ROCKTON DOWNTOWN
STREETSCAPEMASTER PLAN
Steering Committee Meeting #3 | March 27, 2018Teska Associates | Christopher Burke Engineering
AGENDA
1. Schedule
2. Gateway & Wayfinding Signage
3. Streetscape Materials & Products
4. Streetscape Typologies & Concepts
5. Streetscape Costs & Phasing
6. Next Steps
7. Adjourn
SCOPE & SCHEDULE
PHASE 1 | DATA COLLECTION
PHASE 4 | FINAL PLAN
PHASE 5 | IMPLEMENTATION PLAN
PHASE 2 | OUTREACH
PHASE 3 | PRELIM PLAN
c
cc
p p
vbc p vb
committee public Village Board
Aug
Sept
Oct
Nov
Dec
Jan
Feb
Mar
Apr
STREETSCAPE STRATEGIES
#1: REINFORCE DOWNTOWN STREETS AS THE HISTORIC AND CULTURAL CENTER OF ROCKTON.Evaluate opportunities to balance existing roadway/on-street parking functions with widened sidewalks and active seating/dining areas.
#2: PROMOTE ROCKTON’S IMAGE AND FUNCTION THROUGH SIGNAGECreate a comprehensive signage program that addresses gateway, wayfinding, parking and business directory signage
#3: REINFORCE FESTIVAL SPACESAccommodate a variety of fest types, including large format events at Settlers Park, and smaller format events on Main and/or Hawick Streets.
#4: ENHANCE OFF STREET PARKING AND ALLEYWAY CONNECTIONSImprove off street parking functions and alleyway connectivity through design treatments.
#5: IMPROVE CONNECTIVITY BETWEEN DOWNTOWN AND RIVERFRONTProvide interconnected experiences that draw users between Downtown and Riverfront. Experiential elements may include interconnected pathways, crosswalks, sidewalks, seating/ gathering areas, river overlooks, passive open space, active play and interpretive landscaping.
Preferred Sign Concept
GATEWAY & WAYFINDING SIGNAGE
Gateway Sign Directional Sign Parking Identifier
Parking Directional
Business Directory Kiosk
Bicycle/Pedestrian Directional Sign
LIGHTING
Ashberry LED post topLandscape Forms
Option 1 Option 2
Square Lantern Series LED post topLumec
Existing light pole
BENCHES / RECEPTACLES
Victor Stanley, Backless CR-296 (6’ bench, 30” chair) / Landscape Forms, Concord Trash and Recycling Receptacles
Existing donor bench
SHOPPING / DINING STREETSCURB & GUTTER • Opportunities to redistribute / expand
downtown parking• Expanded corner bump outs at intersection
cornersLIGHTING • Decorative LED pedestrian light
PLANTINGS • Planter pits at intersection corners / bump outs• Trees in grates at narrow sidewalk sections
PAVING • Unit pavers at accent corners• Concrete sidewalks with regular joint pattern• Unit pavers at crosswalks
SITE FURNISHINGS • Clustered benches, trash receptacles and planter pots at intersection corners
• Bike racks and repair stations at intersection corners
Diagonal parking
Diagonal parking
Parallel parking
M.1 – MAIN STREET
MAIN ST
BLA
CK
HA
WK
GR
EEN
ST
PRA
IRIE
ST
VillageHall
LibraryDairyhaus
Rockton Food & Sprirts
LocalDoughCafe
Pedestrian Lighting- with Decorative Planter Pots
6” Landscape Planter Curbs- with Outcropping Stone,
Limestone Benches,
Parallel Parking (both sides)- 17 spaces
M.2 – MAIN STREETMAIN ST
HAWICK
PRA
IRIE
ST
LocalDoughCafe
Post Office
Greater RocktonCentre
Trees in Expanded Grates
Corner Bump-outs-Decorative Pavers, Benches, Planter Pots,Bike Racks, and 6” Landscape Planter Curbs
Landscape Bump-outs- Modified for Snow Operations
M.3 – MAIN STREET
MAIN ST
HAWICK
PRA
IRIE
ST
LocalDoughCafe
Post OfficeGreater RocktonCentre
AmericanLegion B
LAC
KH
AW
K
CEN
TER
ST
CO
TTA
GE
Hawick Riverfront Plaza-Limestone Seatwall, Decorative Pavers, Limestone Boulders
Riverfront Pathway – 8’w
Cottage Riverfront Plaza-Decorative Pavers, Benches, Limestone Boulders
New Parking Area- 10 spaces
New Parking Area- 7 spaces
Pedestrian Lighting- with Decorative Planter Pots
New Parallel Parking- 28 spaces
TRANSITION STREETS
CURB & GUTTER
• New curb and gutter as required• Expanded corner bump outs at intersection
cornersLIGHTING • Decorative LED pedestrian light
• Decorative LED bollard light at park areas
PLANTINGS • Parkway trees in lawn areas• Dwarf shrub / groundcover plantings at curb
bump out areas
PAVING • Unit pavers at accent areas• Concrete sidewalks with regular joint pattern• Painted crosswalks
SITE FURNISHINGS
• Clustered benches, trash receptacles and bike racks at key areas such as Village Green Park
C.1 – CHAPEL STREET
CHAPEL ST
Village Green Park
BLA
CK
HA
WK
GR
EEN
ST
Village Green Park Entry Plaza & Sidewalk- benches, bike racks, trash receptacles, plantings
Curb & GutterLandscaped Bump Outs
Painted Crosswalks
FESTIVAL / GATHERING STREETS
CURB & GUTTER • Existing alignment to remain• Expanded corner bump outs at intersection
cornersLIGHTING • Decorative LED pedestrian light
• Decorative LED bollard light at Settlers Park
PLANTINGS • Planter pits at intersection corners / bump outs• Trees at Settlers Park
PAVING • Unit pavers at accent areas• Concrete sidewalks with regular joint pattern• Unit pavers at crosswalks
SITE FURNISHINGS
• Clustered benches, trash receptacles and planter pots at intersection corners
• Bike racks and repair stations at intersection corners
29
H.1 – HAWICK STREET
HAWICK ST
BLA
CK
HA
WK
Rockton Sanctuary
Spa
The Mix Cafe
Landscape Bump-outs- Modified for Snow Operations
SETTLER’S PARK IMPROVEMENTS
Naturalized Area w/paths and seating
areas
Athletic Fields/
Ice Skating
Existing Soccer Field
Existing Basketball
CourtsSettler’s
Park
BLA
CK
HA
WK
HAWICK
Splash PadArea
Playground/Large Games New Park Shelter
- 40’ x 60’
New Riverfront Access Pathway
Riverfront Overlook- Decorative Pavers, Benches, Limestone Boulders or Decking Overlook
New Park Lighting
Potential Pathway Extension
New Riverfront Dock
Potential Pathway Extension
Concrete Walkway
ON-STREET PARKINGASSESSMENT
H.1
M.1M.2
M.2
M.3
C.1
EXISTING PARKING
PROPOSED CONCEPT PARKING
H.1HAWICK ST
49 44 {-5}
M.1MAIN ST
59 40 {-19}
M.2MAIN ST
56 57 {+1}
M.3MAIN ST
39 53 {+14}
C.1CHAPEL ST
34 34 {0}
TOTAL 237 228 {-9}
STREETSCAPE PHASING H.1 Hawick StreetBlackhawk Blvd. to Bridge St.
+/- 550 LF
M.1 Main Street Prairie St. to Green St. (Prairie St Intersection Included)
+/- 1,000 LF
M.2 Main Street Center St. to Prairie St. & Prairie Street Main St. to Hawick St.
+/- 650 LF
M.3 Main Street Cottage St. to Center St. & Hawick Street Center St. to Blackhawk Blvd.
+/- 1,700 LF
C.1 Chapel Street Blackhawk Blvd. to Green St.
+/- 550 LF
H.1
M.1M.2
M.2
M.3
C.1
STREETSCAPE BUDGET COSTS:PROJECT CATEGORIES & ELEMENTSRoadway & Drainage Site mobilization; curb & gutter remove and replace; pavement
resurfacing; tree removals; pavement marking; detectable warning plates; alternate utility improvements, signal modifications.
Lighting & Support Infrastructure
Decorative light poles.
Hardscape & Furnishings Decorative pavers, stone outcropping, outcropping seating, stone lighting pier bases, 6” concrete planter curb, sidewalk, benches, planter pots, litter & recycling.
Signage Gateway signs, directional signs, business directory kiosks, bike/ped directional signs, parking identifier, parking directional
Plantings Trees, shrubs, perennials/groundcover, soils, mulches.
Streetscape budget costs are provided for Village planning purposes. Costs are derived based on past planning efforts, aerial photography and site reviews. Final design and engineering is required to produce final cost estimates.
STREETSCAPE COSTS H.1 - Hawick Street - Blackhawk Blvd. to Bridge St
Roadway $366,500
Lighting $86,500
Hardscape & Furnishings $89,000
Utility Upgrades (sewer) $75,000
Plantings $61,500
Design and Engineering (15%) $112,300
Maintenance of Traffic / Admin $71,000
TOTAL $861,800
H.1
STREETSCAPE COSTS M.1 - Main Street - Prairie St. to Green St
Roadway $948,000
Lighting $270,000
Hardscape & Furnishings $590,500
Utility Upgrades (sewer) $271,000
Traffic Signal Modifications $120,000
Plantings $102,500
Design and Engineering (15%) $386,500
Maintenance of Traffic / Admin $275,000
TOTAL $2,963,500
M.1
IDOT COORDINATION
IDOT requires a formal Phase 1 study for any upgrades that involve Blackhawk Rd (IL-75). Typical timeframe:
▫ Phase 1 review – 1 year▫ Phase 2 construction docs – 1 year▫ Phase 3 – Construction – 1 year
Design team is meeting with IDOT April 10 to discuss intersection upgrades.
STREETSCAPE COSTS M.2 - Main Street - Center St. to Prairie St. & Prairie Street - Main St. to Hawick St.
Roadway $606,000
Lighting $130,000
Hardscape & Furnishings $162,000
Utility Upgrades (sewer, structure adjustments)
$204,000
Plantings $45,000
Design and Engineering (15%) $198,000
Maintenance of Traffic / Admin $173,000
TOTAL $1,518,000M.2
M.2
STREETSCAPE COSTS M.3 - Main Street - Cottage St. to Center St. & Hawick Street - Center St. to Blackhawk Blvd.
Roadway $778,500
Lighting $270,000
Hardscape & Furnishings $371,500
Utility Upgrades (sewer, water main west of Blackhawk, structure adjustments)
$942,500
Plantings $60,000
Design and Engineering (15%) $390,000
Maintenance of Traffic / Admin $180,000
TOTAL $2,992,500M.3
M.3
STREETSCAPE COSTS C.1 - Chapel Street - Blackhawk Blvd. to Green St
Roadway $232,500
Lighting $0
Hardscape & Furnishings $26,500
Utility Upgrades (sewer laterals, structure adjustments)
$89,500
Plantings $18,000
Design and Engineering $65,000
Maintenance of Traffic / Admin $68,000
TOTAL $499,500
C.1
PARK COSTS Settlers Park Base Infrastructure Improvements
Site Preparations $84,000
Hardscape & Furnishings $212,500
Lighting $432,000
Plantings $104,500
Design and Engineering (15%) $131,500
Maintenance of Traffic / Admin $42,000
TOTAL $1,006,500
Settlers Park
Settlers Park Specialty Park Amenities
Specialty Amenities $1,260,000 to $2,340,000
Design and Engineering (15%) $165,000 to $300,000
Maintenance of Traffic / Admin $60,000
TOTAL $1,485,000 to $2,700,000
STREETSCAPE COSTSSUMMARY
H.1 - Hawick Street - Blackhawk Blvd. to Bridge St. (approx. 550 LF)TOTAL: $861,800
M.1 - Main Street - Prairie St. to Green St. (Prairie St Intersection Included) (approx. 1,000 LF)
TOTAL: $2,963,500M.2 - Main Street - Center St. to Prairie St. & Prairie Street - Main St. to Hawick St. (approx. 650 LF)
TOTAL: $1,518,000M.3 - Main Street - Cottage St. to Center St. & Hawick Street -Center St. to Blackhawk Blvd. (approx. 1,700 LF)
TOTAL: $2,992,500C.1 - Chapel Street - Blackhawk Blvd. to Green St. (approx. 550 LF)
TOTAL: $499,500Settlers Park Base Infrastructure Improvements
TOTAL: $1,006,500Settlers Park Specialty Park Amenities **Not included in total costs
TOTAL: $1,485,000 to $2,700,000
Streetscape Project Total: $9,841,800
UTILITY POLE UPGRADESCosts to relocate utilities underground
H.1 - Hawick Street - Blackhawk Blvd. to Bridge St. (approx. 550 LF)TOTAL: $208,800
M.1 - Main Street - Prairie St. to Green St. (Prairie St Intersection Included) (approx. 1,000 LF)
TOTAL: $295,200M.2 - Main Street - Center St. to Prairie St. & Prairie Street - Main St. to Hawick St. (approx. 650 LF)
TOTAL: $146,400M.3 - Main Street - Cottage St. to Center St. & Hawick Street - Center St. to Blackhawk Blvd. (approx. 1,700 LF)
TOTAL: $590,400C.1 - Chapel Street - Blackhawk Blvd. to Green St. (approx. 550 LF)
TOTAL: $244,800Settlers Park Base Infrastructure Improvements
TOTAL: $2,505,510
Utility Pole Upgrades Project Total: $3,991,110
COMMUNITY IDENTITYWAYFINDING SIGNAGE
WAYFINDING SIGNAGE
Gateway Sign (Option A) – (2 signs) $100,000
Gateway Sign (Option B) – (2 signs) $40,000
Directional Sign – 4” Letters – (7 signs) $70,000
Directional Sign – 3” Letters – (2 signs) $16,000
Business Directory Kiosk – (4 signs) $60,000
Bicycle/Ped Directional Sign – (3 signs) $7,500
Parking Identifier – (5 signs) $37,500
Parking Directional – (5 signs) $25,000
SUBTOTAL $379,200
Design & Engineering (10%) $ 37,920
TOTAL $417,120
NEXT STEPS
Committee discussion:
1. Streetscape concepts & treatments2. Implementation & priority projects
Open House / Plan Commission – April 10Village Board - TBD