Riverside Industrial Park Superfund Site
• Long industrial history - paints & varnish to cosmetics & packaging
• 2009 – EPA traced Passaic River discharge to pipe on site
• 2009-2014 - EPA found illegally stored chemicals & took several actions including:– plugging discharge pipes– removing drums & tanks
• 2013 - added to Superfund List• 2014 - EPA signed agreement
with PPG to study the site
Region 2 serving the people of New Jersey, New York, Puerto Rico and the U.S. Virgin Islands
1
Riverside Industrial Park
Riverside Status• 2017 – EPA approved the Remedial Investigation / Feasibility Study
(RI/FS) Work Plan • August 2017 to June 2018 - Phase 1 field investigations• January 2018 – City of Newark executed redevelopment agreement:
– 5 Lots within the Site and 6 Lots North of the Site– Future warehousing/light manufacturing– Environmental remediation
• March 2018 – EPA approved PPG’s aggressive 2-year schedule to RI/FS completion – Timed to coincide with redeveloper’s 2 year due diligence period
Region 2 serving the people of New Jersey, New York, Puerto Rico and the U.S. Virgin Islands
7057
16465
63
68
67
300 Penn Center Boulevard | Suite 800 Pittsburgh, PA 15235412-241-4500 | www.woodardcurran.com
COMMITMENT & INTEGRITY DRIVE RESULTS
#16
#13
69
59#14
58#15
#10
#2
#160#6
61
62#9
#12
#7
#3#15A
#19
61#17
#4#5
#17A 66
#17#7A
#23
LOT NUMBER
BUILDING NUMBER
LEGEND
FORMER BUILDING FOOTPRINT
APPROXIMATE SITE BOUNDARY
APPROXIMATE LOT BOUNDARY
VACANT BUILDING
Site Map
Phase 1 Investigation (Summer 2017-Summer 2018)
Phase 1 Investigation Summary• Efforts completed:
– Ground Penetrating Radar survey – Evaluations of abandoned buildings, containers/tanks, sewers and
subsurface piping – Soil Sampling
• 14 Surface Soil samples• 69 Soil Borings (surface and deeper samples)
– Groundwater Sampling• 30 Monitoring Wells• Sampled in March and June
– Sewer and abandoned containers sampling– Tidal evaluation
Region 2 serving the people of New Jersey, New York, Puerto Rico and the U.S. Virgin Islands
Riverside Next Steps• Sept/Oct 2018 – PPG
submitted:– Phase 2 Field
Investigation Work Plan– Conceptual Site Model– Pathways Analysis Report
(for the Risk Assessment)– Identification of
Candidate Technologies Memo (for the Feasibility Study)
• Documents under review
Region 2 serving the people of New Jersey, New York, Puerto Rico and the U.S. Virgin Islands
• Phase 2 Remedial Investigation (RI) Field Work –December thru February 2019
• Risk Assessment Process –now thru Summer 2019
• RI Completion – Fall 2019• Feasibility Study – now thru
Spring 2020• Proposed Plan – Summer 2020
• Continued CAG presentations/opportunity for feedback (whole group or sub-committee)?
• Assist with local North Ward contacts/outreach?
• Engage with City officials on redevelopment plans?
Timeline & Potential Areas for CAG Involvement