at Duckbill Weir.
3.4 Ownership
The ownership of the Weirs is unknown to the authors, but it is believed to be in
private ownership.
3.5 Ecology
The following statuary ecological designations are present within a 5 km radius of the
site3:
Allestree Park (LNR) – 4.3km south of the site
Duffield Millennium Meadow (LNR) – 2km south of the site
Belper Parks (LNR) – 1.5km north of the site
Kedleston Park (SSSI) – 4.8km south west of the site
3.6 Rights of way
There are no public rights of way adjacent to the river in the vicinity of the weir
complex4.
3.7 Existing studies
An outline design for a fish pass solution at this structure has already been produced5.
The design consists of a rock ramp extending downstream from the relic sluice on the
left bank.
Harton et al 2012 have undertaken an assessment of hydropower resource in the
Derwent Valley including the Foundry weir complex. The site includes an offtake for
an operational 180kW Francis turbine with a design flow of 6.3m3/s 6.
————————————————————————————————————————
3 Source: Statutory ecological designations from Magic https://magic.defra.gov.uk/MagicMap.aspx. Accessed 20th November 2018.
4 Source: Derbyshire County Council Mapping Portal [Accessed 26th Nov 18]. Available from: https://maps.derbyshire.gov.uk/connect/analyst/mobile/#/main?mapcfg=Ordnance_Survey_Maps
5 Fish passage in the Derwent Valley World Heritage Site. Presentation material authored by Trent Rivers Trust.
6 Harton, S., Chandler, P. & Beardmore, J., 2012. Estimate of Hydro Resource in the Derwent Valley. Report for Transition Belper.
2018s0632 - Foundry Weir Assessment (Final) v3.0
9
4 Condition Assessment
A condition assessment has previously been undertaken of this weir in 2016.7
4.1 Basis of assessment
The condition assessment is based on the 2016 report plus a new visual inspection by
Jeremy Benn of the weir and its surroundings on 14 August 2018 (a day of relatively
low flow). Access to the structure other than by public rights of way wasn’t possible
and observations were limited to using binoculars from a position on the river bank.
The conclusions that are drawn must therefore be read in the context that there could
be damage or other defects to the weir that could not be detected without entering
the river and undertaking a probing survey.
Condition grades have been based on the widely used ‘Condition Assessment Manual’
published by the Environment Agency (March 2012 issue). The grades range from 1
(Very Good) to 5 (Very Poor), as shown below:
4.2 Findings
All components of the weir and its adjacent structural elements were in a Fair or Good
condition as in 2016 – except for four sections of the iron weir crest plate/board and
the northern sluice gate (which is leaking and gradually deteriorating). There were
mature trees growing out of the river walls upstream of the northern sluice and also
downstream of the right weir abutment and in Pier No.5 of the former footbridge.
The southern (right bank) sluice gate which controls flow into the mill goyt and the
supply of water to the hydroelectric turbine downstream was refurbished in 2017 with
new timbers being installed and general repainting. As a result the condition grade of
this part of the weir structure has changed from 3 (Fair) in December 2016 to 1 (Very
Good) today.
The condition of the weir has not materially changed since 2016. The mature trees
and saplings should be removed, and the roots killed using an approved systemic
weed killer.
————————————————————————————————————————
7 Engineering Assessment of Foundry Weir, Milford. Report by JBA Consulting for DerwentWISE, December 2016.
Grade Rating Description
1 Very Good Cosmetic defects that will have no effect on performance
2 Good Minor defects that will not reduce the overall performance of the asset
3 Fair Defects that could reduce performance of the asset
4 Poor Defects that would significantly reduce the performance of the asset. Further investigation needed
5 Very Poor Severe defects resulting in complete performance failure
2018s0632 - Foundry Weir Assessment (Final) v3.0
10
5 Fish passage & hydropower
5.1 Approach
Design criteria in the following documents have been used to produce a list of options
for fish passage measures at the site and to consider feasibility of installation of a
hydropower scheme:
Environment Agency Fish Pass Manual8. This reference provides a
framework for decision making on selecting suitable fish passage options;
this piece of work has used a combination of the framework listed in this
reference, as well as expert judgement to propose potential fish passage
solutions.
Environment Agency Guidance for run of river hydropower development9.
Environment Agency Guidance for run of river hydropower development -
Competing hydropower schemes10.
It should be noted at this point that all the fish pass solutions considered in this study
are likely to be expensive to construct (>£0.5M). Whilst the importance of minimising
the risk of any negative environmental impacts associated with the construction and
operation of any fish pass solution cannot be emphasised enough, particularly with
regard to the important heritage receptors in the immediate area of the weir,
construction costs of this magnitude mean that achievement of optimal fish passage
efficiency has to be a core design criteria; compromise to passage efficiency would
quickly render such significant expenditure non-cost beneficial.
5.2 Hydrology
There is an existing Environment Agency gauge located at Horseshoe Weir,
approximately 4.5km upstream of the site, although this is a level gauge only.
The nearest flow gauge downstream is at St Mary's, Derby, approximately 11.5 km
downstream (NGR 435390 336880 Station ID 4085). It is important to note however
that a number of inflows join the Derwent between Foundry weir and the St Mary's
gauging station, these include:
River Ecclesbourne 2.5km downstream
Bottle Brook 5.25km downstream
Boosemoor Brook 6km downstream
Dam Brook 9.3km downstream
The nearest flow gauge upstream is at Whatstandwell, approximately 11.5km
upstream (SK0331405456; ID 28117). It is important to note however that a number
of inflows join the Derwent between Foundry weir and the Whatstandwell gauge
however; these include:
Peatolts Brook, approximately 7km upstream.
Pendleton Brook, approximately 6km upstream.
River Amber, approximately 3.8km upstream. This inflow is substantial and drains a catchment area of approximately 140km2, compared to a
catchment area of the Whatstandwell gauge of approximately 755km2. A
flow gauge exists at Wingfield Park, approximately 5km upstream of the
confluence with the Derwent.
————————————————————————————————————————
8 Environment Agency Fish Pass Manual: Guidance Notes On The Legislation, Selection and Approval Of Fish Passes In England And Wales. 2010. Environment Agency, Bristol.
9 Guidance for run of river hydropower development. LIT 4122. 2017. Environment Agency, Bristol.
10 Guidance for run of river hydropower development - competing hydropower schemes. LIT 7517. 2017. Environment Agency, Bristol.
2018s0632 - Foundry Weir Assessment (Final) v3.0
11
Coppice Brook, approximately 2.7km upstream.
Given the approximate scale of ungauged catchments between Foundry weir and the
Whatstandwell/Wingfield Park and St Marys/Duffield gauge options, it was decided
that the Whatstandwell/Wingfield Park option is most reflective of the situation at
Duckbill. Mean daily flow data for the full record was obtained from the National River
flow Archive (NRFA) for the Whatstandwell gauge (1st January 1997 to 30th
September 2017) and Wingfield Park (1st January 1997 to 30th September 2017) and
a flow duration curve constructed using that data - Figure 5.1.
Key flow statistics based on the Whatstandwell mean daily flow dataset are
summarised below and expressed as the percentage of time that flow is exceeded
at key flows relevant to the designed-for species of interest:
Flow exceeded 95% of the time (Q95) – 0.71m3/s
Average daily flow (Qmean) – 12.07 m3/s
Flow exceeded 10% of the time (Q10) – 26.83m3/s
It was beyond the scope of this study to refine flow data from the nearest gauge.
Figure 5.1 - Flow duration curve – Whatstandwell & Wingfield Park
5.3 Flood risk
A copy of the current flood model for the River Derwent was requested from, and
supplied by, the EA. The supplied model (linked 1D/2D) includes Foundry Weir. The
hydrology within the model has made an allowance of 20% above the 100-year return
period flood flow value to reflect the impacts of climate change.
Current climate change guidance11 specifies differing allowances for increases in flood
flow depending on the type of development; a hydropower scheme is likely to be
classed as Essential Infrastructure whereas a stand-alone fish pass scheme is likely
to be classed as Water-compatible Development. Assuming a design life of 30 years
for both a hydropower scheme and a fish pass scheme, and therefore the need to
consider the impacts of climate change into the 2050s, it is recommended that the
————————————————————————————————————————
11 Guidance - Flood Risk and Coastal Change. Gov.uk. 2014. [viewed 30th October 2018]. Available from
https://www.gov.uk/guidance/flood-risk-and-coastal-change#flood-zone-and-flood-risk-tables
0
50
100
150
200
250
0 10 20 30 40 50 60 70 80 90 100
Flo
w (m
3/s
)
Percentage of time equalled or exceeded
2018s0632 - Foundry Weir Assessment (Final) v3.0
12
following allowances are made above the 100-year flood flow to predict the flood risk
impacts arising from the scheme when considering the impacts of climate change:
standalone hydropower scheme - 30%
standalone fish pass scheme - 15%
5.4 Hydropower feasibility
Hands off flow
Hands off flow is a condition of any hydropower licence issued by the Environment
Agency (EA) which is the flow at which abstraction must stop, to maintain flow in the
river for the purposes of maintenance of natural ecological processes.
The EA confirms that the site is within Abstraction Sensitivity Band 3 - High Sensitivity
(A Lumsdon, pers comm). When considering the Q95/Qmean value is 0.3 (meaning
the river has a high base flow), Table A of the EA Guidance for run-of-river hydropower
development indicates that the EA would likely apply a Hands off Flow exceedance
value of Q97, limit turbine abstraction to Qmean (4.4m3/s) and the percentage of take
above HoF to 35%. It should be highlighted that the EA may be willing to licence a
variation from these guideline values if various conditions are met; only direct
engagement with the EA would clarify the likelihood of licensing such variation.
Flow split
Considering the above guideline scenario of a peak turbine abstraction of 4.4m3/s, the
minimum acceptable flow to any fish pass installed as part of any hydropower scheme
would likely be 0.4m3/s at Q95.
Other
The presence of an existing hydropower scheme offtake substantially complicates the
feasibility of installation of any subsequent hydropower scheme. It is highly likely that
there is insufficient, un-used water resource at the site to enable the development of
a second hydropower scheme without the need for substantial engagement and
negotiation with the operator of the existing scheme, Derwent Hydro.
In the unlikely event that the existing operator is willing to negotiate a re-
apportionment of the licensable water resource to enable establishment of a second
scheme, it is likely that the following issues will be key to enabling any scheme to
secure appropriate licences:
Co-location of two parallel schemes (which, to all intents and purposes,
would likely mean a single large scheme) will likely be looked on more
favourably than two independent schemes that are remote from each
other, i.e. one on the main river channel, one on the mill leat.
The schemes will need to ensure that any re-apportionment of flow does
not compromise achievement of Water Framework Directive objectives by
resulting in changes to the existing flow split that give rise to any depleted
reach that is more ecologically-constraining than current.
Early engagement with the EA would be essential in ensuring efficient progression and
delivery of any second hydropower scheme.
5.5 Fish pass feasibility
Options
Topographic survey has been supplied for the Foundry weir and associated sluice
structures at the site (Figure ). The glacis of the weir extends for approximately 50m,
and has an estimated overall height of up to 2m. Surveyed water levels provided on
the topographical data indicate a head of at approximately 2m on the day of survey.
The below option was considered but discounted on the grounds specified:
2018s0632 - Foundry Weir Assessment (Final) v3.0
13
Any option associated with the right bank sluice, leading into the mill leat
as a result of both the existing hydropower scheme downstream and the
large culverted section of the leat itself presenting a behavioural barrier
to migration.
Options taken forward and considered in more detail are given below:
1. Larinier fish pass with dedicated eel pass facility within the left bank sluice
channel, and extending downstream from the sluice gate (which would be
removed)
2. Pool and traverse within the left bank sluice channel extending downstream
from the sluice gate (which would be removed)
3. Regularisation of left-hand extent of weir glacis downstream of left bank notch
and installation of low-cost baffle arrangement on resulting slope
4. Partial rock ramp on left side of the weir glacis downstream of left bank notch.
5.6 Design criteria
Impact on the following design criteria have been used in the appraisal of the above
2 options:
Designed-for species: engagement with local staff from the Fisheries
function of the EA (A Lumsdon, pers comm) confirms that the designed-for
species of any proposed fish passage measure are as follows:
o Atlantic Salmon
o Brown Trout and sea trout
o Coarse fish
o European eel
Hydromorphic condition
Engineering feasibility
Heritage features of interest
Landscape and visual impact
Stakeholder opinion
Public health and safety
Operational phase - maintenance
Appendix B presents a rapid assessment of the two options proposed above in the
context of the above design criteria. Each criterion is assigned a score using the
regime given in Error! Reference source not found. below.
Table 5.1 - Scoring of design criteria
Score Achievement of criteria
3 Significant positive impact (compared to existing)
2 Moderate positive impact
1 Minor positive impact
0 Neither positive or negative impact
-1 Minor negative impact
-2 Moderate negative impacts
-3 Significant negative impact
2018s0632 - Foundry Weir Assessment (Final) v3.0
14
Figure 5.2: - Topographic survey at the site
Foundry weir
Left bank sluice – main channel
Right bank sluice – upstream mill leat
2018s0632 - Foundry Weir Assessment (Final) v3.0
15
2018s0632 - Foundry Weir Assessment (Final) v3.0
16
6 Conclusions and recommendations
6.1 Conclusions
Appendix B suggests that Option 1 - Larinier fish pass with dedicated eel pass facility
within the left bank sluice channel and extending downstream from the sluice gate
(which would be removed) is the recommended solution. The Grade II* listed status
of the weir and sluices and the location being within the boundary of the World
Heritage Site means that there is a necessity to consider in detail the compatibility of
the recommended solution and the heritage value of the structure to confirm
feasibility.
Although there are other statutory ecological designations within 5km of the structure
their proximity means they are unlikely to be impacted by implementation of the
recommended solution.
6.2 Recommendations
The promotor of any fish pass scheme is recommended to undertake the following
work, given in priority order, to inform next stage design of any fish passage and
hydropower scheme:
1. Engage with Derwent Hydro to determine feasibility of a renegotiation of their
existing abstraction licence.
2. Undertake a services search of the immediate area around the weir to identify
the presence of any services that may constrain or limit feasibility (approx.
£0.5k).
3. Commission a contractor to provide Early Contractor Involvement to inform
next stage feasibility/design (approx. £1.5k).
4. Produce a concept design of the proposed fish passage solution to determine
outline geometry to further inform feasibility (approx. 1k).
5. Scale the hydrology data from the St Marys gauge to determine a more
precise flow at the Foundry Weir site (approx. £1k)
6. Undertake a desktop geological study, or Phase 1 contaminated land study,
to determine bedrock/superficial geology and risk of accumulated
contaminated sediments upstream of the weir to inform construction
options/feasibility (approx. £1.5k).
7. Consider installing a water level data logger downstream of the weir to
complement the same available upstream, to inform design water levels for
any solution, or use the hydraulic model to determine approximate design
head (approx. £3k - £5k).
8. Undertake a Preliminary Ecological Appraisal to define the ecological baseline
in the area of potential works (approx. £2.5k).
Indicative design costs associated with the recommended option, excluding those
given above, are given below:
Outline design - £10,000
Detailed design - £75,000
Indicative constructed costs for the considered options are given in Appendix B.
2018s0632 - Foundry Weir Assessment (Final) v3.0
17
Appendices
A Maps
B Options appraisal matrix
Offices at
Coleshill Doncaster Dublin Edinburgh Exeter Glasgow Haywards Heath Isle of Man Limerick Newcastle upon Tyne Newport Peterborough Saltaire
Skipton Tadcaster Thirsk Wallingford Warrington Registered Office No.1 Broughton Park Old Lane Broughton SKIPTON North Yorkshire BD23 3AQ United Kingdom +44(0)1756 799919 [email protected] www.jbaconsulting.com Follow us: Jeremy Benn Associates Limited Registered in England 3246693 JBA Group Ltd is certified to: ISO 9001:2015 ISO 14001:2015 OHSAS 18001:2007