ronan point collapse group 1: gareth nolan james o’brien jennie quigley laura woodbyrne
TRANSCRIPT
![Page 1: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/1.jpg)
Ronan Point Collapse
Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne
![Page 2: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/2.jpg)
![Page 3: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/3.jpg)
Background
Housing destroyed by 2nd World War Development of prefabricated construction
techniques Therefore high-rise apartment buildings:
Large numbers of people Save land Constructed quickly Affordable
![Page 4: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/4.jpg)
The Building
Clever Road, East London 22 storeys high Total of 110 apartments Consisted of both one and two bed Cost £500,000 to build
![Page 5: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/5.jpg)
The Structure Construction began on July 25 1966,
completed March 11 1968 (less than 2 yrs to build)
Larsen – Nielsen method of construction Developed in Denmark in 1948 Walls, floors & stairways all pre-cast Slotted into place and connected on site Minimise amount of on-site construction
work Each floor was load bearing and supported the
floor above.
![Page 6: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/6.jpg)
The collapse
5.45a.m May 16th 1968 Apartment 90 on the 18th floor Struck a match to light gas stove Explosion due to a gas leak resulting from
a substandard brass nut Magnitude of explosion very minor,
(<70kPa) should not have led to such a collapse
![Page 7: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/7.jpg)
Apartment 90 on the 18th floor
![Page 8: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/8.jpg)
Force of explosion knocked out the opposite corner walls of apartment
These walls were sole support for walls directly above.
Chain reaction All these floors collapsed onto floor 18
which was unable to take the extra weight. Floor 18 then collapsed onto floor 17,
which fell on floor 16 and so on to ground level.
![Page 9: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/9.jpg)
Floor plan of the apartments:
Collapse sheared of the living room and kitchen portion of the apartments, leaving bedrooms intact
![Page 10: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/10.jpg)
4 People died & 17 were injured. The reason for such low fatalities was
that almost all residents were asleep in their bedrooms.
All of the fatalities occurred in apartments 17-22, where the bedrooms also collapsed.
![Page 11: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/11.jpg)
Cause of collapse Lack of structural redundancy No fail safe mechanisms No alternative load paths to support
upper floors should lower floors collapse
Building codes not kept up to date Poor workmanship
![Page 12: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/12.jpg)
After the collapse
Reinforced with blast angles Continuing public concerns Demolished in May 1986, only 18
years after completion Life expectancy of 60 years.
![Page 13: Ronan Point Collapse Group 1: Gareth Nolan James O’Brien Jennie Quigley Laura Woodbyrne](https://reader036.vdocuments.net/reader036/viewer/2022062515/56649f495503460f94c6b269/html5/thumbnails/13.jpg)
Effect on building regulations
Initiated changes to the regulation codes Must now account for progressive collapse Also consider forces from an internal
explosion Minimum amount of ductility and
redundancy to be factored into design