ron domitrovic program manager, energy efficiency variable capacity hp subcommittee 8/28/2013 load...

7
Ron Domitrovic Program Manager, Energy Efficiency Variable Capacity HP Subcommittee 8/28/2013 Load Based Testing for Unitary HVAC

Upload: phyllis-hamilton

Post on 05-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ron Domitrovic Program Manager, Energy Efficiency Variable Capacity HP Subcommittee 8/28/2013 Load Based Testing for Unitary HVAC

Ron DomitrovicProgram Manager, Energy Efficiency

Variable Capacity HP Subcommittee8/28/2013

Load Based Testing for Unitary HVAC

Page 2: Ron Domitrovic Program Manager, Energy Efficiency Variable Capacity HP Subcommittee 8/28/2013 Load Based Testing for Unitary HVAC

2© 2013 Electric Power Research Institute, Inc. All rights reserved.

Load Based Testing of Variable Systems

• Psychrometric rating testing is standard for unitary HVAC equipment

– 80°/67° is accepted as THE standard

– Controlled return air conditions

– Measured capacity/power/efficiency with system on.

• Works well for single-speed HVAC systems

Page 3: Ron Domitrovic Program Manager, Energy Efficiency Variable Capacity HP Subcommittee 8/28/2013 Load Based Testing for Unitary HVAC

3© 2013 Electric Power Research Institute, Inc. All rights reserved.

Load Based Testing of Variable Systems

• Common standards:

– AHRI 210/240: Systems < 65,000Btu/hr

– AHRI 340/360: Systems > 65,000 Btu/hr

– ANSI/AHRI 1230: VRF systems <300,000 Btu/hr

Page 4: Ron Domitrovic Program Manager, Energy Efficiency Variable Capacity HP Subcommittee 8/28/2013 Load Based Testing for Unitary HVAC

4© 2013 Electric Power Research Institute, Inc. All rights reserved.

Load Based Testing of Variable Systems

– Designed for fair comparison among similar systems

– NOT primarily designed for energy calculation

• However; generally OK with single speed systems

• Difficulties with variable capacity systems

THESE ARE RATING STANDARDS

Page 5: Ron Domitrovic Program Manager, Energy Efficiency Variable Capacity HP Subcommittee 8/28/2013 Load Based Testing for Unitary HVAC

5© 2013 Electric Power Research Institute, Inc. All rights reserved.

Load Based Testing of Variable Systems

– Why?

• Current standards require fixed operation

• Fixed operation may not capture actual (field) behavior

• Systems can be configured for optimal operation (for rating)

– May or may not match field operation

• Energy use is dependant on actual operation

Page 6: Ron Domitrovic Program Manager, Energy Efficiency Variable Capacity HP Subcommittee 8/28/2013 Load Based Testing for Unitary HVAC

6© 2013 Electric Power Research Institute, Inc. All rights reserved.

Load Based Testing of Variable Systems

• Load Based Testing

– Also called “calorimetric testing”

– Load on system is held constant

– No fixed control of system under test

– ASHRAE TC 8.11 is exploring possibilities

– Potentially more appropriate for energy calculation

– More difficult—labs are not currently set up for it

Page 7: Ron Domitrovic Program Manager, Energy Efficiency Variable Capacity HP Subcommittee 8/28/2013 Load Based Testing for Unitary HVAC

7© 2013 Electric Power Research Institute, Inc. All rights reserved.

Together…Shaping the Future of Electricity