rockaway boardwalk reconstruction

43
Rockaway Boardwalk Reconstruction CB14 Parks Committee Meeting November 18, 2013 7:00 P.M. Knights of Columbus

Upload: others

Post on 30-Jan-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rockaway Boardwalk Reconstruction

Rockaway Boardwalk Reconstruction CB14 Parks Committee Meeting

November 18, 2013 7:00 P.M. Knights of Columbus

Page 2: Rockaway Boardwalk Reconstruction

2

Agenda

Rockaway Reconstruction

• Recap

• Community Meetings To Date

• Surface Treatment Survey Results

• Initial Construction Area

• Scope of Work

• Project Area Schematic and Renderings

• Amenities

• Surface Treatment Concepts

Page 3: Rockaway Boardwalk Reconstruction

3

Previous Community Meetings

Rockaway Reconstruction

Meeting Date

September 17, 2013 CB14 Parks Committee

Presentation – Background and

Constraints

September 23, 24, 25, 2013 Neighborhood Listening Sessions –

Access, Surface, Recreation and

Boardwalk Design

October 8, 2013 Full CB 14 Meeting – Update and

General Design Principles

October 23, 2013 Community Listening Session –

Access, Surface and Amenities

Page 4: Rockaway Boardwalk Reconstruction

4

Rockaway Reconstruction

Surface Survey Results 680 Respondents

0

50

100

150

200

250

300

Feel on your feet/roughness Ability to stay cool/temperature Unique Identity

Walking down the boardwalk, which of the following would you rate as most

important? Please choose 1.

Page 5: Rockaway Boardwalk Reconstruction

0

50

100

150

200

250

300

350

400

450

Bright Color Sparkle Special Material (shells or glass)

Sandy Memorial (examples on boards)

5

Rockaway Reconstruction

If you had to choose a way to highlight special areas of the boardwalk, what

would be your top choice? Please choose 1 or 2.

Surface Survey Results 680 Respondents

Page 6: Rockaway Boardwalk Reconstruction

0

50

100

150

200

250

300

350

400

450

Lighter (cooler but with more glare) Darker (warmer but less glare)

6

Rockaway Reconstruction

Which color preference is more important? Please choose 1.

Surface Survey Results 680 Respondents

Page 7: Rockaway Boardwalk Reconstruction

7

Rockaway Reconstruction

For special areas, which do you prefer for decorative finish? Please choose 1.

0

50

100

150

200

250

300

350

400

Tumbled Recycled Glass Colored Stone

Surface Survey Results 680 Respondents

Page 8: Rockaway Boardwalk Reconstruction

8

Rockaway Reconstruction

0

50

100

150

200

250

300

350

Entrances Playgrounds Sitting areas

0

10

20

30

40

50

60

What types of areas should have special accents (e.g. playgrounds, sitting areas,

entrances, etc.)

Please choose 1 or 2.

Surface Survey Results 680 Respondents

Page 9: Rockaway Boardwalk Reconstruction

0

50

100

150

200

250

300

350

Designated bike lane Informal bike lane Yes, bike lane No bike lane

9

Rockaway Reconstruction

Would you like to have a designated bike lane (marked with striped or special

paving) or an informal bike lane (with just signs)?

Surface Survey Results 680 Respondents

Page 10: Rockaway Boardwalk Reconstruction

10

Rockaway Reconstruction

0

50

100

150

200

250

300

350

Positive

Negative

Mixed

Overall Aesthetics Durability Texture Walking, Jogging,

and Biking

Do you like the existing precast planks on the boardwalk between Beach 77 and

Beach 81? Why or why not?

Surface Survey Results 680 Respondents

Page 11: Rockaway Boardwalk Reconstruction

11

Initial Construction Area Overall Site Plan

Rockaway Reconstruction

Page 12: Rockaway Boardwalk Reconstruction

12

Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design

Rockaway Reconstruction

Page 13: Rockaway Boardwalk Reconstruction

13

Boardwalk Accent Preliminary Concepts Option B: Bubble Design

Rockaway Reconstruction

Page 14: Rockaway Boardwalk Reconstruction

14

Boardwalk Accent Preliminary Concepts Option C: Wave Design

Rockaway Reconstruction

Page 15: Rockaway Boardwalk Reconstruction

15

Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design

Rockaway Reconstruction

Page 16: Rockaway Boardwalk Reconstruction

16

Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design

Rockaway Reconstruction

Page 17: Rockaway Boardwalk Reconstruction

17

Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design

Rockaway Reconstruction

Page 18: Rockaway Boardwalk Reconstruction

18

Boardwalk Accent Preliminary Concepts Option A: Graphic Text Design

Rockaway Reconstruction

Page 19: Rockaway Boardwalk Reconstruction

19

Boardwalk Accent Preliminary Concepts Option B: Bubble Design

Rockaway Reconstruction

Page 20: Rockaway Boardwalk Reconstruction

20

Boardwalk Accent Preliminary Concepts Option B: Bubble Design

Rockaway Reconstruction

Page 21: Rockaway Boardwalk Reconstruction

21

Boardwalk Accent Preliminary Concepts Option B: Bubble Design

Rockaway Reconstruction

Page 22: Rockaway Boardwalk Reconstruction

22

Boardwalk Accent Preliminary Concepts Option C: Wave Design

Rockaway Reconstruction

Page 23: Rockaway Boardwalk Reconstruction

23

Boardwalk Accent Preliminary Concepts Option C: Wave Design

Rockaway Reconstruction

Page 24: Rockaway Boardwalk Reconstruction

24

Boardwalk Accent Preliminary Concepts Option C: Wave Design

Rockaway Reconstruction

Page 25: Rockaway Boardwalk Reconstruction

Boardwalk Lighting Height Options

Rockaway Reconstruction

Lighting Option: 30’ Davit Pole

Page 26: Rockaway Boardwalk Reconstruction

Boardwalk Lighting Height Options

Lighting Option: 16’ Davit Pole

Rockaway Reconstruction

Page 27: Rockaway Boardwalk Reconstruction

27

Lighting Options

Rockaway Reconstruction

City Light LED

Fixture

Solar LED Lighting Davit Pole with

LED Cobra

Head

TBTA Pole

Page 28: Rockaway Boardwalk Reconstruction

28

Lighting Option Davit Pole with Cobra Head

Rockaway Reconstruction

Page 29: Rockaway Boardwalk Reconstruction

29

Lighting Option TBTA Pole with Teardrop Head

Rockaway Reconstruction

Page 30: Rockaway Boardwalk Reconstruction

30

Lighting Option City Light

Rockaway Reconstruction

Page 31: Rockaway Boardwalk Reconstruction

31

Lighting Option Solar Swan – 25’

Rockaway Reconstruction

Page 32: Rockaway Boardwalk Reconstruction

32

Lighting Option Solar Swan – 15’

Rockaway Reconstruction

Page 33: Rockaway Boardwalk Reconstruction

33

Boardwalk Elevation Initial Construction Area

Rockaway Reconstruction

Page 34: Rockaway Boardwalk Reconstruction

34

Boardwalk Construction Engineering Elements

Rockaway Reconstruction

Page 35: Rockaway Boardwalk Reconstruction

35

Boardwalk Construction Pile Cap Removal and Pile Extensions

Rockaway Reconstruction

Demolition of Existing Pile Cap Pile Cap

Extension Detail

Page 36: Rockaway Boardwalk Reconstruction

36

Boardwalk Construction Engineering Elements

Rockaway Reconstruction

Page 37: Rockaway Boardwalk Reconstruction

37

Benches

Rockaway Reconstruction

1964 World’s Fair Bench with RPL Slats

and Galvanized Steel Legs

1964 World’s Fair Backless Bench with

RPL Slats and Galvanized Steel Legs

Page 38: Rockaway Boardwalk Reconstruction

38

Drinking Fountains

Rockaway Reconstruction

Haws Fountain WXY Prototype as seen at Transmitter

Park

Page 39: Rockaway Boardwalk Reconstruction

39

Foot Showers

Rockaway Reconstruction

Page 40: Rockaway Boardwalk Reconstruction

40

Railing Options

Rockaway Reconstruction

Pipe Railing – Potential for South Side DPR Standard Rail

Page 41: Rockaway Boardwalk Reconstruction

41

Bike Racks

Rockaway Reconstruction

DPR Standard Bike Rack

Page 42: Rockaway Boardwalk Reconstruction

42

Trash Receptacles

Rockaway Reconstruction

Trash and Recycle Receptacles

Page 43: Rockaway Boardwalk Reconstruction

43

Questions and Discussion