rmh tower flood proofing fact sheet
DESCRIPTION
project design features showcased at The 5th National FloodProofing Conference and ExpositionLevees and Beyond: Making Wise ChoiceTRANSCRIPT
Design Measures to Implement for an Operational Hospital During Flooding Rideout Regional Medical Center
Facility Rideout Memorial Hospital
TypeRegional Medical Center
Size of Facility215,000 sq. ft.
Location Marysville, CAYuba County
Population 12,072 in city72,155 in county
Client ContactMr. Tony ModdesetteVice President, Facilities and Projects
Architect of RecordStafford King Wiese Architects Associate Architect, Kelly Architecture & Planning
Structural EngineerBuehler & Buehler Structural Engineers, Inc.
Mechanical/PlumbingFrank M. Booth Design Build, Co.
Electrical EngineeringToft Wolff Farrow, Inc.
Located 40 miles north of Sacramento, Marysville is flanked by rivers and levees on three sides. The Feather River is to the west, and to the south and east the Yuba River boarders the city. The two rivers converge just southwest of the city. Due to the proximity of the Sierra Nevada moutains, snow runoff or heavy rain from winter storms present a significant flooding risk to the city.
When Fremont-Rideout Health Group decided to expand their Rideout Memorial Hospital into a Regional Medical Center, the design team took the opportunity to implement certain “flood proofing” measures into the design. Because Marysville is in a natural flood plain, it was likely that routine flooding may occur in the region and it was important that this critical care facility could stay operational and continue to serve the community.
9 1 6 . 9 3 0 . 5 9 0 0 s k w a i a . c o m
Feather River
Yuba River
MARYSVILLE
Rideout Memorial Hospital
Rideout Regional Medical Center
water levelsEstimates of routine flooding water levels between •zero and 10 feet
100 year flood plain estimates water levels to reach •26 feet
flood-proofing measures
architectural solutionsDue to flood risk, all utilities are located above ground •floor and building design omitted basement
Emergency food storage room located on 6th floor•
structural solutionsEmergency generators are 50,000 pounds each with •an additional 20,000 pounds of concrete curbs - this equipment caused a 50% increase in steel weight in this area
Main electrical room and associated equipment with •housekeeping pads - caused a 35% increase in steel weight to support the room
Emergency generator at the main roof is estimated to •be 6,800 pounds. - caused an increase in the supporting steel for the single pad
The braced frame lateral system was significantly •impacted in the area affected on the 2nd floor level. The brace sizes and associated connections increased due to the amount of weight added to the structure. As many as eight of the braced frames have increased loading at the 2nd floor level. However, the seismic anchorage demand on the units attached to the low roof at the 2nd floor level is nominally larger and yields similar anchorage. The foundation system has slight increases but the capacity of the auger cast pile system allows for the flexibility to move the electrical system up to the 2nd floor level with little impact.
mechanical & plumbing solutionsWith the exception of the bulk oxygen and specialized •surgical gasses, all major mechanical and plumbing equipment needed to maintain ventilation, heating and med gas needs for patient care are located on the 6th floor.
Domestic water and propane connections are provided •in the penthouse to provide emergency water and heating needs.
electrical solutionsMain electrical room and emergency generators located •on the 2nd floor at 15 feet above grade level
An additional housekeeping pad was provided on the •tower’s roof to allow emergency portable generator to be air-lifted to the building and installed for temporary use
A mechanism was integrated to de-energize the 1• st and 2nd floor in the event of flooding. To do this, “kirk-key” operated breakers were specified to disconnect all electrical lines (branch circuits and feeders) at the third floor. To operate at kirk-key breaker, one physically takes a “key” from the breakers on the 3rd floor and “turns” this breaker to the “open circuit” position so that no current will flow between floors 2 and 3. Next, one removes this same “key” and proceeds to the roof, where a portable generator will be dropped on the roof from a helicopter and positioned near an electrical distribution panel. This panel will have breakers that are “keyed” to match the breakers on the 3rd floor. With the key from the 3rd floor, the roof breakers, after connecting to the portable generator will be “turned” to the “closed” position allowing current to flow until it reaches the “open circuit” on the third floor. Now the building is energized from a generator on the roof and the 1st and 2nd floors are de-energized.
Emergency generator units
on 2nd floor rooftop at 15
ft. above grade
helistop
additional housekeeping pad for emergency portablegenerator
Main electrical room
main electrical room; systems have ability to disconnect from 2nd floor during flooding
additional housekeeping pad for emergency portable generator
3rd floor = 31 ft.
2nd floor = 15 ft.
Rideout Regional Medical Center
aesthetic roof screen lengthened to enclose electrical room
Designated room on
6th floor for emergency
food storage
Designated room on
6th floor for emergency food
storage
All major mechanical
and plumbing equipment needed for
patient care is located on
6th floor